EIA Report PDF
EIA Report PDF
EIA Report PDF
Project Proponent
Table of Contents
Compliance of TOR
Executive Summary
CHAPTER 1: INTRODUCTION
1.1 Preamble 1-1
1.2 Importance and Benefits of the Project 1-2
1.3 Need and Process of Environmental Clearance 1-3
1.4 Regulatory Compliance Requirement 1-4
1.5 Terms of Reference (TOR) 1-5
1.5.1 Location of Guwahati Airport 1-6
1.5.2 Geographical Conditions of the Study Area 1-6
1.6 Structure of Environmental Impact Assessment Report 1-9
List of Tables
CHAPTER 2 : PROJECT DESCRIPTION
Table 2.1 Projections for Domestic Passenger Traffic at Guwahati Airport 2-3
Table 2.2 Projections for International Passenger Traffic at Guwahati Airport 2-3
Table 2.3 Area Statement for New Integrated Terminal Building 2-9
Table 2.4 AC Load Estimation for Proposed Integrated Terminal Building 2-16
Table 2.5 Daily Water Demand Calculations for New Integrated Terminal Building 2-25
Table 2.6 Water Consumption Summary & Treated Waste Water Recycle 2-26
Table 2.7 Estimated Manpower Requirement for New Integrated Terminal Building 2-29
Table 6.1 Environmental Monitoring Plan for New Integrated Terminal Building at 6-3
Guwahati Airport
Table 6.2 Cost of Environmental Monitoring 6-7
Table 9.1 Environmental Management Plan for New Integrated Terminal Building at 9-27
Guwahati Airport
Table 9.2 Details of CSR Activities Proposed for Guwahati Airport 9-44
Table 9.3 Budget for Implementation of Environmental Management Plan 9-45
List of Figures
CHAPTER 1: INTRODUCTION
Figure 7.1 Intensity Radii for Late Pool Fire for Leakage of HSD from Unloading 7-10
Hose
Figure 7.2 Flash Fire Envelope for Leakage of HSD from Unloading Hose 7-11
Figure 7.3 Intensity Radii for Late Pool Fire for Leakage of ATF from Loading Hose 7-12
Figure 7.4 Flash Fire Envelope for Leakage of ATF from Loading Hose 7-13
Figure 7.5 Intensity Radii for ATF Tanker on Fire 7-14
Figure 7.6 Late Explosion Worst Case Radii for ATF Tanker on Fire 7-15
Figure 7.7 Flash Fire Envelope Radii for ATF Tanker on Fire 7-16
Figure 9.1 Schematic Diagram for Membrane Bioreactor Type STP 9-5
Figure 9.2 East West Façade for New Terminal Building 9-10
Figure 9.3 South & North Façade for New Terminal Building 9-10
Figure 9.4 Low Impact Design – Passive Design Feature 9-11
Figure 9.5 Wind Direction Consideration for Selected Building Orientation 9-12
Figure 9.6 Energy Efficient Construction Materials and Design 9-15
Figure 9.7 Provision of PV Panels for Over Car Parking at New Integrated Terminal 9-18
Building
Figure 9.8 Green Plan for New Integrated Terminal Building 9-19
Figure 9.9 Organogram for Environmental Management Cell 9-41
Annexure :
Annexure 1: Terms of Reference issued by Ministry of Environment, Forest and Climate Change
Annexure 2: Copy of application submitted for clearance from NBWL
EXECUTIVE SUMMARY
0.1 Introduction
Lokpriya Gopinath Bordoloi International Airport at Guwahati, one of the major airport in
India and in North East Region is situated in the state of Assam, belongs to AAI.
Operators like Air India, Jet Airways, Spice Jet, Indigo, Go Air, Vistara, Air Asia India and
Pawan Hans Helicopters are presently operating with 75 flights movements per day and
528 flights in a week. The Airport is an International Airport being developed as
inter‐region hub and suitable for operation of B‐767/A‐310 type of aircraft.
The existing terminal building at Guwahati Airport is capable to handle 850 pax (425
arriving + 425 departing) at a time. The existing terminal building at Guwahati has
saturated. In view of the future traffic growth at Guwahati Airport, there is a requirement
of construction of New Integrated Terminal Building at the available land within the
airport premises.
Airports Authority of India (AAI) has planned centrally air-conditioned New Integrated
Terminal Building of modular design with all modern facilities and associated facilities
like multilevel car parking. The Integrated Terminal Building with area of 90000 sqm
(excluding Service area as per requirement in Basement covering area of 7500 sqm)
have been designed for 2900 Domestic and 200 International passengers at a time with
the recommended area specifications and to match the level of service “B” as per IATA
recommendations in initial years & finally to match level of service ʺCʺ in year of
saturation.
The EIA studies have been carried out as per TOR approved by MoEF&CC vide letter
Dated 26 October, 2016.
The existing terminal building at Guwahati has saturated. In view of the future traffic
growth at Guwahati Airport, there is an urgent requirement of construction of New
Integrated Terminal Building at the available land within the Guwahati airport premise.
The passenger handling capacity existing terminal building has already saturated. In
view of the future traffic growth at Guwahati Airport, there is urgent requirement of
construction of new integrated terminal building on turn key basis. The scope of work for
proposed integrated terminal building.
• The total estimated electrical demand load of the new integrated terminal building
is approximately 7.5 MW, which shall be supplied at 33 KV as per Assam
Electricity Board and 2 no (1 Working and 1 Standby) power transformers 33/11
KV each 10 MVA capacity. Provision of 100% emergency back up by DG sets of 6
no each 2000 kVA has been kept.
• Central Airconditioning plant is proposed and total estimated air-conditioned load is
3300 TR after diversity. Microprocessor based control system (BMS) will also be
installed at the Airport.
• At the new integrated terminal building Energy Conservation will be as per Energy
Conservation Building Code 2007 (ECBC). 540 kW solar PV power plant will be
esteblished to generated solar power.
• Fresh water requirement will be 710 KLD for domestic, food courts, retail, offices,
HVAC, etc. (Total water requirement including recycled water- 1010 KLD). Water
requirement will be extracted through bore wells at the airport.
• As per water balance diagram, 810 kl/d sewage will be generated after the
operation of integrated terminal building which will be treated in STP of capacity
1000 kl. Membrane bioreactor (MBR) Technology will be used for treatment of
waste water at the airport.
• For storm water management at the site, rectangular sections for side drains will
be provided. The drains have been kept sufficiently away from the taxiway /
runway.
0.2.4 Project Cost - The estimated cost of new integrated terminal building and associated
works at Guwahati Airport is estimated as Rs 1232 Cores.
Geology: The Guwahati is geologically an extension part of the Shillong plateau of the
Pre Cambrian Age. Geologically, the city is characterized by Precambrian granite
gneissic complex composed of granite gneiss, biotite schists, gneiss and quartzite.
Soil Characteristics: The soil type found in the study area is mainly sandy, silty and
clay type. Soil found on river banks and in plains are rich in nutrients and are suitable for
arable farming.
Water Quality: Water quality of study area meets desirable limit. Ground water
resources in the study area were found fit for drinking purpose.
Micro Meteorology: During the study period maximum temperature was recorded as
320C and minmum as 110C. The relative humidity was recorded to be varying between
44 to 87%. The wind speed was recorded in the range between 0.5 to 4.2 kmph. The
predominant wind direction during study period was from North East to South West (from
NE towards SW).
Ambient Air Quality: Ambient air quality monitoring have been carried out at eight
locations during post monsoon season for PM2.5, PM10, SO2, NO2, NH3, O3, C6H6, BaP,
Pb, As, Ni and CO. National ambient air quality standards for industrial, residential, rural
& other areas are met for all monitored parameters at all AAQM locations during the
study period.
Noise Level: Nose measurements were carried out at 8 locations. Measured day and
time Leq noise levels are within the limit stipulated noise standards.
Natural Hazards and Disaster Risk: The Guwahati Airport lies in seismic zone V
according to zoning map of India. Structure of new terminal building has been designed
in view of seismic factor and other natural hazards.
Landuse & Land Cover in the Study Area – As per satellite image interpretation, more
than 50% of the study area is covered by fvegetation & agriculture fields and followed
by marshy land (11.59.9%), Settlement (9.26%), water body (9.17%) and dry river bed
(9.17%), whereas the open shrub land is 4.85% in the study area.
Terrestrial Ecology: Vegetation in the area is common type. During the study, no tree,
shrubs and grass was observed, which are endangered or threatened under IUCN
(International Union for Conservation of Nature and Natural resources) guidelines.
Aquatic Ecology - Brahmaputra River is perennial river flowing within the 10 km radius
study area. Brahmaputra river alongwith ponds, lake and other small water bodies form
the aquatic ecosystem. Deepor bill (Water body) is a Ramsar site is the largest habitat of
migratory birds situated about 3 km towards eastern side of the project site.
Mitigation Measures
• Land clearing at the site will be kept to the absolute minimum practicable; and
• Construction site would be designed to minimize filling of the earths.
• Borrowing of earth will be ensured only from approved borrow area having valid
environmental from District Level Environmental Impact Assessment Authority
(DEIAA).
Land Use Pattern: For construction of new integrated terminal building and associated
works at Guwahati Airport, total 90000 sqm land is required, which is already available
within the airport. The land use pattern of the land used for construction of new
integrated terminal building and associated works, will be changed permanently,
however this impact will be localized.
Mitigation Measures
• Land clearing for construction site will be kept to the absolutely minimum practicable;
• The filling and cutting of soil would be kept minimum; and
• Construction debris and waste generated during construction activities will be
collected and disposed in environmental sound manner as per applicable rules
depending upon type of wastes.
Water Resources and Water Quality: During the construction phase of the
construction of new integrated terminal building and other associated work at Guwahati
Airport, approx 300 kl/day water will be required depending upon the type of construction
activities. The water requirement will be met through existing deep bore well. Total water
requirement at Guwahati Airport after proposed new integrated terminal building is
estimated as 1010 kld (Fresh Water 710 kld), which includes water for HVAC, CFT,
green belt purposes. Waste water generated from airport will be treated in Sewage
Treatment Plant (STP) and reused for HVAC, flushing, greenery development.
Mitigation Measures
• Continuous efforts will be made to reduce water consumption using less water
required cisterns ;
• Water efficient urinal and toilets will be provided in new integrated terminal building.
• Efforts will be made to stop wastage and leakage of water;
• Sewage and domestic waste water will be treated in MBR based Sewage Treatment
Plant
• Reused treated waste water in HVAC, flushing, greenery and landscaping
Soils: Approx 3100 kg per day solid waste will be generated during operation of the new
terminal building at Guwahati airport, which is collected, segregated and managed by
external agency for disposal as per Solid Waste Management Rule, 2016. Hence, the
impact on the soil will be insignificant as an organized solid waste collection and
disposal practices exist at the Guwahati Airport.
Mitigation Measures
• Agency will be hired for disposal of solid wastes as per the provisions of the Solid
Waste Management Rule, 2016;
• Solid waste generated from the airport is transported in close containers;
• Used lubricating waste oil and oil contaminated clothes etc is collected separately in
containers and is sold to authorized recyclers as per CPCB/ Pollution Control Board,
Assam (ASPCB) guidelines.
Ambient Air Quality: During the operational phase of the new terminal building at
Guwahati Airport, the intermittent air emissions are generated from aircraft engines
during approach, landing, taxiing, take-off and initial climb, which is termed as reference
Landing and Take-off Cycle (LTO cycle). For power back up, there will be 6 DG sets of
2000 KVA capacity each will be available, which will be sufficient for new terminal
building and associated facilities. Vehicular emissions will also be generated from the
operation of vehicular traffic at the new integrated terminal building as ground support
vehicles, passengers’ pickup and dropping vehicles. Exhaust emissions comprising NO2,
SO2, PM, CO, HC, etc will be generated from aircraft, DG sets and vehicular emissions.
Mitigation Measures
Noise Levels: The new integrated terminal building at Guwahati Airport will be sound
proof. DG sets room will be acoustically treated to control noise levels.
Mitigation Measures
• The compliance of all standards prescribed by the ICAO during operation of aircrafts
by preventive maintenance and monitoring,
• Proper traffic management will be prepared to ensue that there is no traffic
congestion at the airport. It helps in reduction of vehicular noise emissions from the
airport,
• DG sets will be provided with acoustic enclosure as per CPCB guidelines,
• Green belt, landscaping and boundary at the airport act as barrier for noise;
• Monitoring of ambient air quality/source emission will be carried out as per
monitoring plan.
Terrestrial Ecology: Greenery and landscaping will be developed at the new integrated
terminal building. For irrigation of green belt, treated waste water from STP and
accumulated rainwater will be available and used. This will have positive and long term
beneficial impact on terrestrial ecology of the area.
Deepore Beel Bird Sanctuary, a Ramsar Site is located at a distance of 3 km from the
project site of integrated terminal building. The Deepore Beel Bird Sanctuary is not
located in funnel area of runway of Guwahati Airport. Noise modelling carried for existing
airport, indicate that impact of aircraft noise from aircraft operation on the Deepore Beel
Bird Sanctuary is negligible.
1. Landscaping and green belt will be developed towards Deepore Beel Bird Sanctuary.
2. Solid Waste Generated from new integrated terminal building will be collected,
segregated and disposed in designated site as per Solid Waste Management Rule
2016.
3. Sewage generated from the integrated terminal building will be treated in Sewage
Treatment Plant and reused for horticulture and flushing.
4. Recommendations of Chief Wildlife Warden will be implemented.
• Airport Terminal building will be designed and constructed for GRIHA Rating 4 star,
• Use of Energy Efficient building material & glass,
• Use of LED lamps instead of GLS lamps,
• Use of Solar Backed up Light Emitting Diode Lamps instead of par lamps,
• Energy efficient HVAC system,
• Solar passive techniques for terminal building,
• Use of 5 star BEE energy efficiency rating electrical equipments,
• Microprocessor-based Building Management System (BMS) will be installed for
minimization of energy consumption,
• Automatic lighting on/ off control system will be provided in the airport area for
optimum utilization of energy.
It is proposed that 5400 KW solar power generation plant will be established at the
airport to produce clean energy. By adopting above measures more than 30% energy
will be saved.
Hazard occurrence at the new integrated terminal building at Guwahati Airport may
result in on-site implications, like, fire at the storage of HSD for DG sets followed by fire,
bomb threat at terminal building, cargo terminal & aircraft and natural calamities like,
earthquake, flood, etc. Other incidents, which can also result in a disaster at the
Guwahati airport are agitation/forced entry by external group of people, sabotage, air
raids; and aircraft crash while landing or take-off.
Disaster management plan has been prepared comprising key functions of Airport
operator, other supporting organizations/agencies/services for response during
emergency at the new integrated terminal building at Guwahati Airport.
The direct and indirect benefits of the construction of new integrated terminal building at
Guwahati Airport are as follows:
The Airports Authority of India will be responsible for the implementation of mitigation
measures identified in Environmental Management Plan (EMP) for construction and
operation phases of the new integrated terminal building at Guwahati Airport. There will
be Environmental Management Cell (EMC) at new integrated terminal building at
Guwahati Airport to look after day to day basis implementation of mitigation measures
for construction and operation phases.
Total budget of Rs 5.27 Crores has been kept for implementation of environmental
management plan during construction and operation phases of new integrated terminal
building and associated facilities. Total budget of Rs 0.11 Crore has been kept for
environmental monitoring during construction and operation phases.
CHAPTER – 1
INTRODUCTION
1.1 Preamble
The present Guwahati Airport was established in year 1958. Initially it was
maintained and operated by CPWD, in later which was handed over to National
Airports Authority of Indian (NAAI) now known as Airports Authority of India (AAI),
after merger of NAAI and AAI in the year 1995 for maintaining and operations of the
existing airports. In 1989, its Air Traffic Control Tower (ATC) was built up along with
expansion of existing terminal building which was commissioned in the year 1993-
1994. Since then only minor modifications were executed in order to cope up with
passenger inflow increase and now presently Guwahati Airport is functioning as a
Gateway of entire North East part of India.
Guwahati Airport, one of the major airport in India and in North East Region is
situated in the state of Assam, belongs to AAI Operators like Air India, Jet Airways,
Spice Jet, Indigo, Go Air, Vistara, Air Asia India and Pawan Hans Helicopters are
presently operating with 75 flights movements per day and 528 flights in a week. The
Airport is an International Airport being developed as inter‐region hub and suitable
for operation of B‐767/A‐310 type of aircraft.
The existing terminal building at Guwahati Airport is capable to handle 850 pax (425
arriving + 425 departing) at a time. The existing terminal building at Guwahati has
saturated. In view of the future traffic growth at Guwahati Airport, there is a
requirement of construction of New Integrated Terminal Building at the available land
within the airport premises.
Airports Authority of India (AAI) has planned centrally air-conditioned New Integrated
Terminal Building of modular design with all modern facilities and associated facilities
like multilevel car parking. The Integrated Terminal Building with area of 90000 sqm
(excluding Service area as per requirement in Basement covering area of 7500 sqm)
have been designed for 2900 Domestic and 200 International passengers at a time
with the recommended area specifications and to match the level of service “B” as
per IATA recommendations in initial years & finally to match level of service ʺCʺ in
year of saturation. The building should be provided with aesthetically appealing and
soothing interior decoration matching the modern structure. Space planning should
ensure that no dead Space/ Area is created in the building.
Environment plays a vital role in overall development of the country. Recognizing the
importance of environmental protection and sustainable development, the Ministry of
The Ministry of Environment, Forest and Climate Change (MoEF&CC) has made
prior environmental clearance (EC) for Airport projects mandatory through its
notification issued on 14th September 2006 and as amended on 1st December 2009.
During 9th meeting of Expert Appraisal Committee (Infra-2) for “Projects related to All
ship breaking yard including ship breaking unit, Airport, Common Hazardous Waste
Treatment, Storage and Disposal Facilities, Ports and Harbours, Aerial Ropeways,
CETPs, Common Municipal Solid Waste Management Facility, Building/Construction
Project, Townships and Area Development projects held on 21st – 22nd September,
2016, the project was considered and TOR was finalised vide letter Dated 26
October, 2016. EIA & EMP report has been prepared as per TOR approved by
MoEF&CC.
The existing terminal building at Guwahati has saturated. In view of the future traffic
growth at Guwahati Airport, there is an urgent requirement of construction of New
Integrated Terminal Building at the available land within the Guwahati airport
premises.
The direct and indirect benefits of the New Integrated Terminal Building at Guwahati
Airport are as follows:
As per the EIA notification of 14th September 2006 and its amendment dated 1st
December 2009, airport projects are divided into two categories as mentioned below:
Project or Category with threshold limit Conditions if any
Activity A B
(a) ( (1) (2) (3) (4) (5)
7(a) Airports All projects - Note:
including airstrip, Air strips which do not involve
which are for bunkering/ refueling facility and
commercial use”; or Air Traffic Control, are
exempted.”
Flow-chart depicting stage to obtain the prior environmental clearance for proposed
project are presented in Figure 1.1:
The operational and geographic impacts associated with airport development and
operations are covered by policy drives (both strategies and legislation) at global,
regional and national levels.
The International Civil Aviation Organisation (ICAO), which oversees the level and
direction of effort involved in addressing the environmental impact of the sector, also
deals with the emissions from aircraft.
The work of the CAEP is more technical in nature. The process of securing
consensus in ICAO is lengthy, not least because membership is voluntary. Though
the members are responsible for enacting certain standards and practices, they are
not legally bound to do so. They are only honour bound to implement the resolution
on environmental policies and practices.
India being one of the member states of ICAO, implements the resolution on
environmental policies and practices adopted by ICAO through Director General of
Civil Aviation (DGCA), under Ministry of Civil Aviation, GOI at national level to
mitigate the operational impact associated with aviation at airports.
It ensures that environmental concerns are strategically integrated into air transport
policy by improving technical environmental standards on noise and gaseous
emissions; advancing long term technology improvements; inspecting aerodrome site
for issuing aeronautical clearance; improving the air traffic management and
promoting flight safety environment at airports.
During 9th meeting of Expert Appraisal Committee (Infra-2) for “Projects related to All
ship breaking yard including ship breaking unit, Airport, Common Hazardous Waste
Treatment, Storage and Disposal Facilities, Ports and Harbours, Aerial Ropeways,
CETPs, Common Municipal Solid Waste Management Facility, Building/Construction
Project, Townships and Area Development projects” held on 21st – 22nd September,
2016, the project was considered and TOR was finalised given vide letter dated 26
October 2016. EIA & EMP report has been prepared as per TOR approved by MOEF
& CC. The compliance of TOR is given in the beginning of EIA Report.
xii. Noise monitoring shall be carried out in the funnel area of flight path.
xiii. Requirement of water, power, with source of supply, status of approval, water
balance diagram, man-power requirement (regular and contract)
xiv. The EIA should specifically address to vehicular traffic management as well as
estimation of vehicular parking area.
xv. Details of fuel tank farm and its risk assessment.
xvi. Public hearing to be conducted and issues raised and commitments made by the
project proponent on the same should be included in EIA/EMP Report in the form
of tabular chart with financial budget for complying with the commitments made.
xvii. Any litigation pending against the project and/or any direction/order passed by
any Court of Law against the project, if so, details thereof shall also be included.
Has the unit received any notice under the Section 5 of Environment (Protection)
Act, 1986 or relevant Sections of Air and Water Acts? If so, details thereof and
compliance/ATR to the notice(s) and present status of the case.
xviii. A tabular chart with index for point wise compliance of above TORs.
Guwahati Airport, one of the major airports of North East Region is located about 15
km in East -North East Direction from the main Guwahati city. The Reference point of
Existing Guwahati Airport is 26o6'22" N and 91o35'09" E. The index map of Guwahati
Airport is shown on Figure 1.2.
The 10 km radius study area has been considered for environmental impact
assessment studies. The 10 km radius study area around Guwahati airport on
Google map is shown in Figure 1.3. The locations of various important locations are
given below:
Survey of India Toposheets for the project area are restrict for photocopy and
reproduction. Therefore, 10 Km study area based on SOI Toposheets has been
prepared and shown in Figure 1.4. Deepor Beel Bird Sanctuary is located at a
distance of 3 km from the project site.
The Environmental Impact Assessment (EIA) Report has been prepared as per
format described in the EIA Notification 2006 and the structure of EIA report is given
below. The EIA report has been divided into 10 Chapters which area presented as
follows:
Compliance of TOR
Chapter 1: Introduction
This chapter deals need for the project, project location, project layout, terminal
buildings, utilities and services, power requirements, parking facilities, water
requirement and sources, drainage and sewage disposal system, storm water
drainage system, horticulture and landscaping, energy conservation measures, the
project implementation schedule, estimated cost of development, etc.
This chapter describes the anticipated impact on the environment and mitigation
measures for project. The method of assessment of impact including studies carried
out, modeling techniques adopted to assess the impact where pertinent have been
elaborated in this chapter. It gives the details of the impact on the baseline
parameters, both during the construction and operational phases and suggests the
mitigation measures to be implemented by the proponent. It also describes the
overall both-direct and indirect, reversible and irreversible impacts of the proposed
activities on different environmental parameters on different environmental
parameters during construction and post construction phase and underscores the
areas of concern, which need mitigation measures.
This chapter examines alternative means for proposed project involves description of
each alternative, summary of adverse impacts of each alternative, mitigation
measures proposed for each alternative and selection of best alternative.
This chapter describes environmental monitoring plan (EMP) for the project during
construction and operation phases.
This chapter spelled out hazard identification, risk analysis and disaster management
plan for an unlikely event of emergency at new integrated terminal building of
Guwahati Airport.
This chapter comprises the name of consultants engaged with their brief resume and
nature of consultancy rendered.
Annexure 1
CHAPTER 2
DESCRIPTION OF PROJECT
2.1 Introduction
The existing terminal building is capable to handle 850 pax (425 arriving + 425
departing) at a time. The major facilities available at the Guwahati Airport are:
The existing Guwahati airport covers 528.225 Acres. No additional land will be
acquired for the proposed project. The master plan of Guwahati Airport is shown in
Figure 2.1.
A consolidation of the growth rates in the domestic and international passenger and
cargo traffic shows the CAGR percentages. The steady growth is observed
passenger movement and also for the Aircraft movement but the growth of
International Cargo has developed negative growth while the steady growth is
observed for Domestic cargo.
The projections for domestic Passenger Traffic at Guwahati Airport are given in
Table 2.1. The projections for International Passenger Traffic at Guwahati Airport are
given in Table 2.2.
The passenger handling capacity existing terminal building has already saturated. In
view of the future traffic growth at Guwahati Airport, there is a requirement of
construction of new integrated terminal building on turn key basis. The scope of work
for proposed integrated terminal building.
