27909e01 3D Model Review Procedure
27909e01 3D Model Review Procedure
27909e01 3D Model Review Procedure
27909.VAR.LCI.STD
Rev.01 - June 2016
GENERAL NOTE This Re-coding does not affect the document content.
TO THE Documents traceability is guaranteed by the unchanged document
DOCUMENT RE-
number.
CODING
Any cross-reference between documents remains unaffected.
/
La presente ricodifica non ha effetto sul contenuto del documento.
NOTA
GENERALE
La rintracciabilità dei documenti è garantita dal numero di documento
ALLA che resta immodificato.
RICODIFICA I riferimenti incrociati fra i vari documenti rimangono validi.
REVISION TRACKING
INFORMATION REQUEST
For information about the content of this standard, please refer to responsible and accountable
person as per above RACIE table or to Technical Authority coordinator (COETA).
Table of Contents
1. GENERAL ............................................................................................................. 5
1.1 SCOPE ............................................................................................................................................................... 5
1.2 DEFINITIONS .................................................................................................................................................... 6
1.3 ACRONYMS .......................................................................................................................................................... 6
1.4 ROLES AND RESPONSIBILITIES ................................................................................................................................... 7
1. GENERAL
In order to ensure efficient management and monitoring of 3D Models produced by different
CONTRACTORs, it is necessary to have a clear and shared procedure.
During design process, CONTRACTORs will produce 3D Models, whose progress shall be
monitored and reviewed at times defined by Company to verify technical content and formal
compliance with Project schedule.
The deliverables required to CONTRACTOR for each engineering department and for each
review session (30%, 60% and 90%) shall be clearly defined.
It is also required to CONTRACTORs the full compliance with eni spa methodologies contained
in the “Interdisciplinary Documents” (including items and components coding, piping classes
production, etc.).
On projects of large complexity involving more CONTRACTORs, it is also necessary to monitor
the interfaces among the 3D Models produced by all CONTRACTORs.
This document defines a series of activities and guidelines to properly manage the 3D Model
monitoring before, during and after the reviews between Company and CONTRACTORs.
1.1 SCOPE
The 3D CAD model development is a Project activity of utter importance and periodical reviews
have to be considered as Project milestones for proceeding with the engineering activities.
The scope of this document is to report the work process to be followed in order to ensure a
proper review of the 3D Model developed by CONTRACTORs during the Project Execution Phase.
It consists in several activities and guidelines to be actuated before, during and after the 3D
Model reviews in order to maximize the review efficiency and identify in advance potential
criticalities along the Project execution.
In addition, the deliverables and status of the engineering activities requested for calling a 3D
Model review are clearly explained.
The instructions to CONTRACTORs about how to develop the 3D Model are out of the scope of
this document and reported in [1], [2] and [3] depending upon the software defined Project-
wise.
Operability and Maintainability requirements defined in [5] are assumed already acknowledged
by CONTRACTOR at the beginning of design process. 3D Model Review session aims,
furthermore, to verify the compliance in terms of operability, ergonomics, maintainability of
the asset.
1.2 DEFINITIONS
Hereinafter definitions of terms used in the best practice are shown:
Term Definition
Company (Eni) The party that initiates the project and ultimately pays for its design
and construction. The Company will generally specify technical
requirements. The term “Company” may also include agents or
consultants authorized to act for, and on behalf of, the Company.
Contractor A person or organisation that undertakes responsibility for the
performance of a contract.
Contract An acceptance of legal relations between two or more parties for the
transfer of goods or services for value.
Sub-Contractor Any supplier, distributor, vendor, or firm that furnishes supplies or
services to or for a prime contractor or another subcontractor.
Vendor A supplier of material or services offered from a catalogue or price list
and purchased by issue of a purchase order.
Project Unique process, consisting of a set of coordinated and controlled
activities with start and finish dates, undertaken to achieve an objective
conforming to specific requirements, including the constraints of time,
cost and resources.
CS Independent Classification Society whose scope is to verify/certify that
the design is in accordance with the appropriate Class rules and
regulations.
WORK All the works and services required to be performed by CONTRACTOR
under the CONTRACT.
