SL-ELT-PR-WPS1-4105-C1-S1 Topside Load Out Procedure
SL-ELT-PR-WPS1-4105-C1-S1 Topside Load Out Procedure
SL-ELT-PR-WPS1-4105-C1-S1 Topside Load Out Procedure
St To s i de Loa d Ou t P
rocedu re
AREA DISCIP L. D SC SE REV.
O OP E Q.
C.
AFC
A roved f or Cou s rru
crlon
.. IRANIAN OFFSHORE OIL COMPANY
(IOOC}
� ENGINEERING & DESIGN DEPARTMENT
Approved For Construction
Contra ctor
--- -�
Si gna tu re: S'�gmi tti t. s i�
)f\ �/\·,J
'. ll-�' ' V . DATE:
....
\. _.,_-,:::::;::.
CO\TRACT NlJ!V(lfER:FG-2-91-45�
C1 12- Dec- 2019 Approved for Construction A.HK A.HK A.HK O.MO M.HO
co 09- Nov- 2019 Issued For Approval A.HK A.HK A.HK O.MO M.HO
TABLE OF CONTENTS
1 INTRODUCTION....................................................................................................................
5
2 DEFINITIONS
........................................................................................................................ 5
3 SCOPE OF WORK
3.1
................................................................................................................6
RULES AND REGULATIONS .......................................................................................................................... 6
4 ORGANIZATION
................................................................................................................... 6
5 LIST OF
EQUIPMENTS......................................................................................................... 7
6 PRE-REQUISISITES AND INITIAL CONDITIONS................................................................ 7
7 OPERATIONAL PROCEDURE-PRE LOAD OUT-BARGE ................................................... 9
8 Operational procedure – load out..................................................................................... 10
8.1 METHOD.........................................................................................................................................................
10
8.2 OPERATIONS.................................................................................................................................................
11
9 DESIGN AND CALCULATION FOR MOORING................................................................. 11
9.1 overall model .................................................................................................................................................
11
9.1.1 Environmental condition ...................................................................................................................... 12
9.1.2 TOPSIDE AND BARGE MODEL............................................................................................................ 14
9.2 MOORING ANALYSES .................................................................................................................................. 16
9.2.1 SCOPE OF THE ANALYSES ................................................................................................................. 16
9.2.2 MOORING LINES LOAD LIMITATIONS................................................................................................ 17
9.2.3 DIFFERENT POSITIONS FOR MOORING ANALYSES ....................................................................... 17
9.2.4 POSITION 1 ............................................................................................................................................ 17
9.2.5 POSITION 2-1 ......................................................................................................................................... 19
9.2.6 POSITION 2-2 ......................................................................................................................................... 20
9.2.7 DAMAGE CONDITION (TRANSIENT ANALYSIS)................................................................................ 22
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDICES
1 INTRODUCTION
This project involves work in two locations; new facilities in satellite wellhead platform, S1, over the Salman
reservoir and additions to the existing Salman Complex. The modifications to Salman Complex facilities are
intended to increase the predictability of the oil wells by increasing gas lift capabilities in S1 facilities.
Salman Oil and Gas Field is an active oil producing complex in the Persian Gulf, in Iranian waters some 144
km south of Lavan Island. This field straddles the Iran – Abu Dhabi border with approximately two-thirds of
the producing structure lying in Iranian waters.
The existing offshore facilities at the Salman oil and gas field have been producing since 1968. The extracted
crude oil is processed and exported via a subsea pipeline to onshore facilities at Lavan Island.
2 DEFINITIONS
PROJECT NAME Transportation, Engineering, Procurement,
Installation of S1 Topside for Salman Field
CLIENT Iranian Off-shore Oil Company (IOOC)
EPCIC CONTRACTOR Asfalt Tous Company (ATC)
INSTALLATION SUB-CONTRACTOR Sanaye Daryafan Qeshm (SADAF)
INSTALLATION ENGINEERING SUB- Farazan Saze Darya (FARDA)
CONTRACTOR
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
3 SCOPE OF WORK
This document contains procedure for S1 Topside load out operation and is submitted for approval. The
procedure contained within this document has been designed to ensure the safe and efficient transfer of S1
Topside from its assembly area to the cargo barge (LB90).
