Shutdown Report July 10

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 21
At a glance
Powered by AI
The report describes maintenance activities performed during a shutdown period of the thermal power plant in July 2010, including activities on the boiler, coal handling plant, electrical equipment, and vibration measurements.

Maintenance activities on the boiler included fabrication and erection of an over bed fuel feeding chute, renewal of bed drains and pipes, and renewal of thermocouples.

Components replaced or renewed in the coal handling plant included the reverse shuttle feeder conveyor belt and the coal handling plant dust extraction bag filter.

SHUT DOWN REPORT

JULY – 2010

SAMRUDDHI SITE

1 X 12.5 MW THERMAL POWER PLANT

Shutdown from : 05 – July – 2010 - 00:10 Hrs

Synchronized at : 23 – July – 2008 - 20:28 Hrs


CONTENTS

DESCRIPTION PAGE No

1) MAJOR EVENTS : 3

2) ACTIVITIES ON BOILER : 5

3) ACTIVITIES ON ASH HANDLING SYSTEM : 8

4) ACTIVITIES ON COAL HANDLING PLANT : 9

5) ACTIVITIES ON TURBINE AUXILIARIES : 9

6) ACTIVITIES ON RO/DM & COOLING TOWER : 10

7) OTHER ACTIVITIES : 11

8) SAFETY VALVE SETTINGS REPORT : 12

9) DISPLACEMENT / SPEED, VIBRATION / SENSORS


INSPECTION / MEASUREMENT REPORT : 13 - 20

Hofincons – Samruddhi site - Shutdown report – July - 2010 2


MAJOR EVENTS

 Fabrication & Erection of over bed fuel feeding chute for 2nd & 3rd Compartment.
 DCF#1, #2, #3 & #4 new chain replaced.
 DCF #1, #2 & #4 - DE & NDE Shaft with sprockets and bearings replaced.

 ID Fan DE & NDE bearing and Plummer block renewed.

 PA fan #2 DE & NDE bearings renewed.

 FD Fan DE and NDE bearing renewed.

 Boiler all bed drains below and pipe renewed.

 All vertical and Horizontal PA line pipes renewed and extra gate additionally

added

 Reverse Shuttle Feeder conveyor Belt renewed.

 BFW Pump #2 DE & NDE Bearing hosing, stuffing box and bearing renewed.

 Ash silo bag filter inspection and renewed.

 CHP Dust extraction bag filter inspection and renewed.

 CHP Dust extraction hopper modification.

 CHP Bucket elevator discharge chute renewed.

 Cooling tower fan # 1 gear box renewed.

 TPP & DG all HT panel and LT panel, GCP, GRP panel relays testing coordination

done.

 TPP All LT Breakers servicing coordination done.

 TPP All HT Breakers servicing and O/G terminal side inspection work done.

 TPP to DG-2 DSLC panel cable termination, programming and commissioned work
U/p

Hofincons – Samruddhi site - Shutdown report – July - 2010 3


 TPP Aux TR-1&2, ESP TR-1&2 Oil filtration and checked Oil BDV test coordination
done.

 TPP Main Battery Bank and Stand by Battery Bank Load test coordination and
checked found working normal.

 DG All HT Breaker servicing work done.

 TPP Alternator, Exciter, PMG cleaning and inspection work done.

 TPP Alternator LASCPT panel, NGR panel, GCP, GPR, AVR panel cleaning and
inspection work done.

 Turbine major O/H Bolt heating equipment power cable, JB fixed and termination
work done.

 All Boiler & Turbine area MOV valves and actuators cleaned and signal cables
terminations checked and operation checked from DCS Found normal.

 All local Instrument JBs cleaned and terminations checked found normal.

 All vibration probes & speed probe in Turbine and Alternator side removed for
major O/H then fixed back found all probes are normal the gap voltage measured
is enclosed for reference at Page No : 14 - 21

 All Boiler & Turbine aux. system PGs and TGs calibrated and found normal.

 Five numbers of bed thermo well and all thermocouples renewed.

 All Control valves & RPCs calibrated as well as stroke checked found normal.

 All transmitters were calibrated found all in order.

 TPP UPS battery cell voltage checked and found ok.

 FD, PA & ID vibration probe and Temperature sensor serviced and fixed back.

 All FD & PA line power cylinders & all bleed valves and SOVs serviced and fixed
back.

 MOV valves were stroke & found ok

Hofincons – Samruddhi site - Shutdown report – July - 2010 4


ACTIVITIES ON BOILER

• Remaining fuels emptied from Lignite & Coal bunkers and all bunker lumps
removed.