1.3 ACRONYMS
Hereinafter the definition of the acronyms used in this document:
ACRONYM DEFINITION
ADM (CONTRACTOR) System Administrator/Coordinator
AFC Approved for Construction
CAD Computer Aided Design
FDM Facility Data Management (c/o Company)
FP Focal Point
IFA Issued for Approval
IFC Issued for Construction
IFR Issued for Review
MODEL 3D CAD Model
P&ID Piping/Process and Instrumentation Diagram
RDB Reference DataBase SPCPuma\Elena
SOP (CONTRACTOR) System Operator
Tag Method to identify a specific comment made in a Design Review
ToR Terms of Reference
CONTRACTOR is liable for organizing and planning MODEL implementation, as well as carrying
out the necessary checks to confirm the fulfillment of the targets required at the different steps
relevant to the various MODEL review sessions as described on this document.
As part of MODEL implementation, CONTRACTOR may refer to the appointed FDM team to get
support on COMPANY documents application, with particular reference to [1], [2] and [3].
3. ACTIVITIES DESCRIPTION
The activities below described are intended to ensure proper implementation and model review
management along the Project execution.
These activities refer to a Project in Execution Phase where the objective of the MODEL review
is to progressively “freeze” the design, i.e. once comments from a specific review are resolved,
the scope of the facilities/activities covered in such review will be frozen so that relevant
deliverables can be generated and released.
CONTRACTOR is called to organize 3 (three) MODEL review along the WORK execution, namely
at 30%, 60% and 90% of the engineering progress.
CONTRACTOR shall perform several activities before, during and after the MODEL review in
order to properly explain the status of the MODEL and demonstrate it to COMPANY.
At the beginning of the Project CONTRACTOR is asked to organize a dedicated meeting with
the FDM FP should any explanation or clarification on [1] is requested.
• If not provided by COMPANY, Project Specific Checklists, split for each phase (30-60-90),
developed on the basis of the checklist reported in attachment to this document and issued
to COMPANY for approval.
The above documents shall be part of the Project MDR and issued for COMPANY approval. In
addition to the above documents CONTRACTOR shall develop and apply a clear Management
of Change Procedure as well as a Design Change Note procedure with the final scope to ensure
that what has been defined/frozen on the MODEL will not be affected by other
changes/modifications, as well as to drive the isometric definition and issuance.
COMPANY shall be advised in advance of and may participate in all such reviews to the extent
they deem necessary. All Internal Project Reviews shall be properly documented, findings
logged and resolutions appropriately tracked and recorded. CONTRACTOR shall afford
COMPANY the option to review all findings related to internal Project reviews.
Multidisciplinary review aims to ensure that completeness, quality and progress of MODEL to
be submitted to COMPANY are in line with the expectations defined for each review session.
Process and Utilities P&IDs (IFR for 30%, IFA for 60%, AFC for 90%);
Distribution P&IDs (IFR for 30%, IFA for 60%, AFC for 90%
Escape routes layout (IFR mandatory at 30%);
Process & Utility Flow Diagrams;
Mechanical Handling philosophy (IFR mandatory at 30%);
Mechanical Handling Report (IFR mandatory at 60%);
Plot plans (IFR at 30%, AFC for 90%);
Comments resolution of previous model review session (a specific document shall be
issued to properly close-out the identified actions);
CONTRACTOR Data sheets/equipment drawings (preliminary for 30%, IFA for 60%, AFC
for 90%);
Line List (AFC for 90%);
Safety studies, with particular reference to EERA, ESSA, FERA and QRA (60%
mandatory);
Vendor Drawings when available in accordance with checklist.
Equipment list (IFR for 30%, IFA for 60%, AFC for 90%);
Critical line list (AFC for 90%);
This list is not exhaustive and it could be integrated with additional list of documents identified
by each engineering department, or modified in agreement with COMPANY on the basis of the
Project specific requirements and schedule of the Work.
CONTRACTOR shall assemble the documentation two weeks in advance of all the External
Project Reviews. The documentation shall already be approved by COMPANY or by CS if
applicable. Resolution of discrepancies, deficits, non-conformances shall be highlighted to
COMPANY in the ToR and approved by COMPANY before proceeding.