• S1 Topside - Leg Distance: 22.0 m Long, 11.5 m Wide, weight with 3% contingency= 1046 MT
Load out operations will be executed in a manner that meets their approval. The principle and mode of lifting
is similar to operation installation.
Detailed analyses of the structure in various positions throughout the operation have been performed. (Lift
Analysis)
Ballasting and stability calculations have been performed co-relating barge type, structure, movement,
ballasting effects (see appendix G)
The equipments and methods described here-in have been developed over many years of experiences of
performing load out operations.
4 ORGANIZATION
1. The load-out operation will be under the control of the installation superintendent. A Designer capable of
reworking ballasting and strength calculations will be available, close at hand.
2. The barge master is in charge of anchor running and mooring operation as instructed by the field
engineer.
3. Tank soundings, tide level and barge draft will be taken by Plant personnel and data will be reported back
to the ballasting Engineer.
4. In the case of accident injury or absence of a senior member of the team, responsibilities will be
redistributed as listed below.
Absent Deputy
5. In case of emergency the senior personnel will continue with their assigned responsibilities.
6. The list of the barge will be monitored by the surveyors and load-out Engineer.
7. There will be a Safety Officer on the site for the duration of the operation, to ensure that only the
authorized personnel are in the vicinity of the barge and that adequate personnel safety precaution are being
taken.
8. 24 Hours prior to the load-out there will be a meeting of all senior personnel, to ensure all activities are going
to plan, and establish any contingency action which may be necessary.
9. Ambulance and medic shall be at place during operation.
5 LIST OF EQUIPMENTS
1. Safety Equipment
2. Skid Beam of Yard and Barge
3. Barge LB90
4. SADAF3000 Crane Barge
5. 1 No. Tug for standby and 1 no. AHT for anchor running)
6. Steel wire for mooring system
7. Cotton wire for mooring system
8. A Lift-truck for pull the LB90
9. ATC Yard bollards for mooring system
10. Shackle for mooring
11. Rigging for Topside lifting
12. Grillage on the barge
13. Sadaf3000 anchors for mooring
14. 3 pumps with 100 m3/hr flow-rate
2. The weight and C.O.G location is based on Weight Control report and lift analysis document No.SL-ELT-
AN-WPS1-4114-C0.
3. The skid beam on barge will be welded and inspected before the load out and grillage will be welded and
inspected on barge skid beam.
4. The S1 Topside will be lifted using SADAF3000 Crane Barge from ATC Yard to LB90 Barge. According to
lift analysis document No.SL-ELT-AN-WPS1-4114-C0, the weight of S1 Topside with 3% Contingency is
1046 MT (excluding DAF Factor), and according to SADAF3000 Load chart the Capacity of Jib Hook is
1291MT for harbour condition.
5. The water depth at the quayside is 6.00 m (LAT) for S1 Topside load out location in the yard. The quay
wall details and water depth available at the location are illustrated in the attached sketch (see appendix C).
6. The tidal range in ATC is on average 1.8m. Tide cycles vary, but are approximately 5 hours ebb and flood
with 1 hour slack water, as the tide turn. Mooring arrangements have proven to be more than adequate to
maintain a barge in position, perpendicular to the quay during a full 24 hours cycle of tides. See drawing
for mooring pattern of cargo barge during load out. (see appendix D)
7. Portable diesel pump will be installed on the barge and ready to operate. The ballasting for load out must
be done as appendix E.
8. During load out the equipment will be used for the purpose which they were designed. All equipment will
have been properly maintained and serviced regularly. There will be plant mechanics on standby during the
load out operations.
9. Imminent and forecast weather condition will be examined prior to load out. The load out operation will be
carried out under the following environmental condition:
Wind 20 knots
Current 4 knots
Wave (Hmax) 0.5 m
10. Sea fastening items will be fabricated, and parked on the barge in a close proximity to their design
locations for ease of handling a fitting when the structures are in their final position. The barge
arrangement has been shown in Appendix G.
11. Supply of 3 No. ballast pumps for ballasting operations during load out 2 pumps with nominal flow rate equal
100 m3/h for ballasting operation and 1 pump with nominal flow rate equal 100 m3/h for emergency cases.
