ASSIGNMENT ON PERT AND CPM

CEB814 – PROJECT MANAGEMENT

STUDENT NAME: -------------------------------------- ID: ------------------------------------------------

DATE AND TIME OF SUBMISSION: 17.06.2020 & 6:00 PM WEIGHTAGE: 30%

Q1. Find the following for the below list of activities presented in Table.1 of a Construction Project? [20]

a. Calculate the total duration to finish the project


b. Determine the Critical Path of the Project
c. Compute the Earliest Start Time (EFT), Earliest Finish Time (EFT), Latest Start Time (LST), Latest
Finish Time (LFT) Total Float/Slack (TF/TS) and Free Float/Slack (FF/FS) of each activity in a
tabular format.

Table: 1

Q2. Find the following for the below list of activities presented in Table.2 of a Construction Project? [20]

a. Calculate the total duration to finish the project


b. Determine the Critical Path of the Project
c. Compute the Earliest Start Time (EFT), Earliest Finish Time (EFT), Latest Start Time (LST), Latest
Finish Time (LFT) Total Float/Slack (TF/TS) and Free Float/Slack (FF/FS) of each activity in a
tabular format.
d. Compute the Variance of each Activity.
e. What is the probability to finish this project in 130 days? Also find the probability to complete
this project in 140 days?

Note: Use the standard deviation and Variance Chart Table: 5 for Probability Calculation.

1|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM

CEB814 – PROJECT MANAGEMENT

STUDENT NAME: -------------------------------------- ID: ------------------------------------------------

DATE AND TIME OF SUBMISSION: 17.06.2020 & 6:00 PM WEIGHTAGE: 30%

Table: 2

Q3. From the following data if the duration of activity f only changed from 9 to 10 days then

what would be the critical path and total duration of the project? [10]

Table: 3

Activity Predecessors Duration (days)


a - 3
b a 4
c a 5
d a 4
e b 2
f d 9
g c,e 6
h f,g 2

2|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM

CEB814 – PROJECT MANAGEMENT

STUDENT NAME: -------------------------------------- ID: ------------------------------------------------

DATE AND TIME OF SUBMISSION: 17.06.2020 & 6:00 PM WEIGHTAGE: 30%

Q4. From the following data find out the total float for activity e and f ? [10]

Table: 4

Activity Predecessors Duration (days)

a - 2

b - 4

c a 2

d b 3

e c 2

f c 4

g d,e 5

3|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.
ASSIGNMENT ON PERT AND CPM

CEB814 – PROJECT MANAGEMENT

STUDENT NAME: -------------------------------------- ID: ------------------------------------------------

DATE AND TIME OF SUBMISSION: 17.06.2020 & 6:00 PM WEIGHTAGE: 30%

Table: 5

4|P a ge
Prepared by: Sateesh Kumar Pisini, Principal Lecturer, Dept of Civil Eng, Fiji National University.