National Inventory of STPs - 2021

Download as pdf or txt
Download as pdf or txt
You are on page 1of 187

National Inventory

of
Sewage Treatment Plants

March 2021

Central Pollution Control Board


Parivesh Bhawan
East Arjun Nagar , Delhi
CONTENTS
Page No.

Chapter 1 : Introduction 1-5


1.1 Background 1
1.2 Impacts of Urbanization 3
1.3 Present Study 5

Chapter 2 : Important Definitions 6-7

Chapter 3 : National Inventory of Sewage Treatment Plants ( STPs) 8-25


3.1 Objective 8
3.2 Methodology 8
3.3 Observations 9
3.4 Re-use of Sewage 22
3.4.1 Case Study of Chennai Metropolitan Water Supply and 23
Sewage Board
3.4.2 Case Study of Surat Municipal Corporation 24

Chapter 4 : State-wise Statistics on Sewage Treatment Plants 26-54


4.1 STPs at Andhra Pradesh 26
4.2 STPs at Andaman & Nicobar Islands 27
4.3 STPs at Arunachal Pradesh 27
4.4 STPs at Assam 27
4.5 STPs at Bihar 28
4.6 STPs at Chandigarh 29
4.7 STPs at Chhattisgarh 30
4.8 STPs at Daman, Diu ,Dadra & Nagar Haveli 31
4.9 STPs at Goa 32
4.10 STPs at Gujarat 33
4.11 STPs at Haryana 34
4.12 STPs at Himachal Pradesh 35
4.13 STPs at Jammu & Kashmir 36
4.14 STPs at Jharkhand 37
4.15 STPs at Karnataka 38
4.16 STPs at Kerala 39
4.17 STPs at Lakshadweep 40
4.18 STPs at Madhya Pradesh 40
4.19 STPs at Maharashtra 41
4.20 STPs at Manipur 41
4.21 STPs at Meghalaya 41
4.22 STPs at Mizorum 42
4.23 STPs at Nagaland 42
4.24 STPs at NCT Delhi 43
4.25 STPs at Odisha 44
4.26 STPs at Puducherry 45
4.27 STPs at Punjab 46
4.28 STPs at Rajasthan 47
4.29 STPs at Sikkim 48
4.30 STPs at Tamilnadu 49
4.31 STPs at Telangana 50
4.32 STPs at Tripura 51
4.33 STPs at Uttar Pradesh 52
4.34 STPs at Uttarakhand 53
4.35 STPs at West Bengal 54

Chapter 5 : Major Findings and Way Forward 55-57


5.1 Major Findings 55
5.2 Way Forward 57

Annexures 58-183
Chapter 1
Introduction

1.1 Background

Sewage, or domestic/municipal wastewater, is a type of wastewater that is produced


by a community of people. It is characterized by volume or rate of flow, physical condition,
chemical and toxic constituents, and its bacteriological status. Assessment of quantities of
sewage generation is necessary to ensure its proper collection, conveyance, treatment,
disposal and reuse.
Assessment of quantities of sewage generation and its treatment is being carried out by
Central Pollution Control Board (CPCB) from time to time with the help of State Pollution
Control Boards / Pollution Control Committees and Local Bodies. Questionnaires were
circulated among the concerned stakeholders for collection of information regarding water
supply, sewage generation and treatment capacity. Population is the very basic
independent and dominant factor governing estimation of volume of sewage, size of sewer
network and capacity of sewage treatmen. Based on the information received from local
bodies, status reports were prepared. First such exercise was undertaken during the year of
1978-79.
During last four decades, estimations of domestic waste water generation are made by
CPCB based on the Census Populaton data pertaining to the years 1971, 1981, 1991 and
2001. Gist of the assessment carried out by CPCB is as follows:

 As per census of 1971, 142 class I cities and 190 class II towns were identified.
Accordingly, sewage generation for the year 1978 for class I cities was estimated as
7,006 MLD whereas treatment capacity was 2,755 MLD. In case of class II towns,
treatment capacity was only 5 % of the total wastewater generation of 61 MLD.

-1-
 In 1988-89, the assessment was carried out based on the census data of year 1981. The
sewage generation from 212 class-I cities was estimated as 12,145 MLD whereas
treatment capacity was only 2,633 MLD. Similarly, in 241 class II towns, treatment
capacity was 21 MLD against sewage generation of 1,279 MLD.
 During the assessment period 1999-2000, the number of class I cities went up to 299 and
the sewage generation increased to 16,662 MLD against the treatment capacity of 4,037
MLD. In 345 class II towns, treatment capacity was 61 MLD against the sewage
generation of 1,649 MLD.
 In 2008-09, it was estimated by CPCB that out of 38,254 MLD of sewage generated in
class I cities and class II towns, only 11,787 MLD was treated. As per Census of 2001
and projection of population to 2008, 498 class-I cities and 410 class-II towns were
classified.

Decadal assessment revealed increasing trend in urban population, sewage generation


and treatment capacity as depicted in figure 1.1. Since 1971, the urban population of India
increased 3 times thereby impacting sewage generation which also increased at a rapid
pace. However, rate of development of treatment facilities happened to be much slower as
compared to sewage generation and urban growth. The sewage generation increased from
7,067 MLD in 1978 -79 to 62,000 MLD in 2014-15 whereas treatment capacity augmented
from 2,758 MLD to 23,277 MLD only.

40000 Class-I Sewage Generation (in MLD)

35000 Class-I Sewage Treatment Capacity (in MLD)


Class-II Sewage Generation (in MLD)
30000
Class-II Sewage Treatment Capacity (in MLD)
25000
(in MLD)

20000

15000

10000

5000

0
1978-79 1988-89 1999-2000 2008-09
Year
Figure 1.1: Decadal trend of sewage generation and treatment capacity in Class-I cities
and Class-II towns.

-2-
1.2 Impacts of Urbanization

The growth of cities into meteropolitian cities exerts pressure on water resources in two
ways. The increasing need for water to meet the domestic requirements and impact of
resultant wastewater discharge on the receiving waters have cummuative effect in
deteriorating quality of receiving water.

Water Supply and Sanitation are the basic neccesities of urban centers and various
schemes are devised by Government of India to provide these basic amenties. Over the
last few decades, rapid urbanization essentially lead to rise in water demand and
adequate sanitation as illustrated in Figure 1.2 and summarized in Table 1.0.

50.0
46.9

45.0 POPULATION IN CRORES


40.0 37.7
Population in Millions

35.0

30.0 28.5

25.0
21.7
20.0
15.9
15.0
10.9
10.0 7.8
6.2
4.4
5.0 2.6 2.6 2.8 3.3

0.0
1901 1911 1921 1931 1941 1951 1961 1971 1981 1991 2001 2011 2021

Figure 1.2: Bar diagram shows growth of urban population 1901-2021(E )

-3-
Table 1.0: Decadal Urban Population Growth Since 1901

Year Total Rural Urban Urban, as % Decadal %


of total increase in urban
population
1901 23,83,96,327 21,25,44,454 2,58,51,873 10.84 -
1911 25,20,93,390 22,61,51,757 2,59,41,633 10.29 0.35
1921 25,13,21,213 22,32,35,043 2,80,86,170 11.18 8.3
1931 27,89,77,238 24,55,21,249 3,34,55,989 11.99 19.1
1941 31,86,60,580 27,45,07,283 4,41,53,297 13.86 32.0
1951 36,10,88,090 29,86,44,381 6,24,43,709 17.29 41.4
1961 43,92,34,771 36,02,98,168 7,89,36,603 17.97 26.4
1971 54,81,59,652 43,90,45,675 10,91,13, 977 19.91 38.2
1981 68,33,29,097 52,38,66,550 15,94,62,547 23.34 46.1
1991 84,63,02,688 62,86,91,676 21,76,11,012 25.71 36.5
2001 1,02,70,15,247 74,16,60,293 28,53,54,954 27.78 31.1
2011 1,21,01,93,422 83,30,87,662 37,71,05,760 31.16 32.2
2021 1,31,63,43,000 84,64,16,000 46,99,27,000 35.69 24.6

Source : Population Census Website ( censusindia.gov.in)

In order to meet the water demand, water is tapped for domestic and industrial uses
from rivers, streams, wells and lakes and groundwater resources are also explored.
Approximately 80% of the water supplied for domestic uses, comes out as wastewater. In
different regions of urban centers, wastewater is let out untreated due to the
lack/unavailability of sewerage network and discharged into the natural drainage system
causing pollution in downstream areas.

As on date, emphasis are made on creating facilities for collection, convyenace


and treatment of domestic wastewater. There is also need to think domestic wastewater as
a resource which can be utilized after treatment for meeting the non-potable requirements.
It will help in conserving raw water resources like groundwater and surface water.

-4-
As per Census 2011, population of urban agglomeration increased from 28 crores
in 2001 to 37 crores in 2011. During 2014, Central Pollution Control Board (CPCB) carried
out inventorization of Sewage Treatment Plants (STPs) of the country and as per
information received from State Pollution Control Boards and Pollution Control
Committees, 816 STPs were installed in different States/UTs in the country and sewage
treatment capacity developed during that period was only 23,277 MLD.

Nowadays, STPs are designed on conventional technologies which can treat the
wastewater to meet the non-potable requirement. Sequential Batch Reactor (SBR) and
Activated Sludge Process (ASP) are the prevalent and adopted technologies all across the
country. Oxidation Ponds are used for treatment of sewage in the areas especially where
adequate lands are available for their installation.

1.3 Present Study

A need was felt to upgrade the statistics on sewage generation and its treatment
to chalk-out future strategies. In view of this, CPCB attempted to assess latest status on
domestic wastewater generation by urban population of India and available treatment
capacity. Findings and Wayforward are presented in subsequent sections. It is hoped that
this document shall be helpful for the Policy makers, Regulators, Academicians and all
other concerned.

-5-
Chapter 2
Important Definitions

Definitions of important terms / parameters used in this report are as follows:

a) Biochemical Oxygen Demand (BOD)


Biochemical Oxygen Demand (BOD) – A measurement of the amount of oxygen
utilized by the decomposition of organic material, over a specified period of time
period (usually 5 days at 200 C or 3 days at 270 C) in a wastewater sample; it is used as a
measurement of the readily decomposable organic content of a wastewater.

b) Chemical Oxygen Demand (COD)


Chemical Oxygen Demand (COD) – A measure of the oxygen-consuming capacity of
inorganic and organic matter present in wastewater. COD is expressed as the amount of
oxygen consumed in mg/l. Results do not necessarily correlate to the biochemical
oxygen demand (BOD) because the chemical oxidant may react with substances that
bacteria do not stabilize.

c) Water Pollution
Water pollution is defined as, ‘Any direct or indirect alteration of the physical, thermal,
chemical, biological, radioactive properties of any part of the environment by,
discharge, emission or deposit of wastes so as to affect any beneficial use adversely or
to cause a condition, which is hazardous to public health, safety or welfare of animals,
birds, wildlife, aquatic life or to plants of every description’ (Environment Act of 1980).

d) “prescribed” means prescribed by rules made under the Act by the Central Government
or, as the case may be, the State Government;
Or

-6-
It means prescribed by the Act in which the word occurs or by any regulations made
thereunder, and, in relation to any regulations, where no other authority is empowered
in that behalf in the Act.

e) “sewage effluent” means effluent from any sewerage system or sewage disposal works
and includes sullage from open drains.
Or
It is 99% water carrying domestic wastes originating in kitchen, bathing, laundry, urine
and night soil.

f) “sewer” are pipe or conduits meant for carrying sewage and are laid along the roads
and flow by gravity.
Or
A pipe or conduit (sewer) intended to carry wastewater or water-borne wastes from
homes, business, and industries to the Publicly Owned Treatment Works.

g) “Operational Capacity” means capacity of STPs operating at rated Capacity.

h) “Non-operational Capacity” means capacity of STPs which are not operating

i) “Under Construction Capacity” means capacity of STPs which are under construction
stage

j) “Proposed Capacity” means capacity of STPs which are under the stage of proposal

k) “Installed Capacity “means sum of Operational Capacity, Non – Operational Capacity


and Under Construction Capacity

l) “Total Treatment Capacity” means sum of Installed Capacity and Proposed Capacity

-7-
Chapter 3
National Inventory of Sewage Treatment Plants

3.1 OBJECTIVE

Previous assessment of inventory of Sewage Treatment Plants in India was


carried out by Central Pollution Control Board (CPCB) during 2014-15 in association
with State Pollution Control Boards and Pollution Control Committees. Based on the
information provided by SPCBs /PCCs, it was assessed that there were 816 STPs with
total capacity of 23,277 MLD in 28 States/UTs of India. Out of theses 816 STPs, 522 STPs
were operational, 79 STPs were non-operational, 145 STPs were under construction and
70 STPs had been proposed for construction.
There was/is need to update these information as the country is urbanizing at a
rapid pace and it is imperative to assess availability of sewage treatment facility. In view
of this, an attempt is made by CPCB to assess latest status on domestic wastewater
generation by urban population of India and take sock of available treatment capacity.

3.2 METHODOLOGY

A format was designed by CPCB for collection of data on STPs and the same was
circulated to all State Pollution Control Boards and Pollution Control Committees. The
format is attached at Annexure-I. CPCB has collected the requisite information in the
prescribed format through SPCBs / PCCs. The information so collected were shared with
the Urban Development / Municipal Administration / Local Self Government Department
of the States / Union territories for their comments / confirmation. No comments have
been received by the scheduled date / time and accordingly, it is decided to finalize the
inventory.

Earlier, CPCB had estimated sewage generation to the tune of 62000 MLD for the
year 2014. Estimation was made considering rate of population growth for the year 2001
to 2011 and Water supply @185 lpcd. The average figure of Water Supply for 185 lpcd
-8-
was considered based on CPCB’s report on Class I Cities and Class II towns for the year
2008. Water supply per lpcd was provided by concerned ULBs and accordingly average
185 lpcd considered with respect to Sewage Generation estimated for the year 2008 and
urban population of 2008.

Accordingly, CPCB has assessed present sewage generation based on urban


population of India and projecting the population for the year 2020 considering rate of
growth for the year 2001 to 2011 and Water supply @185lpcd. Rate of sewage generation is
taken as 80 % of the water supply.

3.3 OBSERVATIONS

CPCB has received the data from SPCBs and PCCs on the inventorization of Sewage
Treatment Plants (STPs) located in India in the year 2020-21. Brief observations are as
follows:

i. There are 1,631 STPs (including proposed STPs) with a total capacity of
36,668MLD covering 35 States/UTs. Out of 1,631 STPs, 1,093 STPs are operational,
102 are Non-perational, 274 are under construction and 162 STPs are proposed for
construction.
ii. Out of 1,093 operational STPs, compliance status of 900 STPs is available and only
578 STPs having a combined capacity of 12,200 MLD are found complying with
the consented norms prescribed by the SPCBs / PCCs.
iii. Sewage generation from urban centers estimated as 72,368 MLD.
iv. State-wise sewage generation and treatment capacity are presented in Table 3.1,
3.2 and Figure 3.1.

-9-
Table 3.1: State-wise Sewage Generation and Treatment Capacity of Urban Centers-India

States / UTs Sewage Installed Proposed Total Treatment Operational


Generation Capacity Capacity Capacity Treatment
(in MLD) (in MLD) (in MLD) (in MLD) including Capacity
planned / proposed (in MLD)
Andaman &
23 0 0 0 0
Nicobar Islands
Andhra Pradesh 2882 833 20 853 443
Arunachal
62 0 0 0 0
Pradesh
Assam 809 0 0 0 0
Bihar 2276 10 621 631 0
Chandigarh 188 293 0 293 271
Chhattisgarh 1203 73 0 73 73
Dadra & Nagar
67 24 0 24 24
Haveli
Goa 176 66 38 104 44
Gujarat 5013 3378 0 3378 3358
Haryana 1816 1880 0 1880 1880
Himachal Pradesh 116 136 19 155 99
Jammu & Kashmir 665 218 4 222 93
Jharkhand 1510 22 617 639 22
Karnataka 4458 2712 0 2712 1922
Kerala 4256 120 0 120 114
Lakshadweep 13 0 0 0 0
Madhya Pradesh 3646 1839 85 1924 684
Maharashtra 9107 6890 2929 9819 6366
Manipur 168 0 0 0 0
Meghalaya 112 0 0 0 0
Mizoram 103 10 0 10 0
Nagaland 135 0 0 0 0
NCT of Delhi 3330 2896 0 2896 2715
Orissa 1282 378 0 378 55
Pondicherry 161 56 3 59 56
Punjab 1889 1781 0 1781 1601
Rajasthan 3185 1086 109 1195 783
Sikkim 52 20 10 30 18
Tamil Nadu 6421 1492 0 1492 1492
Telangana 2660 901 0 901 842
Tripura 237 8 0 8 8
Uttar Pradesh 8263 3374 0 3374 3224
Uttarakhand 627 448 67 515 345
West Bengal 5457 897 305 1202 337
Total 72368 31841 4827 36668 26869
Note:
i) Sewage Generation is estimated based on Water supply @ 185lpcd and rate of sewage generation as 80 %.
ii) Sewage generation for NCT of Delhi is estimated based on their 80 % of water supply of 925 MGD

-10-
Table 3.2: State-wise Sewage Generation, Installed Treatment Capacity and Actual
Treatment (As on 30.06.2020)
S.No. State Total sewage Installed capacity Actual quantity treated / capacity utilised
generation (MLD) As % age of (MLD) As % of total As %age of
(MLD) sewage sewage installed
generated generated capacity
1. A & N Islands 23 0 0 0 0 0
2. Andhra Pradesh 2882 833 29 309 11 37
3. Arunachal 62 0 0 0 0
0
Pradesh
4. Assam 809 0 0 0 0 0
5. Bihar 2276 10 0 0 0 0
6. Chandigarh 188 293 156 235 125 80
7. Chhattisgarh 1203 73 6 6 0 8
8. Daman Diu 67 24 36 7 10 29
9. Goa 176 66 38 25 14 38
10. Gujarat 5013 3378 67 2687 54 80
11. Haryana 1816 1880 104 1284 71 68
12. Himachal 116 136 117 51 44
38
Pradesh
13. Jammu & 665 218 33 49 7
22
Kashmir
14. Jharkhand 1510 22 1 15 1 68
15. Karnataka 4458 2712 61 1786 40 66
16. Kerala 4256 120 3 47 1 39
17. Lakshadweep 13 0 0 0 0 0
18. Madhya 3646 1839 50 536 15
29
Pradesh
19. Maharashtra 9107 6890 76 4242 47 62
20. Manipur 168 0 0 0 0 0
21. Meghalaya 112 0 0 0 0 0
22. Mizoram 103 10 10 0 0 0
23. Nagaland 135 0 0 0 0 0
24. NCT Delhi 3330 2896 87 2412 72 83
25. Odisha 1282 378 29 50 4 13
26. Puducherry 161 56 35 30 19 54
27. Punjab 1889 1781 94 1360 72 76
28. Rajasthan 3185 1086 34 478 15 44
29. Sikkim 52 20 38 14 27 70
30. Tamil Nadu 6421 1492 23 995 15 67
31. Telangana 2660 901 34 706 27 78
32. Tripura 237 8 3 1.5 1 19
33. Uttar Pradesh 8263 3374 41 2510 30 74
34. Uttarakhand 627 448 71 187 30 42
35. West Bengal 5457 897 16 213 4 24
Total 72368 31841 44 20236 28 64

-11-
Estimated Sewage Generation:
72368 MLD

Installed Capacity: 31841 MLD


(1469 STPs)

Operational Capacity: 26869 MLD


(1093 STPs)

Actual Utilization: 20235


MLD

Complied Treatment
Capacity: 12197 MLD (578
STPs)

Figure 3.1: Venn diagram depicting Sewage generation, Installed treatment capacity,
Operational Capacity, Actual Utilization and Complied Treatment Capacity

v. Comparison with previous inventory of STPs (2014) is made and it is observed


that sewage treatment capacity has enhanced by 50 %. Comparative statistics
pertaining to the years 2014 and 2020 are presented in Table 3.3 and graphically
also in Figure-3.2.

Table 3.3: Comparative Statistics on the Inventory for the years 2014 and 2020

Sl. No. STP Status 2014 2020


Nos. Of Capacity Nos. Of Capacity
STPs (MLD) STPs (MLD)
1. Operational 522 18883 1093 26869
2. Actual Utilization - - 1093 20235
3. Compliance - - 578 12197
4. Non-operational 79 1237 102 1406
5. Under Construction 145 2528 274 3566
Total (Sl. No. 1+4+5) 746 22648 1469 31841
6. Proposed 70 628 162 4827

-12-
Proposed
Under Construction 7%
5%
Non-operational
2%
Operational
39%
Compliance
18%

Actual Utilization
29%
Figure 3.2 :Status-wise Capacity of STPs

vi. Information on State-wise installed capacity is arranged in decreasing order and


presented in following Table 3.4

Table 3.4: State-wise Installed Treatment Capacity and STPs


State-wise Installed capacity In Descending Order
State Installed Capacity (In MLD) Number of STPs Installed
Maharashtra 6890 154
Gujarat 3378 70
Uttar Pradesh 3374 107
NCT Delhi 2896 38
Karnataka 2712 140
Haryana 1880 153
Madhya Pradesh 1839 126
Punjab 1781 119
Tamil Nadu 1492 63
Rajasthan 1086 114
Telangana 901 37
West Bengal 897 50
Andhra Pradesh 833 66
Uttrakhand 448.18 71
Odisha 378 14
Chandigarh 293 7

-13-
State-wise Installed capacity In Descending Order
State Installed Capacity (In MLD) Number of STPs Installed
Jammu & Kashmir 218 24
Himachal Pradesh 136 78
Kerala 120 7
Chhattisgarh 73 3
Goa 66 11
Puducherry 56 3
Daman, Diu & 3
24
Dadra Nagar Haveli
Jharkhand 22 2
Sikkim 20 6
Bihar 10 1
Mizoram 10 1
Tripura 8 1
Total 31841 1469

vii. Table 3.5 show status of Compliance with respect to consented norms of SPCBs /
PCCs.

Table 3.5: Status of Compliance with respect to consented norms of SPCBs / PCCs

State-wise Compliance capacity (in MLD) ( In Decreasing Order)


States Compliance Capacity No. of STPs
Maharashtra 3598 105
Uttar Pradesh 2114 65
Haryana 1746 144
Tamil Nadu 1368 51
Karnataka 1168 31
Telangana 637 23
Punjab 441 46
Uttarakhand 345 51
Rajasthan 224 16
Andhra Pradesh 154 13
West Bengal 126 8
NCT of Delhi 90 1
Jammu & Kashmir 88 9
Goa 44 9
Dadra & Nagar Haveli 24 3
Jharkhand 22 2
Tripura 8 1
Note:

-14-
State-wise Compliance capacity (in MLD) ( In Decreasing Order)
States Compliance Capacity No. of STPs
i. 08 States / UTs (Gujarat, Himachal Pradesh, Kerala, Pondicherry, Sikkim, Chandigarh,
Chhattisgarh, Madhya Pradesh) has not provided the status of compliance.
ii. Andaman & Nicobar Islands, Arunachal Pradesh, Assam, Lakshadweep, Manipur do not have
any treatment capacity

viii. Break–up of State-wise STPs details are summarized in Table 3.6. Figure 4 depicts
Treatment capacity distribution in percentage among State.

Table 3.6: Status-wise Break-Up of STPs Located in Different States/UTs

Sl. State Number / Installed Proposed Total Operational Non Under Actual Compliance
No. Capacity Capacity Operational Construction Utilization
In MLD
Andhra ∆ 66 1 67 37 5 24 37 13
1
Pradesh ♦ 833 20 853 443 13 377 309 154
∆ 1 24 25 0 0 1 0 0
2 Bihar
♦ 10 621 631 0 0 10 0 0
∆ 7 0 7 6 1 0 6 0
3 Chandigarh
♦ 293 0 293 271 22 0 235 0
∆ 3 0 3 3 0 0 3 0
4 Chhattisgarh
♦ 73 0 73 73 0 0 6 0
Daman, Diu ∆ 3 0 3 3 0 0 3 3
& Dadra
5
Nagar ♦ 24 0 24 24 0 0 7 24
Haveli
∆ 11 3 14 9 0 2 9 9
6 Goa
♦ 66 38 104 44 0 22 25 44
∆ 70 0 70 69 1 0 69
7 Gujarat
♦ 3378 0 3378 3358 20 0 2687 NA
∆ 153 0 153 153 0 0 153 144
8 Haryana
♦ 1880 0 1880 1880 0 0 1284 1746
Himachal ∆ 78 8 86 59 0 19 59 NA
9 Pradesh
♦ 136 19 155 99 0 37 51 NA
Jammu & ∆ 24 2 26 12 6 6 12 9
10
Kashmir ♦ 218 4 222 93 24 101 49 88
∆ 2 10 12 2 0 0 2 2
11 Jharkhand
♦ 22 617 639 22 0 0 15 22
∆ 140 0 140 97 32 11 97 31
12 Karnataka
♦ 2712 0 2712 1922 323 467 1786 1168
∆ 7 0 7 3 4 0 3 NA
13 Kerala
♦ 120 0 120 114 6 0 47 NA

-15-
Sl. State Number / Installed Proposed Total Operational Non Under Actual Compliance
No. Capacity Capacity Operational Construction Utilization
In MLD
Madhya ∆ 126 16 142 45 3 78 45 NA
14
Pradesh ♦ 1839 85 1924 684 22 1133 536 NA
∆ 154 41 195 130 7 17 130 105
15 Maharashtra
♦ 6890 2929 9819 6366 243 281 4242 3598
∆ 1 0 1 0 1 0 0 NA
16 Mizoram
♦ 10 0 10 0 10 0 0 NA
∆ 38 0 38 35 3 0 35 1
17 NCT Delhi
♦ 2896 0 2896 2715 181 0 2412 90
∆ 14 0 14 4 0 10 4 0
18 Odisha
♦ 378 0 378 55 0 323 50 0
∆ 3 1 4 3 0 0 3 NA
19 Puducherry
♦ 56 3 59 56 0 0 30 NA
∆ 119 0 119 95 1 23 95 46
20 Punjab
♦ 1781 0 1781 1601 3 177 1360 441
∆ 114 26 140 57 10 47 57 16
21 Rajasthan
♦ 1086 109 1195 783 41 262 478 224
∆ 6 5 11 5 0 1 5
22 Sikkim
♦ 20 10 30 18 0 2 14 NA
∆ 63 0 63 63 0 0 63 51
23 Tamil Nadu
♦ 1492 0 1492 1492 0 0 995 1368
∆ 37 0 37 27 5 5 27 23
24 Telangana
♦ 901 0 901 842 24 35 706 637
∆ 1 0 1 1 0 0 1 1
25 Tripura
♦ 8 0 8 8 0 0 1.5 8
Uttar ∆ 107 0 107 99 8 0 99 65
26
Pradesh ♦ 3374 0 3374 3224 150 0 2510 2114
∆ 71 10 81 52 2 17 52 51
27 Uttrakhand
♦ 448.18 67 515.18 345 0.18 103 187 345
∆ 50 15 65 24 13 13 24 8
28 West Bengal
♦ 897 305 1202 337 324 236 213 126
∆ 1469 162 1631 1093 102 274 1093 578
Total ♦ 31841 4827 36668 26869 1406 3566 20235 12197
Note:
∆ = Number of STPs, ♦ = Capacity (In MLD)
 States /UTs having no STP are namely Andaman Nicobar & Islands, Arunachal Pradesh, Assam, Lakshadweep, Manipur,
Meghalaya and Nagaland.
 Installed Capacity is sum of Operational Capacity, Non – Operational Capacity and Under Construction Capacity
 Total Treatment Capacity is sum of Installed Capacity and Proposed Capacity.

-16-
Treatment Capacity distribution in Percentage

30.0 26.7

25.0
20.0
15.0
9.2 9.2
10.0 7.4 7.9
5.1 5.2 4.9 5.4
3.3 4.2 3.3
5.0 2.3 1.7 1.7 2.5

0.0

Figure 3.3 : Sewage Treatment Capacity Distribution in Percentage

ix. Various technolgies are employed for treatment of domestic wastewater. It is


observed that Sequential Batch Reactor (SBR) and Activated Sludge Process (ASP)
are the most prevailing technology adopted by ULBs. Technolgical distribution with
respect to number and capacity of STPs are shown in Table 3.7 and Figure 3.4. State-
wise Technological distribution of STPs (On installed Capacity) is placed in Table 3.8
and State-wise Technological distribution of STPs (on operational Capacity) is
placed in Table 3.9.

Table 3.7: Technolgical distribution with respect to number and capacity of STPs
Sl.No. Technology Capacity in MLD Number of STPs
1. ASP 9486 321
2. EA 474 30
3. SBR 10638 490
4. MBBR 2032 201
5. FAB 242 21
6. UASB 3562 76
7. WSP 789 67
8. OP 460 61
9. Any Other 8497 364

-17-
ASP EA
26% 1%

SBR
29%

Any Other
24%

OP MBBR
WSP UASB FAB 6%
1% 2% 10% 1%

Figure 3.4: Technologywise Capacity Distribution of STPs

Table 3.8: Technology-wise Break-up of STPs in various States


Sl. States / UTs Number / Technologies
No. Capacity
ASP EA FAB MBBR OP SBR UASB WSP Any
(In MLD)
Other
Andhra ∆ 12 2 2 12 3 4 5 3 24
1
Pradesh ♦ 321 20 3 39 57 17 130 31 235
∆ 2 0 0 0 0 13 0 0 10
2 Bihar
♦ 150 0 0 0 0 327 0 0 154
∆ 1 0 0 1 0 3 2 0 0
3 Chandigarh
♦ 5 0 0 136 0 107 45 0 0
∆ 3 0 0 0 0 0 0 0 0
4 Chhattisgarh
♦ 73 0 0 0 0 0 0 0 0
Daman, Diu ∆ 0 0 0 0 0 3 0 0 0
5
& Dadra NH ♦ 0 0 0 0 0 24 0 0 0
∆ 0 0 0 0 0 10 0 0 4
6 Goa
♦ 0 0 0 0 0 103 0 0 1
∆ 14 4 0 5 8 24 7 0 8
7 Gujarat
♦ 1254 60 0 175 46 1285 491 0 67
∆ 7 0 0 83 4 49 10 0 0
8 Haryana
♦ 297 0 0 447 14 754 368 0 0
Himachal ∆ 86 0 0 0 0 0 0 0 0
9
Pradesh ♦ 155 0 0 0 0 0 0 0 0
Jammu & ∆ 9 0 3 3 0 10 1 0 0
10
Kashmir ♦ 113 0 15 32 0 52 10 0 0
11 Jharkhand ∆ 0 0 0 0 0 1 0 0 11

-18-
Sl. States / UTs Number / Technologies
No. Capacity
ASP EA FAB MBBR OP SBR UASB WSP Any
(In MLD)
Other
♦ 0 0 0 0 0 12 0 0 627
∆ 12 9 2 2 14 43 2 10 46
12 Karnataka
♦ 667 166 20 35 85 1079 63 61 536
∆ 4 0 0 0 0 0 0 0 3
13 Kerala
♦ 112 0 0 0 0 0 0 0 8
Madhya ∆ 4 0 0 0 0 6 0 7 125
14
Pradesh ♦ 120 0 0 0 0 358 0 178 1268
∆ 24 7 1 35 2 75 6 0 45
15 Maharashtra
♦ 930 146 1 826 36 2452 240 0 5188
∆ 0 0 0 0 0 1 0 0 0
16 Mizoram
♦ 0 0 0 0 0 10 0 0 0
∆ 28 4 1 0 0 4 0 0 1
17 NCT Delhi
♦ 2575 69 3 0 0 245 0 0 4
∆ 3 0 0 0 0 6 0 2 3
18 Odisha
♦ 100 0 0 0 0 183 0 35 60
∆ 0 0 0 0 0 1 2 0 1
19 Puducherry
♦ 0 0 0 0 0 20 36 0 3
∆ 5 0 1 27 0 61 7 17 1
20 Punjab
♦ 207 0 13 165 0 838 501 54 3
∆ 15 0 0 11 2 79 5 15 13
21 Rajasthan
♦ 445 0 0 10 30 428 33 137 112
∆ 0 0 4 2 0 1 0 0 4
22 Sikkim
♦ 0 0 20 2 0 2 0 0 6
∆ 13 4 0 9 4 4 3 0 0
23 Telangana
♦ 85 13 0 133 24 105 541 0 0
∆ 49 0 1 0 1 5 1 2 4
24 Tamil Nadu
♦ 1011 0 6 0 6 319 9 112 29
∆ 0 0 0 0 0 1 0 0 0
25 Tripura
♦ 0 0 0 0 0 8 0 0 0
∆ 20 0 4 3 14 31 24 3 8
26 Uttar Pradesh
♦ 681 0 122 14 101 1176 1095 27 158
∆ 0 0 0 8 0 34 1 0 38
27 Uttrakhand
♦ 0 0 0 20 0 351 1 0 143
∆ 10 0 2 0 9 21 0 8 15
28 West Bengal
♦ 191 0 41 0 63 392 0 160 355
∆ 321 30 21 201 61 490 76 67 364
Total
♦ 9492 474 244 2034 462 10647 3563 795 8957
Note:

-19-
Sl. States / UTs Number / Technologies
No. Capacity
ASP EA FAB MBBR OP SBR UASB WSP Any
(In MLD)
Other
∆ = Number of STPs, ♦ = Capacity (In MLD)
 Activated Sludge Process (ASP), Extended Aeration (EA), Fluidized Aerobic Bed Reactor (FAB), Moving Bed
Biofilm Reactor (MBBR), Oxidation Pond (OP), Sequencing Batch Reactors (SBR), Upflow Anaerobic Sludge
Blanket (UASB)and Waste Stabilization Pond (WSP).
 Technologies included in Any Other are Aerated Lagoon (AL), Trickling Filter (TF), Bio-Tower, Electro
Coagulation (EC), MBR, FMBR and Root Zone etc.
 States /UTs not installed any STP are Andaman Nicobar & Islands, Arunachal Pradesh, Assam,
Lakshadweep, Manipur, Meghalaya and Nagaland.

