General Guidelines For PFS
General Guidelines For PFS
General Guidelines For PFS
Feasibility Studies
(fifth edition)
December 2008
External
Researchers:
Contents
CHAPTER 1
Outline
. Background and Purpose of Revising the General Guidelines
1. Role of the General Guidelines
2. Background and Purpose of Revising the General Guidelines
. Guiding Directions and Major Contents
1. Composition and Directions of the General Guidelines
2. Major Contents and Methodologies
1
1
1
1
3
3
4
CHAPTER 2
Project Overview and Basic Data Analysis
. Project Overview
1. Background and Purpose of a Project
2. Project Selection Process and Implementation Agency
3. Contents of a Project
4. Guidelines for Writing Project Plans for Candidate Projects
. Basic Data Analysis
1. Analysis of the Natural and Living Environments
2. Analysis of the Social and Economic Environments
. Identification of Issues
13
13
14
14
15
16
17
18
18
20
CHAPTER 3
Economic Analysis
. Demand Estimation
1. Transportation Projects
2. Water Resources Projects
3. Other Projects
4. Standards to Reflect Development Plans
. Benefit Estimation
1. Transportation Projects
2. Water Resources Projects
3. Other Projects
. Cost Estimation
1. Transportation Projects
21
22
22
26
32
32
34
35
37
38
40
41
51
54
55
57
57
58
60
64
66
67
68
68
68
70
79
79
80
80
83
84
90
95
CHAPTER 4
Policy Analysis
. Policy Analysis System
. Analysis by Evaluation Item
1. Balanced Regional Development
2. Consistency with Policy and Willingness to Pursue Projects
3. Risks in Pursuing Projects
4. Project-Specific Evaluation Items
97
97
99
99
153
155
157
CHAPTER 5
Comprehensive Evaluation: AHP Method
. Multi-Criteria Analysis and AHP
1. Need for Multi-Criteria Analysis
159
159
159
161
163
165
165
166
169
171
174
175
176
179
179
184
Acronyms
186
References
188
Appendix 1
Appendix 2
Appendix 3
190
194
196
List of Tables
Table 3-19
Table 3-20
Table 3-21
Table 3-22
Table 3-23
Table 3-24
Table 3-25
Table 4- 1
Table 4- 2
Table 4- 3
Table 4- 4
Table 3-14
Table 3-15
Table 3-16
Table 3-17
Table 3-18
2
27
29
33
35
36
37
37
44
46
49
52
53
56
56
57
60
73
74
76
76
78
80
91
94
95
98
100
101
102
Table 4- 5
Table 4- 6
Table 4- 7
Table 4- 8
Table 4- 9
Table 4-10
Table 4-11
Table 4-12
Table 4-13
Table 4-14
Table 4-15
Table 4-16
Table 4-17
Table 4-18
Table 5- 1
Table 5- 2
Table 5- 3
Table 5- 4
Table 5- 5
168
169
170
172
178
List of Figures
Figure 1- 1
Figure 3- 2
Figure 3- 3
Figure 3- 4
Figure 5- 1
12
167
CHAPTER 1
Outline
Table 1-1. Based on the reports published until 2008, a total of 382 preliminary
feasibility studies were completed. Of these reports, 165 were on roads and 74 were
on railroads, accounting for the majority.
Table 1-1
Year
Road
Railroad
Port
Culture &
Tourism
Water
Resources
Others
Total
1999
11
19
2000
11
30
2001
20
14
41
2002
30
2003
11
33
2004
24
13
12
55
2005
11
30
2006
27
11
52
2007
30
45
2008
11
15
37
Total
165
74
23
30
22
58
372
Note: Based on the preliminary feasibility study reports published through August 2008.
and cost calculation; the guidelines for analysis of financial feasibility need to be
devised; and the possibilities to induce private investment need to be studied.
Changes in the circumstance, the Sectoral Guidelines of each type of project, and
such should be considered, and more credible, current data should be referenced.
Second, primarily with respect to the transport projects, some of the indices used
in the process of demand estimation, benefit calculation, and cost calculation should
be renewed, and the precision in the values of parameters should be reviewed. The
details of this work can be found in the study to revise the Sectoral Guidelines for
Road and Railroad Projects.
Third, there is the need to supplement policy analysis that constitutes the basic
analysis framework of preliminary feasibility studies along with economic
feasibility analysis, and to supplement the Analytic Hierarchy Process (AHP)
analysis that comprehensively evaluates both analyses. Data on relative development
by region needs to be updated for policy analysis. Ways need to be considered to
supplement the basic analysis framework for policy analysis and AHP analysis such
as adding special evaluation items and reorganizing the system of evaluation items.
Due to the aforementioned needs and background to revise the General
Guidelines, this revision report mainly intends to develop a range of analysis
methodologies to be uniformly applied to all types of projects and to work out more
detailed principles and standards for application. Particularly, it includes the contents
from the soon-to-be revised Study to Revise and Supplement the Sectoral
Guidelines for Preliminary Feasibility Studies for Road and Railroad Projects (fifth
edition) as well as the Study to Estimate the Values of Cultural and Scientific
Facilities, Study on the Methodologies of Preliminary Feasibility Studies for
Health and Welfare Projects, and Study on the Sectoral Guidelines for Preliminary
Feasibility Studies for ICT Projects currently underway regarding the guidelines for
non-transport projects, in order to increase the scope covered by the General
Guidelines.
Outline
that have been maintained since 2000 and the expectations for low economic growth
due to the decline in the per-capita GDP growth rate and the rate of savings
occasioned by low fertility and population aging. This report intends to
comprehensively consider the needs, issues, etc. of such adjustment and suggest an
appropriate discount rate. To ascertain whether it is necessary to adjust the current
real social discount rate, 5.5%, it reviews changes in the capital market such as the
downward trend in the interest rate, and recent application of discount rates in
developed countries.
Regarding the differentiation of evaluation methods for different types of
projects, it reviews the practicality as well as pros and cons of applying different
social discount rates for such projects as those for roads, railroads, ports, water
resources, and cultural and sports facilities.1
b. Reflection and Inclusion of other Guidelines
As the General Guidelines serve as comprehensive guidelines for different types
of projects, this revision report intends to build a general system by including the
revisions and additions of standard manuals of preliminary feasibility studies.
Nevertheless, this report only carries the outline of analysis and leaves out specific
analysis methods, parameters, etc. to be carried by the manuals and reports of each
type of project.
It includes the contents from the Study to Revise and Supplement the Sectoral
Guidelines for Preliminary Feasibility Studies for Road and Railroad Projects (fifth
edition) (hereinafter Sectoral Guidelines for Road and Railroad Projects)
currently underway. It is also more closely connected and consistent with the
Handbook of Investment Evaluation of Roads and Railroads published by the
competent authority for each project. Since preliminary feasibility studies became
institutionalized, the government agencies that carry out such studies, like the
Ministry of Land, Transport and Maritime Affairs, have developed and used
handbooks of investment evaluation, similar to the General Guidelines for
preliminary feasibility studies and the sectoral guidelines of each type of project.
Though they bear some difference in terms of the execution steps, scope, and
specific study methods, preliminary feasibility studies and regular feasibility studies
apply the same basic evaluation methods. As there is a need to maintain consistency
1 Current water resource projects (dams) have a longer economic life cycle (50 years) than other SOC
projects and thus benefits occur over a long period. For this reason, the social discount rate for such
projects is 6.5% in the first 30 years of operation and 5.0% in the remaining 20 years.
Outline
Outline
the weights on economic feasibility analysis and policy analysis and that of
evaluation results toward the weights on basic and special evaluations. It also
intends to delve into the best way to respond when the evaluators come up with
different decisions and ways to expand the scope of evaluators.
Part I
10
11
Figure 1-1
Economic Feasibility
Analysis
l
l
l
l
l
l
l
Demand Estimation
Technical Review
Benefit Estimation
Cost Calculation
Cost-Benefit Analysis
Sensitivity Analysis
Review of Ways to Attract
Private Investment and
Financial Feasibility
Analysis
Policy
Balanced Regional
Analysis
Development Analysis
Comprehensive Evaluation:
Multi-Criteria Analysis (AHP)
l Feasibility of Project
l Other Policy Suggestions
12
l Regional Backwardness
l Ripple Effects on the
Regional Economy
CHAPTER 2
Project Overview and Basic Data Analysis
. Project Overview
14
3. Contents of a Project
Among the details that go into a project plan to be written by the competent
authority, the most important is contents of the project other than its background and
purpose, selection process, and the implementation agency. Knowing in advance the
location of a project, its construction scale, and costs are important clues in roughly
determining its economic feasibility. A project plan needs to state the spatial
location, construction details, and total project costs based on data and past
experience.
Although the spatial location of a project is the element first considered when
considering whether to pursue it, it requires extensive investigation to determine a
specific location and detailed routes. Also, a bit of preliminary investigation is
required to estimate construction details and total project costs. Arguably, a
preliminary investigation should be conducted to select a specific location and route,
and to estimate construction details and total project costs. Nevertheless, there
should be no request for a preliminary feasibility study without an estimated spatial
15
location, rough route, or total project costs. To this end, it should be mandatory to
include a rough spatial location, construction details, and total project costs in a
project plan submitted to the budget authorities.2
16
If a preliminary feasibility study is launched without concrete project details, the competent authority
should be requested to submit a project plan (draft) of specific details as soon as possible.
Fifth, the plan should also stipulate the expected effects of a project. Such effects
as increased production, employment, added value, and the like once it is completed
may not be definitely known at this step, but other expected effects need to be
roughly presented like, in the case of a transport project, how much travel time can
be reduced, how many commuters or travelers can be accommodated, and how
much congestion costs can be reduced.
17
18
19
. Identification of Issues
Once the outline and basic data on the natural, living, and social and economic
environments of a project are analyzed in detail, the main issues to be dealt with in
its preliminary feasibility study are identified. Such issues depend not only on the
nature and background of the project but also on the natural and socio-economic
environments of the concerned region.
The most important issue in any preliminary feasibility study is the review of
alternatives. Looking into alternatives is as important as estimating the costs and
benefits of a suggested project plan. In the case of highway construction projects, the
question of whether alternatives like expanding other national and/or local roads or
building a railroad instead of building the planned highway are more desirable
should be addressed. There is one restriction in reviewing alternatives: considerable
time and effort are required to compare alternatives at a level playing field as doing
so entails at the very least roughly calculating the costs and benefits of as many
alternatives as possible. Consequently, a detailed and accurate cost-benefit analysis
should be conducted for a project plan while the costs and benefits of alternatives
are estimated using the existing data and such.
One point to bear in mind is that doing something is not the only alternative:
doing nothing is also in many cases an entirely legitimate alternative and should,
therefore, be carefully considered. For example, in addition to considering expansion
of a national highway network or laying a railroad instead of laying an expressway,
doing nothing should be seriously considered as well. The opportunity costs should
be considered in all cases to determine a projects feasibility, and doing nothing may
be found to be in fact the best alternative.
Moreover, preliminary feasibility studies can identify other issues like technical
feasibility, possibility of financing, inter-regional conflicts, national defense
consideration, and possibility of attracting private investment.
Whatever they are, the final report of a preliminary feasibility study must
highlight important issues in analysis and suggest their solutions.
20
CHAPTER 3
Economic Analysis
. Demand Estimation
1. Transportation Projects3
A. Process to Estimate Transportation Demand
The feasibility of a project that invests in transportation facilities can be
analyzed by comparing the associated costs and resulting benefits. Transportation
demand is one of the elements that have the greatest impact on the estimation of
costs and benefits in feasibility evaluation. The decision on whether to go ahead
with the concerned project, priority for investment, etc. is evaluated through the
estimation of transportation demand, and such estimation is used to derive an
appropriate size of transportation facilities to provide and analyze the impact on the
surrounding areas of such facilities. In the case of a PPP project, the estimated
transportation demand serves as important background data to determine the
projects feasibility as well as usage fees and construction subsidies.
Demand for transportation can be estimated by various methods. A model based
on the data of individual travelers or households or a model based on the data of
each zone subject to analysis can be used. In Korea, a four-step model is most
commonly used to estimate transportation demand not only in large cities but also
between regions. It is not so much that the model is appropriate for any case but that
the consistent steps to estimate transportation demand used by the model are easy to
understand, even for laymen.
To estimate transportation demand, each of the four steps of trip generation, trip
distribution, mode choice, and traffic assignment is successively applied based on
Traffic Analysis Zones (TAZ). Each step has different techniques and models to
apply as follows:
First, trip generation estimates trips that are either produced by a TAZ or
attracted to a TAZ and uses the rate of change model, trip rate model, crossclassification, regression analysis, etc. This step discovers the generated and
attracted traffic volume of passengers and cargo in each TAZ.
3
22
In fact, demand estimation methods used only in road, railroad, or bridge construction projects, out of all
transportation projects, can be used as they are, and slightly different methods should be used for projects
to build ports or airports. For demand estimation methods for transportation projects of each type, refer to
the Study to Revise and Supplement the Sectoral Guidelines for Preliminary Feasibility Studies for Road
and Railroad Projects (fifth edition) (KDI, 2008), Study on the Sectoral Guidelines for Preliminary
Feasibility Studies for Port Projects (KDI, 2000), and Study on the Sectoral Guidelines for Preliminary
Feasibility Studies for Airport Projects (KDI, 2000), respectively.
Second, trip distribution allocates the generated and attracted traffic volume
estimated above among TAZ and often uses models like those for growth factor,
gravity, entropy maximization, and intervening opportunity. This step generates
passenger O/D (Origin/Destination)4 and cargo O/D data among TAZ.
Third, mode choice divides the O/D data among traffic zones from the previous
step into the modes of transportation available for choice by users and often uses
trip end models, trip interchange models, disaggregate behavioral models, etc. This
step produces O/D data for different passenger modes like passenger cars, buses,
and railroads and O/D data for cargo like truck and railroad cargo.
Lastly, traffic assignment assigns the O/D data of each transportation mode to
the transportation network in the TAZ, and often uses static assignment techniques
like all-or-nothing assignment, capacity restraint assignment, stochastic assignment,
and equilibrium assignment.5
Figure 3-1 shows the process of transportation demand estimation under the
conventional four-step model. In the preliminary feasibility studies of most road
projects, transportation demand at the origin and destination of each future mode of
transportation estimated by the governments transportation database center is used
so that the three steps out of fourtrip generation, trip distribution, and mode
choiceare omitted. The first thing to do in the process of estimating transportation
demand in a road project is calibration of data from the base year based on given
O/D and network data. This work refers to building a model of current
transportation patterns within the margin of error, and the calibration is considered
well done if the deviation is small between the results of network traffic assignment
within the TAZ and the actual observed traffic volume. Once data calibration of the
base year is completed, future transportation patterns are forecast in accordance with
O/D and network changes based on the assumption that the traffic assignment
pattern of the base year continues. This forecast is compared with the transportation
patterns of a year when the project is implemented to predict any change in
transportation patterns resulting from project implementation such as changes in
traffic volume and speed. Preliminary feasibility studies use commercial
transportation planning software to analyze transportation demand. Recently widely
used are EMME/2, TransCAD, and others developed overseas as well as Koreas
4
In Korea, institutions that have public confidence distribute passenger O/D data, and estimation of
transportation demand often uses relevant O/D data. Some foreign cases use P/A (ProductionAttraction) data for urban transportation analysis.
Recently, there has been substantial research based on real-time dynamic traffic assignment
techniques using ITSs (intelligent transportation systems) to estimate the traffic volume of cars and
passengers for each section of roads and railroads.
Economic Analysis
23
Trip Distribution
(Fratar Method, Gravity Model, etc)
Cargo
O/D
Passenger
O/D
Modal Share
(Trip End Model, Logit Model, etc.)
Construction of
Current
Transportation
Network
Traffic Assignment
(User Equilibrium Model)
Comparison of
Assumed and Observed
Traffic Volume
Establishment of
Four-Step Model
Table of Future
Total O/D Traffic and Each
Modes Traffic
Future Traffic
Assignment
24
Unlike road projects that use the already-established O/D data of each
transportation mode, the mode choice step is very important in railroad projects.
Accordingly, in addition to transportation demand estimation for roads, calibration
in relation to mode choice and transportation demand estimation for each future
transportation mode should be conducted. The calibration is considered well done if
the deviation is small between the demand estimated for each transportation mode in
the base year within the TAZ and the actual demand observed.
Economic Analysis
25
volume like those to build bridges between islands and between islands and the
mainland, the total traffic volume can change to reflect the induced traffic.6
This condition of constant total traffic volume applies only within the zone
system indicated in provided data. If the zone system changes through segmentation,
aggregation, etc., the total traffic volume before and after the change is naturally
different. Under the assumption of constant total traffic volume, the O/D data of
traffic volume by modes can change. In a railroad project, the modal share rate
increases as a result, and the O/D traffic pattern of another transportation mode (i.e.
roads) changes, inevitably leading to change in the O/D data of traffic volume by
modes for both roads and railroads.
26
The Preliminary Feasibility Study on Projects to Build Three Bridges between Islands and between
Islands and the Mainland in Sinan County (KDI, 2003) used the assumption that the construction of
island-connecting bridges causes additional traffic.
more rational and objective methods should be used for such analysis, and much
focus should be placed on it at the step of preliminary feasibility study to ensure
precise estimation.
Analysis Items
Description
n
Water Demand
Estimation
Water Supply
Estimate demand for water to preserve rivers and improve the environment
Investigate supply facilities and plans to expand them in the impact area and estimate
Estimation
Analysis of Water
Supply and Demand
Estimate demand for industrial water in national, regional, and agricultural industrial
Predict future water supply and demand and compare excess or deficiency before and
after development
The demand estimation step in preliminary feasibility studies should refer to the
population plans, penetration rates, various units, and other such prospects
suggested in several higher-level plans. Nevertheless, these higher-level plans make
some of the forecasts only every five years, and these need to be interpolated for
analysis items in annual units. Considering that all sorts of water resource plans
abide by the highest-level plan, the Long-Term Comprehensive Plan on Water
Resources (Water Vision 2020), preliminary feasibility studies should use the same
base period to propose forecasts as that used in the long-term plan. If the time of the
concerned project completed does not coincide with the base year, the supply and
demand status at the time of completion should additionally be suggested.
7
Demand for water consists of water for residential purposes, industrial water, agricultural water,
water to preserve rivers, and water to improve the environment.
Economic Analysis
27
If the estimated demand for water exceeds the actual demand, and the newly
developed water resources and supply facilities are not efficient, the economic
feasibility of the concerned project drops. Similarly, if the estimation falls short of
the actual demand, a new water resource should be developed and its supply
facilities should be planned in the near future, also resulting in lower economic
feasibility. Extorted estimation of future water supply capacity can have similar
results. Preliminary feasibility studies should accurately estimate actual future
supply and demand to determine a point of time when supply exceeds demand as
that of the concerned project completed. Supply and demand should coincide in the
planned year, and the scale of development should be set to ensure smooth
reconciliation of supply and demand. Nevertheless, some degree of flexibility
should be exercised to determine the volume of supply and time of development as
there are many uncertainties in demand estimation.
28
The Long-Term Comprehensive Plan on Water Resources (Water Vision 2020) (Ministry of Land,
Transport and Maritime Affairs, 2006) estimated water demand for residence by an econometric
technique.
Purposes
Description
n Water for household uses, commercial uses (including small-volume industrial uses),
Residential
bathhouse uses, specific industrial uses, public uses, temporary uses, and other uses
(tourism, port maintenance, military, etc.)
Industrial
Agricultural
Preservation of
rivers
Improvement of the
environment
n Water for industrial uses for raw materials, product processing, boilers, and other
purposes
n Water for rice paddies, dry fields, stockbreeding, and other such uses
n Water to discharge to maintain the three functions of rivers: irrigation, water control, and
environmental function.
n Water needed for some sections of rivers to improve the living environment. The water is
provided when requested by a beneficiary group.
Second, the actual demand for water for industrial purposes is divided into that
from industrial complexes in planned locations 9 and that from freely-located
plants10. Preliminary feasibility studies only investigate the demand from industrial
complexes in planned locations by extrapolation and unit load methods.
Extrapolation entails regression analysis of fluctuations in the past use of water to
estimate future demand, and therefore, the past data of each complex needs to be
fully studied. It is impossible to apply this method in Korea because the available
data is inadequate. The unit load method is used to estimate the demand from
industrial complexes. The unit load method applies units, derived from elements
closely related to the amount of industrial water used, to these elements in order to
ascertain the amount of industrial water used. To use this method, the most
appropriate unit should be selected for each industry type, and these units include
the area of a plant site, number of employees, production volume, etc. The per-unit
method is used as the unit for the existing industry complexes. Its applicability was
reviewed in the 2006 Long-Term Comprehensive Plan on Water Resources. The
area of a plant site is used for new complexes as such data is easy to acquire.
Third, water for agricultural purposes is divided into water for rice paddies
(well-irrigated paddies/partially-irrigated paddies), dry fields (irrigated fields/nonirrigated fields), and stockbreeding (livestock/processing). Preliminary feasibility
9
10
Industrial complexes in planned locations are national, regional, and agricultural industrial
complexes that are planned for specific locations and accommodate a large number of plants.
Freely-located plants are small individual plants scattered across the nation.
Economic Analysis
29
30
calculating the supply capacity of a new dam to secure additional water resources.
To ascertain the water supply volume for residential purposes at the water supply
facilities of each administrative district, the data of the Korea Water Resources
Corporation and local governments is to be referred to, and distinction should be
made among regional waterworks, special-purpose waterworks, and such. To
ascertain the volume of water supply facilities for industrial purposes, data should
be gathered on regional and industrial water supply as well as water supply facilities
exclusively for industrial purposes allowed by regional MLTM offices and local
governments to supply water. Underground water facilities used by industrial
complexes and freely-located plants are excluded. The capacity of regional and
industrial water supply facilities for industrial purposes should be calculated
excluding volume used for residential demand under the Water Service Statistics.
Irrigation facilities of agricultural water include reservoirs, pumping and drainage
stations, dammed pools for irrigation, collecting conduits, tube wells, etc. Data kept
by local governments and farmland improvement associations is to be used.
To ascertain the supply capacity of existing water resource supply facilities, that
of water service facilities like distributing reservoirs and clean water reservoirs is to
be calculated by dividing the facility capacity of each district (city, county, and gu)
in the Water Service Statistics by the peak load factor (1.2%~1.35%). The capacity
of water resource facilities like multi-purpose dams to secure unprocessed water is
to be calculated using their facility capacity as reported.
Economic Analysis
31
3. Other Projects
Projects to build industrial, cultural, tourism, sports, and science complexes
generate effects that are direct but not so great. They mostly have indirect effects.11
As such, demand arising from indirect effects must be higher than direct demand for
projects. If the main purpose of a project to form an industrial complex is to raise
the competitiveness of the appropriate industry, the most important is to accurately
estimate the demand to be created by the project in the industry. As demand
estimation can be extremely difficult in some cases, it is recommendable to estimate
demand for both the best-case and worst-case scenarios.
32
Of course, indirect effects mentioned here are not entirely the same as those in the next chapter:
policy analysis. Indirect effects here refer to direct and indirect effects of a project, but not
economic ripple effects directly given to its principal agent. They are also not very general indirect
effects like ripple effects to the local economy to be dealt with in policy analysis.
Details on how to reflect development plans will be dealt with in the guidelines
for different types of projects. In the case of transportation projects, for instance,
they can include how much more traffic should be additionally reflected and how
increased traffic should be distributed. To increase consistency in all studies, these
General Guidelines intend to define clear standards for the step at which
development plans should be reflected in preliminary feasibility studies and suggest
their basis.
In general, the standards to reflect development plans are largely divided into
those of cities and provinces and of the central government. Development plans
include those for housing site development, industrial complex development, and
tourist resort and resort complex development. As the reflection of development
plans can greatly influence the feasibility of projects, the reflection standards should
be carefully approached.
Preliminary feasibility studies have so far reflected development plans when
their detailed implementation plans are approved in order to exclude uncertain plans
from analysis, ensure precise demand estimation, and prevent excessive and
overlapping investment.