12. Gas free check on enclosed tank shall be performed prior to hot work operation during the load out.
13. Before load out 16 No. dog plates shall be cut from Topside leg and skidshoes leg for each leg
14. Throughout the operation the following subjects will be monitored continuously by competent, experienced
personnel.
Load transfer and movement progress will be monitored continuously.
All personnel will be experienced in this type of operation, and know how to monitor and maintain a
feel for the operation.
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
15. Key personnel will be in continuous radio contact throughout the operation 6 No. Radios.
16. The load out operation shall not commence until written approval from COMPANY and appointed Marine
Warranty Surveyor has been obtained.
5. A week prior load out operation 90% of plates that connected to skid shoes and Topside legs shall be cut.
6. Skid Beams and grillages will be positioned on the barge as required.
7. The barge is pre-ballasted to the calculated initial condition for load out. The actual ballast quantities and
tanks designated for pre ballast are defined in appendix E.
8. There is a pre- load out preparations check-list included here below for information. This will also appear
in the load – out operations document with other specific details nearer the time of the operation.
9. 1 hour prior load out operation remaining plates that connected to skid shoes and Topside legs shall be
cut.
Safety
safety check list reviewed
pre-operation on site tool box
Reactive arrangement (Ambulance, medic, firefighters equipment, …)
PPE for all personnel involved
Skid beam and grillage fixation/position
grillage cleaning
Under water survey
Mooring system installation
Barges
Open hatches
Checking of ballasting as per calculation
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
Necessary personal protection equipment such as safety shoes, Helmets and Gloves provided to all
employees on site.
A gangway will be installed to access on the barge from the yard if required.
using tugger winches. Then the cable will be tightened on the bollard according to Appendix D.
They will be assisted by a tug boat that will remain in attendance during the complete operation.
The Grillages will be thoroughly cleared and all burrs ground smooth prior to commencement of the
load out operation.
The lifting operation of the Topside onto the barge will be a slow precise operation.
8.2 OPERATIONS
Receive, inspect and clean barge.
Confirm the current weather conditions are favorable and that an adequate weather window is
available prior to commencing load out.
Clean the grillages on barge.
Confirm that the altitude and barges position is correct.
Warranty surveyor should issue the load out certificate before the operation.
Separate Topside from other construction supports.
Hook up equipment related to load out.
Remove hatches and checked the pre-load out ballasting. Connect the mooring system to the
crane barge as per Appendix D.
Connect Topside lift rigging to SADAF3000 Tackles.
Start lifting operation.
Lift the Topside 3.0m upper than skidshoes, and move the SADAF3000 with it’s mooring system to
opposite of quaywall side about 45m.
Loos the mooring wire No.S6 for moving the LB90 barge.
Move the LB90 Barge alongside the quaywall between SADAF3000 and quaywall in it’s position.
Move the SADAF3000 crane barge to near the LB90 barge and put the Topside in its position.
Install one seafastening of each leg and disconnect Topside rigging from crane barge.
Ballast the barge to transportation draft with even keel.
270 degree
90 degree
Heading=0
Hmax = 0.0 m,
Tz : 0
Heading=45
Hmax = 0.5 m,
Heading=90
Hmax = 0.5 m,
Heading=135
Hmax = 0.5 m,
Heading=180
Hmax = 0.5 m,
Heading=225
Hmax = 0.5 m,
Current : 2 knots (1.0 m/s) because of opposite direction of river. Current is considered in this
direction just for tidal effect and for conservative.
Heading=270
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
Hmax = 0.5 m,
Current : 1 knot (0.5 m/s) – because of opposite direction of river. Current is considered in this
direction just for tidal effect and for conservative.
Heading=315
Hmax = 0.5 m,
Current : 2 knots (1.0 m/s) because of opposite direction of river. Current is considered in this
direction just for tidal effect and for conservative.
The software used to perform these calculations is the MOSES system (version 7.01.047) developed by
ULTRAMARINE, Inc. of Houston, USA.
Vessel origin is at the bow with the X-axis pointing aft-ward coinciding with keel, the Z-axis upwards and the
Y-axis pointing to the starboard side.