Civil Works
designed for 2900 Domestic and 200 International passengers at a time with the
recommended area specifications and to match the level of service “B” as per IATA
recommendations in initial years & finally to match level of service ʺCʺ in year of
saturation. The building should be provided with aesthetically appealing and soothing
interior decoration matching the modern structure. Space planning should ensure
that no dead Space/ Area is created in the building.
(ii) Departure area, Arrival area, Security Hold area and Concourse area are to be
provided with adequate nos. of toilets for gents, ladies and differently‐abled persons
along with drinking water facility. Suitable number of ramps to be provided for entry
and exit of differently‐abled persons in Departure and Arrival area. Provision of
battery operated buggies for senior citizens / differently‐abled persons as per
requirement.
(iii) The design of Terminal building to include Media planning, Retail Area planning,
F & B plan, etc. Overall planning of Building to capture local architectural features
and it to be part of design features of Terminal. The design should include the
required arrangement for its regular maintenance so as to make it in-built part of
execution. Solar power generation viz Solar lighting, Solar roofing system, etc shall
be provided. Maintenance friendly roofing & building façade system including
provision of regular cleaning with maintenance hoists, hooks, etc including cat walk /
rope suspended platform / gondola etc. to be provided.
(iv) Departure Area - The terminal building with provision for departure concourse,
check-in area with adequate number of check-in counters, immigration counters,
baggage conveyor belts, queuing space, segregation railing, back-up offices for
Airlines, facilitation counters, weighing machines, counters etc.
a) Security Hold area with adequate seating arrangements and separate security
check and holding area and associated facilities.
b) The passenger frisking area in security hold with adequate space for locating
required number of DFMDs, X‐ray machines, frisking platforms, Inspection
Tables for manual checking of hand baggage and adequate space / room for
security staff, isolated smoking area etc.
c) Additional Security Hold should be provided in the mezzanine floor to facilitate
holding near the gates provided with aerobridges.
(vi) Duty Free/Retail Area Creation of Retail Islands/ Shops without affecting the
passenger movement.
a) In the ground floor Baggage Claim area, adequate number of baggage conveyor
belts of adequate size should be provided.
b) Adequate space should be provided in the ground floor for required number of
immigration & custom counters and back up offices, Money Exchanger counters,
Bank, space for storing of baggage trolleys, space for storage of mishandled
baggage for airlines, segregation railing and associated passenger amenities.
(x) Airport Director’s office with associated office space, staff canteen, Engineering
office, Toilets for staff etc to be provided in the lower ground floor.
(xi) Construction of multilevel car park with all amenities for at least 1500 cars and
surface parking for VIP cars & 10 buses, Separate car / scooter park area for
AAI and airlines staff at appropriate location. Multilevel Car Parking should be
made for retailer in car parking area & it should be developed on Built &
Operate System and shall include its space planning and model for its
operations.
(xii) Development of four‐lane vehicular road from Terminal Building / Car parking
with canopy covering two lanes in front of the Terminal Building on the city side
and connecting the main approach road to the city.
Electrical Works
Airports Systems
IT Systems
i) Passive and Active networking components such as OFC, UTP cabling, Routers,
Core & Access switches and accessories. Provision of raceways, Cable trays and
Conduiting and Cabling.
ii) Server room and adequate space for keeping network switches along with
electrical power points and UPS.
iii) Access Control System as per BCAS requirement.
iv) Provision of Internet, VPN bandwidth, Wi‐Fi system.
Commercial Works
Inspired by Icarus, the mythological figure who is one of the earliest inspirations of
human flight. The airport roof is styled using the art of Origami, the design is an ode
to human endeavor, crafts and innovation. The facade shall reflect the same
language of origami in certain parts owing to the need of solid wall surfaces
• Indoor rain forest: an experience of a “touch and feel” forest which visually
extends to an outdoor forest
• Crafts village : an immersive experience of the artisanship and culture of the
“Seven Sisters”
• Local art walls: a canvas for the Guwahati artists to showcase their art on a
rotational basis, almost like Graffiti walls.
The Integrated Terminal Building with area of 90000 sqm (excluding Service area as
per requirement in Basement covering 7500 sqm area) shall be designed for 2900
Domestic and 200 International passengers at a time with the recommended area
specifications and to match the level of service “B” as per IATA recommendations in
initial years & finally to match level of service ʺCʺ in year of saturation.
The area statement for new integrated terminal building is given in Table 2.3:
The site plan for departure side for New Integrated Terminal Building is given in
Figure 2.3. The site plan for retail/F&B departure side for New Integrated Terminal
Building is given in Figure 2.4. The site plan for arrival Side for New Integrated
Terminal Building is given in Figure 2.5. The isometric view of new integrated
Terminal Building is given in Table 2.6.
New terminal building, at Guwahati Airport will be above ground. However, 5 m deep
basement covering an area 7500 sqm will be constructed. For construction of the
proposed facilities at the Guwahati Airport, tentatively 100000 cum filling will be
required.
Approx 50000 cum earth excavated from construction of 7500 sqm size
basement will be used filling at airport site. Additional earth will be procured
from approved quarry.
Figure 2.3 : Site Plan for Departure Side for New Integrated Terminal Building
Figure 2.4 : Site Plan for Retail/F&B Departure Side for New Integrated Terminal Building
Figure 2.5 : Site Plan for Arrival Side for New Integrated Terminal Building
The car park with all amenities will be provided for at least 1500 cars and surface
parking for VIP cars & 10 buses. There will be separate car / scooter park area for
AAI and airlines staff at appropriate location. Multilevel Car Parking shall be made for
retailer in car parking area and it will be developed on Built & Operate System and
shall include its space planning and model for its operations.
The total estimated electrical demand load of the new terminal is approximately 7.5
MW, which shall be supplied at 33 KV as per Assam Electricity Board and 2 no (1
Working and 1 Standby) power transformers 33/11 KV each 10 MVA capacity.
Further, reduction in Voltage from 11 KV to 415 Volts shall be done by distribution
transformers at basement of Terminal Building and Utility block to reduce the capital
and operating cost with less voltage drop. Provision of 100% emergency back up by
DG sets of 6 no each 2000 kVA being provided.
2.7 HVAC
All air conditioning equipment installed in the project shall operate on environment
friendly HFC refrigerants with latest state of the art technology and meeting highest
energy efficiency criterion. Central Airconditioning plant is proposed and total
estimated air-conditioned load is 3300 TR after diversity. Microprocessor based
control system (BMS) will also be installed at the Airport.
g) Cooling tower selection for minimum drift and noise level with energy efficient
motors.
h) Heat recovery wheels for pre cooling outdoor air by using the waste exhaust air
from toilet & pantry etc. This ensures reduced energy consumption despite higher
outdoor air intake.
Air conditioning load estimation for the proposed integrated terminal building are
given in Table 2.4:
2.7.1 AC Equipment
The AC plant room is located in the utility block near to terminal building; chilled
water headers will travel in the main service tunnel and reach to the terminal building
from where chilled water pipes will rise to individual floors to cater the air conditioning
loads.
The water chilling machines will not be selected for peak loads as these conditions
occur for a very limited period of time, which means that most of the time the water
chilling machines would be running under part load conditions and will not be most
efficient. In that case we propose to run fewer chillers at full capacity than to run all
chillers at partial capacity under partial condition to save on energy and space. This
will be achieved by proper sequencing of chillers during partial load condition so that
instead of running all the machines on part load, fewer machines are operated on full
load.
The chillers and pumps along with electrical panels shall be placed in the AC plant
room in the utility block, near to the terminal building and cooling towers for air
conditioning system shall be installed on terrace of AC plant room. All motors except
the chillers for air-conditioning system shall be energy efficient type, suitable for 415
+ 10% volts incoming power supply.
AC Plant machinery in the plant room shall be placed on PCC/RCC foundation and
provided with vibration supports. All foundations should be protected from
mechanical damage by providing epoxy coated angle nosing. Seismic restraints
requirement shall also be considered.
Floor drain channels and dedicated drain pipes in slope shall be provided within plant
room space for effective disposal of waste water.
2.7.4 Pipes
Chilled water shall be pumped through plant room to terminal building via insulated
chilled water pipes and enter into the terminal through service tunnel. All pipes shall
be supported in a manner, which will avoid transmission of vibration to roof ceiling
slab and occupied floors.
Closed type expansion tank shall be provided with air separator in chilled water line
and located at central AC plant room.
Selected air handling units (AHU) serving Departure, Arrival areas etc. shall be
variable volume type, double skin (for noise control) construction, comprising
centrifugal fans coupled to variable frequency drive, cooling coil section, stainless
steel double sloping drain pan (for zero water retention) and filter section. These shall
be floor-standing type with ducted arrangement for supply air. Return air shall be
collected through ceiling spaces / ducts and brought back to air handling unit room.
RPM of fan shall be modulated on the basis of occupancy and variation in ambient /
inside temperature.
Air handling units (AHU) serving Offices and normal occupancy areas shall be
constant volume double skin (for noise control) construction, comprising centrifugal
fan, cooling coil section, stainless steel double sloping drain pan (for zero water
retention) and filter section. These shall be floor-standing / ceiling suspended type
with ducted arrangement for supply air. Return air shall be collected through ceiling
spaces and brought back to air handling unit room.
All fresh air and exhaust air louvers shall be away from Airside of the Terminal
Building, in order to avoid ingress of fuel vapors.
The Air conditioning will be designed by using required quantity of outside air to
maintain indoor air quality as recommended by ASHRAE Standard 62 and NBC
2016. The outdoor air system would be controlled by VAV regulated by CO2 sensors
to maintain proper indoor air quality and save energy during high and low occupancy
periods. The outside air will be dehumidified to maintain humidity control. The outside
air will be duly filtered.
Plant rooms shall be provided with supply / exhaust fans for mechanical ventilation.
The system shall consist of tube axial fan, fresh air intake grilles with filters, air
distribution system with grilles, electrical panel, power cabling, control wiring and
earthing. Filtered fresh air shall be drawn from outside and supplied to mechanically
ventilated areas by means of grilles. Equivalent amount shall be directly exhausted
out.
All ducts shall be fabricated out of galvanized sheet steel (GSS) for long life and as
per fire norms. Motorized smoke dampers shall be installed within supply air ducts
and return air ducts at AHU room wall crossings, to prevent spread of smoke / fire to
the adjoining areas. Smoke dampers shall be motorized and shall be actuated by
smoke sensor as per fire regulations. Air handling units shall also be tripped in case
of emergency.
Internal lobbies and enclosed staircases shall be kept under positive pressure at all
times. This shall be achieved by supplying small quantity of cool fresh air at all times
and with no return air picked-up from these areas. This shall help in providing fire-
safe egress in case of emergency.
Selected air handling units / separate fans to be installed for serving open halls in
Departure & Arrival areas shall have provision for smoke extraction in case of
emergency. The AHU / separate fans shall extract the air / smoke into atmosphere
and be actuated through the fire alarm system.
a. Architecture measures
b. Landscape measures
c. Structural measures
d. HVAC & Electrical measures
e. Plumbing measures
f. Construction measures
The following codes & guidelines shall be considered for the design of the project for
GRIHA compliance
• Green Rating for Integrated habitat Assessment (GRIHA) rating system V-2015
• Energy Conservation Building Code 2007 (ECBC)
• ASHRAE 90.1-2010
• ASHRAE 62.1-2010
• National Building Code
Site Planning
a) Passive design strategies such as shading device, overhangs, vertical fins etc.
shall be considered to control heat gain through envelope and maximize day
light penetration.
b) Preservation of existing vegetation / water bodies / other topographical
features if applicable.
c) Strategies like Vegetation will be adopted in reduction of heat islands at
microclimate level.
d) Solar photovoltaics in roof areas as passive measure to heat gain reduction.
e) A minimum of 25% of the site area shall be designed with soft paved and/or
covered with SRI coating > 0.5 and/or shaded by vegetation/solar panels
and/or any combination of these strategies.
f) The net imperviousness factor of site shall designed to meet GRIHA
requirement to make post-construction storm water discharge from the site is
zero.
g) Internal zoning will be done to provide buffer to conditioned spaces for
unfavourable orientations.
h) Massing of the buildings will ensure that the solar access of neighboring
buildings is not blocked if applicable.
Construction Management
a) Top soil shall be preserved at site and shall be re-used later for landscaping
purpose.
b) No existing mature trees will be cut on site to the extent possible or mature
trees will be transplanted within the site and the survival shall be ensured or 3
trees will be planted for every 1 tree cut of the same native/naturalized species
or any combination of these for all mature trees on site.
d) A spill prevention plan (to control effects of spill from hazardous materials like
bitumen, diesel etc.) shall be developed and implemented at site.
e) Measures will be implemented to prevent/reduce soil movement outside the
site.
f) Staging shall be adopted during construction on site.
g) A construction waste management plan for segregation of construction waste,
its safe storage and on-site/off-site recycling shall be developed and
implemented in the project.
h) Strategies to reduce water use during construction shall be adopted.
Energy
a) The thermal properties of envelope (wall, glazing), skylight & roof shall not
exceed the maximum allowable with respect to GRIHA and ECBC.
b) Refrigerant used in HVAC system shall be CFC free.
c) Equipment efficiencies shall be designed to meet & exceed GRIHA & ECBC
requirements.
d) Innovative & practical energy efficient HVAC & Electrical design solutions, such
as displacement ventilation systems, dedicated outdoor air systems, chilled
water plant with high COP, adequate daylight to reduce internal lighting load,
LED luminaries etc shall be adopted
e) 100% of outdoor lighting fixtures shall meet the luminous efficacy requirements
with respect to GRIHA.
f) Interior lighting power budget shall be designed to meet and exceed GRIHA
requirements.
g) If there are ceiling fans required, they shall be minimum BEE 4 Star rated.
h) On-site renewable energy such as photo voltaic shall be designed to offset 1 to
10% of buildings internal artificial lighting and HVAC systems energy
consumption subject to feasibility.
i) Insulation in building shall be CFC and HCFC free.
a) Window to wall ratio of the façade shall be in compliance to GRIHA & ECBC and
the glazing SHGC values shall exceed the minimum performance with respect to
GRIHA & ECBC through passive shades and high performance glass.
b) Adequate daylighting provision will be considered by means of skylight / windows
and the daylighting illuminance level shall meet the minimum illumination levels
(LUX) prescribed in GRIHA & ECBC.
c) Acoustic measures shall be considered to meet acceptable indoor noise levels
with respect to GRIHA requirements.
d) Fire suppression systems & fire extinguishers shall be Halon free.
e) The HVAC design shall be in compliance with Thermal Comfort requirement
stipulated in GRIHA.
f) Acoustic measure shall be considered for the HVAC equipment’s to meet the
acceptable indoor noise level with respect to GRIHA.
g) Indoor ventilation requirement shall meet the minimum requirement with respect
to ASHRAE 62.1-2010.
h) Sensors shall be designed to monitor CO2, temperature and RH at occupied
spaces or at AHU’s.
i) All interior paints and coatings shall be low-VOC with respect GRIHA and lead-
free.
j) All adhesives and sealants used shall be low-VOC with respect to GRIHA & the
interior composite wood-products shall not use urea-formaldehyde as a bonding
resin.
Water
a) Minimum 15% of Ordinary Portland Cement shall be replaced with fly ash by
weight of cement used in structural concrete.
b) Minimum 15% of Ordinary Portland Cement shall be replaced with fly ash in
plaster/masonry mortar.
c) Combined embodied energy of load-bearing structure and masonry walls shall be
reduced by at least 10% below the base case.
d) At least 50% of all materials (calculated by surface area) used for building
interiors shall meet the GRIHA criterion low-impact material requirements.
Socio-Economic Strategies
a) Digital energy meters shall be provided for all major energy end-uses.
b) Water metering shall be provided for all major water use.
c) O&M protocol shall be prepared as a minimum for the following:
Daily water demand calculations for new integrated terminal building at Guwahati
Airport are given in Table 2.5 :
Table 2.5: Daily Water Demand Calculations for New Integrated Terminal
Building
S. Description Total Domestic Water Flushing Water Total
% Flow Flow to
No. Occupancy Water to Sewer
Sewer
No. LPCD LPD LPCD LPD LPD LPD
a. Water requirement 17800 40 712000 30 534000 1246000 80 996800
@ 70 Lit / person
for approximately
17800 passengers.
Fresh water requirement will be 710 KLD for domestic, food courts, retail, offices,
HVAC, etc. (Total water requirement including recycled water- 1010 KLD). Water
requirement will be extracted through bore wells at the airport.
Table 2.6: Water Consumption Summary & Treated Waste Water Recycle
. No. Description Round-Off
Treated water available from the STP @ 95% of Say 770 KL/Day
total sewer generation.
4. Cooling Tower Make -Up - Air Conditioning Say 470 KL/Day
Plant
Total diversify HVAC load 3300 TR.
Water requirement = 3300*24 hr*10 ltrs/hr*0.6 =
470 KLD
5. Flushing Water Requirement Say 440 KL/Day
Conclusion:
The water balance diagram is shown in Figure 2.7. The water requirement for
flushing and HVAC/cooling will be met through reuse of treated waste water from
STP.
Figure 2.7: Water Balance Diagram for New Integrated Terminal Building
As per water balance diagram, 810 kl/d sewage will be generated after the
operation of integrated terminal building which will be treated in STP of capacity
1000 kl. Membrane bioreactor (MBR) Technology will be used for treatment of
waste water at the airport.
2.11 Drainage
For design of drainage at the site of the proposed integrated terminal building,
Hydraulic calculations have been carried out. For storm water management at the
site, rectangular sections for side drains have been provided. The drains have been
kept sufficiently away from the taxiway / runway.
The schematic diagram of proposed drainage system is provided in Figure 2.9. The
drainage system would constitute of four storm water RCC rectangular drains. The
drain designated as Drain D1 shall be connected to the existing drain near western
side compound wall and further discharged to the existing canal on the northern side.
Similarly, the drain D2, D3 & D4 shall be discharged to the existing canal on the
northern side.
At the Guwahati airport, ground water table is about 2-3 m below the general ground
level in this area. Hence, the provision of rainwater harvesting in the form of recharge
trench pits and wells will be avoided.
The estimated cost of new integrated terminal building and associated development
is estimated as Rs 1232 Cores.
The total estimated manpower requirement for construction and operation phases of
the New Integrated Terminal Building is given in Table 2.7:
Chapter 3
Description of Environment
3.1 Introduction
Physical, biological and socio-economic baseline environmental conditions have been studied
within the 10 km radius study area from the LGBI Airport Terminal at Guwahati.
The baseline studies were carried out from 3rd October 2016 to 31st December 2016.
Collection of baseline information on bio-physical, social and economic aspects of the project
area is the most important reference for conducting Environmental Impact Assessment (EIA)
study. Based on the existing environmental scenario potential impacts of LGBI Airport
Terminal at Guwahati will be identified and accordingly management plan will be proposed.
The description of environmental settings includes the characteristic of area in which the
activity of expansion of LGBI Airport Terminal at Guwahati would be occur and cover area
affected by all environmental impacts. For conducting the EIA, existing environmental
conditions in the study area, have been obtained by intensive site visits, primary data
collection, monitoring, sampling and secondary data collection from published source and
various government agencies. Collection of baseline data was designed to satisfy information
requirements and focused on relevant aspects that are likely to be affected in the study area.
Overall topography of the area varies from plain to undulating. The southeastern part of the
study area is hilly and steep undulating converging to flat terrain towards the river
Brahmaputra located northern part of the study area. The River Brahmaputra is flowing at a
distance of 2.2 km from northeast towards west of the site. The terrain is dotted with small hills
to residual hillocks.
Physiographically the study area can be divided into three units; i.e. the hilly region in the
southeast, the alluvial plain in the central and southwestern part and the swampy areas along
Brahmaputra plains. The distinguishable geomorphic units are as follows:
Elevation:
The general elevation of the project site is around 50m above msl and the study area the
elevation varies from 40m to 410m above msl. The highest elevation is towards southeast
where the Garbhanga forest hills are situated and rest of the study area is predominantly flat
with 50m contours.
Drainage:
The Brahmaputra River is the trunk drainage of the Guwahati which is situated on the south
bank of the river. The river flows from east to west splitting Guwahati into north Guwahati and
south Guwahati. The Brahmaputra River is a braided river and is composed of numerous
sediment bars which cover half of the river. Several small streams such as the Kopili, Banasiri,
Bhareli, Dhansiri, Ranga nadi, Puthimari and Manas join the Brahmaputra River from both
Himalayas and Shilong subbasin. The Rivers cover about 60 sq km of the area including the
sediment bars. The river course covers around 17 % of the total study area. An overall
drainage drainage of the Brahmaputra river is shown in the below Figure 3.1.
The local drainage network of study area is shown in the Figure 3.2 indicating dominence of
Brahmaputra river basin with number of streams joining the main river. The drainage network
in the study area is reflecting both dentritic and parallel. The contour map is shown in the
Figure 3.3.
Assam is among the most seismically active parts of India. Geomorphologically, northeast
India is located in an earthquake prone zone (zone V) of the Indian subcontinent. In this region
earthquakes come with land slides, floods along with series of earthquakes of smaller
magnitude. Here earthquakes of up to MM intensity IX can be expected. According to a hazard
map by the Global Seismic Hazard Assessment Program, the state can expect to have a peak
gravitational acceleration (PGA) of 0.24g to 0.48g. The sesmic map of the area is given In
Figure 3.4.
3.4 Geology
The Guwahati is geologically an extension part of the shillong plateau of the Pre Cambrian
Age. Geologically, the city is characterized by Precambrian granite gneissic complex
composed of granite gneiss, biotite schists, gneiss and quartzite.
Geologically the area is a north-eastern continuation of the Pre Cambrian Gneissic Complex of
the Shillong Plateau. The Shillong Plateau is an extension of the Indian shield separated
tectonically by the Garo Rajmahal Gap. The study area is covered by Recent Alluvium and the
Precambrian rocks are exposed in the residual hills. The Recent Alluvium consists of cobbles,
pebbles, sands of various grade, silt and clay. Lithological heterogeneity is reflected by
presence of a variety of rock types. These rocks can be categorized broadly into two types:
Granitic Rocks
• Biotite schist
• Hornblende- biotite schist
• Amphibolite
Quartzofeldspathic gneiss (QFG) and granites constitute the predominant rock types of the
area. QFG show inhomogeneous appearance and colour variation. They are light grey to
whitish grey in colour marked by well developed bands of dark and light coloured minerals. In
some cases the bands are very prominent, the bands being about 5 cm in thickness, while in
some cases appearance is streaky. The rocks are medium grained; rarely fine and coarse
grained.
Granites include the grey porphyritic granite of Kamakhya Hills, Garchuk and pink granite of
Kalapahar area. Granitic veins in the form of sills and dykes occur in the porphyritic granite.
The grey granite of Kamakhya is found in contact with the granite gneiss. But the pink granite
occurs in association with the QFG and porphyritic granite. One of the characteristic features
of these granites is that they occur at relatively higher elevation. Fine grained granite found in
association with the granite gneiss and grey porphyritic granite occurs in Nabagraha Hill side,
Dispur and Jalukbari area.
Quartzites are limited in extent and small dimension quartzites are found in the Kamakhya
foothills and Nabagraha. Pegmatites of varied dimension occurring as lenses and veins are
found almost in all quarries. Quartz veins are also common.
Climate of the region is characterized in the following sections on the basis of nearest Indian
Meteorological Department (IMD) observatory station at Guwahati on the basis of the
observation: 1971-2000.