To suggest clearer standards about when to reflect development plans, these
General Guidelines studied the rate of project implementation, mainly for the
development plans of housing sites and industrial complexes, according to the
development plan procedures suggested in the Evaluation Guidelines for
Transportation Infrastructure by MLTM (2007), Land Business Handbook (2007),
and Housing Business Handbook (2008) of the Ministry of Land, Transport and
Maritime Affairs that are used as the standards in feasibility studies. As a result, the
times of reflection are indicated in Table 3-3 as follows:
Table 3-3
Classification
Current Guidelines
(fourth edition)
Changed Guidelines
Note: The standard for reflecting any type of development plan is when the development plan is approved in the case of water
resources projects.
Economic Analysis
33
Not many housing site and industrial complex projects in the past were
cancelled after sites were designated. Nevertheless, as the O/D data distributed by
the Korea Transport Institutes Korea Transport Database Center already reflect
most development plans, reflecting those plans of which detailed implementation
plans are approved would improve the accuracy of analysis.
Plans for multi-functional administrative cities, innovation cities, transfers of
provincial governments, and such led by the central government, which are more
likely to be implemented than other development plans, need to be reflected before
approval of detailed implementation plans. When development plans have a great
influence on project feasibility, scenario analysis can also be carried out, and clear
description needs to be made in reports. However, any reflection of development
plans should be carefully done taking into account actual conditions. These General
Guidelines focused on development plans for housing sites and industrial complexes,
but it would be appropriate to reflect plans of other kinds like those for tourist
resorts and resort complexes at a step corresponding to approval of detailed
implementation plans.
. Benefit Estimation
Benefit estimation starts with the identification of benefit items. Benefit items
vary greatly according to the characteristics and contents of projects, and they need
to be subdivided according to project plans submitted by the competent ministry.
Once they are identified, opportunity cost or value per unit is calculated by item to
estimate benefits. For instance, the estimated benefit Bit is expressed as follows:
Bit = Pi Dit ,
Bt =
it
where value per unit of benefit item i is Pi and estimated demand is Dit at the
point of time t .
The following is divided into transportation, water resource, and other projects.
As in Section 1, demand estimation, the individual guidelines should be referred to
for more specific estimation methods, and these General Guidelines only deal with
34
overall estimation.
1. Transportation Projects
Investment projects of transportation facilities generate direct benefits for
transportation and indirect social benefits. The benefit items of road and railroad
projects are indicated in Table 3-4 and Table 3-5.
Direct benefits generated by transportation projects for users of transportation
facilities include savings in vehicle operating costs, travel time, and accident costs
as well as increased pleasure, improvements in punctuality, greater safety, and such.
It is relatively easy to put a monetary value on the first three items, but it is difficult
to do so for the others as their value can vary according to individuals subjective
levels of satisfaction. For railroad projects, the benefits resulting from shifts in
demand from aviation and shipping and benefits from reductions in accidents and
delays thanks to improved crosswalks need to be reflected, but quantifying these
benefits is difficult.
The indirect benefits are ripple effects for all people regardless of their use of
transportation facilities and include pollution cost savings and noise cost savings,
regional development, expansion of markets, and improvement in industrial
structures. For railroad projects, also considered are savings in expressway O&M
costs thanks to shifts in demand, lower opportunity costs of parking spaces thanks to
lower demand for parking, and negative benefits in the form of increased congestion
and reduced road space during construction.
Table 3-4
Classification
Direct Benefits
Indirect Benefits
Benefits
n
Regional development
Expansion of markets*
Economic Analysis
35
Table 3-5
Classification
Benefits
Railroad User
Reduced travel time for people and cargo using railroads (both existing and new)
Benefits
Benefits for
Users of
Other Modes
Regional development*
Expansion of markets*
Indirect Benefits
(Non-User Benefits)
Lower opportunity costs of parking spaces due to lower demand for parking
Direct
Benefits
(User
Benefits)
Studies have been conducted to quantify pollution cost savings and noise cost
savings, and they can now be reflected in cost-benefit analysis. However, to realize
the benefits of regional development, expansion of markets, and reorganization of
industrial structures, investment should be made in other areas in tandem with
transportation facilities, which means difficulty in quantification. There is also
controversy regarding directly classifying them as benefits in cost-benefit analysis
due to crowding-out effects, etc. As such, they are not included as benefits. Savings
in expressway O&M costs need to be reflected, but they are still not easy to quantify.
Putting together the above discussion, these General Guidelines divide the scope of
benefit calculation into common benefits and benefits specific to projects as follows.
Common benefits are common to both road and railroad projects, and benefits specific
to projects are those to be calculated only for evaluation of specific projects.
36
Table 3-6
Classification
Benefits
Common Benefits
Benefits Specific to
Projects
Project
Type
Dam
(reservoir)
Waterworks
Underground
water
Agricultural
water
supply
Canal
Drain
River
restoration
River
park
River
repair
Retention
ponds for
flood
control
Benefits
Residential
water
Industrial
water
Agricultural
water
Underground
water
retention
facility
Small
hydropower
plants
Reduced
flood
damage
Economic Analysis
37
Table 3-7
Project
Type
Continued
Dam
(reservoir)
Waterworks
Underground
water
Benefits
Electric power
production
Environmental
cost savings
Agricultural
water
supply
Canal
Drain
River
restoration
Riv
er
park
River
repair
Retention
ponds for
flood
control
Underground
water
retention
facility
Small
hydropower
plants
Improved quality
of unprocessed
water
Improved natural
resources
Recreation
Emergency
water
Inland
transportation by
ship
Asset
advancement
Land formation
Transportation
facilitation/dama
ge prevention
Improved public
health
3. Other Projects
As in demand estimation, the benefit estimation method differs slightly for
different projects of building industrial, cultural, tourism, sports and science
complexes as they are each of somewhat different character.
The benefits of industrial complexes can be derived from the revenue of
additional added value or industrial production that will occur as a result of their
formation. When calculating expected added value, simple transfer income, namely,
revenue expected to be transferred from other regions or projects should be
excluded.
38
The benefits of cultural and tourism facilities are divided into their admission
and sales from their supplementary facilities. The admission revenue includes
admission fees, usage fees arising inside the facilities, and viewing fees, and also
items closely related to their establishment goals. The sales from their amenities
include those of shops (food and beverages, souvenirs, etc.), and sales and extra
income of lodgings (hotels, youth hostels, condominiums, etc.). Admission revenue
or sales should be determined thoroughly based on users willingness to pay, not
just on prices.
The main benefits of sports facilities are profits from various programs offered
within the facilities like training, screening, and competitions; extra income derived
from them; usage fees of facilities, etc. Training revenue should be divided
according to the characteristics of programs and target groups to make estimation
easier. Extra income should be estimated in the same way, and it includes income
from lodgings, sales of food and beverages, sales of souvenirs, and the like. If the
main purpose of a project is to provide sports facilities and tools, facility usage fees
like venue rental fees will be the main benefit.
The next step in benefit estimation is estimating the per-unit prices of specific
benefits. Unit prices are amounts assigned to a unit of services provided at facilities.
Examples are per-capita admissions to theme parks, lodging charges per capita and
room at lodgings, and per-capita training fees of training programs. Unit prices
should be estimated as necessary depending on the benefits and such estimation
should consider the following:
First, the characteristics and purposes of facilities should be considered.
Minimum unit prices necessary for facility operation should be applied if the
facilities are more like public properties or established for policy purposes like the
restoration and preservation of traditional culture and improvement in public health.
Examples are museums, restored historic sites, and public sports facilities. If they
are less like public properties and likely to be operated by a private party, unit prices
are in principle set at levels that maximize profit in reference to the size and unit
prices of similar facilities at home and abroad.
Second, when referencing the unit prices of similar facilities at home and abroad,
the data of facilities similar to those targeted for preliminary feasibility studies in
terms of the purpose, size, and characteristics should be chosen.
Third, the locational conditions of facilities should also be considered, which
include the natural environment, tourism resources, and transportation from inland
cities.
Economic Analysis
39
It should also be noted that there are limitations to the value estimation of
cultural and science facilities, as follows:
First, admission fees reflected as a benefit are not determined based on market
prices but by law, which means that the amounts users willingly pay, the result of
true value judgment by users, are not properly reflected.
Second, reference to overseas data due to the absence of similar domestic
facilities can be problematic as the value of benefits varies with differences in
nations income levels, the publics preferences, and cultural and social conditions.
Third, preliminary feasibility studies define benefits from an economic
viewpoint as the highest amounts users willingly pay by reducing spending on other
goods. Benefit calculation based on unit prices does not properly reflect this, and its
theoretical basis is weak.
Fourth, including user spending at cultural and science facilities as part of
benefits does not reflect value judgments by people who do not use the concerned
facilities but still grants significant value to them. It disregards value held by nonusers. This is very problematic in that the true value of cultural and science facilities
for public interest should be estimated.
Fifth, there is always a possibility of underestimation when calculating admission
revenue, extra income, etc. as benefits. Time and travel expenses and the like to come
and go between home and cultural and science facilities are willingly paid to receive
value from the facilities, so they should be included as part of benefits.
In this light, to overcome the limits of unit price-based value estimation, preliminary
feasibility studies have since 2004 used the contingent valuation method (CVM) and the
conjoint analysis method (CAM) to estimate the value of non-market goods. 12
Preliminary feasibility studies of cultural and science facilities should, therefore, use unit
price estimation or CVM and CAM that is appropriate for the concerned projects.
. Cost Estimation
Cost estimation also differs depending on the nature and specifics of projects.
Project costs can be largely divided into construction costs, land acquisition costs,
12
40
For more details, refer to Park, Hyeon, Gyeongjun Yu, and Seungjun Gwak, Study on the Value
Estimation of Cultural Facilities (2004).
Operating and Maintenance costs (O&M costs), etc. Construction costs refer to the
entirety of project costs minus lot purchase costs and additional facility costs, and,
land acquisition costs are the costs of buying lots in the project area and
compensation costs. O&M costs include not only initial investment costs but also
ordinary operating costs that even consider life cycle costs to maintain the functions
of fixed assets like land, buildings, and facilities.
The following reviews and suggests cost estimation methods for transportation,
water resources, and other projects:
1. Transportation Projects
Cost analysis should be done differently for different transportation projects to
build expressways, roads, bridges, railroads, ports, and airports.
Demand and benefit analysis for railroad and bridge construction has a similar
analysis framework to that of road construction, but they require different criteria
for cost analysis. Also, not only demand and benefit analysis but also cost analysis
for port and airport construction differ from that of road construction.13
A. Road Projects
The costs of road projects should be clearly stated in the process of reviewing
project feasibility. When calculating project costs, both the number or scale of
structures in concerned projects and average construction costs should be considered.
Though figures that are as realistic as possible should be suggested, routes are not
yet finalized at the stage of preliminary feasibility study, so cost items, quantities,
unit prices, and other figures will need to be adjusted at the actual step of project
implementation.
The following are some basic assumptions for cost estimation in road projects
defined in the Sectoral Guidelines for Road and Railroad Projects:
13
As in demand and benefit estimation, these General Guidelines only deal with the basic assumptions
and directions about cost estimation in the Sectoral Guidelines for Road and Railroad Projects.
Refer to the appropriate guidelines for specific analysis methods and relevant parameters like unit
prices to apply.
Economic Analysis
41
Suggested values are averages, but if there are reasons and grounds,
appropriate unit prices can be calculated that reflect the characteristics of
project area.
For road design standards, the Rule on Road Facilities and Standards and
Road Design Handbook of the MLTM and Road Design Guidelines of
the Korea Expressway Corporation, and other latest standards should in
principle be applied.
Construction costs and lot purchase costs account for the vast bulk of road
project costs. Construction costs are divided into main route earthwork, bridges and
tunnels, and affiliated facilities like access facilities (interchanges & junctions),
tollgates (including buildings), and rest areas.
Road project costs are calculated as indicated in the following Figure 3-2.
42
Figure 3-2
The Sectoral Guidelines for Road and Railroad Projects (fifth edition) stipulate
that cost estimation results by type of construction or work be suggested in certain
forms. The following form shown in Table 3-8 is to be used to indicate the details of
the Total Project Costs (TPC) of road projects.
Economic Analysis
43
Table 3-8
Total length:
km (existing:
km, extension:
IC
ea, JC
ea, tollgates at main route ea
Structures: Bridge
ea ( m), tunnel ea ( m)
Others:
Construction type
Standard
Unit
Unit price
Quantity (1 million won)
A. Construction costs
A-1. Earthwork
Slab
RC
PC
PSC-Beam
A-2. Bridge
A-3. Tunnel
A-4. Entrance facility
A-5. Tollgate
PC-Box
ILM
FCM
MSS
FSM
ST.Box
ST.Plate
RC Rahmen
Two lanes
Three lanes
IC
ea
JC
ea
Main route
ea
IC
ea
ea
(A1~A6)rate(%)
formula
(A1~A6)rate(%)
formula
B-3. Supervision
(A1~A6)rate(%)
formula
(A1~A6)rate(%)
formula
B-5. VAT
(B-1~B-4)10%
formula
formula
C-2. IC, JC
formula
formula
44
(A+B+C)10%
km)
formula
(A+B+C+D)
Amount
(100 million
won)
B. Railroad Projects
There are many more things to consider in railroad projects than in road projects,
and they require very complex approaches to cost estimation. The bulk of road project
costs arise from civil engineering structures (roadbed and entrance facilities) and land
acquisition, and when necessary, can be divided into the cost of supplementary facilities
like rest areas, incidental costs, and O&M costs to allow relatively easy cost estimation.
Railroad projects, however, should separately calculate system construction costs as
well as roadbed facility costs and add costs for train car rail yards and train car
purchases. They also have a relatively high ratio of operating costs.
Cost estimation at the step of preliminary feasibility study is for generating costs
associated with railroad facility construction and maintenance to allow rational
policy making and provide standards for budget execution.
Most railroad facilities are greatly affected by natural topography and social
conditions, which leads to a great deviation among projects. Accurate calculation of
project costs requires a great deal of time and effort. Accurate cost estimation is
inevitably extremely difficult at a project design step like preliminary feasibility
study. Cost estimation at this step inevitably involves errors compared to actual
input costs, and to minimize such errors, the general guidelines for preliminary
feasibility studies, handbook of investment evaluation of roads, and the like have
continually been revised. These General Guidelines also conducted analysis keeping
this in mind and strived to ensure realistic cost estimation. The previous General
Guidelines (fourth edition) dealt with cost estimation only for general railroads, but
this Fifth Edition also includes cost estimation for regional railroad networks, which
are now becoming operational.
a. General Railroad Projects
The total project costs of general railroad projects are divided into construction
costs (roadbed, tracks, buildings, electricity, systems, etc.), incidental costs, lot
purchase costs, and initial car purchase costs. In consideration of errors in cost
estimation, preliminary feasibility studies add contingencies of some ratio to the
construction, incidental, and lot purchase costs.
The details of the Total Project Costs (TPC) of railroad projects suggested in the
Sectoral Guidelines for Road and Railroad Projects (fifth edition) are indicated in
Table 3-9 as follows:
Economic Analysis
45
Table 3-9
Standard
A. Construction costs
A-1. Roadbed(main route)
General section
km
A-1-1. Earthwork
Others
A-1-2. Bridge
Direct foundation
km
Pile foundation
km
Others
NATM
km
A-1-3. Tunnel
Others
Overbridge
Underground road
Overhead walkway
ea
A-1-4. Interchange
Others
A-2. Roadbed (stop)
A-2-1. Earthwork
2 homes, 2 lanes
ea
2 homes, 4 lanes
ea
Others
A-2-2. Bridge
2 homes, 2 lanes
ea
2 homes, 4 lanes
ea
Others
A-2-3. Underground
2-level excavation
ea
3-level excavation
ea
Others
A-3. Track
46
km
Table 3-9
Continued
Construction type
Standard
Above
rail
A-4. Building
On
ground
Below
rail
Way station
ea
Junction
ea
Start/terminal
ea
Way station
ea
Junction
ea
Start/terminal
ea
Way station
ea
Junction
Underground
Others
A-5. System
km
km
km
km
km
km
ea
(A1A6)rate (%)
formula
(A1A6)rate (%)
formula
(A1A6)rate (%)
formula
B-3. Supervision
(A1A6)rate (%)
formula
(B1B4)10%
formula
formula
(A+B+C)10%
Initial year
(A+B+C+D+E)
Replacement
investment costs
Note: E. Car purchase costs need to be reflected after confirming whether they are included as part of the total project costs to
manage.
Economic Analysis
47
48
Table 3-10
Construction Type
Standard
Unit
Earthwork
km
Bridge
km
U-type
km
A. Construction costs
A-1. Civil engineering
Excavation
10m or less
at depth
km
20m or less
km
30m or less
km
NATM
km
Tunnel
A-1-2. Stop
A-1-3. Ventilation
hole
A-1-4. Hold track
Others
km
On ground
m or ea
Elevated
m or ea
Underground
(excavation)
2 levels
m or ea
3 levels
m or ea
Others
m or ea
ea
Excavation
km
NATM
km
Others
A-2. Track
A-2-1. Main route
Steel wheels
km
Rubber wheels
km
On ground
A-3. Building
A-3-1. Stop
Elevated
Underground
2 levels
3 levels
Economic Analysis
49
Table 3-10
Continued
Construction Type
Standard
Unit
On ground
Elevated
A-3. Building
A-3-1. Stop
Underground
2 levels
3 levels
A-4. System
A-4-1. Electricity
Electricity facility
Power line
km
km
Substation facility
Electrified line
km
km
km
A-4-2. Signal
A-4-3. Communication
A-5. Train car rail yard
A-5-1. Train car rail yard
A-5-2. Inspection facility
A-6. VAT
B. Incidental costs
B-1. Basic design
km
car
(A1~A5)rate (%)
(A1~A5)rate (%)
formula
(A1~A5)rate (%)
formula
(A1~A5)rate (%)
formula
(A1~A5)rate (%)
A4rate (%)
formula
formula
formula
(B1~B6)rate (%)
formula
formula
(A+B+C)10%
(A+B+C+D+E)
Replacement
investment costs
Note: E. Car purchase costs under F. Total project costs should be reflected only when they are included as part of total
project costs to manage, unlike costs for economic analysis.
50
A. Dam Projects
For the estimation of dam construction costs, flood volume is calculated through
hydraulic analysis, and design flood discharge is determined for each structure to
determine the form and size. Hydraulic calculation, etc. is conducted for each
structure, structures are planned using standards determined by dam design
standards, and details of construction works should be produced for each structure
as much as possible.
Estimating costs for each structure is difficult at the step of preliminary
feasibility study, but it should be done in as much detail as possible in consideration
of its impact on future feasibility studies and changes in the construction costs of
basic and detailed designs.
To help address difficulties in the estimation of construction costs, the Sectoral
Guidelines for Water Resources Projects (fourth edition) suggested unit
construction costs and construction cost calculation methods for several types of
structures for reference. Cost estimation results for each type of structure are to be
suggested in a certain form, and the standard details of total project costs of dam
construction are to be listed in the table of details of total project costs as in the
following Table 3-11:
Economic Analysis
51
Table 3-11
Construction type
Standard
Unit
Quantity
A-3 39%
sum
sum
1 million
sum
sum
Unit
Amount Remarks
price
A. Construction costs
A-1. Temporary facility
A-2. Diversion of waterway
A-3. Main construction
A-4. Spillway
A-5. Discharge facility
A-6. Power plant
A-7. Access road
A-8. Appurtenant work
A-1~A-7 33%
B. Incidental costs
B-1. Research and survey
Rate
B-2. Design
Rate
Rate
A~C 10%
E. Maintenance costs
F. Total project costs
A+B+C+D+E
B. River Projects
When calculating the costs of river work, both the specific quantity of structures
to build and average construction costs should be considered. The location of a spoil
bank, distance to carry revetment materials, and the characteristics of the river, etc.
are very important. Since no standard unit price or the like has been defined, it is
difficult to use the standard construction cost per unit length or area. Furthermore, at
the step of preliminary feasibility study, routes on river banks, length of the
embankment, locations and standards of structures, whether to establish cutoff walls,
etc. are not determined. For this reason, cost items, quantities, unit prices, and other
figures will need to be partially adjusted in the actual implementation step.
River conservation work involves the construction of five major components:
52
Unit
Price
Quantity
A-1. Embanking
Sum
A-2. Revetment
Sum
Sum
Sum
Construction Type
Standard
Unit
Price
Amount
Remarks
A. Construction Costs
A-3. Structure
A-4. Cutoff
A-5. Appurtenant Work
A-1A-2 20%
B. Incidental Costs
B-1. Research & Survey
Rate
B-2. Design
Rate
Rate
AC 10%
A+B+C+D
Economic Analysis
53
3. Other Projects
Initial investment in forming cultural, tourism, sports, and science complexes
includes construction costs, land acquisition costs, and other costs. The costs are to
be estimated based on the size and characteristics of facilities, but unit prices need to
be separately determined by the preliminary feasibility study team.
Construction costs include those to build the components of infrastructure like
civil engineering, landscaping, electricity and communication, and roads, and those
to build facilities. It is easier to separately estimate the number or scale of each cost
item required and unit prices. The unit prices are estimated by referring to the Unit
Price Table for Building Construction of the Korea Appraisal Board and consulting
with construction companies. To estimate the number or scale of each item required,
the scale of construction indicated in the basic project design should be referred to,
but if it is unrealistic or not suggested, similar cases should be referenced or
construction companies consulted.
Land acquisition costs are estimated using the exact location of a complex in the
project design and a map that indicates its lot number and area. If such is not
indicated in the project design, the average land prices and relevant data of the
project area should be used. It is still not easy to acquire such data, and even when
acquired, the estimates may not be reliable.
Land acquisition costs are purchase costs of land and compensation for
obstructions that must be demolished when exercising eminent domain, indirect
compensation, and other incidental costs. First, market prices for different
possession types and uses in the project area are estimated, and the prices are
multiplied by the areas of different uses to estimate the land purchase costs.
Compensation for obstructions and indirect compensation are estimated based on
the past cases of compensation and the Enforcement Rule of the Act on Special
Cases Concerning Acquisition and Loss Compensation of Public Lots. In this
light, due diligence should be conducted for the target district, and various
obstructions and economic actions be confirmed. However, precise estimation is
difficult at the step of preliminary feasibility study, and compensation costs may
increase. This requires, in principle, that on-site investigation based on an
arrangement map of facilities be conducted, but if the amount at issue is
insignificant or cannot be confirmed at the time of study, precise estimation
should be made at the full-scale feasibility study step.
To report total project costs, etc., forms used for road and transportation projects
should be used as much as possible.
54
14
Economic Analysis
55
Table
3-13 Compensation Ratios Used in Land Acquisition by City and County and Land
Category
Classification
Cities
Counties
Average
Lots
2.37
3.61
3.40
Rice paddies
2.45
3.21
3.12
Dry fields
2.50
2.94
2.89
Forest land
6.52
6.02
6.11
Others
3.38
4.49
4.28
Average
3.84
3.86
3.85
Next, in consideration of the fact that the official land value has increased four times
on average in response to the recent rise in market prices for land, a survey on
compensation ratios was conducted of appraisers who are responsible for land appraisal
for compensation in the field. The survey divided regions into the Seoul metropolitan
area, non-metropolitan area, and cities and counties, and asked about average
compensation ratios for different land categories across the nation. The current
compensation ratios applied by appraisers are some 1.5 to 2.7 times for regions and 1.5
to 2.0 times for land categories, a bit higher or lower than the current guidelines.
