ABSTRACT : This paper describes the capacity enhancement of coal fired power plants with through operational optimization, control techniques and better maintenance practices The philosophy of Prevention is Better than Cure is dealt in detail to improve the Plant load factor (PLF) of plant. The energy conservation measures are also implemented in improving the plant performance and are enumerated in this paper.
1.0 INTRODUCTION
The Indian power sector is highly dependent on thermal power generation i.e., 64.6 % of total generation. The power generation by coal forms about 53.4 % of total energy generation. The coal is fissile fuel which is a finite source of energy and is going to be exhausted. The Indian power sector has alarmed to reduce the energy loss and conserve the energy to reduce the huge gap between supply and demand (energy deficit of 10 % and peak demand shortage of about 12 %). Therefore, it is essential to generate the power with energy efficiently and Dahanu Thermal Power Station (DTPS) is committed to generate power with energy efficiently. DTPS had taken up lot of initiatives in conserving the energy while generating the power. The performance improvement of individual thermal power generating units will help in achieving Increased power generation and there by reducing the demand supply gap Reduction in power generation cost and thereby improving the competitiveness of Indian industry Reduction in Green house gas emissions and Global warming Reliance Infrastructure Limited is a fully integrated utility engaged in the generation, transmission and distribution of electricity. It ranks among Indias top listed private companies on all major financial parameters, including assets, sales, profits and market capitalization. Dahanu TPS is Reliance Infrastructure Ltd.s single largest power generating facility. It is a 500 MW (2 X 250 MW) coal based thermal power station situated approximately 120 kms North of Mumbai on the western seacoast. The power plant was commissioned in 1995 and has been constantly upgraded to maintain its technological edge. It is the first generating utility in the country to be certified as ISO 9001 and ISO 14001 for its Quality Management System and Environmental Management system respectively. The health and safety of the employee is given utmost importance at DTPS and the plant is also certified as OHSAS 18001 as well as SA-8000 for Social Accountability. The DTPS is a first utility in Thermal power plants in India which was certified as BS EN 16001 for Energy Management System. One of the key contributors to this is the continuously improving Operation & Maintenance practice. The present shape of maintenance management practices has been evolved over a period of 10 years of striving towards excellence. This paper showcases the typical organization of operation & maintenance setup at DTPS and the maintenance philosophy being followed. Organization wide SAP as a part of maintenance management system, efficiently performs day-to-day asset management functions. Reviews & monitoring at daily, weekly & monthly frequencies ensure effective implementation of maintenance strategies
The performance improvement of the power generating units was taken up in the following areas: Safety Availability Reliability Output Efficiency Cost Environment protection
3.1 Methodology
The maintenance methodologies include Preventive Maintenance, Corrective or Reactive Maintenance, Predictive Maintenance, Proactive Maintenance and Maintenance Prevention techniques in an integrated manner to increase the probability that equipment will function with desired operating parameters over its life cycle with minimum maintenance. These different maintenance strategies are proactively deployed to avoid breakdowns, premature equipment malfunctions and to increase response times to recover from failure, in order to effect improvements in overall plant availability. Appropriate selection of right maintenance strategy to deal with each situation, is based on maintenance requirements supported by sound technical and economic justification. The flow chart below demonstrates the various methods.
Electrical, Control & Instrumentation, Civil & Coal Handling Plant are given target figures against each parameter. This daily review keeps maintenance aware of the current performance and further improving them. Equipment Status shows all major equipment under maintenance for the day. Critical equipments, which are down or under maintenance for more than 7 days & 15 days are also listed to keep the plant management informed. Critical work orders, Equipment with abnormal parameters (detected through condition monitoring) or any other information affecting plant performance is given. Daily Defect Report: All new and pending defects pertaining to all maintenance departments appear in Defect Review Report. These are reviewed, planned, scheduled & rescheduled. Inter departmental coordination & issues resolution is also catered. These defects are tagged as Corrective, Predictive, Modification, ES (requiring Equipment Shutdown), US (requiring Unit Shutdown), CS (requiring Station Shutdown) and Miscellaneous, as decided.