• RSFD #1 conveyor Belt renewed.

• All DCFs were cleaned.

• All DCFs were provided with new rail plates.

• DCF #1, #2, #3 & #4 new chain provided.

• DCF #1, #2 & #4 renewed DE & NDE Shaft with sprockets and bearings.

• DCF # 3 DE and NDE both bearing renewed.

• Boiler PA drain #1, #2, #3 and #4 compartment all pipe line renewed and

extra gate 16 nos provided.

• Boiler PA horizontal #1, #2, #3 and #4 compartment all pipe line from Air

box to Mixing nozzle renewed.

• Boiler- compartment #2 and #3rd OBF chute renewed.

• Boiler MCC panel bus, cable chamber and all feeders maintenance work done.

• All Lignite and Coal Pocket feeder motors DE & NDE side bearing renewal and

winding cleaning varnish applied.

Phase to Earth IR Value WR Value

#1 100 meg Ω 11.1 Ω /ph


#2 100 meg Ω 11.3 Ω /ph
#3 100 meg Ω 11.5 Ω /ph
#4 100 meg Ω 11.4 Ω /ph
#5 100 meg Ω 10.2 Ω /ph
#6 100 meg Ω 10.9 Ω /ph
#7 100 meg Ω 10.5 Ω /ph
#8 100 meg Ω 11.4 Ω /ph

• All Drag Chain Feeder motors DE & NDE side bearing renewal and winding

cleaning varnish applied.

Phase to Earth IR Value WR Value

#1 100 meg Ω 9.1 Ω /ph


#2 100 meg Ω 9.3 Ω /ph
#3 100 meg Ω 9.5 Ω /ph

Hofincons – Samruddhi site - Shutdown report – July - 2010 5


#4 100 meg Ω 9.4 Ω /ph

• Mixing nozzles downstream spool in


1st Comp. – All 4 Nos
2nd Comp. –All 4 Nos
3rd Comp. – All 4 Nos.
4th Compt. – All 4 Nos. renewed.

PA drain pipes –--- 1st Compt. – All 4 nos Renewed


2nd Compt. – All 4 nos Renewed
3rd Compt. – All 4 nos Renewed
4th Compt. – All 4 nos Renewed

Cross –------ 1st Compt. – 3 Renewed


2nd Compt. – 2 Renewed
3rd Compt. – 1 & 2 Renewed
4th Compt. – All cross found in good condition

Coal nozzle cap – 1st Compt. – 2 Renewed


2 Comp.
nd
– All caps found in good condition
3 Comp - 2,3 & 4 Renewed
rd

4th Compt. – 2 & 3 Renewed

• PA fan #1 fan bearings inspected found normal grease renewed. PA fan


#1 Discharge damper inspected found gasket and bearing damaged. It was
renewed and then trial run taken found normal.

• PA fan #1 Motor winding and cable Phase to earth & phase to phase I.R Value :
200mΩ, Phase to phase; W.R Value : 0.5 Ω/ph. Bearing both ends lubrication,
feeder side checking work done.

• PA fan #2 Discharge damper inspected found gasket and bearing damaged. It was
renewed and then trial run taken found normal
• PA fan #2 Motor winding and cable Phase to earth & phase to phase I.R Value :
200mΩ, Phase to phase; W.R Value : 0.5 Ω/ph. Bearing both ends lubrication,
feeder Power and control cable terminal inspection work done.

• FD fan motor side power cable melted, so cable-1&2 new glanded, lugged and
terminated, DE and NDE bearing and grease renewed, megger value was checked-
750 meg Ω/phase.
• FD Fan, lignite, Coal, Lime stone VFD panel cleaning and Power and control cable
terminal inspection work done.

Hofincons – Samruddhi site - Shutdown report – July - 2010 6


• ID Fan motor DE and NDE bearing and grease renewed, megger value was
checked-750 meg Ω/phase, VFD panel cleaning and Power and control cable
terminal inspection work done.

• ID fan DE and NDE Bearings and Plummer block renewed, alignment work was
done.

• Furnace, PSH and RSH were cleaned and all air nozzles air flushed.

• BFW Pump #2 DE & NDE side bearing housing, bearing and stuffing box renewed.

• All air boxes cleaned and boxed up.

• Boiler drum was opened and inspected, found normal and boxed up.

• BFW Pump both suction strainers cleaned and fixed back.