Before each review session, CONTRACTOR shall send to COMPANY a ToR with following
indications/attachments:
CONTRACTOR shall state that the facilities dedicated for the MODEL review are adequate for
the scope both in terms of space in the room as well as hardware used to navigate the MODEL.
In such perspective, CONTRACTOR shall provide a computer station powerful enough to
navigate the model in a fluid and handy way as well as at least 2 (two) projectors to show the
MODEL and any documentation available in electronic format that may be needed during the
review session.
Both the Agenda and the ToR shall be sent to COMPANY 2 (two) weeks in advance and shall be
issued for COMPANY approval.
5. 3D MODEL REVIEWS
Review session with COMPANY is formally executed, after CONTRACTOR internal
multidisciplinary review, in three different sessions (30%, 60%, 90%) corresponding to the
targets indicated in the Project schedule.
Upon completion of each session, MODEL will be verified to allow subsequent activities
development.
CONTRACTOR shall appoint an ADM, who will coordinate the review team and shall have a
thorough knowledge of the Project, of the MODEL and computer systems used in the review
sessions, with the support of a system operator.
ADM is responsible for the review process efficiency, for the proper reporting of comments and
their implementation.
In reviews with COMPANY and according to each stage of MODEL completion, representatives
from all engineering departments involved shall compose CONTRACTOR’s team assigned to the
review. CONTRACTOR shall program possible presence of various specialists needed for a
deeper understanding of specific topics.
The attendance of the following figures is mandatory:
The attendance of the following roles may be required part time or on call depending on the
review needs. CONTRACTOR is requested to evaluate the need of having them on a continuous
basis and to justify to COMPANY their absence:
5.2 3D MODEL
MODEL content evaluation as a basis for measuring the progress shall be executed at each
review and shall be performed by CONTRACTOR, as here below defined.
The following paragraphs summarize contents and goals for each phase.
Goal of this phase is to ensure layout solutions adopted meet both technical and contractual
requirements related to accessibility, operability, maintenance; areas for future expansion
match as well the above requirements.
According to CONTRACTOR’s planning, AFC deliverables may be issued for most elements (e.g.
secondary structures, equipment foundation, isometrics for piping prefabrication, main
supports, etc.).
The checklist reported in attachment of this document reports the list of items expected to be
modeled in this session.
All piping shown in P&IDs and Process Auxiliary Services, Pipe supports and In-line and
on-equipment instruments;
Equipment and both electrical and instrumental components, including supports for
cable trays;
Safety features, such as emergency showers, eye washers, fire protection, lighting and
communication devices;
Vendors GA drawings for all Equipment and Instruments are Approved for Construction
(AFC).
Goal of this phase is to verify that MODEL contains enough details to let the extraction of final
count of required materials (NOT including allowance for prefabrication nor contingencies) and
to allow the completion of issuance of deliverables Approved for Construction (AFC).
The checklist reported in attachment of this document reports the list of items expected to be
modeled in this session.
3D-CAD Design Review model presentation will be performed using a large screen having a
high resolution. Naviswork (or equivalent) software will be used to 'Walkthrough' the model.
The review session will be driven by the CONTRACTOR ADM, who is normally a member of the
Layout and Piping group, assisted by the CAD coordinator. In case SUB-CONTRACTORs are part
of the Project, the role of ADM can be delegated to SUB-CONTRACTOR group having the same
know-how and knowledge of its own part of WORK. In order to guarantee the integrity of the
design CONTRACTOR ADM shall always be present in order to comment if necessary what
presented by Sub-CONTRACTORs.
Plot plan drawings, PFDs, P&IDs and any documentation useful for explaining or navigating the
MODEL shall be present in the room in paper copy, as previously agreed between Parties in the
3D MODEL ToR (see Section 7.3). Each participant should have a set of such documentation.
Any other documentation that may be required to ease the review shall be available in
electronic format and promptly projected upon request on the second screen.
The review shall mandatorily start with a presentation of CONTRACTOR in which the status of
the activities is shown and the non-compliances, if any, discussed and motivated against the
review team.