Table 3-14
Region
Seoul Metropolitan Area
Non-Seoul Metropolitan
Area
Rice Paddies
Dry Fields
Lots
Forest Land
City
1.51
1.52
1.37
1.98
County
1.74
1.72
1.50
2.53
City
1.76
1.72
1.65
2.25
County
1.81
1.81
1.65
2.49
City
1.58
1.57
1.41
2.09
County
1.86
1.90
1.57
2.69
1.56
1.54
1.44
1.87
1.77
1.79
1.52
2.40
All
1.56
1.50
1.40
1.94
The following three alternative ways to estimate purchase costs of land can be
suggested based on the compensation ratios of the above land acquisition cases and
survey results. The first is to choose as samples some 5% of land within the project
area in consideration of the land characteristics and ask the Korea Association of
Property Appraisers or Korea Appraisal Board to perform a summary appraisal on
56
them. The second is to receive existing land acquisition data about areas
surrounding the project area from the execution agency of a project that requested a
preliminary feasibility study to drive a compensation ratio and calculate the land
acquisition costs. The third is to apply standard compensation ratios below. Table 315 below has standard compensation ratios to use when calculating purchase costs
of land based on compensation ratios. Compensation for obstructions is to be set at
10 to 15% as the conditions of each project site require.
Table 3-15
Region
Rice Paddies
Dry Fields
Lots
Forest Land
Seoul Metropolitan
City
1.50
1.50
1.40
2.00
Area
County
1.75
1.75
1.50
2.50
Non-Seoul
City
1.75
1.75
1.65
2.30
Metropolitan Area
County
1.80
1.80
1.65
2.50
Economic Feasibility is evaluated using the benefit and cost numbers from the
above estimation of demand, benefits, and costs. Evaluation of economic feasibility
basically depends on cost-benefit analysis.
Economic Analysis
57
1. Analysis Methods
A Benefit-Cost Ratio (BCR) is first calculated to evaluate economic feasibility.
A BCR is the ratio of benefits to costs where both benefits and costs are expressed
as discounted present values. In other words, costs and benefits to occur in the
future are converted into present values, and the present value of benefits is divided
by that of costs. A project is generally economically feasible if the BCR is at least
1.0.
Of course, it is inappropriate to simply determine that a government-financed
project is economically feasible merely because the BCR is no less than 1.0. This does
not apply, for example, in the U.S. The special standards for public investment
analysis suggested by the U.S. Office of Management and Budget (OMB) explain that
the BCR should be at least 1.25 for a project to be economically feasible in
consideration of the excess burden resulting from tax distortion and the like15. Also, in
Korea, the theoretical minimum BCR should be 1.10 to 1.15 for economic feasibility
to be recognized in consideration of the marginal costs of public capital due to the
difficult financial situation and tax distortion, etc. Nevertheless, it cannot be said that
there is sufficient social overhead capital as Korea is still a developing country.
Furthermore, it can cause unnecessary confusion to apply the minimum BCR of 1.10
to 1.15 at the step of preliminary feasibility study as other studies use a ratio of 1.0. In
comprehensive consideration of the above, the figure of 1.0 will be used as the
minimum BCR instead of the theoretically estimated BCR for the time being:
n
BCR =
t =0
Bt
/
(1 + r ) t
Ct
(1 + r )
t =0
Where Bt : Benefit at the time t , Ct : Cost at the time t , r : discount rate, and
n : Duration of the concerned facility (period subject to analysis) .
Secondly, it is important to calculate the Net Present Value (NPV). The NPV is
the total benefits minus total costs incurred by a project (both benefits and costs
expressed in discounted present values of the base year). An NPV of at least zero
means the project is economically feasible:
15
58
The special standards for public investment analysis under Section 11 of Circular No. A-94 of the U.S. OMB
explains that estimation of the marginal costs of public capital in consideration of the excess burden of taxation
reveals that a public investment with the minimum BCR of 1.25 can be recognized for economic feasibility.
NPV =
t =0
Bt
(1 + r )t
Ct
(1 + r )
t =0
t =0
Bt
=
(1 + R)t
Ct
(1 + R)
t =0
Determination of feasibility is not always the same in BCR, NPV, and IRR
calculation. First, NPV calculation evaluates the flow of net benefits with the value
in the start year of a project, but it is not normalized with respect to the scale of
projects, making it inappropriate for comparison among projects. For instance, when
doubling both benefits and costs, the NPV automatically doubles. It is, therefore,
inappropriate to compare the profitability of two different projects with the same
characteristics only based on their NPV. Second, IRR calculation does not consider
the scale of projects, but it has a shortcoming in that an IRR is not calculated
according to the profit generation structure. Third, a BCR value differs according to
which items are classified as benefits or costs, but this is the one that is generally
used as an investment evaluation standard.
Preliminary feasibility studies are to calculate the BCR, NPV, and IRR without
exception to evaluate economic feasibility, compare priority among projects, and for
other such purposes.16
16
In some cases, the BCR, NPV and IRR come up with different conclusions about feasibility. For
details, refer to Kim (2008) Cost-Benefit Analysis.
Economic Analysis
59
Table 3-16
Analysis
method
Critical
value
BCR
B/C1
NPV0
n Difficult to understand
n An error may occur when determining
the order of priority among alternatives
IRRr
NPV
IRR
Merits
Demerits
60
discount rate in depth,17 this section looks at the value of the finally-set discount
rate and several issues related to application of this value.
Refer to the part about the social discount rate in Chapter 6, Part 2 for details on how to set the
social discount rate.
Economic Analysis
61
Despite being based on a short time-series data, this has recently become
apparent in the major economic indices. Growth is forecast to slow due to slower
growth in per-capita GDP and a declining savings rate resulting from population
aging and the low birth rate, while interest rates will remain low compared to before
2000. The current real interest rate of 6.5% is, therefore, somewhat high. Of course,
the appropriate social discount rate with regard to public investment projects should
not only consider simple figures but also qualitative factors.
STPR = r + m g
In the above formula, r refers to a discount rate of future consumption under
the assumption that per-capita consumption does not change. g is an annual percapita consumption increase rate, and m is the elasticity of marginal utility of
consumption. In the end, m g is to reflect the diminishing effect of marginal
utility due to consumption change.
Calculation of this social time preference rate according to the formula revealed
that the appropriate range is 5.0 to 5.5%.
The basic interest rate based on the real interest rate of five-year government
bonds and long-term premiums for the last five years also falls within this range.
Lastly, estimation of a real weighted average cost of capital as part of financial
feasibility analysis revealed that 5.5% is proper for a real discount rate used in
financial feasibility analysis as the spread between the interest rates of three-year
corporate bonds and government bonds narrowed from 2% to no more than 1%, and
thereby, the cost of debt capital decreased.
However, the current economic analysis does not fully review a projects risks
except for some sensitivity analysis, which can require a higher discount rate. Also,
the tendency to evade a sudden adjustment of the discount rate should be considered
62
Economic Analysis
63
64
estimated with focus on the consumer price (price paid by consumers, which is the
supply price plus tax). When estimating reduced car operation costs, time value,
value associated with traffic accidents, etc. they should be evaluated with focus on
the price paid by consumers. Accordingly, it is appropriate to include tax in the
benefit afforded by an expressway. The benefit of an expressway should be
estimated as a consumer price that includes tax, and it is inappropriate to deduct tax
again from the estimated benefit amount.
It should be noted, however, that costs have a different aspect with regard to
analysis of expressway projects. In general, costs in public investments are
evaluated as maximum alternative benefits forgone of inputs. As long as the inputs
of expressway construction (e.g. cement, sand, asphalt) meet the conditions of
competitive sourcing, the market prices of these inputs should be regarded as social
opportunity costs. However, if the prices of inputs already include tax (indirect tax),
it can be handled in two ways: First, if inputs required in public investments are
redirected from existing users, in other words, if the entire supply to society of the
inputs is constant without regard to the implementation of a public investment, their
prices including tax should be used in cost evaluation as they are. In this case, it is
inappropriate to evaluate costs as market prices minus taxes. Second, if inputs are
additionally produced and supplied for a public investment, in other words, if the
entire supply to society of the inputs increases and the increased quantity is inputted
in the public investment, tax should be deducted to appropriately evaluate the social
opportunity costs. For instance, if tax is imposed on cement assuming a constant
supply, the social marginal utility (willingness to pay) of cement exceeds its social
marginal cost. If more cement is produced to lay an expressway, the social
opportunity costs of cement should be calculated as social marginal costs. In this
case, the market price of cement minus tax should be regarded as costs.
For this reason, textbooks on cost-benefit analysis state that the social value
(opportunity costs) of inputs is evaluated as a (market price including tax) + (1 a ) (market price excluding tax). (1- a ) here reflects the additional production
rate of inputs. That is, the a rate of inputs in public investments refers to inputs
redirected from existing users, and (1- a ) is the rate of additional production. In
other words, if inputs in public investments are all consumed by existing users, it is
appropriate to conduct cost-benefit analysis based on the market price including tax.
However, if only a portion of inputs (e.g. a portion corresponding to the a rate) is
used by existing users, the market price including tax should be used in evaluation
only for that rate. And the rest should be evaluated based on the price excluding tax.
At issue is how to estimate , the rate of inputs redirected from existing users. It
is very difficult to estimate how much of inputs are redirected from existing users in
Economic Analysis
65
B. Other Projects
When there is only one execution agency for a project like the Korea Expressway
Corporation or the Korea Railroad Corporation, and the methods and items of cost
estimation are relatively systemized based on existing data, tax deduction is possible to
some degree using the existing data. In other projects, it is not obvious who the
responsible parties are in most cases, and cost items vary greatly from one project to
another, which serves to complicate tax deduction. Namely, how to deduct which taxes
remains controversial. If there are multiple parties involved in projects, they bear various
types of taxes, which leads to variable cost items and makes it very difficult to
determine which tax is imposed on which cost item.
Accordingly, tax deduction in the economic analysis of other projects is to be
temporarily left to the discretion of each study team. There should be further study
on how to deduct taxes more systematically.
In the end, transfer payments such as taxes should be handled considering both
producers and users. The KDI plans to conduct in-depth studies to come up with the
most appropriate way to handle taxes in cost calculation.
66
Analysis that excludes from benefits 10% VAT borne by the Korea Expressway Corporation means
analysis that deducts 10% taxes from the costs of building various facilities suggested by the Korea
Expressway Corporation.
For more details, refer to the Study to Revise and Supplement the Sectoral Guidelines for
Preliminary Feasibility Studies for Road and Railroad Projects (fifth edition).
Economic Analysis
67
6. Sensitivity Analysis
The calculation of benefits and costs in economic analysis used to evaluate
feasibility engenders many uncertainties. Sensitivity analysis is often conducted to
deal with these uncertainties. This analysis looks at how economic feasibility
changes when each important variable that can affect investment costs or economic
feasibility like initial construction costs, operating costs, demand for transportation,
discount rates, etc. changes by a certain degree.
Preliminary feasibility studies conduct sensitivity analysis about these variables.
The scope and methods of sensitivity analysis can differ slightly depending on the
type of a project.
68
Economic Analysis
69
with an appropriate level of government financial support can be turned into PPP
projects. It also prescribes that whether to pursue a project with public finances or
with private investment should be determined when conducting a preliminary
feasibility study. To satisfy this regulation, there should, obviously, be a way to
determine whether or not to pursue a project with public finances or with private
investment at the step of preliminary feasibility study.
70
Figure
Determine
feasibility
No
Reject a project
proposal
Yes
Determine eligibility
for VFM test
No
Yes
Determine feasibility
as a private
investment
No
Yes
Pursue as a government-financed
project
Economic Analysis
71
Figure 3-4
Possibility of
being pursued as
a PPP project
(B/C : 0.9)
Policy analysis
No
Yes
Yes
Projects asked to be
a BTL type by the
competent authority
No
Financial feasibility
analysis (BTO)
Economic feasibility
Ease of management
Creativity and efficiency
Risk distribution
Publicness
72
Table
Step
3-17 Preliminary Feasibility Study Checklist Items to Evaluate the Possibility of Private
Investment
Evaluation
Items
Evaluation Details
Step
Remarks
Can move to
Required
items
only if yes is
selected
Ease of
management
Creativity &
efficiency
How to
Score
The more
items with
high scores
Scoring
survey
higher is the
results
score to
determine
Risk distribution
Publicness
project
implementation
Economic Analysis
73
Table
Project Type
Responsible Ministry
Road (3)
Infrastructure Type
Railroad (3)
MLTM
Port (3)
MLTM
Airport (1)
MLTM
Airport facilities
Water resource
(3)
MLTM
Ministry of Environment
Information &
telecommunications (5)
Korea Communications
Commission
Energy (3)
Environment (5)
Ministry of Environment
Distribution (2)
MLTM
Culture &
tourism (9)
MLTM
Science museums
MLTM
Urban parks
Education (1)
MEST
National
defense (1)
Housing (1)
MLTM
Welfare (3)
Forest (2)
Note: Enforced three months after promulgation of a revision to the Act on Public-Private Partnerships in Infrastructure.
Source: Act on Public-Private Partnerships in Infrastructure ([Enforced on July 31, 2009]).
74
21
22
23
24
The principle of users being willing to pay higher usage fees (except for BTL projects): Higherquality service can be provided compared to that of the existing facility with lower usage fees, and
users are willing to pay higher usage fees for such higher benefits.
Principle of being profitable (except for BTL projects): The private investor can secure profitability
that justifies investment in consideration of usage fees allowable by the government and payable by
users and construction subsidies providable by the government.
Principle of being beneficial: If the project is public investment, it is difficult to quickly complete
facility construction and provide service due to budget limits, etc. If private investment is made, it
can be completed by a scheduled time, quickly generating benefits.
Principle of being efficient: The private sectors creativity is leveraged to increase efficiency in SOC
construction and operation, and competition with other public investment facilities is facilitated to
improve service quality
Economic Analysis
75
Table 3-19
Type
1. Core Service
2. Usage Fee
3. Profitability
X/
Case
Environmental
treatment
facility,
railroad
Museum,
science
museum
School,
military facility,
welfare facility
PPP Project
Implementation Method
BTO
BTL/BTO
BTL
BTL
Theme park,
National road,
public rental
sewer system
housing
BTL
BTL/BTO
Evaluation
Item
Feasibility in
Terms of Law
and Policy
PPP Project
Implementation
Method
76
Comprehensive
judgment
Remarks
Economic Analysis
77
Table 3-21
Evaluation
Item
Economic
Feasibility
Review Item
Are the total costs of this project high enough to secure value for money?
Is the project sufficiently economically feasible?
Can it stand alone without being connected with existing facilities (projects)?
Ease of
Management
Are the interested parties of this project clearly defined, and can opinions and
information be effectively exchanged?
Are the purpose and scope of the project clear, and can it suggest a definite required
service level for the concerned facility?
Is it believed that the private sectors creativity and efficiency will be exercised to
substantially reduce life cycle costs at the construction and operation phases?
Is it believed that the private sectors creativity will be exercised to provide better
Creativity &
Efficiency
Risk Distribution
Will its risks related to design and construction be transferred to the private investor to
reduce the governments burden?
Are there any restrictions to consider in project implementation (design, construction,
operation, acquiring approval, etc.)?
Is there a possibility that excessive benefits will accrue to a special interest party if
this project is implemented?
Are considerable ripple effects expected with the private partys participation such as
Publicness
78
Remarks
Economic Analysis
79
Table 3-22
Classification
Economic Analysis
Financial Analysis
Perspective of evaluation:
National economy
Measured price:
Shadow price
Market price
Transfer payments:
Excluded
Included
2. Basic Assumptions
A. Investment Methods of Projects
Financing for public investment projects can be divided into cases where a
separate corporation is established and those where an existing corporation serves as
a responsible party. Both cases use equity capital and debt capital and can
additionally consider government subsidies, government loans, etc. Equity capital is
funds raised by the responsible party with reserve funds or capital increase, or funds
by a separate corporation through equity participation by specific parties, IPOs, and
such. Debt capital can be raised through borrowing from domestic and foreign
financial institutions, issuance of corporate bonds, etc. As SOC construction is
usually capital-intensive, the share of debt capital is often high.
In financial feasibility analysis, which often uses the discounted cash flow
method based on conventional financial theories, different financing methods,
strictly speaking, do not have a big impact on analysis results. Nevertheless,
assumptions about the ratios of equity capital and debt capital, financing methods,
etc. have an impact on the calculation of appropriate discount rates, so these should
be determined in advance.
Public investment projects pursued with private capital usually take the form of
BOT (Build-Operate-Transfer), BTO (Build-Transfer-Operate), BOO (Build-OwnOperate), and BTL (Build-Transfer-Lease), etc. Preliminary feasibility studies, in
general, validate whether target projects are suitable to be pursued as BOT or BTO
projects, if unless other implementation methods are economically persuasive.
80
C. Salvage Value
In general, salvage value is related to the duration of the concerned facility and
period of economic feasibility analysis. In the case of facilities and equipment, the
calculation and amount of salvage value can vary according to such project types as
BOT, BTO, and BOO. It should, therefore, be calculated accordingly. In economic
feasibility analysis, salvage value is included as part of negative costs at the final
point of analysis. In financial feasibility analysis, as the ownership of a facility
reverts to the government or a local government organization in a BOT or BTO
project, the private party does not get to have salvage value. However, if the private
party is granted facility ownership at the end of analysis, salvage value shall be
considered as a negative cost.
25
As values estimated from economic feasibility analysis are used for income and costs, the analysis
standards should be the same as those in economic feasibility analysis.
Economic Analysis
81
E. Supplementary Projects
If the responsible party conducts not only the concerned project but also
supplementary projects, the costs and revenues of the supplementary projects should
be included in financial feasibility analysis. Supplementary projects here refer to the
construction of supplementary facilities directly related to the concerned project.
Minor supplementary projects should be excluded. These include shopping malls
and the like that have little direct bearing on the characteristics of the project.
Supplementary projects that can be reviewed in financial feasibility analysis as part
of a preliminary feasibility study are those that can be directly handled by the
government when the government is the implementation party of the main project.
The investment costs of supplementary projects should fall within the scope of
the costs of the concerned PPP project. Supplementary projects should serve to
increase benefits in the national economy and the business value of the concerned
project, and be implemented at locations geographically close to that of the
concerned project.26
Cases that can be considered as supplementary projects are, in road projects, the
net income of advertising facilities and net income of amenities leasing. In railroad
26
82
The upper limit on the amount of income from supplementary projects cannot be suggested by law
or regulation. In the case of the Korea Expressway Corporation, income from supplementary
projects (rest area lease) accounts for less than 3.0% of the total income. This can be used as a
benchmark.
projects, an example is income other than fares such as the income of advertising in
train cars and stations or of vending machines. The estimation of investment costs
(e.g. installation costs), operating costs, and profits related to supplementary
projects should consider the installation costs of rest areas from the Korea
Expressway Corporation and income of advertising in subway cars of the Seoul
Metro.
3. Analysis Methods
The most commonly used discounted cash flow methods are used for financial
feasibility analysis.
The discounted cash flow methods estimate future cash flows and calculate
present values discounted by the opportunity cost of capital (e.g. weighted average
cost of capital). The discounted cash flow methods include the Net Present Value
(NPV), Internal Rate of Return (IRR), Profitability Index (PI) methods, and more.
The NPV method is the sum of expected cash flows, both incoming and
outgoing, that are discounted by the weighted average cost of capital. This means
the amount by which corporate value increases when the concerned investment
proposal is adopted. If the financial NPV is positive, the project is believed to be
financially feasible.27
n
FNPV =
Rt
Ct
(1 + r ) - (1 + r )
t
t =0
t =0
where Rt refers to the incoming cash flow of period t , and Ct to the outgoing
flow of period t .
The IRR method calculates an IRR (FIRR), a discount rate that reconciles the
present values of incoming and outgoing cash flows expected from investment into
the planned project, and compares it with capital costs to evaluate an investment
proposal. When the IRR exceeds the capital costs, the project is considered
financially feasible.
27
To distinguish from the NPV and IRR used in economic feasibility analysis, they are indicated as
FNPV and FIRR in financial feasibility analysis.
Economic Analysis
83
0=
t =0
Rt
(1 + FIRR)t
Ct
(1 + FIRR)
t =0
The PI method is the ratio of the net value of incoming cash flows divided by
that of outgoing cash flows (cash flows occurring from investment). If the PI is
higher than 1, the project is judged to be financially feasible. While the NPV method
measures the financial feasibility of an investment proposal as an absolute amount,
the PI method measures the ratio of cost vs. profit in a proposal as a relative ratio.
n
PI =
t =0
n
Rt
Ct
/
t
(1 + r ) t = 0 (1 + r )t
84
supplementary projects and environment-related costs are cash flows incurred due to
the investment project and should, therefore, be included in the cash flow estimation
of financial feasibility analysis.
Second, sunk costs are not considered. Such costs have already occurred without
regard to implementation of the investment project, so they are not included in its
financial feasibility analysis.
Third, opportunity costs resulting from the use of existing facilities, land, and
buildings should be considered. Cash flows that can occur when existing facilities,
land, buildings, etc. are used not for the investment project but for alternative
purposes are lost as these assets are used for the investment project. They should be
used as the opportunity cost of the investment project targeted for analysis.
Fourth, additional opportunities that occur in relation to the investment project
should be considered. If there are expansion options that can further increase the
scale of the project after its implementation, additional cash flows that can occur
accordingly should be considered.
Fifth, expense distribution should be considered.
28
29
Refer to the appendix for cash flow calculation and how to fill out pro-forma financial statements.
Nevertheless, if a government agency and the Korea Expressway Corporation are the responsible
party of the project, the figure from economic feasibility analysis can be used as it is.
Economic Analysis
85
the operators income of the route subject to the study should be used from among
the operators income estimated in economic feasibility analysis. In this case, the
operators income can be calculated by using the traffic volume of the route ( q )
computed in economic feasibility analysis and the toll rate of the expressway ( p )
used in the generalized cost formula.30
The toll level ( p ) used at the step of preliminary feasibility study is a value
based on the toll rate of the Korea Expressway Corporation in consideration of
social benefits. As the toll level of privately financed expressways currently under
operation is higher than that of the Korea Expressway Corporation, use of the Korea
Expressway Corporation rate for financial feasibility analysis can distort the
profitability of the project. When the assumption is that the project is to be
conducted by a private party, a realistic toll level should be applied. If the traffic
volume resulting from a preliminary feasibility study is used to calculate operating
revenue, the demand can be overestimated. For this reason, the private party needs
to analyze the traffic demand again to set the toll at a more rational level.
As a toll is determined through negotiations when it becomes certain that a
project is to be implemented as a PPP project, usage fees including tolls should be
reset at rational levels and traffic volume reestimated to conduct financial feasibility
analysis again when the possibility of private financing of a project is strong.
2) Other Revenues
Other revenues can include cash flows from supplementary projects and ancillary
projects, but it is difficult to estimate them at the step of preliminary feasibility study. In
general, supplementary projects and projects to construct affiliated facilities are judged
to be small enough to be disregarded. It is best to consider only indispensible ones from
among them at the step of preliminary feasibility study and to consider income and costs
from them when determining tolls and the length of the free-use period at the step of
full-fledged evaluation or negotiations.31 Nevertheless, if there is supplementary income
that is definitely expected, it can be calculated by a rational method and included among
other revenues.
30
31
86
As of 2007, the basic rate of a closed toll collection system of the Korea Expressway Corporation
was 862 won; and the toll rate of a two-lane expressway was 40.50 won/km for type 1 vehicles,
41.30 won/km for type 2, 42.90 won/km for type 3, 57.50 won/km for type 4, and 68.00 won/km for
type 5. The standards used in economic feasibility analysis should be consistent with these.
90.3% of the total revenue of the Korea Expressway Corporation is toll income; 6.0% is from
supplementary projects like government projects and research outsourcing; and 3.7% is from
ancillary projects like lease income. In case of a large-scale road project, the percentages of
different items can be used in these feasibility studies or evaluation to select a responsible party.
32
33
Survey and Research Costs: Survey and other costs in preparation for
project implementation (based on the standard fees for compensation
for engineering projects under Article 10 of the Engineering
Technology Promotion Act)
Article 22(1) of the Enforcement Decree of the Act on Public-Private Partnerships in Infrastructure
and Article 9 of the Basic Plan for PPP Projects (calculation of total project costs) are referred to.