Table 3.9: Technology-wise Break up of STPs with respct to Operational Capacity


Sl.No. States / Uts Number Technologies
/
Capacity ASP EA FAB MBBR OP SBR UASB WSP Any
(In Other
MLD)
Andhra ∆ 7 2 2 10 2 2 5 3 4
1
Pradesh ♦ 166 20 3 28 56 0.4 130 31.5 8
∆ 1 0 0 1 0 3 1 0 0
2 Chandigarh
♦ 6 0 0 136 0 106 23 0 0
∆ 3 0 0 0 0 0 0 0 0
3 Chhattisgarh
♦ 73 0 0 0 0 0 0 0 0
Daman, Diu & ∆ 0 0 0 0 0 3 0 0 0
4 Dadra Nagar
Haveli ♦ 0 0 0 0 0 24 0 0 0
∆ 0 0 0 0 0 5 0 0 4
5 Goa
♦ 0 0 0 0 0 43 0 0 1
∆ 14 3 0 5 8 24 7 0 8
6 Gujarat
♦ 1254 40 0 175 46 1285 491 0 67
∆ 7 0 0 83 4 49 10 0 0
7 Haryana
♦ 297 0 0 447 14 754 368 0 0
Himachal ∆ 59 0 0 0 0 0 0 0 0
8
Pradesh ♦ 99 0 0 0 0 0 0 0 0
Jammu & ∆ 4 0 3 1 0 4 0 0 0
9
Kashmir ♦ 21 0 15 30 0 27 0 0 0
∆ 0 0 0 0 0 1 0 0 1
10 Jharkhand
♦ 0 0 0 0 0 12 0 0 10
∆ 12 9 1 1 10 24 2 8 30
11 Karnataka
♦ 667 167 15 15 68 447 64 47 432
∆ 2 0 0 0 0 0 0 0 1
12 Kerala
♦ 111 0 0 0 0 0 0 0 3
13 Madhya ∆ 4 0 0 0 0 6 0 7 28

-20-
Sl.No. States / Uts Number Technologies
/
Capacity ASP EA FAB MBBR OP SBR UASB WSP Any
(In Other
MLD)
Pradesh ♦ 120 0 0 0 0 358 0 178 28
∆ 18 2 1 24 2 52 6 0 25
14 Maharashtra
♦ 792 34 1 508 36 2024 240 0 2731
∆ 25 4 1 0 0 4 0 0 1
15 NCT Delhi
♦ 2393 69 3 0 0 245 0 0 5
∆ 0 0 0 0 0 0 0 2 2
16 Odisha
♦ 0 0 0 0 0 0 0 35 20
∆ 0 0 0 0 0 1 2 0 0
17 Puducherry
♦ 0 0 0 0 0 20 36 0 0
∆ 4 0 1 24 0 42 7 16 1
18 Punjab
♦ 203 0 13 152 0 677 501 52 3
∆ 13 0 2 2 22 4 9 5
19 Rajasthan
♦ 399 0 0 2 30 156 25 88 83
∆ 0 0 3 0 0 0 0 0 2
20 Sikkim
♦ 0 0 16 0 0 0 0 0 2
∆ 10 3 0 8 0 3 3 0 0
21 Telangana
♦ 66 13 0 128 0 94 541 0 0
∆ 49 0 1 0 1 5 1 2 4
22 Tamil Nadu
♦ 1011 0 6 0 6 318 9 113 29
∆ 0 0 0 0 0 1 0 0 0
23 Tripura
♦ 0 0 0 0 0 8 0 0 0
∆ 19 0 3 3 11 31 24 2 6
24 Uttar Pradesh
♦ 614 0 113 14 91 1177 1094 13 108
∆ 0 0 0 6 0 32 1 0 13
25 Uttrakhand
♦ 0 0 0 8 0 324 2 0 11
∆ 8 0 2 0 6 1 0 2 5
26 West Bengal
♦ 130 0 41 0 50 8 0 20 88
∆ 259 23 18 168 46 315 73 51 140
Total
♦ 8422 343 226 1643 397 8107.4 3524 577.5 3629
Note:
∆ = Number of STPs, ♦ = Capacity (In MLD)
 Activated Sludge Process (ASP), Extended Aeration (EA), Fluidized Aerobic Bed Reactor (FAB), Moving Bed
Biofilm Reactor (MBBR), Oxidation Pond (OP), Sequencing Batch Reactors (SBR), Upflow Anaerobic Sludge
Blanket (UASB)and Waste Stabilization Pond (WSP).
 Technologies included in Any Other are Aerated Lagoon (AL), Trickling Filter (TF), Bio-Tower, Electro
Coagulation (EC), MBR, FMBR and Root Zone etc.
 States /UTs not installed Operational STPs are Andaman Nicobar & Islands, Arunachal Pradesh, Assam,
Bihar, Lakshadweep, Manipur, Mizoram, Meghalaya, and Nagaland.

-21-
3.4 RE-USE OF SEWAGE

As mentioned earlier, sewage generation is estimated as 72,368 MLD and capacity


utilization is only 20,235 MLD and remaining quantity of 52,133 MLD is let-out as
untreated sewage. Considering such gap of untreated sewage, there is need to realize
sewage as a resource which can be treated as per requirement and utilized for non-potable
purposes and industrial utilities. Utilization of sewage has following positive impacts:
 Re-use of treated sewage will allow to decrease the water demand from aquatic
sources like river, ponds, lakes and also groundwater resources.
 Less consumption of raw water will help in conserving natural water resources.

In recent past, different ULBs and concerned authorities focused on reuse of treated
sewage and initiated reuse of treated sewage in horticulture, irrigation, non-contact
impoundments and washing and utilization for industrial activities. Central Public Health
and Environmental Engineering Organisation (CPHEEO) has prescribed standards for re-
use of treated sewage for different purposes like horticulture, irrigation, non-contact
impoundments and washing and same is attached as Annexure-II.
In compliance with the directions of Hon’ble NGT in the matter of OA no. 148 of 2015 titled
Mahesh ChanderSaxena Vs South Delhi Municipal Coorporation, all the States / UTs have
prepared action plans on utilization of treated sewage. Salient features of the action plans
are mentioned below:
 In 07 States /UTs namely Delhi -405 MLD (12.5 %), Gujarat-60 MLD (1.55 %),
Haryana-192 MLD (16 %), Madhya Pradesh-84 MLD (4 %), Tamil Nadu -211 MLD
(6.6 %), Chandigarh- 27-40 MLD (10-16 %) and Puducherry – 15.3 MLD (26 %),
domestic wastewater treated and re-used for different purposes like horticulture,
irrigation, non-contact impoundments, washing (Roads, Vehicles, Trains),
Construction and Industrial Actvities.
 Percentage of reuse of treated sewage is maximum in Haryana (80 %) followed by
Puducherry (55 %), Delhi (50 %), Chandigarh (35 %), Tamil Nadu (25%), Madhya
Pradesh (20 %), Andhra Pradesh (5 %).
 NCT of Delhi has set target to increase their re usage from 12.5 % to 60 %. In future,
utilization of 341 MGD treated sewage are proposed for drinking purpose (197
MGD), Irrigation (112 MGD) and 10 MGD in rejuvenation of water bodies

Apart from above, case studies of Chennai Metropolitan Water Supply and Sewerage
Board and Surat Municpal Corporation on reuse of treated sewage via Tertiary Treatment
Reverse Osmosis (TTRO) Plant for industrial activity are presented below:

-22-
3.4.1 Case study of Chennai Metropolitan Water Supply and Sewerage Board

Chennai Metropolitan Water Supply and Sewerage Board has installed 02 TTRO
plants at Koyambedu and Kodungaiyur of capacity 45 MLD each to meet the raw water
requirement of Industrial areas. Details of TTRO plant at Koyambedu and Kodungaiyur
are mentioned below:
i. 45 MLD Capacity TTRO Plant at Koyambedu
 Work Awarded
M/s WABAG – IDE Consortium, Chennai- Rs 396.50 Crore towards
construction cost and Rs 197.59 Crore towards Operation and
Maintenance cost for 15 years.

 Project Plan
Construction of TTRO plant of capacity 45 MLD and MS Tranmission
main for conveying product water including construction of
Intermediate storage tanks at Pillaipakkam, VallamVadagal and
Oragadam for onward supply to the SIPCOT industries located at
Irungattukottai, Sriperumbudur and Oragadam by SIPCOT.

The TTRO product water from TTRO plant at Koyambedu is being


supplied to the SIPCOT industries located at Irungattukottai viz.
Hyundai, Schwingstetter, Hwwin, etc., at Sriperumbudur viz. Saint
Gobain, Capro, Samsung Mobiles, etc., and at Oragadamviz, Apollo
tyres, Nissan Kone Elevators, Mando, Yamaha & Enfield, etc., and to
all other small scale industries located at Pillaipakkam and
VallamVadagal from 18.12.2019 onwards.

 Details of TTRO Plant treatment stage: Pre-chlorination, Rapid


Sand Gravity Filters
 Secondary treatment stage: Basket strainers, Ultrafiltration
system
 Tertiary treatment stage: Cartridge filters, Reverse Osmosis
system and Ozonation.

 Benefits
 Saving of Fresh Water-Due to the commencement of the supply
of TTRO water to SIPCOT industries, the quantity of fresh
water of around 20MLD which was being supplied to them for
industrial use from Chembarambakkam has now been diverted
for drinking water purpose of the Chennai city people
 Revenue- The rate / tariff for the supply of TTRO water to the
SIPCOT industries from TTRO plant at Koyambedu is fixed as
Rs.65/- per KL. The total Revenue Generated is Rs 19.67 Crores.

-23-
ii. 45 MLD Capacity TTRO Plant at Kodugaiyur
 Work Awarded
M/s BGR Energy Systems Limited, Chennai- Rs235 Crores towards
construction cost and Rs205 Crore towards Operation and
Maintenance cost for 15 years
Project Plan
Construction of TTRO plant of capacity 45 MLD and laying DI
conveying main to supply product water to the industries at Manali –
Ennore Corridor and Manali – Minjur Corridor, Chennai.
 Details of TTRO Plant
 Pre-treatment stage: Pre-chlorination, Rapid Sand Gravity
Filters
 Secondary treatment stage: Basket strainers, Ultrafiltration
system
 Tertiary treatment stage: Cartridge filters, Reverse Osmosis
system and Ozonation
 Benefits
 Saving of Fresh Water-Due to the commencement of the supply
of TTRO water to the industries, the quantity of fresh water /
desalination waterof around 20MLD which was being supplied
to them for industrial use has now been diverted for the
drinking water purpose of the Chennai city people
 Revenue- The rate / tariff for the supply of TTRO water to the
SIPCOT industries from TTRO plant at Koyambedu is fixed as
Rs.80/- per KL. The total Revenue Generated is Rs48.17 Crores.

3.4.2 Case study of Surat Municpal Corporation

Surat Municipal Corporation (SMC) is supplying an average of 55 MLD of water


to Pandesara GIDC Industrial area since 1998. Water demand of Pandesara industries is
approximately 90-100 MLD comprising 80-85 MLD of process water requirement and
10-15 MLD of potable quality water demand.

SMC has constructed 40 MLD TTRO plant to treat secondary treated water from
Bamroli STPs and recycle, generate and supply Industrial grade water for Pandesara
Industrial Estate. Details of project are mentioned below:

-24-
 Work Awarded
M/s Enviro Control Associates (I) Pvt. Ltd, Surat- Rs 85.10 Crore
towards construction cost and Rs 80 Crore towards Operation and
Maintenance cost for 10 years
 Details of TTRO Plant
 Sand Filtration
 Ultra Filtration
 Reverse Osmosis (RO)
 Activated Carbon Filteration (ACF)
 Benefits
 Saving of Fresh Water-SMC is now able to sapre 40 MLD of
potable water, which was earlier supplied to Pandesara
industries.
 Revenue- The rate / tariff for the supply of TTRO water to the
Pandesaraindustriesfrom TTRO plant is fixed as Rs.23/- per KL.
The total Revenue Generated is Rs 48.17 Crores
 Replicability
 35 MLD capacity at Bamroli (Phase-II) to cater need of Sachin
Industrial Estate
 40 MLD capacity at Dindoli to cater additional need of
Pandesara Industrial Estate
 To explore further use of Tertiary Treated Sewage Wate for
Gardening, Lake Development, One TTP of 01 MLD capacity is
completed as pilot project at KaviKalapi Garden, West Zone of
Surat
 Reuse of Secondary Treated Sewage Water for plants on Road
Divider
 For new proposed 06 EWS Housing Scheme having more than
3000 units under SMART City Mission, SMC has initiated to
establish TTP to treat the Domestic Sewage and Re-use it for
Toilet flushing and Gardening.

*******************************************

-25-
Chapter 4
State-wise Statistics on Sewage Treatment Plants

Interaction were made with all the SPCBs / PCCs to get the information pertaining
to respective State in a prescribed format and the same have been received. It is
communicated by the SPCBs of ArunachalPradesh, Andaman & Nicobar Islands,
Lakshadweep, Manipur and Nagaland that there is no STP in these States. Brief State-wise
observations of remaining 28 States/UTs are presented in subsequent sectionsof this
chapter. Detailed information received as such from the SPCBs / PCCs are attached as
Annexure-III.

4.1 STPs AT ANDHRA PRADESH

Estimated sewage generation for the State of Andhra Pradesh is 2882 MLD and total
capacity (including proposed) is 853.05MLD (67 STPs). Figure 4.1 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
non operational, under construction and proposed. Based on the dataanalysis, following
observations can be made:
1. Installed capacity is 833 MLD (39.61 %) against the sewage generation of 2882 MLD. It
shows that there is gap of 2049 MLD (71.09 %) in treatment capacity.
2. Out of 833 MLD installed capacity developed, operationalized capacity is 443 MLD
(53.18 %).
3. Actual utilized capacity is 309 MLD and capacity of complied STPs is only 154 MLD.
4. STPs based on ASP and MBBR technologies are predominant as compared to natural
treatment systems. However, STPs designed on natural treatment system show more
than 50 % compliance with respect to prescribed norms.

- 26 -
3500

3000 2882

2500

2000
In MLD

1500

1000 853 833

443 377
500 309
154
13 20
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.1 : Sewage generation and Treatment Capacity (MLD) – Andhra Pradesh

4.2 STPs ATANDAMAN & NICOBAR ISLAND

Andaman & Nicobar Islands has no STP and septic tanks are used for treatment of sewage
in the State.

4.3 STPs AT ARUNACHAL PRADESH

Arunachal Pradesh has no STP and septic tanks are used for treatment of sewage in the
State.

4.4 STPs AT ASSAM

Assam has no STP and septic tanks are used for treatment of sewage in the State.

- 27 -
4.5 STPs AT BIHAR

Estimated sewage generation in the State of Bihar is 2276 MLD and total capacity
(including proposed) is 631 MLD (25 STPs). Figure 4.2 depicts sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity, non
operational, under construction and proposed. Based on the dataanalysis, following
observations are made:

1. Installed capacity is 10 MLD (0.43 %) only against the sewage generation of 2276 MLD.
It shows that there is gap in treatment capacity of 2266 MLD (99.56 %). Rest of the
treatment capacity is either in the planning or construction phase.
2. Out of 10 MLD installed capacity, operationalized capacity is zero.

2500
2276

2000

1500
In MLD

1000

631 621

500

10 10
0
Sewage Total Capacity Installed Capacity Under Proposed
Generation Construction
Figure 4.2 : Sewage Generation and Treatment Capacity ( MLD) - Bihar

- 28 -
4.6 STPs AT CHANDIGARH

Estimated sewage generation for the union territory of Chandigarh is 188 MLD
and total capacity (including proposed) is 293 MLD (07 STPs). Figure 4.3 depicts sewage
generation, total capacity, operational capacity, actual utilization, complied capacity, non
operational, under construction and proposed. Based on the dataanalysis, following
observations are made:
1. Installed capacity is 293 MLD against the sewage generation of 188 MLD. It shows that
there is an excess of treatment capacity to the tune of 105 MLD.
2. Out of 293 MLD of installed capacity developed, operationalized capacity is 271 MLD
(92.49 %).
3. Actual utilized capacity is 235 MLD (86.72 %) out of 271 MLD operational capacity.
4. Figures on actual utilized capacity are more than the sewage generation figures of the
city which indicates that possibility of sewage coming from the adjoining cities or
mixng of industrial waste-water into sewage can’t be ruled out. Alternatively, water-
supply from unaccounted sources may also be taking place.

350

293 293
300
271

250 235

200 188
In MLD

150

100

50
22

0
Sewage Total Capacity Installed Operational Actual Non
Generation Capacity Utilization Operational

Figure 4.3: SewageGeneration and Treatment Capacity ( MLD) - Chandigarh

- 29 -
4.7 STPs AT CHHATTISGARH

Estimated sewage generation in the State of Chhattisgarh is 1203 MLD and total
capacity (including proposed) is 73 MLD (03 STPs). Figure 4.4 depicts sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity, non
operational, under construction and proposed. Based on the dataanalysis, following
observations are made:

1. Installed capacity is 73 MLD against the sewage generation of 1203 MLD. It shows that
there is gap in treatment capacity of 1130 MLD (93.93 %).
2. Out of 73 MLD installed capacity developed, operationalized capacity is also 73 MLD
(100 %).
3. Actual utilized capacity is 06 MLD out of 73 MLD operational capacity.
4. STPs based onASP technology is predominant in the State as compared to natural
treatment systems.

1400

1203
1200

1000

800
In MLD

600

400

200
73 73 73
6
0
Sewage Generation Total Capacity Installed Capacity Operational Actual Utilization

Figure 4.4 : Sewage Generation and Treatment Capacity ( MLD) – Chhattisgarh

- 30 -
4.8 STPs AT DAMAN DIU & DADRA NAGAR HAVELI

Estimated sewage generation for the union territory of Daman Diu & Dadra Nagar
Haveli is 67 MLD and total capacity is 24 MLD (03 STPs). Figure 4.5 depicts information
on sewage generation, treatment capacity, operational capacity, actual utilization and
complied capacity. Based on the dataanalysis, following observations are made:
1. Installed capacity is 24 MLD (35.82 %) against the sewage generation of 67 MLD. It
shows that there is gap in treatment capacity of 43 MLD (64.17 %).
2. All the STPs are in operation i.e. operational capacity is also 24 MLD. However, actual
utilized capacity is only 07 MLD out of 24 MLD of operational capacity.

80

70 67

60

50
In MLD

40

30
24 24 24 24

20

10 7

0
Sewage Total Capacity Installed Operational Actual Complied
Generation Capacity Utilization Capacity

Figure 4.5: Sewage Generation and Treatment Capacity (MLD) – Daman, Diu and DNH

- 31 -
4.9 STPs AT GOA

Estimated sewage generation for the State of Goa is 176 MLD and total capacity (including
proposed) is 104 MLD (14 STPs). Figure 4.6 depicts sewage generation, treatment capacity,
operational capacity, actual utilization, complied capacity, non operational, under
construction and proposed. Based on the dataanalysis, following observations are made:

1. Installed capacity is 66 MLD (25 %) against the sewage generation of 176 MLD. It
shows that there is gap in treatment capacity of 110 MLD (62.5 %).
2. Out of 66 MLD installed capacity developed, operationalized capacity is 44 MLD (66.67
%).
3. Actual utilized capacity is 25 MLD out of 44 MLD operational capacity and all the STPs
are complying with norms.

200
176
180
160
140
120 104
100
In MLD

80 66
60 44 44
38
40 25 22
20
0
Sewage Total Installed Operational Actual Complied Under Proposed
Generation Capacity Capacity Utilization Capacity Construction

Figure 4.6: Sewage Generation and Treatment Capacity (MLD) – Goa

- 32 -
4.10 STPs AT GUJARAT

Estimated sewage generation for the State of Gujarat is 5,013 MLD and total capacity
(including proposed) is 3,378 MLD (70 STPs). Figure 4.7 depicts information on sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
non operational, under construction and proposed. Based on the dataanalysis, following
observations are made:
1. Installed capacity is 3,378 MLD (67.38 %) against sewage generation of 5,013 MLD. It
shows that there is a gap in treatment capacity to the tune of 1635 MLD (32.61 %).
2. Out of 3378 MLD installed capacity developed; operational capacity is 3358 MLD
(99.40 %).
3. Actual utilized capacity is 2,687 MLD out of 3,358 MLD operational capacity.
4. STPs based on SBR and ASP technologies are predominant as compared to natural
treatment systems.

6000

5013
5000

4000
3378 3378 3358
In MLD

3000 2687

2000

1000

20
0
Sewage Total Capacity Installed Operational Actual Non
Generation Capacity Utilization Operational

Figure 4.7: Sewage Generation and Treatment Capacity (MLD) – Gujarat

- 33 -
4.11 STPs AT HARYANA

Estimated sewage generation for the State of Haryana is 1816 MLD and total
treatment capacity (including proposed) is 1880 MLD (153 STPs). Figure 4.8 depicts
sewage generation, treatment capacity, operational capacity, actual utilization , complied
capacity, capacities of non operational STPs , under construction STPs and proposed STPs.
Based on the data analysis, following observations are made:

1. Installed treatment capacity is 1880 MLD against sewage generation of 1816 MLD. It
shows that the treatment capacity is in excess by 64 MLD.
2. All the STPs can be operated at full capacity. However, actual utilized capacity is 1284
MLD only and capacity of complying STPs is only 1746 MLD.
3. STPs based on SBR and MBBR technologies are predominant in the state of Haryana.

2000 1880 1880 1880


1816
1800 1746

1600

1400 1284
1200
In MLD

1000

800

600

400

200

0
Sewage Total Capacity Installed Operational Actual Complied
Generation Capacity Utilization Capacity

Figure 4.8: Sewage Generation and Treatment Capacity (MLD) - Haryana

- 34 -
4.12 STPs AT HIMACHAL PRADESH

Estimated sewage generation for the State of Himachal Pradesh is 116 MLD and total
capacity (including proposed) is 155 MLD (86 STPs). Figure 4.9 depicts sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity and
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
the data analysis, following observations are made:

1. Installed capacity is 136 MLD against sewage generation of 116 MLD. It shows that the
treatment capacity is in excess by 20 MLD.
2. Out of 136 MLD of installed capacity developed, operationalized capacity is 99 MLD
(72.79 %) and actual utilized capacity is only 51 MLD.

180

160 155

136
140
116
120
99
100
In MLD

80

60 51
37
40
19
20

0
Sewage Total Installed Operational Actual Under Proposed
Generation Capacity Capacity Utilization Construction

Figure 4.9: Sewage Generation and Treatment Capacity (MLD) – Himachal Pradesh

- 35 -
4.13 STPs AT JAMMU & KASHMIR

Estimated sewage generation for the State of Jammu & Kashmir is 665 MLD and
total capacity (including proposed) is 222 MLD (26 STPs). Figure 4.10 represents
information sewage generation, treatment capacity; operational capacity, actual utilization,
complied capacity, capacities of non operational STPs, under construction STPs and
proposed STPs. Based on the data analysis, following observations are made:

1. Installed capacity is 218 MLD (32.78 %) against sewage generation of 665 MLD. It
shows that there is gap of 447 MLD (67.21 %) in treatment capacity.
2. Out of 218 MLD installed capacity developed, operationalized capacity is 93 MLD
(42.66%)
3. Actual utilized capacity is 49 MLD and further, capacity of complied STPs is only 88
MLD.

700 665

600

500

400
In MLD

300
222 218
200
93 88 101
100 49
24
4
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.10: Sewage Generation and Treatment Capacity (MLD) – Jammu and Kashmir

- 36 -
4.14 STPs AT JHARKHAND

Estimated sewage generation for the State of Jharkhand is 1510 MLD and total capacity
(including proposed) is 639 MLD (12 STPs). Figure 4.11 depicts sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity, capacities
of non operational STPs, under construction STPs and proposed STPs. Based on the data
analysis, following observations are made:

1. Installed capacity is 22 MLD (1.45 %) against sewage generation of 1510 MLD. It shows
that there is a gap of 1488 MLD (98.55 %) in treatment capacity.
2. Installed STPs can be operated at 100 % of capacity. However, actual utilized capacity
is only 15 MLD and meeting the consented norms.

1600 1510

1400

1200

1000

800
In MLD

639 617
600

400

200
22 22 15 22
0
Sewage Total Installed Operational Actual Complied Proposed
Generation Capacity Capacity Utilization Capacity

Figure 4.11: Sewage Generation and Treatment Capacity (MLD) - Jharkhand

- 37 -
4.15 STPs AT KARNATAKA

Estimated sewage generation for the State of Karnataka is 4,458 MLD and total
capacity (including proposed) is 2,712 MLD (140 STPs). Figure 4.12 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
data analysis, following observations are made:

1. Installed capacity is 2,712 MLD (60.83 %) against sewage generation of 4,458 MLD. It
shows that there is gap of 1,746 MLD (39.17 %) in treatment capacity.
2. Out of 2,712 MLD of installed capacity developed, operational capacity is 1922 MLD
(70.87 %).
3. Actual utilized capacity is 1786 MLD (92.92 %) and further, capacity of complied STPs
is only 1168 MLD.
4. STPs based on SBR, OP and ASP technologies are predominant.

5000
4458
4500

4000

3500

3000 2712 2712


In MLD

2500
1922
2000 1786

1500 1168
1000
467
500 323

0
Sewage Total Installed Operational Actual Complied Non Under
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.12: Sewage Generation and Treatment Capacity (MLD) – Karnataka

- 38 -
4.16 STPs AT KERALA

Estimated sewage generation for the State of Kerala is 4,256 MLD and total capacity
(including proposed) is 120 MLD (07 STPs). Figure 4.13 depicts sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity, capacities
of non operational STPs and under construction STPs. Based on the data analysis,
following observations are made:

1. Installed capacity is 120 MLD (2.82 %) against the sewage generation of 4,256 MLD. It
shows that there is a gap in treatment capacity of 4136 MLD (97.18 %).
2. Out of 120 MLD installed capacity developed, operationalized capacity is 114 MLD (95
%) and actual utilized capacity is 47 MLD only.

4500 4256

4000

3500

3000

2500
In MLD

2000

1500

1000

500
120 120 114 47 6
0
Sewage Total Capacity Installed Operational Actual Non
Generation Capacity Utilization Operational

Figure 4.13: Sewage Generation and Treatment Capacity (MLD) – Kerala

- 39 -
4.17 STPs AT LAKSHADWEEP
Lakshadweep has no sewage treatment plant. Septic tanks are used for disposal of
sewage.

4.18 STPs AT MADHYA PRADESH

Estimated sewage generation for the State of Madhya Pradesh is 3,646 MLD and total
capacity (including proposed) is 1,924 MLD (142 STPs). Statistics on sewage generation,
treatment capacity, operational capacity, actual utilization, complied capacity and
capacities of non operational STPs , under construction STPs and proposed STPs are
graphically presented in Fig. 4.14. Based on the data analysis, following observations are
made:
1. Installed capacity is 1,839 MLD (50.44 %) against sewage generation of 3,646 MLD. It
shows that there is gap of 1,807 MLD (49.56 %) in treatment capacity.
2. Out of 1839 MLD installed capacity developed, operationalized capacity is 684 MLD
(37.19 %) and actual utilized capacity is 536 MLD.
3. STP technologies in respect of 123 STPs are not mentioned by MPPCB. Remaining STPs
are predomninantly based on SBR and WSP technologies.

4000
3646
3500

3000

2500

1924 1839
In MLD

2000

1500
1133
1000
684
536
500
22 85
0
Sewage Total Installed Operational Actual Non Under Proposed
Generation Capacity Capacity Utilization Operational Construction

Figure 4.14: Sewage Generation and Treatment Capacity (MLD) – Madhya Pradesh

- 40 -
4.19 STPs AT MAHARASHTRA

Estimated sewage generation for the State of Maharashtra is 9,107 MLD and total
capacity (including proposed) is 9,819 MLD (195 STPs). Figure 4.15 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs , under construction STPs and proposed STPs . Based
on the data, following observations are made:

1. Installed capacity is 6,890 MLD (75.65 %) against sewage generation of 9,107 MLD. It
shows that there is gap of 2217 MLD (24.35 %) in treatment capacity.
2. Out of 6,890 MLD of installed capacity developed, operationalized capacity is 6,366
MLD (92.39 %) and actual utilized capacity is 4,242 MLD. Further, the capacity of
complied STPs is only 3598 MLD.

12000

9819
10000 9107

8000
6890
6366
6000
In MLD

4242
4000 3598
2929

2000
243 281
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.15: Sewage Generation and Treatment Capacity (MLD) – Maharashtra

4.20 STPs AT MANIPUR


Manipur has no sewage treatment plant. Septic tanks are used for disposal of sewage.

4.21 STPs AT MEGHALAYA


Meghalaya has no sewage treatment plant. Septic tanks are used for disposal of sewage.

- 41 -
4.22 STPs AT MIZORAM

Estimated sewage generation for the State of Mizoram is 103 MLD and total treatment
capacity is only 10 MLD (01 STP). Figure 4.16 depicts statistics on sewage generation,
treatment capacity, operational capacity, actual utilization and complied capacity. It is
informed that installed STP is non-operational and entire sewage is discharged untreated.

120

103
100

80
In MLD

60

40

20
10 10 10

0
Sewage Generation Total Capacity Installed Capacity Non Operational

Figure 4.16: Sewage Generation and Treatment Capacity (MLD) – Mizoram

4.23 STPs AT NAGALAND


Nagaland has no sewage treatment plant. Septic tanks are used for disposal of sewage.

- 42 -
4.24 STPs AT NCT DELHI

Estimated sewage generation for the union territory of NCT Delhi is 3,330 MLD and total
treatment capacity is 2,896 MLD (38 STPs). Figure 4.17 shows information on sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity and
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
data analysis, following observations are made:

1. Installed capacity is 2,896 MLD (86.96 %) against sewage generation of 3330 MLD. It
shows that there is gap in treatment capacity of 434 MLD (13.04 %).
2. Out of 2,896 MLD installed capacity developed, operationalized capacity is 2715 MLD
(35 STPs) (93.75 %) and actual utilized capacity is 2412 MLD and further capacity of
complied STPs is only 90 MLD.
3. ASP based treatment technology is predominant as compared to natural treatment
system.

3500 3330

3000 2896 2896


2715

2500 2412

2000
In MLD

1500

1000

500
181
90
0
Sewage Total Installed Operational Actual Complied Non
Generation Capacity Capacity Utilization Capacity Operational

Figure 4.17: Sewage Generation and Treatment Capacity (MLD) – NCT Delhi

- 43 -
4.25 STPs AT ODISHA

Estimated sewage generation for the state of Odisha is 1,282 MLD and total treatment
capacity is 378 MLD (14 STPs). Figure 4.18 depicts sewage generation, treatment capacity,
operational capacity, actual utilization, complied capacity, capacities of non operational
STPs, under construction STPs and proposed STPs. Based on the data analysis, following
observations are made:

1. Installed capacity is 378 MLD (29.48 %) against sewage generation of 1,282 MLD. It
shows that there is gap of 904 MLD (70.51 %) in treatment capacity.
2. Out of 378 MLD of installed capacity developed, operationalized capacity is 55 MLD
(14.55 %) and actual utilized capacity is 50 MLD only.

1400
1282

1200

1000

800
In MLD

600

378 378
400 323

200
55 50
0
Sewage Total Capacity Installed Operational Actual Under
Generation Capacity Utilization Construction

Figure 4.18 : Sewage Generation and Treatment Capacity (MLD) – Odisha

- 44 -
4.26 STPs AT PUDUCHERRY

Estimated sewage generation for the State of Puducherry is 161 MLD and total
treatment capacity (including proposed) is 59 MLD (04 STPs). Figure 4.19 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
data analysis, following observations are made:

1. Installed capacity is 56 MLD (34.79 %) against sewage generation of 161 MLD. It shows
that there is gap of 105 MLD (65.21 %) in treatment capacity.
2. All the STPs installed can be operated at full capacity but actual utilized capacity is 30
MLD only.
3. STPs based on UASB technology are predominant as compared to other conventional
treatment systems.

180
161
160

140

120

100
In MLD

80
59 56 56
60

40 30

20
3
0
Sewage Total Capacity Installed Operational Actual Proposed
Generation Capacity Utilization

Figure 4.19: Sewage Generation and Treatment Capacity (MLD)

- 45 -
4.27 STPs AT PUNJAB

Estimated sewage generation for the State of Punjab is 1,889 MLD and total treatment
capacity is 1,781 MLD (119 STPs). Figure 4.20 depicts sewage generation, treatment
capacity, operational capacity, actual utilization, complied capacity, capacities of non
operational STPs, under construction STPs and proposed STPs. Based on data analysis,
following observations are made:

1. Installed capacity is 1,781 MLD (94.28 %) against sewage generation of 1,889 MLD. It
shows that there is gap of 108 MLD (5.72 %) in treatment capacity.
2. Out of 1781 MLD of installed capacity developed, operationalized capacity is 1601
MLD (89.89 %) and actual utilized capacity is 1,360 MLD (84.94 %). Further , the
capacity of complied STPs is only 441 MLD.
3. SBR, MBBR and WSP based STPs are predominant as compared to other conventional
treatment systems.

2000 1889
1781 1781
1800
1601
1600
1360
1400

1200
In MLD

1000

800

600
441
400
177
200
3
0
Sewage Total Installed Operational Actual Complied Non Under
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.20: Sewage generation and Treatment Capacity (MLD) - Punjab

- 46 -
4.28 STPs AT RAJASTHAN

Estimated sewage generation for the State of Rajasthan is 3,185 MLD and total treatment
capacity (including proposed) is 1,195 MLD (140 STPs). Figure 4.21 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
the data analysis, following observations are made:

1. Installed capacity is 1,086 MLD (34.10 %) against sewage generation of 3,185 MLD. It
shows that there is gap of 2,099 MLD (65.90 %) in treatment capacity.
2. Out of 1086 MLD of installed capacity developed, operationalized capacity is 783 MLD
(72.09 %) and actual utilized capacity is 478 MLD. Further, capacity of complied STPs
is only 224 MLD.

