Assignment Cum Exam On Pert and CPM PDF
Assignment Cum Exam On Pert and CPM PDF
Assignment Cum Exam On Pert and CPM PDF
Q1. Find the following for the below list of activities presented in Table.1 of a Construction Project? [20]
Table: 1
Q2. Find the following for the below list of activities presented in Table.2 of a Construction Project? [20]
Note: Use the standard deviation and Variance Chart Table: 5 for Probability Calculation.
1|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM
Table: 2
Q3. From the following data if the duration of activity f only changed from 9 to 10 days then
what would be the critical path and total duration of the project? [10]
Table: 3
2|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM
Q4. From the following data find out the total float for activity e and f ? [10]
Table: 4
a - 2
b - 4
c a 2
d b 3
e c 2
f c 4
g d,e 5
3|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM
Table: 5
4|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.