SADAF3000 BARGE
Analyses are performed for sea headings from different directions. For each heading a detailed mooring analysis
is carried out and the mooring lay-out is studied to meet the related criteria.
In order to mooring system the results of the analysis are compared with the allowable (limiting) values of the
tensions on the cables. Besides, the barges movements at the operating positions are the controlled since
keeping the convenient clearance to the Topside is one of the most important aspects of the analyses.
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
The Flipper Delta type 5.0 to 7.0 ton anchor is recommended for SADAF3000. According to API-RP2SK, for a
sand seabed, these type of anchor have 79 to 143 ton grip capacity.
Position 1- SADAF3000 is near the quay wall and lift the Topside.
Position 2- SADAF3000 move opposite side of quay wall for putting Topside on LB90 Barge.
Position 2-1: loos the mooring wire S6 and disconnect mooring lines S7 and S8 for moving LB90
Barge.
Position 2-2: LB90 is located in it’s position for putting the Topside
Damage condition (transient analysis): in this case wire with maximum mooring load is broken.
9.2.4 POSITION 1
Figure 1 and Figure 2 show the mooring system lay-out considered for position 1.
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
S3
S4
S7
S2
S8
S6
S5
S1
The results show that none of the mooring lines reach 60 percent of the minimum breaking load. The
maximum tension is 352.2 KN for S1 line which the allowable tension is 824 KN..
Time histories of all mooring line forces and motions of the barge are presented in APPENDIX H.
S3
S4
S2
S6
S5
S1
The results show that none of the mooring lines reach 60 percent of the minimum breaking load. The
maximum tension is 492.5 KN for S5 line which the allowable tension is 824 KN..
Time histories of all mooring line forces and motions of the barge are presented in APPENDIX H.
S3
S4
S7
S2
S8
S6
S5
S1
Table 6 which implies that all lines at all sea state headings are tensioned below the limitations mentioned in
section 9.2.2.
The results show that none of the mooring lines reach 60 percent of the minimum breaking load. The
maximum tension is 452.3 KN for S5 line which the allowable tension is 824 KN..
Time histories of all mooring line forces and motions of the barge are presented in APPENDIX H.
The results show that none of the mooring lines reach 95 percent of the minimum breaking load. The
maximum tension is 829 KN for S1 line which the allowable tension is 1304 KN..
Time histories of all mooring line forces and motions of the barge are presented in APPENDIX H.
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX A
ORGANIZATION CHART
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
TO BE SUBMITTED LATER
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX B
TOPSIDE WEIGHT AND C.O.G
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
1 GENERAL ARRANGEMENT
S1 platform is a Four (4) leg jacket with no batter. The jacket Support the following
appurtenances:
Two J tubes
The primary horizontal elevations for the jacket framing are as follows:
EL (-) 21.00 meters; bottom bracing level
n
Description Design Data
No. of Legs 4
Jacket dimension at Working Point 11.5 x 22 (mxm)
Jacket elevation at Working Point El + 7.500 (LAT)
Height of Jacket 30.60
Number of Piles 4 (DI=46 inches)
Risers 1x12” DIA & 2X6” DIA
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
J-tube 2
Caisson 30”
Conductor 6 x 30” DIA
Boat Landing 1
Barge Bumper 5
P
Lowe Part of
Skid Shoe
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
a
Jacks s
locations
COG
G
Y
5.98 m
COG
X 11.50 m
16.98
4.90 m
22.0 m
Note: all installation analysis and documents shall be prepared based on weighing report
results.
APPENDIX C
SKETCH OF YARD FOR WATER DEPTH
0 0 0 0 0 0 0
0
0 0 0 0 0 0 I
0 0 0 0 0 0
0
0
r 0
0
+3.soo
0
I OJ
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX D
MOORING PATTERN
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX E
BALLASTING FOR LB90 BARGE
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
Ballasting for load out operation is not important because of lift method, therefore ballasting is
considered as pre-ballast according to below table:
+++ B U O Y A N C Y A N D W E I G H T F O R L B 9 0 +++
===============================================================
Process is DEFAULT: Units Are Degrees, Meters, and M-Tons Unless Specified
Ballasting Tanks
Percentage
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX F
GRILLAGE DESIGN AND SKID BEAM CHECK
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
Please refer to document S1 Topside Trans. & Seafastening Analysis & Report
No. SL-ELT-AN-WPS1-4117
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
APPENDIX G
BARGE ARRANGEMENT
B A
COG
COR
B A
C OG
COG
STERN
BOW
SADAF
SADAF Co.
