57 Zawtika Float-Over
57 Zawtika Float-Over
57 Zawtika Float-Over
Equipment: 30 x 24PS Ballast Pumps 23 x 10PS De-Ballast Pumps & 18 x 325 HPU’s
Abnormal Load Engineering Limited, Sotherby Road, Middlesbrough, TS3 8BS, United Kingdom
Tel:+44 (0) 1642 292 299 Fax:+44 (0) 1642 242 004 Web: www.ale-heavylift.com
Registered Office: New Road, Hixon, Staffordshire, ST18 0PE, United Kingdom
ALE 57
Company Registration No. 1708850 VAT No: 765329995
The Zawtika Project is a gas field development project located in the Gulf of Moattama, Myanmar.
The development area covers Block M9 and small portion of Block M11, owned by Myanmar Oil & Gas
Enterprise (MOGE). The field lies approximately 300 km south of Yangon and 290 km west of Tavoy on the
Myanmar coast with an average water depth if approximately 135-160 meters, (LAT).
Topside barge being manoeuvred into position between the ZPQ jacket legs
The barge used was the Saipem S45 with key dimensions, 180meters long
x 42 meters. The barge was towed to the offshore site from Singapore
following the topside load out. The barge was manoeuvred very carefully
between the jacket legs lining up the topside before the ballasting operation to lower the topside onto the
jacket commenced.
Drawing showing the ballast pipe and pump layout on the barge deck
The ballast system and layout is bespoke and designed for each
individual project, in particular to this job the ballast system had to
be designed to the S45 barge layout and had to meet site
requirements we provided enough ballasting to reduce the barges
draft by 1m in 10 minutes that's 62’000 Cu.M/hour.
Once the barge approached the final
destination , the ALE Operation Team were
remobilised to re-commission and function test
the EBBS. The barge was manoeuvred between
the Zawtika jacket legs and once the topside
slots were aligned the ballasting system was
activated in ALE’s Central Control Room.
Barge and loadout support frame being lowered and removed Topside in Final Position with Barge removed.
After approximately 1 hours of ballasting the topside was transferred from the barge onto its
permanent supports. The barge was then removed from under the topside and the operation was
successfully completed.