ARCHITECTURAL WORK
AEI-CVL-MES-0153-0017
PREPARED FOR
CONTRACTOR
Sign :
Date :
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
Page 2 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
TABLE OF CONTENT
REVISION LOG REGISTER ...................................................................................................................2
TABLE OF CONTENT ............................................................................................................................ 3
1. Scope Of Work ................................................................................................................................. 4
2. Reference ......................................................................................................................................... 4
3. Definitions ......................................................................................................................................... 5
4. Responsibilities ................................................................................................................................. 5
4.1. Project Manager...................................................................................................................... 5
4.2. Construction Manager ............................................................................................................ 6
4.3. Site Engineer .......................................................................................................................... 6
4.4. QA/QC Engineer / Inspector ................................................................................................... 6
4.5. Surveyor .................................................................................................................................. 7
4.6. HSE Engineer/Officer ............................................................................................................. 7
4.7. Foremen/ Works Supervisor ................................................................................................... 7
5. Architectural Section Support of Contractor ..................................................................................... 7
5.1. Work Description..................................................................................................................... 7
We have several scope for our Architectural Section Facility, therefore; ....................................... 8
5.2. Manpower, Material, Equipment, Personal Protective Equipment Requirement ................... 8
5.3. Procedure / Method Implemented ........................................................................................ 10
Page 3 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
1. Scope Of Work
This procedure covers the requirements on PT Linde and PT Asuka Engineering Indonesia that
must be implemented to Java LG Project – TSF and Civil Construction Work. And the scope is
at listeb building below;
a. Machine House
b. Administration / Multipurpose Building
c. Workshop and Warehouse
d. Driver Shelter
e. Oil Storage
f. Guardhouse
g. Refuse Chamber
h. Chemical Storage
i. Motorcycle Shed & Smoking Area
j. Car Parking Area & Shading
k. Emergency Diesel
l. LV & MV Substation
m. Transformer
n. Chemical Dozing Shelter
2. Reference
The requirements contained in the last edition of the regulations and standards below is a unity
with the requirements of this specification way and to the limit specified here.
Page 4 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
Linde Standards
_LDI-CA00-C-SP 2009.102_RevB_SPECIFICATION
&ASU W-TB 9215 (EN) ITP Civil Finishing Works
3. Definitions
COMPANY : PT. Linde Indonesia
CONTRACTOR : PT. Asuka Engineering Indonesia
SUB-CONTRACTOR : The company that manufactures or supplies equipment and services
to perform duties specified by CONTRACTOR. "VENDOR" covers
Manufacturer/ Supplier/Sub-vendor.
4. Responsibilities
Group / person who will be responsible in the site is listed bellow :
1) Project Manager
2) Construction Manager
3) Project Engineer
4) QA/QC Inspector
5) Safety Officer
6) Foremen / Work Supervisors
7) Equipment Operators
8) Skilled and unskilled labourers
Page 6 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
4.5. Surveyor
1. To establish benchmarks from agreed reference points, provide required
setting out and level markings and follow up with regular checks.
2. Co-ordinate with the Project Engineer / Foreman and ensure the approved
shop drawings/construction drawings shall be implemented properly.
3. Maintain survey details and reports, periodically check the progressing
works and advise the project manager of any deviation from the drawings.
Page 8 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
Plastic
Plywood
Floor Raising panels
pedestals
8) In Railing
Railing Platform
Dynabolts
Painted Zynchromate
9) In Grating
Gratings Platforms
10) In Ladder
Ladder
Steel
Pipe Steel
11) In Ceiling work
Hanger
Screw
Galvalume
Gypsum-board, Akustic-board, etc.
b) Equipment (listed below but not limited to)
1) In Setting Out and Preparation
Total Station,
Precision Automatic Levels,
Optical Plummet,
Laser Plummer
2) In Concrete Block Wall,
Buket
Shovel;
Hoe
Hose
Sandfilter
thread
3) In Plastering and rendering work
Bucket,
Shovel,
Hoe,
Raskam,
Hose,
Sandfilter,
4) In painting work.
Page 9 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
Paint roll,
Bucket
Hammer
Hand Steel trowel
5) In Ceramic tiles
Shovel
Rubber hammer
Paint brush;
6) In Epoxy Coating tiles
Roller
Broom
7) In Floor Hardener
Steel Trowel
8) In Raising Floor
Broom
Roll meters
9) In Railing Platform
Welding machine
Waterpass
Grinding machine
Meter
Hammer
Chisel
Wrench
10) In Ladder
Bolts
Dyna-bolts
11) In Ceiling work
drill,
screw,
Page 10 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
4) In Painting work,
a. Interior painting
Sanded and cleaned wall surface, traces of cement.
Wall surfaces that are not good enough to be repaired locally.
First coat of rolling Alkaline Primer (prime coat) wait until it dries
Second layer of inner wall paint roll (layer 1)
Page 11 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
Page 12 of 13
Java LG Project-TSF and Civil Construction Work
ARCHITECTURAL METHOD STATMENT
c. Mark the position of the railing pole and check the slope of the stairs in the field
against the working drawings.
d. Check its connection with other works such as stairs, position against
embankments, walls and others.
e. Installation of railing to the floor can use anchors that have been prepared
beforehand or use dyna-bolts or be welded to ring beams.
f. Installation of stair railing pipe/plate connections by welding or bolts
g. Inspection of the results of the installation
h. Clean up the welded joints or bolts with a grinder then caulking and sanding them
until they are even and smooth
i. Railing is painted with zinc-chromate, after it is dry then do the finishing painting
10) In Grating
a. The top of the Grating must be installed flush with the concrete beside it
This is so that the load that passes through it does not occur shock
b. The foundation concrete at the bottom of the grating must be level or the same
height. The concrete foundation of the grating is made sturdy so that it can
withstand grating loads and also the loads that pass through it
11) In Ledder
a. Prepare Outdoor ladder w/ cage material
b. Drill the point that has been marked
c. Then install Ledder and strengthen it with dyna-bolts
d. Outdoor Ledder is ready to use
12) In Ceiling work,
a. Install ceiling hangers
b. Make sure all hanger are securely fastened and in a safe position to be afraid to be
in the room.
c. Hanging load test using ballast
d. Measuring the level of the hanging pole with a waterpass.
e. Installing the ceiling frame.
f. Installation of ceiling according to the material used
g. Recheck the level of the ceiling that has been installed.