APPENDIX H
MOORING ANALYSIS RESULT
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
POSITION 1
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
MAG:S1
MAG:S2
MAG:S3
77.
MAG:S4
6
MAG:S5
MAG:S6
69.
MAG:S7
2
MAG:S8
60.
8
52.
4
MORRING FORCE (KN)
44
35.
6
27.
2
18.
8
10.
4
2
1
X:SADAF300
Y:SADAF300
0.23
Z:SADAF300
0.1
RX:SADAF300
-
-
RY:SADAF300
RZ:SADAF300
0.66
1.2
-
-
1.09
2.3
-
-
*10**-3
1.52
3.4
-
-
DISPLACEMENT (m)
(DEG.)
1.95
4.5
-
-
6.7ROTATION
2.38
5.6
-
-
2.81
-
-
3.24
7.8
-
-
3.67
8.9
-
-
-10
4.1
-
MAG:S1
MAG:S2
243
MAG:S3
MAG:S4
MAG:S5
MAG:S6
216
MAG:S7
MAG:S8
189
162
MORRING FORCE (KN)
135
108
81
54
27
0
0.1
0.4
-
X:SADAF300
Y:SADAF300
0.77
Z:SADAF300
0.0
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
1.14
0.0
2
-
0.02
1.51
-
-
0.06
1.88
-
-
DISPLACEMENT (m)
0.14 (DEG.)
2.25
0.1
-
-
0.18ROTATION
2.62
-
-
2.99
-
-
0.22
3.36
-
-
0.26
3.73
-
-
4.1
0.3
-
MAG:S1
MAG:S2
324
MAG:S3
MAG:S4
MAG:S5
MAG:S6
288
MAG:S7
MAG:S8
252
216
MORRING FORCE (KN)
180
144
108
72
36
0
0.5
0.4
-
X:SADAF300
Y:SADAF300
0.77
Z:SADAF300
0.3
RX:SADAF300
7
-
RY:SADAF300
RZ:SADAF300
1.14
0.2
4
-
1.51
0.1
1
-
0.02
1.88
-
-
DISPLACEMENT (m)
0.28 (DEG.)
0.15
2.25
-
-
0.41ROTATION
2.62
-
-
2.99
-
-
0.54
3.36
-
-
0.67
3.73
-
-
4.1
0.8
-
MAG:S1
MAG:S2
243
MAG:S3
MAG:S4
MAG:S5
MAG:S6
216
MAG:S7
MAG:S8
189
162
MORRING FORCE (KN)
135
108
81
54
27
0
0.2
0.2
-
X:SADAF300
Y:SADAF300
0.59
Z:SADAF300
0.1
RX:SADAF300
5
-
RY:SADAF300
RZ:SADAF300
0.98
0.1
-
1.37
0.0
5
-
1.76
0
-
DISPLACEMENT (m)
(DEG.)
0.05
2.15
-
-
0.15ROTATION
2.54
0.1
-
-
2.93
-
-
3.32
0.2
-
-
0.25
3.71
-
-
4.1
0.3
-
MAG:S1
MAG:S2
MAG:S3
99
MAG:S4
MAG:S5
MAG:S6
88
MAG:S7
MAG:S8
77
66
MORRING FORCE (KN)
55
44
33
22
11
0
100
X:SADAF300
Y:SADAF300
0.23
Z:SADAF300
80
RX:SADAF300
-
RY:SADAF300
RZ:SADAF300
0.66
60
-
1.09
40
-
20
-
DISPLACEMENT (m)
1.95
0
-
2.38
-20
-
2.81
-40
-
3.24
-60
-
-80
3.67
-
4.1
100
-
MAG:S1
MAG:S2
126
MAG:S3
MAG:S4
MAG:S5
MAG:S6
112
MAG:S7
MAG:S8
98
84
MORRING FORCE (KN)
70
56
42
28
14
0
0.2
X:SADAF300
Y:SADAF300
0.05
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.1
0.5
2
-
0.95
0.0
8
-
0.0
1.4
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.85
0
-
0.08ROTATION
2.3
-
-
2.75
-
-
0.12
3.2
-
-
0.16
3.65
-
-
4.1
0.2
-
MAG:S1
MAG:S2
117
MAG:S3
MAG:S4
MAG:S5
MAG:S6
104
MAG:S7
MAG:S8
91
78
MORRING FORCE (KN)
65
52
39
26
13
0
0.7
X:SADAF300
Y:SADAF300
0.05
Z:SADAF300
0.5
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.4
0.5
2
-
0.95
0.2
8
-
0.1
1.4
4
-
DISPLACEMENT (m)
0.14 (DEG.)