• Deaerator was opened inspected, found normal and boxed up.

• Economiser all inspection doors opened and inspected found normal then tube
surfaces cleaned with compressed air, boxed up and then taken on line.

• Both Drum safety valves, HP Heater safety valve, LP Heater safety valve and Line
safety valve were serviced. Then, safety valve floating done the setting detail is
enclosed in Page No : 13

• Oxygen analyzer calibrated.

• BFW pump-1&2 Motor Megger value checked found to be R, Y&B – Infinity, DE


and NDE bearing and grease renewed, air tubes cleaned.

• TPP Auxiliary transformer #1 Break Down value (BDV) was checked.45KV-30SEC;


55KV-1min; 60KV-2min. Primary winding IR Value – 1000 meg Ω , Secondary
winding - 1000 meg Ω. Bushing, cable & Bus inspection, breather silica gel renewed
done.

• Auxiliary transformer #2 Break Down value (BDV) was checked.40KV-1 min;


50KV-1min; 60KV-10sec. Primary winding IR Value – 1000 meg Ω , Secondary
winding - 1000 meg Ω. Bushing, cable & Bus inspection, breather silica gel renewed
done.

• DG auxiliary transformer Break Down value (BDV) was checked - 40KV-1 min;
50KV-1min; 60KV-1min.

Hofincons – Samruddhi site - Shutdown report – July - 2010 7


ACTIVITIES ON ASH HANDLING SYSTEM

• ESP field I & II was cleaned by Compressed air wash.

• Sys-110 hopper was observed with full level of ash, drained and all system hoppers
cleaned.

• Ash collected at APH tube sheets on both passes was cleaned.

• ESP–I field collecting 1st 3rd and 6th hammer found missing was replaced and Shaft
support bearing housing worn out-2 nos and renewed.

• ESP Transformer #1 Break Down value (BDV) was checked - 40KV-1 min; 50KV-
1min; 60KV-10sec. Primary winding IR Value – 500 meg Ω, Secondary winding -
500 meg Ω. Bushing, cable & Bus inspection, breather silica gel renewed done.

• ESP Transformer #2 Break Down value (BDV) was checked - 45KV-1 min; 50KV-
45sec; 60KV-15sec. Primary winding IR Value – 500 meg Ω, Secondary winding -
500 meg Ω. Bushing, cable & Bus inspection, breather silica gel renewed done.

• All rapping motors general maintenance done.

• ESP-1&2 all insulators, field collecting plate and emitting rods inspection work
done.

• AHP MCC panel, ESP MCC panel, ESP controls panel-1&2, P&V Blower MCC panel,
ACDB Panel, APDB MCC panel bus, cable chamber and all feeders maintenance
work done.

• Battery charger panel-1&2, DCDB panel bus, cable chamber and all feeders
maintenance work done.

• Ash hopper all level probes serviced and fixed back.

• AHP all system BFVs & MCVs serviced and fixed back.

• All oil AFRL were renewed.

Hofincons – Samruddhi site - Shutdown report – July - 2010 8


ACTIVITIES ON COAL HANDLING PLANT

• CHP MCC panel bus, cable chamber and all feeders maintenance work done.

• Crusher motor DE and NDE bearing and grease renewed, megger value was
checked-150 meg Ω/phase.
• All hammers of coal crusher turn it.

• Dust extraction bag filter inspection and cleaning work was done.

• Dust extraction bag filter hopper bottom side modification work was done.

• In dust separator line back filter area all SOV’s were calibrated and found ok.

ACTIVITIES ON TURBINE AUXILIARIES

• Turbine lube oil cooler was opened cleaned and taken on line after leak check.

• Lube oil filter elements 6 Nos renewed for “A” Filter and for “B” all elements
cleaned and fixed back.

• All CEP, MCW Pumps and ACW Pumps suction strainers cleaned and fixed back.

• Alternator cooler tubes were checked found OK. Third alternator cooler was
cleaned with rod with brush and water jet with service water.

• In Main condenser front and rear inspection doors opened and found the tube
sheet and tubes are free from deposits, fouling etc. general checked up done and
boxed up.

• I&C Air Compressor-1&2 winding and cable Phase to earth & phase to phase I.R
Value : 100mΩ, Phase to phase; W.R Value : 0.6 Ω/ph. Bearing both ends
lubrication, feeder side Power contactor renewed, power & control cable terminal
inspection work done

• Turbine MCC panel bus, cable chamber and all feeders maintenance work done.