As there are cases where a zero tax rate is applied, like construction outsourcing of urban railroad
projects, analysis tables of profitability and financial statements should be written in consideration
of VAT application for different areas.
Economic Analysis
87
land. If there is none, the Detailed Guidelines for VfM Test shall
apply mutatis mutandis.
n
2) Operating Costs
Operating costs are the sum of costs of facility operation during the operating period
after facility completion. The items included are costs of sales, maintenance costs,
selling and general administrative costs, corporate taxes (actual corporate taxes +
interest costs corporate tax rate), VAT, etc.
As in the assumption of total project costs, interest costs occurring in the operating
88
34
Depreciation cost is accounted for as a deduction item when calculating pre-tax profits, but as it
does not accompany cash disbursements, it is not included in the assumption of cash flows. A
reduction in corporate taxes due to depreciation cost should nevertheless be considered.
Economic Analysis
89
35
90
Refer to Section 3 of Chapter VII for detailed discussions on discount rate calculation.
Year
Government Bond
Corporate Bond
(3 year)
(off-board, three year, AA-)
1995
13.39
13.79
0.40
1996
11.84
11.87
0.03
1997
12.26
13.39
1.13
1998
12.94
15.10
2.16
1999
7.69
8.86
1.17
2000
8.30
9.35
1.05
2001
5.68
7.05
1.37
2002
5.78
6.56
0.78
2003
4.55
5.43
0.88
2004
4.11
4.73
0.62
2005
4.27
4.68
0.41
2006
4.83
5.17
0.34
Overall average
7.97
8.83
0.86
1999 to 2006
5.36
6.14
0.83
Economic Analysis
91
rj = rf + b j (rm - rf )
where ri refers to the cost of equity capital for an investment project j ; rm to the
market-expected rate of return; r f to the risk-free rate; and b j to the systemic
risk of the investment project j .
a. Assumption of a Market Risk Premium
The markets risk premium, (rm - r f ) has a relatively stable time series, so a rate
92
The equity beta ( b s ) is affected by the debt ratio of each company, and the beta
needs to be adjusted as follows according to the target debt ratio of a PPP project:
38
This 27.5% is a sum of the corporate tax rate of 25% to be applied from 2005 and residence tax (10%
of the principal tax) (2.5%).
Economic Analysis
93
Table 3-24
Discount
Rate
Capital Cost of
Debt
Calculation Process
Long-term risk-free rate
(r f ) = 6.8%
(rm - rf ) = 6%
(rs )
= rf + b s rm - rf
The real discount rate becomes 5.4% by deducting the expected inflation rate of
3% from the nominal WACC of 8.56%. The figure is derived from various
assumptions. In future financial feasibility analysis of preliminary feasibility studies,
an approximate value to the derived value - 5.5% - is to be used as a real financial
discount rate.
Depending on the nature of PPP projects and changes in the economic situation,
the beta value, target debt ratio, economic growth rate, and expected inflation rate
94
can differ. Table 3-25 shows the calculation results of a real discount rate according
to changes in the economic growth rate, debt ratio, and beta. The study team can set
an appropriate discount rate for individual projects in consideration of their risks
and government assistance.
Table 3-25
Risk-free rate
5.2%
5.7%
6.2%
100%
200%
300%
100%
200%
300%
100%
200%
300%
b1 = 1.157
8.88
8.53
8.35
9.30
8.92
8.73
9.72
9.32
9.12
b 2 = 0.671
6.44
6.21
6.10
6.86
6.61
6.49
7.28
7.01
6.87
b med = 0.515
5.65
5.47
5.38
6.07
5.87
5.76
6.49
6.26
6.15
b 3 = 0.406
5.11
4.95
4.88
5.53
5.35
5.26
5.94
5.75
5.65
b 4 = 0.153
3.84
3.75
3.71
4.25
4.15
4.09
4.67
4.54
4.48
Note: Assumptions are as follows: inflation rate=3.0%; short-term risk-free rate=YTM of three-year government bonds; long-term
liquidity premium=1.1%; long-term risk-free rate=short-term risk-free rate + long-term liquidity premium; default risk
premium=2.0%; capital cost of debt=long-term risk-free rate + default risk premium.
Economic Analysis
95
FNPV =
CFt + zt
(1 + r ) -
t
Invt - subt
and a =
(1 + r ) t
Sub
Inv
96
CHAPTER 4
Policy Analysis
Policy Analysis
97
Mid-level categorization
Balanced regional development
n Possibility of financing
n Environmental nature
n Additional evaluation items (elective)
Under the mid-level category balanced regional development are the level of
regional development and ripple effects on the regional economy. Added are
project-specific evaluation items related to balanced regional development. Under
consistency with policy and willingness to pursue projects are consistency with
relevant plans and policy directions, willingness to pursue and preference for
projects, level of project preparedness, and other relevant evaluation items. Under
risks in pursuing projects are the possibility of financing, environmental nature,
and other relevant evaluation items. Lastly, the project-specific evaluation items
category includes evaluation items not included in the above three categories.
98
UI r =
r
i
Wi
Policy Analysis
99
Area
Measurement method
Data source
Before change
After change
Statistics Korea
web site
Population
Population
increase rate
Industry
Ratio of people
engaged in
manufacturing
Statistics Korea,
basic statistical
survey report of
businesses
Local
infrastructure
Road ratio
Transportation
No. of registered
passenger cars
Aging index
Statistics Korea
web site
Degree of
financial selfreliance1)
(Local taxesnon-tax
Ministry of Public
revenue/total tax revenue under Administration and Security
general accounting)100;
(MOPAS), annual report on
last three years average
local finance
Health
social welfare
Government
administration,
finance, etc.
MOPAS,
annual report on
local finance
Note: According to the custom of calculating the degree of financial self-reliance of Seoul, six metropolitan cities, and nine
provinces, the fiscal data of gross totals of the provincial and metropolitan city governments is used for calculation of the
level of regional development of cities and counties; and the fiscal data of net totals of the provincial and metropolitan city
governments, and lower-level local governments is used to calculate the level of regional development of cities and
provinces.
39
100
Ministry of Land, Transport and Maritime Affairs, Work Guidelines for Regional Development
Projects, February 21, 2003.
The scales of the eight indices are different but need to be reconciled to control
the effects. For this purpose, the eight indices are standardized using the following
unit normal scaling. Nevertheless, as a higher aging index is interpreted as a strong
indication of low regional development, it is given a negative value when calculating
the regional development index.
Zi =
Xi - Xi
Si
For calculation of the regional development index, weights for indices should be
set up. For this purpose, a survey was conducted of people working at appropriate
academic societies and research institutes, who have experience in preliminary
feasibility studies, etc. to set up weights for indices as in Table 4-3.
Table 4-3
Weight (%)
Index
Weight (%)
8.9
12.4
Aging index
4.4
Road ratio
11.7
29.1
6.3
13.1
14.2
Source: KDI, Study to Amend and Supplement General Guidelines for Preliminary Feasibility Studies (fourth edition), 2004.
The AHP method is one of the decision-making techniques for systematic evaluation of opposing
alternatives when there are multiple and complex goals for decision-making or multiple and
complex evaluation standards. It stratifies complex issues into major or detailed elements and
derives their level of importance through pair-wise comparison. It is widely used in multi-criteria
decision-making that includes qualitative evaluation items. For AHP, refer to the Study on MultiCriteria Analysis for Preliminary Feasibility Studies (2) by Park et al. (2001) (KDI).
Policy Analysis
101
Classification
Project Type
Economic
Feasibility Analysis
Policy Analysis
Balanced Regional
Development
Before
Change1)
40 ~ 50
25 ~ 35
15 ~ 25
Construction
40 ~ 50
25 ~ 35
15 ~ 30
R&D,
informatization
30 ~ 50
50 ~ 70
(Analysis of technical nature and
policy nature)
Other non-investment
finance projects
25 ~ 50
50 ~ 75
(Analysis of technical nature and
policy nature)
After
Change 2)
Note: 1) KDI, Study to Amend and Supplement General Guidelines for Preliminary Feasibility Studies (fourth edition), 2004.
2) MOSF, 2006 Operating Guidelines for Preliminary Feasibility Studies, April 2006.
3) MOSF, 2009 Operating Guidelines for Preliminary Feasibility Studies, April 2009.
b. Current Indices for Determining Less Developed Regions and Their Change
1) Standards for selection of less developed regions under the Special Act on
Balanced National Development
Subparagraph 5 of Article 2 of the Special Act on Balanced National
Development defines less developed regions as follows:
Remote areas under Article 2 of the 'Remote Area Development Promotion Act;
Islands to develop under Paragraph 1 of Article 4 of the Island Development
Promotion Act;
Border areas under Subparagraph 1 of Article 2 of the Border Area Support Act
Development promotion districts under Article 9. (1) of the Balanced Regional
102
Development and Support for Local Small and Medium Enterprises Act; and
Other areas where the standard of living and the level of development are
very low and designated by presidential decree
Applicable laws suggest concrete standards for different kinds of less developed
regions. Article 2 of the Remote Area Development Promotion Act41 classifies
remote areas as those which are located far from cities; have underdeveloped
transportation systems, low income levels, low standard of living; and meet
conditions designated by presidential decree. Article 2 of the Enforcement Decree of
this Act stipulates the designation standard of remote areas as myeon-level (villageor township-level) administrative districts that fall below the average of myeon
districts across the nation in terms of the level of development (indices that indicate
the population increase/decrease rate, population density, and income or
development level. Result of comprehensive analysis as designated by the Minister
of Public Administration and Security) as a result of a basic survey of myeon
districts across the nation. Nevertheless, myeon districts that fall under the Island
Development Promotion Act and those not inhabited or without a myeon district
office are excluded from the scope of remote areas.
Table 4-5
Type
Designation Standards
n Administrative districts that fall below the average of myeon districts
Remarks
n Islands to
develop and
uninhabited
areas excluded
n 399 myeon
Remote
result of a basic survey of myeon districts across the nation (Article 2.(1)
districts as of late
area
2003
Table 4-5
41
Continued
The Remote Area Development Promotion Act was abolished (March 28, 2008, Act no. 9008), but
its Enforcement Decree remained in effect until December 31, 2009.
Policy Analysis
103
Type
Designation Standards
n Island districts constantly inhabited by no fewer than ten people which
Island
Remarks
n Uninhabited islands
request to be developed
excluded
n 410 islands
n Eup, myeon, and dong districts belonging to cities and counties within
Border
area
15 cities and
20km south of the Civilian Control Line (CCL) where no fewer than three
provinces 98 eup,
districts
Article 2 of the Island Development Promotion Act defines the scope of islands
as all the islands on the sea excluding the main island of Jeju. Islands that can be
designated as less developed regions are those constantly inhabited by no fewer than
ten people (Article 4 of the Enforcement Decree of the Act).
Article 2 of the Border Area Support Act stipulates border areas as belonging to
the jurisdictions of cities and provinces south of the CCL under Paragraph 3 of
Article 2 of the Protection of Military Bases and Installations Act and designated
by presidential decree based on the distance from the CCL, geographical conditions,
degree of development, etc. Paragraph 3 of Article 2 of the Protection of Military
Bases and Installations Act prescribes the designation standards of border areas as
eup, myeon, and dong (small district units) belonging to cities and counties within
20km south of the CCL where no fewer than three out of the population
increase/decrease rate, road pavement rate, water service penetration rate, ratio of
people engaged in manufacturing, and occupation rate of areas subject to the
Protection of Military Bases and Installations Act are lower than the national
average in the last five years (Article 2 of the Enforcement Decree of the Act). Also,
border areas are the areas located between the CCL and 2km south of the Military
Demarcation Line (MDL), and Baengnyeongdo, Daecheongdo, Socheongdo, large
Yeonpyeongdo, and small Yeonpyeongdo, and their surrounding islands south of the
104
Table
4-6 Selection Standards for Development Promotion districts (Less Developed Region
Policy Analysis
105
Type)
Index
Detailed Standards
Population
density
Ratio of the population of 2004 divided by the area of administrative districts under Statistics
Koreas National Demographics(2004) & MLTMs Administrative Districts and Population in
Local Governments (2004)
Annual
average
population
increase/
decrease rate
Annual average population increase/decrease rate for 34 years ((population of a past year for
comparison - population of the base year) period from the past year to the base year
population of the base year)) based on Statistics Koreas Population & Housing Census (1970
2004) and National Demographics(2004)
Total of
income-base
residence tax
Total of tax amounts imposed each year under MOPASs Annual Regional Tax Administration
Report (2001~03) (tax amounts in each city or county in the corresponding year=lease
income+interest income+personal income like transfer+income subject to withholding
tax+dividend income+pension income+temporary property income+other incomes <agricultural
income tax and residence tax (corporate tax base) are excluded>)
Financial
power index
Ratio of base revenue divided by base demand for finance from the last three years from 2003 to
2005 according to MOPAS Comprehensive Report on Analysis of Local Governments Finances
(2003~2005) and the ministrys web site on local governments finances (lofin.mogaha.go.kr)
(2005)
Aging index
Ratio of the number of 65-year-old or older people divided by that of 14-year-old or younger people of
the corresponding city or county under Statistics Koreas National Demographics (2004)
Ratio of the
employed
Ratio of the total number of people engaged in businesses by the size of population of the
corresponding city, county, or gu district under Statistics Koreas Statistics on the Number of People
Engaged in Each Industry (2003) and major statistics on cities, counties, and gu districts (2003)
Ratio of the length of the roads of the corresponding city, county, or gu district by its population
and administrative district area ((length of roads of base year
Road ratio
Accessibility
Source: Ministry of Land, Transport and Maritime Affairs, Work Guidelines for Regional Development Projects, March 2006
106
Policy Analysis
107
Table 4-7
Area
Index
Population
Industry
economy
Finance
Data
Source: MOPAS, Guidelines for Projects on Regions for Revitalization, October 2004.
2
+ Z(income - base residence tax) + Z(financial powerindex)
A composite index for 234 local governments was calculated, and the bottom 30%
or the bottom 70 regions were designated as regions for revitalization. The amount
of support for them was determined in consideration of special accounting for
regional development, cases of support for less developed regions overseas, etc.
For the second step of designation, the PCRD announced in 2007 a draft
proposal on regional classification according to the level of regional development
(selection base: 14 indices in five areas). The proposal classified 234 local
governments according to the development level in comprehensive consideration of
14 indices in the five areas of population, economy, finance, welfare and
infrastructure. 234 cities, counties, and gu districts were divided into four groups,
less developed regions (1), stagnant regions (2), growth regions (3), and developed
108
regions (4). Nevertheless, the special city, metropolitan cities (counties excluded),
and Jeju Special Self-governing Province are each classified as one region by using
the average value of their cities, counties, and gu districts. Also, in consideration of
different levels of regional development, the grade for the Seoul metropolitan area is
automatically raised one level. More specifically, a region which would be given
grade 1 in the provinces is given 2 in the Seoul metropolitan area, and so on.
Table 4-8
Classification
Weight
0.33
Population
0.33
0.33
0.25
0.25
Industry,
economy
1
0.25
0.25
0.33
Finance
0.33
0.33
0.25
Welfare
0.25
0.5
0.25
Description
n Population increase/decrease rate
(10 years)
n Population density
population
person
n Average land value of individual
people
n Increase/decrease rate of the total no.
of employed people
2005
person
n Increase/decrease rate of the
population
n Increase rate of the collected amount of
Road ratio
0.5
0.25
Infrastructure
Index
Source: MOPAS press release, presentation on a Draft Proposal on Regional Classification according to the level of regional
development, September 2007.
Policy Analysis
109
110
For details, refer to Chapter 10, Calculation of Regional Development Indices of the Direction
and Strategy of Regional Development Policy (KDI, 2008).
models was slightly better, but based on differences of no less than 20% and 30%,
that of the current preliminary feasibility studies was slightly better.
Table 4-9
Classification
No. of cities,
counties, & gu
districts (a)
Combined
models
Current
preliminary
feasibility
study
158
41
17
25.9%
10.8%
4.4%
158
46
15
29.1%
9.5%
3.8%
Policy Analysis
111
Table 4-10
Region
Population
Aging
increase
index
ratio
Spe-cial
Economy
Financial
selfreliance
Infrastructure
Ratio of
No. of
people in
registered
Road
manufa-
passenger
ratio
cturing
cars
No. of Urban
Compo-
Compo-
site
site
Regional
doc-
land use
develop-
tors
ratio
ment index
Regional
development
ranking
Seoul
-0.148
38.815
95.065
5.556
21.458
13.130 0.185
39.920
1.400
Busan
-0.828
46.493
73.203
5.492
19.131
3.488
0.148
16.267
0.140
Daegu
-0.098
37.403
73.923
6.156
24.814
2.407
0.152
11.806
0.469
Incheon
0.538
30.805
71.876
8.837
21.946
2.704
0.117
10.986
0.387
Gwangju
0.473
29.204
59.254
4.943
22.763
2.684
0.159
14.136
0.266
Daejeon
1.010
30.171
73.406
3.236
26.479
2.982
0.153
13.456
0.590
Ulsan
0.953
22.103
66.591
12.845
26.834
1.477
0.103
8.187
0.690
Gyeonggi
3.132
29.836
76.897
9.173
23.942
1.090
0.122
5.467
0.649
Gangwon
-0.493
60.141
23.536
2.769
23.365
0.466
0.126
1.044
-0.719
14
Chungbuk
-0.041
53.121
29.938
8.152
22.951
0.709
0.100
2.692
-0.417
11
Chungnam
0.534
64.770
39.610
4.509
22.290
0.787
0.114
3.749
-0.422
12
Jeonbuk
-1.138
62.409
21.136
4.341
20.954
0.810
0.143
3.048
-0.787
15
Jeonnam
-1.540
78.054
17.034
4.509
18.144
0.720
0.095
2.800
-1.172
16
Gyeongbuk
-0.736
68.618
24.608
9.772
23.158
0.608
0.091
1.966
-0.533
13
0.498
46.803
33.203
10.943
23.435
0.882
0.104
3.013
-0.157
0.596
42.025
36.761
1.533
24.233
1.592
0.115
3.182
-0.384
10
city
metropolitan
city
Province
Gyeongnam
Jeju
Note: Gijang County belongs to Busan Metropolitan City; Dalseong County to Daegu Metropolitan City; Ganghwa County and
Ongjin County to Incheon Metropolitan City; and Ulju County to Ulsan Metropolitan City.
112
Table 4-11
Ratio of
No. of
registered
rate of
people in
Road
Region
doctors
registered
manufa-
ratio
per
cturing
Financial
self-
Development
ratio
reliance
Index
index
cars per
residents
Urban
land use
Aging
passenger
person
person
Special city
Seoul
11
13
14
15
10
12
Gwangju
10
10
Daejeon
14
13
Gyeonggi
Gangwon
12
15
16
12
16
14
14
Chungbuk
14
14
11
14
12
11
Chungnam
11
11
11
11
14
12
Jeonbuk
15
13
12
14
13
11
15
15
Jeonnam
16
12
13
16
15
16
13
16
16
Gyeongbuk
13
15
16
15
15
13
13
Gyeongnam
10
12
10
12
11
Jeju
16
10
10
10
10
Busan
(Gijang County)
Daegu
(Dalseong
County)
Metropolitan city
Incheon
(Ganghwa,
Ongjin County)
Ulsan
(Ulju County)
Province
Note: Gijang County belongs to Busan Metropolitan City; Dalseong County to Daegu Metropolitan City; Ganghwa County and
Ongjin County to Incheon Metropolitan City; and Ulju County to Ulsan Metropolitan City.