1.85
0
-
0.28ROTATION
2.3
-
-
2.75
-
-
0.42
3.2
-
-
0.56
3.65
-
-
4.1
0.7
-
MAG:S1
MAG:S2
126
MAG:S3
MAG:S4
MAG:S5
MAG:S6
112
MAG:S7
MAG:S8
98
84
MORRING FORCE (KN)
70
56
42
28
14
0
0.2
X:SADAF300
Y:SADAF300
0.05
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.1
0.5
2
-
0.95
0.0
8
-
0.0
1.4
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.85
0
-
0.08ROTATION
2.3
-
-
2.75
-
-
0.12
3.2
-
-
0.16
3.65
-
-
4.1
0.2
-
POSITION 2-1
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
MAG:S1
MAG:S2
189
MAG:S3
MAG:S4
MAG:S5
MAG:S6
168
147
126
MORRING FORCE (KN)
105
84
63
42
21
0
10
X:SADAF300
Y:SADAF300
0.32
Z:SADAF300
7
RX:SADAF300
-
RY:SADAF300
RZ:SADAF300
0.74
4
-
1.16
1
-
-2
-
DISPLACEMENT (m)
-5
-2
2.42
-8
-
2.84
-11
-
3.26
-14
-
3.68
-17
-
-20
4.1
-
MAG:S1
MAG:S2
432
MAG:S3
MAG:S4
MAG:S5
MAG:S6
384
336
288
MORRING FORCE (KN)
240
192
144
96
48
0
0.1
0.2
-
X:SADAF300
Y:SADAF300
0.59
Z:SADAF300
0.0
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.98
0.0
2
-
0.02
1.37
-
-
0.06
1.76
-
-
DISPLACEMENT (m)
0.14 (DEG.)
2.15
0.1
-
-
0.18ROTATION
2.54
-
-
2.93
-
-
0.22
3.32
-
-
0.26
3.71
-
-
4.1
0.3
-
MAG:S1
MAG:S2
450
MAG:S3
MAG:S4
MAG:S5
MAG:S6
400
350
300
MORRING FORCE (KN)
250
200
150
100
50
0
0.5
0.3
-
X:SADAF300
Y:SADAF300
0.68
Z:SADAF300
0.3
RX:SADAF300
7
-
RY:SADAF300
RZ:SADAF300
1.06
0.2
4
-
1.44
0.1
1
-
0.02
1.82
-
-
DISPLACEMENT (m)
0.28 (DEG.)
0.15
2.2
-
-
0.41ROTATION
2.58
-
-
2.96
-
-
0.54
3.34
-
-
0.67
3.72
-
-
4.1
0.8
-
MAG:S1
MAG:S2
306
MAG:S3
MAG:S4
MAG:S5
MAG:S6
272
238
204
MORRING FORCE (KN)
170
136
102
68
34
0
0.2
0.1
-
X:SADAF300
Y:SADAF300
Z:SADAF300
0.1
0.5
RX:SADAF300
5
-
RY:SADAF300
RZ:SADAF300
0.1
0.9
-
0.0
1.3
5
-
1.7
0
-
DISPLACEMENT (m)
(DEG.)