DTPS monitoring all HT auxiliaries energy consumption very closely by using in house developed software in excel. This report can help to operation and maintenance engineers to take a decision for operation and maintenance of individual equipment in view of energy efficiency and conservation. Any deviation observed will be taken as a FIR (Non Conformity) and CA/PA will be taken for the same. This report can influence the scheduled maintenance and changeover of stand by equipments. The decision will be taken by all O&M personals during daily planning meeting.
DTPS follow the FIR system for not meeting the targets for its energy, process, safety, environment, fire and human and CA/PA to be prepared to avoid the recurrence of the same.
DTPS taking CA/PA for non conformity products which were raised through FIR system. 4.5 Improvement Plans
DTPS taking improvement plans for Energy, Process, Safety, Environment, Fire and Health. The source for improvement plans are. a. Participation in national and international seminars/Workshops/Award functions. b. Visit to different plants in India and aboard. c. Discussion with vendors and suppliers. d. Discussion among cross functional teams. e. Outcome of CA/PA f. Suggestions from individual employee.
The planning requires assessment of the maintenance activities of both corrective as well as preventive nature, to keep the plant and its auxiliaries fit and performing, without any significant downgrading of the overall equipment effectiveness, till the next schedule overhaul.
5.1 Scope of work It is assessed from the experience gained through running the unit, the pre outage survey and thorough efficiency tests. The assessment is also benefited from the experience of previous major and minor overhauls of both the Units. Following are the measures that ensure the completion of unit overhauling in minimum time. 5.2 Learning from past to beat the surprises - We have tried to learn from the experiences from the previous overhauls. This has helped to anticipate the surprises that arise during the overhaul. 5.3 Selected & Motivated Contracting Participants - The contracting agencies have a vital
bearing on the quality and timely completion of the work. The contract conditions are made stringent and fine-tuned to include penalty, safety & incentive clauses. A lucrative incentive to the major overhaul agencies is also included in the contract terms & conditions, to keep them motivated.
5.4 Tools Tackles & Moving Equipments- The required T & Ps such as welding machines,
cutting sets etc are placed such that these can be operated all across the area. The requirement of TIL, Hydra etc is evaluated prior to the overhaul and activities are scheduled accordingly to conveniently share these resources. Backup arrangements are also kept ready for any unforeseen requirement.
5.6 Safety and Environment - Ensuring a good work environment and safety & security of the man and machine on work, is of utmost importance for the timely success of the overhaul. All employees and contract people use personal protective equipments during overhaul. During overhaul, Fire fighting people are deputed round the clock at various locations to avoid any incidence fire. 5.7 Use of IT Tools -The overhauling plans are implemented using various planning & scheduling tools of SAP and professional project management software like Primavera.
PERFORMANCE INDICES GENERATION (MUS) PLF (%) AVAILABILITY (%) LOADING FACTOR (%) AUX. POWER CONSUMPTION (%) SP. OIL CONSUMPTION (ML/KWH) SP. COAL CONSUMPTION (KG/KWH) DM MAKE UP (%) TOTAL OUTAGE (Nos.) HEAT RATE (KCAL/KWH) TRIPPINGS/ 1000 HRS RUNNING HOURS
PREVIOUS BEST 4481 101.79 97.18 105.30 7.34 0.11 0.22 6 2261 0.056
F.Y 2003-04 4407 100.34 96.84 103.61 7.34 0.115 0.526 0.39 6 2268 0.117
F.Y 2004-05 4439 101.35 96.88 104.61 7.53 0.13 0.531 0.37 14 2261 0.412
F.Y 2005-06 4323 98.7 94.71 104.22 7.59 0.18 0.534 0.38 17 2286 0.301
F.Y 2006-07 4458 101.79 96.79 105.17 7.64 0.11 0.533 0.24 8 2278 0.177
F.Y 2007-08 4459 101.53 96.7 104.99 7.67 0.13 0.544 0.22 8 2279 0.176
F.Y 2008-09 4423 100.99 96.31 104.86 7.71 0.13 0.575 0.24 12 2300 0.355
F.Y 2009-10 4481 102.33 97.18 105.3 7.6 0.14 0.581 0.32 8 2288 0.176
F.Y 2010-11 4424 101 96.48 104.69 7.37 0.192 0.626 0.42 10 2282 0.056
GeneratorCurrentinAmpatLoad between260to265MW
MainSteamFlowinT/hratLoad between260to265MW
Extraction
Pumps
There are two Condensate Extraction Pumps (CEP) of 700 kW. One pump will be continuously working and second will be stand-by. CEP 1A is provided with Variable frequency drives (VFD). Figure 3 gives the variation of CEP current with plant load. CEP 1A motor is provided with variable frequency drives. The current rating of CEP is 71.2 A and the maximum current recorded at a plant load of 271 MW was 62.21 A. The currents are not exceeded the design current rating of CEP motors. The performance of these CEPs are quite good and the better performance of individual equipment will enhance the overall capacity of plant.