• CEP-1&2, CWP-1,2&3 winding and cable Phase to earth & phase to phase I.R Value :
100mΩ, Phase to phase; W.R Value : 0.4 Ω/ph. Bearing both ends lubrication,
feeder side power & control cable terminal inspection work done

Hofincons – Samruddhi site - Shutdown report – July - 2010 9


• CT Fan-1&2, ACWP-1&2, AOP, EOP, Turning gear, VEM-1&2 Motor side
maintenance work done.

• After the turbine O/H HP Governing actuator operation was checked and
calibrated found normal.

• Turbine ESV limit switches & turning gear engage limit switch serviced and fixed
back.

ACTIVITIES ON RO / DM PLANT & COOLING TOWER

• MGF open backwash was done after soaking the media in Hcl for 30 minutes.

• ACF open backwash carried out.

• Service water tank, RO-I & II rejects sumps were cleaned.

• DM Plant MCC panel, Fire & Raw water MCC panel & 2 nd RO plant MCC panel bus,

cable chamber and all feeders maintenance work done.

• DM Plant HPP-1&2 Power contactor renewed work done.

• CT Fan-1, ACWP-1 Power contactor renewed work done.

• Cooling water sump was cleaned and Fills were cleaned with water jet up to the

reachable distance.

Hofincons – Samruddhi site - Shutdown report – July - 2010 10


OTHER ACTIVITIES

The 12.5 MW Captive power plant along with its auxiliary systems were taken
shutdown on 05-07-2010 at 00.10 Hrs for taking annual maintenance. Apart from the
jobs done by us, we have also coordinated for the works done by other agencies
during the shutdown like :

1. Turbine Major overhauling was carried out by M/s S V Turbo Engg. Works.

2. Cooling tower fan # 1 gear box and base frame renewed by M/s Dynamic
Engineering.

3. Bucket elevator repairing work was carried out by M/s DRK contractors.

4. PCC-1&2, all MCCs, BFWP-1&2, GCP, GRP and TG incomer relays testing was done
by M/s Elsy Tech.

5. All LT ACBs serviced by M/s L&T.

6. TPP to DG-2 DSLC panel commissioning work U/P by M/s Wartsilla.

7. TPP Main/Stand by battery bank load tested by M/s HBL.

During the course of 18 days long shut down activities stringent safety practices
were followed and the shutdown is completed safely with zero incidents reported.

On completion of all planned shut down activities, DP test was done and TPP was
started and synchronized on 23.07.2010 at 20.28 Hrs .

Hofincons – Samruddhi site - Shutdown report – July - 2010 11


SAFETY VALVE SETTINGS REPORT

Drum safety valve 2 Nos. and super heater safety valves were serviced assembled
back to original settings.

• Drum LHS / RHS Safety Valve Model / size : 2” J2 4 HCI

• Super heater Safety Valve Model / size : 1.5” H2 3 HCI

During the safety valve floating / setting on 22.07.2010 the following settings were
done:

Name of the Set Actual lift Resetting


Blow down
safety Valve pressure Pressure Pressure
74.5
Drum LHS 78 kg/cm2 77.4 kg/cm2 3.75%
kg/cm2

76.5
Drum RHS 77 kg/cm2 74.4 kg/cm2 2.75%
kg/cm2

Super heater 69 kg/cm2 69.7 kg/cm2 67.7 kg/cm2 2.86%

At normal operation above valve performance result found satisfactory.

Hofincons – Samruddhi site - Shutdown report – July - 2010 12


TURBINE DISPLACEMENT / SPEED / VIBRATION PROBES INSPECTION &
MEASUREMENT REPORT

TAG NO : ZE – 3400-A
SERVICE : Turbine Axial (thrust) displacement
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

SENSO
GAP BENTLY
DCS R
VOLT NEVEDA PROXIMITOR
MONITOR ST
AGE PANEL STATUS
DISPLAY AT
DISPLAY
US

BEFORE
06.07.1
DISMANTLIN 1.930µ m
0 - 11.85V 0.07 mm OK OK
G /pp

21.07.1 AFTER
0.0µ m/p
0 MOUNTING -10.0V 0.0mm OK OK
p

TAG NO : ZE – 3400-B
SERVICE : Turbine Axial (thrust) displacement
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP
BENTLY DCS
VOL SENSOR
NEVEDA MONITO PROXIMITO
TAG STA
PANEL R R STATUS
E TUS
DISPLAY DISPLAY