3500
3185

3000

2500

2000
In MLD

1500
1195
1086
1000 783

478
500
224 262
41 109
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.21: Sewage Generation and Treatment Capacity (MLD) - Rajasthan

- 47 -
4.29 STPs AT SIKKIM

Estimated sewage generation in Sikkim is 52 MLD and total treatment capacity (including
proposed) is 30 MLD (11 STPs). Figure 4.22 depicts sewage generation, treatment capacity,
operational capacity, actual utilization, complied capacity, capacities of non operational
STPs, under construction STPs and proposed STPs. Based on the analysis, following
observations are made:

1. Installed capacity is 20 MLD (38.46 %) against sewage generation of 52 MLD. It shows


that there is gap of 32 MLD (61.54 %) in treatment capacity.
2. Out of 20 MLD of installed capacity developed, operationalized capacity is 18 MLD (90
%).
3. Similarly, actual utilized capacity is 14 MLD (77.77 %) out of 18 MLD of operational
capacity.
4. STPs based on FAB and MBBR technologies are predominant as compared to natural
treatment systems.

60
52
50

40

30
30
In MLD

20
20 18
14
10
10
2
0
Sewage Total Installed Operational Actual Under Proposed
Generation Capacity Capacity Utilization Construction

Figure 4.22 : Sewage Generation and Treatment Capacity (MLD) – Sikkim

- 48 -
4.30 STPs AT TAMIL NADU

Estimated sewage generation for the State of Tamil Nadu is 6,421 MLD and total treatment
capacity is 1,492 MLD (63 STPs). Statistics on sewage generation, treatment capacity,
operational capacity, actual utilization, complied capacity, capacities of non operational
STPs, under construction STPs and proposed STPs are presented in Figure 4.23. Based on
the data analysis, following observations are made:

1. Installed capacity is 1,492 MLD (23.23 %) against the sewage generation of 6421 MLD.
It shows that there is gap of 4,929 MLD (76.77 %) in treatment capacity.
2. Out of 1,492 MLD of installed capacity developed, operationalized capacity is also
1,492 MLD (100 %) and actual utilized capacity is 995 MLD. Further, the capacity of
complied STPs is only 1,368 MLD.
3. ASP technology based STPs are predominant as compared to natural treatment
systems.

7000
6421

6000

5000

4000
In MLD

3000

2000
1492 1492 1492 1368
995
1000

0
Sewage Total Capacity Installed Operational Actual Complied
Generation Capacity Utilization Capacity

Figure 4.23: Sewage Generation and Treatment Capacity (MLD) – Tamilnadu

- 49 -
4.31 STPs AT TELANGANA

Estimated sewage generation for the State of Telangana is 2,660 MLD and total treatment
capacity (including proposed) is 901 MLD (37 STPs). Figure 4.24 depicts sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
the data analysis, following observations are made:

1. Installed capacity is 901 MLD (33.87 %) against sewage generation of 2,660 MLD. It
shows that there is gap in treatment capacity of 1,759 MLD (66.13 %).
2. Out of 901 MLD of installed capacity developed, operationalized capacity is 842 MLD
(93.45 %) and actual utilized capacity is 706 MLD. Further, the capacity of complied
STPs is only 637 MLD.
3. STPs based on ASP and MBBR based technologies are predominant as compared to
natural treatment systems.

3000
2660

2500

2000
In MLD

1500

1000 901 901 842


706
637

500

24 35
0
Sewage Total Installed Operational Actual Complied Non Under
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.24: Sewage Generation and Treatment Capacity (MLD) – Telangana

- 50 -
4.32 STPs AT TRIPURA

Estimated sewage generation for the State of Tripura is 237 MLD and total treatment
capacity is 08 MLD (01 STP) only. Figure 4.25 depicts sewage generation, treatment
capacity, operational capacity, actual utilization and complied capacity. Based on the data
analysis, it is found that there is only one STP in the State which is receiving only 1.5 MLD
of sewage and meeting the consented norms.

250 237

200

150
In MLD

100

50

8 8 8 8
1.5
0
Sewage Total Capacity Installed Operational Actual Complied
Generation Capacity Utilization Capacity

Figure 4.25 : Sewage Generation and Treatment Capacity ( MLD) – Tripura

- 51 -
4.33 STPs AT UTTAR PRADESH

Estimated sewage generation for the State of Uttar Pradesh is 8,263 MLD and total
treatment capacity is 3,374 MLD (107 STPs). Figure 4.26 depicts sewage generation,
treatment capacity; operational capacity, actual utilization, complied capacity and capacity
of non operational STPs. Based on the data analysis, following observations are made:

1. Installed capacity is 3,374 MLD (40.83 %) against sewage generation of 8,263 MLD. It
shows that there is gap of 4,889 MLD (59.17 %) in treatment capacity.
2. Out of 3,374 MLD of installed capacity developed, operationalized capacity is 3,224
MLD (95.55 %) and actual utilized capacity is 2,510 MLD (77.85 %). Further, capacity of
complied STPs is only 2,114 MLD.
3. STPs based SBR, UASB and ASP technologies are predominant as compared to natural
treatment systems.

9000
8263
8000

7000

6000

5000
In MLD

4000
3374 3374 3224
3000 2510
2114
2000

1000
150
0
Sewage Total Installed Operational Actual Complied Non
Generation Capacity Capacity Utilization Capacity Operational

Figure 4.26: Sewage Generation and Treatment Capacity (MLD) – Uttar Pradesh

- 52 -
4.34 STPs AT UTTARAKHAND

Estimated sewage generation for the State of Uttarakhand is 627 MLD and total
capacity (including proposed) is 515 MLD (81 STPs). Figure 4.27 represents statistics on
sewage generation, treatment capacity, operational capacity, actual utilization, complied
capacity, capacity of non operational STPs, under construction and proposed STPs. Based
on the dataanalysis, following observations are made:

1. Installed capacity is 448 MLD (71.45 %) against sewage generation of 627 MLD. It
shows that there is gap of 179 MLD (28.55 %) in treatment capacity.
2. Out of 448 MLD of installed capacity developed, operationalized capacity is 345 MLD
(77 %) and actual utilized capacity is 187 MLD. Further, capacity of complied STPs is
only 345 MLD.

700
627
600
515.18
500
448.18

400
345 345
In MLD

300

187
200

103
100 67

0.18
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.24: Sewage Generation and Treatment Capacity (MLD) - Uttarakhand

- 53 -
4.35 STPs AT WEST BENGAL

Estimated sewage generation for the State of West Bengal is 5,457 MLD and total capacity
(incl. proposed) is 1,202 MLD (65 STPs). Figure 4.26 represents statistics on sewage
generation, treatment capacity, operational capacity, actual utilization, complied capacity,
capacities of non operational STPs, under construction STPs and proposed STPs. Based on
the data analysis, following observations are made:

1. Installed capacity is 897 MLD (16.43 %) against the sewage generation of 5,457 MLD. It
shows that there is gap of 4,560 MLD (83.57 %) in treatment capacity.
2. Out of 897 MLD of installed capacity developed, operationalized capacity is 337 MLD
(37.56 %) and actual utilized capacity is 213 MLD (63.20 %). Further, capacity of
complied STPs is only 126 MLD.

6000
5457

5000

4000
In MLD

3000

2000

1202
897
1000
337 213 324 236 305
126
0
Sewage Total Installed Operational Actual Complied Non Under Proposed
Generation Capacity Capacity Utilization Capacity Operational Construction

Figure 4.26: Sewage Generation and Treatment Capacity (MLD) – West Bengal

- 54 -
Chapter 5
Major Findings and Way Forward
----------------------------------------------------------------------------------------------
5.1 MAJOR FINDINGS

Information received from the SPCBs on STPs are collated and compiled and analysis of
data are carried out with respect to installed capacity, operational capacity, actual
utilization and technological adopted along with compliance status. Observations are as
follows :

1. Sewage generation estimated to 72,368 MLD whereas installed treatment capacity is


31841 MLD (43.9 %). Out of 31,841 MLD installed capacity developed, operationalized
capacity is 26,869 MLD (84 %).

2. Similarly, actual utilized capacity is 20,235 MLD (75 %) out of 26,869 MLD operational
capacity. This is due to lack of infrastructure for conveyance system (Household
connectivity, sewer lines, Sewage pumping stations).

3. STPs based on various treatment technologies are installed by the States which ranges
from conventional to advanced technologies.

4. STPs based on Sequential Batch Reactor (SBR) treatment technology are installed and
predominate in most of the States / UTs. This is followed by ASP technology based
STPs. In total, 490 STPs are designed on SBR technology followed by 321 STPs
designed on Activated Sludge Process (ASP).

- 55 -
5. 76 STPs are based on Upflow- Anaerobic Sludge Blanket (UASB) technology.

6. Apart from conventional treatment technologies, STPs based on natural treatment


systems are also established all over the country.67 STPs are based on Waste
Stabilization Pond system and 61 STPs belong to the category of Oxidation Ponds.

7. States of Maharashtra, Gujarat, Uttar Pradesh, NCT of Delhi and Karnataka are the top
5 States which have installed significant sewage treatment facilities. These 5 States
jointly contribute to 19, 250 MLD i.e. 60.5 % of the total installed treatment capacity of
the country.

8. In addition to 1 above, States of Haryana, Madhya Pradesh, Punjab,Tamil Naduand


Rajasthan i.e. these 10 States contribute to the tune of 86 % (approx..) towards total
installed treatment capacity.

9. Arunachal Pradesh, Andaman & Nicobar Islands, Lakshadweep, Manipur, Meghalaya


and Nagaland have not installed sewage treatment plants.

10. 08 States / UTs (Gujarat, Himachal Pradesh, Kerala, Pondicherry, Sikkim, Chandigarh,
Chhattisgarh, Madhya Pradesh) has not provided the status of compliance.

11. Considering, treatment capacity developed per capita, Chandigarh (240 lpcd), Haryana
(184 lpcd), NCT of Delhi (151 lpcd), Punjab (141 lpcd) and Maharashtra (115 lpcd) have
higher treatment capacity. 29 States / UTs have treatment capacity of less than 100 lpcd.

12. State of Maharahtra has highest installed treatment capacity as well as highest complied
treatment capacity. However, per capita installed capacity is maximum observed in UT
of Chandigarh (240 lpcd) whereas Maharashtra is having per capita treatment capacity
of 115 lpcd.

13. State of Haryana has the maximum complied per capita treatment capacity (142 lpcd)
whereas Maharashtra is having complied per capita treatment capacity of 58 lpcd.

14. NCT of Delhi has the fourth highest treatment capacity of 2896 MLD and per capita
treatment capacity is 151 lpcd (3rd highest) wheres complied treatment capacity is only 4
lpcd.

- 56 -
5.2 WAY FORWARD

1. Considering the rapid urbanization and sewage generation , there is need to bridge the
existing gap in sewage treatment. Apart from filling the gap, there is also need to
synchronize future requriment of treatment capacity.

2. As, it is found that utilization of existing infrasturtre is only 75 % of operationalized


treatment capacity and thereby, it is suggested that sewerage conveyance system
which include laying of sewer line, individuals households sewer connections require
to be strenghthen considering existing and future demand.

3. With respect to compliance requirement, it is found that only 23 % of treatment


capacity is meeting the consented parameters of SPCBs / PCCs. In view of this , there
is also needed to have focus on operation and maintenance of treatment facility so that
STPs meet desired quality of treatment.

4. ULBs shall focus on uilization of treated sewage for non potable purposes like
horticulture, irrigation, fire fighting, industrial cooling , toilet flushing, non-contact
impoundments and washing (floors, roads, buses , trains etc.).

5. Treated sewage shall also be provided to industrial clusters / zones so that industrial
zone shall treat further as per their requirement and utilize the same.

********************************

- 57 -
ANNEXURE-I

Name of the State -

INVENTORIZATION OF SEWAGE TREATMENT PLANTS (As of 30.06.2020)

Sl. City/ Location of Date of Status Installed Actual Utilization Technology (UASB Use of Compliance
No Town STPwith Commissioning (Operational Capacity of of installed / ASP / OP / SBR / treated Status
Coordinates / Non- STP (in MLD) Capacity (in MBR/ FAB Etc.) sewage with (Comply / Non-
(Latitude and Operational / MLD) Quantity comp /Partially
Longitude, If Under Comply.)
available) Construction)

58
ANNEXURE-II

RECOMMENDED NORMS BY CPHEEO FOR TREATED SEWAGE QUALITY FOR SPECIFIED ACTIVITIES AT
POINT OF USE

Recommended norms of treated sewage quality for specified activities at point of use
Sl. Parameter Toilet Fire Vehicle Non-contact Landscaping, Horticulture & Agriculture
N o. flushing protection Exterior impoundments Horticulture, Crops
washing Golf course Non crops which are eaten
edible
crops
Raw Cooked
1 Turbidity (NTU) <2 <2 <2 <2 <2 AA <2 AA
2 SS nil nil nil nil nil 30 nil 30
3 TDS 2100
4 pH 6.5 to 8.3
5 Temperature °C Ambient
6 Oil & Grease 10 nil nil nil 10 10 nil nil
7 Minimum Residual Chlorine 1 1 1 0.5 1 nil nil nil

8 Total Kjeldahl Nitrogen as N 10 10 10 10 10 10 10 10


9 BOD 10 10 10 10 10 20 10 20
10 COD AA AA AA AA AA 30 AA 30
11 Dissolved Phosphorous as P 1 1 1 1 2 5 2 5
12 Nitrate Nitrogen as N 10 10 10 5 10 10 10 10
13 Faecal Coliform in 100 ml nil nil nil nil nil 230 nil 230

14 Helminthic Eggs/ litre AA AA AA AA AA <1 <1 <1


15 Colour Colourless Colourless Colourless Colourless Colourless AA Colourless Colourless
16 Odour Aseptic which means not septic and no foul odour
All units in mg/l unless specified; AA-as arising when other parameters are satisfied;
A tolerance of plus 5% is allowable when yearly average values are considered.

59
ANNEXURE-III
STATE-WISE DETAILS OF STPS AS PER PROFORMA
ANDHRA PRADESH
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Non complying. A letter was
Activated
Mudasarlova, To golf club play communicated on 07.03.2020 for
1 April'2008 Operational 13 6.5 Sludge
Hanumantuwaka ground effective operation of the STP to
Process
meet to the specified standard.
Non complying. A letter was
Activated
Appughar, communicated on 07.03.2020 for
2 Sep. 2010 Operational 25 23 Sludge To sea
Santhi Asramam effective operation of the STP to
Process
meet to the specified standard.
Non complying. A letter was
Activated
Laxmi talkies communicated on 07.03.2020 for
3 Mar.2019 Operational 38 23.4 Sludge To GVMC Drain
Gnanapuram PS effective operation of the STP to
Process
meet to the specified standard.
Anakapalle (Storm Activated
4 Visakhapatnam Water Drainage Apr-18 Operational 15 5 Sludge To Municipal Drain Complied
Treatment Plant ) Process
Activated
Narava,
5 Aug-01 Operational 54 19.6 Sludge To GVMC Drain Complied
Viman nagar PH
Process

Non complying. A letter was


Madinabagh Moving Bed
communicated on 07.03.2020 for
6 Adiesent at Steel Apr-18 Operational 2 0.4 Biofilm To GVMC Drain
effective operation of the STP to
plant Reactor
meet to the specified standard.

Yathapalem
Fluidized
APIIC Area
7 April'2008 Operational 2.5 -- Aerobic Bed To GVMC Drain Non complying.
,Gajuwaka
Reactor
Gangavaram

60
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Non complying. A letter was
Fluidized
Srinagar,Gajuwaka communicated on 07.03.2020 for
8 April'2008 Operational 0.5 0.2 Aerobic Bed To GVMC Drain
Area of Zone-V effective operation of the STP to
Reactor
meet to the specified standard.
Non complying. A letter was
Moving Bed
Mantripalem Near communicated on 07.03.2020 for
9 April'2008 Operational 1 0.35 Biofilm To GVMC Drain
Lankelapalem effective operation of the STP to
Reactor
meet to the specified standard.
Non complying. A letter was
Moving Bed
Rathi Cheruvu communicated on 07.03.2020 for
10 Sep-19 Operational 2 1 Biofilm To GVMC Drain
Pendurthi effective operation of the STP to
Reactor
meet to the specified standard.
Moving Bed
Kommadi,
11 Aug' 2018 Operational 4 2.8 Biofilm To GVMC Drain Complied
Madhurawada
Reactor
Visakhapatnam Non complying. A letter was
Moving Bed
Bakkannapalem communicated on 07.03.2020 for
12 Aug-11 Operational 1 0.6 Biofilm To GVMC Drain
Madhurawada effective operation of the STP to
Reactor
meet to the specified standard.
Non complying. A letter was
Marikavalasa Moving Bed
communicated on 07.03.2020 for
13 Madhurawada Dec-12 Operational 2 1.5 Biofilm To GVMC Drain
effective operation of the STP to
Zone-I Area Reactor
meet to the specified standard.
Non complying. A letter was
Moving Bed
communicated on 07.03.2020 for
14 VAMBAY Colony Aug' 2011 Operational 3 2 Biofilm To GVMC Drain
effective operation of the STP to
Reactor
meet to the specified standard.
Non complying. A letter was
YSR Nagar, Moving Bed
communicated on 07.03.2020 for
15 Madhurawada Aug' 2011 Operational 2 1.3 Biofilm To GVMC Drain
effective operation of the STP to
Zone-I Area Reactor
meet to the specified standard.

61
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Non complying. A letter was
Boyapalem Moving Bed
communicated on 07.03.2020 for
16 Paradesipalem Aug-11 Operational 1 0.7 Biofilm To GVMC Drain
effective operation of the STP to
Madhurawada Reactor
meet to the specified standard.
Karnavanipalem
Moving bed
Gajuwaka, APIIC
17 Dec-19 No Operational 5 -- bio film -- Non-operational
Colony, Ward
reactor
No.51
Visakhapatnam
Aganampudi
Moving bed
Gajuwaka Area,
18 Dec-15 No Operational 6 -- bio film -- Non-operational
Nr.Duvvada, Ward
reactor
No.57
Treated water for
19 East Godavari Hukumpet Mar-09 Operational 30 30 UASB Complied
grass fields
Partially comply. The outlet of
20 Ajith Singh Nagar May-11 Operational 40 39.52 UASB Budameru canal the STPs meet the standards
except BOD
Partially comply. The outlet of
21 Ajith Singh Nagar May-12 Operational 20 20 UASB Budameru canal the STPs meet the standards
except BOD
Partially comply. The outlet of
Ramalingeswar
22 Jun-12 Operational 20 19.74 UASB Krishna River the STPs meet the standards
Nagar
Krishna except BOD
Extended Partially comply. The outlet of
Ramalingeswar
23 Oct. 2006 Operational 10 9.8 Aeration Krishna River the STPs meet the standards
Nagar
System except BOD
Extended Partially comply. The outlet of
Autonagar Nagar
24 Mar-05 Operational 10 9.7 Aeration Guntatippa drain the STPs meet the standards
(Old)
System except BOD
Partially comply. The outlet of
25 Jakkampudi Jul-17 Operational 20 13.5 UASB Budameru canal the STPs meet the standards
except BOD

62
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Moving bed Partially comply. The outlet of
Krishna Autonagar Nagar
26 Dec-18 Operational 10 9.8 bio film Guntatippa drain the STPs meet the standards
(New)
reactor except BOD
Tadepalli
Municipality (STP - Sequential
27 0.2 MLD), 2019 Operational 0.2 0.2 Batch Used for greenery Partially complied
Mahanadu Road Reactor
No. 19 Tadepalli,
Tadepalli
Municipality (STP -
Sequential
0.2 MLD),
28 2019 Operational 0.2 0.2 Batch Used for greenery Partially complied
Mahanadu Road
Guntur District Reactor
No. 07 Tadepalli,
Guntur District
Narasaraopet
Municipality (STP -
15.55 MLD), Near Activated
29 Compost Yard, 2019 Operational 15.55 8.5 Sludge Used for greenery Partially complied
Narasaraopet Process
(V&M), Guntur
District.
Activated
Janardhanreddy
30 Nellore Dec-19 Operational 5 3 Sludge Used for greenery Complying
Colony
Process
Tungabhadra
Pump House STP Soil bio-
31 Kurnool Mar-18 Operational 0.8 0.8 For Horticulture 0.7 Complied
Kurnool Municipal technology
Corporation
Sankal Bagh STP
Soil bio-
32 Kurnool Municipal Mar-19 Operational 0.8 0.8 For Horticulture 0.7 Complied
technology
Corporation
Kurnool
Jammichettu STP
Soil bio-
33 Kurnool Municipal Mar-20 Operational 0.8 0.8 For Horticulture 0.7 Complied
technology
Corporation

63
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Chittoor Municipal 1999 Operational 50 36 Aerobic The treated waste Partially Complied
corporation, Oxidation water is being taken
Tirupati ponds by M/s. Sri
Kalahasti pipes Ltd
of about 3.0 MLD
for industrial
purpose and 33.0
34 MLD treated
effluents are being
disposed to nearby
Isuka vagu from
there by farmers are
using for
agricultural
purpose.
Reuse of treated
waste water is not
planned. The
treated sewage is
Sri Bramaramba
Soil bio- being disposed on
35 Kurnool Maliikarjuna varla Feb-17 Operational 6 4.7 Complied
technology the land. Adjoining
Devastanam,
River Krishna is
approximately
1.2 KM away from
STP site.
Waste
For green belt
36 Kadappa Nanepalli Aug-12 Operational 20 4 stabilization Complied
development
ponds
Oxidation
For green belt
37 Kadappa Pulivendula Jan-09 Operational 6.5 2 pond Complied
development
system
Waste Partially used for
CP Colony,
38 Ananthapur Oct-10 Operational 8 6.5 stabilization green belt Complied
Tadipatri
ponds development

64
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Waste Partially used for
39 Yellanur, Tadipatri Oct-10 Operational 3.5 1.5 stabilization green belt Complied
ponds development
Sai Nagar, Oxidation
40 - No Operational 0.5 -- -- Non-operation
Puttaparthi Ponds
Gokulam, Under
41 - 0.5 -- -- -- Non-operation
Puttaparthi Rehabilitation
Prasanth Gram, Under
42 - 0.5 -- -- -- Non-operation
Puttaparthi Rehabilitation
Sequential
43 31.03.2022 Under 10 Batch
Srikakulam Srikakulam construction Reactor
Under
44 5
Vizianagaram Vizianagaram construction
Under
45 54 ASP
Visakhapatnam Visakhapatnam construction
Under
46 5
Bhimavaram Bhimavaram construction
Under
47 5
Tanuku Tanuku construction
Under
48 5
Eluru Eluru construction
Jakkampudi, Under
49 Vijayawada 20
Vijayawada construction
Guntur Rural, Under
50 10
Guntur Gorantla construction
Under
51 20
Reddypalem construction
Under
52 28
Etukuru Road construction
Guntur
Under
53 42
Suddapalli Donka construction
Montigetu Donka, Under
54 27
Near Railway Track construction
65
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status (Comply /
No Commissioning (Operational / Capacity Utilization (UASB / sewage with Non-comply / Partially
. Non- of STP of ASP /OP / quantity Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction / (In MLD)
Proposed)
Under
55 2
Tenali construction
Under
56 10
Tenali construction
Under
57 5
Chilakaluripet construction
Near Keerthi Estate,
Under
58 Ashramam Road, 0.2
construction
Tadepalli
Under
59 Prakasam 15 MBR
Ongole construction
Under
60 55 ASP
Allipuram construction
Under
61 11 ASP
Drivers Colony construction
Nellore
Under
62 20 ASP
Pottepalem construction
Under
63 Kavali 15 ASP
construction
Under
64 Chittoor Srikalahasthi 7 SBR
construction
Under
65 5
Madanapalle Madanapalle construction
Near Annamayya
Under
66 Annamayya Bhawan, Back side 1
construction
Bhawan in Tirupati town
Kadapa Municipal
67 Proposed 20
Kadapa Corpn.

66
BIHAR
Sl. City / Location of Date of Status (Operational Installed Actual Technology Use of treated sewage Compliance status
No. Town STP Commissioning / Non-Operational / Capacity of Utilization (UASB / with quantity (Comply / Non-
Under Construction STP (In of Installed ASP /OP / comply / Partially
/ Proposed) MLD) Capacity SBR / MBR Comply)
(In MLD) / FAB etc.)
Under construction Not applicable as STP Not applicable as STP
1 Pahari Dec-20 Physical Progress- 60 -- SBR is not commissioned is not commissioned
53.00% (60 MLD) till date till date
Under construction Not applicable as STP Not applicable as STP
2 Beur Aug.-20 Physical Progress- 43 -- SBR is not commissioned is not commissioned
99.00% (43 MLD) till date till date
Karmalichak Completed Physical Progress- 37 -- SBR
DPR
3 100% Trial started --
under preparati on
(37 MLD)
Under construction Not applicable as STP Not applicable as STP
4 Saidpur Jan-21 Physical Progress- 60 -- SBR is not commissi oned is not commissi oned
93.00% (60 MLD) till date till date
Survey work is
completed, for Not applicable as STP Not applicable as STP
sewerage network, is not commissi oned is not commissi oned
5 Patna Digha Dec-22 100 -- ASP
design under till till
progress. date date
(100 MLD)
Design and drawing Not applicable as STP Not applicable as STP
6 Kankarbagh Dec-22 under progress. 50 -- ASP is not commissi is not commissi
(50 MLD) oned till date oned till date
The decision to re-
tender shall be taken
up in coming Not yet
7 Danapur Dec-21 25 -- Not applicable Not applicable
BUIDCo Board finalized
meeting.
(25 MLD)
Maner Jun-21 Agreement executed 6.5 -- SBR
with successful
8 Not applicable Not applicable
bidder.
(6.5 MLD)

67
Sl. City / Location of Date of Status (Operational Installed Actual Technology Use of treated sewage Compliance status
No. Town STP Commissioning / Non-Operational / Capacity of Utilization (UASB / with quantity (Comply / Non-
Under Construction STP (In of Installed ASP /OP / comply / Partially
/ Proposed) MLD) Capacity SBR / MBR Comply)
(In MLD) / FAB etc.)
The decision to re-
tender shall be taken
Not yet
9 Fatuha Jun-21 in up in coming 7 -- Not applicable Not applicable
finalized
BUIDCo Board
meeting. (7 MLD)
Barh Dec-20 Physical Progress- 11 -- SBR
10 Not applicable Not applicable
37.00% (11 MLD)
Patna Bakhtiyarpu Jun-21 Agreement executed 10 -- SBR
11 r with successful Not applicable Not applicable
bidder. (10 MLD)
The decision to re-
tender shall be taken
Phulwarisha Not yet
12 Dec-21 up in coming 13 -- Not applicable Not applicable
ri ff finalized
BUIDCo Board
meeting. (13 MLD)
DPR is under
13 Lakhisarai Mokama Dec-20 preparation by 8 -- SBR Not applicable Not applicable
NEERI (8 MLD)
Two Bids received.
Financial bid is
opened and under
decision with respect
Not yet
14 Vaishali Hajipur Dec-22 to legal opinion 22 -- Not applicable Not applicable
finalized
received and sent to
BUIDCo for
necessary action.
(22 MLD)
Physical Progress-
15 Saran Chhapra Dec-21 32 -- SBR Not applicable Not applicable
5.00% (32 MLD)
Vaishali Sonepur Dec-20 Physical Progress- 3.5 -- SBR
16 Not applicable Not applicable
15.00% (3.5 MLD)
Survey work is
completed, Physical
17 Begusarai Begusarai Jun-22 17 -- SBR Not applicable Not applicable
Progress- 5.00%.
(17 MLD)

68
Sl. City / Location of Date of Status (Operational Installed Actual Technology Use of treated sewage Compliance status
No. Town STP Commissioning / Non-Operational / Capacity of Utilization (UASB / with quantity (Comply / Non-
Under Construction STP (In of Installed ASP /OP / comply / Partially
/ Proposed) MLD) Capacity SBR / MBR Comply)
(In MLD) / FAB etc.)
Observations of
NMCG and World
Bank have been
Not yet
18 Buxar Buxar Dec-22 received the same 16 -- Not applicable Not applicable
finalized
are being complied
by BUIDCo.
(16 MLD)
Munger Munger Dec-22 Agreement executed 30 -- SBR
19 with successful Not applicable Not applicable
bidder. (30 MLD)
Physical Progress-
20 Bhagalpur Sultanganj Dec-20 10 -- MBR Not applicable Not applicable
26.00% (10 MLD)
Proposal of BUIDCo
for hiring of new
consultant for DPR
correction has been
approved by SPMG Not yet
21 Bhagalpur Bhagalpur Jun-22 45 -- Not applicable Not applicable
and finalized
same submitted to
NMCG vide BGCMS
letter no- 165 dated:
08.04.2020. (45 MLD)
Physical Progress-
22 Bhagalpur Naugachia Dec-20 9 -- SBR Not applicable Not applicable
15.00% (9 MLD)
Three Bids received. Wetland
Bid Evaluation technology
23 Khagaria Khagaria Dec-21 4.5 -- Not applicable Not applicable
under progress.
(4.5 MLD)
Three Bids received. Not yet
Bid Evaluation finalized
24 Lakhisarai Barahiya Dec-21 6 -- Not applicable Not applicable
under progress.
(6 MLD)
Three Bids received. Not yet
Bid Evaluation finalized
25 Bhagalpur Kahalgaon Jun-22 6 -- Not applicable Not applicable
under progress.
(6 MLD)

69
CHANDIGARH

Sl. City / Location of Date of Status Installed Actual Technology Use of treated sewage Compliance status
No. Town STP Commissioning (Operational / Capacity of Utilization of (UASB / ASP with quantity (Comply / Non-
Non-Operational STP (In Installed /OP / SBR / comply / Partially
/ Under MLD) Capacity (In MBR / FAB Comply)
Construction / MLD) etc.)
Proposed)

Drains ultimately leads Falls under the


1 Diggian Mohali 2010 Operational 136.2 102.15 MBBR into river Ghaggar jurisdiction of PPCB

Drains ultimately leads Consent to Operate


2 Raipur Khurd 2006 Operational 5.67 5.67 ASP into river Ghaggar obtained

Drains ultimately leads Consent to Operate


3 Raipur Kalan 2007 Operational 22.7 22.7 UASB into river Ghaggar obtained
Chandigarh
Drains ultimately leads Consent under
4 3 BDR Phase I 2008 Non-Operational 22.7 0 UASB into river Ghaggar process
Drains ultimately leads
5 3 BDR Phase II 2013 Operational 49.94 31.78 SBR into river Ghaggar Consent obtained
Drains ultimately leads
6 Dhanas 2013 Operational 34.05 34.05 SBR into river Ghaggar Consent obtained
Drains ultimately leads
7 Maloya 2019 Operational 22.7 11.35 SBR into river Ghaggar Consent obtained

70
CHHATTISGARH

Sl. City / Location Date of Status Installed Actual Technology Use of Compliance
No. Town of STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational (In Installed SBR / MBR with Non-comply
/ Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)

1 Bilaspur Chilhati 13-04-2013 Operational 17 2.5 ASP River

2 Bilaspur Domuhani 03-01-2018 Operational 54 1.5 ASP River

Near Mini
3 Kawardha Mata 2013 Operational 2.1 1.65 ASP River
Chowk

71
DAMAN DIU & DADARA NAGAR HAVELI

Sl. City / Locatio Date of Status Installe Actual Technolog Use of treated Complianc
No Town n of Commissioni (Operationa d Utilizatio y (UASB / sewage with e status
. STP ng l / Non- Capacit n of ASP /OP / quantity (Comply /
Operational y of Installed SBR / MBR Non-
/ Under STP (In Capacity / FAB etc.) comply /
Constructio MLD) (In MLD) Partially
n/ Comply)
Proposed)
1 Silvassa Silvassa 19.01.2019 Operational 13 1.2 SBR Cleaning of Roads, Compiled
Flushing of Storm
Water Drainage and
Compaction of
Pipeline Trenches
(Approx. Quantity
being utilised 24
KLD)

2 Daman Daman 24.02.2018 Operational 4.21 1.1 SBR Watering the fort Compiled
periphery garden

3 Diu Diu Operational 7 4.5 SBR Watering for Compiled


Gardens, Cleaning of
Roads, Flushing of
Storm Water
Drainage etc.
(Approx. Quantity
being utilised 24
KLD)

72
GOA
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational / Capacity Utilization (UASB / treated status
Non- of STP of ASP /OP / sewage with (Comply /
Operational / (In Installed SBR / MBR quantity Non-
Under MLD) Capacity / FAB etc.) comply /
Construction / (In MLD) Partially
Proposed) Comply)
1 Vasco Katem Baina Mormugo 30.09.2017 Operational 20 8 SBR Nullah / Sea Comply
Nullah /
2 Navelim Shirvodem Navelim 28.06.2017 Operational 20 14 SBR River Comply
Goa Medical College Used for
3 Bambolim Bambolim 2009 Operational 1.35 0.7 SBR Gardening Comply
4 Durbhat Durbhat Ponda 29.09.2017 Operational 1 0.4 SBR River Comply
5 Sanquelim Sanquelim 20.03.2020 Operational 0.8 0.8 SBR Nallah Comply
6 Sancaole Sancaole Cortalim 2017 Operational 1 1 NTS Nallah Comply
Vrudavan Society Used for
7 Ponda Ponda 2014 Operational 0.1 0.08 NTS social forest Comply
Used for
8 Porvorim DTE Porvorim 2015 Operational 0.08 0.05 NTS Gardening Comply
Santa MBR + Used for
9 Cruz Santa Cruz Bardez 2015 Operational 0.025 0.017 MBBR Gardening Comply
Under
10 Quela Quela Ponda Construction 15 0 SBR
Under
11 Colva Colva Construction 7.5 0 SBR
12 Undir Undir Eandora Ponda Proposed 15 0 SBR
13 Curti Curti Ponda Proposed 8 0 SBR
14 Porvorim Porvorim Proposed 15 0 SBR