3.5.1 Climatology
The climatological summary details of parameters like temperature, relative humidity, rainfall,
cloud cover, wind speed and wind direction were obtained for IMD Guwahati as given in Table
3.1:
Table 3.1 Climetological Summary at IMD Guwahati (1971-2000)
Month Daily mean Relative Rainfall (mm) Cloud
Speed (km/h)
0
Temp. ( C) Humidity cover (in Station Level
Mean Wind
No. of
Rainy
17:30
17:30
17:30
Total
days
8:30
8:30
8:30
Max
Min
January 23.6 10.6 87 70 11.5 1.2 2.3 3.2 2.0 81 81 1011.3 1007.2
February 26.0 12.2 76 55 22.3 2.2 2.3 3.1 2.7 64 61 1009 1004.8
March 29.8 15.9 66 48 50.9 4.3 2.6 3.3 4.0 41 40 1006.0 1001.3
April 31.0 20.0 73 60 159.3 9.2 4.1 4.1 4.9 27 23 1003.5 998.5
May 31.0 22.5 79 70 256.3 13.3 5.4 4.8 4.1 29 30 1000.6 996.3
June 31.9 24.9 83 77 303.6 14.4 6.4 6 3.4 36 35 996.3 992.7
July 31.8 25.5 85 80 356.8 16.8 6.7 6.2 3.1 40 34 996.1 992.7
August 32.2 25.5 83 80 258.6 12.6 6.4 6.1 3.1 44 37 997.4 993.9
September 31.5 24.5 84 81 194.4 10.5 5.9 5.8 2.7 48 51 1001.7 997.7
October 30.3 22.0 83 79 103.9 4.9 4.4 4.1 2.6 45 71 1006.2 1002.1
November 27.7 17.0 84 78 18.4 1.3 3.2 3.1 2.3 60 83 1009.6 1005.7
December 24.6 11.9 87 77 7.4 0.6 2.2 2.7 1.8 78 83 1011.9 1007.9
Annual or 29.3 19.4 80.8 71.3 1743.4 91.3 4.3 4.4 3.1 49.4 52.4 1004.1 1000.1
Mean
Source: Indian Meteorological Department (IMD)
Relative Humidity
The Relative Humidity (RH) at 8:30 hrs varied from (66% in March) to 87% (in December)
while at 17:30 hrs it varied from 48% (in March) to 81% (September). The annual RH
varied from 71.3 % (in 17:30 hrs) to 80.8% (In 8:30 hrs). Graphical Presentation of Relative
Humidity is shown in Figure 3.5.
The monthly mean wind direction varied from 4.9 to 1.8 km/hr occurring in April and
December respectively. The calm winds at 8:30 minimum 27% in April and maximum 81%
in Janauary while at 17:30 hrs minimum 23% and Maximum 83% in April and December
respectively. The table shows to equality of the calm percentage in morning and evening.
Wind direction is genraly North West (NW). The windrose diagrams for October, November
and December for morning and evening at IMD Guwahati are shown in Figure 3.6.
Cloud Cover
Cloudy condation were observed during monsoons monts reaching to 6.7 Oktas in July
and min 2.2 in December. The sky was slightly cloudy during orther months. Graphical
Presentation of Cloud Cover is shown in Figure 3.7.
Temperature
The monthly mean temperature varied from 19.4 OC to 29.3OC where minmum 10.6 OC in
Janauary month and maximum in 32.2 OC in August months. Graphical Presentation of
Temperature is shown in Figure 3.8.
Rainfall
The climatological data revealed that rainfall occurred maximum in 356.7mm in July and
7.4mm in December. The total rainfall recived in the year is abour 1743.4 mm with total
number of rainy days of about 91.3 days. Graphical presentation of the rainfall is shown in
Figure 3.9.
The micrometeorological data has been collected on hourly basis during winter season (Oct,
Nov and Dec.2016). The parameters covered are temperature, relative, humidity, wind speed,
wind direction and rainfall. The summary of micrometeorological data is given in Table
3.2.
Table 3.2: Site Specific Meterologocal Data
Location: Observations
S. No.
Parameters 01.10.2016 to 31.12.2016
Dry Bulb Temperature (°°C)
Maximum 32
1
Minimum 11
Average 24.5
2 Relative Humidity (%)
Maximum 87.0
Minimum 44.0
Location: Observations
S. No.
Parameters 01.10.2016 to 31.12.2016
Average 71.4
Wind Speed (Km/h)
Maximum 4.2
Minimum 0.5
3 Average 3.1
Predominant Wind Direction (From) NE
Percentage of calm wind 74.8
Rainfall(mm)
4
During Study Period 1.5
The site specific micro meterologocal parameter for the monitoring season revealed that the
maximum temperature was recorded as 320C and minmum as 110C. The relative humidity was
recorded to be varying between 44 to 87%. The wind speed was recorded in the range
between 0.5 to 4.2 kmph. The predominant wind direction during study seasion was from NE.
Wind rose diagram for the project site is given in Figure 3.10:
3.6 Soil
The soil type found in the study area is mainly sandy, silty and clay type. Soil sampling was
carried out to establish the baseline characteristics and to assess the anticipated impacts due
to proposed project.
The soil quality assessment study has been carried out during study period to determine the
potential of soil in the area and to identify the impacts of the proposed expansion of airport on
soil quality.
For studying soil characteristics of the area, sampling of five locations were selected to assess
the baseline soil conditions in the study area. The physical, chemical and nutrient
characteristics of soil samples were determined. The samples were collected on 18/11/2016
by ramming a core-cutter into the soil up to a depth of 15 cm.
The sampling locations have been identified with the following objectives;
Soil samples collected from each location were mixed to make composite sample that were
analyzed. Details of the soil sampling locations are shown in Table 3.3. The soil sampling
locations in the study area are shown in Figure 3.11.
The results of analysis of soil samples collected in the study area are given in Table 3.4, with
a brief interpretation of analyzed parameters is given below:
Texture: Soil in the study area are sandy, silty loam, sandy clay, clay loam in texture.
pH: The pH of soil in the study area ranges from 5.68 to 6.78.
Electrical Conductivity: The Electrical conductivity of soil in the study area ranges from
0.036 to 0.096 µS/cm.
Bulk Density: Bulk density of soil in the study area is ranges from 1.27 to 1.41 gm/cc.
Available Nitrogen: Available Nitrogen content in soil in the study area ranges from 19.2 to
46.4 kg/ha.
Potassium: Potassium content in soil in the study area ranges from 158 to 232 kg/ha.
Exchangeable Calcium: Exchangeable Calcium content in soil in the study area ranges from
9.64 to 17.2 meq/100g.
Exchangeable Sodium: Exchangeable Sodium content in soil in the study area ranges from
0.31 to 0.65 meq/100g.
Total Organic Matter: Total Organic Matter content in the study area ranges from 0.97 to
1.74%.
1 pH (1:5 Suspension) IS -2720(Part 26) 1987(RA 2011) 6.35 6.47 6.78 6.61 5.68
In the study area, the major surface water body is Brahmaputra River and followed by number
of streams and lakes covering about 9.17% of the study area.
The area consists of two broad hydrogeological units: 1) Pre-Cambrian consolidated rocks and
2) Quaternary alluvium consisting of unconsolidated sediments.
Pre-Cambrian consolidated rocks are confined to hilly areas and inselbergs, where ground
water occurs in shallow weathered zone and this can be developed through open wells. The
joints and fractures developed due to tectonic activities form potential water bearing zones and
suitable for development through construction of bore wells. In the alluvial plain, groundwater
occurs in regionally extensive aquifers down to the depth of 305 m. It has a very good yield
prospect. The aquifers are consisting of sands of various grades with gravel and are suitable
for construction of both shallow and deep tube wells. The water level rests at shallow depth
and in major parts of the study area, it rests between 2 – 5 m bgl during pre-monsoon period.
The study of long term water level trend shows no significant change in rise/fall in water level
in the last 10 years.
The shallow tube wells tapping aquifers within 50 m depth are capable of yielding about 10 lps
in major places, deep tube wells constructed within 95 m depth tapping about 30 m granular
zones are yielding 10 – 20 lpm. The transmissivity of the aquifer ranges from 41 to 6162
m2/day and the permeability varies from 10 to 59 m/day. In hard rock, the yield of bore well
constructed in greater Guwahati area ranges from 4 to 300 lpm.
Thick and extensive alluvial deposit with rich aquifer system covering major part of the district
is suitable for ground water development through open wells, shallow tube wells and deep
tube wells. To meet the drinking and other requirements of limited quantities of individual
households, open wells and filter point wells are feasible almost in all parts of the study area,
except the areas occupied by hills. Ring wells of 0.80 to 1.20 m diameter to depth of 5 to 10 m
bgl are likely to hold sufficient quantity of water to meet the requirement. Filter point wells to
the depth of about 20 to 25 m bgl by providing galvanized iron/PVC pipes with slotted pipes
against the granular zones are suitable for extraction of groundwater for domestic use.
In the majority of the villages in the study area depends on the groundwater and some of the
villages have piped water supply for their domestic needs.
Surface water sample analysis results are given in Table 3.6. Analysis results for surface
water sample have been compared with Tolerance limits for Inland surface waters, Class C
and Class E. (IS 2296- 1992) as given in Table 3.6.
The following observations can be made from the tabulated data in Table 3.6.
pH value of all surface water samples ranges from 6.54 to 7.13 and meet the tolerance limits
of 8.5 for inland surface waters (IS: 2296-1992).
TDS value of all surface water samples ranges in the range of 55 to 160 mg/l, respectively and
meet the tolerance limits of 1500 mg/l for inland surface waters (IS: 2296-1992) for Class C.
Conductivity: Conductivity value of all surface water samples varies 86 to 294 μS/cm and
meets the tolerance limits for inland surface waters, (IS: 2296-1992) for Class –E.
Total Hardness: Total Hardness of all surface water samples ranges from 12 to 86 mg/l. No
limit has been prescribed in IS:2296-1992 for hardness in surface water.
Sulphate: Sulphate content in all surface water samples ranges between 1 and 18 mg/l and
meet the tolerance limits of 400 mg/l for inland surface waters, (IS: 2296-1992) for Class C.
Colour: Colour content in all surface water samples ranges between <0.1 and 12 Hazen unit
and meet the tolerance limits of 300 Hazen unit for inland surface waters (IS: 2296-1992) for
Class C.
Chloride as Cl: Chloride content in all surface water samples range between 9 and 35 mg/l
and meet the tolerance limits of 600 mg/l for inland surface waters (IS: 2296-1992) for Class
C.
Iron as Fe: Iron content in all surface water samples range between 0.05 mg/l to 0.57 mg/l
and meet the tolerance limits of 50 mg/l for inland surface waters (IS: 2296-1992) for Class C.
Zinc as Zn: Zinc content in all surface water samples range between 0.1mg/l to 0.26 mg/l and
meet the tolerance limits of 15 mg/l for inland surface waters (IS: 2296-1992) for Class C.
Sodium as Na: Sodium content in all surface water samples range between 9 mg/l to 29 mg/l.
No limit has been prescribed in IS:2296-1992 for Sodium in surface water.
Potassium as K: Potassium content in all surface water samples range between 1.1 mg/l to
2.3 mg/l. No limit has been prescribed in IS:2296-1992 for Potassium in surface water.
Calcium as Ca: Calcium content in all surface water samples range between 3.1 mg/l to 16
mg/l. No limit has been prescribed in IS:2296-1992 for Calcium in surface water.
Magnesium as Mg: Magnesium content in all surface water samples range between 1 mg/l to
9.5 mg/l. No limit has been prescribed in IS:2296-1992 for Magnesium in surface water.
Dissolved Oxygen: Dissolved Oxygen content in all surface water samples range between
6.6 mg/l to 7.5 mg/l and minimum meet the tolerance limits of >4 mg/l for inland surface waters
(IS: 2296-1992) for Class C.
Turbidity: Turbidity content in all surface water samples range between 0.5 to 20.9 NTU. No
limit has been prescribed in IS:2296-1992 for Turbidity in surface water.
BOD: BOD content in all surface water samples found below 2 mg/l and meet the tolerance
limits of 3 mg/l for all inland surface waters (IS: 2296-1992) for Class C.
Nitrate: Nitrate content in all surface water samples ranges between 1.7 to 5.3 mg/l and
meets the tolerance limits of 50 mg/l for all inland surface waters (IS: 2296-1992) for Class C.
Total Alkalinity: Total Alkalinity content in all surface water samples ranges between 18 to 85
mg/l and no limit has been prescribed in IS:2296-1992 for total alkalinity in surface water.
Total Coliform: Total Coliform content in all surface water samples ranges between 18 to 94
mg/l and meets the tolerance limit of 5000 MPN/100 ml in IS:2296-1992 for total coliform in
surface water for Class C.
Under natural conditions, surface water quality reflects environmental conditions to a great
extent. Hydro-geochemical factors influence colour, odour, taste, temperature and the degree
of mineralisation of water derived from surface run off, springs, etc. Besides, human
settlements, overall land use, morphology of the basin area, seasonal distribution of rainfall
and winds, disposal of industrial effluents and sewage, etc. contribute a great deal in
determining the quality of water. The quality of ground water is influenced by surface and sub-
surface environmental conditions. The quantity and quality of water entering the underground
regime is another important parameter which influences underground water quality. Rainfall
absorbs atmospheric pollutants during its descent through the atmosphere.
During the study period, eight (08) ground water samples were collected from the study area.
The locations of ground water sampling are given in Table 3.8 and shown in Figure 3.12.
The analysis results for ground water samples are given in Table 3.9. Indian Standard
Specification for Drinking Water (IS 10500-2012) are given in Table 3.19.
pH: The pH value of ground water samples was found in the range 6.52 to 7.44 and meets
the drinking water acceptable limit of 6.5 to 8.5.
Colour: The colour of ground water samples was found between <1 to 3 hazen unit and
meets the acceptable limit of 5 hazen unit for drinking water standard.
Turbidity: The turbidity of ground water samples was found in the range of <0.5 to 2.8 NTU
and meets the permissible limit for drinking water standard.
Total Dissolved Solids (TDS): TDS of ground water samples were found in the range 72 to
257 mg/l and meets the acceptable limit of 500 mg/l in the absence of alternate source.
Calcium: Calcium content in ground water samples was found in the range 8 to 33 mg/l and
meets the acceptable limit of 75 mg/l.
Magnesium: Magnesium content in ground water samples was found in the range 4.4 to 19
mg/l meets the acceptable limit of 30 mg/l.
Sodium as Na: Sodium content in ground water samples was found in the range 14 to 35
mg/l. No limit has been prescribed for Sodium as per Drinking Water Standards : IS
10500;2012.
Potassium as K: Potassium content in ground water samples was found in the range 1 to 2.1
mg/l. No limit has been prescribed for Potassium as per Drinking Water Standards: IS
10500;2012.
Iron: The iron content in ground water samples was found in the range <0.05 to 0.1 mg/l and
found within the acceptable limit of 0.1 mg/l for drinking water.
Total Alkalinity: Total alkalinity values ground water samples were found in the range 50 to
87 mg/l and meets the acceptable limit of 200 mg/l in the absence of alternate source.
Total Hardness: Total hardness values ground water samples were found in the range 34 to
161 mg/l and meets the acceptable limit of 200 mg/l.
Chloride: Chloride content of ground water samples was found the range 9.8 to 83 mg/l and
meets the acceptable limit of 250 mg/l in the absence of alternate source.
Fluoride: Fluoride content of ground water samples was found in the range <0.1 to 0.67 mg/l
and meets the acceptable limit of 1 mg/l in the absence of alternate source.
Sulphate: Sulphate content in ground water samples was found in the range 2 to 26 mg/l and
meets the acceptable limit of 200 mg/l in the absence of alternate source.
Nitrate: Nitrate content in ground water samples was found in the range 2 to 14 mg/l and
meets the acceptable limit of 45 mg/l for drinking water.
Copper: Copper content of water sample was found below <0.03 mg/l and meets the
acceptable limit of 0.05 mg/l for drinking water.
Zinc: Zinc content of water sample was found in the range 0.05 to 0.14 mg/l and meets the
acceptable limit of 5 mg/l for drinking water.
Conclusions: The results of analysis ground water samples were compared to Indian
Standard Specification of drinking water IS: 10500:2012. The monitored parameters are within
the IS: 10500:2012.
Table 3.10: Indian Standard Specification for Drinking Water (IS 10500-2012)
Sl. Characteristic Requirement Permissible Protocol
No. (Acceptable Limit in the
Limit) Absence of
Alternate
Source
I Organoleptic and Physical Parameters
i) Colour, Hazen units, Max 5 15 IS 3025 (Part 4)
ii) Odour Agreeable Agreeable IS 3025 (Part 5a)
iii) pH value 6.5-8.5 No relaxation IS 3025 (Part 11)
iv) Taste Agreeable Agreeable IS 3025 (Part
7&8)
v) Turbidity, NTU, Max 1 5 IS 3025 (Part 10)
vi) Total dissolved 500 2000 IS 3025 (Part 16)
solids, mg/l, Max
II General Parameters Concerning
Substances Undesirable in Excessive
Amounts
i) Aluminium (as Al), mg/l, 0.03 0.2 IS 3025 (Part 55)
Max
ii) Ammonia (as total 0.5 No relaxation IS 3025 (Part 34)
ammonia-N), mg/l, Max
iii) Anionic detergents (as 0.2 1.0 IS 13428
MBAS) mg/l, Max
iv) Barium (as Ba), mg/l, Max 0.7 No relaxation IS 15302
v) Boron (as B), mg/l, Max 0.5 1.0 IS 3025 (Part 57)
vi) Calcium (as Ca), mg/l, Max 75 200 IS 3025 (Part 40)
vii) Chloramines (as Cl2), mg/l, 4.0 No relaxation IS 3025 (Part 26)
Max IS
viii) Chloride (as Cl), mg/l, Max 250 1000 IS 3025 (Part 32)
ix) Copper (as Cu), mg/l, Max 0.05 1.5 IS 3025 (Part 42)
x) Fluoride (as F) mg/l, Max 1.0 1.5 IS 3025 (Part 60)
xi) Free residual chlorine, mg/l, 0.2 1 IS 3025 (Part 26)
Min
xii) Iron (as Fe), mg/l, Max 0.3 No relaxation IS 3025 (Part 53)
xiii) Magnesium (as Mg), mg/l, 30 100 IS 3025 (Part 46)
Max
xiv) Manganese (as Mn), mg/l, 0.1 0.3 IS 3025 (Part 59)
Max
xv) Mineral oil, mg/l, Max 0.5 No relaxation IS 3025 (Part 39)
xvi) Nitrate (as NO3), mg/l, Max 45 No relaxation IS 3025 (Part 34)
xvii) Phenolic compounds (as 0.001 0.002 IS 3025 (Part 43)
C6H5OH), mg/l, Max
xviii) Selenium (as Se), mg/l, 0.01 No relaxation IS 3025 (Part 56)
Max
xix) Silver (as Ag), mg/l, Max 0.1 No relaxation IS 13428
xx) Sulphate (as SO4) mg/l, 200 400 IS 3025 (Part 24)
Max
xxi) Sulphide (as H2S), mg/l, 0.05 No relaxation IS 3025 (Part 29)
Max
xxii) Total alkalinity as Calcium, 200 600 IS 3025 (Part 23)
mg/l, Max
xxiii) Total hardness (as 200 600 IS 3025 (Part 21)
CaCO3), mg/l, Max
xxiv) Zinc (as Zn), mg/l, Max 5 15 IS 3025 (Part 49)
III Parameters Concerning Toxic Substances
The ambient air quality with respect to the study area has baseline information. The study
area represents mostly urban, rural/residential environment. The sources of air pollution in
the region are vehicular traffic, engines and DG sets, aircraft opearion, dust arising from
domestic fuel burning. The prime objective of the baseline air quality study is to establish the
existing ambient air quality in study area. This will also be useful for assessing the
conformity to standards of the ambient air quality specified by CPCB.
This section describes the identification of sampling locations, methodology adopted for
monitoring and frequency of sampling. The results of monitoring during the study period are
also presented in this section.
The baseline status of the ambient air quality has been established through a scientifically
designed ambient air quality monitoring network and is based on the following
considerations:
Ambient air quality monitoring (AAQM) stations were set up at 8 locations with due
consideration to the above mentioned points. The locational details of ambient air quality
monitoring locations are as given in Table 3.11 and shown in Figure 3.13.
Ambient air quality monitoring has been carried out with a frequency of two days per week at
8 locations during the study period. The baseline data of air environment is monitored for the
below mentioned parameters:
• Ammonia (NH3);
• Ozone (O3);
• Lead (Pb);
• Nickle (Ni);
• Arsenic (Ar);
• Benzene; and
• Benzo @ Pyrine
The techniques adopted for sampling and analysis are given in Table 3.12 along with the
minimum detection limits for each parameter.
The ambient air quality monitoring was carried out eight locations in order to assess the
present air quality of the stydy area. Ambient quality monitoring results are given in Table
3.13 to Table 3.20. National ambient air quality standards are presented in Table 3.22. On
the basis of tabulated results, the following observations can be made:
Out of 8 monitoring locations with in the study area, maximum and minimum concentrations
for PM10 are 106 µg/m3 and 56 µg/m3, respectively. The mean PM10 concentration was
reorded as 79 µg/m3. The 98 %tile value of PM10 was 103 µg/m3.
Out of 8 monitoring locations with in the study area, maximum and minimum concentrations
for PM2.5 are 66 µg/m3 and 35 µg/m3, respectively. The mean PM2.5 concentration was
reorded as 48 µg/m3. The 98 %tile value of PM2.5 was 63 µg/m3.
The maximum and minimum concentrations for SO2 are 11.2 µg/m3 and 5.1 µg/m3,
respectively. The mean SO2 concentration was reorded as 6.8 µg/m3. The 98 %tile value of
SO2 was 10.8 µg/m3.
The maximum and minimum concentrations for NO2 are 19.6 µg/m3 and 7.5 µg/m3,
respectively. The mean NO2 concentration was reorded as 13.2 µg/m3. The 98 %tile value of
NO2 was 18.9 µg/m3.
The maximum and minimum concentrations for CO are 0.38 µg/m3 and 0.1 µg/m3,
respectively. The mean CO concentration was reorded as 0.18 µg/m3. The 98 %tile value of
CO was 0.32 µg/m3.
Ammonia (NH3)
Ammonia level were below detection limit (<5.0 µg/m3) at all the locations.
Ozone (O3)
Ozone level were below detection limit (<5.0 µg/m3) at all the locations.
Other Components
Lead, Arsenic, Nickel, Benzene and Benzo-pyrene concentrations were below detection limit
at all the locations.
National ambient air quality standards for rural, residential, industrial area and other area for
PM10 and PM2.5 are some time exceeding. However, most of time, values of PM10 and PM2.5
are within the National Ambient Air Quality Standrads for PM10 and PM2.5. Monitored values
for SO2, NO2 and CO are within the National Ambient Air Quality Standrads. The monitored
values for Ammonia (NH3), Ozone (O3), Lead (Pb), Nickle (Ni), Arsenic (Ar), Benzene, and
Benzo @ Pyrine are below the detection limit.
During the study period, preliminary reconnaissance survey was undertaken to identify the
major noise generating sources in the area. The noise at different noise generating sources
has been identified based on the Industrial, commercial and residential activities, traffic and
noise at sensitive areas.
Sound Pressure Level (SPL) measurements were undertaken at all locations, with an
interval of about 5 seconds over a period of 10 minutes per hour for 24 hr. The day noise
level has been monitored during 6 AM to 10 PM and night levels during 10 PM to 6 AM at all
locations.
On the spot measurement device manufactured by Castle Associates, England was used.
The sound level meter measures the Sound Pressure Level (SPL), the maximum sound
pressure level (Max) and the equivalent continuous noise level (Leq) by switching on the
corresponding function mode. Time constant for fast, slow, impulse and peak responses are
provided and the suitable response conditions can be selected by operating other switch.
The operation of a resetting button permits to erase the maximum hold and integrated
values.
For noise levels measured over a given period of time interval, it is possible to describe
important features of noise using statistical quantities. This is calculated using the percent of
the time certain noise levels are exceeded during the time interval. The notation for the
statistical quantities of the noise levels are described below:
The Leq is the equivalent continuous sound level, which is equivalent to the same sound
energy as the actual fluctuating sound measured in the same period. This is necessary
because sound from noise source often fluctuates widely during a given period of time. This
is calculated from the following equation:
3-47
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
Also:
• Lday is defined as the equivalent noise level measured over a period of time during day (6
AM to 10 PM).
• Lnight is defined as the equivalent noise level measured over a period of time during night
(10 PM to 6 AM).
Hourly measurements have been carried out in day and night time at Project Site, Garal,
Majir Gaon, Azara, Kahi Kuchi, Palasbari, Pasania Para, Kaita Sidhi locations during study
period. Noise Measurement locations are given in Table 3.23 and shown in Figure 3.14.
Day and night-time Leq have been calculated from measured hourly leq values. Day and
night time Leq at monitoring locations are given in Table 3.24. Ambient standards in respect
of noise are given in Table 3.25.
Table 3.24 gives the day and night-time Leq noise levels. The measured Leq noise levels
are below the prescribed limit stipulated for commercial area at the Guwahati Airport
Terminal and Residential area at Garal, Majir Gaon, Azara, Kahi Kuchi, Palasbari, Pasania
Para, Kaita Sidhi in the study area.
3-48
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of India Description of
Environment
3-49
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
The mapping of land use and land cover of the area falling within the 10 km buffer zone of
the proposed project is undertaken with the help of topographical data, satellite data and
field studies.