Policy Analysis
113
Table 4-12
Metro-
Economy
Popula-
Aging
Finan-
politan
City,
tion
index
city,
county
increase
province
Special city
Metropolitan city
Metropolitan city
Metropolitan city
Metropolitan city
Metropolitan city
Metropolitan city
Busan
Daegu
Incheon
Incheon
Reliance
ratio
Ratio of
manuf-
Composite
Infrastructure
No. of
Road
No. of
Urban
ratio
doctors
land use
passenger
ratio
Regional Regional
devel-
devel-
opment
opment
index
ranking
acturing
cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Seoul
-0.148
38.815
98.958
4.600
21.458
13.011
0.205
39.920
2.862
Busan
-0.878
46.202
75.157
5.346
19.069
4.443
0.154
21.257
1.320
14
Daegu
-0.138
37.437
78.238
5.389
24.796
3.906
0.160
19.440
1.517
Incheon
0.555
28.725
76.963
9.068
22.034
5.287
0.117
22.179
1.633
Gwangju
0.473
29.204
59.780
4.943
22.763
2.684
0.181
14.136
0.979
21
Daejeon
1.010
30.171
78.504
3.236
26.479
2.982
0.176
13.456
1.395
11
Ulsan
0.898
19.288
71.859
11.533
26.895
3.256
0.107
19.181
1.556
1.547
58.257
38.937
11.968
21.886
1.094
0.066
3.754
0.327
53
0.500
36.969
31.631
17.459
25.077
0.802
0.051
3.628
0.364
49
-0.482
129.223
16.916
1.903
19.509
0.728
0.055
3.236
-0.495
115
2.294
117.637
33.224
0.439
17.842
1.069
0.038
1.872
-0.220
81
Gijang
County
Dalseong
County
Ganghwa
County
Ongjin
County
Ulsan
Ulju County
1.239
36.410
48.735
19.666
26.515
0.765
0.067
3.788
0.781
31
Gyeonggi
Suwon
2.0f63
21.896
58.006
4.827
25.059
5.732
0.148
26.536
1.535
1.345
31.279
73.221
4.064
24.375
3.367
0.166
15.307
1.326
13
2.213
32.011
50.007
1.341
20.209
3.898
0.335
12.086
0.890
23
Gyeonggi
Gyeonggi
114
Seongnam
Uijeong-bu
Table 4-12
Continued
Population
Economy
Infrastructure
Composite
Metropolitan
city,
Popula-
Aging
tion
index
Finan-
Ratio of
No. of
Road
No. of
Urban
ratio
doctors
land use
Regional Regional
City, county
developincrease
province
rate
manufac
-turing
passenger
develop-
ratio
ment
ment
index
ranking
cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Gyeonggi
Anyang
1.524
27.420
61.406
5.486
22.643
5.697
0.163
24.348
1.469
Gyeonggi
Bucheon
2.032
25.933
64.447
8.354
20.421
9.624
0.145
38.886
2.102
-0.547
29.835
47.156
3.743
18.907
4.225
0.224
18.041
0.814
30
11.500
26.856
60.204
8.662
28.530
0.820
0.017
6.689
1.199
15
1.728
35.182
43.114
16.472
26.833
1.265
0.130
7.947
0.828
28
1.946
47.769
21.471
5.160
19.956
1.086
0.636
5.625
0.378
48
3.835
19.055
60.194
15.466
23.623
5.824
0.063
20.626
1.615
-3.179
31.810
44.021
1.768
24.882
1.505
0.513
7.958
0.655
36
2.592
26.148
47.741
1.652
21.250
4.163
0.079
12.505
0.721
33
4.696
30.870
42.477
4.359
21.777
0.627
0.074
3.654
0.329
52
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gwangmyeong
Yongin
Pyeongtaek
Dongducheon
Ansan
Gyeonggi Gwache-on
Gyeonggi
Guri
Gyeonggi Namyang-ju
Gyeonggi
Osan
4.207
18.654
45.270
7.791
25.080
3.122
0.204
16.239
1.102
18
Gyeonggi
Paju
6.462
45.951
41.131
12.671
25.469
0.673
0.036
4.062
0.624
37
Gyeonggi
Siheung
4.209
17.733
55.259
20.425
24.827
3.573
0.054
13.466
1.365
12
Gyeonggi
Gunpo
0.666
25.889
52.911
10.349
22.590
3.981
0.058
17.962
1.048
19
Gyeonggi
Uiwang
3.756
28.645
46.302
6.305
23.816
2.598
0.099
8.232
0.727
32
Gyeonggi
Hannam
1.629
38.152
43.590
5.779
21.509
0.744
0.130
4.500
0.330
51
Policy Analysis
115
Table 4-12
Continued
Population
Popula
Aging
City,
-tion
index
county
increa-
Metropolitan city,
province
Economy
Finan-
No. of
Road
No. of
registered
ratio
reliance
manufac
passenger
-turing
cars
ratio
al
-al
devel-
devel-
opment opment
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
index
ranking
Gyeonggi
Icheon
1.019
35.983
43.659
15.447
25.681
0.496
0.058
4.586
0.567
39
Gyeonggi
Goyang
2.582
29.356
59.926
2.821
24.929
2.606
0.028
10.046
0.857
25
Gyeonggi
Anseong
3.018
51.583
29.369
15.918
25.012
0.784
0.053
4.122
0.380
47
Gyeonggi
Gimpo
5.228
34.797
40.264
20.599
26.364
0.774
0.050
7.225
0.854
26
Gyeonggi
Yangju
6.591
34.054
36.996
18.055
22.608
1.226
0.087
5.853
0.709
34
Gyeonggi
Yeoju
0.242
61.849
32.917
6.221
24.149
0.699
0.049
3.022
0.076
66
Gyeonggi
Hwaseong
9.271
35.351
57.567
37.656
27.405
0.676
0.040
6.164
1.626
Gyeonggi
Gwangju
8.950
31.333
47.457
15.022
27.242
0.804
0.038
4.185
0.946
22
-2.094
88.799
21.309
4.430
20.539
0.423
0.130
1.202
-0.363
93
Gyeonggi
Yeoncheon
Gyeonggi
Pocheon
1.850
49.054
30.378
18.419
22.506
0.565
0.029
3.092
0.271
56
Gyeonggi
Gapyeong
-0.317
88.734
24.504
2.099
20.583
0.361
0.031
1.219
-0.382
96
0.751
93.744
16.973
1.534
23.309
0.484
0.037
1.870
-0.371
95
0.351
50.959
33.378
1.688
26.298
0.779
0.183
1.844
0.166
60
1.368
42.234
36.958
4.698
24.641
0.821
0.190
2.734
0.304
55
-0.716
55.343
29.259
2.436
25.652
0.596
0.168
1.898
0.027
70
Gyeonggi
Gangwon
Gangwon
Gangwon
116
Composite
se rate
Ratio of
Infrastructure
Yangpyeong
Chuncheon
Wonju
Gangneung
Gangwon
Donghae
-0.954
47.932
25.381
2.611
24.156
1.069
0.095
5.672
-0.032
73
Gangwon
Taebaek
-1.625
62.360
18.218
1.838
22.532
0.638
0.110
1.405
-0.363
94
Gangwon
Sokcho
-0.589
43.140
32.670
1.467
22.697
1.312
0.091
5.980
0.057
68
Gangwon
Samcheok
-2.269
86.300
18.176
2.086
20.823
0.531
0.063
0.745
-0.517
117
Gangwon
Hongcheon
-0.908
85.316
19.735
2.639
19.475
0.339
0.101
0.691
-0.457
105
Gangwon
Hoengseong
-0.962
114.842
17.790
7.313
19.502
0.404
0.036
1.028
-0.461
107
Table 4-12
Continued
Population
Metropolitan city,
province
Economy
Infrastructure
Popula
Aging
Finan
Ratio of
No. of
Road
No. of
-tion
index
-cial
people in
register
ratio
self-
manufac-
-ed
reli-
turing
passen
ance
Composite
Urban
ratio
-ger cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Regional Regional
devel-
devel-
opment
opment
index
ranking
Gangwon
Yeongwol
-2.955
113.813
14.052
3.241
19.324
0.402
0.077
0.802
-0.652
133
Gangwon
Pyeong chang
-0.852
95.389
17.405
2.160
21.387
0.337
0.024
0.637
-0.517
118
Gangwon
Jeong seon
-2.626
98.800
24.377
1.766
20.206
0.372
0.068
0.624
-0.472
109
Gangwon
Cheorwon
-1.625
62.828
13.625
2.245
20.107
0.425
0.065
0.963
-0.573
123
Gangwon
Hwa cheon
-1.153
71.841
11.870
1.192
19.444
0.413
0.084
0.439
-0.632
132
Gangwon
Yanggu
-1.637
68.733
24.704
1.802
19.212
0.426
0.042
0.514
-0.460
106
Gangwon
Inje
-0.428
61.655
16.910
1.637
20.836
0.265
0.052
0.374
-0.500
116
Gangwon
Goseong
-1.958
99.137
18.741
2.372
19.063
0.493
0.022
0.840
-0.593
126
Gangwon
Yangyang
-0.568
102.541
23.710
3.377
22.799
0.430
0.044
0.920
-0.308
90
Chungbuk
Cheongju
1.682
26.635
51.108
4.821
25.138
4.072
0.130
19.281
1.118
17
Chungbuk
Chungju
-1.028
57.720
23.414
4.471
22.343
0.855
0.115
2.719
-0.156
76
Chungbuk
Jecheon
-1.308
61.115
23.559
3.123
22.077
0.645
0.088
1.735
-0.262
86
Chungbuk
Cheong-won
-0.599
81.332
30.077
20.174
22.994
0.665
0.027
4.238
0.237
58
Chungbuk
Boeun
-2.906
152.896
16.713
5.154
16.540
0.617
0.064
1.603
-0.665
135
Chungbuk
Jincheon
0.325
62.020
29.665
28.745
23.583
0.749
0.063
3.596
0.494
45
Chungbuk
Goesan
-1.955
108.790
16.619
6.979
19.102
0.545
0.054
1.804
-0.488
113
Chungbuk
Eum-seong
-0.208
66.779
28.438
21.920
22.363
0.729
0.098
4.661
0.324
54
Chungbuk
Danyang
-3.079
112.924
19.913
6.875
18.591
0.442
0.049
0.984
-0.523
119
Chungnam
Cheonan
3.983
26.841
52.651
12.810
26.339
1.425
0.176
7.358
1.019
20
Chungnam
Gongju
-0.801
83.482
20.494
4.327
20.790
0.768
0.108
2.382
-0.290
87
Chungnam
Boryeong
-1.775
81.823
25.902
3.396
19.807
0.690
0.087
3.051
-0.291
88
Chungnam
Asan
2.295
50.629
46.210
21.957
24.223
1.046
0.075
6.095
0.815
29
Policy Analysis
117
Table 4-12
Continued
Population
Metro-
Popula-
Aging
tion
index
Economy
Finan-
Composite
No. of
Road
No. of
ratio
reliance
rate
Ratio of
Infrastructure
manufac
-ed
-turing
passen
Urban
ratio
-ger cars
118
(0.089)
(0.044)
(0.291)
(0.131)
Regional
devel-
devel-
opment
opment
index
ranking
(0.142)
Chungnam
Seosan
0.127
56.449
32.668
6.062
22.436
0.947
0.079
3.589
0.069
67
Chungnam
Nonsan
-0.088
69.573
22.048
4.587
21.117
0.897
0.102
4.491
-0.163
77
Chungnam
Geumsan
-1.866
125.766
19.282
10.819
19.348
0.519
0.120
2.111
-0.307
89
Chungnam
Yeongi
1.094
74.547
27.303
13.823
21.998
0.717
0.080
4.629
0.150
62
Chungnam
Buyeo
-2.520
129.725
17.082
4.288
16.492
0.651
0.097
3.012
-0.586
124
Chungnam
Seocheon
-3.068
141.961
17.456
5.883
18.939
0.884
0.090
4.020
-0.465
108
Chungnam
Cheongyang
-3.128
166.077
18.362
5.699
16.523
0.703
0.100
2.130
-0.597
127
Chungnam
Hong-seong
-0.892
97.879
18.727
3.517
19.256
0.661
0.098
3.554
-0.390
98
Chungnam
Yesan
-2.123
115.596
19.151
5.777
19.755
0.564
0.061
3.395
-0.420
101
Chungnam
Taean
-1.418
104.555
34.708
0.980
18.858
0.593
0.078
2.498
-0.257
85
Chungnam
Dangjin
-0.131
78.772
31.946
7.684
21.968
0.614
0.071
4.436
0.036
69
Jeonbuk
Jeonju
0.050
32.797
39.459
2.001
24.034
1.951
0.196
15.132
0.585
38
Jeonbuk
Gunsan
-1.018
48.721
28.185
5.562
22.871
2.045
0.086
9.405
0.174
59
Jeonbuk
Iksan
-0.966
47.323
31.742
6.305
21.628
1.527
0.254
6.548
0.255
57
Jeonbuk
Jeongeup
-3.223
90.746
17.529
4.643
16.889
0.787
0.105
3.184
-0.531
121
Jeonbuk
Namwon
-1.960
89.384
13.505
3.907
17.022
0.687
0.113
2.040
-0.590
125
Jeonbuk
Gimje
-2.327
122.629
17.554
6.787
18.807
0.863
0.075
3.997
-0.422
102
Jeonbuk
Wanju
0.055
87.347
24.213
13.154
20.871
0.474
0.061
2.348
-0.079
74
Jeonbuk
Jinan
-1.427
159.596
12.046
3.147
15.501
0.546
0.058
1.039
-0.794
152
Jeonbuk
Muju
-2.365
149.819
17.297
1.570
16.140
0.382
0.038
0.919
-0.773
146
Jeonbuk
Jangsu
-3.801
156.500
9.755
2.982
14.876
0.660
0.032
1.107
-0.947
166
Jeonbuk
Imsil
-2.807
194.572
13.932
2.656
15.082
0.740
0.049
1.430
-0.847
159
Jeonbuk
Sunchang
-1.524
154.939
11.737
3.154
14.580
0.687
0.050
1.607
-0.813
154
Table 4-12
Continued
Population
Metropolitan city,
province
City,
county
Economy
Population
increase
rate
Aging
index
Finan- Ratio of
cial self- people
reliance
in
manufa
-cturing
(0.089)
(0.044)
(0.291)
Infrastructure
Composite
No. of
registered
passenger
cars
Road
ratio
No. of Urban
doctors land use Regional
ratio
development
index
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Regional
development
ranking
Jeonbuk
Gochang
-2.965
147.527
14.142
2.352
14.939
0.720
0.081
2.785
-0.767
145
Jeonbuk
Buan
-2.747
135.154
14.441
2.356
16.360
0.806
0.083
2.705
-0.693
140
Jeonnam
Mokpo
-0.160
33.630
33.418
1.646
20.213
6.678
0.137
26.366
0.873
24
Jeonnam
Yeosu
-1.394
45.598
31.597
5.785
19.533
1.322
0.084
6.891
0.010
71
Jeonnam
Sun-cheon
0.093
39.369
31.420
1.940
21.675
1.074
0.117
2.454
-0.031
72
Jeonnam
Naju
-1.964
117.495
15.845
5.612
17.111
0.796
0.116
3.631
-0.491
114
Jeonnam
GwangYang
0.091
30.628
47.337
9.043
25.069
1.186
0.050
6.042
0.524
43
Jeonnam
Dam-yang
-1.738
142.795
17.698
7.928
18.460
0.579
0.089
2.657
-0.441
103
Jeonnam
Gok-seong
-3.678
166.522
13.345
8.567
15.304
0.391
0.052
1.625
-0.754
143
Jeonnam
Guryeo
-2.514
144.547
15.654
1.438
15.845
0.445
0.057
1.522
-0.780
150
Jeonnam
Goheung
-3.695
193.910
11.431
3.300
12.116
0.687
0.099
2.024
-0.949
167
Jeonnam
Boseong
-2.840
177.794
16.829
3.181
14.547
0.592
0.086
2.146
-0.756
144
Jeonnam
Hwasun
-1.217
79.416
20.320
3.572
18.668
0.488
0.314
1.638
-0.249
84
Jeonnam
Jangheung
-3.121
148.246
13.441
2.323
14.463
0.519
0.087
1.865
-0.829
156
Jeonnam
Gangjin
-2.820
151.274
13.348
2.510
14.376
0.521
0.084
2.219
-0.817
155
Jeonnam
Haenam
-2.774
124.845
13.422
2.803
14.397
0.589
0.089
2.136
-0.779
149
Jeonnam
Yeongam
-0.822
90.377
16.011
19.444
18.070
0.629
0.056
4.049
-0.168
79
Jeonnam
Muan
-2.436
122.076
13.358
3.164
15.757
0.860
0.079
3.219
-0.682
139
Jeonnam
Hampyeong
-2.302
168.890
12.743
3.717
14.514
0.804
0.052
3.132
-0.782
151
Jeonnam
Yeonggwang
-3.344
106.697
23.876
3.216
16.139
0.623
0.130
3.623
-0.477
110
Policy Analysis
119
Table 4-12
Continued
Population
Metropolitan city,
province
Jeonnam
Jangseong
Infrastructure
FinanRatio of
No. of
cial self- people in registered
reliance manufac passenger
-turing
cars
Road
ratio
Composite
Population
increase
rate
Aging
index
No. of Urban
Regional Regional
doctors land use
ratio develop- development
ment
index
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
-2.462
124.903
18.067
7.737
18.298
0.638
0.054
2.436
-0.485
111
Jeonnam
Wando
-2.531
136.165
14.432
4.021
12.181
0.651
0.049
2.544
-0.830
157
Jeonnam
Jindo
-2.863
153.328
13.848
1.461
14.315
0.724
0.055
1.714
-0.856
161
Jeonnam
Sinan
-2.670
205.192
12.485
1.567
10.149
0.582
0.026
1.615
-1.082
168
Gyeongbuk
Pohang
-0.316
38.057
47.518
7.454
26.499
0.759
0.111
4.286
0.504
44
Gyeongbuk
Gyeong-ju
-0.959
63.688
31.489
10.323
24.636
0.738
0.118
2.807
0.165
61
Gyeongbuk
Gim-cheon
-1.090
83.587
24.892
7.538
21.040
0.841
0.083
1.986
-0.178
80
Gyeongbuk
Andong
-1.357
84.530
18.950
1.869
21.020
0.617
0.134
1.445
-0.388
97
Gyeongbuk
Gumi
2.088
20.294
57.653
24.180
27.003
0.799
0.110
5.466
1.155
16
Gyeongbuk
Yeongju
-1.863
84.910
18.619
3.241
20.126
0.726
0.060
2.146
-0.451
104
-2.096
107.434
19.872
10.394
21.722
0.550
0.097
2.081
-0.242
83
-2.377
131.916
15.732
3.029
18.190
0.577
0.072
1.799
-0.629
131
-2.771
122.402
15.954
2.843
18.109
0.637
0.089
1.630
-0.622
129
1.364
43.661
32.864
11.005
25.658
1.886
0.101
5.963
0.466
46
Gyeongbuk
Gyeongbuk
Gyeongbuk
Gyeongbuk
120
City,
county
Economy
Yeongcheon
Sangju
Mungyeong
Gyeongsan
Gyeongbuk
Gunwi
-3.202
234.615
15.750
6.161
18.578
0.408
0.036
1.163
-0.719
141
Gyeongbuk
Uiseong
-3.318
241.741
11.797
2.868
16.335
0.431
0.052
1.331
-0.914
163
Table 4-12
Continued
Population
Metropolitan city,
province
City,
county
Population
increase
rate
Economy
Infrastructure
Aging
index
(0.089)
Ratio of
No. of
Road
Finanpeople in registered ratio
cial selfmanufac passenger
reliance
-turing
cars
(0.291)
(0.044)
(0.131)
(0.124) (0.117)
No. of
doctors
(0.063)
Composite
Urban
land use Regional Regional
develop- developratio
ment
ment
index
ranking
(0.142)
Gyeongbuk
Cheongsong
-3.077
176.797
15.798
1.415
17.714
0.433
0.065
0.814
-0.774
147
Gyeongbuk
Yeongyang
-2.621
204.525
11.219
1.185
16.303
0.438
0.025
0.536
-0.945
165
Gyeongbuk
Yeongdeok
-2.492
174.335
11.583
3.145
15.652
0.523
0.058
1.063
-0.847
160
-2.230
210.263
14.725
3.423
19.090
0.521
0.070
1.496
-0.678
137
-1.679
135.925
18.963
17.298
23.069
0.497
0.043
2.055
-0.131
75
Gyeongbuk Cheong-do
Gyeongbuk
Gorye
-ong
Gyeongbuk
Seongju
-1.586
145.156
15.700
9.198
21.228
0.535
0.048
1.867
-0.411
99
Gyeongbuk
Chilgok
0.862
43.341
33.089
22.482
27.389
0.653
0.067
3.028
0.563
40
-3.166
205.087
13.884
2.359
15.998
0.584
0.049
1.978
-0.844
158
-3.119
191.615
11.479
3.590
15.012
0.400
0.035
0.715
-0.930
164
Gyeongbuk
Gyeongbuk
Yecheon
Bonghwa
Gyeongbuk
Uljin
-3.066
109.896
24.700
1.918
18.888
0.406
0.060
0.946
-0.527
120
Gyeongbuk
Ulleung
-1.407
111.966
15.625
4.607
15.487
1.051
0.000
1.339
-0.673
136
-0.568
18.420
66.234
19.691
30.696
2.365
0.079
11.788
1.456
10
Gyeongnam
Changwon
Gyeongnam
Masan
-0.324
40.390
38.500
4.723
23.497
1.659
0.151
5.906
0.331
50
Gyeongnam
Jinju
-0.283
44.819
31.058
3.965
22.780
0.904
0.213
3.463
0.113
64
Gyeongnam
Jinhae
3.292
37.243
32.391
6.886
25.410
2.164
0.088
11.362
0.562
41
-0.545
53.408
21.935
5.883
17.680
1.558
0.070
4.432
-0.233
82
Gyeongnam
Tongyeong
Policy Analysis
121
Table 4-12
Continued
Population
Metropolitan city,
province
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeong-nam
122
City,
county
Sacheon
Gimhae
Milyang
Geoje
Yangsan
Uiryeong
Haman
Changnyeong
Goseong
Namhae
Hadong
Sancheong
Hamyang
Geochang
Hapcheon
Economy
Infrastructure
Road
ratio
Composite
Population
increase
rate
Aging
index
Finan- Ratio of
No. of
cial self- people in registered
reliance manufac passenger
-turing
cars
No. of
Urban
doctors land use Regional Regional
develop- developratio
ment
ment
index
ranking
(0.063) (0.142)
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
-1.316
68.918
20.617
8.941
20.702
1.173
0.079
3.863
-0.167
78
5.141
22.631
42.983
15.518
24.867
1.458
0.091
7.433
0.842
27
-1.776
97.918
18.738
4.249
19.882
0.790
0.087
2.222
-0.415
100
2.502
27.277
32.431
20.322
24.097
1.100
0.073
4.280
0.535
42
2.914
28.972
44.911
18.177
23.322
1.262
0.085
3.751
0.698
35
-2.003
211.768
14.535
5.820
17.430
0.836
0.057
1.790
-0.661
134
-0.941
98.785
23.182
20.816
22.784
0.828
0.064
3.554
0.131
63
-2.330
140.504
15.863
5.977
19.538
0.588
0.098
2.635
-0.487
112
-2.377
141.558
17.278
6.705
17.120
0.976
0.062
2.414
-0.537
122
-2.802
194.596
12.927
1.556
13.914
0.794
0.065
2.671
-0.879
162
-2.257
142.842
17.169
1.931
17.121
0.628
0.056
1.678
-0.678
138
-2.364
198.799
14.252
2.803
17.002
0.512
0.030
1.187
-0.802
153
-2.196
157.701
18.061
4.052
14.584
0.488
0.058
1.201
-0.730
142
-1.470
108.853
14.671
2.793
17.988
0.468
0.072
1.298
-0.626
130
-0.983
174.458
13.463
2.566
15.694
0.551
0.044
1.282
-0.778
148
Table 4-12
Continued
Population
Metropolitan city,
province
City,
county
Population
increase
rate
(0.089)
Economy
Infrastructure
Aging
index
Ratio of
No. of
Road
Finanpeople in registered ratio
cial selfmanufac passenger
reliance
-turing
cars
(0.291)
(0.044)
(0.131)
(0.124) (0.117)
No. of
doctors
(0.063)
Composite
Urban
Regional Regional
land use
develop- developratio
ment
ment
index
ranking
(0.142)
Jeju
Jeju
1.166
36.757
24.567
1.653
24.990
2.055
0.129
3.535
0.097
65
Jeju
Seogwi-po
-0.790
57.442
16.846
1.226
22.300
1.072
0.072
2.786
-0.345
91
Policy Analysis
123
Table 4-13
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Financial selfreliance
rate
Infrastructure
Composite
Ratio of
No. of
Road
No. of
people in
register-
ratio
Urban
manufac-
ed
turing
passen-
ratio
including the
bottom 50
ger cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
No. of indices
Regional
development
ranking
Special city
Seoul
59
44
85
73
Metropolitan city
Busan
79
54
74
110
20
14
Metropolitan city
Daegu
58
41
73
31
13
19
Metropolitan city
Incheon
45
18
38
64
35
Metropolitan city
Gwangju
47
20
14
78
52
20
13
17
21
Metropolitan city
Daejeon
40
23
109
11
19
15
19
11
Metropolitan city
Ulsan
41
31
17
43
11
Busan
Gijang
County
31
68
42
30
67
43
100
63
53
Daegu
Dalseong
County
46
39
59
18
22
67
134
67
49
Incheon
Ganghwa County
67
127
122
144
100
84
123
76
115
Incheon
Ongjin
County
21
119
49
168
126
48
150
116
81
Ulsan
Ulju County
36
37
23
13
77
99
62
31
Gyeonggi
Suwon
24
15
79
24
22
35
26
93
34
16
17
15
13
22
29
22
163
89
14
21
23
SeongGyeonggi
Gyeonggi
124
nam
Uijeong-bu
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Ratio of
rate
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
manufac-
ed
turing
passen-
Urban
ratio
(0.044)
(0.291)
(0.131)
(0.124)
including the
bottom 50
ger cars
(0.089)
No. of indices
Regional
development
ranking
Gyeonggi
Anyang
32
16
10
72
54
18
Gyeonggi
Bucheon
25
10
44
87
23
69
22
28
98
113
12
30
14
11
41
63
167
33
15
28
34
36
20
37
28
28
28
26
56
88
75
93
44
43
48
12
12
23
41
107
161
28
33
148
28
32
27
36
17
11
24
152
75
10
80
20
33
25
38
89
68
110
89
65
52
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gwangmyeong
Yongin
Pyeongtaek
Dongducheon
Ansan
Gwacheon
Guri
Namyangju
Gyeonggi
Osan
10
31
46
21
18
14
18
Gyeonggi
Paju
53
39
29
18
96
154
57
37
Gyeonggi
Siheung
18
30
15
127
18
12
Gyeonggi
Gunpo
44
19
35
56
12
115
13
19
Gyeonggi
Uiwang
13
17
29
57
40
22
49
26
32
Gyeonggi
Hanam
30
43
35
67
72
80
29
48
51
Policy Analysis
125
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Ratio of
rate
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
manufac-
ed
turing
passen-
Urban
ratio
No. of indices
including the
bottom 50
ger cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Regional
development
ranking
Gyeonggi
Icheon
39
36
34
24
15
140
116
47
39
Gyeonggi
Goyang
18
21
13
121
27
21
161
24
25
15
62
67
21
25
73
129
56
47
AnGyeonggi
seong
Gyeonggi
Gimpo
33
40
12
75
136
31
26
Gyeonggi
Yangju
32
44
17
55
39
68
41
34
Gyeonggi
Yeoju
50
71
51
59
37
90
139
83
66
35
17
95
148
35
27
26
25
65
151
55
22
118
94
89
88
86
155
27
144
93
27
59
64
15
58
124
160
80
56
64
93
78
138
85
165
158
143
96
43
98
121
158
45
144
152
117
95
48
61
48
150
14
74
12
120
60
33
47
45
82
32
62
11
88
55
74
64
68
130
17
115
16
115
70
83
57
73
127
36
47
56
42
73
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gyeonggi
Gangwon
Gangwon
Gangwon
Gangwon
126
Hwaseong
Gwangju
Yeoncheon
Pocheon
Gapyeong
Yangpyeong
Chuncheon
Wonju
Gangneung
Donghae
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Ratio of
rate
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
manufac-
ed
turing
passen-
Urban
ratio
Gangwon
Gangwon
Gangwon
Gangwon
Taebaek
Sokcho
Samcheok
Hongcheon
Hoengseong
Gangwon Yeong-wol
Gangwon
Gangwon
Pyeongchang
Jeongseon
Gangwon Cheor-won
Gangwon
Hwacheon
including the
bottom 50
ger cars
Gangwon
No. of indices
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
103
73
106
146
57
105
40
137
94
72
48
53
159
53
36
58
38
68
124
91
107
139
82
132
108
160
117
81
90
95
126
102
166
47
162
105
85
116
110
51
101
159
153
151
107
151
115
145
108
105
160
85
159
133
78
99
115
137
74
167
165
163
118
140
103
79
149
90
164
97
164
109
104
74
149
136
92
154
102
153
123
91
80
161
165
103
156
74
167
132
Gangwon
Yanggu
105
77
75
147
107
153
147
166
106
Gangwon
Inje
66
70
123
154
81
168
133
168
116
114
104
101
131
111
141
166
157
126
71
105
82
105
49
152
145
155
90
29
12
21
80
20
11
26
10
17
GoGangwon
seong
Yang-
Gangwon
yang
Chungbuk Cheong-ju
Policy Analysis
127
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Ratio of
rate
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
manufac-
ed
turing
passen-
Urban
ratio
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
Chungbuk
ju
Jecheon
Cheongwon
Boeun
Okcheon
Yeongdong
Jincheon
Goesan