73
GUJARAT
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / Use of Compliance
No Commissioning (Operational / Capacity Utilization ASP /OP / SBR / treated status
. Non- of STP of Installed MBR / FAB etc.) sewage (Comply /
Operational / (In Capacity with Non-comply
Under MLD) (In MLD) quantity / Partially
Construction / Comply)
Proposed)

1 Pirana 2009 Operational 60 60 ASP 60

2 Old Pirana 2004 Operational 106 106 UASB 106

3 Pirana 2009 Operational 180 180 ASP 180

4 Vasna 2004 Operational 126 126 UASB 126

5 Vasna 2009 Operational 35 35 ASP 20 15

6 Vasna 2011 Operational 240 235 ASP 140 95

7 Vinzol 2011 Operational 70 70 ASP 70

8 Vasna 2018 Operational 48 48 SBR 48


Jalvihar Vadaj
Operational 60 55 SBR 55
9 2019
Ahmedabad Vinzol 2020 Operational 35 22 SBR 22
10
Shahpur
ShankarBhuvan Operational 25 17 SBR 17
11 2020
12 Lambha Operational 5 2 SBR 2

13 Arvind Mill Operational 8 8 8

14 Naroda AUDA Operational 7 7 7

15 Rasala Operational 1 1 MBBR 1

16 Vastrapur Lake Operational 0.5 0.5 MBBR 0.5

17 V S Hospital Operational 1 1 MBR 1

18 Nikol Operational 0.5 0.5 Electro Oxidation 0.5


Sequential Batch
Singanpore
Surat Operational 155 147.58 Reactor (SBR) 1.0 140.68
(2003/2014)
19 Process

74
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / Use of Compliance
No Commissioning (Operational / Capacity Utilization ASP /OP / SBR / treated status
. Non- of STP of Installed MBR / FAB etc.) sewage (Comply /
Operational / (In Capacity with Non-comply
Under MLD) (In MLD) quantity / Partially
Construction / Comply)
Proposed)
Integrated Fixed
Karanj Film Activated
Operational 140 136.59 1.5 130.99
(1999/2015) Sludge (IFAS)
20 Process
CASP + Sequential
Bhatar
Operational 162 165.25 Batch Reactor (SBR) 54 103.00
(1999/2014/2017)
21 Process
Integrated Fixed
Anjana Film Activated
Operational 122 88.51 1.5 83.47
(1995/2007/2019) Sludge (IFAS)
22 Process
UASB + Extended
Aeration +
Surat
Bamroli Integrated Fixed
Operational 100 77.90 57 19.34
(2008/2019) Film Activated
Sludge (IFAS)
23 Process
Conventional
Bhesan
Operational 100 113.08 Activated Sludge 20 87.43
(1995/2009)
24 Process
Moving Bed Bio
Khajod
Operational 25 21.36 Reactor (MBBR) 4.5 16.22
(2011)
25 Process
Moving Bed Bio
Asarama
Operational 15 19.23 Reactor (MBBR) 1 17.65
(2011)
26 Process
CASP + Sequential
Dindoli
Operational 167 33.39 Batch Reactor (SBR) 1.5 30.55
(2012/2020)
27 Process
Moving Bed Bio
Surat
Reactor (MBBR)
Variav-Kosad
Operational 134 119.64 Process + Sequential 1.5 113.35
(2012/2017)
Batch Reactor (SBR)
28 Process

75
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / Use of Compliance
No Commissioning (Operational / Capacity Utilization ASP /OP / SBR / treated status
. Non- of STP of Installed MBR / FAB etc.) sewage (Comply /
Operational / (In Capacity with Non-comply
Under MLD) (In MLD) quantity / Partially
Construction / Comply)
Proposed)
Sequential Batch
Gavier
Operational 53 5.37 Reactor (SBR) 0.5 4.66
(2016)
29 Process
Activated Sludge
Tarsali Operational 52 52 0 52
Process (ASP)
30
Activated Sludge
Gajarawadi Operational 66 66 0 66
Process (ASP)
31
Upflow Anaerobic
Kapurai Operational 43 43 Sludge Blanket 0 43
Vadodara
32 Reactor (UASB)
Sequencing Batch
Rajivnagar Operational 78 26 Reactor (SBR)with 3 26
33 Tertiary Treatment
Extended Aeration
Sayaji garden Operational 8.5 7 2 7
34 (MBBR E2o)
35 Channi Operational 21 21 Extended Aeration 0 21
Upflow Anaerobic
Sludge Blanket
Atladara (old) Operational 43 43 Reactor (UASB), Gas 0 43
based Power
36 generation
Vadodara
Upflow Anaerobic
Sludge Blanket
Atladara (new) Operational 43 43 Reactor (UASB), Gas 0 43
based Power
37 generation
38 Jaspur 2007 Operational 76 41 AST Technology - Causeway

39 Gandhinagar Sargasan 2012-13 Operational 10 3 SBR Technology 3 -


Forest
Basan 2011-12 Operational 2 1 SBR Technology -
40 Nursery
41 Rajkot Nr Raiya village Operational 51 35 ASP 0 35

76
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / Use of Compliance
No Commissioning (Operational / Capacity Utilization ASP /OP / SBR / treated status
. Non- of STP of Installed MBR / FAB etc.) sewage (Comply /
Operational / (In Capacity with Non-comply
Under MLD) (In MLD) quantity / Partially
Construction / Comply)
Proposed)
2010
42 Raiyadhar 2017 Operational 56 15 SBR 0.02 14.98

43 Nr Madhapar 2018 Operational 44.5 15 ASP 1.34 13.66


Nr Kothariya
Operational 15 5 SBR 0 5
44 Village 2017
45 Gavaridad 2018 Operational 70 30 SBR 0.9 29.1

46 Madhapar 2019 Operational 80 20 SBR 1.34 18.66


Nari road,
UASB + Oxidation
Kumbharwada Operational 30 24
pond
47 Bhavnagar 31.10.2018 40
Behind Excel
Operational 45 40 SBR 20
48 industries 9.3.2018
Navagam Ghed
Jamnagar Operational 70 65 SBR - 65
49 31.08.2016
50 Gandhidham Gandhidham Operational 18.00 18 Advanced Extended 18 -
Anjar Anjar Operational 12.00 4 Oxidation 4 -
51
52 Patan Patan Operational 25.00 13 SBR - 13
53 Nadiad Nadiad Operational 51.26 20 SBR - 20
54 Siddhpur Siddhpur Operational 5.62 5 Oxidation Pond - 5
Vallabh Vallabh
Operational 15.00 Oxidation Pond -
55 Vidhyanagar Vidhyanagar 12 12
Non Extendede Areation
Sanand Sanand 20.50 -
56 Operational 0 process -
57 Himmatnagar Himmatnagar Operational 17.51 6 ASP - 6
Extendede Areation
Petlad Petlad Operational 10.37 -
process
58 8 8
59 Dholka Dholka Operational 13.60 8 SBR - 8
60 Savarkundla Savarkundla Operational 13.90 5 Arocated Lagoon - 5

77
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / Use of Compliance
No Commissioning (Operational / Capacity Utilization ASP /OP / SBR / treated status
. Non- of STP of Installed MBR / FAB etc.) sewage (Comply /
Operational / (In Capacity with Non-comply
Under MLD) (In MLD) quantity / Partially
Construction / Comply)
Proposed)

61 Gadhda Gadhda Operational 6.50 2 Areated lagoon type - 2


62 Kathlal Kathlal Operational 3.80 2.59 Oxidation Pond - 2.59
63 Mahudha Mahudha Operational 2.10 1.76 Oxidation Pond - 1.76
64 Bayad Bayad Operational 4.00 2.06 Oxidation Pond - 2.06
65 Patadi Patadi Operational 2.80 1.33 Oxidation Pond - 1.33
66 Sojitra Sojitra Operational 2.30 2 Oxidation Pond - 2
67 Dwarka Dwarka Operational 7.50 2.28 SBR - 2.28
68 Godhra Godhra Operational 27.60 4 SBR - 4
69 Bhuj Bhuj Operational 23.70 19 SBR - 19
70 Bhachau Bhachau Operational 10 4 Oxidation Pond - 4

78
HARYANA
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Rathdana Road Non
1 Sonepat 2003 Operational 30 20 UASB Complying
Kakrai Road Non
2 Sonepat 2018 Operational 25 10 SBR Complying
Rajeev Gandhi
Education City
3 Sonepat Phase I 2019 Operational 7.5 0.3 ASP Complying
4 Kharkhoda 2013 Operational 4.5 2.5 MBBR Complying
Non
5 Ganaur STP 2012 Operational 7 6.29 MBBR Complying
6 Gohana 2015 Operational 3 1.8 MBBR Complying
7 Gohana 2012 Operational 8.3 6 MBBR Complying
Sewah Road
8 Panipat 2000 Operational 35 35 UASB Complying
Sewah Road
9 Panipat 2000 Operational 25 19.37 SBR Complying
Jattal Road
10 Panipat 2000 Operational 10 5 UASB Complying
Panipat Jattal Road
11 Panipat 2016 Operational 20 12 SBR Complying
12 Samalkha 2013 Operational 5 2.82 MBBR Complying
Sector 19
13 Panipat 2018 Operational 30 6 SBR Complying
14 Sector 6 Panipat 2019 Operational 0.8 0.5 SBR Complying
15 R.K. Puram Operational 8 2 SBR
Non
16 Karnal 2001 Operational 40 40 SBR Complying
Karnal Under
17 Karnal 2000 Operational 8 8 SBR upgradation
Gogari Road
18 Karnla 2019 Operational 10 4.5 SBR Complying
79
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)

19 Gharaunda 2018 Operational 7 4.5 SBR Complying


20 Inderi 2003 Operational 1.5 1.5 OP Complying
21 Asandh 2014 Operational 5 3 MBBR Complying
22 Nilokheri 2014 Operational 6 3.5 MBBR TT Complying
23 Nissing 2016 Operational 4 1.5 MBBR TT Complying
24 Taraori 2016 Operational 5.5 3 MBBR TT Complying
25 Thanesar 2019 Operational 25 17 SBR Complying
26 Pheowa 2019 Operational 8 1.57 MBBR Complying
Ladwa Road
Kurukshetra
27 Shahbad 2016 Operational 11.5 4.64 SBR Complying
28 Ladwa 2016 Operational 7 3.5 MBBR Complying
29 Urban Estate 2020 Operational 15 12.5 SBR Complying
Naya Gaon
30 Phase I 2011 Operational 3.5 1.25 MBBR Complying
Naya Gaon
31 Phase II 2016 Operational 3.5 1.25 MBBR Complying
Urban Estate
32 Amabala City 2015 Operational 2 2 MBBR Complying
Baldev Nagar
33 Phase I 2012 Operational 5 1.85 MBBR Complying
Baldev Nagar
34 Ambala Phase II 2016 Operational 3.25 2.5 MBBR Complying
Moti Nagar
35 Phase I 2010 Operational 5 1.3 MBBR Complying
Moti Nagar
36 Phase II 2016 Operational 5 1.75 MBBR Complying
37 Modal Town 2012 Operational 6 2.2 MBBR Complying
Nasirpur
38 Ambala City 2016 Operational 3.25 3.25 MBBR Complying
39 Sadopur 2016 Operational 0.25 1.01 MBBR TT Complying
80
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Ambala

40 Devi Nagar 2013 Operational 3.25 1.5 MBBR Complying


Naraingarh
41 Ambala 2014 Operational 3 1.2 MBBR Complying
42 Barara 2019 Operational 4 2.65 SBR Complying
Punchkula
43 HUDA 2002 Operational 18 18 ASP Complying
Punchkula
44 HUDA 2011 Operational 39 39 ASP Complying
Sector 28
45 Punchkula 2012 Operational 15 8 ASP Complying
Punchkula
46 Kalka 2015 Operational 4.5 3.3 MBBR Complying
47 Kalka 2017 Operational 0.25 0.1 MBBR Complying
Nalagarh Road
48 Manakpur 2015 Operational 5 0.35 MBBR Complying
Chandimandir
49 Punchkula 2012 Operational 9 6 MBBR Complying
Kosli Road,
50 Jhajjar 2007 Operational 5.5 4.5 MBBR Complying
Jhajjar Sampla Road,
51 Jhajjar 2014 Operational 5 3.7 MBBR Complying
52 Beri, Jhajjar 2010 Operational 2 0.5 OP Complying
Linepar
53 Bahadurgarh 2012 Operational 18 7.5 UASB Complying
Najafgarh
Road,
Bahadurgarh
54 Bahadurgarh 2014 Operational 36 12.6 SBR Complying
Beri Road
Jhajjar,
55 Bahadurgarh 2014 Operational 10 6 UASB Complying
Manas Road
Kaithal
56 Kaithal 2012 Operational 10 6.8 SBR Complying

81
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Manas Road
57 Kaithal 2006 Operational 10 7 MBBR Complying
Jind Road
58 Kaithal 2012 Operational 10 1.75 SBR Complying
59 HUDA Kaithal 2016 Operational 7.5 7.5 SBR Complying
60 Pundri 2014 Operational 3.5 2.1 MBBR Complying
61 Kalayat 2014 Operational 5 1.66 MBBR TT Complying
62 Cheeka 2013 Operational 10 6 MBBR Complying
PGIMMS,
63 Rohtak 2016 Operational 19.5 10 SBR Complying
64 Sonaria, Rohtak 2016 Operational 40 27 UASB Complying
Kalanour,
65 Rohtak 2010 Operational 3.5 1 MBBR Complying
Meham, Bharan
66 Road, Rohtak 2013 Operational 5 3.6 MBBR Complying
Rohtak Singhpura, under
67 Rohtak 2017 Operational 10 5.5 MBBR maintenance
Singhpura,
68 Rohtak 2015 Operational 14 7.5 SBR Complying
Rohtak, Kanheli
69 Road 2008 Operational 10 6 UASB Complying
Sampla Town,
70 Rohtak 2011 Operational 4 3 MBBR Complying
Sohna,
71 Gurgaon 2014 Operational 6 3.5 MBR Complying
Dhanwapur,
72 Gurgaon 2004 Operational 68 68 ASP Complying
Gurgaon Dhanwapur,
73 Gurgaon 2014 Operational 100 100 ASP Complying
Dhanwapur,
74 Gurgaon 2018 Operational 50 50 SBR Complying
75 Punhana, 2015 Operational 4.5 2.5 MBBR Complying

82
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Mewat

76 Nuh, Mewat 2016 Operational 3.6 1.5 MBBR Complying


77 Tauru, Mewat 2017 Operational 4.5 1 MBBR Complying
FirozpurZhirka,
78 Mewat 2020 Operational 5 1.6 MBBR Complying
79 Pataudi 2017 Operational 4.5 3 MBBR Complying
80 Behrampur 2010 Operational 50 45 ASP Complying
81 Behrampur 2014 Operational 120 110 UASB Complying
82 Farrukhnagar 2018 Operational 3 2.8 SBR Complying
83 Hally Mandi 2020 Operational 5.5 1.85 SBR Complying
84 Faridabad Badshahpur 2011 Operational 45 10 SBR Complying
85 Pratapgarh 1999 Operational 50 50 UASB Complying
Ballabhgarh
86 Munjheri 1999 Operational 45 45 UASB Complying
MBBR +
87 Hasanpur 2016 Operational 3 1.2 Dual Filter Complying
88 Palwal Hathin 2015 Operational 4.5 2.9 MBBR Complying
89 Hodal 2013 Operational 9 4.35 MBBR Complying
90 Palwal 2007 Operational 9 8 OP Complying
91 Jind 2009 Operational 15 15 MBBR Complying
92 HUDA 2014 Operational 10 10 SBR Complying
Patiala Road
93 Narwana 2011 Operational 3.5 2 MBBR Complying
94 Jind Narwana 2011 Operational 3.75 3 MBBR Complying
Dablain Road
95 Narwana 2017 Operational 2 0.75 MBBR Complying
96 Uchana 2012 Operational 2 1.25 MBBR Complying
97 Uchana 2013 Operational 1.5 1 OP Complying

83
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)

98 Jind 2016 Operational 5 5 MBBR Complying


99 Julana 2016 Operational 4 2.6 MBBR Complying
100 Safidon 2018 Operational 9 4.5 SBR Complying
101 Jind 2020 Operational 7 4 MBBR Complying
Dhana Road
102 Bhiwani 2013 Operational 10 6.11 MBBR Complying
103 Bhiwani 2014 Operational 10 7.1 MBBR Complying
104 Bhiwani Phase I 2013 Operational 15 10.5 SBR Complying
Bhiwani Phase
105 II 2014 Operational 15 12.5 SBR Complying
106 Huda, Bhiwani 2015 Operational 10 10 SBR Complying
Jhajjar / Delhi
Road Charkhi
107 Bhiwani Dadri Bhiwani 2014 Operational 5 1.5 MBBR Complying
Chiriya Road
Charkhi Dadri
108 Bhiwani 2013 Operational 5 4.25 SBR Complying
109 Bawani Khera 2015 Operational 4.5 1.25 MBBR Complying
Loharu
110 Bhiwani 2015 Operational 3.5 2.16 MBBR Complying
Tosham,
111 Bhiwani 2014 Operational 3 2 MBBR Complying
112 Siwani 2014 Operational 4 2.25 MBBR Complying
Dulana Road
113 Mohindergargh 2014 Operational 6.5 1.37 MBBR Complying
Ateli Mandi
114 Mohindergarh 2016 Operational 2 1.9 MBBR Complying
Mohindergarh
Kanina
115 Mohindergarh 2016 Operational 3 0.6 MBBR Complying
Rewari Road
116 Narnaul 2015 Operational 7.5 4 MBBR Complying

84
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Kharkhara
117 Dharuhera 2017 Operational 9.5 3 SBR Complying
118 Bawal 2014 Operational 3 1.75 MBBR Complying
119 Rewari 2014 Operational 6.5 5 MBBR Complying
Rewari
120 Rewari 2007 Operational 8 4.5 MBBR Complying
121 Rewari 2014 Operational 16 12 SBR Complying
122 Kosli Rewari 2016 Operational 3 2 MBBR Complying
123 Rewari HUDA 2019 Operational 5 3 SBR Complying
124 Hisar 2019 Operational 6.5 1 SBR Complying
Dhani Kusal
Bhiwani Road
125 Hansi 2014 Operational 5 4 MBBR Complying
Lalpura Jind
126 Road Hansi 2014 Operational 7.5 6 MBBR Complying
Dhani Gram
127 Barwala 2014 Operational 6 2.5 MBBR Complying
Azad Nagar
Hisar Rajgarh Road
128 Hisar 2014 Operational 15 6 SBR Complying
Rishi Nagar
129 Hisar 2017 Operational 40 15 SBR Complying
130 Namauda Hisar Operational 4 2 MBBR TT Complying
131 Ukiana Hisar 2017 Operational 6.5 4 MBBR Complying
Dabara Tosham
132 Road Hisar 2014 Operational 15 14.5 SBR Complying
Kaimiri Road
133 Hisar 2018 Operational 4 2 SBR Complying
Shamsabad
Patti Kalania
134 Sirsa Road Sirsa 2012 Operational 15 9.15 MBBR Complying
135 Nattar Vill Sirsa 2013 Operational 5 4.5 MBBR Complying
85
Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
Nattar Vill2
136 Sirsa 2017 Operational 5 5 MBBR Complying
137 Ellenabad Sirsa 2015 Operational 7.5 6 MBBR Complying
Daddu Road
138 Sirsa 2018 Operational 9.5 4.5 SBR Complying
139 Rania Sirsa 2017 Operational 6 4 SBR Complying
140 Dabawali Sirsa 2017 Operational 16.5 4.5 SBR Complying
Kelnia District
141 Sirsa 2019 Operational 20 9 SBR Complying
Bhodia Khera
142 Fattehabad 2013 Operational 10 7.5 MBBR Complying
Amani Tohana
143 Fattehabad 2013 Operational 10 8 MBBR Complying
Ratia
144 Fattehabad Fattehabad 2014 Operational 6.5 4 MBBR Complying
Majra
145 Fattehabad 2017 Operational 10 1 SBR Complying
146 Kharati Khera 2018 Operational 5 3 SBR Complying
Jhakai Mandi
147 Fattehabad 2019 Operational 3 1 SBR Complying
Radaur Road
148 Yamuna Nagar 2020 Operational 25 25 SBR Complying
Radaur Road 2019
149 Yamuna Nagar (September) Operational 20 20 SBR Complying
Badi Majra
150 Yamuna Yamuna Nagar 2020 (June) Operational 10 10 SBR Complying
Nagar Chhachhrauli
151 Yamuna Nagar 2015 Operational 3 3 MBBR TT Under Trial
Parwalo
152 Yamuna Nagar 2018 Operational 24 15 SBR Complying
Radaur
153 Yamuna Nagar 2015 Operational 3.5 3.5 MBBR TT Under Trial

86
HIMACHAL PRADESH
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
1 STP Ghumarawin 2005-06 Operational 1.2 0.84 ASP
2 Bilaspur STP Naina Devi ji 2005-06 Operational 1.35 0.75 ASP
ASP with
3 Khaliar NA Operational 0.47
NA EA
4 STP Chamba Barga 20.03.2008 Operational 1.501 0.85 ASP
5 Chamba STP Chamba Bhagot 25.02.2008 Operational 0.89 0.75 ASP
6 STP Shitla Bridge 23.03.2010 Operational 0.2 0.12 ASP
STP Hamirpur,
7 Distt.Hamirpur 6.08.2008 Operational 1.35 1.05 ASP
Zone II
STP Hamirpur,
8 Distt.Hamirpur 23.01.2010 Operational 3.13 0.78 ASP
Zone I
STP Hamirpur,
9 Hamirpur Distt.Hamirpur 23.01.2010 Operational 0.68 0.44 ASP
Zone III
10 STP Nadaun 16.01.2008 Operational 1.69 0.1 ASP
11 STP Sujanpur Zone I 16.01.2008 Operational 1.5 0.52 ASP
12 NIIT hamirpur 01.03.1999 Operational 0.27 0.27 ASP
STP Sujanpur Zone
13 16.01.2008 Operational 1.75 0.1 ASP
II
STP
14 2006-07 Operational 2.5 1.5 ASP
Bhootnath,Kullu
15 STP Manali 2006-07 Operational 1.82 1.82 ASP
16 Kullu STP Badah 2008-09 Operational 0.38 0.12 ASP
17 STP Lanka Baker 2009-10 Operational 2.57 1.7 ASP
STP Mela Ground
18 2006-07 Operational 0.99 0.68 ASP
(Bhunter)

87
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
STP Sharabai
19 2006-07 Operational 0.46 0.25 ASP
Kullu (Bhunter)
20 STP Jard 2000-01 Operational 0.87 0.19 ASP
STP Sanjauli
22.10.2003 CTE ASP with
21 Malyana, Operational 4.44 4.44
24.05.2004 ctP EA
Distt.Shimla
22 STP Lalpani, Shimla 24.05.2004 Operational 10 10 ASP
ASP with
23 STP Dhalli,Shimla 22.10.2003 Operational 0.76 0.76
EA
STP
24 Rampur,(khopri) 19.06.2006 Operational 1 0.48 ASP
Distt. Shimla
STP Rampur
25 24.06.2014 Operational 0.5 0.26 ASP
(Choohabag)
ASP with
26 STP Rohroo 16.06.2008 Operational 1.745 1
EA
Shimla ASP with
27 STP Jubbal 10.11.2005 Operational 0.65 0.3
EA
North Disposal, 5.8 ASP with
28 Operational
Shimla 22.10.2003 NA EA
1.35 ASP with
29 Snowdon Operational
24.05.2004 NA EA
3.93 ASP with
30 Summer Hill Operational
22.10.2003 NA EA
ASP with
31 Narkanda Operational 0.45
03.04.2010 NA EA
32 STP Jhakri 03.05.2017 Operational 1 0.28 ASP
33 STP Theog Feb-20 Operational 1.15 NA ASP
34 STP Kotkhai Zone I Feb-20 Operational 0.305 0.305 ASP
35 STP Kotkhai Zone II Feb-20 Operational 0.16 0.16 ASP

88
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
STP at Saraswati
36 Shimla NA Operational 0.65 0.65 ASP
Nagar
STP Raghunath ka
37 31.01.2006 Operational 3.83 0.47 ASP
Pahar
38 STP Sunder Nagar 2007-08 Operational 3.55 2.9 ASP
Mandi
STP Neri Khadd, ASP with
39 2009-10 Operational 1.735 1.21
Joginder Nagar EA
STP Sarkaghat Zone
40 01.12.2016 Operational 0.7 0.15 ASP
B
41 STP Dharamsala 10.10.2006 Operational 5.15 3 ASP
STP Tanda Medical
42 09.11.2006 Operational 1.4 0.9 ASP
College Dharamsala
43 STP Jwalmukhi 19.10.2004 Operational 2.83 0.7 ASP
44 STP Palampur 2005 Operational 0.351 0.3 ASP
ASP with
45 Kangra STP Kangra Zone I 23.12.2006 Operational 1.68 1.05
EA
ASP with
46 STP Kangra Zone II 23.12.2006 Operational 1.46 0.38
EA
STP Kangra Zone ASP with
47 23.12.2006 Operational 0.63 0.44
III(old kangra) EA
48 STP Nagrota 29.03.2007 Operational 1.34 1 ASP
49 STP Dehra 27.08.2008 Operational 1.38 1.38 ASP
50 Kinnaur STP Rekong-Peo 29.06.2007 Operational 1 0.3 ASP
STP Paonta Sahib
51 08.07.2008 Operational 0.44 0.33 ASP
Zone I
Sirmour
STP Paonta Sahib
52 08.07.2008 Operational 1 0.2 ASP
Zone II

89
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
ASP with
53 STP Solan Zone B 19.06.2006 Operational 2.9 0.56
EA
ASP with
54 STP Arki 06.02.2007 Operational 0.7 0.27
EA
55 Solan Nalagarh NA Operational 3.62 ASP
3.62
56 Parwanoo 2020 Operational 0.07 0.07 ASP
ASP with
57 STP Kunihar Arki 07.09.2015 Operational 0.9 0.31
EA
58 Una Zone-D 22.08.2006 Operational 0.65 0.24 ASP
Una
59 Una Zone-B 06.09.2003 Operational 2.53 0.128 ASP
STP for Baddi Town Under
60 Solan 5.5 ASP
at Kenduwal NA Construction NA
Under
61 Mandi STP at Rewalsar 0.35 ASP
15.01.2014 Construction NA
Under
62 Bilaspur STP at Talai 1 ASP
24.08.2016 Construction NA
Under
63 Shimla STP at Sunni 0.65 ASP
22.06.2010 Construction NA
Executive Engineer,
IPH, Div. Dalhousie,
Under
64 Chamba STP at Dalhousie, 2.15 ASP
Construction
District- Chamba
(Dalhousi Town) 03.05.2017 NA
Under
65 STP Gagret 3.14 ASP
11.12.2014 Construction NA
STP at Chintpurni Under
66 0.57 ASP
(Zone-1) 31.03.2017 Construction NA
Una
STP at Chintpurni Under
67 2.01 ASP
(Zone-2) 31.03.2017 Construction NA
STP at Chintpurni Under
68 2.49 ASP
(Zone-3) 31.03.2017 Construction NA
90
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
STP Mehatpur Town Under
69 0.77 ASP
(Zone ABC) 02.06.2012 Construction NA
STP NIT Under
70 Una 0.6 ASP
(Expansion) NA Construction NA
STP at Santoshgarh Under
71 1.65 ASP
(Zone-II) 25.02.2004 Construction NA
* STP Zone-III,
Paonta Sahib
Paonta (Badripur- Under
72 1.72 ASP
Sahib Kishanpura at Construction
Jambu Khala area to
be covered) 08.07.2008 NA
* Upgradation Work
of STP Dhalli (1.75 Under
73 ASP
MLD) awarded on Construction
19.05.2020 NA 1.75 NA
* Upgradation Work
of STP Lalpani (9.35 Under
74 ASP
MLD) awarded on Construction
5.06.2020 NA 9.35 NA
Shimla
* Upgradation
Work of STP
Under
75 Malyana (0.74 MLD) ASP
Construction
awarded on
19.03.2020 NA 0.74 NA
New STP at
Under
76 Panthghati of 02 ASP
Construction
MLD NA 2 NA
STP at Industrial Under
77 Kullu ASP
area Kullu NA Construction 0.06 NA
STP Marhi in Under
78 Kullu ASP
progress. NA Construction NA

91
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational / (In Installed SBR / MBR with Non-comply
Under MLD) Capacity / FAB etc.) quantity / Partially
Construction (In MLD) Comply)
/ Proposed)
STP at Parwanoo,
79 Solan Planning 1 ASP
Sector-5, Parwanoo NA NA
STP at Parwanoo,
80 Solan Village-Tipra, Planning 1 ASP
District- Solan H.P NA NA
STP at sarkaghat
81 Mandi Planning 1.67 ASP
Zone-C NA NA
Executive Engineer,
IPH, Div. Dalhousie,
82 Chamba STP at Dalhousie, Planning 1.01 ASP
District- Chamba
(Chowari Town) NA NA
Paonta STP at Trilokpur,
83 Planning 1 ASP
Sahib Kala Amb NA NA
2.90 MLD
# STP at Solan, (completed) +
84 Solan 3.9 ASP
District- Solan H.P. 01 MLD
NA (Proposed) NA
The Executive
Engineer, I&PH,
85 Kangra Div. Nurpur, Tehsil Planning 3.13 ASP
Nupur, Distt.
Kangra NA NA
Proposed STPs at
86 Mandi Planning ASP
Mandi NA 6.28 NA

92
JAMMU & KASHMIR
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No Commissioning (Operational / Capacity Utilization (UASB / sewage with status
. Non- of STP of ASP /OP / quantity (Comply /
Operational / (In Installed SBR / MBR Non-comply
Under MLD) Capacity / FAB etc.) / Partially
Construction / (In MLD) Comply)
Proposed)

1 Bhagwati Nagar 2017-18 Operational 30 13 MBBR No Comply


Under Testing & Under Testing &
2 Bhagwati Nagar Commissioning Commissioning 27 0 ASP No
Under Under
refurbushment refurbushment
Jammu Testing & Testing &
3 Bhagwati Nagar Commissioning Commissioning 10 0 UASB No
Under Testing & Under Testing &
4 Bhagwati Nagar Commissioning Commissioning 0.164 0 ASP No
Under Under
5 Belicharana Construction Construction 4 0 SBR No
6 Nagrota Jagti 2018-19 Operational 4 2 SBR No Comply

7 Patnatop Patnatop Non Operational 1.2 0 MBBR No


8 Baryal Non Operational 8 0 SBR No
9 Udhampur Omara Non Operational 4 0 SBR No
10 Pittan Non Operational 1.6 32.92315 SBR No
Gardening
11 Reasi Katra Bhawan LoA 09.01.2006 Operational 3.2 2.08 ASP Fire Hydrants Comply
Disposal into
12 Hazratbal 2006 Operational 7.5 7 FAB Dal Lake Comply
Disposal into
13 Habak 2006 Operational 3.2 3 FAB Dal Lake Comply
Disposal into
14 Nishat Laam 2006 Operational 4.5 4.2 FAB Dal Lake Comply
Srinagar Disposal into
Barinambal
15 Barinambal New 2013 Operational 16.1 12 SBR Lagoon Comply
16 Barinambal Old 1993-94 Operational 17.1 ASP River Jhelum Comply
Nallah Amir Disposal into Non -
17 Khan 2013 Operational 5.4 4 SBR Nigeen Lake Comply
93
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No Commissioning (Operational / Capacity Utilization (UASB / sewage with status
. Non- of STP of ASP /OP / quantity (Comply /
Operational / (In Installed SBR / MBR Non-comply
Under MLD) Capacity / FAB etc.) / Partially
Construction / (In MLD) Comply)
Proposed)

18 B.B. Cantt Non Operational 5 0 ASP River Jhelum N.A.


Disposal into
19 Pahalgam 2016 Operational 2 1 SBR Lidder Nallah Comply
Noorbagh Under
20 Palpora Construction 60 0 ASP
21 Gulmarg Proposed 2.5 0 SBR
Srinagar
22 Mehndi Kadal Non Operational 4 0 SBR
23 Uranhal Batingo 2019 Operational 0.062 0 ASP
24 Alochi Bagh 2019 Operational 0.164 0 ASP
Under
25 Achen Construction 0.13 0 ASP
26 Sonamarg Proposed 1 0 MBBR

94
JHARKHAND
Sl. Town Existing Capacity Status (DPR/ Technology Remarks Whether
No. STP Being tendering/ under Complying
Capacity Utilized construction/ ETC etc.) or not
(MLD) (MLD)

phytorid
1 Ranchi 10 10 Operational technology complying
Jumar ( kanke dam to kadal
2 Ranchi (Zone -1) 37 0 Under Construction ) Priority V

Ranchi (Zone Subernarekha ( Hatia dam


3 2,3,4) 269 0 Proposed to Jamshedpur ) Priority IV
4 Sahibganj 12 5 Operational SBR complying
5 Rajmahal 3.5 0 Under Construction
Subernarekha ( Hatia dam
6 Adityapur 36 0 Under Construction to Jamshedpur ) Priority IV
Damodar Phusro road bdg
7 Dhanbad 144 0 Proposed to turio Priority V
Damodar Phusro road bdg
8 Phusro 15 0 Proposed to turio Priority V
Damodar Phusro road bdg
9 Ramgarh 40 0 Proposed to turio Priority V
Subernarekha ( Hatia dam
10 Mango 43 0 Proposed to Jamshedpur ) Priority IV
Subernarekha ( Hatia dam
11 Jamshedpur 20 0 Proposed to Jamshedpur ) Priority IV
Subernarekha ( Hatia dam
12 Jugsalai 9 0 Proposed to Jamshedpur ) Priority IV

