Ask - Wo-22.2672-Method-Swc-004 - Work Method Concrete Wall Rev.03
Ask - Wo-22.2672-Method-Swc-004 - Work Method Concrete Wall Rev.03
Ask - Wo-22.2672-Method-Swc-004 - Work Method Concrete Wall Rev.03
PREPARED FOR
CONTRACTOR
2 04-05-23 Issued for Approval MRB MJK DNP PT. Linde Indonesia
Date :
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
2 8-9 24-03-23 Add section Drawing, Add flowcharts, Add Shown Scaffolding Access
3 10 - 11 04-04-23 add drawing Section A -A displays parts 1 and 2, Explains the items on
drawing in detail, add Drawing 3D Model In Facility Mac Blow
4 12 04-04-23 Explains in detail the casting concrete Sub Bab, adds a work description sub-
Bab, adds a drawing formwork point lifting
6 9-10 11-04-23 improved the flowchart, explains in detail the base stand point formwork
Page 2 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
TABLE OF CONTENT
Page 3 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
1. Scope Of Work
This procedure covers the requirements of PT Linde and PT Asuka Engineering Indonesia Jawa
LG – TSF Project and Civil Construction Works regarding the work of the high concrete wall
casting method in several facilities, namely:
2. Reference
The requirements contained in the last edition of the regulations and standards below is a unity
with the requirements of this specification way and to the limit specified here.
- SNI 03-4810-1998, Method for Molded and Cured Concrete Testing Specimen at Field
- OHSA 1926
Linde Standards
_LDI-CA00-C-SP 2009.102_RevB_SPECIFICATION
3. Definitions
COMPANY : PT. Linde Indonesia
CONTRACTOR : PT. Asuka Engineering Indonesia
SUB-CONTRACTOR : The company that manufactures or supplies equipment and services
to perform duties specified by CONTRACTOR. "VENDOR" covers
Manufacturer/ Supplier/Sub-vendor.
4. Responsibilities
1) Project Manager
2) Construction Manager
3) Project Engineer
4) QA/QC Inspector
5) HSE Manager
7) Surveyor
9) Lifting Supervisor
1. Ensuring that the project works in his zone are carried out in accordance with
Company policies and in accordance with the requirements of this Quality plan.
2. Ensuring the full compliance of subcontractors with Company Quality policies and
with the requirements of this Quality plan.
Page 5 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
3. To ensure that all the equipment required to execute the works according to the
construction programme are available, in good condition, and provide any
additional equipment that might be required.
4. To co-ordinate with the Construction Manager, Project Engineer, Safety Engineer,
Foreman and Surveyor for a safe and proper execution of the works.
5. To guide specific attention to all safety measures in co-ordination with the safety
officer/engineer.
1. The engineer shall carry out his duties in a manner that shall be co-ordinated by
the project manager on a daily basis, and shall ensure proper distribution of the
workforce and equipment at required locations.
2. To be aware of test frequencies related to the formation level.
3. To control disposal of waste excavated material according to the instructions
received from the Project Manager.
4. To co-ordinate with the Safety Officer to maintain safe working and proper
housekeeping of the site. To comply with the safety measures and ensure that all
Safety Officer Teams are aware of the same to prevent accident and loss.
5. To monitor and check all activities and ensure that works shall be carried out
according to specifications, quality and approved drawings.
6. To inform the QC Inspector of the areas ready for inspection.
Page 6 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
4.5. Surveyor
Page 7 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
5. To give special concern to housekeeping, and ensure that the site is maintained
clean and tidy.
6. To ensure all the relevant safety sign boards for different works are in place.
1. Ensure the works are progressed in the sequence as agreed with the Project
Manager.
2. Liaise with the Project / Construction Manager for the allocation of the work force,
ensuring adequate manpower is available.
3. Liaise with the site manager to ensure all the required plant / materials are available
to construct the works.
4. Full time supervision shall be required to ensure the works are carried out in
accordance to specifications, quality and approved drawings
Page 8 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
START
REBAR INSTALLATION
FORMWORK INSTALLATION
POURING CONCRETE
NEXT SECTION
TOP SECTION
FINISH
Page 9 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
- Worker has pass working at height training and have sticker WAH training in safety Helmet
- Full body Harness Double lanyard must be use ( if the height more than 6.25 m should have
absorber)
- Worker who involve at working at height should be conduct Dailiy check up (DCU) by Medic
( nurse)
In the installation of scaffolding, the work is divided into several sections, each section
having a height of 3 - 4 m according to the height of the building. Installation of scaffolding
around the building as much as 3 scaffolding shafts. for the distance between the building
and scaffolding as wide as 1/2 meter
Page 10 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
Page 11 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
At this stage the installation follows the size of the plywood, which is 2000 mm x 1120 mm
x 18 mm which will be arranged vertically. the installation is arranged in a maximum of 2
plywood in a vertical direction and a horizontal direction following according to the width of
the building.
1. Rebar is installed with a 6m persection and then given a spacer to maintain the distance
between the 2 main bars and installed concrete decking and formwork to maintain
verticality
2. The formwork is given a tierod to hold the panel but before being assisted using a
support that is plugged into the ground, for a height of above 3m, the formwork is
supported using iron that is plugged into the previous section.
3. In each section, the tie rod that is at the top is given a wire rope to maintain the
stability of the formwork and its verticality
4. For manhole holes use the opening listed on the Drawing forcon for access, a
minimum of 60 cm x 60 cm according to the opening of the building. for the location
adjust the opening point (according to the Drawing forcon ). if there is no opening in
the forcon drawing then we make a manhole and it will be closed with grouting after
casting at the highest elevation and finishing has been done.
5. The process of lifting the formwork is divided into 2, namely manually and using a
crane. if manual lifting, formwork will be assembled one by one on top of the building.
if using a crane, the formwork has been assembled below and then lifted to be
installed.
Page 12 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
At the casting stage using a concrete pump to support the work and can reach all areas.
During the concrete filling stage, the entire area must be filled to a maximum height of 1
meter before continuing at the next height so that the results of casting can produce
maximum results. The concrete pump must pour the concrete gradually in one pouring. Use
an external vibrator for each layer pouring to assist the internal vibrator. Concrete is poured
over the top of the formwork using a 3'' dim tremy pipe and placed at the pour point so that
the concrete spreads evenly.
Page 13 of 14
Java LG Project-TSF and Civil Construction Work
TEMPORARY SITE FACILITY METHOD STATMENT
We have several scope for our Concrete Wall Section Facility, therefore;
Page 14 of 14