During the presentation, the same files attached to the ToR shall be displayed and discussed,
highlighting the critical items that may constitute a risk for the Project schedule and/or
construction activities.
The check list, already populated as attached to the ToR shall be discussed highlighting the
items that have not been modeled, if any. Any non-conformity to the check list shall be
presented, motivated, discussed and minuted.
In case any action coming from previous 3D MODEL session is not finalized, a general review
of the open actions shall be performed. CONTRACTOR shall clarify the reason why the actions
have not been closed. All the outstanding actions, once clarified, shall be reported as actions
on the review report.
Should any SUB-CONTRACTOR be present on the Project, the above steps shall be repeated.
As soon as the above preliminary steps have been done, the 3D Model review will start by
navigating through the 3D Model, starting from the escape/handling ways and generally
starting from the upper deck and moving downward.
While navigating through the escape ways, each discipline is responsible for reviewing the area,
highlighting potential non conformities with the Project requirements with particular attention
to safety, operability and maintainability aspects (ref. [5]). For this scope a dedicated screening
focused on operable and maintainable items (vent valve, drain valve, spectacle blind, manual
valve, filters, Valve Control Panel etc,) can be required by the COMPANY.
Every time an equipment is met, vendor drawing (if available) has to be asked, showed on a
second screen and checked whether in line with the model (with particular attention to the
nozzle position and orientation).
As soon as the module by module/area by area activity has been carried out as above,
depending upon the review stage, complexity and type COMPANY will decide to perform a
partial or complete review of the plant piping by following the P&IDs. Each time a line is checked
and comments/recommendations duly recorded, the line shall be yellow highlighted on the
relevant P&ID(s).
The meeting will be closed after a complete review of the recorded actions, in order to double
check that the comments have been recorded in a clear way and that every team member
agree with the actions.
Each comment shall be recorded in a form developed for the specific project on the basis of
the template as reported in ANNEX “B”. CONTRACTOR shall include all information’s required
to ensure comment intent is uniquely defined.
To ensure traceability of points, following information shall be printed on the form:
1. Review identification code (30%, 60%, 90%);
2. Serial number (tag);
3. Facility or project code;
4. Line number or reference equipment;
5. P&ID number on which lines or equipment in question are represented;
6. Note on action to be taken;
7. State of analyzed point;
8. Explanatory note if point resolution is different from what was agreed during review;
9. Engineering department involved;
10. Review date;
11. Date for comment implementation;
12. Signatures of approval for completion point under consideration;
Form shall be constantly updated until resolution of all comments, classifying analyzed points
according to following codes:
Within ten days after review completion, ADM prepares a design review file and 3D model
backup complete.
The expectation of COMPANY is that CONTRACTOR performs the design review archive to
COMPANY ensuring that all the information included and the deliverable produced are updated
according to design review report.
The expectation of COMPANY is that CONTRACTOR performs the Final Handover of the system
to COMPANY ensuring that all the information included and the deliverable produced are in As-
Built status.
7. ANNEXES
30% Review
No. Item
1.0 General
Documentation status
Plot Plan issued and in line with the 3D Model. Extent of Module/Plant and Direction Check against Plot
1.1
Plan/Ship’s GA
1.2 Process & Utility Flow Diagrams issued
1.3 Process and Utilities P&IDs issued IFR at least
1.4 Escape routes layout issued IFR at least and in line with the model
1.5 Drainage philosophy issued and main headers/lines modeled.
1.6 Mechanical Handling philosophy issued
1.7 Other documentation as per ToR agreed with Company
Other
1.8 Space for future construction and erection access – General overview
1.9 Major Interference and clash check performed
3.0 Mechanical
Equipment
All equipment on equipment list modeled (as per data sheet/preliminary vendor drawings). Packages
3.1
modeled as boxes.