The land use and land cover (LULC) map have been prepared by adopting the interpretation
techniques of the image in conjunction with collateral data and ground truth. Image
classification was done by using visual interpretation techniques and digital classification
using ArcGIS 9.3.1 image processing software. LANDSAT 8 image were acquired and used
to evaluate LULC changes. The image processing software is used for preprocessing,
rectification, and classifying the satellite data for preparation of land use land cover map for
assessing and monitoring the temporal changes in land use land cover and land
developmental activities.
The land use map covering the study area is given as Figure 3.15 and land use pattern are
tabulated in Table 3.26. The distribution of land use land cover categories in the study area
in Figure 3.16
3-50
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of India Description of
Environment
Figure 3.15 : Land Use Land Cover Within the Study Area
3-51
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
The above table indicates that, more than 50% of the study area is covered by vegetation &
agriculture covering and followed by marshy land (11.59.9%), Settlement (9.26%), water
body (9.17%) and dry river bed (9.17%), whereas the open shrub land is 4.85% in the study
area.
Generally, biological communities are good indicators of climatic and edaphic factors
because of their strong relationships with them. The studies on the biological aspects of the
ecosystem are important in Environment Impact Assessment studies for the suitability of
natural flora & fauna. Information on the impact of environment stress on the community
structure serves as an inexpensive and efficient early warning system to check the damage
on a particular ecosystem. The biological environment includes mainly terrestrial and
aquatic ecosystem.
Assam state is part of the transition zone between the Indo-Malayan and Indo-Chinese
biogeographical regions. Favorable climate, topographic and edaphic factors support
luxuriant growth of diverse plant communities and create varied habitats. The project site is
located in Guwahati city in Kamrup district of Assam. The Brahmaputra river flows in east to
3-52
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
west direction and others like Kulsi river flows towards southern side. Water bodies like
Deepor beel, Dighori Beel lie in the buffer zone.
3.12.1 Objectives
The objectives of ecological study during the study period may be outlined as follows:
• To characterize the environmental components like land, water, flora and fauna;
• To understand their present status;
• To understand carrying capacity of the ecosystem;
• To assess present bio-diversity; and
• To identify susceptible and sensitive areas.
This study has been carried out during the early spring season during January 2017 during
study period for the purpose of providing an independent and comprehensive baseline
assessment of the flora, terrestrial vertebrate, aquatic fauna and associated habitat values
of the site and within 10 Km radius area around the Guwahati Airport terminal and a
subsequent assessment of potential ecological impacts from the proposed plant activities.
The study area falls under North East as far as the Indian Biogeographical Zones (Rodger,
Panwar, and Mathur 2000) are concerned. Under the biogeographical provinces, the study
area falls under the category of 9A- North East- Brahmaputra Valley. The study area of 10
km radius does have Garbahnga Forest land and the main land use feature of the study
area is comprised habitation and cultivating lands. From the primary observations, the tree
species recorded in the forest were Lagerstroemia flos reginae (Ajhar), Cocos nucifera
(Coconut), Shorea robusta (Sal), Borassus flabellifer (Tal), Bombax malabaricum (Simul)
etc.
The detailed ecological assessment of the study area has been carried out with the following
objectives:
• To establish the present status of ecological conditions surrounding the project location;
• To study the existing anthropogenic stresses on the prevailing ecosystem.
• To identify and predict the likely impacts on the local ecosystem from the proposed
activities;
• To list out floral species, terrestrial vertebrate and aquatic flora and fauna present within
the study area, and significance status under The Wildlife (Protection) Act, 1972;
• To define ecological/conservation status of each species as per IUCN categories (Red
Data List).
• To formulate mitigatory measures and a sustainable Environmental Management Plan
(EMP) basing upon the likely impacts.
3-53
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
3.12.2 Methodology
Terrestrial investigations for flora and fauna records were collected by random field survey
and a checklist was prepared. During field survey, discussions with the local people were
carried-out to collect information related to local biodiversity in and around the villages. The
ecological status of the study area has been assessed based on the following methodology:
3-54
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
10m X 10m for tree species (record trees >25 cm in GBHOB /species);
3m X 3m [four plots] was laid along diagonals wherein all the shrubs recorded.
1m X 1m [five plots], one at the centre and four at one per quadrate] was laid and
herbs, grasses in five plots to be noted.
The standard method chosen for the assessment of plant diversity involves the use of
square vegetation quadrates (‘plots’). These quadrates were used to measure most
vegetation attributes in most vegetation types. Quadrate locations marked by pegs or
sometimes by grid system.
The study area is demarcated as 10 km from the periphery of project area based on the
MoEF&CC guidelines. After demarcation, the study area is divided into sampling units, i.e.
the areas which are approximately true representative of the whole area, and were sampled
for the identification of plant and animal species.
A. Floral Study
The assessment of the flora of the study area is done by an extensive field survey of the
area.
• Plants species were identified based on their specific diagnostics characters of family,
genus and species using available floral, other related literature and herbarium Botanical
Survey of India (BSI).
• Besides the identification of plant species, information was collected on the vernacular
names and uses of plants made by local inhabitants.
• Qualitative analysis of vegetation is made by two different methods such as floristic (by
simple studying various genera and species of various plant groups i.e. herbs, shrubs,
trees etc).
B. Phyto-sociology
A nested quadrates technique was used for sampling the vegetation. All the plots sampled
were representative of most common types, sampling 10m x 10m for trees and 3m x 3m for
shrubs, 1m x 1m for herbs square meter quadrates were laid. Selection of sites for sampling
of vegetation is done by random sampling procedure. However, in general to study the
phytosociological attributes, quadrates of 10 m × 10 m size for tree species are randomly
3-55
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
laid out at each site at different elevations. Then the observation on the following parameters
is recorded:
The field data for phytosociological studies was collected in the study area. Vegetation data
was quantitatively analyzed for frequency, density and dominance using standard
methodologies. The relative values of frequency, density, and dominance of all the recorded
species was summed up to represent Importance Value Index (IVI). Not only IVI facilitates
comparison between species of a community, but also the data collected on dispersion,
number and cover can be profitably used in comparing the vegetation structure of two or
more stands or of the same stand over a period of time. Vegetation structure with respect of
varying environmental factors can also be studied through such studies in sets of varying
environmental conditions. The IVI was determined as the sum of the relative frequency,
relative density and relative dominance. It thus incorporate three important parameters that
measures of productivity and diversity of every species therefore.
C. Faunal Study
Ground surveys are carried out by trekking the study area for identification of important
animal groups such as birds, mammals and reptiles for sampling of animals through the
following methods.
• For sampling birds/ avifauna ‘point sampling’ along the fixed transects (foot trails) were
done to record all the species of birds with the help of binoculars; field guides and
photography for more than 1 hour on each transect (n=4).
• For sampling mammals, ‘direct count on open width (20 m) transect’ were used on the
same transects. Besides, information on recent sightings/records of mammals by the
locals are also collected from the study areas.
• ‘Reptiles’ mainly lizards were sampled by ‘direct count on open width transects’.
• Secondary information collected from local villagers, published government data etc.
List of the endangered and endemic species as per the schedule of The Wildlife
Protection Act, 1972
Emphasis is given to identify avifauna and mammals to determine the presence and
absence of Schedule-1 species, listed in The Wildlife Protection Act 1972, as well as in Red
List of IUCN. Various methods used for study animals are as follows:
A. Point Survey Method: Observations were made at each site for 15-20 min duration.
B. Road Side Counts: The observer travelled by motor vehicles from site to site and all
sightings were recorded.
3-56
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
The ecology and diversity survey was conducted in the 10 km radius in the study area and
the surrounding area. It is observed that human settlements present within the study area of
10 km radius and many of villages have moderate ranges of plantations. Most of the
vegetation area is in agricultural fields. During site assessment several floral species
encountered within the 10 km radius area. The Wildlife (Protection) Act 1972 prohibits
picking, uprooting, damaging, destroying, acquiring or collecting six species of plants from
forest land and any area specified, by notification, by the Central Government [Clause 17A
of Chapter IIIA (Protection of Specified Plants), page 346 of Handbook Vol.1]. The six
species are: Beddome’s cycad (Cycas beddomei), Blue Vanda (Vanda coerulea), Kuth
(Sassurea lappa), Ladies slipper orchids (Paphiopedilum sp.), Pitcher plant (Nepenthes
khasiana), Red Vanda (Rananthera imshootiana). None of these species is recorded in the
forests of the study area.
Interspersed with crop fields were patches of scrub land. This land was especially the village
waste land and the vegetation was scrub type. The predominant species herein was
Lagerstroemia flos reginae (Ajhar), Cocos nucifera (Coconut), Shorea robusta (Sal),
Borassus flabellifer (Tal), Bombax malabaricum (Simul). Total 6 nos. of quadrates has been
considered for the study of the floral species in the 10 km radius around the study area. The
quadrates of size 10 m X 10 m have been taken as plot for study of tree, shrubs, and herbs.
The most of the vegetation found is of deciduous type.
The following species were encountered from the study area during the field visits as given
in Table 3.27.
Tree
1 Lagerstroemia flos reginae Ajhar Lythraceae Not yet Assessed
2 Spondias pinnata Amra Anacardiaceae Not yet Assessed
3 Cassia fistula Sonal Leguminosae Not yet Assessed
4 Emblica officinalis Amlokhi Phyllanthaceae Not yet Assessed
5 Ficus elastica Atha bor Moraceae Not yet Assessed
6 Ficus bengalensis Bot Moraceae Not yet Assessed
7 Psidium guajava Guava Myrtaceae Not yet Assessed
8 Aegle marnelos Bel Rutaceae Not yet Assessed
9 Mangifera indica Aam Anacardiaceae Not yet Assessed
10 Delonix regia Gulmohar caesalpiniaceae Least concern
11 Terminalia belerica Bahera Combretaceae Not yet Assessed
12 Cocos nucifera Coconut Arecaceae Not yet Assessed
13 Ficus hispida Dimaru Moraceae Not yet Assessed
14 Azadirachta indica Neem Meliaceae Not yet Assessed
3-57
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
3-58
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
The detailed study of the core zone revealed dominance of Tal, Ajhar trees and no such
endemic plant species were found. The detailed list of plant species found in each quadrat
provided in Table 3.29. Total 46 species of trees found in the study area along with 19 shrub
species and 13 herbs and grass species observed. From the result below the predominant
species are Lagerstroemia flos reginae (Ajhar), Cocos nucifera (Coconut), Shorea robusta
(Sal), Borassus flabellifer (Tal), Bombax malabaricum (Simul) among tree species and
Calotropis procera, Lantana camara, Mimosa himalayana, Bambusa tulda found to be the
predominant species among shrub. Among the herbaceous species Cynodon dactylon,
Mimosa pudica found to be abundant.
Phytosociological Analysis
Phytosociological parameters, such as, density, frequency and Importance Value Index of
individual species were determined in randomly placed quadrats of different sizes in the
study area. Relative frequency, relative basal area and relative density were calculated and
the sum of these three represented Importance Value Index (IVI) for various species. For
3-59
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
shrubs, herbs and seedlings, the IVI was calculated by summing up relative frequency,
relative density and relative abundance.
Sample plots were selected in such a way to get maximum representation of different types
of vegetation and plots were laid out in different part of the block area and surrounding
areas. Analysis of the vegetation will help in determining the relative importance of each
species in the study area and to reveal if any economically valuable species is threatened in
the process. Phytosociological analysis of tree Species is given Table 3.28.
3-60
ABC Techno Labs India Pvt. Ltd.
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of India Description of
Environment
Abundance
Abundance
Frequency
Frequency
Relative
Relative
Relative
Density
Density
Total no.
Total Total No.
IVI
%
Sl.No. Scientific name Local name Q1 Q2 Q3 Q4 Q5 Q6 of quad
No. of quad
with sp.
Tree Species
1 Lagerstroemia flos reginae Ajhar 1 1 1 3 3 6 0.004 3.66 50.0 3.9 1.00 0.04 7.59
2 Spondias pinnata Amra 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
3 Cassia fistula Sonal 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
4 Emblica officinalis Amlokhi 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
5 Ficus elastica Atha bor 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
6 Ficus benghalensis Bot 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
7 Psidium guajava Guava 1 1 1 3 3 6 0.004 3.66 50.0 3.9 1.00 0.04 7.59
8 Aegle marmelos Bel 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
9 Mangifera indica Aam 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
10 Delonix regia Gulmohar 1 1 1 3 3 6 0.004 3.66 50.0 3.9 1.00 0.04 7.59
11 Terminalia belerica Bahera 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
12 Cocos nucifera Coconut 1 2 1 4 3 6 0.005 4.88 50.0 3.9 1.33 0.05 8.82
13 Ficus hispida Dimaru 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
14 Azadirachta indica Neem 1 2 3 2 6 0.004 3.66 33.3 2.6 1.50 0.04 6.29
15 Butea monosperma Palas 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
16 Adina cordifolia Haldu 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
17 Elaeocarpus robustus Helok 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
18 Terminalia chebula Harida 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
19 Syzygium cumini Jamun 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
20 Macaranga indica Juglo 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
21 Saraca indica Asoka 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
22 Ficus gibbosa Jaribar 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
Abundance
Abundance
Frequency
Frequency
Relative
Relative
Relative
Density
Density
Total no.
Total Total No.
IVI
%
Sl.No. Scientific name Local name Q1 Q2 Q3 Q4 Q5 Q6 of quad
No. of quad
with sp.
23 Anthocephalus cadamba Kadam 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
24 Ficus racemosa Umber 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
25 Aquilaria agallocha Agar 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
26 Bauhinia sp. Kanchan 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
27 Artocarpus heterophyllus Kanthal 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
28 Bauhinia purpurea Kurial 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
29 Schima wallichii Makri 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
30 Bischofia javanica Uriam 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
31 Tamarindus indica Tetul 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
32 Tectona grandis Segun 1 1 2 2 6 0.003 2.44 33.3 2.6 1.00 0.02 5.06
33 Shorea robusta Sal 1 1 2 4 3 6 0.005 4.88 50.0 3.9 1.33 0.05 8.82
34 Borassus flabellifer Taal 1 2 1 1 5 4 6 0.006 6.10 66.7 5.2 1.25 0.06 11.35
35 Acacia auriculiformis Setbabul 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
36 Zizyphus jujuba Kul 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
37 Bursera serrata Nour 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
38 Alstonia scholaris Satiana 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
39 Acacia nilotica Babla 2 2 1 6 0.003 2.44 16.7 1.3 2.00 0.02 3.76
40 Pterocarpus indicus Padauk 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
41 Bombax malabaricum Simul 1 1 1 3 3 6 0.004 3.66 50.0 3.9 1.00 0.04 7.59
42 Albizia chinensis Siris 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
43 Pongamia pinnata Karanj 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
44 Polyalthia longifolia Debdaru 1 1 1 3 3 6 0.004 3.66 50.0 3.9 1.00 0.04 7.59
45 Diospyros melanoxylon Kendu 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
46 Dalbergia sissoo Shishoo 1 1 1 6 0.001 1.22 16.7 1.3 1.00 0.01 2.53
Abundance
Abundance
Frequency
Frequency
Relative
Relative
Relative
Density
Density
Total no.
Total Total No.
IVI
%
Sl.No. Scientific name Local name Q1 Q2 Q3 Q4 Q5 Q6 of quad
No. of quad
with sp.
Abundance
Abundance
Frequency
Frequency
Relative
Relative
Relative
Density
Density
Total no.
Total Total No.
IVI
%
Sl.No. Scientific name Local name Q1 Q2 Q3 Q4 Q5 Q6 of quad
No. of quad
with sp.
The interpretation vegetation study results of the study area are presented in the following
Table 3.29.
Biodiversity index is a quantitative measure that reflects how many different types species, there
are in a dataset, and simultaneously takes into account how evenly the basic entities (such as
individuals) are distributed among those types of species. The value of biodiversity index
increases both when the number of types increases and when evenness increases. For a given
number of type of species, the value of a biodiversity index is maximized when all type of
species are equally abundant. Interpretation of Vegetation results in the study area is given in
Table 3.30.
From Table 3.31, it can be interpreted that tree community has higher diversity. While the shrub
community shows less diversity. It is also observed that most of the quadrates have controlled
generation of plant species with older strands. Higher tree species diversity can be interpreted
as a greater number of successful species and a more stable ecosystem where more ecological
niches are available and the environment is less likely to be hostile, environmental change is
less likely to be damaging to the ecosystem as a whole.
Agricultural Crops: Paddy, maize is the main crop grown widely. As there was no assured
irrigation, Paddy was cultivated with ground water. The principal cash crops are tea, jute,
oilseeds, sugarcane, cotton, and tobacco. Also Tomato, Chillies etc were grown occasionally.
Different fruits like papaya, mangoes, custard apple also grown by the local people.
Medicinal Plant Species: The nearby area is also endowed with the several medicinal plants
which are commonly available in the shrub forest and waste lands. The common medicinal
plants of the region are Aegle marmelos (Bel), Azadirachta indica (Neem) etc.
Rare And Endangered Floral Species: During the vegetation survey in the study area did not
encounter any such species which are endangered or threatened under IUCN (International
Union for Conservation of Nature and Natural resources) guidelines.
Faunal Communities
Both direct (sighting) and indirect (evidences) observations methods were used to survey the
faunal species around the study area. Additionally reference of relevant literatures (published/
unpublished) and dialogues with local villagers were also carried out to consolidate the
presence of faunal distribution in the area (Smith 1933-43, Ali and Ripley 1983, Daniel 1983,
Prater 1993, Murthy and Chandrasekhar 1988).
Mammals: No wild mammalian species was directly sighted during the field survey. Dialogue
with local villagers located around the study area also could not confirm presence of any wild
animal in that area. Rhesus Monkey, common mongoose, Common otter, Indian rat, Small
Indian civet, Common five Stripped Squirrel were observed during primary survey.
Avifauna: Since birds are considered to be the indicators for monitoring and understanding
human impacts on ecological systems (Lawton, 1996) attempt was made to gather quantitative
data on the avifauna by walk through survey within the entire study area and surrounding areas.
From the primary survey, a total of 47 species of avifauna were identified and recorded in the
study area. The diversity of avifauna from this region was found to be quite high and
encouraging.
The list of fauna species found in the study area are mentioned in Table 3.31. The tree lizard
and common garden lizards are also seen. Variety of butterflies (like common grass yellow,
Common Mormon, plain tiger) and insects (such as beetles, spiders, red ants, and flies) are
spotted in abundance in the study zone.
Table 3.31: Fauna Recorded from the Primary Survey in the Study Area and their
Conservation Status
Sl.No Scientific name English Name Schedule of Status as per Method
Wildlife IUCN Red
Protection Data List
Act
Mammals
1 Macaca mulatta Rhesus Monkey II Least Concern DS
2 Herpestes edwardsii Common Indian Mongoose II Least Concern DS
Near
3 Macaca assamensis Assamese macaque II NS
Threatened
4 Viverricula indica Small Indian Civet I Least Concern NS
5 Canis bengalensis Indian fox - Not assessed NS
6 Mus musculus Common mouse V Least Concern DS
Near
7 Lutra lutra Common otter II DS
Threatened
8 Cannomys badius Bay bamboo rat V Least Concern DS
9 Lepus nigricollis Indian rabbit IV Least Concern DS
10 Mus rattus Indian rat V Not assessed DS
11 Bandicoota bengalensis Common Indian Rat V Not assessed DS
Common five Stripped
12 Funambulus pennanti IV Not assessed DS
Squirrel
13 Felis bengalensis Leopard cat I Not assessed NS
14 Axis axis Spotted deer II Least Concern NS
15 Platanista gangetica Ganges river dolphin I Endangered NS
16 Felis chaus Jungle cat II Least Concern NS
Birds
1 Corvus splendens House crow V Least Concern DS
2 Corvus macrorhynchos Jungle crow - Least Concern NS
3 Aerodotheres tristis Common Maina IV Not assessed DS
4 Milvus migrans Common kite IV Least Concern DS
5 Anas poecilorhyncha Eastern Spot billed duck IV Least Concern DS
6 Ardea alba Great Egret IV Least Concern DS
7 Vanellus cinereus Grey Headed Lapwing IV Least Concern DS
8 Anas strepera Gadwall IV Least Concern DS
9 Himantopus himantopus Black winged Stilt IV Least Concern DS
10 Actitis hypoleucos Common sandpiper IV Least Concern DS
11 Leptoptilos javanicus Lesser Adjutant IV Vulnerable DS
12 Dicrurus macrocercus Black Drongo IV Least Concern DS
13 Nettapus coromandelianus Cotton pigmy goose IV Least Concern DS
14 Tringa glareola Wood Sandpiper IV Least Concern DS
Livestock like cattle, buffalo, goat, poultry, duck, and pig are reared for dairy products, meat,
egg and for agriculture purpose. Majority of cattle and buffalo are of local variety. Backyard
poultry farms are mostly common in this area; however, some commercial poultry farms are
also recorded in the study area.
ABC Techno Labs India Pvt. Ltd. 3-69
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
The study area is marked with moderate population of flora and fauna. With reference to the
Wildlife Protection Act 1972 total number of wildlife tabulated in this study can be
characterized as given in the Table 3.32.
Table 3.32: Characterization of Fauna In The Study Area (As Per W.P Act, 1972)
Sl.No. Schedule of Wildlife Protection Act 1972 No. of Remark
Species
1 Schedule I 3 -
2 Schedule II 8 -
3 Schedule III 0 -
4 Schedule IV 71 -
5 Schedule V 6 -
6 Schedule VI 0 -
The details of flora and fauna identified within 10 km radius of the project site are tabulated In
Table 3.33.
There is one major river present within the 10 km radius study area. The major river is
Brahmaputra River alongwith ponds, lake and other small water bodies form the aquatic
ecosystem. Deepor bill (Water body) is a Ramsar site is the largest habitat of migratory birds
situated about 3 km towards eastern side of the project site.
The most dominant macrophytes are Phragmites karka, Arundo donax, Alternantha sessilis,
Cyperus iria, Hydrilla verticillata and Nymphoides cristrat. A total of 21 species of aquatic
macrophytes were recorded from these aquatic ecosystems. Lists of Macrophytes recorded
within the study area are given in Table 3.34.
Fish is widely available in the still (Bills / Ponds) and flowing water bodies (Rivers/Nalas) of
the study area. Freshwater fish species within the 10 km radius study area has been
identified. Major fish fauna of fresh water bodies include catla, rohu, mrigala, Cat fish,
Prawn, Murrel, etc. A total of 17 species of fishes were recorded from these aquatic
ecosystems. The list of fish species recorded within the study area is given in Table 3.35.
Table 3.35: List of Fish species Recorded within the Study Area
Sl.No Scientific Name English Name
1 Catla catla Katla
2 Channa punctatus Lata
3 Channa striatus Sole
4 Channa gachua Chang
5 Labeo rohita Rohu
6 Cirrhinus mrigala Mrigal
heard were made for 10-minute periods with cumulative subtotals recorded at 5-minute
intervals. Birds were identified by primary song, other calls, and sight. All individual birds, except
for dependent fledglings, were recorded. To reduce the potential for overcounting moving birds,
multiple individuals of a species were recorded only when concurrent observations clearly
established their presence. The numbers of species and individuals recorded on point counts
appear to decline in midmorning. The bird population study at Deepor Bill is given in Table 3.36.
The graphical presentation of distribution of bird population is shown in Figure 3.18.
Number of species
Number
Sl. Common IUCN Site 1 Site 2 Site 3 Site 4
Name of Species Family Name of
No. name STATUS Total Total
species 0-5 5-10 0-5 5-10 0-5 5-10 Total 0-5 5-10 Total
Min Min Min Min Min Min Min Min
Cotton
Nettapus Least
15 pigmy Anatidae 124 37 0 37 25 12 37 32 0 32 12 6 18
coromandelianus Concern
goose
Least
16 Bubulcus ibis Cattle Egret Ardeidae 16 3 1 4 2 3 5 1 2 3 1 3 4
Concern
Wood Least
17 Tringa glareola Scolopacidae 3 1 0 1 0 0 0 0 0 0 2 0 2
Sandpiper Concern
White Least
18 Motacilla alba Motacillidae 3 0 0 0 0 0 0 0 0 0 2 1 3
Wagtail Concern
Result shows that Site 1 having more percentage of total population of bird species. Most
number of species observed was Anas strepera (Gadwall), followed by Anas poecilorhyncha
(Eastern Spot billed duck) and Milvus migrans (Common Kite).
The result shows that Duck population (Anatidae family) dominates the total bird population of
about 60.8% followed by Accipitridae family of about 18.71% and Ardeidae family of about
12.38%.
The Government of Assam has recognised this area as a sanctuary, but no thought has so far
been given on addressing some of the threats to the entire beel ecosystem including the
sanctuary area, pollution, encroachments, garbage dumping, eutrophication, dense growth of
weed etc witnessed by the study team.