Eumseong
Dan-
including the
bottom 50
ger cars
Chung-
No. of indices
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
89
67
84
87
61
58
37
89
76
93
69
83
116
63
103
63
124
86
73
84
65
11
47
97
162
54
58
150
144
126
76
137
113
105
132
135
107
108
96
43
97
104
88
111
92
130
126
116
77
129
131
128
142
128
49
72
66
42
79
106
69
45
113
110
127
52
108
129
125
121
113
61
76
69
60
83
51
45
54
156
114
93
54
118
148
138
152
119
11
13
20
28
13
34
14
30
20
76
86
91
90
83
76
42
99
87
109
85
72
104
95
91
66
81
88
yang
Chungnam
Chungnam
Chungnam
Cheonan
Gongju
Boryeong
Chungnam
Asan
20
60
30
35
50
87
36
29
Chungnam
Seosan
51
65
54
61
59
52
81
70
67
128
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Composite
No. of
Road
No. of
register-
ratio
reliance manufac-
ed
rate
Ratio of
Infrastructure
turing
Urban
ratio
passen-
Chungnam
Nonsan
Geumsan
including the
bottom 50
ger cars
Chungnam
No. of indices
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
56
79
86
86
77
54
45
49
77
112
125
97
33
104
136
32
107
89
Chungnam
Yeongi
38
81
71
26
65
88
78
46
62
Chungnam
Buyeo
137
128
120
91
139
102
55
84
124
154
135
114
64
112
55
59
59
108
159
150
105
69
138
89
48
106
127
80
100
103
102
106
98
52
72
98
Chungnam
Chungnam
Chungnam
Seocheon
Cheongyang
Hongseong
Chungnam
Yesan
120
117
98
68
96
125
111
75
101
Chungnam
Taean
98
106
46
167
115
116
84
95
85
Chungnam
Dangjin
57
82
57
48
66
114
94
50
69
Jeonbuk
Jeonju
55
30
41
140
39
27
10
16
38
Jeonbuk
Gunsan
88
58
70
71
48
26
69
25
59
Jeonbuk
Iksan
86
55
58
58
71
31
34
57
163
97
113
83
136
72
44
78
121
115
95
150
97
134
94
38
110
125
Jeonbuk
Jeonbuk
Jeongeup
Namwon
Jeonbuk
Gimje
126
122
112
55
116
56
86
60
102
Jeonbuk
Wanju
54
92
80
27
80
145
110
100
74
Policy Analysis
129
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Financial selfreliance
rate
Infrastructure
Composite
Ratio of
No. of
Road
No. of
people in
register-
ratio
Urban
manufac-
ed
turing
passen-
ratio
including the
bottom 50
ger cars
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Regional
development
ranking
Jeonbuk
Gimje
126
122
112
55
116
56
86
60
102
Jeonbuk
Wanju
54
92
80
27
80
145
110
100
74
Jeonbuk
Jinan
99
149
160
114
150
128
114
150
152
Jeonbuk
Muju
129
142
117
155
143
163
149
156
146
Jeonbuk
Jangsu
168
147
168
118
156
99
157
148
166
Jeonbuk
Imsil
146
159
146
125
153
81
141
136
159
101
146
163
113
158
93
137
131
154
152
140
144
134
155
87
77
87
145
Jeonbuk
Jeonbuk
Sunchang
Gochang
Jeonbuk
Buan
142
130
141
133
140
64
75
90
140
Jeonnam
Mokpo
60
31
47
153
88
24
24
Jeonnam
Yeosu
96
52
60
66
99
35
73
32
71
52
45
62
141
70
45
34
96
72
116
118
131
70
133
69
36
66
114
53
24
27
39
23
40
135
37
43
108
136
111
45
120
122
62
92
103
166
151
156
42
152
162
130
129
143
Jeonnam
Jeonnam
Jeonnam
Jeonnam
Jeonnam
130
(0.089)
No. of indices
Suncheon
Naju
Gwangyang
Damyang
Gokseong
Table 4-13
Continued
Population
Metropolitan city,
City,
province
county
Popula-
Aging
tion
index
increase
Economy
FinanRatio of
cial self- people in
reliance manufac-
rate
turing
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
ed
Urban
ratio
No. of indices
including the
passen-
bottom 50
ger cars
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
Regional
development
ranking
Jeonnam
Gurye
136
138
136
161
146
147
120
133
150
Jeonnam
Goheung
167
158
166
106
167
92
50
112
167
Jeonnam
Boseong
148
156
125
111
159
117
70
104
144
Jeonnam
Hwasun
92
83
92
101
117
142
127
84
158
141
152
135
161
137
67
119
156
Jeonnam
Jangheung
Jeonnam
Gangjin
147
143
155
129
163
134
72
102
155
Jeonnam
Haenam
144
123
153
123
162
118
61
105
149
Jeonnam
Yeongam
77
96
128
14
124
108
122
58
79
Jeonnam
Muan
133
120
154
112
147
57
83
77
139
125
152
158
99
160
66
132
79
151
165
107
81
110
144
111
30
68
110
134
124
108
47
121
106
126
97
111
Jeonnam
Jeonnam
Jeonnam
Hampyeong
Yeonggwang
Jangseong
Jeonnam
Wando
138
132
142
95
166
101
140
94
157
Jeonnam
Jindo
149
145
148
160
164
86
124
125
161
Jeonnam
Sinan
141
164
159
156
168
121
163
130
168
Gyeong-buk
Pohang
63
42
25
50
10
78
39
52
44
84
75
61
36
33
82
33
85
61
Gyeong-buk Gyeongju
Policy Analysis
131
Table 4-13
Continued
Population
Metropolitan city,
City,
province
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Composite
No. of
Road
No. of
register-
ratio
reliance manufac-
ed
rate
Ratio of
Infrastructure
turing
Urban
ratio
passen-
Gimcheon
including the
bottom 50
ger cars
Gyeong-buk
No. of indices
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
90
87
74
49
78
59
76
113
80
Gyeong-buk
Andong
95
88
100
145
79
112
25
135
97
Gyeong-buk
Gumi
23
16
68
41
44
16
Gyeong-buk
Yeongju
111
89
104
107
91
85
112
103
104
119
109
94
34
69
127
54
108
83
131
129
134
117
122
123
92
122
131
143
121
129
120
123
107
60
128
129
34
50
52
32
16
28
46
39
46
Gyeong-buk
Gyeong-buk
Gyeong-buk
Gyeong-buk
Yeongcheon
Sangju
Mungyeong
Gyeongsan
Gyeong-buk
Gunwi
162
167
133
60
119
157
155
147
141
Gyeong-buk
Uiseong
164
168
162
119
141
151
131
139
163
155
155
132
162
127
150
103
158
147
139
162
167
166
142
149
164
165
165
135
153
164
115
149
133
118
149
160
122
165
138
103
109
135
95
134
137
106
131
99
19
46
139
146
109
75
Gyeong-buk
Gyeong-buk
Gyeong-buk
Cheongsong
Yeongyang
Yeongdeok
Gyeong-buk Cheong-do
Gyeong-buk
Goryeong
Gyeong-buk
Seongju
102
139
135
37
76
130
143
118
99
Gyeong-buk
Chilgok
42
49
50
100
98
82
40
132
Table 4-13
Continued
Population
Metropolitan city,
province
City,
county
Popula-
Aging
tion
index
increase
Economy
Finan-
Composite
No. of
Road
No. of
register-
ratio
reliance manufac-
ed
rate
Ratio of
Infrastructure
turing
Urban
ratio
passen-
Gyeong-buk
Yecheon
Bonghwa
including the
bottom 50
ger cars
Gyeong-buk
No. of indices
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
160
163
147
132
145
120
142
114
158
157
157
165
100
154
161
156
161
164
Gyeong-buk
Uljin
153
112
76
143
114
158
113
154
120
Gyeong-buk
Ulleung
97
113
137
84
151
49
168
138
136
Chang-won
70
12
23
79
22
10
Masan
65
46
43
81
43
29
21
40
50
Jinju
62
51
63
96
51
53
74
64
Jinhae
14
40
56
53
19
24
64
23
41
68
63
87
63
128
30
96
51
82
Sacheon
94
78
90
40
84
41
82
61
78
Gimhae
37
22
29
33
57
29
27
Miryang
110
101
102
92
94
71
65
101
100
Geoje
19
15
55
10
38
42
90
53
42
Yangsan
16
19
32
16
44
38
71
64
35
117
166
140
65
130
60
119
123
134
82
102
85
50
61
104
71
63
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeong-
Tong-
nam
yeong
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeongnam
Gyeong-
Ui-
nam
ryeong
Gyeongnam
Haman
Policy Analysis
133
Table 4-13
Continued
Population
Metropo-
Popula-
Aging
litan city,
City,
tion
index
county
increase
province
Economy
Finan-
Ratio of
rate
Infrastructure
Composite
No. of
Road
No. of
register-
ratio
manufac-
ed
turing
passen-
Urban
ratio
No. of indices
including the
bottom 50
ger cars
Regional
development
ranking
(0.089)
(0.044)
(0.291)
(0.131)
(0.124)
(0.117)
(0.063)
(0.142)
127
133
130
62
98
119
53
93
112
Gyeong-
Chang-
nam
nyeong
Gyeongnam
Goseong
132
134
118
56
132
51
109
98
122
Gyeongnam
Namhae
145
160
157
157
165
70
101
91
162
Gyeongnam
Hadong
123
137
119
142
131
109
121
126
138
Gyeongnam
Sancheong
128
161
143
122
135
138
159
146
153
Gyeongnam
Hamyang
121
148
109
94
157
143
117
145
142
Gyeongnam
Geochang
100
111
139
124
125
146
91
140
130
Gyeongnam
Hapcheon
87
154
151
128
148
126
144
141
148
Jeju
Jeju
37
38
77
151
26
25
31
73
65
Jeju
Seogwi-po
75
66
124
164
62
46
93
86
91
Note: 1) The ranking by index for 168 local governments is from higher to lower figures of each index. Nevertheless, the higher
the ranking in the aging index, the lower the level of development. Thus, the ranking is from lower to higher figures.
2) The composite ranking of regional development is based on the regional development index in Table 4-12 calculated by
standardizing the eight indices, multiplying by the weights, and adding them together.
134
Policy Analysis
135
analyze ripple effects into subdivisions of the construction sector as in the KDI
MRIO. There is only a modest increase in the number of analysis steps. Ripple
effects on the regional economy used in preliminary feasibility studies refer to
effects to vitalize the regional economy. Using the PCRDPCNACI MRIO is
acceptable as focus is on regions, not on industries.
Interpretation of the induced effects of GRDP (Gross Regional Domestic
Product), added value, employment, wages, etc., suggested as a result of MRIO
model analysis of ripple effects on the regional economy, involves limitations as
follows:
First, such effects do not directly translate into economic benefits. To convert
economic ripple effects from an MRIO model into national economic benefits, the
following conditions should be met: economic effects do not occur if the
concerned project is not implemented; production factors inputted in the project
are not used for other purposes if the project is not implemented; and
implementation of this project does not replace other economic activities43. It is
believed that there are not many government-financed projects that can satisfy these
conditions in Korea, where the unemployment rate is not high and land use is
intensive. Nevertheless, as policy makers consider government-financed projects
ripple effects on the economy of underdeveloped regions, they are not reflected as
economic benefits but considered in policy analysis.
Second, ripple effects on the regional economy from an MRIO model are limited
to effects caused by project implementation. They only reflect direct effects and
relevant effects that occur when government investment, an exogenous shock, is
added in a demand-driven ripple effect model. For instance, induced effects of added
value resulting from implementation of a road project only reflect effects occurring
when total project costs to conduct the project are inputted in the concerned region.
They do not reflect ex post facto effects resulting from laying of the road. To
describe the economic induced effects through an MRIO model as ripple effects on
the regional economy would be to apply an overly broad definition of these ripple
effects, but the term is still used because induced effects analyzed through an MRIO
model have been used to describe the induced effects on the regional economy.
Accordingly, if it is believed that indirect economic ripple effects from project
43
136
Adler, Hans A.(1987), Economic Appraisal of Transport Projects: A Manual with Case Studies,
Revised and Expanded Edition, the World Bank, pp.33~37.
Policy Analysis
137
Table 4-14
Example of an MRIO Structure (Two Regions, Three Industries, & Competitive Input Type)
Intermediate Demand
Output
Region L
Final Demand
Total
Region M
Consum-
Input
Industry Industry
Industry Industry
ption,
etc.
Industry
Industry
1 2 3
1 2 3
deEx-
mand
Import
Net
Total
goods
out-
receipt
put
-25
150
port
Re-
Industry 1
10 15 20
5 10 15
40
15
130
Inter-
gion
Industry 2
20 10 40
15 25 20
50
35
215
10
200
medi-
Industry 3
20 25 10
10 35 15
85
45
245
-10
250
ate
Re-
Industry 1
5 20 10
40 50 30
80
95
330
25
300
input
gion
Industry 2
25 10 30
70 30 90
70
30
355
10
-5
350
Industry 3
10 35 30
60 80 80
100
25
420
10
10
400
Added value
60 85 110
Total input
138
Table 4-15
Regional Classification
Classification
Special City
Region
Seoul
Busan
Daegu
Metropolitan City
Incheon
Gwangju
Daejeon
Ulsan
Gyeonggi
Gangwon
Chungbuk
Chungnam
Province
Jeonbuk
Jeonnam
Gyeongbuk
Gyeongnam
Jeju
Table 4-16
1101-1144
Mining
2101-2137
3101-3191
Textiles
3201-3219, 3231-3233
Clothing
Footwear
3244-3245
3301-3319
Petrochemistry, rubber
3611-3612, 3631-3668
10
Non-metallic minerals
3701-3736
11
3801-3911
12
4001-4029
13
4101-4108, 4141-4145
14
Semiconductors
4113-4114
15
4111-4112, 4115-4132
Policy Analysis
139
Table 4-16
Continued
Trial Balance Classification
16
4201-4206
17
Automobiles
4301-4307
18
Shipbuilding
4311-4313
19
Aerospace
4322
20
4321, 4323-4324
21
4401-4417
22
5101-5113
23
Construction
5201-5222
24
6101-6102
25
6201-6202
26
Logistics
27
Seaborne logistics
28
29
6401-6403
30
6501-6505
31
6601-6620
32
6701-6702
33
6801-6817
34
6911-6918
140
regional industry, the credibility of the entire model greatly depends on that of
estimated intermediate demand data. The fabrication effects approach reflects the
added value of each regional industry, but this greatly depends on the quality of
added value data.
The PCRDPCNACI MRIO model first applies the fabrication effects approach
to reflect the difference in the added value ratio of each regional industry; then, the
LQ approach to estimate the intermediate demand; and then the RAS approach to
estimate technical coefficients for adjustment.
Estimation of regional technical coefficients depends largely on the availability
of regional data. It is not an exaggeration to say that the evolution of the estimation
methods has been determined by the availability of data, and for this reason, the
credibility of a model likely depends on the quantity of regional data used, but not
on the estimation method.
Use of more regional data, however, does not guarantee greater accuracy
because the regional data is not trusted in Korea. This is because objective
comparison and evaluation is difficult without an MRIO table resulting from direct
investigation by a government institution with public confidence like the BOK.
As the model reflects the added value ratio by regional industry, it better suits the
original goal of an MRIO table than the regional product mix approach, but the
degree to which the fabrication effects approach is rectified by the RAS approach is
unclear. In other words, the fabrication effects approach reflects the difference in the
added value ratio among regions and thereby recognizes the difference in the
productivity among regions. However, all intermediate inputs uniformly increase in
the industries with a low added value ratio while all of them uniformly decrease in
those with a high ratio. By estimating the initial intermediate demand amount by the
LQ approach, the intermediate demand amount is underestimated in regional
industries where its share is lower than the national average while it becomes the
same as the national average in regional industries where its share is high. This gives
rise to the problem of disproportionality adjustment. It is not clear how much this
distortion is corrected in the RAS adjustment process.
The PCRDPCNACI MRIO model has the merits of different methods, but their
demerits become inherent in the model as well. It is significant as a new attempt, but
it is too early to assess its usefulness. This matter requires more in-depth study.
In conclusion, we cannot know when building a model which methods can better
explain the reality with regard to estimation of regional technical coefficients. Even
so, the PCRDPCNACI MRIO is very useful in that an MRIO table is written to
ascertain the difference in the production structure of different regions, though this
applies only when the data on the added value of each regional industry is credible.
Policy Analysis
141
142
Large-Sized
Medium-Sized
(77 sectors)
Small-Sized
(168 sectors)
Construction
Housing construction
Basic
(404 sectors)
Reinforced concrete/steel houses
Other houses
44
Refer to the distribution table of investment expenditures by industry when investing 100 billion
won in the road sector in Table 4-18.
Policy Analysis
143
Table 4-17
Large-Sized
Continued
Medium-Sized
(77 sectors)
Small-Sized
(168 sectors)
Construction &
Non-housing Construction
Basic
(404 sectors)
Non-reinforced concrete/steel houses
Buildings other than houses
Repair
Repair
Repair
Road facilities
Railroad facilities
Transportation Facility
Subway facilities
Construction
Port facilities
Airport facilities
Road facilities
Railroad facilities
Construction
Transportation Facility
Civil Engineering &
Subway facilities
Construction
Port facilities
Construction
Airport facilities
River anti-erosion work
Water & sewage facilities
Other types of civil
engineering &
construction
Table
4-18 Distribution of Investment Costs by Industry when Investing 100 billion won in the Road
Sector
(Unit: 100 billion won)
144
Classification
Investment Costs
7.0
Mining
12.8
0.0
Textiles
0.5
Investment costs
Clothing
0.7
Footwear
0.3
14.0
Petrochemistry
36.4
Fine chemistry
5.9
10
Non-metallic minerals
303.4
11
Primary metals
242.0
12
Machinery
10.9
13
13.4
14
Semiconductors
0.0
15
Communications devices
0.7
16
Precision instruments
2.8
17
Automobiles
5.6
18
Shipbuilding
0.0
19
Aerospace
0.0
20
0.0
21
0.4
22
4.2
23
Construction
0.2
24
31.0
25
0.0
26
Logistics
15.5
27
Seaborne logistics
2.1
28
Culture
2.7
29
Information communications
6.1
30
37.8
31
Industrial service
208.8
32
0.0
33
9.2
34
25.6
Total
1,000
Policy Analysis
145
X = ( I - CA) -1 C Y
(4-1)
For instance, on the presumption of two regions ( L , M ) and two industries (1, 2)
and the self-sufficiency rate of 70% in industry 1 of region L ,45 C Y in this formula
means that, if final demand of 10 billion won occurs in industry 1 of region L , 70%
goes into industry 1 of region L and 30% into industry 1 of region M . Ripple effects
are, therefore, measured by distributing in advance the final demand of 7 billion won in
industry 1 of region L and 3 billion won in industry 1 of region M .
45
146
This means 0.7 unit is supplied in region L and 0.3 unit in region M for one unit production in
industry 1 of region L .
X = ( I - CA) -1 Y
(4-2)
The production inducement coefficient can use both formulas (4-1) and (4-2).
Formula (4-1) distributes change in the final demand of a specific region through an
input coefficient to not only the region but also all regions and all industries and then
measures effects on production inducement. Formula (4-2) distributes the final demand
change of a specific region only to all the industries of the region using an input
coefficient to measure effects on production inducement. As such, if formula (4-1) is
used as a production inducement coefficient, the final demand change of a specific
region is distributed to the industries of other regions, so ripple effects within the region
become markedly lower than in formula (4-2). To measure ripple effects on the regional
economy, a production inducement coefficient as in formula (4-2) is generally used.
X = ( I - CA) -1 Ah Y
(4-3)
Instead of the inverse matrix of the inducement coefficient ( I - CA) -1 in formula (43), an inverse matrix that excludes a specific industry can be used.46 This only considers
the effects of a specific industry on other industries, and as the effects on its own
industry are excluded, the ripple effects can be underestimated.
About this method, refer to p121~124 in the BOKs IO analysis explanation - principles and
practice (1987).
Policy Analysis
147
V = AV ( I - CA) -1 C Y
(4-4)
The added value inducement coefficient becomes 1 in a model that does not
distinguish between domestic and overseas areas. This is because the gross
production X is as seen below from the perspective of supply and, when
multiplying both sides by AV , the added value becomes as in formula (IV-5).
X = (1 - CA) -1 CY
(4-5)
AV X = AV (1 - CA) -1 CY
From the perspective of input, the gross production X is defined as in the first
row: It becomes as in the second and third rows when written based on AV :
X = CAX + AV X
AV X = ( I - CA) X
AV = ( I - CA)
(4-6)
AV X = ( I - CA) ( I - CA) -1 CY
(4-7)
AV X = CY
Substitution of formula (4-7) into formula (4-5) produces AV ( I - CA) -1 = I .
The sum of regional added values does not become 1 in a non-competitive-type
MRIO model that distinguishes domestic products and import products. In this case,
148
the sum of the regional import inducement coefficient and the regional added value
inducement coefficient becomes 1. This means some of the effect on production
inducement resulting from change in regional final demand is regional imports and
the rest is represented as regional added value.47
The added value items include remuneration for the employed (wages),
operating surplus, consumption of fixed capital, indirect taxes, etc. To come up with
an inducement coefficient for each of them, AV of the added value inducement
coefficient is replaced with each items diagonal matrix.
3) Salaried Employment & Total Employment Multiplier
Production activity is basically made possible by combining intermediary goods
with primary factors of production like capital and labor. As the production activity
of relevant industries due to increased demand is accompanied by demand for labor,
measuring labors industrial ripple effects can provide important data for predicting
labor demand and establishing relevant plans.
The salaried employment inducement coefficient is basically calculated by the
same method as the added value inducement coefficient. Namely, it can be
calculated by combining the production inducement coefficient and the labor
coefficient. When the diagonal matrix of the labor coefficient is 1, l ( I - CA) -1 in
the formula below is the labor inducement coefficient.
l X = l ( I - CA) -1 Y
(4-8)
The labor coefficient is a coefficient that divides the amount of labor inputted in
production for a certain period (one year here) by gross production volume. As it
means the amount of labor spent to produce one unit (one million won here), it is in
a reciprocal relationship to labor productivity.