3.2 Nozzles, Manholes & associated platforms for static equipment (orientations and Location)
3.3 Equipment Check – Location correct for Erection / Removal
Handling
3.4 Obstruction Volumes of Handling ways & handling
3.5 Obstruction Volumes of davits/etc. modeled
7.0 HVAC
7.1 Main HVAC system routes and rooms positioned.
8.0 Structural
Primary structure modeled (including pipe racks, and main structures modeled as single-line typical profiles
8.1
with main cable tray supports, monorails, main entrances, platforms)
8.2 Preliminary representation of secondary structures outlined
8.3 Stairs for primary escape modeled
8.4 All the connections likely to create clashes modeled (gussets, stiffeners, pad-eyes, bracing etc.)
10.0 Others
60% Review
No. Item
1.0 General
1.1 Tags of 30% model review closed
Documentation status
Safety studies issued and recommendations implemented into the design, with particular attention to FERA,
1.2
QRA and noise assessment
Vendor Data for key equipment available at least in first revision. Main equipment modeled according to
1.3
Vendor data, including nozzle orientation, size and utilities connection
1.4 Plot Plan in line with the 3D Model. Extent of Module/Plant and Direction Check against Plot Plan/Ship’s GA
1.5 Process & Utility Flow Diagrams in final revision
Process and Utilities P&IDs issued IFD at least, in line with HAZOP recommendations (i.e. HAZOP shall be
1.6
performed before 3D Model 60% and all the actions shall be closed)
1.7 Escape routes layout issued IFA at least and in line with the model
1.8 Drainage philosophy finalized. Drainage report issued and headers/lines modeled (above 2”).
1.9 Mechanical Handling philosophy finalized. Mechanical Handling report(s) issued.
1.10 Other documentation as per ToR agreed with Company
1.11 Other
Space for future construction and erection access – Detailed analysis available guaranteeing no impacts on
1.12
the design due to installation and management of future equipment
1.13 Interference and clash check performed
3.0 Mechanical
Equipment
All equipment on equipment list modeled as per Vendor data (first revision acceptable for minor equipment).
3.1 Size (and weight) in line with Vendor feedback. Equipment have been modeled complete with all components
and accessories, including insulation when required
3.2 Nozzles, Manholes & associated platforms for static equipment modeled as per Vendor drawings
3.3 Equipment Check – Location correct for Erection / Removal
Handling
Mechanical Handling Equipment (Crane, Monorail, Davit, Pad Eye, EOT etc.) all modeled and with clear
3.4
identification of handling routes and handling obstruction volumes
3.5 Projection of monorails for loading/ unloading/ dropout area
7.0 HVAC
7.1 Secondary HVAC routes modeled
8.0 Structural
Primary structure modeled and finalized. Beams, columns, braces and main connections, stairs and accesses
8.1
modeled.
Definition of Secondary structures based on Vendor equipment data including monorails, davits, overhead
8.2
travelling cranes, etc. as per single-line drawings
8.3 Pipe racks as per single-line drawings finalized
8.4 Stairs and walkways as per single-line drawings finalized
8.5 Cable trays supports for electrical and instrumentation cables defined
8.6 All the connections likely to create clashes modeled (gussets, stiffeners, pad-eyes, bracing etc.)
10.0 Others
90% Review
No. Item
1.0 General
1.1 Tags of 60% model review closed
Documentation status
1.2 Safety studies completely finalized
1.3 Vendor Data for key equipment all available in final revision.
1.4 Process and Utilities P&IDs issued IFC
1.5 Escape routes layout issued IFC
1.6 Mechanical Handling report(s) issued IFC
1.7 Other documentation as per ToR agreed with Company
1.8 Other
Space for future construction and erection access – Detailed analysis available guaranteeing no impacts on
1.9
the design due to installation and management of future equipment
1.10 Interference and clash check performed
3.0 Mechanical
Equipment
3.1 Equipment upgrade (based on Vendor IFC drawings).
3.2 Nozzles, Manholes & associated platforms for static equipment modeled as per Vendor drawings
3.3 Machinery and packages upgrade (final Vendor data)
7.0 HVAC
7.1 Fire and gas/ESD devices modeled
8.0 Structural
Secondary structures finalized including monorails, davits, overhead travelling cranes, etc. as per single-line
8.1
drawings
8.2 Tertiary structures finalized
8.3 Cable trays supports for electrical and instrumentation cables upgrade and finalized
8.4 All the connections likely to create clashes modeled (gussets, stiffeners, pad-eyes, bracing etc.)
10.0 Others