57 Zawtika Float-Over

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3
At a glance
Powered by AI
ALE provided ballasting services to lower the topside of an offshore structure onto a preinstalled jacket during the Zawtika project in Myanmar.

ALE was responsible for the rapid ballasting of the barge during the critical float-over installation stage to transfer the load from the barge to the jacket legs. This included ballast engineering, procedures, and installation supervision.

ALE provided pumps, power packs, control valves, pipework and an in-house ballast monitoring and control system. The equipment included 24 x 10PS de-ballast pumps.

Zawtika - Topside Mating

Floatover Installation Ballasting

Data project sheet


Client: Saipem Singapore

Project location: PT Worldwide—Batam, Offshore - Gulf of Moattama, Myanmar

Equipment: 30 x 24PS Ballast Pumps 23 x 10PS De-Ballast Pumps & 18 x 325 HPU’s

Weights: 14885 Metric Tonne

Abnormal Load Engineering Limited, Sotherby Road, Middlesbrough, TS3 8BS, United Kingdom

Tel:+44 (0) 1642 292 299 Fax:+44 (0) 1642 242 004 Web: www.ale-heavylift.com

Registered Office: New Road, Hixon, Staffordshire, ST18 0PE, United Kingdom
ALE 57
Company Registration No. 1708850 VAT No: 765329995
The Zawtika Project is a gas field development project located in the Gulf of Moattama, Myanmar.
The development area covers Block M9 and small portion of Block M11, owned by Myanmar Oil & Gas
Enterprise (MOGE). The field lies approximately 300 km south of Yangon and 290 km west of Tavoy on the
Myanmar coast with an average water depth if approximately 135-160 meters, (LAT).

Once again, Saipem approached


and contracted ALE to perform the
Float-Over Installation rapid
ballasting during the Zawtika
installation. This was awarded
following the similar successful Bien
Dong Project Float-Over 2012.

Currently ALE own one of the


largest fleet of Ballast pumps in the
world - with a total pumping capacity
of over 160,000 Cu.M/Hr.

Zawtika Field Development

ALE’s scope of work was to


provide the “Rapid Ballasting” of
the barge at the critical stage of
the “Float-Over Installation” for
load transfer from the barge to the
preinstalled jacket legs.

ALE performed all of the Rapid


Ballast engineering associated
with the float-over installation from
Ballast Calculations, to
Procedures. ALE’s scope of work
also included Float-Over
installation supervision. ALE also
provided all necessary equipment
and control systems associated to
the RBS. Major equipment
included pumps, power packs, Zawtika ZPQ under tow
directional control valves,
pipework and ‘In-House’ Ballast/
Draft Monitoring and Control
system.

Topside barge being manoeuvred into position between the ZPQ jacket legs
The barge used was the Saipem S45 with key dimensions, 180meters long
x 42 meters. The barge was towed to the offshore site from Singapore
following the topside load out. The barge was manoeuvred very carefully
between the jacket legs lining up the topside before the ballasting operation to lower the topside onto the
jacket commenced.

Client: Saipem Singapore Location: PT Worldwide—Batam


Offshore - Gulf of Moattama,
Project: Zawtika Ballasting Myanmar
Market Sector: Offshore
ALE 57
ALE’s On Site installation crew
accessed the barge onshore at PT
Worldwide Site in Batam, Indonesia to
work alongside the Saipem yard team to
install the External Barge Ballast
System, (EBBS).

Following procedures, 24PS pumps


were lowered down the 30 overboard
risers pipes, individual tank transducers
were placed in the corresponding draft
tubes and all hydraulic systems were
commissioned. Following a function test
and completion certificate the system
was operational within 2 days.

Drawing showing the ballast pipe and pump layout on the barge deck

The ballast system and layout is bespoke and designed for each
individual project, in particular to this job the ballast system had to
be designed to the S45 barge layout and had to meet site
requirements we provided enough ballasting to reduce the barges
draft by 1m in 10 minutes that's 62’000 Cu.M/hour.
Once the barge approached the final
destination , the ALE Operation Team were
remobilised to re-commission and function test
the EBBS. The barge was manoeuvred between
the Zawtika jacket legs and once the topside
slots were aligned the ballasting system was
activated in ALE’s Central Control Room.

Barge and loadout support frame being lowered and removed Topside in Final Position with Barge removed.

After approximately 1 hours of ballasting the topside was transferred from the barge onto its
permanent supports. The barge was then removed from under the topside and the operation was
successfully completed.

Client: Saipem Singapore Location: PT Worldwide—Batam


Offshore - Gulf of Moattama,
Project: Zawtika Ballasting Myanmar
Market Sector: Offshore
ALE 57

You might also like