BEFORE
06.07.1
DISMANTLI OK.
0 - 11.39V 1.549µ m/pp 0.05mm OK
NG
21.07.1 AFTER
OK
0 MOUNTING -10.0V 0.0µ m/pp 0.0mm OK

Hofincons – Samruddhi site - Shutdown report – July - 2010 13


TAG NO : KQE – 3400
SERVICE : Turbine speed measurement
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
DCS SENSOR PROXIMIT
VOLT NEVEDA
MONITOR STA OR
AGE PANEL
DISPLAY TUS STATUS
DISPLAY

BEFORE
06.07.10
DISMANTLING - 9.7V OK OK
AFTER
06.07.10
MOUNTING -10.0V OK OK

TAG NO : VE – 3400-A
SERVICE : Turbine front shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.920 0.49
DISMANTLING - 10.1 V OK OK
µ m/pp micron

AFTER
21.07.10 0.872 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 14


TAG NO : VE – 3400-B
SERVICE : Turbine front shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.920 0.49
DISMANTLING - 10.02 V OK OK
µ m/pp micron

AFTER
21.07.10 0.960 0.49
MOUNTING -10.0 V OK OK
µ m/pp micron

TAG NO : VE – 3401-A
SERVICE : Turbine rear shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

SENSO
GAP BENTLY
DCS R
VOLT NEVEDA PROXIMIT
MONITOR ST
AGE PANEL OR STATUS
DISPLAY AT
DISPLAY
US

BEFORE
06.07.10 DISMANTLIN 0.630 0.49
- 9.9 V OK OK
G µ m/pp micron

AFTER
21.07.10 0.630 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 15


TAG NO : VE – 3401-B
SERVICE : Turbine rear shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP
BENTLY
VOL DCS SENSOR
NEVEDA PROXIMITOR
TAG MONITOR STA
PANEL STATUS
E DISPLAY TUS
DISPLAY

06.07.1 BEFORE
0.561 0.49
0 DISMANTLING - 9.7 V OK OK
µ m/pp micron

AFTER
21.07.10 0.581 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

TAG NO : VE – 3402-A
SERVICE : Gear box high speed shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.530 0.49
DISMANTLING - 9.16V OK OK
µ m/pp micron

AFTER
21.07.10 0.533 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 16


TAG NO : VE – 3402-B
SERVICE : Gear box high speed shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.580 0.49
DISMANTLING - 9.26 V OK OK
µ m/pp micron

AFTER
21.07.10 0.533 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

TAG NO : VE – 3403-A
SERVICE : Gear box low speed shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.633 0.49
DISMANTLING - 9.9 OK OK
µ m/pp micron

AFTER
21.07.10 0.533 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 17


TAG NO : VE – 3403-B
SERVICE : Gear box low speed shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.588 0.49
DISMANTLING - 10.1 V OK OK
µ m/pp micron

AFTER
21.07.10 0.533 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

TAG NO : VE – 3404-A
SERVICE : Generator front shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.681 0.53
DISMANTLING - 9.8 V OK OK
µ m/pp micron

AFTER
21.07.10 0.630 0.49
MOUNTING -10.01 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 18


Hofincons – Samruddhi site - Shutdown report – July - 2010 19
TAG NO : VE – 3404-B
SERVICE : Generator front shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.681 0.59
DISMANTLING - 9.6 V OK OK
µ m/pp micron

AFTER
21.07.10 0.581 0.49
MOUNTING -10.01 V OK OK
µ m/pp micron

TAG NO : VE – 3405-A
SERVICE : Generator rear shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.630 0.58
DISMANTLING - 9.6 V OK OK
µ m/pp micron

AFTER
21.07.10 0.632 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 20


TAG NO : VE – 3405-B
SERVICE : Generator rear shaft vibration
MAKE : BENTLY NEVADA
PROBE CABLE LENGTH : 5 METER
PROXIMITOR MODEL : 3300 XL 5/8 MM
P/N : 330180-50-00
OUTPUT : 7.87 V/mm (200 mV / mil)

GAP BENTLY
SENSOR
VOL NEVEDA DCS
ST PROXIMITOR
TAG PANEL MONITOR
AT STATUS
E DISPLA DISPLAY
US
Y

BEFORE
06.07.10 0.680 0.49
DISMANTLING - 9.4 V OK OK
µ m/pp micron

AFTER
21.07.10 0.581 0.49
MOUNTING -10.00 V OK OK
µ m/pp micron

Hofincons – Samruddhi site - Shutdown report – July - 2010 21

You might also like