PMSA Knowledge Package
PMSA Knowledge Package
PMSA Knowledge Package
The South African Chapter of the CII was launched in May 2015
and is based at the Graduate School of Technology
Management, University of Pretoria
CII Vision, Goal, Purpose
Examples:
• Abbott • Alstom Power Inc.
• ArcelorMittal • Bechtel Group, Inc.
• AstraZeneca • Bentley Systems Inc.
• Eskom Holdings SOC Ltd • Black & Veatch
• General Electric Company • Fluor Corporation
• The Procter & Gamble Company • POWER Engineers, Inc.
• Sasol Technology • SNC-Lavalin Inc.
• Shell • WorleyParsons
CII Best Practices are proven
Best Practices
• Alignment • Materials Management
• Benchmarking & Metrics • Partnering
• Change Management • Planning for Startup
• Constructability • Project Risk Assessment
• Disputes Prevention & Resolution • Quality Management
• Front End Planning • Team Building
• Implementation of CII Research • Zero Accidents Techniques
• Lessons Learned
CII Research is university-based
Commissioning
Business Case
Start Up &
OPTION SELECTION PROJECT DEFINITION PROJECT
DEVELOP OPTIONS AND VIABILITY AND PLANNING PHASE IMPLEMENTATION PHASE
Front End Planning by another name
Boundaries
Project
Management
Process
The process of managing the work of the project
Manage the project context
For Success
Intensive Focus Here
Here
‘The Relative Impacts Of Selected Practices On Project Cost And Schedule’, Sang-Hoonlee, Stephen R.Thomas and Richard L.Tucker, Construction Management
and Economics (June 2005) 23, 545–553.
Significant difference in performance
‘CII Implementation Resource 268-2 – Infrastructure Projects; CII Implementation Resource 113-2 – Industrial Projects; CII Implementation Resource 113-2 – Building Projects.
Five critical drivers of success
‘Development of the Project Definition Rating Index (PDRI) For Infrastructure Projects Auth: Evan Bingham. Thesis Presented in Partial Fulfillment of the Requirements
for the Degree Master of Science - ARIZONA STATE UNIVERSITY December 2010
4 Project Definition Readiness & Cost Estimate Accuracy 09:10 – 09:25
Project definition readiness index
CII PDRI Tools Examples of projects showing which tool they would use
Industrial PDRI • Bottling plant • Pharmaceutical process plant • Server farm
Each tool is used to assess the project against 3 broad scope definition sections
PDRI
How well defined is the How comprehensively have all How well have the
justification and supporting the design parameters and requirements of the owner’s
information for the project. And specifications been defined to execution been identified and
how well have the options and ensure the scope of the project defined, to ensure the project
alternatives been determined and is fully understood and defined. can be implemented and
evaluated, to ensure alignment delivered effectively.
with the business’s objectives
Example of CII PDRI
PDRI sections cover all aspects
CII Project Definition Rating Index, Industrial Projects, CII Implementation Resource 113-2, version 3.2
Readiness assessed across 70*elements
The completeness of the project scope definition is reviewed to a quantifiable level of detail
* The number of ‘Elements’ ranges between 64 and 70 dependent on the PDRI tool employed,.
Each element assessed by the team
The emphasis is on identifying and evaluating the impact of the risks and the mitigation actions
Identified
Gaps / Risks
and Impacts The gaps and
and Actions associated risks and
Thabo mitigation actions are
Mashegoane described.
Piet
Steinkamp
The next actions to
close the gaps are
Dumisa
Moeketsi assigned to named
individuals responsible
Linda Sithole
for correcting them.
Linda Sithole
Linda Sithole
Linda Sithole
Linda Sithole
Linda Sithole
Gaps and associated risks identified
1 2 3 4
1 PDRI Score
The PDRI score is the sum of the scores for each Element [scored between 1 – 5 ],
for (a) the Section and (b) the Category.
2 Min Score
This is the minimum attainable score for the sum of all the Elements within the
applicable Section and Category. This is the eventual score the project team should
be aiming for.
3 Max Score
This is the maximum weighted score attributable to the applicable Section and
Category.
4 Def (%)
5
The Definition percentage is the level of completeness of the respective Section and
Category based on the score for the current PDRI assessment.
5 Top Elements
These are the top 10 Elements having the highest weightings in the PDRI. These are
the Elements which should be focussed on first in terms of level of completeness of
the definition .
FEP critical for definition completeness
FEP critical for cost accuracy
AACE International Recommended Practice No. 18R-97: Cost Estimate Classification System – As Applied in Engineering, Procurement, and Construction for the
Process Industries. AACE® International – The Association for the Advancement of Cost Engineering
FEP – Cost and activities
Value of Best Practices Survey completed in 2010; owners with high front
end planning usage on average spend 8% less than those with low usage
1. Managing the Front-End: how project managers shape business strategy and manage project definition, 2005,
Peter Morris Originally published as a part of 2005 PMI Global Congress Proceedings – Edinburgh, Scotland
2. Front End Planning In The Modern Construction Industry By Roberta Patrice Bosfield, ARIZONA STATE
UNIVERSITY May 2012
3. Development of the Project Definition Rating Index (PDRI) For Infrastructure Projects by Evan Bingham.
ARIZONA STATE UNIVERSITY December 2010
4. A risk-management approach to a successful infrastructure project, McKinsey Working Papers on Risk, Number
52, November 2013
5. Critical Activities in the Front-End Planning Process Ryan George1; Lansford C. Bell, F.ASCE2; and W. Edward
Back, M.ASCE3. JOURNAL OF MANAGEMENT IN ENGINEERING © ASCE / APRIL 2008
6. Prioritising Project Scope Definition Elements in Public Building Projects, Fageha, M.K & Aibinu, A.A. 2014,
‘Prioritising Project Scope Definition Elements in Public Building Projects’, Australasian Journal of Construction
Economics and Building, 14(3), 18-33.
7. CII South Africa Launch. CII’s Impact on Capital Projects, May 21, 2015 University of Pretoria Stephen P. Mulva,
Ph.D. Associate Director, CII
6 Q&A, Networking and Event Close 09:30 – 10:00
About EPCM Global
EPCM Global is a management consulting services firm for public and private sector clients. We provide specialist
solutions and competitive insights within our three core offerings:
• Consulting solutions for business, project and engineering management
• Business architecture – review the integration of your business strategy, systems architecture, sustainability principles and operations.
• Business process development and re-engineering – develop, re-engineer and standardise processes for sustainability.
• Plant lifecycle and performance improvement – develop processes and tools to address shortcomings within your company’s asset lifecycle
management.
• Operational optimisation – develop and implement operational improvement solutions.
• Project readiness assessments – facilitate project definition readiness.
• Project lifecycle methodology – assess, develop and standardise project lifecycle models.
• PMO establishment – Establish the strategy, architect, structure, organise and establish programme and/or project management office