Right Marginal Bund Report
Right Marginal Bund Report
Right Marginal Bund Report
Project Background: NHA is constructing “SHAHEED BENAZIR BHUTTO BRIDGE” over river Indus
connecting Chachran Sharif district Rahim Yar Khan with KotMithan district
Rajanpur.
The IRI Lahore sent the Hydraulic Model Study Report No.IRI-1270 dated
January, 25 2012 with their recommendation for final location and length of the
bridge.
The project envisaged the construction of a 1200 m long concrete bridge, with
approaches, and river training works. The scope of work relating to river training
works includes construction of guide banks upstream and downstream of the
bridge. According to the model study the design flood of the proposed bridge as
36,817 cumecs, construction /raising of Right Marginal Bund on Kotmithan side
and raising and improvement of Minchin Bund (Left Marginal Bund) including J-
Spur No1&2 on upstream side and other Spurs on downstream side have been
included on the direction of Chief Engineer D.G Khan and PRO Hydraulics IRI
Lahore.
Main Components:
Revised PC-1 with amount 9304.160 (M) was approved by ECNEC in its meeting
held on 26th July 2017.
Execution of Works: From the detailed scrutiny of the documents / record produced by the Irrigation
department it was found that Irrigation department is executing the earth work
component of sub-project through its machinery division.
XEN Irrigation Jampur attended this office on 19th November 2018 for
submission of record. He was asked to provide the approval of competent
authority for execution of works through department itself, He was also
directed to provide the cost comparison in case of open bidding compared with
departmental execution.
Conclusion / Findings:
1. Currently work on earth work component is in progress.
2. Irrigation department is executing only one component through its
machinery division.
3. All other components would be executed through open / competitive
bidding.
4. Work is being executed as per approved design and drawings.
5. No any formal approval from competent authority has been accord for
execution of works by machinery division of Irrigation department.
Machinery Division
1 75.49 270 28.687 148.656
Multan
Exacavator Division
2 29.66 150 10.378 53.789
Faisalabad
Construction
3 Division Dera Gazi 15.94 75 0.956 4.955
Khan
G.TOTAL 40.021 207.4
9. Total Progress Till Todate:
Total Cost (Approved Utilization % tag
Component
Cost) Till To date Progress
Earth Work 627.462 207.4 33%
Shingle Work 27.533 0 0%
Out Fall Structures 61.564 0 0%
Machinery
Rate per 1000
Rates Difference %
Task Dated MRS Period cft with same Remarks
(per 1000 (Amount) age
specifications
cft)
(Bi-Annual
Submission of February 2016 to
22.04.2016 6678.4 5182 1496.4 29% Above
PC-1 July 2016) of
District Rajanpur
(Bi-Annual 2nd
Approval of
07.08.2017 July-2017 to 7932.55 5182 2750.55 53% Above
PC-1
December – 2017)
Technical (Bi-Annual 1st
Sanction of 03.03.2018 January-2018 to 8392.5 5182 3210.5 62% Above
Estimate July– 2018)