The labor coefficient can be divided into the salaried employment coefficient
and total employment coefficient according to the scope of the amount of labor
included. The salaried employment coefficient only covers salaried workers, and the
total employment coefficient covers both the employed and the self-employed and
unpaid family workers.
47
Refer to p.30~31 of the BOKs 1990 IO table (making report) (December 1993).
Policy Analysis
149
( I - CA )
-1
LL
a
=
a ML
1.126
0.628
0.512
=
0.L625
0.237
0.472
LM
a
a
MM
0.323
0.247
0.217
0.167
1.232
O LL = [2.2262.2902.005] , O MM = [2.0941.6331.615]
150
O L = O LL + O ML = [3.5993.4873.048]
O M = O MM + O LM = [3.4593.6362.339]
c. Limits of Analysis Models and Cautions to note when Interpreting Them
It is true that an MRIO model provides useful information with regard to
regional economic analysis, but it has its own limits, and the process of establishing
a model and interpretation of estimation results also has many limits.
Two criticisms can be raised due to a models own limits. First, it can be stated
that an MRIO model faces the limit of the basic assumption of an IO table for the
stability of input coefficients that products are homogeneous, and there is no
economy of scale. However, this limit is inherent to IO analysis and is not unique to
this model. Moreover, the assumption that there is no qualitative variance among
products and no economy of scale is not unusual in economic analysis. In other
words, this first criticism is not a serious issue.
The second criticism is that MRIO analysis only analyzes positive ripple effects
from project costs and cannot consider together negative ripple effects from
financing. Spending requires financing, and finances that would be invested
somewhere else are inputted into the concerned project, limiting financing for other
investments. This is the crowding out effect. The criticism is that even though
opportunity costs occur, IO analysis fails to consider them. There is definitely a
crowding out effect. However, a model that completely considers crowding-out
effects is extremely rare, and to simultaneously analyze all ripple effects, a multiregional, multi-sector model needs to be established. As very little regional timeseries data is currently available, establishment of a multi-regional, multi-sector
model is a task to be accomplished step-by-step.
Policy Analysis
151
152
Policy Analysis
153
154
included as part the willingness to pursue and preference for projects. Since the
importance of environmental issues continues to rise, there is a need to analyze
environmental impact as a separate item. It will be difficult to separately judge the
impact of project implementation on the ecosystem and the resulting attitude of local
residents toward the project. Local residents objection to the project due to
environmental issues, etc. is, therefore, analyzed in environmental impact analysis
to be reflected in evaluation.
Policy Analysis
155
projects that are partially or wholly financed by a private party, the possibility of
financing should be closely reviewed to ascertain whether they can proceed as
planned. If projects impose significant financial strains on local governments in
consideration of their fiscal condition, they can become delayed, suspended, or face
other such problems. In PPP projects where the profitability is low, selecting a
private investor and conducting negotiations can be time consuming. Even in the
case of projects funded by the government, the possibility of raising necessary funds
should be confirmed if the project costs are much higher than the given budget.
The evaluation of financing plans in the General Guidelines (fifth edition)
excludes analysis on the suitability of government support which was conducted in
the General Guidelines (fourth edition). This is because, in most projects subject
to preliminary feasibility studies, the responsible ministry requesting the study
suggests a legal and administrative basis for pursuing them, thereby justifying
government support at least for the time being and rendering confirmation of every
project for suitability of government support of little use. Also, such suitability is
different in nature from the mid-level classification of risk factors in pursuing
projects, which can cause a problem in the evaluation structure.
For projects where the suitability of government support is raised as an issue due
to their nature, this should be set as a project-specific evaluation item and be
analyzed separately from a financing plan.
B. Environmental Nature
Environmental impact analysis roughly evaluates impact from project
implementation. Environmental impact analysis does not have to be conducted for
every project. In preliminary feasibility studies, environmental impact analysis is to
ascertain in advance whether an environmental issue will occur in any step after
preliminary feasibility studies and decide whether to pursue a project accordingly,
and at the same time to raise the possibility of an environmental issue in the
following steps and encourage more in-depth analysis.
For projects with potential environmental issues, the impact of project
implementation is to be qualitatively and quantitatively evaluated through separate
consultation with specialists, prior discussion, etc.
Also, as mentioned above, the possibility of local civil complaints due to an
environmental issue when the project is implemented should be analyzed not in the
156
willingness to pursue and preference for projects item, but in the environmental
impact analysis item.
Mid-Level
Classification
Example
Increased fairness between Yeongnam and Honam regions,
Balanced regional
development
Fairness
pursue projects
Propriety in methods of
projects
Policy Analysis
157
Table 4-19
Continued
Mid-Level
Classification
Evaluation Items
Example
Possibility of technically difficult sections occurring, possibility of
Technical feasibility
Suitability of government
support
Evaluation of projects
special characteristics
Unquantifiable
benefits/additional effects
158
CHAPTER 5
Comprehensive Evaluation: AHP Method
to comprehensively evaluate the feasibility of a project which has a high BCR but is
not consistent with high-level plans.
The second difficulty is about combining the same qualitative analysis items
when they have different scales. For instance, if the BCR in a government-financed
project is 0.9, which is less than 1.0, but the project can generate a significant
number of jobs, say 2,000 jobs, it is difficult to decide whether to go ahead with the
project or cancel it and by which standards.
The third difficulty is to both ensure consistent evaluation and reflect a projects
specialty. Among projects subject to preliminary feasibility studies are national
strategy projects, cultural asset protection projects, and the like where special
evaluation items, not quantified within the framework of economic feasibility
analysis, are much more important. Policy analysis in preliminary feasibility studies
reflects such specialty in the framework of evaluation. There is, however, the risk
that consistency in evaluation with other projects may decline if the special nature of
a project assumes too much weight in comprehensive evaluation. For the
preliminary feasibility study framework to retain its value as a general analysis
framework, the impact that the special nature of a project has on determining
whether to pursue it should be objectively evaluated.
The fourth difficulty is to collect and reconcile the opinions of multiple
evaluators participating in comprehensive evaluation and draw a final conclusion.
When there is only one evaluator performing comprehensive evaluation, only the
feasibility of such judgment matters. But when putting together several peoples
opinions, issues arise such as how to come up with a representative comprehensive
judgment and how to reach a final decision when individual researchers have
opposing opinions on whether to pursue a project.
Multi-criteria analysis is suggested to overcome these difficulties. This is a
decision-making method that considers multiple attributes to devise an optimal
alternative that satisfies multiple objectives. The comprehensive evaluation of
preliminary feasibility studies also considers multiple quantitative and qualitative
evaluation items to distinguish projects that are feasible in terms of both economy
and policy.
To find the most suitable methodology for comprehensive evaluation as part of
preliminary feasibility studies, KDI compared and evaluated various methods of multicriteria analysis, and adopted the Analytic Hierarchy Process (AHP) method. It has
adjusted and applied the AHP method in a way that suits preliminary feasibility studies.
160
49
50
This term represents how alternatives are evaluated according to the evaluation criteria and is called
alternatives preference, performance, attractiveness, etc. according to the need.
This term represents the subject by which the preference of alternatives is compared and is called
criteria, attributes, elements, etc. according to the need.
Cases using the AHP method around the world can be found on the web site of Expert Choice at
http://www.expertchoice.com/ and domestic cases at http://www.expertchoice.co.kr/.
161
51
162
Refer to the AHP analysis process under Section 2 of this chapter for the detailed guidelines on how
to conduct each step.
Feedback
Drawing a comprehensive decision and policy suggestions (concluding)
3. Evaluator Selection
A preliminary feasibility study team consists of a project manager and multiple
specialists, and their opinions are reflected in comprehensive evaluation to have
group decision-making characteristics. The AHP method is a proper methodology
not only for individuals decision-making but also as an aid to group decisionmaking to put together group members opinions and come to a final decision.
In group decision-making, the selection of group members directly impacts the
decisions made, so evaluators should be carefully selected to comprehensively
evaluate preliminary feasibility by the AHP method. Evaluators to perform
comprehensive evaluation of preliminary feasibility should satisfy the following two
conditions:
First, evaluators should be specialists with sufficient knowledge about the
concerned project. They should be knowledgeable about the purpose of the project,
requirements to meet the purpose, project details, relevant areas, etc. and be in a
position to predict the projects socio-economic and policy ripple effects.
Second, they should have objectivity to evaluate government-financed projects
from the perspective of the public interest. Even when one has specialized
knowledge, thereby meeting the first condition, he may distort the decision-making
if he has a personal interest in the project, with the result that the ultimate decision
does not maximize the public interest.
Parties involved in government-financed projects can be divided into the
following four groups: The first is the group of public officials, which includes those
of the ministry of the central government responsible for the concerned project; the
budget authorities that mediate different interests among ministries and set priorities
among projects to assign a budget; and the local government of the city and province
or the city, county, and gu district in the region where the project will be
implemented. The second is the group of researchers in charge of governmentfinanced projects, which includes those at the KDI performing preliminary
feasibility studies; professors or researchers of research institutes in the concerned
field; researchers of the KDI PIMAC (Public and Private Infrastructure Investment
Management Center) responsible for preliminary feasibility studies; and researchers
of private companies like engineering companies performing technical research and
163
consultation, etc. The third is local residents living in the region affected by the
implementation of the project. The fourth is interest groups with interests in the
project.
Among these, those who best satisfy the professionality and objectivity
conditions required of evaluators of AHP-based comprehensive evaluation are
central government officials responsible for budgets, projects managers of the KDI,
researchers of the KDI PIMAC, professors in relevant fields, etc. Ultimately, these
Guidelines excluded public officials responsible for budgets and included as
evaluators researchers of private companies responsible for the technical part of
preliminary feasibility studies. Public officials responsible for budgets are excluded
because the comprehensive opinion of preliminary feasibility studies is that of
participating researchers, and the budget authorities that decide the preliminary
feasibility of projects have an opportunity to finally and directly reflect their opinion.
Researchers of private companies in relevant fields like engineering are included to
reflect the fact they are not only part of preliminary feasibility studies but also
participate in social decision-making in various forms. Interested parties affected by
government-financed projects like local residents and interest groups are excluded as
they are believed not to be in a position to objectively judge the interests of all of
society. Nevertheless, the various voices of interested parties in a diverse society are
reflected in the decision-making process through various channels, which affects the
political feasibility of project implementation. In consideration of this reality,
evaluators in comprehensive evaluation are required through the AHP method to
comprehensively evaluate the impact of project implementation on regional
development to reflect the concerned regions opinions. They must consider, for
example, the importance of regional development on the feasibility of a project; the
demand of local residents and local governments for project implementation; ripple
effects on the regional economy from project implementation; and development of
less developed regions.
To reflect this, preliminary feasibility studies usually had three or four evaluators
participate in AHP analysis for individual projects. However, this was cited as
problematic in that one evaluator in such a small group could unduly bias the overall
decision-making. These Guidelines, therefore, call for a group of seven or eight
researchers to include more KDI evaluators and separate reviewers in AHP
evaluation. The highest and lowest scores given by any two evaluators are excluded,
and the results from the remaining five or six evaluators are used to come up with a
weighted sum.
164
1. Conceptualizing
The first step of AHP analysis is conceptualization to form a conceptual
framework about evaluation including its goal, evaluation items, alternatives,
restrictions, evaluators, and interested parties. This conceptualization process allows
evaluators to better understand the overall project like its characteristics and issues
and to share information and critical thinking about the project. This step should be
carried out at the early stage of a preliminary feasibility study to ensure clear
understanding of the project along with the rest of the study.
Brainstorming is often done for efficient and effective conceptualization. It is a
group creativity technique to uncritically enumerate as many considerations as
possible about the concerned project and consider them one by one.
Preliminary feasibility studies entail the two following steps of brainstorming:
The first step is brainstorming at the level of individual projects to increase the
understanding of them and know about their characteristics through meetings among
the project manager and joint research teams, visits to the responsible ministry and
involved agencies, and visits to the concerned region. The second step is
brainstorming at the level of all the projects of the corresponding type. The KDI
preliminary feasibility study management team discusses the research results of the
project with all the researchers participating in projects of the same type to find
issues that are not found at the level of individual projects. This provides an
opportunity to hear expert opinions from researchers performing preliminary
feasibility studies on relevant or similar projects to ensure exchange of valuable
information.
This two-step brainstorming allows the project manager to obtain information to
comprehensively understand projects. The first type of brainstorming is conducted
through official and unofficial procedures under the supervision of the project
manager. The second type is performed under the supervision of the KDI
preliminary feasibility study management team that comprehensively coordinates
and manages preliminary feasibility studies.
52
For details on AHP analysis, refer to the Study to Supplement Comprehensive Evaluation Using
AHP of the General Guidelines for Preliminary Feasibility Studies (fourth edition).
165
2. Structuring
Next is structuring to review evaluation items identified at the conceptualization
step and finalize evaluation standards, gather them into homogeneous groups, and
hierarchize these groups at an appropriate level.
Evaluation items identified at the conceptualization step can vary in terms of
importance and scope, ranging from the trivial to the important and from the detailed
to the comprehensive. Also, as no terms were precisely defined in advance,
evaluators may have different understandings of the same terms. For instance,
economic feasibility analysis can mean cost-benefit analysis, and in some cases, can
include aspects like ripple effects on the regional economy. As such, to finalize
evaluation standards, the meaning of identified evaluation items should be clearly
defined first to minimize potential for confusion and misunderstanding.
Once evaluation items for comprehensive evaluation are finalized, it is time to
gather items with different levels of importance and scopes into homogeneous groups
and stratify these groups at an appropriate level. In general, the items at a low level
become detailed evaluation standards that concretize high-level items. At the highest
stratum is comprehensive evaluation of preliminary feasibility, the final goal of
decision-making. Preliminary feasibility is evaluated based on the results of economic
feasibility analysis and policy analysis. Policy analysis involves basic evaluation items
and project-specific evaluation items: basic evaluation items are those included in any
preliminary feasibility study, and project-specific evaluation items are those which
should be given due consideration in evaluating the concerned project.
These Guidelines define the basic structure of AHP analysis in preliminary
feasibility studies as in Figure 5-1. The final goal of AHP analysis is to evaluate the
feasibility of projects. The first stratum consists of economic feasibility analysis,
policy analysis, and balanced regional development analysis. The second stratum is
of consistency with policy and willingness to pursue projects; risk factors in
pursuing projects; and evaluation of projects special characteristics (mid-level
classification) comprising policy analysis. The third stratum is of the detailed
evaluation items under the mid-level classification of policy analysis, and those
under balanced regional development analysis.
These Guidelines partially changed the stratification system of the basic AHP
structure in preliminary feasibility studies from the previous General Guidelines
(fourth edition). Balanced regional development analysis, which had been included
in policy analysis in the previous guidelines, was moved to the first stratum. It was
first applied to preliminary feasibility projects in 2007 due to change to the 2006
166
Operating Guidelines for Preliminary Feasibility Studies and was reflected in these
Guidelines.53
The AHP structure separates items of which evaluation is connected, and this may
render focusing on evaluation items difficult for evaluators who are unfamiliar with AHP
analysis. Therefore, the previous guidelines set up an AHP structure with the evaluation
items of three mid-level classifications and project-specific evaluation items according
to evaluation details. These Guidelines adopted the meaning and operation of projectspecific evaluation items without change from the previous guidelines.
Figure 5-1
First
Stratum
Economic feasibility
analysis
Consistency with
Second
Stratum
policy and
Risk factors in
determination to
pursuing project
pursue project
characteristics
Implementation of a project
Evaluation of
projects Special
Possibility of financing
Projects preparedness
53
Evaluation
Alternative
Third
Stratum
Balanced regional
development analysis
Policy analysis
Non-implementation of a project
In case of R&D projects, the first stratum includes technical analysis items instead of balanced
regional development, and balanced regional development is placed under policy analysis of the first
stratum.
167
Project-Specific Evaluation
Items
Evaluation
Item
1
Improving driving
safety
Evaluation Details
Sections with less than a 400m curve radius exist intermittently along the
railroad of which design standard is fourth grade. Even sections with a 250m
radius span 10.5km, making improvement of driving safety urgent.
Reducing losses
due to service
due to rockslides, roadbed loss, etc., which in turn prevents road congestion and
disruption
The KDI preliminary feasibility study management team reviews whether the
structure and evaluation items set by the study team are proper and suggests possible
additional evaluation items to the study team.
54
55
168
There are also other AHP axioms like reciprocality and expectation. Under the reciprocal axiom,
decision makers should be able to pair and compare two items within the same stratum and express
the strength of preference. This strength of preference should satisfy the reciprocal condition. For
instance, if A is regarded to be x times as important as B, it means B is 1/x times as important as A.
The expectation axiom is based on the assumption that the stratums should comprehensively include
matters about the goal of decision-making.
Jo, Geuntae, Jo, Yonghyeon, and Hyeonsu Kang, 2003, Analytical Hierarchy Decision-Making,
Donghyeon Publishing Company, Seoul, Korea, p.4
3. Weighting
This step is where the level of relative importance is determined among
evaluation items at each stratum of the hierarchy structure. Evaluators repeatedly
answer questions that compare the relative importance (or preference) between
evaluation items regarding all the pairs of two evaluation items belonging to the
same group and stratum. This pair-wise comparison process represents evaluators
judgment as verbal expressions and grants quantified scores corresponding to such
expressions. Relative evaluation through pair-wise comparison requires a credible
evaluation scale. This scale should be set in a scope that can reflect the maximum
differences that humans tend to sense. The AHP method uses a scale of nine points
as a basic type based on research results in the cognitive psychology area.
Table 5-2
Quantitative scoring
Extreme preference
Strong preference
Weak preference
Equal preference
169
As the weights of economic feasibility analysis and policy analysis at the highest
stratum have a big impact on the weighted sum, the previous guidelines set the
scope of preliminary weights (45%-56%) for economic feasibility analysis to reduce
motivational bias in case of road and railroad projects.
These Guidelines set the calculation scope of weights for different analysis areas
as in Table 5-3 according to the change in the 2009 Operating Guidelines for
Preliminary Feasibility Studies:
Table 5-3
Classification
Economic
feasibility
Technical
feasibility
Policy
feasibility
Balanced
regional
development
25~35%
15~30%
Construction project
40~50%
R&Dinformatization
30~50%
25~50%
50~70%
-
50~75%
For the weights of low-level evaluation items, Saatys nine-point scale is used to
measure the relative importance between two items through pair-wise comparison
and ultimately estimate the relative weights among the items. When an evaluator
performs a pair-wise comparison a total of n C 2 times for n number of evaluation
items in one level, he can know the actual relative weights, and using these,
compose the following pair-wise comparison matrix Ann :
w1 / w1
w / w
A = aij = 2 1
M
wn / w1
[ ]
w1 / w2 L w1 / wn
w2 / w2 L w2 / wn
M
wn / w2 L wn / wn
(5-1)
where aij that comprises matrix A is the estimate of wi / w j , the relative weight
of element i to element j . Matrix A is a reciprocal matrix where the element
values of the principal diagonal all become 1 (a ji = 1 / aij ) .
When multiplying matrix A by column vector w = (w1 , w2 ,LL, wn )T , the
weight that represents the level of relative importance among evaluation items, it
becomes formula (5-2).
170
w1 / w1
w / w
2 1
M
wn / w1
w1 / w2 L w1 / wn w1 nw1
w2 / w2 L w2 / wn w2 nw2
=
M M M
wn / w2 L wn / wn wn nwn
A w = n w
(5-2)
(5-3)
Here n is the maximum eigenvalue of matrix A and the number of rows (or
columns). Formula (5-3) is an eigenvalue problem to calculate a non-zero value
from a series of n number of simultaneous equations. The w value calculated
from formula (5-3) is used as a weight vector by evaluation item.
Matrix A is calculated based on pair-wise comparison by determining the relative
importance of elements above the diagonal, using the level of importance of elements in
each row as 1. If the original aij of matrix A obtained from pair-wise comparison has
the value of wi / w j , cardinal consistency should obtain. In other words, aij a jk = aik
should be valid. The meaning of aij a jk = aik is that if i is thought to be x times as
important as j and j is thought to be y times as important as k , i is evaluated to
be x y times as important as k . However, it is difficult to maintain such consistency
completely in actual answers, so there is a need to verify the cardinal consistency of
matrix A . If answers to pair-wise comparison do not maintain complete consistency,
their credibility can be questioned.
In AHP analysis, the degree of consistency in answers is represented as an
inconsistency ratio. An inconsistency ratio of zero means the answerers keep
perfect consistency in pair-wise comparison. According to Saaty, if the
inconsistency ratio is less than 0.1, pair-wise comparison is judged to have rational
consistency, and if it is less than 0.2, an acceptable level of inconsistency is
recognized. If the ratio is 0.2 or higher, consistency is lacking, suggesting the need
for re-study. These Guidelines set the maximum allowable inconsistency ratio at
0.15, and answerers who exceed the 0.15 ratio are to increase consistency through
feedback.
4. Scoring
This step is to score preferences for alternatives based on each evaluation item.
Table 5-4 shows scoring standards for preliminary feasibility studies. From among
171
Evaluation Item
Scoring Standards
Remarks
n The higher the BCR, the higher
the project implementation
score.
Ripple effects on
the regional
economy
GRDP
Determination to
pursue projects
and preference
Projects
preparedness
Environmental
nature
172
During the scoring process, special care should be taken to ensure that scoring of
specific evaluation items is independent from that of others. For instance, a general
attitude toward project feasibility should not be reflected in the scoring of individual
evaluation items. The evaluation items of regional development and ripple effects on
the regional economy have different scoring standards, but their scoring is often
connected because they belong to the same mid-level classification: balanced
regional development. One of the strengths of the AHP method is increasing
information processing ability of humans in that it determines whether to pursue a
project based on one characteristic by evaluation item.
As in the step of setting up weights, AHP analysis in preliminary feasibility
studies is done to learn the relative suitability between an alternative to implement a
project and an alternative not to implement a project through pair-wise comparison
based on each evaluation item, and perform scoring. In principle, Sattys 9-point
scale is used as a scoring scale here too. Nevertheless, the following two
considerations should be made in scoring.
First, a problem arises in evaluating the relative suitability of an alternative to
implement a project and an alternative not to implement a project when scoring the
evaluation items of possibility of financing and environmental nature, which are
not problematic in most projects. For instance, it should be determined whether to
give a score of 9 points for the suitability of an alternative to implement a project in
terms of environmental nature if there is no environmental issue when the project is
implemented, or give 1 point to be neutral with an alternative not to implement a
project. In the case of a project to lay a short national road with no problem of
financing, there can be a problem with evaluation of the suitability of an alternative
to implement the project. The AHP analysis of preliminary feasibility studies sets
the maximum score of possibility of financing and environmental nature at 1 in both
cases. This means that the fact there is no problem with environmental nature or
financing does not facilitate implementation of the project but does not negatively
impact its implementation.
Second, standard scores are granted to quantified evaluation items to ensure
consistency in the evaluation of different projects. These Guidelines have standard
score conversion formulas for economic feasibility analysis and the regional
development index where consistent evaluation is especially required. Economic
feasibility analysis uses cost-benefit analysis in all preliminary feasibility studies to
resolve the issue of researchers making different judgments about the same BCR.
The following standard score conversion formulas are used for the BCR and
regional development index:
173
5.11532 ln( B / C ) + i
B / C 1 i = 1,
(5-4)
B / C < 1 i = -1
(5-5)
a 0 i = 1,
a < 0 i = -1
5. Synthesizing
This step entails calculating the weighted sum of each alternative by multiplying
the weight of each evaluation standard by the score of alternatives for each standard.
An alternative with the highest weighted sum from among alternatives compared is
chosen by the AHP model.
As mentioned in the discussion of evaluator selection, comprehensive evaluation
of preliminary feasibility by the AHP method has a group decision-making
characteristic. As such, a process is necessary to combine the weights of evaluation
items, scores of alternatives, and weighted sums used and given by individual
evaluators into the evaluator groups common weights, scores, and weighted sums.
