Crane Safety
Crane Safety
Crane Safety
27
17. Maintain the minimum distances provided in Table 2
in the Electrical Safety safety topic when operating
cranes around overhead power lines.
18. Use Critical Lift Plans (see GI 7.028) for certain
conditions and activities, including:
• Cranes operating around power lines.
• Operating around hydrocarbons and aboveground
pressurized piping areas, populated/traffic areas,
and railroads.
• All loads of 40 tons or greater.
• All loads exceeding 85% of the rated load
capacity of the crane for that specific lift.
• Tandem, multiple, or tailing lifts (any lift requiring
two or more cranes to lift one load).
• Lifts involving a crane-suspended personnel
platform (manbasket). A Crane Suspended
Personnel Platform (Manbasket) Permit is
required (see GI 7.027).
• High level and/or long reach crane lifts.
• Lifts on barges, vessels, or loading piers.
• On rubber or pick and carry lifts.
• Nighttime crane lifts, except as approved during
a turnaround and inspection (T&I) or shutdown.
• Blind lifts.
• Other lifts as determined by Saudi Aramco
management.
Rigging Practices and Inspection
1. Rig all crane loads using a certified rigger.
2. Use accepted rigging techniques when lifting loads.
28
3. Use only rigging equipment that is rated for the load
being lifted.
4. Avoid sharp bends in slings; protect slings from sharp
edges and abrasions.
5. Rig loads off load-bearing structural members only
after prior approval. Do not rig from process piping.
6. Do not modify, repair, shorten, or lengthen slings.
Verify that the manufacturer’s safe working load
(SWL) and serial number are clearly marked on each
sling.
7. Do not use sling angles less than 30 degrees above
the horizontal. The recommended safe working angle
is 60 degrees above the horizontal.
8. Completely close/bolt shackles and other connecting
devices.
9. Do not use fasteners or other rigging hardware
manufactured in-house.
10. Ensure a rigger certified per the requirements of GI
7.025 inspects all slings, fittings, and shackles before
each use.
11. Inspect slings and other rigging hardware per
applicable standards every 6 months using a certified
rigger.
12. Maintain a job-site log of slings that identifies the
sling and periodic inspection results. Record defective
slings in the log and remove them promptly from the
job site.
13. Inspect and certify all “A-Frames” by a certified
inspector prior to attaching any rigging equipment.
29