0.05
2.1
-
-
0.15ROTATION
0.1
2.5
-
-
2.9
-
-
3.3
0.2
-
-
0.25
3.7
-
-
4.1
0.3
-
MAG:S1
MAG:S2
198
MAG:S3
MAG:S4
MAG:S5
MAG:S6
176
154
132
MORRING FORCE (KN)
110
88
66
44
22
0
100
X:SADAF300
Y:SADAF300
0.32
Z:SADAF300
80
RX:SADAF300
-
RY:SADAF300
RZ:SADAF300
0.74
60
-
1.16
40
-
20
-
DISPLACEMENT (m)
-2
0
2.42
-20
-
2.84
-40
-
3.26
-60
-
-80
3.68
-
4.1
100
-
MAG:S1
MAG:S2
144
MAG:S3
MAG:S4
MAG:S5
MAG:S6
128
112
96
MORRING FORCE (KN)
80
64
48
32
16
0
0.2
X:SADAF300
Y:SADAF300
0.14
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.58
0.1
2
-
1.02
0.0
8
-
1.46
0.0
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.9
0
-
0.08ROTATION
2.34
-
-
2.78
-
-
0.12
3.22
-
-
0.16
3.66
-
-
4.1
0.2
-
MAG:S1
MAG:S2
171
MAG:S3
MAG:S4
MAG:S5
MAG:S6
114
95
57
19
0
0.7
X:SADAF300
Y:SADAF300
0.14
Z:SADAF300
0.5
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.58
0.4
2
-
1.02
0.2
8
-
1.46
0.1
4
-
DISPLACEMENT (m)
0.14 (DEG.)
1.9
0
-
0.28ROTATION
2.34
-
-
2.78
-
-
0.42
3.22
-
-
0.56
3.66
-
-
4.1
0.7
-
MAG:S1
MAG:S2
198
MAG:S3
MAG:S4
MAG:S5
MAG:S6
176
154
132
MORRING FORCE (KN)
110
88
66
44
22
0
0.2
X:SADAF300
Y:SADAF300
0.23
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.66
0.1
2
-
1.09
0.0
8
-
1.52
0.0
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.95
0
-
0.08ROTATION
2.38
-
-
2.81
-
-
0.12
3.24
-
-
0.16
3.67
-
-
4.1
0.2
-
POSITION 2-2
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
MAG:S1
MAG:S2
MAG:S3
99
MAG:S4
MAG:S5
MAG:S6
88
MAG:S7
MAG:S8
77
66
MORRING FORCE (KN)
55
44
33
22
11
0
10
X:SADAF300
Y:SADAF300
0.23
Z:SADAF300
7
RX:SADAF300
-
RY:SADAF300
RZ:SADAF300
0.66
4
-
1.09
1
-
-2
-
DISPLACEMENT (m)
1.95
-5
-
2.38
-8
-
2.81
-11
-
3.24
-14
-
3.67
-17
-
-20
4.1
-
MAG:S1
MAG:S2
243
MAG:S3
MAG:S4
MAG:S5
MAG:S6
216
MAG:S7
MAG:S8
189
162
MORRING FORCE (KN)
135
108
81
54
27
0
0.1
0.2
-
X:SADAF300
Y:SADAF300
0.59
Z:SADAF300
0.0
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.98
0.0
2
-
0.02
1.37
-
-
0.06
1.76
-
-
DISPLACEMENT (m)
0.14 (DEG.)
2.15
0.1
-
-
0.18ROTATION
2.54
-
-
2.93
-
-
0.22
3.32
-
-
0.26
3.71
-
-
4.1
0.3
-
MAG:S1
MAG:S2
414
MAG:S3
MAG:S4
MAG:S5
MAG:S6
368
MAG:S7
MAG:S8
322
276
MORRING FORCE (KN)
230
184
138
92
46
0
0.5
0.2
-
X:SADAF300
Y:SADAF300
0.59
Z:SADAF300
0.3
RX:SADAF300
7
-
RY:SADAF300
RZ:SADAF300
0.98
0.2
4
-
1.37
0.1
1
-
0.02
1.76
-
-
DISPLACEMENT (m)
0.28 (DEG.)