Some of the natural and threatening the Deepor Beel include:
• Construction of railway line along the southern boundary of the Deepor Beel;
• Industrial development within the periphery of the Beel;
• Large scale encroachment within the Deepor beel area;
• Allotment of government vacant land to private parties by Government settlement
department;
• Brick kiln and soil cutting within the beel ecosystem;
• Hunting, trapping and killing of wild birds within and adjoining areas of Deepor Beel;
• Unplanned and destructive fishing practices without any control/regulation on mesh size,
etc.
Large-scale encroachment, heavy siltation from the denuded hills surrounding the beel,
accumulation of all sorts of filth and wastes from the Bharalu and Bahini rivers, unregulated
fishing practices, invasion of aquatic weeds, industrial development within its periphery,
construction of railway line along the southern boundary, quarrying within the beel ecosystem,
etc., have pushed this once-pristine ecosystem to the brink of disappearance.
The growth of infrastructure developments and industrial sectors in and around the agriculture
dominant areas, villages and towns are bound to create its impact on the socio- economic
aspects of the local population. The impacts may be positive or negative depending upon the
developmental activity. To assess the impacts on the socio-economics of the local people, it is
necessary to study the existing socio- economic status of the local population, which will be
helpful for making efforts to further improve the quality of life in the study area. The section
delineates the overall appraisal of the socially relevant attributes. The data collection on the
impact of infrastructure development on the socio-economic aspects in the study area has been
done through analysis of various secondary data and also supplemented by the primary data
generated through the process of socio- economic survey.
parameters helps in identifying, predicting and evaluating the likely socio-economic impacts due
to proposed project.
The existing Guwahati airport is located at Borjhar in Guwahati at distance of 1.2 km from NH-
37 and 18 km from Guwahati City. The proposed development including new integrated terminal
building and associated works will be constructed on the land available within the existing
airport. Therefore, no additional land acquisition is required for the proposed construction and
operation activities.
The 10km study area from centre of proposed site covers a total 34 rural villages comprises (10
villages from Azara sub-district of Kamrup metropolitan district and 24 villages of Palasbari sub-
district of Kamrup district) and 08 census towns include (05 from Azara sub-district of Kamrup
metropolitan district and 03 from Palasbari sub-district of Karrup district) of Assam state. The
details of villages and town falls within study area are given in Table 3.37.
3.13.1 Methodology
The methodology adopted in the assessment of socio-economic condition in the study area is
as given below:
The primary data on socioeconomic profile was collected through site observation, interviews
with the key-informants and group discussions in the selected villages. Local respondents
(male-female) and school teacher were interviewed for the collection of socio-economic
baseline information during the site visit by ABC Team from 9th to 12th January 2017. The
secondary data includes demographic profile, and employment pattern have been sourced from
Primary Census Abstract-2011 compact disk (CD) of Assam obtained from Office of Registrar
General India, New Delhi and Infrastructure resource base has been extracted from District
Census Handbook;Census of India,2011.
Demographic Profile
• Study area includes 34 villages and eight census town from Azara sub-district of Kamrup
metropolitan district and Palasbari sub-district of Kamrup district
ABC Techno Labs India Pvt. Ltd. 3-80
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of
India Description of Environment
• Total population of 112892 comprises 57730 male and 55162 female from 25379
households lie within the study area.
• Scheduled caste population and scheduled tribe population is 8.3% and 5.6%, respectively.
However, the scheduled tribe population was found to be insignificant in rural area i.e.1.1%.
• Sex ratio (No. of females per 1000 males) is 960 which is higher than Kamrup Metropolitan
district (Rural) and Kamrup district (Rural) ie. 936 and 949 females per 1000 males as well
as national average sex ratio (940) as per the latest reports of Census 2011 Directorate.
• The literacy rate in the study area is 87.7% which is similar with average literacy rate of
Kamrup metropolitan district i.e. 88.7% and higher than Kamrup district (rural) i.e. 75.5%
and as well as that of Assam state (rural) i.e., 69.3%.
District Profile
The staple crop of the district is rice. The indigenous manufactures are confined to the weaving
of silk and cotton cloths for home use, and to the making of brass cups and plates. The chief
exports are rice, oil seeds, timber and cotton; the imports are fine rice, salt, piece goods, sugar,
betel nuts, coconuts and hardware.
As per 2011 census, the occupational pattern of the study area shows that the percentage of
main, marginal and non workers is 27.3%, 9.7% and 63% respectively. However, the majority of
main workers are engaged as cultivators i.e.81.8% followed by others workers*(25%),
agriculture labourers (9.3%) and household labourers (3.8%). However, majority of marginal
workers are engaged as others workers* i.e.63.7% followed by household labourers (15.6%),
agriculture labourers (14.4%) and cultivators (76.3%).The percentage of non-workers in the
study area is higher i.e. 63%. The village-wise employment pattern in the study area is given in
Annexure II.
The employment pattern of the study area at a glance is shown below in Table 3.39.
During survey and interaction with local people it was revealed that Agriculture and its allied
activities is the main occupation of the people in the study area. Due to sufficient rain, people
are mostly depending upon rain water to carry out agricultural activities. Few households having
good financial conditions use modern equipments and tractors to carry out the agricultural work.
The predominant field crop is rice. Vegetable crops such as potato, pumpkin, brinjal and
cauliflower are also grown. The villagers sell these products in weekly market of surrounding
town and main market of Guwahati. Besides, people are also engaged as construction labour
and govt. and private jobs as a source of livelihood. Few are engaged in fishing activity as a
source of income.
Besides, people in the study area are expert in making bamboo and cane products and a small
number of womenfolk is engaged in handloom, handicraft and weaving works which is
additional source of income for them.
The existing health infrastructure and services in the study area comprises of a Primary Health
Centre (PHC) at Mirzapur and Dispensary/Health Centre at Azara, Kahi Kuchi, Dharapur and
Garal. During our visit, it was informed that PHCs are inadequate with respect to staff and
equipments but organizes general health check-up and awareness programme on maternal and
child care and immunization camps in the surrounding villages on a regular basis. People visit
Allopathic hospital exists in Palasbari and Azara for minor illness.
No major diseases were reported by local people in the study area except routine cough, cold
and fever etc. The residents of surveyed villages reported annual expenditure on health to be
above Rs. 500-800 per family of 5 members. Due to the lack of equipments, infrastructure and
poor coverage of the existing health services in rural area, the residents consult private
practitioners at nearby towns and Guwahati city which is time consuming and expensive also.
The private hospitals in Guwahati city are equipped with better facilities than the PHCs in the
study area. The discussions with the local people indicate that these private clinics mostly
caters to the affluent class residents i.e., mostly belonging to middle income group in the area.
The average family size in the study area is 5 per family. However, joint families are
ranging from 5-10 members per household.
Mekhela chador is the traditional Assamese dress worn by women all ages except the
children. The top portion of the two-piece dress, called the chador, is a long length of cloth
that has one end tucked into the upper portion of the Mekhela and the rest draped over and
around the rest of the body.
The study area have mostly single dwelling unit. The houses are made largely using
cement, brick and roof of galvanized iron sheet. Also used wood based materials.
Among surveyed villages, adequate educational facility (1st to 10th standard) is within reach
of the local people. To avail further education like degree, diploma, polytechnic and
engineering, students travel to Guwahati town.
Most common source of potable water in the village comprises hand pump and tube wells.
People informed during survey that health issues are increasing among local people due to
presence of high percentage of iron in potable water.
In surveyed villages, 80% households have individual toilet facility. Toilets are constructed
away from the main house near the periphery of the plot.
Power supply facility is available for domestic use in all the villages but few households in
each surveyed village does not have electric connection which may be due to very low
economic status. Wood remains the primary source of fuel for lower income groups
whereas some of the economically better off families have shifted to LPG for cooking
purposes.
During survey, it was informed by local people that Primary Health Center (PHC) and
(PHS) available in the rural villages are not adequate with respect to staff and equipment.
Also, in case of emergency, people have to travel Govt hospital at Guwahati which is time
consuming and expensive also. Inhabitants also added that only people from lower income
group of rural area visit PHC whereas people who can afford consult private practitioners at
Guwahati city. Therefore, people are expecting a Health clinic with adequate staff,
diagnostic equipments and infrastructure facilities to be provided by proponent in nearby
area under welfare activity.
The major crop cultivated in the area is paddy. Few households grow green vegetables
potato, brinjal, and cauliflower which are sold in weekly market in the surrounding towns or
in main market of Guwahati.
The approach road and internal road network in rural villages are narrow and in bad
condition due to heavy rain/flood condition. State transport bus service up to the village is
not available but towns have good state transport bus facility. Besides, people use two
wheeler and auto rickshaw for their routine household chores. The nearest railway station
is Guwahati.
Rice, sugar and kerosene are being distributed to those families who are having valid ration
cards under public distribution system (PDS) run by the government.
The communication facilities can be termed as satisfactory as the surveyed villages are
privileged by post offices and mobile phones.
Recreational facilities like television and radio are available in households having good
economic status.
People expect that social welfare activities viz. improvement in road condition which gets
damaged due to heavy rains/flood in the area and implementation water purification system
which will help to decrease iron percentage in potable water which is affecting health of the
local people. The villagers should be consulted while deciding the welfare programmes by
the project proponent.
The people are not against the setting up of proposed project in the area as this will surely
result into improvement in quality of life provided it is equipped with adequate measures for
environmental pollution control and preference should be given to local people in job
opportunities on the basis of their qualification, experience and skill.
It will be of profound importance to study the perception as well as reaction of the community
people towards the proposed project activity. Group discussions with local people and school
teacher of selected villages was done to gather the existing baseline socio-economic
information on a various parameters of Quality of Life. During discussion, issues related to
employment generation, information flow, health and safety, social welfare activity etc. were
discussed.
During discussion with local people at village Azara it was revealed that improvement in
road condition which gets damaged due to heavy rains/flood every year in the area is
primary need of people. Besides, people expect preference should be given to local people
for employment opportunities in various activities during construction phase.
Further, people have to travel long distance to avail health facilities for major illness in
surrounding towns, which is time consuming and expensive. Therefore, people are
expecting a mobile medical facility with testing and diagnostic facilities to be provided by
proponent in nearby area under welfare activity.
In Kahi Kuchi, head-master of English
primary school run by AAI opined that lack
of teaching staff and poor condition of
school building and infrastructure is
affecting attendance and result of students.
Hence monitory help to improve these
facilities and also to complete higher
education to meritorious students is
expected from AAI.
There is however a desire among the local
youth for technical training to enhance their
opportunities for employment in the nearby
industries.
Mr. Jugal Kotaki, Assistant Teacher of Palasbari Girls High school stated that land is not
available to construct toilets for 250 girls studying in the school and hence they expect
financial help for land availability for construction of toilets.
Further, inadequate health facilities and presence of iron in potable water is the major
concern of the local people in the area.
Annexure I
Demographic Profile of the study area
District Sub- Village Area Number Population Population Schedule Population Schedule Literates
district of Caste Tribes
Type Household Total Male Female Total Male Female Total Male Female Total Male Female
Rural
Kamrup Azara Mikirpara
Metropolitan Chokardoi Rural 609 2802 1409 1393 957 476 481 167 76 91 2155 1150 1005
Mirzapur Rural 737 3355 1677 1678 109 54 55 18 10 8 2661 1403 1258
Kendukuchi Rural 200 863 450 413 0 0 0 0 0 0 675 374 301
Agcia Rural 325 1410 703 707 0 0 0 1 1 0 1173 608 565
173
Pat Gaon Rural 684 2772 2 1040 72 44 28 880 468 412 2154 1419 735
Jabe Rural 53 228 114 114 0 0 0 175 86 89 181 91 90
Jogipara Rural 1065 4482 2249 2233 232 109 123 79 37 42 3569 1851 1718
Matikutni Rural 2 11 6 5 0 0 0 0 0 0 7 5 2
Kamar Gaon Rural 1 2 2 0 0 0 0 0 0 0 2 2 0
Pacheniapara Rural 541 2446 1245 1201 12 6 6 0 0 0 1687 913 774
Kamrup Palasbari Joypur Rural 18 35 18 17 0 0 0 0 0 0 8 5 3
Dakhala Rural 851 4049 2096 1953 16 8 8 0 0 0 3210 1749 1461
Barhanti
Rangamati Rural 781 3598 1797 1801 0 0 0 0 0 0 2843 1485 1358
Dole Gaon Rural 22 99 51 48 0 0 0 0 0 0 74 42 32
Salesala Rural 117 536 280 256 0 0 0 0 0 0 436 237 199
Kaita Sidhi Rural 532 2363 1201 1162 12 6 6 2 2 0 1819 970 849
Bongara Rural 684 3273 1654 1619 0 0 0 0 0 0 2626 1383 1243
Maliata Rural 992 4534 2313 2221 156 88 68 1162 582 580 3412 1854 1558
Chayani
Moniari Rural 557 2654 1347 1307 35 18 17 10 5 5 2094 1124 970
Chayani
Rangamati Rural 420 1960 1039 921 548 296 252 0 0 0 1595 889 706
Hudumpur Rural 328 1510 764 746 0 0 0 0 0 0 1291 680 611
Barkukuria Rural 282 1309 685 624 0 0 0 0 0 0 1096 607 489
Kokjar
(Kokrajhar) Rural 762 3560 1842 1718 1016 518 498 5 3 2 2780 1519 1261
Baranti Maniari Rural 596 2587 1339 1248 33 13 20 1 1 0 2050 1130 920
Santola Rural 524 2423 1229 1194 815 419 396 500 240 260 1984 1078 906
Sadilapur Rural 162 791 408 383 366 186 180 0 0 0 591 332 259
Kamargaon Rural 90 435 227 208 1 0 1 108 49 59 306 166 140
Sajan Para Rural 99 452 225 227 0 0 0 413 208 205 341 183 158
Rajapanichanda Rural 118 555 259 296 0 0 0 525 244 281 387 207 180
Nargaon Rural 230 1037 535 502 0 0 0 269 138 131 668 376 292
Kachari
Allibari Rural 146 648 335 313 1 0 1 8 3 5 541 286 255
Kallapara Rural 362 1554 808 746 62 35 27 1155 593 562 956 533 423
Kallapara N.C. Rural 55 209 108 101 0 0 0 209 108 101 125 65 60
ABC Techno Labs India Pvt. Ltd. 3-87
EIA for Construction of New Integrated Terminal Building at LGBI Airport, Guwahati by Airports Authority of India
Description of Environment
Garal (CT) Urban 973 4400 2239 2161 144 70 74 4 2 2 3610 1913 1697
Majir Gaon (CT) Urban 1083 4774 2440 2334 221 116 105 1 0 1 4016 2125 1891
Kahi Kuchi (CT) Urban 2522 9917 5130 4787 834 435 399 311 171 140 7905 4219 3686
Dharapur (CT) Urban 1796 8095 4117 3978 195 103 92 33 18 15 6587 3506 3081
Kamrup Palasbari Palasbari (MB) Urban 1034 4925 2469 2456 341 174 167 5 3 2 4177 2178 1999
Kochpara (CT) Urban 1709 7540 3840 3700 124 59 65 130 74 56 6450 3409 3041
Parlli Part (CT) Urban 1290 5788 2825 2963 1610 793 817 15 5 10 4660 2441 2219
Total (B) 12409 54219 27514 26705 4952 2474 2478 600 316 284 44479 23547 20932
Total (A+B) 25379 112892 57730 55162 9395 4750 4645 6287 3170 3117 90001 48280 41721
Source: District Census Handbook; Census of India (2011); Kamrup Metropolitan and Kamrup District;Assam
Annexure II
Workers Participation Details
District Sub- Village Name Area Number of Population Main Marginal Non
district Household Workers Workers Workers
Type
Rural
Kamrup Azara Mikirpara Rural 609 2802 812 262 1728
Metropolitan Chokardoi
Mirzapur Rural 737 3355 875 183 2297
Kendukuchi Rural 200 863 261 54 548
Agcia Rural 325 1410 399 144 867
Pat Gaon Rural 684 2772 1193 125 1454
Jabe Rural 53 228 53 9 166
Jogipara Rural 1065 4482 1158 234 3090
Matikutni Rural 2 11 4 1 6
Kamar Gaon Rural 1 2 2 0 0
Pacheniapara Rural 541 2446 459 200 1787
Azara (CT) Urban 2002 8780 2475 311 5994
Garal (CT) Urban 973 4400 1226 209 2965
Majir Gaon (CT) Urban 1083 4774 1352 176 3246
Kahi Kuchi (CT) Urban 2522 9917 3012 344 6561
Dharapur (CT) Urban 1796 8095 2260 363 5472
Kamrup Palasbari Joypur Rural 18 35 15 3 17
Dakhala Rural 851 4049 1121 831 2097
Barhanti Rural 781 3598 974 921 1703
Rangamati
Dole Gaon Rural 22 99 22 6 71
Salesala Rural 117 536 95 112 329
Kaita Sidhi
(Poitasidhi) Rural 532 2363 484 326 1553
Bongara Rural 684 3273 733 222 2318
Maliata Rural 992 4534 907 544 3083
Chayani Moniari Rural 557 2654 847 166 1641
Chayani
Rangamati Rural 420 1960 597 331 1032
Hudumpur Rural 328 1510 408 44 1058
Barkukuria Rural 282 1309 410 55 844
Kokjar
(Kokrajhar) Rural 762 3560 1055 308 2197
Baranti Maniari Rural 596 2587 644 334 1609
Santola Rural 524 2423 280 541 1602
District Sub- Village Name Area Number of Population Main Marginal Non
district Household Workers Workers Workers
Type
Sadilapur Rural 162 791 108 152 531
Kamargaon Rural 90 435 132 3 300
Sajan Para Rural 99 452 53 160 239
Rajapanichanda Rural 118 555 192 143 220
Nargaon Rural 230 1037 302 310 425
Kachari Allibari Rural 146 648 152 28 468
Kallapara Rural 362 1554 659 358 537
Kallapara N.C. Rural 55 209 49 86 74
Garbhanga F.V. Rural 25 131 28 0 103
Total (A) 12970 58673 15483 7196 35994
Urban
Kamrup Azara Azara (CT) Urban 2002 8780 2475 311 5994
Metropolitan Garal (CT) Urban 973 4400 1226 209 2965
Majir Gaon (CT) Urban 1083 4774 1352 176 3246
Kahi Kuchi (CT) Urban 2522 9917 3012 344 6561
Dharapur (CT) Urban 1796 8095 2260 363 5472
Kamrup Palasbari Palasbari (MB) Urban 1034 4925 1508 404 3013
Kochpara (CT) Urban 1709 7540 1987 882 4671
Parlli Part (CT) Urban 1290 5788 1519 1008 3261
Total (B) 12409 54219 15339 3697 35183
Total (A+B) 25379 112892 30822 10893 71177
Source: District Census Handbook; Census of India (2011); Kamrup Metropolitan and Kamrup District; Assam
CHAPTER – 4
4.1 Introduction
The design, construction and operational phase of the New Integrated Terminal
Building and associated works at Guwahati Airport comprises various activities each
of which may have an impact on some or other environmental parameters. Various
environmental attributes during the construction and operation phase have been
studied/analyzed to estimate the overall impacts on the surrounding environment.
Due to the new integrated terminal building and associated works at Guwahati
Airport, water environment, air environment, noise, land environment, ecological
environment and socio-economic factors are identified as the significant
environmental components likely to be affected. The anticipated impacts on the
environmental components are identified, quantitatively/qualitatively evaluated,
predicted and discussed below with suitable mitigation measures.
The anticipated environmental impacts due to new integrated terminal building, and
associated works at Guwahati Airport may be beneficial or adverse, short or long
term (acute or chronic), temporary or permanent, direct or indirect and local or
regional. Adverse environmental impacts include such impacts which can lead harm
to living resources, atmosphere, damage to human health, birds & animal,
vegetation, land & water resources, hindrance to activities in place, harm of quality
for use, reduction of amenities, damage to physical structures, etc. Environmental
risk is also evaluated based on its likelihood and significance for each identified
potential environmental impact due to proposed activities in the area. For the new
integrated terminal building and associated works at Guwahati Airport, the impacts
assessment has been carried out in the following three steps:
In Step 3, all the potential environmental impacts are evaluated and a qualitative
evaluation is carried out. An impact level is rated as “low”, “medium” or “high”. The
impact rating is based on two parameters, i.e. “severity of environmental impacts” and
“likelihood of occurrence of the environmental impacts”.
Notes:
Negligible Impact : Defined as magnitude of change comparable to natural
variation
Minor Impact : Defined as detectable but not significant
Moderate Impact : Defined as insignificant; amenable to mitigation; should be
mitigated where practicable
Major Impact : Defined as significant; amenable to mitigation; must be
mitigated
The one of primary purpose of New Integrated Terminal Building and associated
works at Guwahati Airport is to increase the capacity of passengers. Accordingly,
keeping in view the current and future requirement, new terminal building and
associated works is proposed at Guwahati Airport.
The likely impacts of the new integrated terminal building at Guwahati Airport would
be due to:
• Pre-construction Phase
• Construction phase, which would be mainly regarded as temporary or short term;
and
• Operation phase, which would have long-term and permanent impacts.
The construction and operation phases of the new integrated terminal building and
associated works at Guwahati Airport comprise of various activities, which have been
considered to assess the anticipated impact on one or other environmental
parameter as described in the following sections:
The mitigation measures for adverse environmental impacts have been suggested as
applicable regulatory requirements on environmental and socio-economic issues and
are intended to meet the following objectives:
• Prevent air, water, soil and noise pollution during construction & operation
phases;
• Adopt environmental and social enhancement measures;
• Encourage the socio-economic development in the region.
The anticipated environmental impacts of the new integrated terminal building and
associated works at Guwahati Airport and corresponding mitigation measures for
construction and operation phases have been described in the following sub-
sections:
The pre-construction phase will involve completion of necessary legal formalities with
respect to environmental clearances, site surveys/design and bidding of new
integrated terminal building and other associated works. The integrated terminal
building and other associated works and other associated works will require
equipment and machinery, requisite skilled, semi-skilled manpower & labour. The
supervision and project management will be undertaken by Airports Authority of
India.
The construction phase will mainly consist of transportation of earth for filling,
machinery and construction materials to be used for construction, clearing and
levelling of land, construction of terminal building, parking etc and associated works
as per approved design, etc.
Topography of the site is plains. For construction of new integrated terminal building
at Guwahati Airport, 5 m deep basement covering an area 7500 sqm will be
constructed. For construction of the proposed facilities at the Guwahati Airport,
tentatively 100000 cum filling will be required. Approx 50000 cum earth excavated
from construction of 7500 sqm size basement will be used filling at airport site.
Additional earth will be procured from approved quarry. After cutting and filling, land
for construction purpose will be leveled for construction of terminal building, parking
and associated works. The proposed construction will be confined within available
land only. Hence, the anticipated impact on the topography during construction
phase is rated as:
Mitigation Measures
• Land clearing at the site will be kept to the absolute minimum practicable; and
• Construction site would be designed to minimize filling of the earths.
• Borrowing of earth will be ensured only from approved borrow area having valid
environmental from District Level Environmental Impact Assessment Authority
(DEIAA).
• Borrow area will be rehabilitated after borrowing of necessary earth.
Mitigation Measures
• Land clearing for construction site will be kept to the absolutely minimum
practicable;
• The filling and cutting of soil would be kept minimum; and
• Construction debris and waste generated during construction activities will be
collected and disposed in environmental sound manner as per applicable rules
depending upon type of wastes.
For construction of the proposed facilities at the Guwahati Airport, tentatively 100000
cum filling will be required. Approx 50000 cum earth excavated from construction of
7500 sqm size basement will be used filling at airport site. Natural soil/sand from
approved borrow areas will be brought to the site.
During the construction phase, hydraulic lube oil, fuels and lubricating oils would be
used near proposed construction site. There is possibility of spills of such oils during
loading, unloading, storing and handing. During construction phase, waste oil shall
be generated as and when lubricating oil will be changed from engines of DG sets
and construction machineries. Used oil shall be collected and stored in leak proof
drums and sent to be used oil recyclers. The used oil drums shall be properly
identified with a label in Assamese and English. Used oil generated shall be handed
over to authorised recyclers for treatment and reuse. Other solid wastes, like debris,
metal pieces, cotton wastes, electrical wires cuttings, etc so generated will be
collected & segregated and will be disposed off as per standard practices.