95
KARNATAKA
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
Anekal Town Municipal Non
1 Council, Anekal Town, Operational 3.1 SBR
Kasaba Hobli, Anekal Taluk, Non
2 Bangalore Urban District 2018 Operational 3.3 SBR
3 Bangalore Urban, Dasarahalli 06.01.2018 Operating 20 8.218 SBR
4 Bangalore Urban, Dasarahalli 01.06.2019 Operating 20 7.778 EAT
5 Bangalore Urban, Dasarahalli 01.06.2020 Operating 5 3.145 SBR

Open Pond
6 CMC, Doddaballapura Operating 12 5 Oxidation Method
waste stabilization
CMC, Kollegala, pond & extended
7 Charnarajanagara District 2005 Operating 3.34 3.34 aerated lagoons
Factultative aerated
8 CMC, Charnarajanagar 2018 Operating 9 6 Lagoons
TMC, Gundlupet( (2 no) 2.1 waste stabilization
9 MLD & 1.5 MLD) 2019 Operating 3.6 3 pond
MBBR (Moving bed
10 CMC Chikkarnagalur 2019 No 20 0 bio-film reactor)
TMC Birur, Chikkarnagalur Oxidation ponds-3
11 District 2017 Not Operating 2.5 2.5 No's
The Commissioner, City
Municipal Council, Haveri Under
12 District Construction 4.71 FAB
The Commissioner, City
Municipal Council,
13 Ranebeunur, Haveri District Operating 15 4 FAB
The Chief Officer, Town
Municipal Council, Byadgi , Under
14 Haveri District Construction 5 SBR
CMC - Chikkaballapura, (Lagoons)
15 Chikkaballapura (T) &(D) 2009 Operating 10 5 Oxidation pond

96
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
CMC- Chintharnani,
Chintharnani (T), (Lagoons)
16 Chikkaballaoura (D) 2004-05 Operating 2 2 Oxidation pond
CMC - Shidlaghatta,
Shidlaghatta (T), (Lagoons)
17 Chikkaballapura (D) Not Operating 3.1 0 Oxidation pond
18 Chitradurga Mar-19 Operating 20 3 SBR
Eklaspur City Municipal Factultative aerated
19 Council, Raichur District 2019 Operating 20 10 Lagoons
Facultative Aerated
20 Hosur 2019 Operating 8 5 Lagoons Type
Hutti Notified Area, Hutti,
Lingasugur-Tq. Raichur Extended Aeration
21 District. 2x1.25 Operating 2.5 0 Systern
Dharwad (2 STPs 01-40MLD,
22 01-20MLD) Operating 60 60 SBR
Anaerobic logoon +
Sacculaction Pond-
Waste stabilization
23 CMC,GADAG 2016 No 10.8 pond Type
TMC, LAXMESHW ARA, AERATED
24 Gadag District No 5.5 LAGOON TYPE
Anaerobic logoon +
Sacculaction Pond-
TMC, NARAGUND, Gadag Waste stabilization
25 District No 4.18 pond Type
26 CMC Hassan 2011 Operating 10 10 Conventional
27 TMC Belur, Hassan District 2008 & 2013 Operating 2.7 2.7 Conventional
TMC Arsikere, Hassan
28 District 2019 Operating 3.5 3.5 Conventional
TMC Channarayapatna,
29 Hassan District 2007 Operating 4.5 4.5 Conventional

97
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
TMC Holenarasipura, Hassan
30 District 2004 Operating 3 3 Conventional
31 Kalaburagi 2016 Operating 40 30 SBR Technology
32 Kalaburagi 2019 Operating 25 10 SBR Technology
TMC Jewargi, Kalaburagi
33 District 2011 No 3.25 0 MBR
34 CMCKarwar 2011 Operating 1.5 1.5 Aerator Lagoon
35 TMC Bhatkal, Karwar District 2006 Operating 1.5 1.5 ASP
City Municipal Conuncil (CM Under SBR Technolgy
36 C) Koppal Construction 9 proposed
City Municipal Conuocil (C M
C ) Gangavathi, Koppa! Non
37 District 2019 Operational 9 SBR Technology
Convention
CMC Mandya (2 Nos. of STP Treatment
38 of 9.6 MLD & 8.9 MLD) 2007 & 2009 Operating 18.5 11.2 (Oxidation Pond)
Convention
TMC Maddur, Mandya Treatment
39 District 2005 Operating 3.5 2.8 (Oxidation Pond)
Convention
TMC Malavalli, Mandya Treatment
40 District 2016 Operating 5.69 3.6 (Oxidation Pond)
Convention
TMC Srirangapatna, Mandya Treatment
41 District 2014 Operating 3.59 2.69 (Oxidation Pond)
Convention
TMC Nagamangala, Mandya Treatment
42 District 2014 Operating 3 1.6 (Oxidation Pond)
Extended aeration
City CorporationMangalore 1 system followed by
43 STP PANCHADY 2011 Operating 8.75 8.75 taritiary treatment

98
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
Extended aeration
2 STP Surthkal, Dakshina system followed by
44 Kannada (Man galore) 2016 Operating 16.5 16.5 taritiary treatment
3. STP Extended aeration
Jappinamogaru,Dakshina system followed by
45 Kannada (Mangalore) 2015 Operating 20 20 taritiary treatment
4. STP Kavoor, Dakshina
46 Kannada (Man galore) 2008 Operating 43.5 43.5 UASBR & ASP
Town Panchayat(TP)-
Sullia,Dakshina Kannada
47 (Mangalore) 2010 Operating 0.5 400 Wet Well System
Nanjangud, CMC, Mysore
48 District 2017 Operating 7 1.365 Lagoons
Hunsur, CMC, Mysore
49 District 2000 Operating 3.9 3.9 Lagoons
T.Narasipura, TMC, Mysore Sequencing Batch
50 District Operating 5.5 3.8 Reactor
51 Bannur, TMC, Mysore District 2010 Operating 3.31 2.36 Lagoons
52 K.R.Nagar, TMC 1998 Operating 1.45 3.8 Lagoons
Non
53 K.R.Nagar, TMC 2002 Operational 1.45 3.8 Lagoons
Non
54 Kesare, Mysore District 2001 Operational 30 15 SBR
Non
55 Rayankere, Mysore District 2003 Operational 60 39 SBR
Vidyaranyanpuram, Mysore Non
56 District 2001 Operational 67.65 51 SBR
57 CMC-Ramanagara 2004 Operating 7.56 6 Aerated Lagoons
CMC-Kanakapura,
58 Ramanaaar District 2014 Operating 6.29 3.8 Fabultative Lagoons
TMC-Magadi, Ramanaaar
59 District 2014 Operating 3.7 2.9 Lagoons

99
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
City Corporation,Shivamogga
Sy.No.27 Thevarachatnally, Areated Lagoons
60 Shi vamogga Tq & Dist. 2017 Operating 35.58 13 System
City Corporation,Shivarnogga
Gandhi Park,Shivamogga
City,Shivamogga Taluk &
61 Dist. No 0.05 13 SBR
City Corporation,
Shivamogga,
Sy.No.33/PIPurle village,
62 Shivamogga Tq & Dist. No 5.13 13 SBR
Town Municipal
Council,Shikaripura,Sy.No.37,
Ambargoppa Benharak
Grarna,Kuprihalli
63 Gramtana,Shivamogga Dist. 2019 No 5 SBR
City Municipal Council Sagar,
Sy.46,Kasaba Hobli, Shiruvala
Village,SagarTq, Shivamogga
64 District No 9 SBR
City Municipal Council,
Bhadravathi Jatpat
Nagara,Bhadravathi,Shivamo Waste Stabilization
65 gga Dist. 2010 Operating 5.83 3 Pond/Lagoons
City Municipal
Council,Bhadravtahi, Tarikere
Road, Bhadravathi, Waste Stabilization
66 Shivarnogga Dist. Operating 7.2 3 Pond/Lagoons
City Municipal Council,
Bhadravathi, Sy.13, Ward
No.22, Ujjinipura,
67 Bhadravathi, Shivamogga NO 1 3 SBR
68 CMC, Vijayapura 2018-19 Operating 31 21.7 SBR
69 CMC, Yadgir 2018-19 Operating 11

100
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
70 CMC, Shhaapur Operating 9
71 CMC, Shorapur Operating 1.1
72 TMC, Gurumitkal Operating 0.3
Davangere CC, Kundvada
73 village 2015 Operating 14.8 10 WSP
Doddabhudihal Village,
74 Davanagere District 25.02.2015 Operating 20 16 SBR
Doddabhudihal Village,
75 Davanagere District 25.02.2015 Operating 20 16 SBR
Avaragere Village,
76 Davanagere District 25.02.2015 Operating 5 3 SBR
Harihara CMC, Davanagere Under
77 District Construction 18 6.8 FAL
Lined lagoon
system with surface
78 City Corporation Tumkur 2003 Operating 25 20 aerators
City Municipal Council
79 Tiptur, Tumkur District Operating 12 6 SBR
Town Panchayath
80 Turuvekere, Turnkur District 2014 1.97 0 ASB
Waste Stabilization
TMC, Badami, Bagalkot pond followed by
81 District 2013 4.3 0 Soil Bio Technology
CMC, Mudhol, Bagalkot Waste, Stabilization
82 District 2017 9.06 0 Pond
Conventional
83 CMC, Ilkal, Bagalkot District 8 0 treatment
CMC, Jarnakhandi, Bagalkot Facaltative Aerated
84 District 7.6 0 lagoons
CMC, Bagalkot (BTDA), Conventional
85 Bagalkot District 7.5 0 treatment
CMC, Bagalkot, Bagalkot
86 District 8 6 Oxidation ditch
101
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
TMC, Hunagund,Bagalkot Conventional
87 District 2019 3.5 2.8 treatment
Facultative Aerated
88 Ballari 2004 Operating 30 20 Lagoon (FAL)
Facultative Aerated
89 Ballari 2004 Operating 15 7.5 Lagoon (FAL)
Huvinahadagali/Ba!alri Waste Stabilization
90 Ballari District 28.06.2016 Operating 4.27 2.3 Pond (WSP)
91 Bidar Aug-17 No 17.26
92 Humnabad Tq, Bidar District No 6
TMC Chikkodi, Chikkodi
93 District 2018 Operating 5.8 2.1448 Oxidation Pond
TMC Sadalaga, Chikkodi
94 District 2018 Operating 3.72 1.1424 Aerated Lagoon
CMC Gokak, Chikkodi Extended Aeration
95 District Operating 8.7 2.5312 Technology
Roughing Filters-2
Nos., Facultative
Aerated Lagoons-2
96 CMC Udupi 2007 Operating 12 5.5 Nos., Clarifier-1 No.
TMC Kundapura, Uduoi
97 District No 3.1 0
Oxidation Ponds-5
98 TMC Karkala, Udupi District 1993 No 3 0 Nos.
99 TMC Kaup, Uduoi District No 0.3 0
Under
100 City Corporation, Belagavi Construction SBR Technology
Activated Sludge
101 Bangalore urban, Rajacanal 2004 Operating 40 36 Process (ASP) 36 Comply
102 Bangalore urban, Rajacanal 2018 Operating 40 40 Extended Aeration 40 Comply
Moving Bed Biofilm
103 Bangalore Urban, Jakkur 2018 Operating 15 15 Reactor (MBBR) 15 Comply

102
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
Bangalore Urban,K & C Activated Sludge
104 Valley 2005 Operating 218 183 Process (ASP) 183 Comply
Bangalore Urban,K & C
105 Vallev 2005 Operating 30 30 Extended Aeration 30 Comply
Sequencing Batch
106 Bangalore Urben, Horamavu 2018 Operating 20 20 Reactor (SBR) 20 Comply
Sequencing Batch
107 Bangalore Urban, Sarakki 2019 Operating 5 4 Reactor (SBR) 4 Comply
Bangalore Urban, Bellandur Activated Sludge
108 Amanikere 2018 Operating 90 90 Process (ASP) 90 Comply
Activated Sludge
Process and UV
109 Bangalore Urban, Lalbagh 2006 Operating 1.5 method 1.5 Comply
Bangalore Urban, Cubbon Membrane Bio
110 Park 2018 Operating 4 Reactor (MBR) 4 Comply
Activated Sludge
111 Bangalore Urban, Hebbal 1999 Operating 60 35 Process (ASP) 35 Comply
Activated Sludge
112 Bangalore Urban, Yelhanka 2003 Operating 10 8 Process (ASP) 8 Comply
Bangalore Urban, Yelemelle Sequencing Batch
113 chellappa chetty 2018 Operating 15 13 Reactor (SBR) 13 Comply
Bangalore Urban, Sequencing Batch
114 Chikkabanavara 2018 Operating 5 3.5 Reactor (SBR) 3.5 Comply
Activated Sludge
115 Bangalore Urban, Mailsandra 2005 Operating 75 75 Process (ASP) 75 Comply
2 stage trickling
116 Bangalore Urban, V Vallev 2009 Operating 180 70 filter 70 Comply
Bangalore Urban ,VValley High Rate Clarifier
117 (TIP) 2004 Operating 10 10 DENSADEG 10 Comply
Bangalore Urban, Activated Sludge
118 Kemparnbudhi 2002 Operating 1 1 Process (ASP) 1 Comply
Bangalore Urban, Sequencing Batch
119 Mallathahalli 2011 Operating 5 5 Reactor (SBR) 5 Comply
120 Bangalore Urban, Kadugodi 2018 Operating 6 4 Sequencing Batch 4 Comply

103
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
Reactor (SBR)
Sequencing Batch
121 Bangalore Urban, Halasuru 2018 Operating 2 1.8 Reactor (SBR) 1.8 Comply
Sequencing Batch
122 Bangalore Urban, Nagasandra 2018 Operating 20 10.814 Reactor (SBR) 10.814 Comply
123 Bangalore Urban, Nagasandra 2005 Operating 20 8.484 Extended Aeration 8.484 Comply
Upflow Anaerobic
Sludge Blanket
124 Bangalore Urban, K R Purarn 2005 Operating 20 20 Reactor (UASB) 20 Comply
Sequencing Batch
125 Bangalore Urban, Doddabele 2019 Operating 40 30 Reactor (SBR) 30 Comply
Bangalore Urban, Activated Sludge
126 Kadabeesanahalli 2005 Operating 50 42 Process (ASP) 42 Comply
Bangalore Urban, K & C Activated Sludge
127 Valley 2018 Operating 60 60 Process (ASP) 50 Comply
Activated Sludge
128 Bangalore Urban, Kengeri 2018 Operating 60 40 Process (ASP) 40 Comply
Sequencing Batch
129 Bangalore Urban, Doddabele 2018 Operating 20 20 Reactor (SBR) 20 Comply
Sequencing Batch
130 Bangalore Urban, Hulimavu 2020 Operating 10 4.5 Reactor (SBR) 4.5 Comply
Sequencing Batch
131 Bangalore Urban, Agaram 2020 Operating 35 15 Reactor (SBR) 15 Comply
Under Sequencing Batch
132 Bangalore Urban, K&C Valley Construction 150 Reactor (SBR)
Bangalore Urban, Under Sequencing Batch
133 Chikkabegur Construction 5 Reactor (SBR)
Under Sequencing Batch
134 Bangalore Urban, K.R. Puram Construction 20 Reactor (SBR)
Under Sequencing Batch
135 Bangalore Urban, Hebbal Construction 100 Reactor (SBR)
Under Sequencing Batch
136 Bangalore Urban, V. Valley Construction 150 Reactor (SBR)

104
Sl. STP_Name Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization adapted Treated Status
/Non of STPs of installed (UASB/ASP/OP/SB sewage
Operational / (in MLD) Capacity ( R/ MBR/FAB etc) with
Under In MLD) quantity
Construction /
Proposed)
Town Municipal Council, Waste Stabilization
Basavana Bagewadi Bagewadi pond On-land for Partialy
137 Taluk, Vijayapura District. 2014-15 Operating 4.02 2.4 system irrigation Comply
Town Municipal Council,
Muddebihal Town, Mudnal Under
138 Tank, Muddebihal Taluk, Construction 5.24
Town Municipa] Council,
Tlikote Town, Muddebihal On-land for Partialy
139 Taluk, 2015-16 Operating 4.24 2.5 WSB irrigation Comply
Town Municipal Council, Indi On-land for Partialy
140 Town, Indi Taluk, Vijayapura 2016-17 Operating 4.24 2.5 OP irrigation Comply

105
KERALA

Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / ASP treated status
Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-comply /
Under MLD) etc.) quantity Partially
Construction / Comply)
Proposed)

1 Thiruvananthapuram Thiruvananthapuram Operational 107 44 ASP


Coagulation
5 3.5
2 Pathanamth Pathanamth & setting

Electrolytic
0.18 0.18
3 Alappuzha Alappuzha Oxidation

4 Kottayam Kottayam 0.09 0.09 ASP


5 Ernakulam Ernakulam Operational 4.5 3.5 ASP

Aerobic
3 3 Niological
Process
6 Thrissur Thrissur Operational
7 Kannur Kannur 0.5 0.5 ASP + MBBR

106
MADHYA PRADESH
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
1 Bhopal (M Corp.) Operational 35 30.43 5.89
2 Bhopal (M Corp.) Operational 10 8.69 1.68
3 Bhopal (M Corp.) Operational 16.7 14.52 2.81
4 Bhopal (M Corp.) Operational 2.59 2.25 0.44
5 Bhopal Bhopal (M Corp.) Operational 4.5 3.91 0.76
6 Bhopal (M Corp.) Operational 13 11.30 2.19
7 Bhopal (M Corp.) Operational 4 3.48 0.67
8 Bhopal (M Corp.) Operational 2 1.74 0.34
9 Bhopal (M Corp.) Operational(BHEL) 2.5 2.17 0.42
10 Dewas Dewas (M Corp.) Operational 12 2.6 2.6
11 Gwalior Gwalior (M Corp.) Operational 50 50 5
12 Indore (M Corp.) Operational 245 220.87 22.07
13 Indore Indore (M Corp.) Operational 78 70.32 7.03
14 Indore (M Corp.) Operational 12 10.82 1.08
15 Jabalpur Jabalpur (M Corp.) Operational 50.55 7.00 3.00
Singrauli Singrauli (M Corp.) Operational 28.22 7.94
7.94
16 (NTPC)
17 Ujjain Ujjain (M Corp.) Operational 83 64 21
18 Sehore Sehore (M) Operational 12 5 0
19 Vidisha Vidisha (M) Operational 7.2 7.2 0
20 Burhanpur (M Corp.) Non-Operational 4.5 0
Burhanpur
21 Burhanpur (M Corp.) Non-Operational 6 0
22 Rewa Rewa (M Corp.) Non-Operational 12 0
23 Bhind (M) Bhind (M) Work in progress 12 0
24 Bhopal (M Corp.) Bhopal (M Corp.) Work in progress 3.5 0

107
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
25 Bhopal (M Corp.) Work in progress 3.5 0
26 Bhopal (M Corp.) Work in progress 9.5 0
27 Bhopal (M Corp.) Work in progress 4.5 0
28 Bhopal (M Corp.) Work in progress 2 0
29 Bhopal (M Corp.) Work in progress 6 0
30 Bhopal (M Corp.) Work in progress 32 0
31 Bhopal (M Corp.) Work in progress 20.5 0
32 Bhopal (M Corp.) Work in progress 5 0
Bhopal (M Corp.) Under Testing & 35
33 Commissioning 0
34 Bhopal (M Corp.) Work in progress 2 0
35 Burhanpur (M Corp.) Burhanpur (M Corp.) Work in progress 21 0
36 Datia (M) Datia (M) Work in progress 12 0
37 Guna (M) Guna (M) Work in progress 7.6 0
38 Guna (M) Guna (M) Work in progress 14.65 0
39 Gwalior (M Corp.) Under Trial-run 145 0
40 Gwalior (M Corp.) Work in progress 4 0
Gwalior (M Corp.)
41 Gwalior (M Corp.) Work in progress 65 0
42 Gwalior (M Corp.) Work in progress 8 0
43 Indore (M Corp.) Work in progress 6 0
Indore (M Corp.) Under Testing & 8
44 Commissioning 0
Indore (M Corp.) Indore (M Corp.) Work in progress 7
45 0
46 Indore (M Corp.) Work in progress 35 0
47 Indore (M Corp.) Work in progress 11 0
48 Jabalpur (M Corp.) Work in progress 1 0
Jabalpur (M Corp.)
49 Jabalpur (M Corp.) Work in progress 5 0
108
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
50 Jabalpur (M Corp.) Work in progress 29 0
51 Jabalpur (M Corp.) Work in progress 32 0
52 Jabalpur (M Corp.) Work in progress 34 0
Khargone (M) Khargone (M) Under Testing & 17.6
53 Commissioning 0
54 Morena (M) Morena (M) Work in progress 25 0
Murwara (Katni) (M 7.5
Work in progress
55 Corp.) 0
Murwara (Katni) (M Murwara (Katni) (M 6
Work in progress
56 Corp.) Corp.) 0
Murwara (Katni) (M 11
Work in progress
57 Corp.) 0
Neemuch (M) 7
Work in progress
58 Neemuch (M) 0
59 Neemuch (M) Work in progress 9.5 0
60 Ratlam (M Corp.) Work in progress 16 0
Ratlam (M Corp.)
61 Ratlam (M Corp.) Work in progress 21.5 0
62 Rewa (M Corp.) Work in progress 1 0
63 Rewa (M Corp.) Work in progress 1 0
64 Rewa (M Corp.) Work in progress 1 0
65 Rewa (M Corp.) Rewa (M Corp.) Work in progress 6.5 0
66 Rewa (M Corp.) Work in progress 6.5 0
67 Rewa (M Corp.) Work in progress 3 0
68 Rewa (M Corp.) Work in progress 6 0
69 Sagar (M Corp.) Sagar (M Corp.) Work in progress 43 0
70 Satna (M Corp.) Satna (M Corp.) Work in progress 15 0
71 Satna (M Corp.) Satna (M Corp.) Work in progress 16 0
72 Satna (M Corp.) Satna (M Corp.) Work in progress 11 0

109
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
73 Singrauli (M Corp.) Singrauli (M Corp.) Work in progress 11 0
74 Singrauli (M Corp.) Singrauli (M Corp.) Work in progress 10 0
75 Singrauli (M Corp.) Singrauli (M Corp.) Work in progress 10 0
76 Ujjain (M Corp.) Ujjain (M Corp.) Work in progress 92.5 0
77 Vidisha (M) Vidisha (M) Work in progress 22.25 0
78 Maheshwar Maheshwar Work in progress 4.91 0
79 Shajapur Shajapur Work in progress 11.1 0
80 Chhindwara Chhindwara Work in progress 28 0
81 Nasrullaganj Nasrullaganj Work in progress 4.2 0
82 Amarkantak Amarkantak Work in progress 1.2 0
83 Dindori Dindori Work in progress 3.85 0
84 Budhni Budhni Work in progress 2.8 0
85 Budhni Budhni Work in progress 1.08 0
Shahganj Shahganj The ULB has 2
resolved "not to
execute" the
sewerage scheme
and hence, the
work is stopped till
86 final decision. 0
87 Mandleshwar Mandleshwar Work in progress 3 0
88 Omkareshwar Omkareshwar Work in progress 0.55 0
89 Dharampuri Dharampuri Work in progress 2.5 0
90 Nemawar Nemawar Work in progress 1 0
91 Hoshgabad Hoshgabad Work in progress 21 0
92 Badwani Badwani Work in progress 9 0
93 Sendhwa Sendhwa Work in progress 8.5 0
94 Barwaha Barwaha Work in progress 3.74 0
110
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
95 Anjad Anjad Work in progress 3.66 0
96 Saikhda Saikhda Work in progress 2.6 0
97 Chitrakoot Chitrakoot Work in progress 4.7 0
Dewas Dewas Under 14
98 Construction 0
Dewas Dewas Under 22
99 Construction 0
Shivpuri Shivpuri Under 20
100 Construction 0
101 Bhedaghat Bhedaghat Proposed 0.43 0
102 Bhedaghat Bhedaghat Proposed 0.22 0
103 Bhedaghat Bhedaghat Proposed 0.06 0
104 Bhedaghat Bhedaghat Proposed 0.06 0
105 Shahdol Shahdol Proposed 17 0
106 Nagda(Scheme II) Nagda(Scheme II) Proposed 12.62 0
107 Mandla Mandla Proposed 7.75 0
108 Mandla Mandla Proposed 1.75 0
109 Narsingpur Narsingpur Proposed 7.75 0
110 Narsingpur Narsingpur Proposed 1.25 0
111 Khajuraho Khajuraho Proposed 4.45 0
112 Rajnagar Rajnagar Proposed 2.82 0
113 Maihar Maihar Proposed 14.45 0
114 Sanchi Sanchi Proposed 1.9 0
115 Sanawad Sanawad Proposed 5.58 0
116 Dhamnod Dhamnod Proposed 6.8 0
117 Khandwa (M Corp.) Khandwa (M Corp.) Operational 0.0018 0
118 Morena (M Corp.) Morena (M Corp.) operational 0.0012 0.0012

111
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of Installed ASP /OP / sewage (Comply /
Under (In Capacity SBR / MBR / with Non-comply
Construction / MLD) (In MLD) FAB etc.) quantity / Partially
Proposed) Comply)
119 Sagar (M Corp.) Sagar (M Corp.) operational 0.02 0.02
120 Betul Betul operational 0.001 0.001
121 Sarni Sarni operational 2.655 1.65
122 Raisen Raisen operational 1 1
123 Shahganj Shahganj operational 1 0.179
124 Pithampur Pithampur operational 0.02 0.02
125 Sanavad Sanavad operational 1 0.001
126 Maheshwar Maheshwar operational 0.001 0.001
127 Khargone Khargone operational 0.5 0.4
128 Malajkhand Malajkhand operational 0.031 0.015
129 Bamhani Bamhani operational 1 1
130 Kymore Kymore operational 0.8 0.4
131 Gotegaon Gotegaon operational 1 1
132 Chakghat Chakghat operational 1 1
133 Hatta Hatta operational 0.002 0.002
134 Damoh Damoh operational 0.09 0.09
135 Tendukheda Tendukheda operational 0.5 0.1
136 Patera Patera operational 0.5 0.1
137 Banda Banda operational 1.98 1.98
138 Makroniya Makroniya operational 1.35 1.35
139 Bhaurasa Bhaurasa operational 1.5 1.5
140 Ratangarh Ratangarh operational 0.1 0.1
141 Unhel Unhel operational 0.01 0.01
142 Badnagar Badnagar operational 0.001 0.001

112
MAHARASHTRA
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Colaba WWTF Nr Afgan


Church Colaba Mumbai -
1 05 2020 Operational 37 22.51 SBR NIL Comply
Preliminary treatment by
screening & diffused
LGP WWTF-IPS aerated grit chambers.
89,Dr.A.B. Road Worli Dilution & dispersion Non-
2 Mumbai 18. 1991 Operational 757 374.78 through marine outfall. 0.8 Comply
Treated
Preliminary treatment by sewage used
screening & diffused for gardening
Malad STP Marve Road, aerated grit chambers. on Gorai
MithChawky, Malad Dilution & dispersion dumping Non-
3 Municipal (W), Mumbai-95 Apr-98 Operational 240 216.06 through marine outfall. ground Comply
Corporation of Charkop STP MHADA,
Greater Mumbai Sector 8 & 9, Partially
4 Kandivali(W), 2007 Operational 6 4.28 RMBR 0 Comply
Preliminary treatment by
Bhandup WWTF Off screening & diffused
eastern Express Highway aerated grit chambers.
Near Airoli Bridge Traffic Dilution & dispersion
5 Signal Bhandup East 2003 Operational 280 141.48 through marine outfall. 0 Comply
Preliminary treatment by
Ghatkopar WWTF Off screening & diffused
eastern Express Highway aerated grit chambers.
Near Pant Nagar Traffic Dilution & dispersion Non-
6 Signal Ghatkopar East 2003 Operational 386 151.7 through marine outfall. 0 Comply
Worli STP, MCGm,
7 Mumbai Proposed 500 NA

113
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Bandra STP, MCGM,


8 Mumbai NA Proposed 360 NA NA NA NA
Dharavi STP, MCGM,
9 Mumbai Proposed 250 NA NA NA NA
Versova STP J.P. Road
Jn.,Link Road, Near
Apnana Bazar, Andheri Aerobic & Facultative
10 (W), Mumbai-53 1998 Operational 180 108 Lagoon 0 Comply
Preliminary treatment by
Influent Pumping Station screening & diffused
Bandra, Opp Swami aerated grit chambers.
Vivekanand Garden, Dilution & dispersion
Mahim Causway, Mahim through marine outfall at
11 (West), Mumbai 2003 Operational 797 531 3.7 Km into Sea 0 Comply
Ghatkopar STP, MCGM,
12 Mumbai NA Proposed 337 NA NA NA NA
Malad STP, MCGM,
13 Mumbai Proposed Proposed 605 NA NA NA NA
14 TMC STP Kopri, Thane 2012 Operational 120 70 SBR Technology 0 Comply
TMC STP Mumbra, Non-
15 Thane 2015 Operational 32 12 SBR Technology NIL Comply
Inlet Chamber,
Equalization Tank,
Aeration Tank, Settling
Thane Municipal Tank, Filter Tank, Sand
Corporation Filter, Carbon Filter, UV
16 TMC STP Vartak Nagar 2017 Operational 0.9 0.25 and Final Tank 0.25 Comply
17 Vitava 2019 Operational 8.4 1 MBBR Technology 0 NA
Non-
18 Kharegoan 2019 Operational 46.76 NA MBBR Technology NA NA
19 Everest World, Kolshet 2019 Operational 23.06 5 MBBR Technology 0 NA

114
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Non -
20 Lodha 2019 Operational 22.02 NA MBBR Technology NA NA
Under
21 Nagla Bunder NA Construction 7 NA SBR Technology NA NA
Pumping Station, Inlet,
Screen Channels, Grid
Chamber, C-Tech basin,
Sludge sump, Sludge
Non - compactors and UV
22 Hiranandani 2021 Operational 59 NA channels, Outlet. NA NA
Bhayander (W) near
23 Garden Court Tower 17-Jun Operational 8 8 MBBR No Use-0 Comply
Golden Nest Road,
24 Bhayander (E) Goddev 17-Jan Operational 12 12 MBBR Gardening-0.5 Comply
25 Kanakia, Mira Road (E) 14-Mar Operational 17 17 MBBR Gardening-0.5 Comply
Shanti Park - Mira road -
26 Sanghavinagar 14-Mar Operational 13 13 MBBR Gardening-0.3 Comply
Mhada- shanti garden-
Mira Penkarpadagavthan
27 (Mhada Colony) 18-Jan Operational 7 7 MBBR Gardening-0.1 Comply
Mira- Bhaindar
Shanti nagar Mira road
Municipal
station, Near
Corporation
28 ayappamandir, 14-Mar Operational 11 11 MBBR Gardening-0.7 Comply
Near Corporation
garden, Kashimira road, Under
29 Reservation No 170 NA Construction 12 NA NA NA NA
Ghodbunder- Kashigaon,
MashachhapadaBhayand
30 er, Survey No. 233 17-Aug Operational 14 14 MBBR Gardening-0.2 Comply
31 Jesal park 1990 Operational 2 2 Conventional Gardening-0.1 Comply
Shrushti complex, Mira
32 Road 2000 Operational 1.5 1.5 Conventional Gardening-0.1 Comply

115
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

33 Bhayander West NA Proposed 8 NA NA NA NA


34 Kharigaon NA Proposed 13 NA NA NA NA
Partially
35 Bolinge Village STP - 2, 08-01-2017 Operational 30 19 MBBR 0 Comply
36 Chikhaldongri NA Proposed 13 NA MBBR NA NA
Vasai-Virar
37 Nallasopara (East) NA Proposed 30.5 NA MBBR NA NA
Municipal
38 Corporation Nallasopara (West) NA Proposed 49 NA MBBR NA NA
39 Navghar Manikpur NA Proposed 7.1 NA MBBR NA NA
40 Navghar Manikpur NA Proposed 33.85 NA MBBR NA NA
41 Vasai NA Proposed 11.57 NA MBBR NA NA
42 Adharwadi 2013 Operational 25 21 SBR NA Comply
43 Barave 2013 Operational 15 11 SBR NA Comply
44 Kalyan Dombivali Motagaon Old STP Operational 40 0 SBR NA --
45 Municipal Chinchpada 2016 Operational 40 15 SBR NA Comply
Corporation Manda Titwala 2.0
46 MLD.(E) 2014 Operational 2 1 Root Zone NA Comply
Manda Titwala 1.0 MLD
47 (W) 2014 Operational 1 0.5 Root Zone NA Comply
48 Katai-1 2015 Operational 13 13 ASP Comply
Non-
49 Katai-2 1978 Operational 17 0 ASP NA
Bhiwandi
Under
Nizampur
50 Bakra Bazar- Bhiwandi NA Construction 29 NA SBR NA
Municipal
Corporation Under
51 Slaughter House- Idgah NA Construction 30 NA SBR NA
52 Bhadwad NA Proposed 9 NA SBR NA
53 Stepping Garden NA Proposed 31 NA SBR 0 NA