0.15
2.15
-
-
0.41ROTATION
2.54
-
-
2.93
-
-
0.54
3.32
-
-
0.67
3.71
-
-
4.1
0.8
-
MAG:S1
MAG:S2
288
MAG:S3
MAG:S4
MAG:S5
MAG:S6
256
MAG:S7
MAG:S8
224
192
MORRING FORCE (KN)
160
128
96
64
32
0
0.2
0.1
-
X:SADAF300
Y:SADAF300
Z:SADAF300
0.1
0.5
RX:SADAF300
5
-
RY:SADAF300
RZ:SADAF300
0.1
0.9
-
0.0
1.3
5
-
1.7
0
-
DISPLACEMENT (m)
(DEG.)
0.05
2.1
-
-
0.15ROTATION
0.1
2.5
-
-
2.9
-
-
3.3
0.2
-
-
0.25
3.7
-
-
4.1
0.3
-
MAG:S1
MAG:S2
189
MAG:S3
MAG:S4
MAG:S5
MAG:S6
168
MAG:S7
MAG:S8
147
126
MORRING FORCE (KN)
105
84
63
42
21
0
100
X:SADAF300
Y:SADAF300
0.23
Z:SADAF300
80
RX:SADAF300
-
RY:SADAF300
RZ:SADAF300
0.66
60
-
1.09
40
-
20
-
DISPLACEMENT (m)
1.95
0
-
2.38
-20
-
2.81
-40
-
3.24
-60
-
-80
3.67
-
4.1
100
-
MAG:S1
MAG:S2
144
MAG:S3
MAG:S4
MAG:S5
MAG:S6
128
MAG:S7
MAG:S8
112
96
MORRING FORCE (KN)
80
64
48
32
16
0
0.2
X:SADAF300
Y:SADAF300
0.14
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.58
0.1
2
-
1.02
0.0
8
-
1.46
0.0
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.9
0
-
0.08ROTATION
2.34
-
-
2.78
-
-
0.12
3.22
-
-
0.16
3.66
-
-
4.1
0.2
-
MAG:S1
MAG:S2
MAG:S3
MAG:S4
MAG:S5
MAG:S6
144
MAG:S7
MAG:S8
0.7
X:SADAF300
Y:SADAF300
0.14
Z:SADAF300
0.5
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.58
0.4
2
-
1.02
0.2
8
-
1.46
0.1
4
-
DISPLACEMENT (m)
0.14 (DEG.)
1.9
0
-
0.28ROTATION
2.34
-
-
2.78
-
-
0.42
3.22
-
-
0.56
3.66
-
-
4.1
0.7
-
MAG:S1
MAG:S2
153
MAG:S3
MAG:S4
MAG:S5
MAG:S6
136
MAG:S7
MAG:S8
119
102
MORRING FORCE (KN)
85
68
51
34
17
0
0.2
X:SADAF300
Y:SADAF300
0.14
Z:SADAF300
0.1
RX:SADAF300
6
-
RY:SADAF300
RZ:SADAF300
0.58
0.1
2
-
1.02
0.0
8
-
1.46
0.0
4
-
DISPLACEMENT (m)
0.04 (DEG.)
1.9
0
-
0.08ROTATION
2.34
-
-
2.78
-
-
0.12
3.22
-
-
0.16
3.66
-
-
4.1
0.2
-
DAMAGE
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
0 0.16 0.32 0.48 0.64 0.8 0.96 1.12 1.28 1.44 1.6
FERIQUENCY (RAD/SEC)
Engineering, Procurement, Construction and Installation
of Wellhead Platform(S1), Submarine Cables and
Pipelines Between S1 and Salman Complex
MAG:S1
MAG:S2
747
MAG:S3
MAG:S4
MAG:S5
MAG:S6
664
581
498
MORRING FORCE (KN)
415
332
249
166
83
0
0.2
0.1
-
X:SADAF300
Y:SADAF300
Z:SADAF300
0.1
0.5
RX:SADAF300
3
-
RY:SADAF300
RZ:SADAF300
0.0
0.9
6
-
0.01
1.3
-
-
0.08
1.7
-
-
DISPLACEMENT (m)
0.22 (DEG.)
0.15
2.1
-
-
0.29ROTATION
2.5
-
-
2.9
-
-
0.36
3.3
-
-
0.43
3.7
-
-
4.1
0.5
-