Mitigation Measures
• Compaction and stabilization will be ensured during filling to ensure that no loose
soil is washed away with runoff during rains,
• Restoration of land surface with the condition and contours, prior to instigation of
construction activities,
• Wastes, fuel, oil drums, used oil, etc. would be collected and disposed properly,
• Dust bins will be placed at requisite locations at construction site and there will be
segregation of wastes before disposal,
• Used oil from maintenance of DG sets engines and construction equipment will
be collected separately in drums and will be handed over to the authorized used
oil recyclers by the Pollution Control Board, Assam as per the CPCB guidelines.
List of authorized used oil recyclers is already available at ASPCB website,
• Approx. 3100 kg per day municipal wastes, like, plastic, paper, packing waste,
bottles, oil contaminated cottons and clothes, food waste from labour camp, etc
will also be generated and may contaminate soil of the site, if not disposed
properly. These wastes will be segregated and disposed as per Solid Waste
Management Rules, 2016.
Mitigation Measures
• Slope and storm water management shall be provided to maintain drainage and
flow of runoff in the drain.
• Drainage at the site will be maintained as per drainage counter at the site,
therefore, no flooding will be occurred at and around the Guwahati airport during
and after construction of integrated terminal building and associated works.
The Guwahati airport is existing operational airport. The airport is not geographically
vulnerable to floods. During the construction of new integrated terminal building, and
associated works at Guwahati Airport natural drainage will be maintained properly by
storm water management. For storm water management at the site, rectangular
sections for side drains have been provided. The drains have been kept sufficiently
away from the taxiway / runway.
The impact from the flood due to construction of new integrated terminal building and
associated works at Guwahati Airport is rated as:
Environmental Impact Rating Natural Disaster- Flood
Nature of Impact Adverse
Duration of Impact Short term
Impacted Area Localized
Likelihood of Occurrence Low
Severity of Impact Low
Significance of Impact Minor
Mitigation Measures
• Area within the site for construction of new integrated terminal building and
associated works shall be filled and graded properly;
• Natural drainage will be maintained in the surrounding.
• For storm water management at the site, rectangular sections for side drains
have been provided. The drains have been kept sufficiently away from the
taxiway / runway.
• Construction of storm water drainage channels will not allow water logging at the
site and in surrounding area;
During the construction phase of the construction of new integrated terminal building
and other associated work at Guwahati Airport, approx 300 kl/day water will be
required depending upon the type of construction activities. The water requirement
will be met through existing deep bore well. The construction will be completed within
in approximately approx 36 months time. The construction water requirement would
be temporary in nature depending nature of construction activities. Therefore, the
impact on the water resources during the construction phase would be temporary
and variable in nature. The overall impact on water resource during construction
phase is rated as:
Mitigation Measures
Water will be required for construction purposes during the period of construction
especially for concreting and compaction of earth filling. The water requirement will
be met by extracting ground water from existing borewell at the airport.
During the construction phase, excavated loose soil used for filling may be washed
out from the site with runoff during rainfall, which may increase the turbidity and
suspended solids in runoff from construction site. However, this impact may last
when first rain is over as loose soil will be stabilised after first rainfall. Therefore, this
impact will be temporary in nature.
The overall impact during construction phase on water quality is summarized as the
follows:
Mitigation Measures
• Excavation and site clearing work will be planned during non rainy season,
• All debris and wastes from the construction of new integrated terminal building
and other associated work will be collected and disposed off suitably,
• Silt traps will be provided to prevent the discharge of excessive suspended solids,
• Oil trap will be provided in the drainage line to prevent contamination of runoff by
any oil spillage from construction machineries,
• To prevent contamination from spillage of oil, storage areas will be made by
cemented floor, bunded and will be cleaned at regular intervals,
• Wastewater generated from the domestic activities (kitchen/toilet) will be treated
in septic tank after passing through oil trap followed by soak pit or used for green
belt development, and
• Used oil and oil contaminated cotton & clothes will be given to authorised used oil
recyclers.
The potential sources of air emissions during construction phase of new integrated
terminal building and other associated work will be as follows:
The impact of construction activity on ambient air quality is a cause for concern
mainly in the dry months due to settling of dust particles. The main sources of dust
emissions during the construction period are the movement of equipment at the site
and dust emitted during the levelling, grading, earthworks, and other construction
related activities. The dust emitted during the above mentioned activities will depend
upon the type of soil being excavated and the humidity levels. The impact is likely to
be for short duration and confined to vicinity of the construction site. The composition
of dust in this kind of operation is however mostly coarse particles, inorganic and
non-toxic in nature and these are not expected to travel long distance before settling.
Exhaust emissions from vehicles and equipment deployed during the construction
phase also result in marginal increase in the levels of SO2, NO2, unburnt
hydrocarbons and particulate matter (PM10 & PM2.5). The impact will, however, be
reversible, marginal, and temporary in nature.
During the filling of earth, unloading of cement bags and mixing of cement with other
building materials, fugitive dust emissions may be emitted at the construction site. It
may be noted that these emissions would be in the form of coarse particulate matter
and will be settled down ultimately in the closed vicinity of the construction site.
Emissions from the DG sets may cause localised impact on ambient air quality for
short duration as these will be operated during grid power failure. DG sets will be
operated only in case of grid power failure. Adequate height of stacks will be
provided to the DG sets as per guidelines of CPCB to facilitate the dispersion of flue
gases in the atmosphere.
As construction activities will be mainly confined to the project site only for a short
duration, hence the impact on the ambient air quality during construction phase is
rated as given below:
Mitigation Measures
• Dust suppression systems (water spray) will be used as per requirement at the
construction site;
• Construction materials and earth will be fully covered during transportation to the
construction site by road;
• Standard prescribed by the CPCB/ ASPCB for stack height and emissions from
DG sets will be complied with;
• Preventive maintenance will be carried out for vehicles and pollution check will be
mandatory on periodic basis all the vehicles approaching to the construction site;
• Earth moving equipment, typically a bulldozer with a grader blade and ripper, will
be used for excavation work;
• Monitoring of ambient air quality/source emission will be carried out as per details
given in Chapter 6 or as stipulated by the MoEF&CC/ ASPCB.
During the construction phase of the new integrated terminal building and other
associated work, noise will be generated from various sources. Some major sources
of noise generation during construction phase of new integrated terminal building and
other associated work are listed below:
All the above mentioned sources at the proposed construction activities will be
intermittent and would be experienced occasionally. It may also be noted that, most
of the construction activities will be carried out only during the daytime.
The expected noise levels from these activities are given hereunder in Table 4.3:
The combined effect of above sources can be determined as per the following
equation:
Where: Lp1, Lp2 and Lp3 are noise pressure level at a point due to different sources in
dB (A).
For an approximate estimation of dispersion of noise in the ambient air from the
source point, a standard mathematical model for sound wave propagation is used.
The sound pressure level generated by noise sources decreases with increases
distance from the source due to wave divergence. An additional decrease in sound
pressure level from the source is expected due to atmospheric effect or its interaction
with objects in the transmission path. The noise level generated from a source would
decrease with increase in distance from the source because of the wave divergence.
For hemispherical sound wave propagation through homogenous loss of free medium,
noise levels at various locations can be calculated due to different sources using model
based on the first principles as per the following equation:
Where: Lp2 and Lp1 - Sound Pressure Level (SPLs) at points located at source and at
distances of r2 from the source respectively in dB (A).
The resultant maximum noise level for the above sources as calculated using
combined effect equation is 85 dB(A). Assuming no environmental attenuation factors,
noise modelling has been done, which shows noise level will mingle with the baseline
noise level within short distance. Noise modelling results for construction phase have
been given in Table 4.4 and shown in Figure 4.1:
90
80
Resuktant Noise Levels dB(A)
70
60
50
40
30
20
10
0
0.0 20.0 40.0 60.0 80.0 100.0 120.0 140.0 160.0
The noise produced during construction phase will have temporary impacts on the
existing ambient noise levels at the project site but restricted to small distance
(maximum upto 160 m) and only during daytime within the airport. Therefore, the
impact of noise levels on surrounding area will be insignificant during the construction
phase.
The general noise level due to construction activities, such as working of heavy earth
moving equipment and machinery installation, may sometimes go up to 80 dB(A) at
the work site during day time. The workers in general are likely to be exposed to an
equivalent noise level of 70-75 dB (A) in an eight (8) hour shift for which all statutory
precautions as per law will be implemented. Use of proper Personal Protective
Equipments (PPEs) will further mitigate adverse impacts of noise on the workers, if
any. The impacts can be further minimized and made insignificant by using standard
practice of construction. The present noise level, monitored in the study area, is well
within the standards of noise level. Hence, the impact on the noise level during
construction phase is rated as given in the table below:
Mitigation Measures
During the new integrated terminal building and other associated work, no tree will
need to be felled. For construction shrubs and ground flora will be cleared for new
integrated terminal building and other associated work. Therefore, marginal impact is
anticipated on terrestrial ecology during the construction phase.
The overall impact on the terrestrial ecology due to construction activities is rated as:
Environment Impact Rating Ecology
Nature of Impact Adverse
Duration of Impact Long term
Impacted Area Localized
Likelihood of Occurrence Low
Severity of Impact Minor
Significance of Impact Significant
Mitigation Measures
The Deepor Beel Ramsar Site / Deepor Beel Bird Sanctuary is located at distance of
approx 3 km in north-east direction from existing LGBI Airport at Guwahati. Between
Guwahati Airport and Deepor Beel, there populated areas and National Highway.
Deepor Beel Ramsar Site / Deepor Beel Bird Sanctuary is not located in flying path of
the existing Guwahati airport. From the new integrated terminal building, no waste
water of waste will be discharged in the Deepor Beel. The following mitigation
measures will be implemented during the construction phase for avoid any impact on
the Deepor Beel.
During construction phase of new integrated terminal building and other associated
work, the personnel working at the site may be exposed to physical hazards, like,
dust, noise, fugitive dust emissions, welding fumes, working at height, handling of
heavy loads, falling objects underneath of temporary structures, working on
unguarded moving machine, hammering and cutting without PPEs, etc. These are
most occupational hazards at the airport construction site and may have potential
adverse impacts on the Occupational Safety and Health. Hence, overall impact is
rated as follows:
Mitigation Measures
The construction phase of the new integrated terminal building and other associated
work will have beneficial impacts on social environment as private land acquisition is
not involved directly as state government is handovering required land for new
integrated terminal building and other associated work.
literacy, health care, transport facilities and cultural aspect are expected to be
insignificant.
Economic Impacts
The relatively short-lived economic impacts of the construction stage are likely to be
experienced in local area for the duration of construction phase as workers make
everyday purchases from local traders in near by areas. This is likely to give a short-
lived stimulus to the shopkeepers/traders that will disappear as soon as the
construction is complete. Noticeable, flow-on economic impacts will be experienced
in other sectors of economy as a result of purchase of construction materials and the
payment of wages and salaries to the personnel engaged in the new integrated
terminal building and other associated work. Hence, impact on economic impacts is
rated as follows:
Employment
During the construction of the new integrated terminal building and other associated
work, 300 to 400 skilled and semiskilled and unskilled workers will get direct
employment opportunity for about one year, which will have beneficial impact on the
socio-economic conditions of the area. Therefore, overall positive impacts are
anticipated on socio-economic environment during construction phase. Furthermore,
local skilled, semi skilled and unskilled labourers will get indirect employment also
during the construction phase. This may also result in a steep rise in wages of
workers in the surrounding villages. Several other opportunities for locals will be
available in terms of supply of construction materials & machinery, vehicles and other
essential commodities, petty contracts, etc. Hence, overall impact on employment is
rated as follows:
Mitigation Measures
• Preference will be given to locals for direct and indirect employment opportunity;
• Local suppliers for machineries and construction materials will be given
preference;
• Local transporters will be preferred for transportation of machinery/
earth/materials;
• To train unskilled local work, short term skill development course will be
organized in the area.
Although the construction contractors are likely to use unskilled labour drawn from
local communities, use of specialized road construction equipment will require trained
personnel not likely to be found locally. Sudden and relatively short-lived influxes of
construction skilled workers to communities near the airport may have the potential to
‘skew’ certain demographic variables and the traditional social coherence. Hence,
overall impact influx of construction workers is rated as follows:
During operation phase, new integrated terminal building and other associated work
at Guwahati Airport will comprise mainly following activities:
During the operation of the new facilities, the following sources of pollution are
anticipated:
• Exhaust emissions in the form of particulate matters, NOx, SO2 CO and unburnt
hydrocarbons will be emitted from aircrafts movement (take-off, landing and
taxing), vehicular movement, and operation of DG sets;
• Wastewater from domestic usages which include, dine outlets, washing hands,
toilets and urinals, etc;
• Energy consumption for HVAC and lightings in new construction buildings.
• Solid waste from aircrafts, passengers, visitors, staff, cargo handling, sewage
treatment plant (STP), waste lubricating oil from machinery/ equipments, etc;
• Accidental spillage of fuel oil, if any.
The anticipated environmental impacts of the new integrated terminal building and
other associated work at Guwahati Airport & associated activities and corresponding
mitigation measures for operation phase have been described in the following sub-
sections.
During operation phase of the Guwahati Airport after new integrated terminal building
and other associated work, no impact is anticipated on the topography and
physiography of the area. Hence, no mitigation measure is required.
Total water requirement at Guwahati Airport after proposed new integrated terminal
building is estimated as 1010 kld (Fresh Water 710 kld), which includes water for
HVAC, CFT, green belt purposes. Waste water generated from airport will be treated
in Sewage Treatment Plant (STP) and reused for HVAC, flushing, greenery
development.
The overall impact on water resources during operation phase is rated as follows:
Environment Impact Rating Water Resources
Nature of Impact Adverse
Duration of Impact Long term
Impacted Area Localized
Likelihood of Occurrence High
Severity of Impact Medium
Significance of Impact Medium
Mitigation Measures
• Continuous efforts will be made to reduce water consumption using less water
required cisterns ;
• Water efficient urinal and toilets will be provided in new integrated terminal
building.
• Efforts will be made to stop wastage and leakage of water;
• Sewage and domestic waste water will be treated in MBR based Sewage
Treatment Plant
• Reused treated waste water in HVAC, flushing, greenery and landscaping
Total estimated wastewater generation during the operation phase is 808 kld, which
will be treated in Sewage Treatment Plant (STP). After treatment, treated wastewater
is reused for HVAC, flushing, greenery and landscaping. No wastewater will be
discharged outside the airport premises. The overall impact on water quality during
operation phase is rated as follows:
Mitigation Measures
4.4.4 Soil
Approx 3100 kg per day solid waste will be generated during operation of the new
terminal building at Guwahati airport, which is collected, segregated and managed by
external agency for disposal as per Solid Waste Management Rule, 2016. Hence, the
impact on the soil will be insignificant as an organized solid waste collection and
disposal practices exist at the Guwahati Airport.
The overall impact on soil quality during operation phase of proposed terminal building
and associated works is rated as follows:
Environmental Impact Rating Water Quality
Nature of Impact Adverse
Duration of Impact Long term
Impacted Area Localized
Likelihood of Occurrence High
Severity of Impact Low
Significance of Impact Negligible
Mitigation Measures
• Municipal solid waste collection bins will be placed at strategic locations in the
new terminal building;
• Agency has been hired for disposal of solid wastes as per the provisions of the
Solid Waste Management Rule, 2016;
• Solid waste generated from the airport is transported in close containers;
• Used lubricating waste oil and oil contaminated clothes etc is collected separately
in containers and is sold to authorized recyclers as per CPCB/ Pollution Control
Board, Assam (ASPCB) guidelines.
During the operational phase of the operation of the new terminal building at
Guwahati airport, the intermittent air emissions are generated from aircraft engines
during approach, landing, taxiing, take-off and initial climb, which is termed as
reference Landing and Take-off Cycle (LTO cycle). The air pollutants of concern from
the aircrafts emissions are un-burnt Sulphur Dioxide, Hydrocarbons (HC), Carbon
Monoxide (CO) and Oxides of Nitrogen (NOx) as per ICAO guidelines.
For power back up 6 DG sets of 2000 KVA capacities each will be available at the
Guwahati Airport, which will be sufficient during operation of new terminal building
and other associated facilities. Exhaust emissions comprising NO2 and SO2 will be
generated from the operation of DG sets, which will be operated only to meet the
power requirement during grid power failure.
Vehicular emissions will also be generated at the Guwahati Airport from the operation
of vehicular traffic at the airport as ground support vehicles, passengers pickup and
dropping vehicles. These vehicles will be mainly diesel and petrol driven and will be
source of mainly CO, HC and NOx emissions.
For prediction of anticipated impact of emissions from the new terminal building at
existing airport, estimation of emissions load from Aircraft LTO, DG sets and vehicles
is essential. The emissions load estimation from various emission sources has been
carried out in following subsection:
Aircraft Emissions
Airport Air Quality Manual 2011 of International Civil Aviation Organization (ICAO)
has been referred for the aircraft emissions, which states emissions for various types
of aircraft based on one LTO cycle for SO2, NOx, CO and HC pollutants. The referred
emission rates for one LTO have been converted to g/sec based on the duration of
one LTO cycle in seconds. As per International Civil Aviation Organization (ICAO),
time and thrust setting for Reference LTO Cycle is 32.9 minutes (1974 seconds).
During peak hour, it is considered that there will be total 4 LTO (2 LTO for each
Aircraft) at the Guwahati airport, which includes all types of aircrafts. For aircraft
emissions estimation purpose, LTO cycle emissions from B 747-400 and A 320 types
of aircrafts have been considered.
The estimated aircraft emissions for Guwahati Airport are given in Table 4.5.
(Kg/LTO Cycle)
SO2 g/s 0.45 0.39 0.10
HC g/s 0.36 0.29 0.15
CO g/s 3.58 3.14 1.18
NO2 g/s 6.23 4.56 0.92
During peak hour there will be total 18 LTO.
SO2 g/s 2.67 2.34 0.61
HC g/s 2.19 1.73 0.88
CO g/s 21.49 18.81 7.08
NO2 g/s 37.39 27.39 5.53
Emissions Rate from All Aircraft
SO2 g/s 5.62
HC g/s 4.80
CO g/s 47.39
NO2 g/s 70.30
(Source : Airport Air Quality Manual 2011, ICAO)
Six DG sets of 2000 kVA capacity each have been installed at the Guwahati airport
to meet the power requirement during grid power failure.
The exhaust emissions comprising mainly NO2, SO2 and Particulate Matter from the
operation of 6 DG sets of 2000 kVA to be operated in the event of grid power supply
failure. Intermittently particulate matter (PM), carbon monoxide (CO) and un-burnt
hydrocarbons will be emitted during operation of DG sets. Exhaust emissions from
DG sets will be intermittent source of emissions as DG sets will be operated only
during grid power failure. 30 m stack height of combined for DG set will be provided
to vent the flue gases into the atmosphere.
The estimated exhaust emissions characteristics from the DG sets are presented in
Table 4.6.
Vehicular emissions will also be generated from the operation of ground support
vehicles within airport and vehicular traffic for pickup and dropping of passengers at
the existing Guwahati airport. These vehicles will be mainly diesel and petrol driven
and emit mainly CO, HC and NO2. The peak hourly vehicular movement 600 vehicles
(including the ground service vehicles, two wheelers, buses and light duty vehicles
mainly cars and light carriage vehicles). The emissions from the diesel and petrol
driven vehicles have been calculated based on the CPCB emissions standards for
Bharat Stage –III/IV. The estimated vehicular emissions at Guwahati Airport are
given in Table 4.7.
Total emissions from aircraft, DG sets and vehicles movement at the Guwahati Airport
after new integrated terminal building are given in Table 4.8.
There will no continuous emissions source at the Guwahati Airport. Air Flights and
vehicular movement remain intermittent at the airport. DG sets will be operated
intermittently in the event of grid power failure. For air pollution dispersion modelling DG
sets have been considered continuous source of emissions. For obtaining short-term
incremental ground level concentration (glc) isopleths, Breeze Air Suite dispersion
model based on Industrial Source Complex Model (ISC-ST3) developed by USEPA
was used. The ISC-ST3 model for emission sources uses the steady state Gaussian
plume equation for single/multiple continuous elevated sources. Calculations are made
at user specified regular rectangular/radial grid points or at specified special receptors
for any averaging time period as well as for entire period of input meteorology. The
model uses Pasquill-Gafford (for rural and urban areas) or Briggs for urban area
dispersion parameter correlations and Briggs plume rise correlation for calculating
short-or long-time incremental glc values at each grid point and these are then used for
plotting the isopleths over the entire grid. Rectangular grid with 500 m grid point
distance is used up to a distance of +10,000 m in X and Y directions with stack
coordinate as (O, O). For aircrafts and vehicular emissions, multiple volume sources
are considered while for DG set stack point model source is considered.
The estimated emission details for DG sets are given in Table 4.8.
The persistence of atmospheric stability class has been estimated using hourly
monitored wind velocity data along with compiled data for sunrise, sunset, solar
insolation for day-time and cloud cover for night-time for the site.
The knowledge of the site specific mixing height (convective stable boundary layer and
inversion height or nocturnal boundary layer) is crucial in a realistic adoption of
appropriate plume rise and vertical dispersion parameters. In the absence of site
specific mixing heights, “Hourly Mixing Height and Assimilative Capacity of
Atmospheric in India” published by Environmental Monitoring and Research Centre,
India Meteorological Department, New Delhi, 2008, has been referred for hourly
mixing heights.
For the short-term simulations for point emission sources, the concentrations were
estimated on around 1600 receptors to obtain an optimum description of variations in
concentrations over the site in 10 km radius covering 16 directions. The incremental
concentrations are estimated for the study period representing post monsoon season.
The results ground level concentrations for SO2, NO2 and Particulate Matter (PM) are
presented in Table 4.9.
Predicted Concentrations
GLCs values presented in Table 4.9 reveals that the assuming that all six DG sets will
be operated continuously, maximum incremental short term 24 hourly ground level
concentrations of SO2, NO2 and PM likely to be encountered are 5.16 µg/m3, 6.82 µg/m3
and 0.96 µg/m3, respectively. The ground level concentrations are occurring at a
distance of 5.7 km in SW direction from the Guwahati airport site. Isopleths for predicted
ground level concentrations for SO2, NO2 and PM are given in Figure 4.2 to 4.4,
respectively.
The air pollution dispersion modelling predictions indicate that the maximum ground
level concentrations for SO2 and NO2 are likely to be well within the prescribed limit of
80 µg/m3 for industrial, residential, rural and other area. However, it is important to
mention that all six DG sets will not be operated continuously. Only four DG sets will be
operated only during grid power failure and 2 DG Sets will be kept standby. Therefore,
anticipated impacts of DG sets operations will be much below to the predicted ground
level constructions.
Resultant Concentrations
The maximum incremental GLCs due to the Guwahati airport for SO2, NO2 and PM are
already included in baseline air quality monitoring carried during study period as
Guwahati Airport is already in operation. Based on the predicted concentrations of
various pollutants due to operation of existing Guwahati Airport, it can be inferred that
moderate impact is anticipated on the ambient air quality of the area, as suitable
mitigation measures will be taken.
Hence, overall impact on ambient air quality during operation phase is summarized
as follows:
Mitigation Measures
Figure 4.2 : Isopleths of GLCs Values for SO2 for Guwahati Airport
Figure 4.3 : Isopleths of GLCs Values for NO2 for Guwahati Airport
During operation phase of the proposed new terminal building at Guwahati airport,
landing, take-off and taxing of various types of aircrafts and apron will be major
sources of noise emissions. The effects of aircraft noise to receptors at the point of
interest on the ground fundamentally depend on the following factors:
• Effective Perceived Noise Level (EPNL) at the point of interest on the ground
during every aircraft movement;
• Type of aircrafts;
• Flight paths of aircraft during take-off and landing; and
• Number of LTO during the given period of time.
Local topography and weather also affect sound propagation generated during take-
off and landing of aircrafts.
To predict the impact on the existing noise levels in the study area due to the
operation of existing Guwahati airport after proposed new terminal building and
associated work, Integrated Noise Model (INM) developed by Federal Aviation
Administration (FAA), Office of Environment and Energy, USA has been used. This
model has inbuilt information on the various types aircrafts.
Aircraft noise modelling through integrated noise model (INM) uses (1) computation
of the flight-segment geometric and physical parameters; (2) flight-segment noise-
level interpolation process; (3) atmospheric absorption adjustment; (4) acoustic
impedance adjustment; (5) flight-segment noise-fraction adjustment for exposure-
based metrics; (6) aircraft speed adjustment for exposure-based metrics; (7) updated
lateral attenuation adjustment; (8) ground-based directivity adjustment for observers
behind start-of-takeoff-roll, as well as for computing metrics associated with run-up
operations; (9) new helicopter noise modelling capabilities and associated
adjustments (including advancing tip mach number, lateral directivity, static directivity
and static duration adjustments); (10) metric computation process; and (11)
development of a recursively-subdivided irregular grid methodology, which is used for
computing noise contours.