174
6. Feedback
Feedback is another feature of AHP analysis that renders it more useful. This
review process provides respondents with low consistency in their answers with
information on inconsistency and allows them to perform decision-making again to
reduce inconsistency in decision-making. If a decision-maker fails to properly
answer formalized questions, the AHP hierarchy structure should be reconsidered.
This is also true when the definition and explanation of any element comprising the
AHP hierarchy structure is wrong. If the degree of inconsistency is severe and
consistency does not improve in the feedback process, the hierarchy structure of
evaluation items needs to be reorganized or the concepts of stratums and elements
need to be defined or explained again before an AHP survey is conducted again.
In preliminary feasibility studies, data for AHP analysis is collected through two
structuralized questionnaires: the structure questionnaire and answer questionnaire.
This data collection method involves risk that a deviation may occur depending on the
evaluators level of understanding of the AHP method, evaluation items, prior attitude
toward the projects, etc. Of course, the KDI preliminary feasibility study team explains
the AHP method in detail to all team members and has in-depth discussions to build up
an AHP structure. Nevertheless, it is true that the AHP method entails restrictions in
communication for decision-making, as a tool that supports decision-making by experts,
compared to direct AHP analysis by researchers
When consistency is high in decision-making as a result of AHP analysis, for
instance, when all evaluators judge that it is appropriate to go ahead with or reject a
project, it is not difficult to draw a conclusion on the feasibility of a project despite
the above limitations of the AHP method. There are cases, however, where the AHP
score of one evaluator is very high and adversely affects the overall scoring results,
despite the fact that the evaluators are split 2:2 or 1:3. In such cases and other cases
where the robustness of decision-making is low, there is a need for an additional
175
7. Concluding
The last step of the AHP method is to choose between an alternative to
implement a project and an alternative not to implement a project based on weighted
sums drawn from feedback, and to come up with policy suggestions.
The final deliverable from AHP analysis is the weighted sum of an alternative to
implement a project and an alternative not to implement a project, each calculated
by multiplying the weight of each evaluation standard by the scores of the
alternatives for each standard. Under the previous guidelines, if the project
implementation alternative receives a higher weighted sum (higher than 0.5) than
the alternative not to implement a project, the project was considered feasible. This
mechanical way of drawing a conclusion was instituted because the final results of a
preliminary feasibility study are basic data to be used for a binary decision as to
whether or not to allocate a budget to pursue a project.
However, there are limitations as follows when judging whether to implement a
project based on AHP analysis results: the first is when evaluators opinions do not
coincide. In particular, when their opinions are divided into 2:2, though the weighted
176
sum of AHP analysis produces a score indicating whether or not to implement a project,
it is difficult to conclusively determine whether or not to pursue the project without
consensus among the evaluators. In such case, rather than making a binary decision, it is
desirable to state each evaluators opinion and the reasons therefor in the report.
The second is when the difference between the alternative to implement a project
and the alternative not to implement a project based on their weighted sums is
insignificant, with the result that there is no robustness in decision-making. Often
asked when deciding whether or not to implement a project based on an AHP
weighted sum is whether the difference between AHP weighted sums of 0.51 and
0.49 is big enough to make a binary decision about a projects feasibility. The
previous guidelines required a binary decision despite the fact that this question
cannot be stated with confidence because the ultimate goal of preliminary feasibility
studies is to ascertain whether or not the project is feasible. Nevertheless, the
previous guidelines tend to rely excessively on AHP analysis results despite the
limits of AHP analysis.
In consideration of this, these Guidelines establish a grey area as follows to
ensure a cautious approach in making a final decision:
0.5 - 0.05 < AHP weighted sum < 0.5 + 0.05,
Namely, 0.45 < AHP weighted sum < 0.55
The grey area refers to an area where the weighted sum may change if the
researchers change. If the AHP score falls in a grey area, the researchers need to take
a cautious approach in making a comprehensive conclusion through AHP analysis.
There is also a need to change this grey area according to the level of
consistency among evaluators opinions. We can assume some level of confidence
because coincidence in the opinions of the evaluators means that the evaluators
population mean is not very different from the sample mean. However, when their
opinions do not coincide, their population mean can be very different from the
weighted sum. Accordingly, it is necessary to establish a wider grey area if the
consistency among evaluators opinions is lower. In consideration of all this, a grey
area is to be applied according to the following principles:
First, when all of four evaluators agree, their opinions are combined to come up with
a comprehensive opinion depending on whether the AHP score is higher than 0.5.
Second, if they are divided by 3:1, a confidence interval of 84% is to be applied.
If the sample mean is higher than 0.55, the project is considered to be feasible, and if
the AHP score is lower than 0.45, the project is considered to be unfeasible. If the
177
AHP score is no lower than 0.45 and lower than 0.55, the interpretation is that it falls
in the grey area.
Third, if they are divided by 2:2, a confidence interval of 95% is to be applied. If
the AHP score is higher than 0.58, the project is considered to be feasible, and if the
AHP score is lower than 0.42, the project is considered to be unfeasible. If the AHP
score is in between, the tone of results should be brought down and a grey area
acknowledged, and a conclusion should be drawn cautiously.
If the ratio of evaluators for and against project implementation is 3:1 and the
AHP score of the alternative to implement the project is lower than 0.45, or the ratio
is 1:3 and the AHP score of the alternative to implement is higher than 0.55, then
one evaluators judgment throws excessive weight. This cannot be seen as decisionmaking where a consensus was established through sufficient discussion. In this case,
the feedback process should be performed so that evaluators achieve a consensus
through group dynamics management. If the same result occurs even after feedback,
a conclusion should be cautiously drawn.
Table 5-5
Weighted Sum
Implementation:
Non-Implementation
0.55 AHP
4:0
Feasible
Feasible
3:1
Feedback
Very cautious
Slightly cautious
Feasible
AHP<0.42
2:2
Not feasible
AHP>0.42
AHP>0.58
Cautious
Cautious
Slightly cautious
Feasible
AHP<0.58
Slightly cautious
1:3
Not feasible
Slightly cautious
Very cautious
Feedback
0:4
Not feasible
Not feasible
Note: 1) Implementation: non-implementation refers to a ratio of evaluators deciding to implement a project to those deciding not
to do so (based on four persons).
2) AHP refers to the AHP weighted sum of the project implementation alternative
3) The - means that nothing is applicable.
178
clear that the score falls in the grey area and use a reduced tone or be cautious when
making a conclusion. The more divided the opinions, the more cautious the
conclusion should be.
The last step in a preliminary feasibility study is to write summary tables of the
study, include them in a preliminary feasibility study report, and submit relevant
files to the KDI preliminary feasibility study management team. The summary tables
can show all the contents of the study in a condensed and concise way. Having the
tables consistent with the input formats of the preliminary feasibility study database
which has been built since 2004 can facilitate the construction of the database. The
summary tables to be included in a preliminary feasibility study report and computer
data to be submitted to the KDI preliminary feasibility study management team are
as follows:
179
Classification
Alternative
Alternative
n Line that goes via Yemi, Jungnyeom, and
Project
description &
scale summary
Project costs
Main contents
(within 2,000
letters)
33.200km
18.900km
33.200km
18.640km
BCR
0.34
0.47
NPV
IRR
Feasibility
No
No
Optimum
No
Yes
AHP score
0.452
Note: Regarding feasibility, it is the feasibility of an alternative comprehensively evaluated (economic feasibility, policy aspects,
etc.) by the study team, and there can be multiple feasible and infeasible alternatives. Regarding the optimum, it is an
alternative judged to be the best (even when it is not feasible) from among those considered by the study team, so there
should be only one alternative falling under this item.
180
Summary
Classification
Description
Project region
Sub region
Responsible party
Financing method
Project period
Project purpose
(within 500 letters)
2010
n Flood damage and disruptions to safe service occur every year due to the steep slopes
and curves of the mountainous region and deterioration of facilities like bridges.
n Disaster prevention can reduce restoration costs for flood damage and ensure safe
railroad operation.
Note: All the resulting amounts are calculated to the unit of 1 million won and recorded in the unit of 100 million won to the
second decimal place. For instance, 72.035 billion won is expressed as 720.35.
Summary
Classification
Description
Base year
2004
Analysis period
30
Discount rate
6.5
Main
assumptions
(Within 4,000
letters)
n Demand is estimated and benefits are calculated until 2031, the final target year in the KTDB network
and O/D. The annual benefits outside the target years are calculated using the interpolation method,
and benefits and costs after 2031 are supposed to be the same as the values of 2031.
n As most of the line of this project will be tunnels, no cost to restore flood damage is assumed to
occur after the implementation of this project in the calculation of the benefit of flood damage
reduction.
n For benefits from reductions in maintenance and improvement costs, present value conversion is
done to calculate an average mean only in projects where no more spending will be required
when this project is implemented based on data on maintenance and improvement costs inputted
before (the detailed items do not overlap with maintenance costs calculated under the cost
estimation of Chapter IV).
n For benefits from sale of sites to be closed, tracks and streetcar tracks need to be removed, but
their main materials, rails, and steel will be sold along with wooden railroad ties. As a result,
separate removal costs are not considered.
181
Summary
Classification
Description
(Example omitted)
Summary 5
(Example omitted)
(Example omitted)
(Example omitted)
(Example omitted)
(Example omitted)
(Example omitted)
Environmental nature
(Example omitted)
182
Summary 6
Summary 6-1
Evaluator 1
0.470
0.450
0.500
0.500
0.400
0.500
0.450
Policy analysis
0.317
0.300
0.250
0.350
0.350
0.350
0.300
0.143
0.077
0.114
0.155
0.250
0.223
0.043
0.114
0.058
0.095
0.103
0.219
0.186
0.032
0.030
0.019
0.019
0.052
0.031
0.037
0.011
0.063
0.031
0.023
0.059
0.050
0.090
0.129
Possibility of financing
0.037
0.024
0.006
0.044
0.006
0.068
0.107
0.027
0.008
0.017
0.015
0.044
0.023
0.021
0.111
0.191
0.114
0.136
0.050
0.037
0.129
0.088
0.143
0.085
0.108
0.044
0.027
0.107
0.022
0.048
0.028
0.027
0.006
0.009
0.021
0.213
0.250
0.250
0.150
0.250
0.150
0.250
0.142
0.167
0.167
0.100
0.167
0.100
0.167
0.071
0.083
0.083
0.050
0.083
0.050
0.083
Inconsistency ratio
0.007
0.033
0.016
0.033
Evaluation Items
Note: When regional balance is separated, the weights of the level of regional development and ripple effects on the regional
economy under the classification of balanced regional development are set at 2:1.
Summary 6-2
Evaluator
Decision to Implement
Comprehensive
0.452
0.548
Evaluator 1
0.495
0.505
Evaluator 2
0.466
0.534
Evaluator 3
0.426
0.574
Evaluator 4
0.442
0.558
Evaluator 5
0.454
0.546
Evaluator 6
0.440
0.560
183
Summary 7 Conclusion and Policy Suggestion for Mountainous Railroad Improvement Project
Classification
Description
(Example omitted)
(Example omitted)
n
n
184
185
186
Acronyms
AHP
BCR or B/C
Benefit-Cost Ratio
BOK
Bank of Korea
BOO
Build-Own-Operate
BOT
Build-Operate-Transfer
BTL
Build-Transfer-Lease
BTO
Build-Transfer-Operate
CAM
CAPM
CCL
CVM
GRDP
IRR
ITS
KDI
KOTI
KTDB
KWRC
LQ
Location Quotient
MEST
MDL
MLTM
MOPAS
MOSF
MRIO
Multi-Regional Input-Output
NPV
OMB
O/D
Origin/Destination
O&M
P/A
Production-Attraction
PB
Payback Period
PCNACI
PCRD
PFI
PFS
PI
Profitability Index
PIMAC
PPP
Public-Private Partnerships
PSC
RFP
RSF
TAZ
TPC
VAT
VfM
WACC
WSS
WTP
Willingness to Pay
YTM
Yield to Maturity
Acronyms
187
References
Adler, Hans A, Economic Appraisal of Transport Projects: A Manual with Case Studies, Revised and
Expanded Edition, the World Bank, pp.33-37, 1987.
Bank of Korea, IO Analysis Explanation - Principles and Practice pp121-124, 1987.
____________, 1990 IO table (making report) pp30-31, 1993.
Gollier, Christian., Discounting an Uncertain Future, Journal of Public Economics, Vol.85, pp.149166, 2002.
Jo, Geuntae, Jo, Yonghyeon, and Hyeonsu Kang, Analytical Hierarchy Decision-Making, Donghyeon
Publishing Company, Seoul, Korea, p.4, 2003.
KDI, Study to Revise and Supplement the Sectoral Guidelines for Preliminary Feasibility Studies for
Road and Railroad Projects (fifth edition), 2008.
____, Preliminary Feasibility Study on Projects to Build Three Bridges between Islands and between
Islands and the Mainland in Sinan County, 2003.
____, Study on the Sectoral Guidelines for Preliminary Feasibility Studies for Port Projects, 2000.
____ , Study on the Sectoral Guidelines for Preliminary Feasibility Studies for Airport Projects,
2000.
____, Study on the Methodologies of Preliminary Feasibility Studies for Health and Welfare Projects
____, Study on the Sectoral Guidelines for Preliminary Feasibility Studies for ICT Projects
____, Study to Amend and Supplement General Guidelines for Preliminary Feasibility Studies (fourth
edition), 2004.
____, Direction and Strategy of Regional Development Policy, 2008.
Kim, Donggeun, Cost-Benefit Analysis, Parkyoungsa, Seoul, Korea, 2008.
Ministry of Land, Transport and Maritime Affairs, Long-Term Comprehensive Plan on Water
Resources (Water Vision 2020), 2006.
_______________, Evaluation Guidelines for Transportation Infrastructure by MLTM, 2007.
_______________, Land Business Handbook, 2007.
_______________, Housing Business Handbook, 2008.
_______________, Investment Evaluation Guidelines for Transportation Facilities, 2007.
_______________, Work Guidelines for Regional Development Projects, 2003.
_______________, Work Guidelines for Regional Development Projects, 2006.
188
Ministry of Planning and Budget, Basic Plan for PPP Projects, 2004.
Ministry of Public Administration and Security, Development of Selection Indices of Less Developed
Regions, 2004.
_______________, Guidelines for Projects on Regions for Revitalization, 2004.
_______________, Basic Statistical Survey Guidelines for Designation of Remote Areas for
Development, 2005.
Ministry of Strategy & Finance, Basic Plan for PPP Projects, 2008.
_________________________, 2009 Operating Guidelines for Preliminary Feasibility Studies, 2009.
_________________________, 2006 Operating Guidelines for Preliminary Feasibility Studies, 2006.
OMB, Section 11 of Circular No. A-94.
Park, Hyeon, Gyeongjun Yu, and Seungjun Gwak, A Study on the Value Estimation of Culture and
Science Museum, Korea Development Institute, 2004.
Park Hyeon, et al, Study on Multi-Criteria Analysis for Preliminary Feasibility Studies (2), Korea
Development Institute, 2001.
Saaty and Vargas, The Logic of Priorities: Applications in Business, Energy, Health, and
Transportation, Kluwer Academic Publishers, 1982.
UNIDO, Guidelines for Project Evaluation, 1972.
Weitzman, Martin L., Why the Far Distant Future Should Be Discounted at Its Lowest Possible Rate,
Journal of Environmental Economics and Management, Vol. 36, pp.201-208, 1998.
__________________, Gamma Discounting, American Economic Review, Vol.91, No.1, 2001, pp.
260~271.
References
189
Appendix 1
Survey to Evaluate the Possibility of PPP Project at the
Preliminary Feasibility Study Step
(First-Step Checklist)
Evaluation
item
Feasibility in
terms of law
and policy
Survey question
Check box
Yes
No
Does the project suit the governments mid- & long-term SOC plans,
policy directions, investment priories, etc.?
Yes
No
B. Evaluation Items
1. First-Step Evaluation Items
Table 2
Step
Evaluation
How to
item
score
Remarks
terms of law
Infrastructure
and policy
Step 1
Can move
Required
items
competent authority.
PPP project
implementation method
to the next
step only if
yes is
selected
Type
1. Core service
2. Usage fee
3. Profitability
X/
Case
Expressway, light
rail transit, port
Environment
treatment facility,
railroad
National
road,
sewer
system
School,
Theme park,
Museum,
military
public rental
science
facility,
housing
museum
welfare
facility
PPP project
implementation
BTO
BTL/BTO
BTL
BTL/BTO
BTL
BTL
method
Appendix
191
The following questions are intended to determine whether this project can
be pursued as a PPP project.
- Please refer to the study results summary above.
- Please mark on Yes or No to the following questions:
192
Survey questions
Check
box ()
Yes
No
Yes
No
Feasibility in
terms of law
and policy
Does the project suit the governments mid- & long-term SOC plans,
2
policy directions, investment priories, etc.?
Survey questions
item
Check box
()
Can the private party provide infrastructure and service under its
1
PPP project
Yes
No
implementation
method
Yes
No
Yes
No
Appendix
193
Appendix 2
Survey to Evaluate the Possibility of PPP Project at the
Preliminary Feasibility Study Step
(Second-Step Checklist)
194
B. Evaluation Items
1. Second-Step Qualitative Evaluation Items
Table 1
Step
Evaluation
item
Economic
feasibility
Ease of
management
Remarks
Creativity &
Step 2
efficiency
Risk distribution
evaluation and
comprehensive
private capital, and the scale and facilities of the project have any
judgment
Publicness
Appendix
195
Appendix 3
Guidelines for Writing an Analysis Table of Financial
Feasibility
Table 1
Classification
Total
First year
Second year
Remarks
Research cost
Design cost
Construction cost
Lot purchase cost
Incidental cost
Operating facility cost
Various taxes & charges
Operating reserve
Total project costs
Interest during construction
Contingency reserves for
price fluctuation
Contingencies
Total investment costs
Table 2
Government
financial support
ratio
PI/FNPV/IRR
PI/FNPV/IRR
PI/FNPV/IRR
PI/FNPV/IRR
FNPV = 0
Note: Different rates of government financial support and usage fees are to be applied to different areas.
196
Table 3
Cost
Total of
Total
Opera-
Year
Financial
Other
ting
support
revenues
revenue
Oper-
Cor-
ating
porate
costs
tax *
Total
present
Construction
Before
After
discount
discount
costs
Before
After
discount
discount
values
1st year
2008
of
construction
2009
2nd
2010
3rd
2011
4th
2012
5th
2013
6th
2014
7th
1st year
2015
operation
2016
2nd
2017
3rd
2018
4th
2019
5th
2020
6th
2041
27th
2042
28th
2043
29th
2044
30th
Total
Appendix
197
Different projects use different items for operating revenue and operating cost
(including cost of sales) as follows:
Table 4
Sector
Road Project
Toll Income
Railroad Project
Fare Income
Operating Cost
unloading service
Lease Income
Port Project
Lease Project
Note: Whether there are other revenues like those of supplementary projects, operating costs to generate them should be added.
Table 5
2016
2017
2018
2019
2041
2042
2043
2044
1st
2nd
3rd
4th
5th
27th
28th
29th
30th
Sales (A=B+C)
Operating revenue (B)
Other revenues (C)
Cost of sales (D=E+F)
Amortization cost of operation rights (E)
Maintenance costs (F)
Gross profit (H=A-D)
Selling and general administrative costs (I)
Operating profit (J=H-I)
Interest income (K)
Paid interest (L)
Net profit before corporate tax (M=J+K-L)
Corporate taxes (N)
Current-term net profit (O=M-N)
198
Total
Table 6
Operating period
2008
2009
2013
2014
1st
2nd
6th
7th
2015 2016
1st
2nd
2043
2044
29th
30th
Assets
Current assets
Cash and cash equivalents
Non-current assets
Construction-in-progress
Management and operation rights
Liabilities
Current liabilities
Short-term borrowings
Corporate tax payable
Current portion of long-term debts
Long-term liabilities
Long-term borrowings
Shareholders equity
Capital stock
Retained earnings/ accumulated deficits
(Current-term net profit)
Liabilities and shareholders equity
Appendix
199
Table 7
2nd
Operating period
7th
1st
200
2nd
2043 2044
29th
30th
The following are guidelines to fill out the above tables. To draft an analysis
table of profitability and financial statements, the sheets of financial analysis
provided by the KDI are to be used.
A. Overall Order
The sheets of financial analysis include the analysis table of profitability,
statement of cash flows, income statement, and statement of financial
position. The analysis table of profitability is the basis, and the other three
sheets are to be automatically filled out.
The values of the analysis table of profitability and the inflation rate are used
to come up with values for the income, cost, government subsidy items in the
statement of cash flows and income statement.
Interest income and interest cost for accumulated borrowings are calculated
from the statement of cash flows.
Corporate tax from which a tax shield on the interest income and interest
cost computed from the income statement are removed is a current price. It
should be discounted by the inflation rate to convert it into a constant price.
This is to be used as corporate tax in the analysis table of profitability.
All the items of the analysis table of profitability are filled out as above, and
the FNPV is to be calculated at the time of analysis to come up with the PI,
NPV (FNPV), IRR (FIRR), payback period (PB), and discounted PB.
The statement of financial position is not directly related to the analysis table
of profitability. It is written to come up with operation rights by
accumulating construction costs and interest during construction, and divide
it by the free use (operating) period to calculate depreciation cost.
The items of the analysis sheets are used according to the type and
characteristics of the concerned project.
The unit of each analysis table is 100 million won.
Appendix
201
The 2008 Basic Plan for PPP Projects is referred to in order to determine
the financing ratio of equity capital by the investor as no less than 25% of
total PPP costs.
First calculate the FNPV for a case where no government subsidy is paid
(government subsidy rate of 0%) and for a case where a certain level of
government subsidy is provided (e.g. 30% for a road project). Then, by trial
and error, calculate a rate of government subsidy that makes the FNPV zero.
This analysis sheet is composed in a way to automatically calculate the
government subsidy of the corresponding year of the construction period
according to the order of fund inputs (equity capitalgovernment
subsidyborrowings) once the subsidy rate is set for all construction costs.
The income items consist of operating revenue and other revenues generated
from ancillary projects or supplementary projects. Users are to directly enter
values they separately calculated into the corresponding item fields.
e.g. 1) Road Project
- Enter toll income into the operating revenue field. Multiply the traffic
volume of each transportation means estimated for the road section of
each year by the length of the section and then again by the toll per km.
- Reflect the differences in the toll rates and traffic volume between the
Korea Expressway Corporation and a private party as the responsible
party.
- For supplementary income, lease income from advertising boards and
convenience facilities can be considered.
e.g. 2) Railroad Project
- Deduct the number of free passengers from the net number of passengers
and multiply the resulting number by the toll (average toll of the section,
etc.) to come up with operating revenue.
The cost items consist of construction costs and operating costs (maintenance
costs + selling and general administrative costs + replacement costs of
tangible assets), and values from economic feasibility analysis are used.
-
202
Deduct a tax shield on interest income and cost from the corporate tax
computed in the income statement and apply the inflation rate to the resulting
corporate tax.
Come up with a PI, FNPV, and FIRR according to ~. For a PB and a
discounted PB, the user is to find years when the accumulated profit and
loss becomes zero and the net accumulated profit and loss becomes zero
by looking at the accumulated profit and loss and net accumulated profit
and loss rows.
Appendix
203
flows from operating activities + cash flows from investing activities + incoming
cash flows from financing activities - dividend payment under outgoing cash
flows from financing activities.
Paid interest is the same as the paid interest amount from the statement of
cash flows.
For corporate tax, apply 13% (14.3% when residence tax is included) for a
taxable amount of no more than 100 million won and apply 25% (27.5%) for
an amount exceeding 100 million won. For deficits carried forward, apply
the carryover of deficits for five years.
The net profit before corporate tax (ordinary profit) excluding the paid interest
and interest income of the analysis sheet is to calculate corporate tax to be used
in the analysis table of profitability by adding the paid interest to the net profit
before corporate tax and deducting the interest income. Apply a corporate tax
rate to this value to come up with a corporate tax for profitability analysis.
204
Appendix
205
206
Appendix
207