116
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

54 Ambernath Vadalgaon 2016 Operational 45 22 SBR 0 Comply


Municipal Council
55 Chikloli 2016 Operational 9 6 SBR 0 Comply
KulgaonBadalapu
r Municipal
56 Council Badlapur 2016 Operational 22 20 SBR 0 Comply
Under
57 Ulhasnagar Shanti Nagar-1 NA Construction 15 NA SBR NA NA
Municipal Under
58 Corporation Shanti Nagar-2 NA Construction 31.26 NA SBR NA NA
59 Vadholgaon Mar-20 Operational 20.7 NA SBR 0 Comply
60 Sec-12 C.B.D. 10-07-2011 Operational 19 12 SBR 0 Comply
61 Sec-50, Nerul 15/04/2008 Operational 100 40 SBR 0.1 Comply
62 Sec-18, Vashi 30/09/2008 Operational 100 40 SBR 0.1 Comply
63 Navi Mumbai Sec-20, Sanpada 15/04/2012 Operational 37.5 18 SBR 0 Comply
Municipal
Corporation Dec-2016
transferred from
64 Sec-15, Ghansoli CIDCO Operational 30 10 SBR 0 Comply
65 Sec-14, Koparkhairane 27/01/2012 Operational 87.5 45 SBR 0 Comply
66 Sec-18, Airoli 30/04/2008 Operational 80 35 SBR 0 Comply

Bandar Road, Panvel,


67 Dist. Raigad. 2009 Operational 14 12 MBBR 0 Comply
Sector-16, Kharghar, Tal.
Panvel Municipal
68 Panvel, Dist. Raigad. 2008 Operational 25 23 MBBR 0 Comply
Corporation
Sector-16, Kharghar, Tal.
69 Panvel, Dist. Raigad. 2012 Operational 70 63 MBBR 0 Comply
Sector-32, ,Kamothe, Tal. Non-
70 Panvel, Dist. Raigad. 2012 Operational 85 79 MBBR 0 Comply

117
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Sector-12,Kalamboli, Tal.
71 Panvel, Dist. Raigad. 2011 Operational 50 47 MBBR 0 Comply
Sector-06, Ulwe, Tal.
72 Panvel, Dist. Raigad. 2018 Operational 32 26 MBBR 0 Comply
Kalundre, Kalundre
Gaon, Panvel, Navi
73 Mumbai 2019 Operational 2 1.7 MBBR 0 Comply
74 CIDCO Karanjade NA Proposed 28 NA MBBR NA NA
75 CIDCO Taloja Phase-I NA Proposed 32 NA MBBR NA NA
76 CIDCO Pushpak Nagar NA Proposed 45 NA MBBR NA NA
Kundalika River Right
Bank at Survy No.
128/3A at Vill. Ashtami,
about 120 mtrs. away Under MMBR, Multi Media Bio
Roha Municipal
77 from Kundalika River NA Construction 1 NA Reactor NA NA
Council
Kundalika River Left
Bank, at Survy No.
211/1/2/3/4/8/9/10/11
78 (0.43A) at Roha. NA Proposed 4 NA -- NA NA
Partially
79 Chehedi STP 2006 Operational 22 22 UASB 0 Comply
Partially
80 Chehedi STP 2012 Operational 21 21 ASP 0 Comply
Partially
81 Panchak 2004 Operational 7.5 7.5 ASP 0 Comply
Nashik Municipal Partially
82 Corporation Panchak 2012 Operational 21 21 ASP 0 Comply
Partially
83 Panchak 2016 Operational 32 32 UASB+MBBR 0 Comply
UASB +Extended Partially
84 Tapvan 2003 Operational 78 78 Aeration 0 Comply
UASB +Extended Partially
85 Tapvan 2010 Operational 52 52 Aeration 0 Comply
118
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Non-
86 Agar Takali 2015 Operational 70 70 ASP 0 Comply
Partially
87 Agar Takali 2016 Operational 40 40 UASB+MBBR 0 Comply
Partially
88 Municipal STP Gangapur 2020 Operational 18 NA SBR 0 Comply
Municipal STP
89 Pimpalgaon, Baswant NA Proposed 32 NA SBR NA NA

Tryambakeshwar Municipal Council Non-


90 Municipal Council Tryambak 2000 Operational 1 1 FAB 0 Comply
Municipal Council -
Shirpur Municipal Shirpur, TqShirpurDist
91 Council Dhule 2017 Operational 12.5 8.64 SBR 8.64 Comply
Municipal Council -
Nandurbar Nandurbar, Tq and Dist
92 Municipal Council Nandurbar Nov-2018 Operational 17.5 9.3 SBR 9.3 Comply
Shirdi Shirdi, Tal-- Rahata, Dist-
93 Nagarpanchyat Ahmednagar 2015 Operational 16 9 UASB 9 Comply
Ahmednagar
Muncipal Ahmednagar, Tal &Dist-
94 Corporation Ahmednagar NA Proposed 57 NA Proposed NA NA
Erandwane STP
95 S.No.3&4 Erandwane 2004 Operational 50 50 Activated Sludge Process Comply
300-500 MLD
Bopodi STP, S.No.2A, 2B, Extended Ariation as per Partially
requirement to
96 Pune Municipal 2C, 2D &6 (P) Bopodi 03-Jun Operational 18 15 Process Comply
Irrigation
corporation Tanajiwadi S.No.24, Biotower and department Partially
97 Shivajinagar 14-Apr Operational 17 13 extededariation process from Comply
Bhairoba STP, Final plot MundhawaJac
No.330 S.No.33A, 33B kwell
98 Koregaon Park 03-Jul Operational 130 80 Activated Sludge Process pumping Comply

119
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Mundhawa STP,
99 S.No.2,3A,4 Mundhawa 09-Feb Operational 45 42 Sequential Batch Process Comply
Vithalwadi STP, Modified Activated
100 S.No.20(P) Hingane 09-Mar Operational 32 25 Sludge Process Comply
Old Naidu STP, S.No.439
To 444 Pune final Plot Non- Non-
101 No. 98 Knndy Road Nov-88 Operational 90 NA Activated Sludge Process Comply
Baner STP, S.No.221 To
102 227 Baner 11-Jan Operational 30 30 Sequential Batch Process Comply
Kharadi STP, S.No.74, 75
103 Kharadi 12-Feb Operational 40 40 Sequential Batch Process Comply
New Naidu STP,
S.No.439 To 444 Pune
final Plot No. 98 Knndy Partially
104 Road 2010 Operational 115 115 Activated Sludge Process Comply
Pune Municipal
Corporation, Botanical Extended Aeration
105 Garden, Pune NA Proposed 10 NA Process NA
Pune Municipal
106 Corporation, Baner, NA Proposed 25 NA SBR NA
Pune Municipal Extended Aeration
107 Corporation, Warje, Pune NA Proposed 28 NA Process NA
Pune Municipal
Corporation, Vadgaon, Extended Aeration
108 Pune NA Proposed 26 NA Process NA
Pune Municipal Extended Aeration
109 Corporation, TanajiWadi NA Proposed 15 NA Process NA
Pune Municipal Anoxic-Oxic Process
110 Corporation,Naidu NA Proposed 127 NA (A2O)+Power NA
Pune Municipal
Corporation, Dhanori, Extended Aeration
111 Pune NA Proposed 33 NA Process NA NA
120
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Pune Municipal
Corporation, Bhairoba, Anoxic-Oxic Process
112 Pune NA Proposed 75 NA (A2O)+Power NA
Pune Municipal
Corporation, Mundhva,
113 Pune NA Proposed 20 NA SBR NA
Pune Municipal
Corporation, Kharadi,
114 Pune NA Proposed 30 NA SBR NA
Pune Municipal
Corporation, Matsyabij
115 Kendra, Pune NA Proposed 7 NA SBR NA
Baramati Gunawadi Road,
116 Munucipal council Baramati 2019 Operational 11.5 11.5 SBR 11.5 Comply

Daund Municipal Daund Municipal Non-


117 Council Council STP 2016 Operational 4.2 4.2 SBR 0 NA

Saswad Municipal Saswad Municipal Non-


118 Council council STP 2015 Operational 2 2 MBBR 1 Comply
Only civil structure is at
Lonavala Non- site,STP capacity is in
119 Municipal Council Dongar Gaon, Lonavala 1998 Operational 3.6 NA inhancement NA NA
Shirur Municipal Sr. No. 269, Sonar Ali,
120 Council Shirur 2013 Operational 6 2.5 SBR technology 5 Comply
Pune Cantonment Gardening - 5
121 Board 900 Boottee Street, Pune 2018 Operational 20 9 SBR acers Comply
Khadaki Gaddi Adda, Ward No. Conventional type Non-
122 Cantonment Tamela Chawl, Khadaki. 1991 Operational 8 6 treatment Gardening Comply

121
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Board East Khadali, Near


Lokmanya Tilak Conventional type
123 Highschool 2003 Operational 1.2 1.2 treatment Gardening --
124 Chikhali Phase I 1987 Operational 16 Extended Aeration Comply
125 Chikhali Phase II 2000 Operational 16 26.33 ASP 3 Comply
Chinchwad Phase I
126 (Bhatnagar) 2000 Operational 30 28.9 ASP 0 Comply
127 Chinchwad Phase II 2008 Operational 30 28.08 SBR 0 Comply
128 Sangvi Phase I 2011 Operational 10 6.031 ISBR 0 Comply
129 Pimpri Kasarwadi I 1999 Operational 40 ASP Comply
130 Chinchwad Kasarwadi II 2003 Operational 40 ASP Comply
Municipal
131 Corporation Kasarwadi III July.2010 Operational 40 85.312 SBR 15 Comply
132 Pimple Nilekh 2007 Operational 20 18.741 Biotower 0 Comply
133 Ravet 2009 Operational 20 12.547 SBR 0 Comply
134 Akurdi Jan. 2011 Operational 30 26.514 ISBR 0 Comply
135 Sangvi Phase II (Dapodi) 2012 Operational 20 13.774 SBR 0.65 Comply
136 Chahroli Phase I 2013 Operational 21 20.362 SBR 0 Comply
137 Chahroli Phase II 2019 Operational 20 14.3 SBR 0 Comply
138 Degaon STP 24-08-2017 Operational 75 52.12 SBR 2.6 Comply
Solapur Municipal
139 Corporation Kumathe STP 29-03-2018 Operational 12.5 5.39 SBR 0.5 Comply
140 Pratap Nagar STP 26-03-2018 Operational 15 5.22 SBR 0.5 Comply
compartment no. 79(City
Survey no.257/1) behind
Mahabaleshwar KarmachariVasahat, At-
Municipal Council Mahabaleshwar, Tal-
Mahabaleshwar, Dist-
141 Satara 2011 Operational 4 2 MMBR 2 Comply

122
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

at Survey No.626, near


Dhobi Ghat,At-
Mahabaleshwar, Tal-
Mahabaleshwar, Dist-
142 Satara 2013 Operational 1 0.5 SBR 0.5 Comply
Survey No. 83/2 near
Siddharthnagar,At-
Panchgani, Tal-
Mahabaleshwar, Dist-
143 Satara 2011 Operational 0.65 0.65 MBR 0.65 Comply
Plot no. 497/4 & 5 near
Panchagani Shivajinagar,At-
Municipal Council Panchgani, Tal-
Mahabaleshwar, Dist-
144 Satara 2011 Operational 0.35 0.35 MBR 0.35 Comply
Hindu Crematorium,At-
Panchgani, Tal-
Mahabaleshwar, Dist-
145 Satara 2015 Operational 1.5 1.5 MBR 1.5 Comply
Karad Municipal Bara Dabari, Karad, Tal- For Irrigation
146 Council Karad, Dist-Satara 2017 Operational 12.5 9.5 MMBR Technology Perpose 12.5 Comply
A/p-Malkapur Tal
147 Malkapur KaradDist-Satara 2017 Operational 5 5 MBR 0 Comply
Municipal Council A/p-Malkapur Tal
148 KaradDist-Satara 2018 Operational 3 3 MBR 0 Comply
STP
149 Pandharpur Gopalpur,Pandharpur 2013 Operational 15.5 12 SBR 2.9 Comply
Municipal Council
150 STP, 65 Acre,Pandharpur 2019 Operational 2.5 0.5 SBT 0.2 Comply
Kolhapur Kolhapur Municipal
Municipal Corporation STP,
151 Corporation, Kolhapur 2014 Operational 76 55 SBR 0 Comply

123
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Kolhapur Kolhapur Municipal


Corporation STP
152 Dudhali, Kolhapur 2018 Operational 17 17 SBR 0 Comply
Kolhapur Municipal
Corporation STP Bawda,
153 Kolhapur NA Proposed 6 NA SBR NA NA
Kolhapur Municipal
Corporation STP
154 Dudhali, Kolhapur NA Proposed 4 NA SBR NA NA
Non-
155 Dhulgaon STP 2015 Operational 27 27 Oxidation Pond NA Comply
Non-
156 Sangli Municipal STP at Miraj 1970 Operational 9.2 9.2 Oxidation Pond NA Comply
Corporation Hamumannagar STP 100 Partially
157 Footy road 2018 Operational 23.5 13 SBR 0 Comply
Partially
158 SMKC Bedag road Miraj NA Proposed 22.5 NA SBR NA Comply
Ichalkaranji Municipal
Council Old Sangli Naka,
159 Ichalkaranji Ichalkaranji 1995 Operational 20 14 SBR 0 Comply
Municipal Council Ichalkaranji Municipal
Council Ichalkaranji STP Under
160 Takawade NA Construction 18 NA SBR 0 NA
Malvan Municipal
161 Council Malvan Council Proposed 4 NA NA NA NA
Kanchanwadi, Non-
162 Aurangabad 23.12.2017 Operational 161 60 SBR 70 Comply
Aurangabad Non-
163 Municipal Padegaon 24.04.2018 Operational 10 5 SBR 2.5 Comply
Corporation Non-
164 Salim Ali Lake 28.02.2013 Operational 5 4 SBR 2 Comply
Non-
165 At Zalta 16.05.2018 Operational 35 15 SBR 7 Comply

124
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

166 Banewadi Proposed 10 NA NA NA NA


Beed Municipal Under
167 Council Beed NA Construction 35 NA SBR NA NA
Non-
168 Elichpur Nov. 2014 Operational 30 12 ASP 7 Comply
Nanded Waghala
Non-
Municipal
169 Bondar Nov. 2014 Operational 87 35 ASP 0 Comply
Corporation
Non-
170 Sangvi Dec. 2018 Operational 15 10 ASP 0 Comply
171 Bhandewadi 2018 Operational 200 200 SBR 0 Comply
172 Bhandewadi 2016 Operational 130 130 SBR 130 Comply
173 Mankapur 2017 Operational 5 5 MBBR 0 Comply
174 Mokshadham 2017 Operational 5 5 MBBR 0 Comply
175 Kachimet (NIT) 2018 Operational 1 1 SBT ( Soil Bio Tech) 1 Comply
Phytorid bed Trickling
176 Sonegaon (NIT) Sept. 2019 Operational 0.3 0.3 Filter 0 Comply

177 Nagpur Municipal HazariPahad (NIT) Oct. 2019 Operational 4 4 SBR 0 NA


corporation
Somalwada-1(Ongoing Under
178 work by NIT) NA Construction 20 NA -- 0 NA
Somalwada-2 (Ongoing Under
179 work by NIT) NA Construction 20 NA SBR 0 NA
Under Phytorid bed Trickling
180 Ambazari (NIT) NA Construction 3.2 NA Filter 0 NA
Under
181 Dabha(NIT) NA Construction 5 NA SBR 0 NA
Under
182 Ittabhatti(NIT) NA Construction 10 NA SBR 0 NA

125
Sl. City / Town Location of STP Date of Status Installed Actual Technology (UASB / ASP Use of treated Compliance
No. Commissioning (Operational Capacity Utilization /OP / SBR / MBR / FAB sewage with status
/ Non- of STP of etc.) quantity (Comply /
Operational / (In Installed Non-
Under MLD) Capacity comply /
Construction (In MLD) Partially
/ Proposed) Comply)

Hinganghat Pili MazidBhimnagar


183 Municipal Council Ward, Hinganghat. NA Proposed 10 NA ASP NA NA
Horticulture
Mouda Nagar and Road
184 Panchayat Nagpur road NA Proposed 1 NA ASP cleaning NA
Bhandara
185 Municipal Council Tumsar Road, Bhandara NA Proposed 15 NA ASP nil NA
Pauni Municipal
186 Council Near Mandir, Pauni NA Proposed 5 NA ASP NA NA
Amravati
187 Municipal STP-1 –Lalkhadi 2017 Operational 44 44 ASP 0 Comply
188 Corporation STP-2-Lalkhadi 2013 Operational 30.5 30.5 ASP 0 Comply
Under
189 Akola Municipal Shiloda NA Construction 30 NA SBR 0 NA
Corporation Under
190 PDKV NA Construction 7 NA SBR 0 NA
Shegaon
Municipal S.No. 752/1, Charmori, Partially
191 Coundil Shegaon, Dist.-Buldana 2015 Operational 7 3.5 MBR 0 Complied
Opposite to Chamunda
Municipal Council Devi Mandir, Under
192 Washim NimazagaWashim NA Construction 8 NA NA NA NA
Partially
193 Pathanpura 2017 Operational 45 24 MBBR 0 Complied
Chandrapur
Municipal Partially
194 Corporation Rehmat Nagar 2017 Operational 25 22 MBBR 0 Complied
Partially
195 Azad Garden 2017 Operational 0.5 0.5 MBBR 0 Complied

126
MIZORAM

Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational (In Installed SBR / MBR with Non-
/ Under MLD) Capacity / FAB etc.) quantity comply /
Construction (In MLD) Partially
/ Proposed) Comply)
1. Aizawl Bethlehem Consent to Operate Non- 10 MLD N.A SBR (C- N.A N.A
Vengthlang (on Certificate has been Operational technology).
the bank of Chite issued on
stream) 28.11.2019.

127
NCT of DELHI
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / ASP treated status
Non- of STP of Installed /OP / SBR / sewage (Comply /
Operational / (In MLD) Capacity MBR / FAB etc.) with Non-comply
Under (In MLD) quantity / Partially
Construction / Comply)
Proposed)
1 Mehrauli Mehrauli 22.73 18.91 (EA
2003 Operational 11.4
2 Okhla Phase II Okhla Phase II 1983 Operational 54.55 27.24 ASP 168
3 Okhla Phase III Okhla Phase III 1993 Operational 168.2 145.8 ASP
4 Okhla Phase IV Okhla Phase IV 1993 Operational 204.57 176.6 ASP
5 Okhla Phase V Okhla Phase V 2001 Operational 72.74 63.5 ASP
6 Okhla Phase VI Okhla Phase VI 2012 Operational 136.38 120.5 ASP
7 Molarband Molarband 2003 Operational 3 2.3 FAB Nill
8 Sen Nursing Home Sen Nursing Home
Nallah Nallah 1998 Operational 10 10 ASP 10
9 Extended
Vasant Kunj Phase I Vasant Kunj Phase I 1988 Operational 10 7.7 Aeration (EA) 7.7
10 Extended
Vasant Kunj Phase II Vasant Kunj Phase II 1998 Operational 13.64 7.3 Aeration (EA) 7.3
11 Ghitorni Ghitorni 2016 Operational 22.73 2.5 ASP 1.38
12 Delhi Gate Nallah Old Delhi Gate Nallah Old
Phase I Phase I 1998 Operational 10 10 ASP 10
13 Delhi Gate Nallah New Delhi Gate Nallah New
Phase II Phase II 2016 Operational 68.19 68.19 ASP 5.3
14 Kondli Phase II Kondli Phase II 1999 Operational 113.65 113.5 ASP 13.5
15 Kondli Phase IV Kondli Phase IV 2013 Operational 204.57 204.57 ASP
16 Chilla Chilla 2014 Operational 40.91 40.91 SBR 0.91
17 Yamuna Vihar Phase I Yamuna Vihar Phase I 1998 Operational 45.46 45.46 ASP 2.25
18 Yamuna Vihar Phase II Yamuna Vihar Phase II 2002 Operational 45.46 45.46 ASP
19 Yamuna Vihar Phase III Yamuna Vihar Phase III 2015 Operational 113.65 113.65 ASP
20 Akshardham Akshardham 2010 Operational 4.55 0.5 MBR 0.5
21 Coronation Pillar Phase Coronation Pillar Phase I
I & II & II 1957-2000 Operational 90.92 90.92 ASP 90.92

128
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / ASP treated status
Non- of STP of Installed /OP / SBR / sewage (Comply /
Operational / (In MLD) Capacity MBR / FAB etc.) with Non-comply
Under (In MLD) quantity / Partially
Construction / Comply)
Proposed)
22 Coronation Pillar Phase Coronation Pillar Phase
III III 2001 Operational 45.46 38.59 ASP 0.091
23 Narela Narela 2000 Operational 45.46 18.16 ASP 0.227
24
Rithala Phase I Rithala Phase I 1991 Operational 90.92 90.92 ASP 18.16
25
Rithala Phase II Rithala Phase II 2001 Operational 181.84 181.84 ASP 14.3
26 Rohini Rohini 2002 Operational 68.19 22.7 ASP 1.14
27 Keshopur Phase I Keshopur Phase I 1957 Operational 54.55 54.55 ASP 24.97
28 Keshopur Phase II Keshopur Phase II 1975 Operational 90.92 90.92 ASP Nill
29 Keshopur Phase III Keshopur Phase III 1990 Operational 181.84 181.84 ASP Nill
30 Nilothi Phase I Nilothi Phase I 2002 Operational 181.84 68.1 ASP 2.27
31 Nilothi Phase II Nilothi Phase II 2015 Operational 90.92 90.92 SBR Nill
32 Pappankalan Phase I Pappankalan Phase I 2002 Operational 90.92 90.92 ASP 6.81
33 Pappankalan Phase II Pappankalan Phase II 2015 Operational 90.92 90.92 SBR 1.5
34 Najafgarh Najafgarh 2002 Operational 22.73 11.35 EA 0.32
35 Kapashera Kapashera 2014 Operational 22.73 8.17 SBR 0.9
36 Kondli Phase I Kondli Phase I Under
1987 Rehabilitation 45.46 0 ASP
37 Kondli Phase III Kondli Phase III Under
2001 Rehabilitation 45.46 0 ASP
38 Coronation Pillar Old Coronation Pillar Old Under
1957 Rehabilitation 90.92 0 ASP

129
ODISHA
Sl. City / Town Location of Date of Status (Operational / Non- Installed Actual Technology Use of treated Compliance
No. STP Commissionin Operational / Under Capacity Utilization (UASB / sewage with status
g Construction / Proposed) of STP (In of ASP /OP / quantity (Comply /
MLD) Installed SBR / MBR Non-
Capacity / FAB etc.) comply /
(In MLD) Partially
Comply)
Under Construction by Partially
1 Bhubaneswar Rokat 48 - ASP -
2019 OISIP, JICA Comply
Under Construction by
2 Bhubaneswar Meherpalli 56 - SBR -
2020 OWSSB do
Under Construction by
3 Bhubaneswar Basuaghai 28 - SBR -
2020 OWSSB do
Under Construction by
4 Bhubaneswar Kochilaput 43.5 - SBR -
2020 OWSSB do
Under Construction by
5 Bhubaneswar Paikarapur 8 - SBR -
2020 OISIP, JICA do
Under Construction by
6 Cuttack Matgajpur 16 - ASP -
2019 OISIP, JICA do
Partially used for
Under Construction by Tree plantation and
7 Cuttack CDA 36 10 ASP
OISIP, JICA discharged to
2018 Petanallah do
Discharged to
8 Cuttack Mattagajpur Operational 33 33 WSP
2006 River Kathojodi do
Mangalagha Aerated Discharged to
9 Puri Operational 15 12
t 2014 Lagoon River Mangala do
Facultative Discharged to
10 Puri Bankimuhan Operational 5 3
2016 Pond River Sea do
Under Construction by
11 Sambalpur Dhanupalli 40 - - -
2019 OWSSB do
Under Construction by
12 Rourkela Koel Nagar 8 - SBR -
2019 OWSSB do
Under Construction by
13 Rourkela Ruptala 40 - SBR -
2019 OWSSB do
Discharged to
14 Talcher Mandapal Operational 2 2 WSP
2018 River Brahmani do

130
PUNJAB
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)

1 Amritsar (North) 2019 Operational 95 66 ASP

2 Amritsar (South) 2019 Operational 95 92.2 ASP


Amritsar
Amritsar (South Under 27.5 0 SBR
3 East Zone) stabilisation
Barnala Barnala Under 20 0 SBR
4 Construction
Bathinda 2013 Operational 52 30 SBR Not
5 complying
Bathinda Bathinda Under 4.5 0 ASP
6 Construction

7 Bhucho Bhucho 2012 Operational 3 2.25 WSP Complying

8 Goniana Goniana 2012 Operational 3 2.2 WSP Complying

9 Kot fatta Kot fatta 2012 Operational 1.5 1 WSP Complying


Maur Maur 2014 Operational 5 4.95 MBBR Not
10 Complying
11 Rampura Phul Rampura Phul 2012 Operational 7 0 MBBR

12 Sangat Sangat 2012 Operational 1.5 0.8 WSP


Talwandi Sabo Talwandi Sabo 2012 Operational 3 3 MBBR Not
13 Complying
Jaito Jaito Under 6 0 SBR
14 Construction
Kotkapura Under 8 0 SBR
15 Construction
Kotkapura
Kotkapura Under 6 0 SBR
16 Construction
Mandi Mandi 2017 Operational 25 24.6 SBR Complying
17 Gobindgarh Gobindgarh

131
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)
Bassi Pathana Bassi Pathana Under 3 0 SBR
18 Construction
Sirhind Under 5 0 SBR
19 Construction
Sirhind Under 4 0 SBR
Sirhind Construction
20
Sirhind Under 2 0 SBR
21 Construction
Jalalabad (DWSS) Jalalabad (DWSS) Operational 8 12 WSP Not
22 Complying
Abohar (AMRUT) Abohar 2015 Operational 25 23 SBR Complying
23 (AMRUT)
Fazilka Fazilka 2006 Operational 8 11 WSP Not
24 Complying
Ferozepur Ferozepur Under 18 0 SBR
25 Construction
Guru Harsahai Under 4 0 SBR
26 Construction
Guru Harsahai
Guru Harsahai Under 1 0 SBR
27 Construction

28 Makhu Makhu 2018 Operational 4 1.5 SBR Complying

29 Talwandi Bhai Talwandi Bhai 2018 Operational 4 1.3 SBR Complying

30 Zira Zira 2013 Operational 8 6.33 MBBR Complying

31 Dera Baba Nanak Dera Baba Nanak 2012 Operational 1.5 1.2 WSP Complying

32 Sri Hargobindpur Sri Hargobindpur 2014 Operational 1 0.8 WSP Complying


Dasuya Dasuya 2013 Operational 4 0.3 WSP Not
33 Complying
Hoshiarpur Hoshiarpur 2015 Operational 30 20 MBBR Not
34 Complying
35 Mukerian Mukerian 2015 Operational 5 4 MBBR Not

132
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)
Complying

36 Sham Churasi Sham Churasi 2013 Operational 1 0.8 WSP


Tanda Tanda 2017 Operational 4 3.5 SBR Not
37 Complying
Jalandhar 2008 Operational 100 100 UASB Not
38 Complying
Jalandhar 2010 Operational 25 25 SBR Complying
39 (Pholriwal-I)
Jalandhar (Pir 2014 Operational 50 42 SBR Not
40 Jalandhar Dad) Complying
41 Jalandhar 2015 Operational 25 25 SBR Complying
Jalandhar 2015 Operational 25 15 SBR Complying
42 (Jaitewali)
Jalandhar 2016 Operational 10 4.5 SBR Complying
43 (Bambianwali)

44 Nakodar Nakodar 2018 Operational 6 4.5 SBR Complying


Phillaur (North) 2002 Operational 2.6 2.6 DWP Not
45 Phillaur Complying
46 Phillaur (South) 2016 Operational 3 2 MBBR Complying
Nurmahal Nurmahal Operational 2.6 2 MBBR Not
47 (GLADA) (GLADA) Complying
Shahkot Shahkot Under 3 0 SBR
48 Construction

49 Begowal Begowal 2015 Operational 2.5 2 SBR Complying


Bhulath Bhulath 2014 Operational 4 3 WSP Not
50 Complying
51 Kapurthala Kapurthala 2006 Operational 25 25 UASB
Phagwara 2008 Operational 20 15 UASB Complying
52 (North)
Phagwara
Phagwara (South) 2015 Operational 8 8 MBBR Not
53 Complying
133
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)
Phagwara 2015 Operational 8 7.25 MBBR Complying
54 (North)
Sultanpur Lodhi Sultanpur Lodhi 2003 Operational 2.6 2.6 WSP Not
55 Complying
Jagraon 2019 Operational 16 14 SBR Not
56 Complying
Jagraon
Jagraon Operational 12 12 SBR Not
57 Complying
Ludhiana 2008 Operational 152 152 UASB Not
58 (Balloke) Complying
Ludhiana 2007 Operational 111 111 UASB Not
59 (Bhattian) Complying
Ludhiana 2008 Operational 48 48 UASB Not
Ludhiana
60 (Jamalpur) Complying
Ludhiana 2012 Operational 50 50 SBR Complying
61 (Bhattian)
Ludhiana 2011 Operational 105 105 SBR Not
62 (Balloke) Complying
63 Machhiwara Machhiwara 2015 Operational 4 1.7 SBR Complying

64 Sahnewal Sahnewal 2017 Operational 7 4.25 SBR Complying


Maloud (GLADA) Maloud Operational 1 1 MBBR Not
65 (GLADA) Complying
Mullanpur Dakha Mullanpur Dakha 2013 Operational 3 2.85 MBBR Complying
66 (GLADA) (GLADA)
Payal (GLADA) Payal (GLADA) Operational 1 1 MBBR Not
67 Complying
68 Doraha (GLADA) 2015 Operational 2.75 1.5 MBBR Complying
Doraha (GLADA) 2015 Operational 1 0.8 MBBR Not
69 Doraha (GLADA) Complying
Doraha (GLADA) Operational 1 0.75 MBBR Not
70 Complying
Khanna Khanna Under 29 0 SBR
71 stabilisation
134
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)
Baretta Baretta 2012 Operational 3 3 WSP Not
72 Complying
Bhikhi Bhikhi 2012 Operational 3 3 WSP Not
73 Complying
74 Budhlada Budhlada 2016 Operational 6.5 5 MBBR Complying

75 Mansa Mansa 2016 Operational 14 1.5 MBBR


Sardulgarh Sardulgarh 2012 Operational 4 4 WSP Not
76 complying
Boha Boha Under 2 0 SBR
77 Construction

78 Moga Moga 2013 Operational 27 10 SBR

79 Dharamkot Dharamkot 2018 Operational 4 3.65 SBR Complying


Bagha Purana Bagha Purana Under 3.8 0 MBBR
80 (DWSS) (DWSS) Construction
Gidderbaha Gidderbaha Under 7 0 MBBR
81 stabilisation
Shri Mukatsar 2012 Operational 8.7 8.7 MBBR
82 sahib (DWSS)
Shri Mukatsar Shri Mukatsar 2012 Operational 5.7 5.7 MBBR
83 sahib sahib (DWSS)
Shri Mukatsar 2008 Non 3.5 0 MBBR
84 sahib (DWSS) Operational
Malout 2003 Operational 3 3 WSP Not
85 complying
Malout
Malout Operational 10 10 MBBR Not
86 complying
87 Banga Banga Operational 3 2.8 SBR Complying
Nawanshahar Nawanshahar 2015 Operational 6 5.8 SBR Not
88 Complying
Patiala Patiala 2014 Operational 46 46 SBR Complying
89 (Shermajra)
135
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)

90 Patiala (Ablowal) 2014 Operational 10 10 SBR Complying

91 Puda Patiala Operational 13 8 FAB Complying

92 Patran Patran 2017 Operational 4 2.5 SBR Complying

93 Rajpura Operational 10 9.65 SBR Complying


Rajpura Rajpura Operational 7 6 SBR Not
94 Complying
95 Samana Samana 2011 Operational 10 7 SBR Complying
Pathankot Pathankot Operational 27 2.7 SBR Not
96 Complying
Chamkaur Sahib Chamkaur Sahib 2015 Under 1.7 0 WSP
97 stabilisation

98 Morinda Morinda Operational 5.5 1.5 SBR COmplying

99 Nangal 1994 Operational 8 8 ASP Complying


Nangal
100 Nangal (Burari) Operational 5 5 ASP Complying
Anandpur Sahib Anandpur Sahib Operational 8 2 MBBR Complying
101 (DWSS) (DWSS)
Ropar, Badi 2013 Operational 10 7.8 SBR Complying
102 haweli
103 Ropar Ropar, Rasulpur 2014 Operational 2.5 1.2 SBR Complying
Ropar,Sadavarat 2014 Operational 2 0.5 SBR Not
104 Complying
Bhawanigarh Bhawanigarh Under 4 3.5 SBR
105 stabilisation
Dhuri Dhuri Under 5 0 SBR
106 Construction

107 Khanauri Khanauri 2018 Operational 3 2.2 SBR Complying

108 Lehragaga Lehragaga 2018 Operational 4 1.5 SBR COmplying

109 Moonak Moonak 2017 Operational 3 1.8 SBR Complying

136
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Commissioning (Operational Capacity Utilization (UASB / ASP treated status
/ Non- of STP (In of Installed /OP / SBR / sewage (Comply /
Operational / MLD) Capacity (In MBR / FAB with Non-
Under MLD) etc.) quantity comply /
Construction Partially
/ Proposed) Comply)
Sangrur Sangrur Under 4 0 SBR
110 Construction

111 Sunam Sunam 2017 Operational 8 6.8 SBR Complying

112 Banur Banur 2014 Operational 4 2.5 MBBR

113 Dera Bassi Dera Bassi Operational 4 1.2 SBR Complying


Kharar Kharar Operational 11 9 SBR Not
114 Complying
115 Lalru Lalru Operational 1.5 0.1 SBR Complying

116 Kurali (GMADA) Kurali (GMADA) Operational 5 3.2 MBBR Complying


Mohali (AMRUT) Mohali (AMRUT) Operational 45.4 30 UASB Not
117 (DWSS) (DWSS) Complying
Zirakpur Zirakpur 2013 Operational 17.3 13.5 SBR Not
118 Complying
Tarn Taran Tarn Taran Under 9 6.9 SBR
119 stabilisation

137
PUDUCHERRY

Sl. City / Town Location of Date of Status Installed Actual Technology Use of Compliance
No. STP Commissioning (Operational / Capacity Utilization (UASB / treated status
Non- of STP of Installed ASP /OP / sewage (Comply /
Operational / (In Capacity SBR / MBR with Non-
Under MLD) (In MLD) / FAB etc.) quantity comply /
Construction / Partially
Proposed) Comply)
1 Lawespet Operational 19.5 17.5 SBR Watering
of city
parks,
gardens,
Puducherry roads etc.