The predicted noise levels and influenced area due to aircrafts movement at the
Guwahati airport are given in Table 4.10.
The noise levels from 65-85 dB(A) will be confined within the existing Guwahati airport
boundary. The noise levels of 55 dB(A) cross the boundary and affect 1.4 km2 of area
out side the airport. The noise levels of 50 dB(A) cross the boundary and affect 6.7
km2 of area out side the airport. The background noise levels range from 51.8-69.4
dB(A) at nearby villages which are located 1.4 km to 5.5 km from Guwahati airport. As
Guwahati airport is already in operation, therefore, impact of noise levels due to the
operation of existing Guwahati airport is included in monitored background noise
levels. However, noise mitigation measures to be implemented at and around the
existing Guwahati airport will further reduce the noise levels in nearby settlements.
DG Sets
For power back up 6 DG sets of 2000 kVA capacities each (4 DG sets for operation
during grid power failure and 2 DG sets standby) will be available at the Guwahati
Airport to meet the power requirement in the event of grid power failure. DG Sets will
be provided with acoustic enclosures as per CPCB guidelines. Therefore, noise level
will be essentially within 75 dB(A), as per prescribed noise standards.
It is evident from the above discussions that generation of noise level from aircraft
landing and take-off operation will be for a short duration (few seconds). Hence, the
overall impact on noise levels is rated as follows:
Mitigation Measures
The Guwahati Airport is located about 15 km away from Guwahati City. At Guwahati
Airport traffic circulation and management have been provided in such a way no
traffic jam during passenger drop and pick up. For new integrated terminal building,
existing two lane road will be widened to four lane by the state government for
smooth flow of traffic.
At the arrival and departure of proposed integrated terminal building, there will be
proper traffic circulation and management. After construction of new terminal
building, there is no possibility of traffic congestion on the Guwahati airport as proper
traffic management has been designed. Hence, overall impact on traffic management
during operation phase after construction of new integrated terminal building at
Guwahati Airport is rated as follows:
Mitigation Measures
For proposed new terminal building approx no trees felling will be required. It is
proposed that landscaping and green belt will be developed around open space of
proposed terminal building. For irrigation of green belt, treated waste water from STP
is available and same shall be used. This has positive and long term beneficial
impact on terrestrial ecology of the area. Hence, overall impact on terrestrial ecology
during operation phase is rated as follows:
Mitigation Measures
Deepor Beel Bird Sanctuary, a Ramsar Site is located at a distance of 3 km from the
project site of integrated terminal building. The Deepor Beel Bird Sanctuary is not
located in funnel area of runway of Guwahati Airport. Noise modelling carried for
existing airport, indicate that impact of aircraft noise from aircraft operation on the
Deepor Beel Bird Sanctuary is negligible.
1. Landscaping and green belt will be developed towards Deepor Beel Bird
Sanctuary.
2. Solid Waste Generated from new integrated terminal building will be collected,
segregated and disposed in designated site as per Solid Waste Management
Rule 2016.
3. Sewage generated from the integrated terminal building will be treated in Sewage
Treatment Plant and reused for horticulture and flushing.
4. Recommendations of Chief Wildlife Warden will be implemented.
The most significant occupational hazards from the airport operation at the existing
and after proposed facilities may include; collisions with moving ground service
vehicles, or taxing aircraft, high noise levels near aircraft, jet engine hazards, sucking
of person in to aircraft jet engine, fire in terminal building, etc. The overall impact on
occupational hazards and safety during operation phase is rated as follows:
Mitigation Measures
• Operators and workers have been certified with access to airfield operations.
Workers involved in the operation of aircraft support equipment are familiar with
• Shield guards or guard railings have been installed at all belts, pulleys, gears and
other moving parts;
• Conveyors and similar machinery have been provided with a means for stopping
them at any point ;
• Elevated platforms & walkways, and stairways & ramps will be equipped with
handrails, toe-boards and non-slip surfaces;
• Electrical equipment will be grounded, well insulated and conform to applicable
codes;
• Employees will be provided with hard hats, safety boots, eye and ear protection
and snug fitting gloves, as appropriate;
• Procedures will be strictly enforced for the storage, handling and transport of
explosives, flammable and hazardous materials.
• Necessary control measures like ear muff and ear plug, high visible vest with
refractive tape will be provided to ground staffs at the Guwahati Airport.
• Personnel required to work in areas of high temperature and/or high humidity will
be allowed to take frequent breaks away from these areas; and
• Pre-employment and periodic audiometric medical examinations will be
conducted for personnel potentially exposed to high noise areas.
During operation phase new integrated terminal building at Guwahati Airport will
open additional direct and indirect job opportunities in the area and region. Further, it
will attract more and more tourist, commercial and developmental activities in the
area. Therefore, positive impacts are anticipated on socio-economic environment
during operation phase after extension.
The new integrated terminal building, Guwahati Airport will result in a boost in tourism
and commercial activities in the region. This will improve direct and indirect
employment opportunities, revenue generation, commercial and industrial activities;
therefore, resulting in positive impact on the employment and economic growth of the
region. Hence, overall impact during operation phase is rated as:
Environmental Impact Rating Employment & Economic Growth
Nature of Impact Beneficial
Duration of Impact Long term
Impacted Area Regional
Likelihood of Occurrence High
Severity of Impact Medium
Significance of Impact Moderate
Chapter-5
ANALYSIS OF ALTERNATIVES
5.1 Introduction
The existing terminal building at Guwahati has saturated. In view of the future
traffic growth at Guwahati Airport, there is a urgent need requirement of
construction of New Integrated Terminal Building at the available land within the
airport premises. The site for proposed new integrated terminal building will be
within airport. Therefore, no alternative site has been considered for new
integrated terminal building.
5.3 Alternative for New Building
years & finally to match level of service ʺCʺ in year of saturation. The building will
be provided with aesthetically appealing & soothing interior decoration matching
the modern structure.
During design and construction of new terminal building at the Guwahati airport
necessary measures will be taken for conservation of energy in line with “Energy
Conservation Building Code–2017” and “National Building Code 2016”. The
important energy conservation measures proposed for new terminal building are
described below:
• Airport Terminal building have been designed and constructed for GRIHA
Rating 4 star,
• Use of Energy Efficient building material & glass,
• Use of LED lamps instead of GLS lamps,
• Use of Solar Backed up Light Emitting Diode Lamps instead of par lamps,
• Energy efficient HVAC system,
• Solar passive techniques for terminal building,
• Use of 5 star BEE energy efficiency rating electrical equipments,
• Microprocessor-based Building Management System (BMS) will be installed
for minimization of energy consumption,
• Automatic lighting on/ off control system will be provided in the airport area
for optimum utilization of energy.
It is proposed that 540 KW solar power generation plant will be established at the
airport to produce clean energy.
It is proposed that all works necessary will achieve 4 stars GRIHA Rating. GRIHA
is an acronym for Green Rating for Integrated Habitat Assessment. GRIHA is a
rating tool that helps to assess the performance of their building against certain
nationally acceptable benchmarks. It evaluates the environmental performance of
a building holistically over its entire life cycle, thereby providing a definitive
standard for what constitutes a ‘green building’. The rating system, based on
accepted energy and environmental principles, will seek to strike a balance
between the established practices and emerging concepts, both national and
international.
CHAPTER 6
The parameters relevant for analysis of quality of treated waste water from STP are
pH, total dissolved solids, total suspended solids, BOD, COD, oil & grease, etc. The
sampling and analysis of ground water quality will be carried out in accordance with
the Indian Standard Drinking Water Specification - IS 10500:2012.
6.2.4 Soil
During construction and operation phases of new integrated terminal building and
associated facilities at Guwahati Airport, soil may be contaminated if suitable
mitigation measures are not taken. Therefore, composite sample of soil will be
collected and analyzed during construction and operation phases.
Table 6.1: Environmental Monitoring Plan for New Integrated Terminal Building at Guwahati Airport
Environmental Project stage Parameter Standards Locations Duration/
Component Frequency
Air Construction Phase PM2.5, PM10, SO2, National Ambient Existing Airport, Continuous 24-
NO2, CO Quality Standards Guwahati hourly, once in
season
Operation Phase PM2.5, PM10, SO2, National Ambient Existing Airport, Continuous 24-
NO2, CO Quality Standards Guwahati hourly, once in
season
Water Quality Construction Stage Parameters as per IS As per potable One sample at the Once in six months
10500:2012 water quality Guwahati Airport during the
standards (IS construction phase
10500)
Operation Phase Parameters as per IS As per potable Guwahati Airport Once in six months
10500:2012 water quality during the operation
standards (IS phase
10500)
Treated Waste Operation Phase pH, TDS, TSS, BOD, As per prescribed One sample of Once in month
Water from STP COD, Oil & Grease standards treated waste water
at outlet of STP
Noise Construction Phase Day and Night Time As per National 4 locations on the Once in season
Noise Level in dB (A) Noise standards boundary of during the
Guwahati airport construction phase
Operation Phase Day and Night Time As per National Terminal building Once in season
Noise Level in dB (A) Noise standards arrival and during the operation
departure, Boundary phase
of Guwahati Airport.
Soil Construction Composite sample As per EMP At Guwahati Airport Pre and Post
from the site for Monsoon during the
Physio-chemical construction phase
parameters
Responsibilities for overseeing will rest with the Airports Authority of India.
Capacity to quantitatively monitor relevant environmental/ecological parameters
would be an advantage but monitoring will primarily involve ensuring that actions
taken are in accordance with contract and specification clauses, and specified
mitigation measures as per the Environmental Management Plan (EMP).
The reporting system has been prepared for the following phases of the
proposed extension of runway, expansion of apron and associated works at
Guwahati airport, viz:
• Operation Stage
The budget for environmental monitoring for construction and operation phases
of the proposed extension of runway, expansion of apron and associated works
at Guwahati airport has been estimated and presented in Table 6.3. The
construction phase monitoring period for the airport has been considered for 3
years while for operation phase monitoring period has been taken for 5 years.
Air
Operation Six Monthly Monitoring of DG sets 1 no of samples every Rs 4,000/- 60 240000
emissions year for 5 years per sample
Ambient air quality monitoring during Continuous 24-hourly, Rs 5,000/- 60 300000
operation phase at 4 locations twice a week once in per sample
season for 5 years
Ground water at the site for Rs 6,000/- 4 24000
Construction Pre and Post Monsoon per sample
construction period
Ground Water at Site for 5 years of Rs 6,000/- 10 60000
Water Pre and Post Monsoon
operation phase per sample
Operation Treated waste water from outlet
Rs 3000/- per
Sewage Treatment Plant (STP) for 5 Every 6 Month 10 30000
sample
years of operation phase
At equipment yard No. of Samples Rs. 2,000/- As and when 60000
per sample necessary
Ambient noise levels monitoring at One day hourly Rs 2,000/- 50 100000
Construction
construction site in tandem with measurement, once in 6
Noise construction activities at 4 sides months for 5 years
boundary of the Guwahati airport site
Operation Terminal building arrival and One day hourly Rs 2,000/- 40 80000
departure, take off and landing side of measurement, once in 6 per sample
boundary months for 5 years
Soil Construction Composite sample from the site for Pre and Post Monsoon Rs 6,000/- 4 24000
Physio-chemical parameters per sample
CHAPTER – 7
7.1 Introduction
Other incidents, which can also result in a disaster at the new integrated terminal
building at Guwahati airport, are:
7.3.1 Introduction
qualitative/quantitative techniques.
At the airport, HSD is stored and handled for DG sets operation while ATF is
stored for refueling of aircraft. It is essential to have comprehensive information
on High Speed Diesel (HSD) and Aviation Turbine Fuel (ATF) being handled at
the Guwahati airport. An understanding of their physico-chemical properties of
HSD will help for hazard identification.
High speed diesel is a mixture of straight run product (150 °C and 350 °C)
with varying amount of selected cracked distillates and is composed of
saturated hydrocarbons (primarily paraffins including iso, and cycloparaffins),
and aromatic hydrocarbons (including napthalenes and alkylbenzenes). Its
exact composition depends on the source of crude oil from which it is
produced and the refining methods used.
HSD presents a moderate fire hazard. On heating, it can cause pressure rise
with risk of bursting and subsequent explosion. It also forms explosive mixture
with air particularly in an empty container
Aviation Turbine Fuel (ATF) is clear colourless to yellow liquid with slight
petroleum odor. It is flammable liquid and highly flammable in presence of
open flame and spark. The flammability of ATF is ranked as 2 by National Fire
Protection Association (NFPA).
7.3.3.1Hazardous Conditions
An accidental release of HSD for DG operation and ATF from tanks or piping
during unloading and filling in aircraft may result in formation of fixed or
spreading pool of released qualities. In case of immediate ignition a pool fire
will result. Delayed ignition may result in explosion or flash fire, if quantity of
Pool Fire
The extent of injury to people depends on the heat flux and duration of
exposure. The extent of damage to personnel and property depends on the
size of the pool and the duration of fire.
Thermal Effects
In case of fire, thermal effect is likely to cause injury or damage to people and
objects. A substantial body of experimental data exists and forms the basis for
thermal effect estimation. The consequence caused by exposure to heat
radiation is a function of:
The following damage distances for thermal radiation have been used:
Vapour cloud explosion scenarios have been considered for confined (over
pressure scenario) as well as non-confined scenario (flash fire).
If a released HSD and ATF are not ignited directly, the vapour cloud will
spread in the surrounding area towards wind direction. The drifting cloud will
mix with air. As long as the vapour concentration is between the lower and
upper explosion limits, the vapour cloud may be set on fire by an ignition
source. In case of delayed ignition of a vapour cloud, two physical effects
may occur: a flash fire (non-confined) over the whole length of the flammable
vapour cloud; a vapour cloud explosion (confined) which results in blast wave,
with typical peak overpressures circular around the ignition source. For
generation of overpressure effects, some degree of confinement of the
flammable cloud is required. The extent of injury to people & damage to
property or environment depends on the cloud size, explosive mass in the
cloud and the degree of confinement at the time of ignition.
In case of delayed ignition of a natural vapour cloud, two physical effects may
occur:
• A flash fire (non confined explosion) over the whole length of the explosive
vapour cloud;
• A vapour cloud explosion (confined explosion) that results in blast wave,
with typical peak overpressures circular around the ignition source. For
generation of overpressure effects, some degree of confinement of the
flammable cloud is required.
The following Table 7.1 gives damage criteria with respect to the peak
overpressures resulting from a blast wave:
The Table 7.2 below gives an illustrative listing of damage effects caused by
peak overpressure.
At the Guwahati airport, HSD and ATF may be released as a result of failures of
hose pipe used for loading and unloading or catastrophic rupture of pipe or pipe
connection, causing possible fire and explosion resulting damage human and
property in the surrounding area. This section deals with the question of how the
consequences of the release of such substances and the damage to the
surrounding area can be determined by means of models. Maximum Credible
Accident analysis encompasses certain techniques to identify the hazards and
calculate the consequent effects in terms of damage distances of heat radiation,
vapor cloud explosion, etc. Depending upon the effective hazardous attributes
and their impact on the event, the maximum effect on the surrounding
environment and the respective damage caused can be assessed.
The Guwahati Airport may mainly pose flammable and explosion hazards due to
unwanted release or leakage of HSD and ATF. Consequence analysis is
basically a study of quantitative analysis of hazards due to various failure
scenarios. It is that part of risk analysis, which considers failure cases and the
damage caused by these failure cases. It is done in order to form an opinion on
potentially hazardous outcome of accidents and their possible consequences.
The reason and purpose of consequence analysis are many folds like:
The results of consequence analysis are useful for getting information about all
known and unknown effects that are of importance when some failure scenario
occurs and also to get information as how to deal with the possible catastrophic
events.
On release of HSD from unloading hose, HSD will be spread on the ground
and spread pool of HSD will be formed. On early or delayed ignition, spread
pool fire will be observed. Consequence calculations for HSD from unloading
hose followed by fire have been carried out as per the details given below:
Thermal radiation radii from spreading pool fire are shown in Figure 7.1.
Figure 7.1: Intensity Radii for Late Pool Fire for Leakage of
HSD from Unloading Hose
Flash Fire
In the event of delayed ignition, vapours of HSD will be generated from the
surface of spread pool and dispersed into the atmosphere towards prevailing
wind directions. The distances of HSD vapours within the UFL and LFL are
given below:
Distances (m)
Concentrations
4 m/s – B 3 m/s – D 2 m/s - E 2 m/s - F
UFL 5.66 4.188 4.18 2.71
LFL 88.77 114.98 103.55 107.16
Figure 7.2: Flash Fire Envelope for Leakage of HSD from Unloading Hose
On release of ATF during filling aircraft, ATF will be spread on the ground and
spread pool of ATF will be formed. On early or delayed ignition, spread pool
fire will be observed. Consequence calculations for ATF from filling hose
followed by fire have been carried out as per the details given below:
Thermal radiation radii from spreading pool fire are shown in Figure 7.3.
Figure 7.3: Intensity Radii for Late Pool Fire for Leakage of ATF from Loading
Hose
Flash Fire
In the event of delayed ignition, vapours of ATF will be generated from the
surface of spread pool and dispersed into the atmosphere towards prevailing
wind directions. The distances of ATF vapours within the UFL and LFL are
given below:
Figure 7.4: Flash Fire Envelope for Leakage of ATF from Loading Hose
In the event of ATF tank on fire, thermal radiation will be occurred in the
surrounding area. Thermal radiation distances will be as given:
Radiation Thermal Radiation Level Distances (m)
Level 4 m/s – B 3 m/s – D 3 m/s - E 2 m/s - F
Not Not Not Not
37.5 kW/m2
Reached Reached Reached Reached
12.5 kW/m2 24.90 24.49 25.04 24.82
4 kW/m2 58.77 57.11 58.22 56.59
Thermal radiation radii from tank on fire are shown in Figure 7.5.
Explosion Effects: In the event of fire in ATF tanker, explosion may take
place. Maximum distances for overpressure are as given below:
Late explosion worst case radii distances are shown in Figure 7.6.
Figure 7.6: Late Explosion Worst Case Radii for ATF Tanker on Fire
Flash Fire
In the event of delayed ignition, vapours of ATF will be generated from the
surface of spread pool and dispersed into the atmosphere towards prevailing
wind directions. The distances of ATF vapours within the UFL and LFL are
given below:
Figure 7.7: Flash Fire Envelope Radii for ATF Tanker on Fire
The risk mitigation measures already being taken at Guwahati Airport are as
given below:
Fire on the ground can be aircraft related and non-aircraft related. Fire
involving aircraft can be at any location on the taxiway or apron area where
the aircraft is parked. Non-aircraft related fire involves mainly the terminal
buildings, ATF tanker and HSD storage, etc.
During a major disaster such as severe fire outbreak at terminal building, the
various emergency operations will be established immediately to mitigate the
disaster.
Assembly area is an area set up near the incident site to temporarily receive
the uninjured casualties until the arrangements to transport them to the
Hospital is made. Two Assembly Areas (AA) will be near parking in front of
terminal building.
The FRRC serves as a secure area, away from the attentions of the media,
for the friends and relatives of those involved in an accident. The
documentation process within the FRRC helps to confirm who was on the
site/aircraft and facilitates the reunion.
On receiving the "Fire" message, Terminal Director will set up the FRRC.
The staff shall man the FRRC, and the police shall take charge of the security
of the area.
CMC
ECC FRRC
Airport Director – Chairman and his team shall take the lead to handle all
press matters. They are single point media interaction. They will be
responsible for developing the overall information management plan, with
emphasis on strategies to manage the information flow. They will also be
responsible for the preparation of press releases and the organization of
press conferences.
All press personnel will first be directed to Airport Director 's Media Centre. At
the Media Centre, press briefing, communications and transportation service
for taking the press personnel to and from the accident site, when permissible,
will be arranged/provided.
An aircraft can catch fire while it is taxiing in the movement area or parked.
Such a scenario can arise from a defect or malicious act, and may develop
into a major disaster.
When the aircraft on the ground on fire is sighted, Airport Fire Service through
the crash alarm communication system will be informed and provide details of
the aircraft fire, for example:
• Location of aircraft;
• Nature of fire (e.g. undercarriage fire, engine fire);
• Number of POB; and
• Presence of dangerous goods, if known.
The Air Traffic Controller shall give clearance to the responding fire vehicles
to enter the runway/taxiway as soon as possible.
If the fire is large and has caused extensive damage to the aircraft and
external resources are required to aid in the mitigation process, the Air Traffic
Controller shall declare "Aircraft on Fire".
The standard text and format used for the "Aircraft on Fire" message shall be
as follows:
AIRCRAFT ON FIRE:
Aircraft Operator;
Aircraft Type & *Flight Number; Location of Aircraft;
*Nature of Fire (e.g. undercarriage fire, engine fire);
*Number of Persons on Board (POB);
*Any Dangerous Goods on Board.
(*The information shall be provided if it is available and applicable.)
The use of the phrase "Aircraft on Fire" is to give distinction and therefore
avoid confusion between aircraft crash and aircraft on the ground on fire.
Fire may occur at any of the part of Guwahati Airport. If out of control, such a
fire may cripple the key Guwahati airport facilities and disrupt the normal
operations.
During a fire occurrence, however small it may appear to be, any person
discovering it shall:
♦ Raise the fire alarm via the nearest manual call point. If no manual call
point is readily available, raise the alarm by other available means.
♦ Inform the Fire Service immediately of the exact location of the fire via the
following telephone numbers.
♦ On receipt of a structural fire call, the Fire Operator shall request the caller
to provide the following details:
• Location of fire;
• Type of fire;
• Name of caller;
• Telephone number of caller.
The frequency of the drills would vary depending on the severity of the
hazard. However, drills would be conducted once in a year. Scenarios may be
developed in such a manner as to accomplish more than one event objective.
Evaluation of drills and exercises would be carried out which would include
comments from the participants and observers. Discrepancies noted by the
drill observers during the drill shall be pointed out during the drill.
The individual responsible for conducting the drill or exercise would prepare a
written evaluation of the drill or exercise. The evaluation would include
assessments and recommendations on:
The Safety In-charge would track all approved drill and exercise corrective
actions as a means of assuring that corrections are made in a reasonable
amount of time, and shall advise the Terminal Manager of the status of
implementation of corrective actions.
CHAPTER- 8
PROJECT BENEFITS
8.1 General
The existing terminal building has saturated. In view of the future traffic growth
at Guwahati Airport, there is a requirement of construction of new integrated
terminal building on turn key basis. Increasing numbers of passengers and
aircraft require capacity enhancement of existing facilities including terminal
building, apron, link taxiway etc at Guwahati Airport.
The direct and indirect benefits of the new terminal building and associated
facilities at Guwahati Airport are as follows:
Direct Benefits
CHAPTER 9
9.1 Introduction
The Environmental Impact Assessment (EIA) has identified environmental impacts those
are likely to arise during construction of new integrated terminal building and associated
works at Guwahati Airport. The Chapter 4 of this report has examined both adverse and
beneficial impacts on each physical, biological and socio-economic parameters of
environment during construction and operation phases of new terminal building and
associated work at Guwahati Airport. The environmental impact assessment has
examined the extent to which these impacts would be mitigated through the adoption of
standard practices, guidelines and complying with regulatory requirements. The
Environmental Management Plan (EMP) describes both best practice measures and site
specific measures. The implementation of EMP is aimed at mitigating potential
environmental impacts associated with the construction and operation phases of
proposed during new terminal building and associated work at Guwahati Airport.
9.2.1 Soil
Construction Phase
During the construction phase of new integrated terminal building and associated work at
Guwahati Airport, the following measures shall be adopted to minimize adverse impacts in
soil:
• To prevent the soil contamination through the leakage or spillage of fuel oil, oil
containers will be stored and handled carefully on cement lined floor,
• All metal, paper, plastic wastes, debris and cuttings shall be collected from the site
as soon as particular construction activity is over,
Operation Phase
Approx. 3100 kg/d solid waste is generated from the proposed new terminal building in
the form of paper, plastics, polyethylene bags and food waste, etc. Solid waste from the
airport is collected in waste bins.
Approx. 100 to 150 kg sludge generated from STP is used as manure for green belt
development at the airport.
The solid waste handling and disposal services will be outsourced by Airports Authority
of India to authorized agency to ensure proper disposal of solid waste generated at the
existing airport. AAI ensures that solid waste is being management as per Solid Waste
Management Rule 2016.
Construction Phase
The following mitigation measures will be adopted to avoid impacts on water quality
during construction phase:
Operation Phase
The following measures will be taken to protect water quality at the existing Guwahati
airport during operation phase:
• Sewage generated is collected and sent to sewage treatment plant for proper
treatment and disposal.
