Construction Work DMRC

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 33

PRESENTATION ON SUMMER By-

INTERNSHIP IN DMRC Sayyed Rubeel Bin Ali Naqvi


13-BCE-0060
CONSTRUCTION OF ELEVATED STABLING LINE FOR
KALINDI KUNJ DEPOT CC-90

Under the guidance of


Prof. Kafeel Ahmed
Under the supervision of
Executive Engineer
Azharuddin
CONTENT
 OVERVIEW
 CASTING YARD
 ORGANISATION CHART
 CASTING OF I GIRDER
 BATCHING PLANT
 REINFORCEMENT
 QUALITY CONTROL
 CONSTRUCTION OF PIER
 CONSTRUCTION OF DECK SLAB
 LAUNCHING
 MACHINES USED
 SAFETY
OVERVIEW OF CC-90
STABLING YARD
• Length of Stabling Yard – 1.3 km
• Located just near Kalindi Kunj Depot
where DMRC was facing space
constraints
• First of its kind elevated stabling deck
• 30 to 40m wide and 15m above
ground
• Capacity – 27 trains
CASTING YARD
• 3 Types of beams were casted

1. Longitudinal I girder
2. Secondary I girder
3. Transverse beam

• On an average, 10 sections casted


everyday.

• Maximum length of 15m sections can


be casted.
ORGANISATION HEIRARCHY

Project manager

QA/QC INCHARGE SECTION INCHARGE SAFETY MANAGER

QC ENGINEER SAFETY SUPERVISOR


SITE ENGINEER

LAB ASSISTANT SUPERVISOR


CASTING OF GIRDERS
• Bed is prepared for casting.

• Rebar cage is prepared and lifted up and


moved to casting bed using gantry crane.

• Buffing and oiling of shutter.

• Foam is provided at joints.


• Cover blocks are provided.

• M 50 concrete is poured by pump


or bucket.

• Shutters removed after one day.

• Curing for continuous atleast


14 days.
ILLUSTRATION OF CONCRETE PLACING IN
GIRDER MOULD WITH THE USE OF BUCKET

• CONCRETING TAKES USUALLY


10-15 MINUTES.

• COMPACTION IS ENSURED USING


NEEDLE VIBRATOR.

• SUPERVISOR’S PRESENCE IS MUST


AT THE TIME OF CONCRETING.
CONCRETE BATCHING PLANT
• AN EQUIPMENT THAT COMBINES VARIOUS INGREDIENTS TO FORM
CONCRETE. IT INTAKES WEIGHED AMOUNT OF SAND, GRAVELS,
CEMENT AND WATER.
• M10- M60 CONCRETES CAN BE PREPARED.

• 5 SILOS ARE PROVIDED FOR CEMENT IN


WHICH OPC IS FILLED.

• COMPUTER ORIENTED SYSTEM.

RECIPE MASTER
SCREEN
COARSE AGGREGATE AT CASTING YARD

CEMENT SILOS
TRANSIT MIXER

• 6 cubic metre capacity

• Slump test carried out at plant as


well as site.

• Reaches to CC 90 within 1 hour.


REINFORCEMENT
• Fe500 confirming to IS 1786 is used.

Reinforcement checklist-

• Correct bar sizes


• Correct bar spacig
• Covers checked
• Specified bar ties
• Correct lap length
• Bar bending schedule approved
QUALITY CONTROL

LAB TESTS
TESTS ON CEMENT

1. FINENESS TEST
• Cement is passed through 90 micron sieve.
• Percentage retained should be less than 10%.
• Average of three readings is taken.
2. INITIAL SETTING TIME

• Take 400g cement.


• Water conten taken 85% of consistency limit.
• Mix it for 5 minutes.
• Should not be less than 30 minutes.

3. FINAL SETTING TIME

• Should not be more than 10 hours.


• No impression of needle.
4. SOUNDNESS TEST

• 78% water of consistency limit used.

• Take 100g of cement sample.

• Le Chatelier’s apparatus used.

• Gap must not increase more than 10mm


TESTS ON AGGREGATES
• Sieve analysis is carried out.

• Only two types of aggregates


are used in DMRC.

• Conducted in the morning.

• Source- Pathankot & Kotputli


AN ILLUSTRATION OF CARRIED OUT
SIEVE ANALYSIS AT CASTING YARD
TESTS ON CONCRETE

1.Slump test

2.Cube testing

• 150 by 150 by 150mm cubes


• 6 cubes casted per cubic metre of concrete
• Loading rate- 14kN/sq.mm per sec
CONSTRUCTION OF PIER AND PIER CAP

• Layout of pier with the help of established


reference points.

• Fe500D is used.

• Rebar is fixed manually as approved by BBS.

• Temporary staging and working


platforms provided.
• Shuttering fabricated at pier location.

• Cover blocks checked.

• Slump checked at pouring location.

• M 40 concrete poured using boom


placer or concrete pump.

• Concrete compacted using needle vibrators.


• Concrete pouring is to be done in two stages
for peir height more than 6m.

• Deshuttering after 24 hours of concreting.

• Curing carried out for 14 days using water pump.

• Hessian cloth to sustain moisture.


CASTING OF INSITU DECK SLAB
• Stitch beam

• Deck sheet placed between


longitudinal beams.

• Reinforcement fixing carried out


confirming to IS:2502.

• Proper buffing and oiling of shutter.

• Fixing of cover block by GI wire.


• Rubber/ foam provided at shuttering joints.

• M 35 concrete poured by concrete pump.

• Curing using wet hessian cloth for 14 days.

• Deck sheet may not be removed.

SHUTTERING DECK SHEET


LAUNCHING OF I GIRDERS
• 10-15 minutes process.

• 10mm error allowed.

• Using prestressed 25mm diameter cables.

• Each cable’s capacity- 20 tonnes

• Levelled ground.
AN ILLUSTRATION OF GIRDER LAUNCHING AT CC 90 STABLING YARD
MACHINES USED

CRAWLER CRANE
• Working capacity 187 tonnes
• Boom length 120 ft
• Counter weight 90 tonnes

GROOVE CRANE
Maximum capacity
60 tonnes
 TRUCK TRAILER
Capacity- 40 Tonnes

One more crane is deployed.

 MAN LIFT CRANE


• To be used by engineers
and technicians.
• For miscellaneous activities.
SAFETY CONSIDERATIONS
POTENTIAL RISKS AT SITE

 Binding wire may cut hand.


 Shutter may topple or fall and hit the person.
 Wire may slip from stressing jack.
 Lifting hook or wire may fail.
 EOT may hit workers.
 EOT wheel may off track.
 Sudden fall of rebar cage or shutter.
 Fall of worker from scaffolding.
WORKING AT HEIGHT
PRECAUTIONS
 Area below barricaded.

 Safety net should be provided.

 Proper ladder and handrails should be provided

 Anchoring of body harness to nearby handrails.


THANKING YOU….