2 Kanaganeri Operational 17 5 UASB


3 Dubrayarpet Operational 19.5 7 UASB

4 Karaikal Karaikal Proposed 3 0

138
RAJASTHAN
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
1 Brahampuri 31-05-2008 Operational 8 SBR
2 Dalawas Full Disposal to adjoining Non-
15-03-2006 Operational 62.5 ASP
Capacity Nallah Complying
3 Delawas Full Disposal to adjoining Non-
15-03-2006 Operational 62.5 ASP
Capacity Nallah Complying
4 Jaisinghpura Khor Non-
2011 Operational 50 30 Approx. ASP Discharge into Nallah
Complying
5 Jawahar Circle Plantation &
Under
04-09-2010 1 MBBR gardening in Jawahar Complying
Construction
Circle garden
6 Ramniwas Bagh Plantation &
Jaipur gardening in
10-08-2011 Operational 1 MBBR Complying
Ramniwas Bagh
garden
7 Central Park Plantation &
31-05-2017 Operational 1 NA SBR gardening in Central Complying
Park
8 Ralawata Disposal to adjoining Non-
2016 Operational 30 6 KLD ASP
Nallah Complying
9 M/s Jaipur Disposal into Bandi Non-
2015 Operational 30 12 to 15 ASP
Development Authority River Complying
10 Taal Katora Under
NA 1 NA SBR
Construction
11 Agyara Anaerobic
12 to 14 followed by Non-
Jul-12 Operational 20 Irrigation
KLD facultative Complying
Alwar pond
12 Bhiwadi Not being reused.
Approx 04 Partially
2012 Operational 4 SBR Presently discharged
MLD Compiled
into adjacent plot

139
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
13 Nandari On land for Plantation
Non-
2018 Operational 20 20 OP / Horticulture after
Complying
adequate treatment
14 Salawas On land for Plantation
Jodhpur 2004 Operational 50 50 ASP / Horticulture after Complying
adequate treatment
15 Salawas Road On land for Plantation
2011 Operational 50 50 ASP / Horticulture after Complying
adequate treatment
16 Jalore Jalore Partially Utilized for
irrigation - The rest
Watse
flows in downstream,
Stabilization
creates pool of
Pond (WSP) Non-
2013 Operational 10 45% effluent and
(Anaerobic Complying
terminate- No
Facultative
quantification of
Lagoon)
treated effluent used
for irrigation
17 Jaisalmer Jaisalmer On land for Plantation
Non-
2014 Operational 10 10 OP / Horticulture after
Complying
adequate treatment
18 Pushkar To be (1.6 MLD )On land
commissioned Under for Plantation /
3.5 1.6 MBBR
within a period Construction Horticulture after
of 06 months adequate treatment
19 Anasagar Lake into AnnaSagar Lake Non-
Ajmer Operational 13 9 SBR
01.03.2016 (9 MLD) Complying
20 Khanpura Nasirabad To be
discharge into escape
Road commissioned Under
40 ASP channel and irrigation
within a period Construction
purposes.
of 03 months

140
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
21 Kishangarh To be
Watse
commissioned Under
10 6 Stabilization irrigation purposes.
within a period Construction
Pond (WSP)
Ajmer of 02 months
22 PIU-Ajmer I I 8 discharge into escape
Jul-10 Operational 20 12 ASP channel and irrigation
purposes.
23 Nagaur Nagaur Watse
Partially
15.08.2017 Operational 8 3.5 Stabilization irrigation purposes.
Compiled
Pond (WSP)
24 Barmer Barmer Partially Utilized for
irrigation - The rest
Watse
flows in downstream,
Stabilization
creates pool of
Pond (WSP)
2016 Operational 10 35% effluent and
(Anaerobic
terminate- No
Facultative
quantification of
Lagoon)
treated effluent used
for irrigation
25 Karoli Karauli 11.09.2018 Operational 5 1 UASB Complying
26 Bharatpur Makrana no quantification of
Under
NA 8 SBR treated effluent used
Construction
NA for irrigation
27 Dholpur Dholpur Jan-16 Operational 10 10 UASB Complying
28 Sawaimadopur Sawaimadhopur Facultative
10-10-2014 Operational 10 2.5 Stabilization Complying
Pond
29 Chittorgarh Chittorgarh Gardening and
Partially
31.01.2017 Operational 5 1 UASB ground recharge
Compiled
(1MLD)

141
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
30 kota Kota treated water is
dicharged into
Sajidheda Nallah.
This nallah also
carries huge quantity
of untreated sewage
Non-
2016 Operational 30 7-8 MLD SBR which has yet not
Complying
been diverted at inlet
of STP. Finally this
mixed sewage joins
river Chambal at
upstream side of Kota
Barrage
31 kota balita Non- Non-
NA 6 NA SBR
Operational NA Complying
32 Bundi Bundi treated water is
dicharged into natural Non-
2018 Operational 8 2-3 MLD SBR
Nallah flowing near Complying
premises of STP
33 Pali Pali Waste
Non-
01.10.2013 Operational 10 3 Stabilization
Complying
Ponds 3
34 Sirohi Sirohi Non-
2011 Operational 6 1 ASP
1 Complying
35 Jhunjunu Jhunjunu Used in conservative
forest 1056 Hectare
Ready to Land for plantation
8.5 UASB
Commision and nearby farmer
used in agriculture
purpose
36 Churu Gajsar Waste
NA Operational 7 Stabilization Disposed in Jhohar
Ponds

142
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
37 Churu Churu Waste used in Gau shala
Under
NA 2 Stabilization land for agriculture
Construction
Ponds purpose.
38 Churu Sardarsahar Waste used in Gau shala
Ready to Under
5 Stabilization land for agriculture
Commision Construction
Ponds purpose.
39 Bikaner Bikaner Existing STP
not compiled
New STP
Waste
shall be
1.10.2017 Operational 20 Stabilization on land discharge
monitored
Ponds
after
operation of
the plant
40 Bikaner Sarai nathania, Bikaner Waste
Non-
13.12.2016 Operational 12 Stabilization Plantation
Complying
Ponds
41 Hanumangarh Hanumangarh Waste
Non-
2014 operational 7.5 Stabilization on land discharge
Complying
Ponds
42 Hanumangarh Hanumangarh Non-
Oct-17 Operational 5 SBR Farming
Complying
43 Rajsamand Rajsamand Discharged outside
Non-
21.09.2017 Operational 5 1.4-1.7 UASBR the STP premises (1.4
Complying
to 1.7) approx
44 Kota Kota treated water
Non-
2013 Operational 20 12-18 MLD ASP discharged into
Complying
natural nallah.
45 Bhiwara Kuwada Reuse inside the plant
and mines of M/s Non-
01.08.2012 Operational 10 3.8 ASP
Jindal Saw Limited, Complying
N/v pur, Bhilwara

143
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
46 Jhalawar Jhalawar Treated sewage is
Waste
discharged into Non-
2015 Operational 3 1.7 Stabilization
natural nallah flowing Complying
Ponds
near premises of WSP
47 Jhalawar Faisalpur, Treated sewage is
Jhalawar discharged into
natural nallah flowing
near premises of STP
Non- Non-
2016 6 NA ASP however during
operational Complying
inspection the STP
was non operative
and no discharge
observed.
48 Rajsamand Nathdwara Presently in
Non-
dismantled 4.3 NA
operational
situation
49 Udaipur Udaipur Industrial (Sent to
HZL) & Gardening
31.01.2019 Operational 25 25 MBR complying
&Plantation in unit
premises
50 Bhiwara Kuwada NA NA 4.5 3.8
51 Sikar Fatehpur Shekhawati NA Operational 7.5
52 Nagaur Didwana Partialy
July, 2017 Operational 5 3 SBR Irrigation Purposes
Compiled
53 Tonk Tonk Under
NA 1.016 NA NA NA
Construction NA
54 Jaipur Jaipur NA Proposed 2 NA SBR NA NA
55 Nagaur Nagaur Partialy
22.02.2016 Operational 6 SBR Irrigation Purposes
3.5 Compiled
56 Ganganagar Sri Ganganagar Non-
01.01.2018 Operational 10 SBR Farming
Complying
57 Ganganagar Sri Ganganagar NA Under 10 SBR NA NA

144
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
Construction
58 Ganganagar Sri Ganganagar NA Operational 15 SBR NA NA
59 Jaipur Jaipur used for plantation
1.4.2015 Operational 1 MBBR
and gardening
60 Barmer Balotra Diacharged in natural
nallah which Non-
Operational 9 SBR
terminates in Jojari Complying
2016 55% River
61 Sikar Sikar Constuction to
Proposed 5 Propesed
be started
62 Jaipur Jaipur Under
NA 1 NA MBBR discharged into nallah
Construction
63 Jaipur Jaipur Under
NA 0.85 NA MBBR NA NA
Construction
64 Jaipur Jaipur Under
NA 0..38 NA MBBR NA NA
Construction
65 Jaipur Jaipur Under
NA 0.41 NA MBBR NA NA
Construction
66 Jaipur Jaipur Under
NA 0.25 NA MBBR NA NA
Construction
67 Dholpur Dholpur Feb-18 Operational 3 3 SBR 18 Tons per month complying
68 Chittorgarh Chittorgarh Extended
Aeration
type
2002-03 Operational 1 1 Gardening (1 MLD) complying
Activated
Sludge
Process
69 Chittorgarh Chittorgarh discharged into river Partially
16.07.2017 Operational 3 2.5 SBR
(3 MLD) Compiled
70 Jaipur Jaipur Non-
Jun-17 Operational 3 NA SBR in adjoining nallah
Complying

145
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
71 Tonk Tonk Work
terminated. Under
4 4 SBR nil
Retender is in Construction
Progress
72 Jaipur Jaipur NA Operational 1 NA SBR in adjoining nallah complying
73 Pali Pali 26-07-2019 Operational 15 4 SBR complying
74 Tonk Tonk Work
terminated. Under
16 16 SBR nil
Retender is in Construction
Progress
75 Sikar Sikar NA Operational 2 SBR
76 Sikar Sikar Ready to
NA 8 SBR
Commision
77 Alwar Bhiwadi under Under
3 SBR NA NA
Construction Construction
78 Alwar Bhiwadi Not being reused.
Partially
2019 Operational 1.5 1 SBR Presently discharged
Compiled
into adjacent plot
79 Alwar Bhiwadi Not being reused.
Partially
2020 Operational 2 0.05 SBR Presently discharged
Compiled
into RIICO drain
80 Alwar Bhiwadi under Under
3 SBR
Construction Construction
81 Alwar Bhiwadi under under
2 NA SBR NA NA
installation installation
82 Jhunjunu Jhunjunu used in conservative
Civil and
forest 1056 hectare
mechanical
Under land for plantation
work completed 7 SBR
Construction and near by farmer
and electrical
used in agriculture
work pending
purpose.
83 Bhadra bhadra NA Under 3.5 NA SBR NA NA

146
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
Construction
84 Ganganagar Suratgarh Under
NA 2.5 NA SBR NA NA
Construction
85 Ganganagar Suratgarh Under
NA 2.5 NA SBR NA NA
Construction
86 Hanumangarh bhadra Under
NA 1 NA SBR NA NA
Construction
87 Ajmer Beawar 30.07.2020 Proposed 5 2 SBR Irrigation Purpose
88 Chittorgarh Chittorgarh Under
NA 1 NA SBR NA NA
Construction
89 Chittorgarh Chittorgarh Under
NA 2 NA SBR NA NA
Construction
90 Jhunjunu Nawalgargh 31.03.2021 Proposed 3 SBR Irrigation Purpose NA
91 Jhunjunu Jhunjunu 25.11.2020 Proposed 1 SBR Irrigation Purpose NA
92 Jhunjunu Chirawara Ready to
Proposed 3 SBR
Commision
93 Sikar Ramgarh Shekawati Ready to
Proposed 2 NA SBR NA NA
Commision
94 Sikar Laxmangarh Ready to
Proposed 1 NA SBR NA NA
Commision
95 Sikar Laxmangarh Ready to
Proposed 1.5 NA SBR NA NA
Commision
96 Churu Churu under
2.5 NA SBR
Jun-21 Construction
97 Ajmer Beawar 25.11.2020 Proposed 1.5 0.6 SBR irrigation purpose
98 Udaipur Udaipur Industrial (used by
HZL) & Gardening &
Operational 20 MBR Complying
Plantation in unit
2015 20 premises
99 Ajmer Beawar 30.10.2020 Proposed 4 SBR irrigation purpose
1.6
100 Udaipur Fatehnagar NA Proposed 1 0.4 SBR NA NA

147
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
101 Churu Churu under
Jun-21 1 SBR
Construction 1
102 Chittorgarh Badi Sadri Non-
NA 2.5 NA NA NA NA
operational
103 Banswara Kushalgarh,
Not
Banswara NA Proposed 1 NA NA Not Applicable
Applicable
104 Chittorgarh Railway colony Under Not
chittorgarh NA 1 NA SBR Not Applicable
Construction Applicable
105 Chittorgarh Bundi road Under Not
NA 1 NA SBR Not Applicable
Construction Applicable
106 Churu Gas Agency Dumping
Yard, Under
Jun-21 5.5 SBR
Sujangarh Churu, Construction
Rajasthan
107 Churu near Gularia Hotel ,
Khasra Under
Jul-21 2 SBR
no. 787, 246 city Construction
Sujangarh
108 Jodhpur Near Basni Benda Civil work is
To be
Jodhpur NA under 40 NA NA
updated
progress 40
109 Pali Khasra No.432/222
Karoliya village on
Nimbola
01.10.2019 Operational 2 SBR 1 Complying
Road, Tehsil - Pali,
District-
Pali 1
110 Bikaner Near Kali Mata Temple,
Under
Sujandesar, Tehsil and NA 20 NA SBR NA NA
Construction
District- Bikaner
111 Bharatpur Khasara No 44, Ikaran, Under
NA 5 NA SBR NA NA
Village-Nagla Gopal , Construction

148
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
Bharatpur
112 karauli Khasara No. 5430,Near
Under
Ganesh Hotel, Hindaun NA 3 NA SBR NA NA
Construction
City
113 karauli Jaccha Ki Bawri, Tehsil-
Under
Hindaun City, district- NA 0.75 NA SBR NA NA
Construction
Karauli
114 Sawai Khasra No. 275,
Under
Madhopur Gangapur NA 2.5 NA SBR NA NA
Construction
City, Sawai Madhopur
115 Sawai Khasara No. 167,
Under
Madhopur Hingotia , NA 5.5 NA SBR NA NA
Construction
Gangapur City
116 Sawai Khasra No 152, 153 STP
Madhopur (2.5) MLD, Nagar
NA Proposed 1.5 NA SBR NA NA
Parishad,
Gangapur City
117 Chittorgarh behind shamshan ghat
Under
Karthana Road STP, NA 2 NA SBR NA NA
Construction
Nimbahera
118 Chittorgarh near Kasod Basti,
Under
Nimbahera Tebsil.- NA 1 NA SBR NA NA
Construction
Nimbahera
119 Bikaner ward no. 7, Nokha Non-
2012 1 NA MBBR NA NA
operational
120 Churu Gopal Goushala Land
Near
Under
Salasar Road, Khasra Jun-21 1.5 SBR
Construction
No.
202, Sujangarh, Churu
121 Nagaur Ambuja Cement Ltd.,
Marwar Mundwa, Under Industrial use in
31.03.2021 0.3 NA MBBR
Mundwa, Construction Ambuja Limited
Nagaur

149
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
122 Udaipur near FCI Godown
,Tehsil 05.06.2020 Operational 10 NA SBR Complying
Girwa, Udaipur
123 Udaipur Near Karjali House
Under
Tehsil NA 5 NA SBR NA NA
Construction
Girwa, Udaipur
124 Bhiwara Village- Kuwada,
Under
District- NA 30 NA SBR
Construction
Bhilwara
125 Bikaner at Village - Sujadesar
(khasra
NA Proposed NA NA NA NA
no.341,357,358,3 59,360)
Bikaner 0.02
126 Hanumangarh Hanurnangarh Town,
NA Proposed 2 NA SBR NA NA
District-Hanumangarh
127 Hanumangarh Hanumangarh Junction,
Hanumangarh NA Proposed 4 NA SBR NA NA

128 Bundi Bibnawa Road,Tehsil:- To be


NA Proposed 0.5 NA NA NA
Bundi updated
129 Bundi near Gandhi Gram
To be
Tehsil.- NA Proposed 0.5 NA NA NA
updated
Bundi
130 Ajmer Kundan Nagar, Beawar,
25.11.2020 Proposed 1 0.4 SBR Irrigation Purposes
Ajmer
131 Sikar Gogamedi, Ramgarh Under
Mar-20 1 NA SBR NA NA
Shekhawati Construction
132 Kota Dhakar Kheri NA Proposed 40 NA SBR NA NA
133 Nagaur Khasra No. 405, STP
station March, 2021 Proposed 1.5 SBR Irrigation Purposes
road, bad i kuwa 1
134 Kota K.no. 1146, 1189, 1192,
1193, 1217, 1218, 1220, NA Proposed 15 NA SBR NA NA
1277, 1281-1284, 1286,

150
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance
No. Commissioning (Operational / Capacity Utilization (UASB / with quantity status
Non- of STP of ASP /OP / (Comply /
Operational / (In Installed SBR / MBR / Non-comply
Under MLD) Capacity FAB etc.) / Partially
Construction (In MLD) Comply)
/ Proposed)
Kala Talab, Dhakar
Kheri
135 Pali Near E.S.I Hospital Non
03.10.2013 Operational 7.5 2 ASP 2
Complying
136 Jhunjunu Khasra no. 72 I , Bhagat
Singh
NA 1 NA SBR Irrigation Purposes NA
Joha
,Nawalgarh,Jhunjhunu
137 Churu At near Gaushala Waste used in Gaushala land
Bikaner 2 Stabilization for agriculture
road Sardarshar Ponds purpose
138 Jhunjunu Bhageniya Johda,
Chirawa, 2 SBR
Jhunjhunu
139 Chittorgarh near Ambamata temple,
neemuch highway, Not
NA 4.5 SBR Not Applicable
Nimbahera, Tehsil:- Applicable
Nimbahera, C NA
140 Laxmangarh Near Todikui, Sikar Not
Mar-21 NA 3 SBR Not Applicable
NA Applicable

151
SIKKIM
Sl. City / Location of Date of Status Installed Actual Technology Use of Compliance
No. Town STP Commissioning (Operational / Capacity Utilization (UASB / treated status
Non-Operational / of STP of ASP /OP / sewage (Comply /
Under (In Installed SBR / MBR with Non-comply
Construction / MLD) Capacity / FAB etc.) quantity / Partially
Proposed) (In MLD) Comply)
1 Adampool Functional 8 8 FAB
2 Adampool Functional 4.69 3 FAB
3 Ranipool Functional 1.27 1 EMMAR
4 Zone - IV Functional 3.9 1.95 FAB
Under
5 1.6
Zone - II Construction 0 SBR
6 Gangtok Proposed 3.25
Zone - III 0
7 Singtam Functional 0.66 0.66 MBR
8 Rangpo Proposed 1.4 0
9 Namchi Proposed 3.63 0 FAB
10 Jorethang Proposed 1.7 0 MBBR
11 Meilli Proposed 0.5 0 MBBR

152
TAMIL NADU
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)
Activated
1 Ariyalur Ariyalur 05-03-2018 Operational 4.16 0.7 Sludge 0.7 Compiled
Process
2 Perambalur Perambalur 31-12-2010 Operational 4.2 3.2 ASP 3.2 Compiled
TTP RO - 65 MLD,
3 Kodungaiyur 01-08-2006 Operational 110 110 ASP Compiled
Industry Supply - 25 MLD
4 Kodungaiyur 01-04-1985 Operational 80 40 ASP Nil Compiled
5 Kodungaiyur 01-05-1986 Operational 80 40 ASP Nil Compiled
6 Koyambedu 10-07-2005 Operational 60 60 ASP Nil Compiled
7 Chennai Koyambedu 22-12-2014 Operational 120 120 ASP TTP RO - 65 MLD Compiled
8 Koyambedu 05-07-1978 Operational 34 34 ASP nil Compiled
9 Nesapakkam 20-05-2006 Operational 40 40 ASP Nil Compiled
10 Nesapakkam 01-10-2014 Operational 54 54 ASP Nil Compiled
11 Nesapakkam Apr-74 Operational 23 23 ASP Irrigation Compiled
M/s. CBE
12 Corporation STP at 26-02-2011 Operational 70 30 SBR 30 MLD Compiled
Ukkadam
Coimbatore
M/s. CBE
13 Corporation STP at 14-04-2016 Operational 60 5 SBR 5 MLD Compiled
Ondipudur
M/s. Cuddalore
14 Cuddalore Muncipality UGSS 20-01-2010 Operational 12.25 12.25 ASP Partially Compiled
S.F.No.1508 12.25MLD
M/s. Dharmapuri 1 MLD disposed to inland
15 Dharmapuri Municipality UGSS 01-05-2009 Operational 4.86 1 ASP surface water in turn used Compiled
S.No.474/5 for irrigation

153
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)
Fluidised
M/s. Hogenakka 1
Bed Bio 0.35 MLD used for
16 Dharmapuri UGSS STP S.No. 23.10.2016 Operational 0.35 0.35 Compiled
Reactor Gardening
1103/4,6,7
(FBBR)

2 MLD-Mixed with
treated tannery effluent
17 Dindigul Dindigul 19.11.2012 Operational 13.65 2.5 ASP Compiled
and 0.5 MLD- irrigation
on their own land

Treated Sewage 54 MLD


Greater Chennai
18 01.08.2006 Operational 54 54 ASP discharged into Compiled
Corporation
Buckingham canal

Treated Sewage 60 MLD


Greater Chennai
19 Operational 60 60 ASP discharged into Compiled
Corporation
Buckingham canal
Chennai 24.02.2009
Treated Sewage 12 MLD
Greater Chennai
20 02.07.2003 Operational 12 12 ASP discharged into Compiled
Corporation
Buckingham canal

Treated Sewage 18 MLD


Greater Chennai
21 31.01.2018 Operational 18 18 SBR discharged into Compiled
Corporation
Buckingham canal

Treated Sewage 2.2 MLD


22 Maraimalainagar 28.02.2010 Operational 2.2 2.2 ASP discharged into Compiled
Ninnaikarai Eri
Chengalpattu
Treated Sewage 2.34 MLD
23 Mamallapuram 05.10.2015 Operational 2.34 2.34 ASP discharged into Compiled
Buckingham canal

154
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)

Kancheepuram Anaerobic
24 01.09.2010 Operational 14.71 14.71 - SCN issued
Municipality Pond

Let it to inland water


25 Karur Karur 14.01.2005 Operational 15 15 ASP bodies and used for Compiled
irrigation. 15 MLD

26 Hosur Hosur 20.09.2017 Operational 9 9 UASB 7.69 MLD Compiled

on land for irrigation-


27 Sakkimangalam 01.01.2010 Operational 45.7 12 SBR Compiled
Fodder craft
Madurai
on land for irrigation-
28 Avaniyapuram 01.01.2010 Operational 125 20 SBR Compiled
Fodder craft

29 Nagapattinam 18.04.2016 Operational 9.63 4 ASP Into River Devanadhi Compiled


Nagapattinam
30 Mayiladuthru Rai 01.01.2005 Operational 6 6 op Irrigation 6 MLD Compiled
31 Thiruvarur Thiruvarur 24.09.2014 Operational 6.92 4 MBR Irrigation 4 MLD Compiled
32 Namakkal 26.10.2013 Operational 5 5 ASP 5 MLD Compiled
Namakkal
33 Namakkal 25.02.2019 Operational 6.96 1.2 ASP 1.2 MLD Compiled

Discharged in to
34 Nilgiris 1992 Operational 5 4 ASP Generally Compiled
Kamarajar Sagar Dam
Nilgris
Discharged in to
35 Nilgiris 2013 Operational 2 1.5 ASP Generally Compiled
Udhagamandalam lake

155
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)

The Municipality has


provided closed pipe line
to discharge the treated
36 Pudukkottai Pudukkottai Jan-17 Operational 10.62 5.5 ASP sewage quantity of 5.5 Compiled
MLD in to Maruppani Eri
which confluences with
Gundaru River

Discharged into surplus


37 Ramanathapuram Ramanathapuram 06.11.2013 Operational 8.19 ASP Compiled
5 course of River Vaigai
Within Standards (pH,
feacal coliform, Total
Coliform) Exceeded the
Modified standards (TSS, BOD,
38 Salem 22.06.2015 Operational 13 2 2
ASP COD, Ammonical
Nitrogen, Total
Nitrogen, Dissolved
Phospate)
Within Standards (pH,
BOD,feacal coliform,
Total Coliform)
Salem Exceeded the standards
39 Salem 2019 Operational 6 1 FAB -
(TSS, COD,
Ammonical Nitrogen,
Total Nitrogen,
Dissolved Phospate)
Within Standards (pH,
BOD, COD,
Ammonical Nitrogen,
40 Salem 22.10.2006 Operational 5.45 1.7 ASP - Feacal coliform, Total
Coliform) Exceeded the
standards (TSS, Total
Nitrogen)

156
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)
Within Standards (pH,
BOD, COD,
Ammonical Nitrogen,
41 Salem 22.10.2016 Operational 0.92 0.13 ASP - Total Nitrogen, Feacal
Salem coliform, Total
Coliform) Exceeded the
standards (TSS)
42 Salem 31.03.2017 Operational 0.82 0.27 ASP - -
CTE-03/08/2004 CTO Consent fee not paid.
M/s. Tanjavur
43 01.01.2001 Operational 28.05 28.05 ASP 03/08/2015 RCO Valid Revamping works are
Municipality STP
upto 30.09.2017 under progress.
M/s. STP CTO 10/09/2009 RCO
44 Thanjavur Kumbakonam 01.01.2002 Operational 15 15.00 ASP issued on 15.10.2014, Compiled
Municipality Valid upto 31.03.2015
M/s. STP CTE-22/12/2014 CTO-
45 Orathanadu Town 01.01.2014 Operational 1.5 1.5 ASP 27/04/2016 Valid upto Compiled
Panchayat 31.03.2017
Theni Allinagaram on land for irrigation-5.5
46 01.09.2014 Operational 12.05 5.5 ASP Compiled
Municipality MLD
Chinnamanur on land for irrigation-3.6
47 21.06.2011 Operational 3.99 3.6 ASP Compiled
Municipality STP MLD
Theni
Bodinaickanur on land for irrigation-2.5
48 29.01.2018 Operational 12.08 2.5 ASP Compiled
Municipality STP MLD
Periyakulam on land for irrigation-4.0
49 01.07.2017 Operational 5.47 4 ASP Compiled
Municipality STP MLD
Tiruchendur Town Treated effluent disposed
50 Thoothukudi 03.04.2017 Operational 4.39 4 ASP Yet to apply CTO
Panchayat to sea
Not Compiled,
Direction issued vide
Waste
Disposed in irrigation Bd's Proc. No.
51 Thirunelveli Thirunelveli 01.04.2007 Operational 24.2 8 Stabilization
channel-8 MLD T1/TNPCB/F.10807/T
Pond
NV/2020 Dated
25.06.2020

157
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated sewage Compliance status
No Commissioning (Operational Capacity Utilization (UASB / with quantity (Comply / Non-comply
. / Non- of STP of ASP /OP / / Partially Comply)
Operational / (In Installed SBR / MBR
Under MLD) Capacity / FAB etc.)
Construction (In MLD)
/ Proposed)

7.5 MLD Presently let into


Tiruppur Convention
52 22.11.2007 Operational 15 7.5 Nallar odai which finally Generally Compiled
Corporation al ASP
Tiruppur reached Noyyal river

3.4 MLD - To nearby odai Compiled with


53 Udumalpet 31.12.2013 Operational 7.81 3.4 ASP
for Agricultural purpose. standards
2016 (Yet to
Discharged partly into Yet to obtain CTO.
Tiruvallur obtain CTO,
54 Operational 6.208 2 ASP Putlur Eri and remaining Meeting the discharge
Municipality NGT Case
quantity into cooum river standards
involved)
Avadi City
Tiruvallur Discharged partly
55 Municipal 01.01.2019 Operational 4 1 ASP yet to obtain consent
Muthapupet lake
Corporation
Cooum River near the
Tirumazhisai Town
56 04.11.2019 Operational 3 1.6 ASP Thiruverkadu Minor compiled
Panchayat STP
Canal
Disposed to Olaiyaru
57 Tiruvannamalai Tiruvannamalai 01.06.2009 Operational 8.7 2.5 ASP compiled
River
55.32 KLD used for tree
stabilization
plantaion and excess
58 Trichy Trichy 01.05.2007 Operational 88.64 55.32 pond compiled
treated sewage into River
technology
Koraiyar
Vellore City Discharged to Velavadi
CTE Issued vide Proc.
59 Vellore Municipal 30.09.2015 Operational 10.28 7.5 ASP Eri for irrigation to the
09.02.2010
Corporation STP nearby Agricultural Land
Partly used for
Sholingur Liquid Reed Bed
plantation/Gardening
60 Ranipet Waste Management Operational 7 2 Filter Not applied
and remaining discharged
System Technology
2010 to Nandhi River
61 Villupuram Villupuram 2015 Operational 9 NA ASP 9 Not Compiled
62 Villupuram Villupuram 2015 Operational 3.5 NA ASP 3.5 Not Complied
63 Virudhunagar Virudhunagar 19.10.2014 Operational 7.65 3.5 ASP Inland surface water Compiled

158
TELANGANA
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status
No Commissioning (Operational Capacity Utilization (UASB / sewage with (Comply / Non-
. / Non- of STP of ASP /OP / quantity comply / Partially
Operational / (In Installed SBR / MBR / Comply)
Under MLD) Capacity FAB etc.)
Construction (In MLD)
/ Proposed)
1 Amberpet 2009 Operational 339 300 UASB Disposal to Musi Complying
(September) River
2 Miralam Tank Phase I 2007 (March) Operational 10 9.5 ASP + EA Into Miralam tank Complying
and as well
gardening purpose
3 Miralam Tank Phase II 2007 (March) Operational 5 5 ASP + EA Into Miralam tank Complying
and used for
gardening purpose
in Zoo park
4 Kharitabad 1998 Operational 20 20 SBR Into Hussainsagar Complying
Lake
5 Langer House 2005 Operational 1.2 1 ASP + EA Into Langer House Complying
Hyderabad Lake
6 Attapur Phase I 2013 Operational 23 20 SBR River Musi Partially Complying
(Exceeding the
stipulated standards
for BOD)
7 Attapur Phase II 2013 Operational 51 45 SBR River Musi Complying
8 Krishna Kanth Park Non 0.5 0.5 EA Gardening Under Maintenance
Operational
9 Jalagam Vengal Rao 2007 Operational 0.5 0.5 EA Gardening and Complying
Discharging into
small Lake inside the
park
10 Nagole 2008 Operational 172 172 UASB To Musi River Partially Complying
(December) (Exceeding the
stipulated standards
for BOD)
11 Rangareddy Nalla Cheruvu 2009 (June) Operational 30 30 UASB To Musi River Complying
12 Nacharam 2006 Operational 10 10 EA Pedda Cheruvu Complying
Nacharam
13 Durgam Cheruvu 2007 Operational 5 5 ASP Durgam Cheruvu Complying

159
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status
No Commissioning (Operational Capacity Utilization (UASB / sewage with (Comply / Non-
. / Non- of STP of ASP /OP / quantity comply / Partially
Operational / (In Installed SBR / MBR / Comply)
Under MLD) Capacity FAB etc.)
Construction (In MLD)
/ Proposed)
and resued for
gardening at
shilpaparam and
KBRN park
14 Rangareddy Saroornagar 2000 Operational 2.5 0.8 ASP Into Saroornagar Complying
Cheruvu
15 Secunderabad KIMS 2013 Operational 30 30 ASP Into Hussainsagar Complying
Lake
16 Safilguda 2001 (July) Operational 0.6 0.6 ASP Into Safilguda Lake Complying
17 Nanakramguda 2015 Operational 4.5 4 MBBR Pedda Cheruvu Complying
Nanakramguda
18 Khajaguda 2015 Operational 7 5.5 MBBR Khajaguda Lake Partially Complying
(Exceeding the
stipulated standards
for BOD)
19 Rangareddy Khazakunta 2009 (July) Operational 12 12 MBBR Khazakunta Lake Complying
20 Pragathi Nagar 2009 Operational 2.5 2.5 ASP Pragathi Nagar Lake Under Maintenance
21 Rangadhamuni 2012 Operational 5 4.5 ASP Into Rangadhamuni Complying
Cheruvu
22 Noor-Mohammed Kunta 2009 Operational 4 4 ASP + EA To noor Mohd Complying
Kunta Lake
23 Patel Cheruvu 2004 Operational 2.5 2.5 EA Patel Cheruvu Complying
Nacharam
24 Vikarabad Vikarabad Sakaliguda 2015 Operational 13 6 MBBR Reuse by Golf Club Complying
near Aalampally
25 Karimnagar Karimnagar Municipal 2019 Operational 38 2 MBBR Gopal Cheruvu Complying
Corporation
26 Miryalaguda Thallagadda Yet To be 11.5 0 ASP Thallagadda Yet to commission as
commisiioned Cheruvu sewer connections
are to be given
27 Miryalaguda Ramnagar Bandam Under 5.45 0 ASP Under construction
Construction
28 Nizamabad Dubba, Nizamabad 2020 Operational 31.5 6.5 MBBR Phulang vagu Complying