Figure 4 shows the variation of winding temperature of CEP motors with plant load for one year. The CEP winding temperatures are in the range of 87.65 92.29 o C and are well within the permissible limit of 105 o C or 75 oC above the ambient temperature. The performance of cooling system of CEP is good and heat removal capacity is also quite good. The bearing temperatures of CEP are also analyzed for a period of one year. The CEP pump and motor bearing temperatures are in the range of 39.54 53.21 oC and are well within the permissible limit.
are in the range of 85.21 96.89 oC and are well within the permissible limit of 105 oC or 75 oC above the ambient temperature. The performance of cooling system of IDF is good and heat removal capacity is also quite good. The bearing temperatures of IDF are also analyzed for a period of one year. The IDF fan and motor bearing temperatures are in the range of 46.55 68.56 oC and are well within the permissible limit.
also quite good. The bearing temperatures of FDF are also analyzed for a period of one year. The FDF fan and motor bearing temperatures are in the range of 49.25 91.80 oC and are well within the permissible limit.
are in the range of 63.72 84.86 oC and are well within the permissible limit of 105 oC or 75 oC above the ambient temperature. The performance of cooling system of PAF is good and heat removal capacity is also quite good. The bearing temperatures of PAF are also analyzed for a period of one year. The PAF fan and motor bearing temperatures are in the range of 44.92 80.89 oC and are well within the permissible limit.
5.8 Mills
There are three Mills of 2300 kW, Ball Tube mill BBD 4772, two mills will be working continuously and third mill will be stand-by to meet 100 % MCR load. Each mill is provided with two output coal pipes to provide coal to each elevation. The coal-air mixture temperature is maintained by varying the hot air and cold air flow to mills. Figure 11 gives the variation of Mill motor current with plant load. The current rating of Mill motors is 260.6 A and the maximum current recorded at a plant load of 271 MW was 194.68 A. The currents are not exceeded the design current rating of Mill motors. The performance of these mills are quite good and the better performance of these individual equipments will enhance the overall capacity of plant. Figure 12 shows the variation of winding temperature of Mill motors with plant load for past one year. The Mill motor winding temperatures are in the range of 62.74 72.27 o C and are well within the permissible limit of 105 oC or 75 oC above the ambient temperature. The performance of cooling system of mills is good and heat removal capacity is also quite good. The bearing temperatures of Mills are also analyzed for a period of one year. The Mills and motor bearing temperatures are in the range of 44.92 63.97 o C and are well within the permissible limit.
7.0 CONCULSIONS
The main conclusions are: As Dahanu Thermal Power Station shown a path to Indian Thermal Power Sector that, we can generate more than 100% Plant Load Factor without compromising the life of machines. By operating units at maximum capacity without violating the design parameters of individual equipments, it will help to reduce the gap between demand and supply of electricity and conserve energy. Considering the national present average Plant Load Factor (PLF) of 74.8% and around 350 sets of 210 & 250 MW units, by enhancing Plant Load Factor from 74.8 % to 95% and considering 97 % plant availability, we can able to generate 1,26,450 MUs more electricity, which will help for nation building.
********