• Solid wastes generated at the existing Guwahati airport is collected and disposed
suitability as per standards practices.
• Waste oil generated from DG sets is collected and disposed to PCB, Assam
approved waste oil recyclers for recycling and reuse.
Sewage generated from the airport is treated in well designed Sewage Treatment Plant
(STP). Membrane Bio Reactor type sewage treatment plant of 1000 KLD capacity will be
installed at the Guwahati airport.
Coarse Screening: Wastewater from new integrated terminal building will flow by
gravity to the STP. Solids of size larger than 20 mm will be screened out by the
automatic raked coarse screens installed upstream of the equalization tank. The coarse
screening is designed to protect the downstream mechanical equipment in the
equalization tank.
Equalization Tank: The equalization tank is designed to smooth out peak flow and meet
the design flow for two hours. Aeration will be carried out by air supply through diffusers
and blower.
Fine Screening: The equalized wastewater will be then further screened by the
automatic fine screens. Solids of size over 2 mm will be screened out prior to the anoxic
tank. The fine screening is designed to protect the downstream membrane module and
aeration equipment.
Anoxic Tank: Screened wastewater flows to the anoxic tank and is mixed with the
nitrate recycled from MBR tank and pre-aeration tank for denitrification. The design
denitrification rate is 0.02 kg-N/kg-MLSS/d at 18℃.
Membrane Bioreactor: Mixed Liquor Suspended Solids (MLSS) from the anoxic tank is
evenly distributed to two MBR tanks in which biological oxidation and nitrification takes
place. Each MBR tank contains sets of fully submerged flat sheet type membrane
modules and each membrane module will have 200 nos. of membrane panels. The
membrane modules comprises two sections – the top section containing membrane
cartridges fixed into a stainless steel housing constructed with the lower section
containing coarse bubble diffusers. The bubbles released by the lower diffuser section
generate an upward sludge bubble flow over the membrane surface at a velocity of
approximately 0.5 m/s. This bubble flow is able to minimize fouling and allow low
pressure suction filtration of the treated effluent into the inner compartment of membrane
cartridge and thence to the collecting manifold. The membrane nominal (maximum) and
average pore sizes are approximate 0.4 microns and 0.2 microns respectively. The MBR
tank performs both functions of aerobic treatment and solids / liquid separation. The
complete MBR system will be able to operate at high MLSS concentration in the range
6,000 - 20,000 mg/L, low sludge production rate due to long sludge age and strong
resistance to shock pollutant loads. The micro-filtration performance of the flat sheet
type membrane also produces permeate to disinfected quality. As discussed above, the
denitrification is performed in a separate anoxic compartment. Sludge is drawn off at a
constant volume rate to maintain the MLSS at the optimum level according to the
operational needs Design flux rates of 0.35 and 1.2 m3 /m2 /d are used for sizing the
average flow and design peak flow of the MBR system respectively.
Tertiary Treatment : Treated waste water from pre collection tank will be passed
through pressure sand filter and activated carbon filters.
Disinfection: In order to ensure pathogen-free for the recycled water, chlorination using
sodium hypochlorite will be adopted for disinfection followed by the de-chlorination.
Construction Phase
During the construction phase, following measures shall be taken for solid waste
management:
• All metal, wooden, paper, plastic wastes, debris and metal cuttings shall be collected
from site as soon as particular construction activity is over and disposed in suitable
manner.
• Municipal waste generated will be collected and disposed in environmentally sound
manner.
Operation Phase
The following mitigation measures will be taken for management of solid waste during
operation phase of at the new integrated terminal building and associated works.
• Solid wastes management at the new integrated terminal building will be carried out
as per Solid Wastes Management Rules, 2000.
• Solid wastes will be collected in designated waste bins based on their types, placed
at the strategic locations in the airport.
Approx. 3100 kg/d solid waste will be generated from new integrated terminal building.
The solid waste handling and disposal services will be outsourced to authorized agency
to ensure disposal of solid waste generated from the Guwahati airport. Solid waste
generated in the aircrafts will also be disposed off at the designated waste collection
points from where the agency will pick up the garbage bags.
The authorised agency, collect the garbage from designated bins at the new integrated
terminal building. The wet garbage of the aircrafts comprising of left over food in the tray
from the security gates of flight kitchens is also disposed off at the specified place.
After collection of waste, solid waste management plan will be followed by authorized
agency is as given below:
Construction Phase
During the construction phase, only marginal deterioration of ambient air quality is
expected at the construction site due to operation of construction equipment and
machinery, dust emissions from loading and unloading of raw materials, cement and
soils, dust emissions from the batch plant, fugitive emissions from vehicle movement,
etc. However, this deterioration will be temporary in the nature during construction
phase. The following measures will be adopted during construction phase to mitigate the
impact on ambient air quality:
• Installation of batch mix plant at isolated place and providing cover shed around the
plant,
• Providing dust suppression system in loading and unloading area,
• Pollution Under Control Certificate will be mandatory for all vehicles approaching to
the site. Any vehicle not meeting the vehicular pollution standards will not be allowed
within the construction site and for the construction activity;
Operation Phase
Major pollutants from the new integrated terminal building operation will be from aircrafts
exhaust, vehicular traffic as ground support, pickup and dropping at the existing
Guwahati Airport and from DG sets. The major pollutants will be mainly Nitrogen di-oxide
and Carbon monoxide besides particulates and sulphur di-oxide. The baseline ambient
air quality levels in the project area will be within the permissible limits as specified as
National Ambient Air Quality Standards. The following methods of abatement of pollution
will be employed for the air pollution control at the source level during operation phase of
the new integrated terminal building:
Construction Phase
During the construction phase, noise will be generated through the operation of
construction machines, excavators and DG sets. The following measures will be taken
into consideration to mitigate the noise at the construction site:
Operation Phase
All the DG sets rooms will be provided with acoustic treatment to control the noise levels
and new DG sets will also be fitted with acoustic enclosures to control the noise levels.
Terminal building will be sound proof. Further, greenery will be developed at the
integrated new terminal building, which will work as noise barrier.
The passenger capacity of proposed new terminal building will be designed for 2900
domestic (including 200 International) at one point of time. The multilevels car parking
facility will be provided for at least 1500 cars and 10 buses.
The proposed new integrated terminal building will be certified under Green Rating for
Integrated habitat Assessment (GRIHA). GRIHA measures which will be considered in
the design and consideration of the project to achieve the 4 star rating under GRIHA V-
2015 are discussed below with various sustainability measures under the following
categories:
a) Architecture measures
b) Landscape measures
c) Structural measures
d) HVAC & Electrical measures
e) Plumbing measures
f) Construction measures
The following codes & guidelines shall be considered for the design of the project for
GRIHA compliance
• Green Rating for Integrated habitat Assessment (GRIHA) rating system V-2015
• Energy Conservation Building Code 2007 (ECBC)
• ASHRAE 90.1-2010
• ASHRAE 62.1-2010
• National Building Code
Site Planning
a) Passive design strategies such as shading device, overhangs, vertical fins etc.
shall be considered to control heat gain through envelope and maximise day light
penetration.
b) Preservation of existing vegetation / water bodies / other topographical features if
applicable.
c) Strategies like Vegetation will be adopted in reduction of heat islands at
microclimate level.
d) Solar photovoltaics in roof areas as passive measure to heat gain reduction.
e) A minimum of 25% of the site area shall be designed with soft paved and/or
covered with SRI coating > 0.5 and/or shaded by vegetation/solar panels and/or
any combination of these strategies.
f) The net imperviousness factor of site shall designed to meet GRIHA requirement
to make post-construction storm water discharge from the site is zero.
g) Internal zoning will be done to provide buffer to conditioned spaces for
unfavourable orientations.
h) Massing of the buildings will ensure that the solar access of neighboring
buildings is not blocked if applicable.
East - West Façades for New Terminal Building are shown in Figure 9.2.
South & North Façades for New Terminal Building are shown in Figure 9.3.
Figure 9.3: South & North Façade for New Terminal Building
Low Impact Design – Passive Design Features are given in Figure 9.4.
Based on wind direction consideration for selected new integrated terminal building
orientation is shown in Figure 9.5.
Construction Management
a) Top soil shall be preserved at site and shall be re-used later for landscaping
purpose.
b) No existing mature trees will be cut on site to the extent possible or mature trees
will be transplanted within the site and the survival shall be ensured or 3 trees will
be planted for every 1 tree cut of the same native/naturalized species or any
combination of these for all mature trees on site.
c) Following measures shall be adopted on site to curb air pollution during
construction:
• Provision of 3 meter high barricading around the construction area.
• Wheel washing facility at the vehicular entrance of the site.
• Covering of fine aggregate and excavated earth on site with plastic/ geotextile
sheets.
• Provision of stabilized construction entrances, exits and vehicular path
d) A spill prevention plan (to control effects of spill from hazardous materials like
bitumen, diesel etc.) shall be developed and implemented at site.
e) Measures will be implemented to prevent/reduce soil movement outside the site.
f) Staging shall be adopted during construction on site.
g) A construction waste management plan for segregation of construction waste, its
safe storage and on-site/off-site recycling shall be developed and implemented in
the project.
h) Strategies to reduce water use during construction shall be adopted.
Energy
a) The thermal properties of envelope (wall, glazing), skylight & roof shall not
exceed the maximum allowable with respect to GRIHA and ECBC.
b) Refrigerant used in HVAC system shall be CFC free.
c) Equipment efficiencies shall be designed to meet & exceed GRIHA & ECBC
requirements.
d) Innovative & practical energy efficient HVAC & Electrical design solutions, such
as displacement ventilation systems, dedicated outdoor air systems, chilled water
plant with high COP, adequate daylight to reduce internal lighting load, LED
luminaries etc shall be adopted
e) 100% of outdoor lighting fixtures shall meet the luminous efficacy requirements
with respect to GRIHA.
f) Interior lighting power budget shall be designed to meet and exceed GRIHA
requirements.
g) If there are ceiling fans required, they shall be minimum BEE 4 Star rated.
h) On-site renewable energy such as photo voltaic shall be designed to offset 1 to
10% of buildings internal artificial lighting and HVAC systems energy
consumption subject to feasibility.
i) Insulation in building shall be CFC and HCFC free.
a) Window to wall ratio of the façade shall be in compliance to GRIHA & ECBC and
the glazing SHGC values shall exceed the minimum performance with respect to
GRIHA & ECBC through passive shades and high performance glass.
i) Adequate daylighting provision will be considered by means of skylight / windows
and the daylighting illuminance level shall meet the minimum illumination levels
(LUX) prescribed in GRIHA & ECBC.
Water
a) Minimum 15% of Ordinary Portland Cement shall be replaced with fly ash by
weight of cement used in structural concrete.
b) Minimum 15% of Ordinary Portland Cement shall be replaced with fly ash in
plaster/masonry mortar.
c) Combined embodied energy of load-bearing structure and masonry walls shall be
reduced by at least 10% below the base case.
d) At least 50% of all materials (calculated by surface area) used for building
interiors shall meet the GRIHA criterion low-impact material requirements.
The efficient construction Materials and Design for new integrated terminal building is
shown in Figure 9.6.
Socio-Economic Strategies
a) Digital energy meters shall be provided for all major energy end-uses.
b) Water metering shall be provided for all major water use.
c) O&M protocol shall be prepared as a minimum for the following:
• HVAC plant - AHU, Cooling tower, Chillers and pumps, VRF
• Electrical - Transformer, DG, HT & LT panels
• Energy Systems - Solar PV, wind mill, bio gasifier etc.
• STP and/or WTP
During design and construction of new terminal building at the Guwahati airport
necessary measures will be taken for conservation of energy in line with “Energy
Conservation Building Code –2017” and “National Building Code 2016”. The important
energy conservation measures proposed for new terminal building are described below:
• Centralized Chilled water system having water cooled centrifugal chilling machines at
11 KV to reduce the voltage drop and cable sizes.
• Variable chilled water pumping system, Variable Frequency Drives (VFD) for AHUs
and Cooling Tower fans.
• Displacement diffusers to through the chilled air at lower height to reduce the air
conditioning load, wherever feasible.
• Outside Air regulation based upon the carbon dioxide sensors in the air conditioned
space.
• Solar power generation of 540 KW on visitors and staff car parking in front of
terminal building using the solar photovoltaic panels.
• Underground rain water storage for one day of rainfall and reuse for potable use.
As per solar system design calculations, 9 sqm areas required to generate 1 kWp of
connected electrical load. It is proposed to install the 540 kW of solar power generation
on visitor & staff car parking. The provision of PV Panels for over car parking at New
Integrated Terminal Building as shown in Figure 9.7.
Landscape and greenery will be developed at and around the new integrated terminal
building. More than 60 % of existing airport is open and grasses, trees and shrubs. At
new integrated terminal building also landscape and greenery will be developed.
Landscape and greenery plan has been shown in Figure 9.8. Only indigenous trees will
be planted as a part of green belt/plantation.
Figure 9.7: Provision of PV Panels for Over Car Parking at New Integrated Terminal Building
During the construction phase of the proposed new integrated terminal and associate
works, about 300 to 400 skilled, semiskilled and unskilled workers will get direct and
indirect employment opportunities, which will have beneficial impact on the socio-
economic conditions of the area.
The following suggestions are given below to strengthen the beneficial impacts:
Construction Camps
At the Guwahati airport, various types of cargo including dangerous goods (hazardous
materials), live animals, perishable, human remains, Sentimental Shipments, explosive,
solid, petroleum products, etc are handled according to IATA regulations and guidelines.
9.2.10.1Acceptance of Cargo
The Guwahati airport has the authorization for transport of passengers and freight,
revenue and non-revenue cargo, as well as air mail and service cargo. All cargo are
physical checked or x-ray before acceptance.
Personal Effects
Sentimental Shipments
For carriage of sentimental cargo, Death Certificate from a competent medical authority,
embalming and packaging Certificate, certificate issued by Embassy (Nationality of
deceased) with the deceased’s full name, age at the time of death, place of death and
photocopy of passport details, Photocopy of cancelled passport, police certificate are
ensured.
Odd-Sized Cargo
Odd sized cargo or heavy cargo to carry, there is expertise in logistics to carry heavy
and odd –sized.
Dangerous Goods
Valuables
In order to ensure security of valuables, container with a security locker on wide body
aircrafts. The narrow body aircrafts are also fitted with locker for valuable cargo. The
entire operation of loading and unloading are carried out under the vigilant eyes of our
Security personnel.
In order to adhere to the strictest security for handling of cargo at the Guwahati airport, it
are ensured that the cargo is loaded on the flight after physical check or x-ray.
Couriers
Courier traffic is a rapidly growing market. Guwahati airport has facility for transporting
small packages and documents.
Perishable goods are such, whose conditions or suitability for its original or prime
purpose may deteriorate below its useable condition if exposed to undue changes in
temperature and humidity or delayed in transportation (e.g. fresh fruit and vegetables,
flowers, meat and fish shipments, vaccines, medical supplies etc.).
9.2.10.2Cargo Manifesting
The manifest contains all packages that are loaded into an aeroplane. Manifests are
differentiated according to the type of transfer of the cargo at the station:
● Cargo Manifest
● Transfer Manifest
● NIL Manifest
The manifest is used for handling air cargo, with the exception of airmail, and is a
necessary working paper for cargo accounting. Cargo is manifested in the IT systems or
manually.
Dangerous Goods are divided into nine different hazard classes. Some hazard classes
are further subdivided into hazard divisions due to the wide scope of the class.
Class 1 Explosives
Class 2 Gas
Class 3 Flammable Liquid
Class 4 Flammable Solids; Substances liable to Spontaneous Combustion; Substances
which, in contact with Water, emit Flammable Gases
Class 5 Oxidizing Substances and Organic Peroxides
Class 6 Toxic (poisonous) and Infectious Substances
Class 7 Radioactive Material
Class 8 Corrosives
Class 9 Miscellaneous Dangerous Goods
Hazard Labels
The label identifying the primary hazard of the dangerous goods must bear the class or
division number as appropriate in the bottom corner of the label.
Packages containing dangerous goods which might react dangerously with each other or
are harmful to other non-dangerous goods must not be stowed on an aircraft next to
each other or in a position that would allow interaction between them in the event of
leakage.
Toxic (RPB) and Infectious Substances requiring a subsidiary risk "TOXIC" label must
not be stowed in the same compartment with animals, substances marked or known to
be foodstuffs, feed or other edible goods intended for consumption by humans or
animals.
This does not apply if either the toxic or infectious substances and the foodstuffs or
animals are loaded in separate ULDs, not adjacent to each other (minimum distance: 1
loading position).
• don't panic
• advise immediate supervisor
• isolate the package by removing other packages or property
• avoid contact with the contents of the package
• if contents come in contact with body or clothes:
Due to individual procedures being applicable for different perishable goods, the
following different load information codes are used:
Loading - Perishable cargo shall be accepted for carriage only if properly packed in
order to avoid damage and/or contamination to other loads, ULDs or compartments.
Pallets with flowers, fruit or vegetables must not be covered with plastic foils -
Perishable cargo, refrigerated with wet ice or containing fluids or moisture which could
leak (e.g. meat, fish or other sea foods - fresh, salted, smoked or frozen) shall be treated
as "Wet Cargo". Perishable cargo, refrigerated with dry ice (ICE) shall be handled
according to the respective regulations. Care shall be taken when stacking perishable
items so that lower layers of the stack are not damaged by the weight of the upper
layers.
Foodstuffs (EAT)
Foodstuffs shall not be loaded together with poisons (RPB) or infectious substances
(RIS) in the same compartment, unless they are loaded in separate ULDs not adjacent
to each other. Foodstuffs shall not be loaded in close proximity of live animals (AVI) and
human remains (HUM).
Hatching eggs shall not be stowed in close proximity of dry ice (ICE) and cryogenic
liquids (RCL). The temperature in the compartment should remain between 10°C and
15°C during flight and should not exceed 27°C.
At the new terminal building, the following fire fighting facilities will be provided:
The Airports Authority of India (AAI) will be responsible for the implementation of
mitigation measures suggested in EMP for construction and operation phases for new
integrated terminal building and associated works. Environmental Management Plan for
new integrated terminal building the at Guwahati Airport is presented in Table 9.1.
Environmental Management cell will implement and review the compliance of the
stipulated conditions specified in Environmental Clearance and Consent for
Establish/Consent to Operate.
9.3.2 Training
The environmental management cell of AAI would responsible for the implementation of
mitigation measures described in the EMP. Personnel working at the site need to be
trained for the effective implementation of the environmental issues. To ensure the
success of the implementation of mitigation measures, there is a high requirement of
training and skill up-gradation of personnel.
As part of the construction and operation, training programs have been worked out for
capacity building needs of the personnel. The program consists of number of training
modules specific to target groups. The training would cover the basic principles and
postulates of environmental assessment.
Table 9.1 : Environmental Management Plan for New Integrated Terminal Building at Guwahati Airport
S. Environmental Management Measures Responsibility
No. Aspect/Issue Construction Supervision/
Agency Monitoring
I. Construction Stage
Activities to be carried out by the Contractor.
C.1 Site Clearance
C.1.1 Filling by Earth For construction of new integrated terminal building at
Guwahati Airport, 5 m deep basement covering an
area 7500 sqm will be constructed. For construction of
the proposed facilities at the Guwahati Airport,
tentatively 100000 cum filling will be required. Approx
Contractor EMC of AAI
50000 cum earth excavated from construction of 7500
sqm size basement will be used filling at airport site.
Additional earth will be procured from approved
quarry. Simultaneous to filling compaction and water
sprinkling will be carried to suppress dust emissions.
The pre-identified disposal locations will be a part of
comprehensive waste disposal and solid waste
management plan to be prepared by the Contractor in
consultation AAI.
C.5.4 Risk Force Measure The contractor will make required arrangements so Contractor EMC of AAI
that in case of any mishap all necessary steps can be
taken for prompt first aid treatment. Construction
Safety Plan prepared by the Contractor will identify
necessary actions in the event of an emergency.
The contractor will arrange for :
Looking into the potential requirements of each of the target groups, the following
training modules have been suggested for construction and operation phases as
part of the EMP.
Assistant General
Manager (EMC)
Technician
STP Technician Environmental
In order to ensure that grievances and complaints by local people on any aspect
of the environmental and social impacts during construction and operation phases
of the proposed project will be addressed in a timely and satisfactory manner and
that all possible avenues will be available to resolve their grievances (if any),
mechanisms for Grievances Redressal will be setup. Environmental Management
Cell will also work as Grievances Redressal Cell (GRC).
Any complaint received from local area regarding environmental and social
issues will be forwarded to General Manager (EMC), who will promptly take
decision and give instructions to implement necessary measures to resolve the
complaints or grievances. To ensure effectiveness of mitigation measures
monitoring will be done regularly.
The reporting system will operate linearly with the contractor who is at the lowest
step of the implementation system to the project management and will report to
AAI.
For the project all reporting by the contractor will be on weekly basis. The AAI
environmental cell will be responsible for preparing targets for each of the
identified EMAP activities.
The reporting by the contractor will be a monthly report like report of progress on
construction and will form basis for monitoring.
The Corporate Social Responsibility CSR) Policy of the Airports Authority of India
(AAI) is aligned with its overall commitment to maintaining the highest standards
of business performance. The Vision of AAI is "to be a world-class organization
providing leadership in air traffic services and airport management and making a
major hub in Asia Pacific Region by 2016".
The policy has been formulated as per the Guidelines on Corporate Social
Responsibility for Central Public Sector Enterprises issued by the Department of
Public Enterprises, Ministry of Heavy Industries and Public Enterprises (vide
F.No. 15(3)/2007-DPE (GM)-Gl-99 dated 9th April, 2010).
For identification of CSR activities for the area, needs assessment was made
during public consultation during the EIA studies. Details of CSR activities
proposed for Guwahati Airport are given In Table 9.2.
during construction and operation phases of new integrated terminal building and
associated facilities. The estimated budget for environmental monitoring plan is
given in Table 9.3 in Chapter 6. Total budget of Rs 0.11 Crore has been kept for
environmental monitoring during construction and operation phases.
CHAPTER 10
Airport Authority of India entrusted, M/s ABC Techno Labs India Private Limited,
for carrying out EIA/EMP studies for the New Integrated Terminal Building at
Guwahati Airport.
ABC Techno Labs India Private Limited, an ISO 9001, ISO 14001 & OHSAS 18001
Certified Company and NABET (QCI) Accredited Environmental Consultancy
Organization. The office of ABC Techno Labs India Private Limited is located at
Chennai as per details given below:
ABC Techno Labs India Private Limited is accredited by NABET (QCI) in the
following Sectors:
ABC Techno Labs India Private Limited is the first firm to be accredited by NABET
(National Accreditation Board for Education and Training), Quality Council of India,
as an EIA Consultant. We are equipped with in-house, spacious laboratory, accredited
by NABL (National Accreditation Board for Testing & Calibration Laboratories),
Department of Science & Technology, Government of India. Since establishment our
focus is on sustainable development of Industry and Environment based on sound
engineering practices, innovation, quality, R&D and most important is satisfying
customers need. The company has successfully completed more than 100’s projects of
variety of industries, in the field of pollution control. We are also dealing in the
projects of waste minimization and cleaner production technology. Our team of
technocrats and scientists are well experienced to deal with the Designing,
Manufacturing, Fabrication, Installation and Commissioning of Effluent/Wastewater
Treatment Plants, Sewage Treatment Plants, Combined Treatment Plants.
We are having a well experienced team of Scientists & Engineers who are looking
after our well-equipped analytical laboratory with a facility including analysis of
physical, chemical and biological parameters as per the requirements of the State
Pollution Control Board and our clients.
ABC Techno Labs India Private Limited carried out EIA studies for the New
Integrated Terminal Building at Guwahati Airport. The multidisciplinary team
comprising NABET accredited experts in the field of land use, air pollution control,
air quality modeling & meteorology, water pollution control, ecology & bio diversity,
noise/ vibration, socio economy, hydrology, geology, soil conservation, risks &
hazard and solid & hazardous wastes management were deployed as team to carried
out EIA studies. Details of team members with their role and responsibility are given
in Table 10.1.
Name : Tailong
Mobile No. : 9566067777
State : Assam
District : Kamrup
Pincode : 781015
6. Protected Area (ha.) : 0
The proposal will be examined by Wild Life Warden, Forest (Conservation) Act,
1980 to assess its completeness.
(System Administrator)
https://mail.google.com/mail/?ui=2&ik=62d4a82aa8&jsver=M-xhRWn0lp0.en.&view=pt&search=inbox&th=15fca1c89642d7f0&siml=15fca1c89642… 1/1