160
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance status
No Commissioning (Operational Capacity Utilization (UASB / sewage with (Comply / Non-
. / Non- of STP of ASP /OP / quantity comply / Partially
Operational / (In Installed SBR / MBR / Comply)
Under MLD) Capacity FAB etc.)
Construction (In MLD)
/ Proposed)
29 Yellamagutta 2020 Operational 15 2.5 MBBR Yellaiah tank Complying
30 Chintla Cheruvu at 2020 Operational 7.25 5 MBBR Chintla Cheruvu / Complying
Siddipet Mandapallivagu
Siddipet
31 Narsapur Cheruvu 2020 Under 11 0 SBR Narsapur Cheruvu Under Construction
Construction
32 Nalgonda Nalgonda 2020 Under 2.55 0 ASP Under Construction
Construction
33 Serilingampal Gopannapally Under 4.5 0 MBBR Proposed to Construction
Construction discharged into completed yet to
Gopanpally commission
Cheruvu
34 River Godavari at 2003 Non 4 0 OP River Godavari Not in Operational
Ramagundam Operational
Ramagundam
35 Malkapur on River 1998 Non 14 0 OP River Godavari Not in Operation
Godavari Operational
36 Bhadrachala Bhadrachalam near River 2000 Non 2 0 OP River Godavari Not in Operation
Godavari Operational
37 Mancherial River Godavari at 1998 Non 4 0 OP River Godavari Not in Operation
Mancherial Reddy Colony Operational

161
TRIPURA
Sl. City / Location of STP Date of Status Installed Actual Technology Use of Compliance
No. Town Commissioning (Operational Capacity Utilization (UASB / treated status
/ Non- of STP of ASP /OP / sewage (Comply /
Operational (In MLD) Installed SBR / MBR with Non-
/ Under Capacity / FAB etc.) quantity comply /
Construction (In MLD) Partially
/ Proposed) Comply)
1 Agartala Near Lanka October, 2016 Operational 8 1.5 SBR Watering Comply
Mura, W - 02, of city
Chandina Mura, parks,
Agartala, West gardens
Tripura roads etc

162
UTTAR PRADESH
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
Dhadhupura, Agriculture
2001 Operational 78 68.41 UASB Compliance
1 Agra (on land)
Budi ka Nagla, Oxidation Non-
2001 Operational 2.25 2.97 River Yamuna
2 Agra Pond Compliance
Oxidation Non-
Peelakhar, Agra 2001 Operational 10 9.74 River Yamuna
3 Pond Compliance
Devri Road,
(Bhimnagri), 2011 Operational 12 6.35 UASB River Yamuna Compliance
4 Agra
Jaganpur,
Agra Agriculture
Sikandarpur, 2011 Operational 14 13.39 UASB Compliance
(on land)
5 Agra
Sadarban, Agriculture
2013 Operational 40 18.73 UASB Compliance
6 Bichhpuri, Agra (on land)
Dhadhupura Agriculture
2014 Operational 24 18.91 UASB Compliance
7 (New), Agra (on land)
Sadarwan
2018 Operational 36 36 SBR Land/ Agra canal Compliance
8 (Bichpuri) New
Kalindi Vihar,
2014 Operational 4.5 4.5 UASB Karwan River Compliance
9 Agra
Khasra No. 634, ~2 MLD irrigation
Vill- Khedki, and ~9 MLD
Bijnor December, 2018 Operational 24 11 UASB Complying
Tehsil- Bijnor, discharged in
10 District- Bijnor water body (drain)
U.P. Jal Nigam
(13 MLD) STP
drain into Kali
Kannauj sewage treatment Operational 13 10 MBR Comply
River
plant, Jalalur,
11 Amara, Kannauj
STP, Mahilpur
Saharanpur 1998 Operational 38 38 UASB Discharge in river comply
12 Road
33 MLD, Sector-
Noida 2011 Operational 33 26 SBR 20 Comply
13 54, Noida
163
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
25 MLD, Sector-
2015 Operational 25 20 SBR 27 Comply
14 50, Noida
35 MLD, Sector-
2011 Operational 35 28 SBR 26 Comply
15 123, Noida
50 MLD, Sector-
Noida 2015 Operational 50 40 SBR 43 Comply
16 168, Noida
34 MLD, Sector -
2012 Operational 34 27 SBR 28 Comply
17 50 Noida
54 MLD, Sector-
2012 Operational 54 43 SBR 40 Comply
18 54, Noida
03 MLD, Pandav
2013 Operational 3 2.7 ASP - Comply
19 Nagar, Meerut
07 MLD,
Pallavpuram-1, 2012 Operational 7 6.5 ASP - Comply
20 Meerut
10 MLD, Lohiya
2010 Operational 10 2 ASP - Comply
21 Nagar, Meerut
15 MLD,
Shatabdinagar, 2010 Operational 15 4.8 ASP - Comply
22 Meerut
11 MLD,
MBBR
Pallavpuram-2, 2008 Operational 11 8 - Comply
Meerut Technology
23 Meerut
15 MLD,
Vedvyaspuri 2010 Operational 15 4.5 ASP - Comply
24 Meerut
06 MLD,
Rakshapuram, 2011 Operational 6 4.4 ASP - Comply
25 Meerut
06 MLD,
Shradhapuri-1, 2010 Operational 6 5.5 ASP - Comply
26 Meerut
06 MLD Sainik
2017 Operational 6 5.95 UASB - Comply
27 Vihar

164
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
5 MLD
Modipuram 2016 Operational 5 4.9 - - Comply
28 Tiraha
07 MLD, Sports
Goods Complex, 2012 Operational 7 4 ASP - Comply
29 Meerut
10 MLD, Ganga
Meerut 2011 Operational 10 3.8 SBR - Comply
30 Nagar, Meerut
72 MLD Garh
road (Jagriti 2018 Operational 72 65 SBR - Comply
31 vihar)
06 MLD,
Shradhapuri- 2012 Operational 6 5.6 ASP - Comply
32 Phase-2, Meerut
Muzaffar Discharged in Partially
Muzaffar Nagar 2002 Operational 32.5 2.0 OP
33 Nagar River Kali West Comply
USAB
STP, Bharwara 2011 Operational 345 345 345 Comply
34 Reacter
35 2002 Operational 42 FAB 56 Partially
STP, Daulatganj 14
36 2011 Operational 42 Technology Comply
Lucknow 37.5 MLD Awas
Partially
vikas Parishad Operational 37.5 12 SBR 5
Comply
37 STP
6.5 MLD Awas Partially
Operational 6.5 5 SBR 12
38 vikas Parishad Comply
Discharge in River
2007 Operational 29 25.89 FAB Ganga through Comply
39 drain
Prayagraj STP Salori
Discharge in River
2016 Operational 14 16 SBR Ganga through Comply
40 drain

165
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
Partially used for
irrigation/
1999 (60MLD) Operational 60 Activated Discharge in River Comply
STP Naini 60.89 sludge Yamuna through
41 process drain
2013
Operational 20 Comply
42 (20MLD)
Discharge in River
STP Rajapur 2013 Operational 60 79.21 UASB Ganga through Comply
43 Prayagraj drain
Discharge in River
STP Ponghat 2013 Operational 10 6.54 Bio tower Ganga through Comply
44 drain
Discharge in River
STP Numayadahi 2013 Operational 50 55 Bio tower Yamuna through Comply
45 drain
Discharge in River
STP Kodra 2013 Operational 25 29.4 Bio tower Ganga through Comply
46 drain
74 MLD,
Indirapuram, 2013 Operational 74 35-40 SBR Compliant
47 Ghaziabad
56 MLD, Trans
Hindon, Non-
2000 Operational 56 45-50 UASB
Indirapuram, Compliant
48 Ghaziabad
56 MLD,
Ghaziabad
Indirapuram, 2012 Operational 56 50-56 SBR GDA Park Compliant
49 Ghaziabad
56 MLD,
Dudahaida Vijay 2013 Operational 56 50-56 SBR Compliant
50 Nagar Ghaziabad
70 MLD Non-
2000 Operational 70 50-60 UASB
51 Dudahaida Vijay Compliant

166
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
Nagar Ghaziabad

56 MLD,
Irrigation, Farming
Govindpuram, 2014 Operational 56 11 SBR Compliant
and construction
52 Ghaziabad
56 MLD, Morty,
2018 Operational 56 14-16 SBR Compliant
53 Ghaziabad

Ghaziabad 30 MLD,
Not Non-
M.B.B.R, 2012 30 -- MBR --
Operational Compliant
54 Sadullabad, Loni
Irrigation, Farming
Bapudham 2014 Operational 56 1--2 SBR Compliant
55 and construction
5 MLD STP Green belts
2019 Operational 5 2--3 MBR Compliant
56 Tronica city, loni development

57 3 MLD Pilkhuwa 2015 Operational 3 1.9-2.5 UASB Compliant


6 MLD STP Garh
zone
2011 Operational 6 3.5 SBR Irrigation Compliant
Garhmukteshwar
58 Hapur Hapur
3 MLD Brijghat
zone
2011 Operational 3 1 SBR Irrigation Compliant
Garhmukteshwar
59 Hapur
Sultanpur Hathia Oxidation Not
Sultanpur Operational 5 5 None
60 Nala Pond complying
Not
Pratapgarh Pratapgarh 2014 8.95 8.95 FAB
61 Operational

167
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
Discharge into
River Ganga Partially
STP Goithaha 19-02-2019 Operational 120 30 SBR
through Sharda Complying
62 Canal
Discharge into
STP Dinapur 140 Partially
11-11-2018 Operational 140 85 ASP River Ganga
MLD Complying
63 Varanasi through Varuna
STP Dinapur 80 Discharge into Partially
1994 Operational 80 80 ASP
64 MLD River Ganga Complying
Discharge into Partially
STP DLW 6-4-1989 Operational 12 8 ASP
65 River Ganga Complying
Discharge into Partially
STP Bhagwanpur 1989 Operational 9.8 9.8 ASP
66 River Ganga Complying

67 Ayodhya Ayodhya 2014 Operational 12 6 UASB 6-7 MLD Comply


14 MLD STP
Discharge in River Partially
Pakka Pokhra, 1994 Operational 14 1 UASB
Ganga Comply
68 Mirzapur
Sonbhadra
4 MLD STP
Oxidation Discharge in River Partially
Vindhyachal, 2008 Operational 4.0 0.63
Pond Ganga Comply
69 Mirzapur
Not Oxidation Not
Karvi Chitrkoot 2.92
70 Operational Pond Operational
Banda
Kanwara Road, Not Not
2010 4.0 3.6 OP Land
71 Banda Operational Obtained
Not
Chitrakoot Sitapur Gramin 2000 Operational 3.46 3.46 OP River & Field
72 Obtained
Not
Moradabad 20
73 Moradabad Operational
74 Moradabad 2018 Operational 58 18 SBR NO NO
75 2015 Operational 15 0.07 UASB NO NO
Rampur Rampur
76 2016 Operational 14 0.11 UASB NO Yes

168
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
Partially
2016 5 0.003 SBR NO NO
77 Operational
0.805 MLD,
Ahara Road, Oxidation
2003 Operational 0.805 0.25 For Irrigation Comply
Zone-A, Pond
78 Anoopshahar
1.75 MLD, Ahara
Oxidation
Road, Zone-B, 2003 Operational 1.75 0.75 For Irrigation Comply
Pond
79 Anoopshahar
04 MLD Narora
2015 Operational 4 2 SBR In River Comply
80 (NGRBA)
Bulandshahr
2.25 MLD,
Activated
Narora Atomic
2000 Operational 2.25 1 Sludge In River Comply
power Station
Process
81 Narora Township
1.5 MLD
MBBR
Anoopshahar 2016 Operational 1.5 1.25 For Irrigation Comply
Technology
82 Zone A (NGRBA)
STP, Zone-B MBBR
2016 Operational 1 0.75 For Irrigation Comply
83 Anoopshahar Technology
30 MLD STP,
Near Manayar
Kashiram Sahri
Partially
Garib Avas 01.02 2015 Operational 30 24 SBR –
Comply
Yojna, Deoria By
Pass Road,
84 Gorakhpur Gorakhpur.
15 MLD STP,
Maherwa ki bari,
Near Mahadev Partially
01.06.2015 Operational 15 15 SBR –
Jharkhandi, Comply
Kunraghat,
85 Gorakhpur.

169
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
40 MLD Treated
Effluent of either
210 MLD STP
Bingawan or 42
210 MLD at MLD Sajari is Partialy
2015-16 Operational 210 145 UASB
Bingawan proposed to be Comply.
used in Panki
Power Plant
Establish in
86 Kanpur Hamirpur Road.
Total
42 MLD at Sajari 2016-17 Operational 42 30 ASP
87 Comply
05 MLD at Under
1989-90 Operational 5 - UASB Irrigation
88 Jajmau Maintenance
130 MLD at Total
1998-99 Operational 130 105 ASP Irrigation
89 Jajmau Comply
43 MLD at Total
Operational 43 35 ASP Irrigation
90 Jajmau Comply
Some part of
treated effluent is
used in agriculture Total
Fatehgarh Fatehgarh 1992-93 Operational 2.7 2.7 WSP
& remaing treated Comply
effluent sent to the
91 river Ganga.
as per jal Nigam
infromation
Waste approx 10.445
STP near Tixi
Etawah 2001 Operational 10.445 10.445 Stabilization MLD treated Complied
Tempel
Pond sewage is
discharge into
92 river yamuna

170
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
as per jal Nigam
infromation
STP at Mauja Not Not
2013 13.5 3 WSP approx 3MLD
Umrain Operational Complied
treated sewage is
93 for irrigation
as per jal Nigam
infromation
approx 10.4MLD
treated sewage is
discharge into near
STP at Mauja Partially
Mainpuri 2014 Operational 23.0 10.4 UASB Based by kharja nala
Odenya, Padaria Complied
which terminates
in ishan River
ganga and this
river merges into
94 Ganga
as per jal Nigam
infromation
Partially
Safai Safai 2013 Operational 1.6 1.6 SBR approx 1.6MLD
Complied
treated sewage is
95 used for plantation
ASP+
Not Not
Firozabad 2020 67 ---- exended
Operational Complied
96 areation
As per jal kal
Vibhag nagar
nigam infromation
Firozabad approx -3MLD
treated sewage is Non
Firozabad 2014 Operational 3 3 UASB
used by complied
horiculture
department for
irrigation of
97 Plantation/ trees

171
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
No. Commissioning (Operational Capacity Utilization (UASB / Sewage with Status
/ Non of STP of installed ASP / OP / Quantity (Comply /
Operational / (In Capacity SBR /MBR / Non
Under MLD) (In MLD) FAB etc.) Comply)
Construction
)
2.0 MLD Greater
Noida Authority
2015 Operational 2 2 SBR NA Comply
STP, Vill-
98 Badalpur
Greater 137 MLD,
Noida Kasana, 2015 Operational 137 50 SBR NA Comply
99 GreaterNoida
ECOTECH-2 2018 Operational 15 8 SBR NA Comply
100
ECOTYECH-3 2018 Operational 20 10 SBR NA Comply
101
Oxidation Partially
Masani 2007 Operational 13.59 8 08 MLD
102 Pond Comply
Mathura
Oxidation Partially
Trans Yamuna 2007 Operational 14.5 7 07 MLD
103 Pond Comply
Not Oxidation
Vrindavan Near Pagal Baba 2007 4 - - -
104 Operational Pond
Partially
Mathura Trans Yamuna 2015 Operational 16 6 UASB 06 MLD
105 Comply
Vrindavan (Near Partially
Vrindavan 2015 Operational 8 4 UASB 04 MLD
106 100 Bed Hospital) Comply
Oxidation Partially
Goverdhan Goverdhan 2011 Operational 2.76 1.35 1.35 MLD
107 Pond Comply

172
UTTARAKHAND
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)
Banni Gaon, 2017 0.18 ·
Operational 0.26 SBR
1 Badrinath '. Comply
Near 2019
Temple, Operational 0.01 0.01 MBBR
2 Bad~inath. Comply
Badrinath (Near 2019
suspension Under Trial 1 - SBR
3 Bridge) Comply
Joshimath 2019
Operational 1.08 0.421 SBR
4 (Pokhri) Comply
Gopeshwar 2018 Electro
Operational 0.76 0.037
5 (ChamoliGhat) Coagulation Comply
Gopeshwar 2018
(Near old
Electro
Suspension Operational 0.05 0.007
Coagulation
Bridge),
6 Chamoli Chamoli Comply
Gopeshwar 2019
Electro
(Vivekanand Under Trial 1.19 -
Coagulation
7 Colony) Comply
Gopeshwar 2019
Electro
(DeenDayalUpa Under Trial 1.12 0.075
Coagulation
8 dhyak ) Comply
Gopeshwar 2019 Electro
Under Trial 1.25 -
9 (Pokhari Band) Coagulation Comply
Nandprayag 2018 Electro
Operational 0.05 0.002
10 (Sangam Road) Coagulation Comply
Nandprayag 2018 Electro
Operational 0.1 0.002
11 (Forest Office) Coagulation Comply
2018
karan Prayag Electro
Operational 0.05 0.05
(Police Chowki) Coagulation
12 Comply

173
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)

karan Prayag 2018 Electro


Operational 0.1 0.01
13 (Purana Pull) Coagulation Comply
karan Prayag 2018
Electro
(Ward number Operational 0.1 0.025
Coagulation
14 Chamoli 1 &3) Comply
karan Prayag 2019
Electro
(Subhash Operational 0.05 0.02
Coagulation
15 Nagar) Comply
karan Prayag 2019 Electro
Operational 0.05 0.02
16 (Naya Pull) Coagulation Comply
Rudraprayag 2019
(Near Non Electro
0.075 -
AnoopNegi Operational Coagulation
17 School ) Comply
Rudraprayag 2019
Non Electro
(Near Rudra 0.1 0.1
Operational Coagulation
18 Complex) Comply
Rudraprayag 2019
Electro
(Near Bus Operational 0.075 0.009
Rudraprayag Coagulation
19 Stand) Comply
Rudraprayag 2019
Electro
(Near SB! Operational 0.1 0.009
Coagulation
20 Maszid) Comply
Rudraprayag 2019
(Near Steel
Electro
Bridge & Operational 0.125 0.125
Coagulation
Syndicate Bank
21 ) Comply
Kirtinagar (BRO 2018
Operational 0.05 0.024 MBBR
22 Bridge) Comply
Kirtinagar 2018
Operational 0.01 0.01 MBBR
23 Tehri Garhwal (Near Temple) Comply
Bhagirathipura 2006
m, Operational 5 2.5 SBR
24 TehriGarhwal Comply
174
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)

Chorpani, Muni
ki Reti,
Under Trial 5 3.2 MBBR
Dhalwala,
25 Rishikesh Comply
7.50 MLD STP
at
Chandreshwar
Under Trial 7.5 3.5 MBBR
Ghat, Muni
kiReti,Dhalwala
Tehri Garhwal
26 , Rishikesh Comply
3.5 MLD STP at 2016
Tapovan, Operational 3.5 0.893 SBR
27 Rishikesh Comply
0.075 MLD STP 2017
at shanti bazar, operational 0.075 0.012 SBR
28 Devprayag Comply
Sangam bazar, 2017
operational 0.15 0.121 SBR
29 Devprayag Comply
Baah Bazar, 2016
operational 1.4 0.039 SBR
30 Devpravag Comply
Gyansu, 2012
Uttarkashi operational 2 1.783 MBBR
31 Uttarkashi Comply
Gangotri,
operational 1 0.2 SBR
32 Uttarkashi Comply
SriNagar, Pauri 2009
operational 3.5 1.645 MBBR
33 Garhwal Comply
Srinagar, Pauri 2019
operational 1 0.248 SBR
34 Pauri Garhwal Garhwal Comply
Swargashram, 2010
Rish'kesh, Pauri operational 3 2.254 SBR
35 Garhwal. Comply
Lakkarghat, 2020
Dehradun Under Trial 26 10.8 SBR
36 Rishikesh Comply
Jagjeetpur, 2010
Haridwar Operational 27 26.68 SBR
37 Haridwar Comply
175
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)
Jagjeetpur, 1990
Operational 18 18.3 SBR
38 Haridwar Comply
Jagjeetpur, 2020
Operational 68 44.01 SBR
39 Haridwar Comply
Haridwar
Sarai, Haridwar 2013 Operational 18 18 SBR
40 Comply
41 Sarai, Haridwar 2013 Operational 14 13 SBR Comply
42 Saliyar, Roorkee Operational 33 - SBR Comply
Motharawala-1, 2016
Operational 20 13.52 SBR
43 Dehradun Comply
Motharawala- 2018
Operational 20 11 SBR
44 11, Dehradun Comply
Kargi, 2015
Operational 68 13 SBR
45 Dehradun Comply
Vijay Colony, 2019
Operational 0.42 0.3 SBR
46 Dehradun Partially Comply
Salawala, 2019
Operational 0.72 0.35 SBR
47 Dehradun Comply
Indira Nagar, 2019
Operational 5 5 SBR
48 Dehradun Comply
Dehradun Jakhan: 2016
Operational 1 0.35 SBR
49 Dehradun Comply
Bhattafall, 2019
Operational 3.12 0.5 SBR
50 Mussoorie Comply
Happy Vally, 2019
Mussoorie. Operational 1.2 0.2 SBR
51 Mussoorie. Comply
Landour, South, 2019
Operational 1.3 0.25 SBR
52 Mussoorie. Comply
Landour, North, 2019
Operational 0.8 0.3 SBR
53 Mussoorie. Comply
Kulri Bazaar, 2019
Operational 0.9 0.35 SBR
54 Mussoorie Comply
55 Nainital Hari Nagar, 2016 Operational 0.45 0.25 SBR Comply

176
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)
Nainital
Krishna Nagar, 2016
Operational 0.8 0.45 SBR
56 Nainital Comply
Rusi Pond, 2009 Sedimentaio
Nainital Operational 10 6.75
57 Nainital n Tank Comply
Bheemtal, 2009
Operational 1.25 1 UASB
58 Nainital Comply
59 Almora Almora 2004 Operational 2 1.65 MBBR Comply
Acholi, 2020
Operational 5 1 SBR
60 Pithoragarth Comply
Pithoragarth
Mirada, 2020
Operational 1.25 0.8 SBR
61 Pithoragarth Comply
under
Dehradun Kolagarth 3 -
62 Consruction Not Applied
Marwari, under
Chamoli 2.7 -
63 Joshimath Consruction Not Applied
Belani,Rudrpra under
Rudraprayag 0.05 -
64 yag. Consruction Not Applied
junior,srikot, under
0.075 -
65 Shrinacar Consruction Not Applied
Pouri garhwal
Taulia,srikot under
0.05 -
66 ,Shrinagar Consruction Not Applied
STP-1 at under To river rejuvenation
7 -
67 Ramnagar Consruction of Kosi River
STP-2 at under To river rejuvenation
1.5 -
68 Ramnagar Consruction of Kosi River
Nainital
under
Haldwani 28 -
69 Consruction Not Applied
Narayan Nagar, under
0.45 -
70 Nainital Consruction Not Applied
under To river rejuvenation
U.S Nagar Kashipur 18 -
71 Consruction of Dehlla River

177
Sl. City / Town Location of STP Date of Status Installed Actual Technology Use of Compliance Status
No. Commissioning (Operational / Capacity Utilization (UASB / treated (Comply / Non
Non of STP (In of installed ASP / OP / Sewage Comply)
Operational / MLD) Capacity SBR /MBR / with
Under (In MLD) FAB etc.) Quantity
Construction)
Proposed under river
Kashipur, STP. Proposed 10 - rejuvenation of Dehlla
72 River
Proposed under river
Mukhandpur,
Proposed 0.31 - rejuvenation of Dehlla
Kashipr
73 River
Proposed under river
Gularia,
Proposed 0.14 - rejuvenation of Dhella
Kashipr
74 River.
Proposed under river
Jaspur Kurd,
Proposed 1.55 - rejuvenation of Bhella
Kashipr
75 River.
Proposed under river
Hempurlsmile Proposed 0.14 - rejuvenation of Bhella
76 River.
U.S Nagar Proposed under river
Beljuri, Kashipr Proposed 0.31 - rejuvenation of Kosi
77 River.
Proposed under river
Bazpur STP. Proposed 8.5 - rejuvenation of
78 Pilkahar River.
Proposed under river
Rudrapur STP-
Proposed 26 - rejuvenation of
1.
79 Kalyani River.
Proposed under river
Rudrapur STP-
Proposed 18 - rejuvenation of
2.
80 Kalyani River.

Kichha, Proposed under river


Proposed 2 - rejuvenation of Kichha
Rudrapur
81 River.

178
WEST BENGAL
Sl.No. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
Commissioning (Operational / Capacity Utilization (UASB / Sewage with Status (Comply
Non of STP of ASP / OP / Quantity / Non Comply)
Operational / (In installed SBR /MBR /
Under MLD) Capacity FAB etc.)
Construction) (In MLD)
1. Jagaddal Bhatpara 2013(April) Operational 31 FABS Comply
2. Jagaddal Bhatpara Jagaddal Bhatpara 2013(April) Operational 10 FABS Comply
3. Jagaddal Bhatpara 2013(April) Operational 9.5 24.1 ASP Comply
4. Kankinara Kankinara 2013(April) Operational 10 WSP Comply
5. Kalyani Kalyani 2014 (February) Operational 11 TF Comply
19
6. Kalyani Kalyani 2014 (November) Operational 10 WSP Comply
7. Gayeshpur Gayeshpur Partially
2020 (June) Operational 8.33 3.2 SBR Comply
8. Baidyabati Baidyabati Partially
2020 (June) Operational 6 5 AL Comply
9. Bhadreswar Bhadreswar Partially
2020 (July) Operational 7.6 5.5 AL Comply
10. Chandannagore Partially
2020 (July) Operational 18.16 14.5 TF Comply
Chandannagore
11. Chandannagore Partially
2020 (July) Operational 4.5 4.5 OP Comply
12. Bansberia Bansberia Partially
2020 (July) Operational 0.3 0.3 ASP Comply
13. Konnagar Konnagar Partially
2019 (December) Operational 22 12 OP Comply
14. Naihati Naihati Partially
2019 (December) Operational 11.56 7 ASP Comply
15. Titagarh Titagarh 2016 (January) Operational 9 8.5 ASP
16. Budge Budge Budge Budge Under
2016 (October) Construction 9.33 0 SBR
17. Barrackpore Barrackpore Under
2015 (December) Construction 24 0 SBR
18. Halisahar Halisahar Under
2019 (March) Construction 16 0 SBR
19. Nabadwip Nabadwip
Under
2019 (September) Construction 9.5 0 SBR

179
Sl.No. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
Commissioning (Operational / Capacity Utilization (UASB / Sewage with Status (Comply
Non of STP of ASP / OP / Quantity / Non Comply)
Operational / (In installed SBR /MBR /
Under MLD) Capacity FAB etc.)
Construction) (In MLD)
20. Kancharapara Kancharapara Under WSP /
2020 (February) Construction 18 0 Tertiary
21. Baharampore Baharampore Under
2020 (February) Construction 3.5 0 SBR
22. Jangipur Under
2020 (February) Construction 8 0 SBR
Jangipur
23. Jangipur Under
2019 (December) Construction 5 0 SBR
24. Bandipur (Khardaha) Bandipur
(Khardaha) Non-
2020 (July) Operational 14 0 WSP
25. Champadani Champadani Non-
2019 (December) Operational 1 0 AL
26. Garulia Garulia Non-
2019 (December) Operational 7.9 0 OP
27. Naihati Naihati Non-
2019 (December) Operational 6.5 0 WSP
28. Panihati Panihati Non- Low Cost
2020 (July) Operational 12 0 STP
29. Serampore Serampore Non-
Operational 18.6 0 TF
30. Balli (Kona) Balli (Kona) Non-
Operational 62 0 WSP
31. Howrah Howrah Non-
Operational 65 0 TF
32. Kamarhati - Kamarhati - Non-
Baranagar Baranagar Operational 60 0 TF
33. Maheshtala Maheshtala Proposed 35 0 SBR
34. Hooghly-Chinsurah Hooghly-Chinsurah Proposed 29.3 0 SBR
35. North-Barracpore North-Barracpore Proposed 17.75 0 SBR
36. Ranaghat Proposed 4 0 SBR
37. Ranaghat Ranaghat Proposed 5.2 0 SBR
38. Ranaghat Proposed 2.6 0 SBR

180
Sl.No. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
Commissioning (Operational / Capacity Utilization (UASB / Sewage with Status (Comply
Non of STP of ASP / OP / Quantity / Non Comply)
Operational / (In installed SBR /MBR /
Under MLD) Capacity FAB etc.)
Construction) (In MLD)
39. Bangur STP Kaji Bangur STP Kaji Constructed by
Nazul Islam Sarani, Nazul Islam Sarani, KMDA in the year
Lake Town, Kolkata- Lake Town, 1993 and
700055 Kolkata-700055 augmented by
KEIP in the year Partially
2011 Operational 52 26 ASP Nil Comply
40. Gardenreach STP Gardenreach STP Constructed by
Taratala Road, Taratala Road, KMDA in the year
Santoshpur, Kolkata- Santoshpur, 1997 and
700066 Kolkata-700066 augmented by
Kolkata
Environmental
Improvement
Project (KEIP) in Non- Partially
the year 2011 Operational 57 0 ASP Comply
41. South- suburban South- suburban Constructed by
(Keorapukur) (Keorapukur) KEIP in the year
Dhalipara, Dhalipara, 2010. [Again
Haridevpur, Kolkata- Haridevpur, rejuvinated by Partially
700104 Kolkata-700104 KEIIP in 2020] Operational 45 36 AL Nil Comply
42. Baghajatin STP Baghajatin STP Constructed by
Baghajatin Rail Baghajatin Rail KMDA in the year
Bridge, E.M Bye-pass, Bridge, E.M Bye- 1994 and handed
Kolkata pass, Kolkata over to KMC in Non- Partially
the year 2010 Operational 15 0 AL Nil Comply
43. Hatisur STP Santi Hatisur STP Santi Constructed by
Pally, Kasba, Kolkata- Pally, Kasba, KMDA in the year
700107 Kolkata-700107 2004 and handed
over to KMC in Partially
the year 2012 operational 10 8 OP Nil Comply
44. At Rajpur-Sonarpur, At Rajpur- Under
Rania Sonarpur, Rania 2023 Construction 30 0 SBR
45. Near WBSETCL, Joka Near WBSETCL, Under
Joka 2022 Construction 45 0 SBR
46. At Bank Plot, M.G At Bank Plot, M.G
2022 Under 40 0 SBR
181
Sl.No. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
Commissioning (Operational / Capacity Utilization (UASB / Sewage with Status (Comply
Non of STP of ASP / OP / Quantity / Non Comply)
Operational / (In installed SBR /MBR /
Under MLD) Capacity FAB etc.)
Construction) (In MLD)
Road Road Construction

47. Police Telecom Police Telecom


Department Land, Department Land,
near Wireless Park near Wireless Park Proposed 15.3 0
48. Near Golf Garden, Near Golf Garden,
Sukhapukur Sukhapukur Proposed 5.06 0
49. Near Kavi Nazrul Near Kavi Nazrul
Metro Station, Birji Metro Station, Birji
Road Road Proposed 5.7 0
50. STP Near L.S 10 STP Near L.S 10 Proposed 16 0 SBR
51. STP Near At STP Near At
SurinaamGhat, SurinaamGhat,
DhankhetiNikashi DhankhetiNikashi Proposed 25 0 SBR
52. STP Near STP Near
BhangaKhal, BhangaKhal,
Gardenreach area Gardenreach area Proposed 35 0 SBR
53. Proposed STP for Proposed STP for
Borough-XII Borough-XII Proposed 70 0
54. New Town, Rajarhat, New Town,
Kolkata Action Area- Rajarhat, Kolkata
IIB Action Area-IIB 2011 (December) Operational 14 11 ASP Gardening Comply
55. New Town, Rajarhat, New Town,
Kolkata Action Area- Rajarhat, Kolkata
IIC Action Area-IIC 2011 (December) Operational 31 20 ASP Gardening Comply
56. New Town, Rajarhat, New Town, To be
Kolkata Action Area- Rajarhat, Kolkata Under completed by
IIID Action Area-IIID Construction 24 0 SBR 31/10/2020
57. Tarapith Birbhum Tarapith Birbhum To be
District Tarapith District Tarapith Under completed by
Temple Temple Construction 4.25 0 ASP 30/06/2021
58. Nabadwip Fansitala Nabadwip Fansitala Land disposal &
Ghat Ghat Pisiculture by Partially
1995 Operational 10 6.72 OP Municipality Comply

182
Sl.No. City / Town Location of STP Date of Status Installed Actual Technology Use of treated Compliance
Commissioning (Operational / Capacity Utilization (UASB / Sewage with Status (Comply
Non of STP of ASP / OP / Quantity / Non Comply)
Operational / (In installed SBR /MBR /
Under MLD) Capacity FAB etc.)
Construction) (In MLD)
59. Diamond Harbour Diamond Harbour
Near Diamond Near Diamond
Harbour Harbour
Police Station Police Station Discharge to Partially
2013 Operational 2.03 0.2 OP nearby canal Comply
60. Katwa Municipality Katwa Municipality Partially
2011 Operational 2.36 2.36 ASP Gardening Comply
61. Behrampore Behrampore Non-
Indraprastha Indraprastha Operational 3.7 0 OP
62. Murshidabad Ward Murshidabad Ward Partially
No 2 Lalbag No 2 Lalbag 2010 Operational 1.96 0.283 OP Gardening Comply
63. JiaganjAjimganj JiaganjAjimganj 2009 Handed over
Takia, Jiaganj Takia, Jiaganj to Jiaganj-
Azimganj Non-
Municipality Operational 1.39 0 OP
64. Siliguri Left Bank of Siliguri Left Bank of
Mahananda River Mahananda River Proposed 15 0 WSP
65. Siliguri Jorapani And Siliguri Jorapani
Fuleshwari And Fuleshwari
River River Proposed 24 0 WSP

183