DPR Indravati Final V4 Total 2
DPR Indravati Final V4 Total 2
DPR Indravati Final V4 Total 2
Table 2- Performance of commercial crystalline silicon PV Technologies. (It is possible that some multi-
crystalline cells cross the 15% limit due to quality of the process used and the silicon.)........................................26
Table 4- A comparative advantage and disadvantages of floating PV plants and traditional ground-mounted PV
installations...........................................................................................................................................................35
Table 7 Barriers and Best Practices (Source - Enabling floating solar photovoltaic (FPV) deployment, USAID-NREL
June 2021)..............................................................................................................................................................93
Table 10- List of FPV system suppliers with EPC services offered (based on SERIS report, 2018).........................106
Table 12- FPV projects in India with their respective investment costs.................................................................114
Table 13- Salient features, reservoir capacity and water spread of Indravati Dam............................................117
Table 14- Comparison of GHI of the Indravati site based on different sources..................................................121
Table 25- Summary of the business models for the implementation of the project........................................159
Figure 3- Variation of the LCOE with the CAPEX considering 8% discount factor...............................................23
Figure 1- Detail of the components of a c-Si module and the assembly (source: Saint – Gobain)...........................27
Figure 6- Example of a floating PV system in Japan ((Hyogo prefecture, Japan - 1,076 kWp)................................37
Figure 15 Design for an underwater grounding system for a floating PV (Photovoltaic) system...........................55
Figure 18- Overview of the SERIS testbed in the Tengeh reservoir in Singapore....................................................61
Figure 19- Bird’s eye view of the SERIS testbed at the Tengeh reservoir in Singapore...........................................62
Figure 20- Comparison between the ambient temperature (weighted temperature of the air: OnS – land, OffS –
water).................................................................................................................................................................... 63
Figure 21- Comparison between the wind speed (weighted wind speed: OnS – land, OffS – water).....................63
Figure 22- Comparison between the air humidity (weighted average humidity: OnS – land, OffS – water)..........64
Figure 23- Albedo for 15 Mar 2017 and similar to the average (OnS – land, OffS – water)......................................64
Figure 26- Comparison of the performance of the floating PV systems versus a reference rooftop system.........67
Figure 27- Major problems witnessed at SERIS testbed on the floating PV systems..............................................68
Figure 30 – 6.3 MWp Queen Elizabeth II reservoir solar project in operation since 2016..................................79
Figure 31 – A sight of Sellingen solar plant with 41 MW DC. The 72,000 solar modules have a west-east
orientation. The plant is located in a former sand extraction lake.....................................................................79
Figure 32 – Alqueva dam in Portugal, where 70 MW of Floating PV are set to become the largest FPV plant in
EU..........................................................................................................................................................................80
Figure 34 – SDE ++ scheme for floating PV in 2020: Ranking and phases by maximum category base amount
............................................................................................................................................................................... 87
Figure 36 - O'MEGA1 was one of the first large solar PV plant in Europe based on floating solar technology
(Hydrelio@ from Ciel y Terre) Source: Akuo.......................................................................................................88
Figure 38 – Overview of key stakeholders in the FPV industry including in the EU...........................................90
Figure 41 – Dutch Offshore FPV specialized company “Oceans of Energy” projects: EU-SCORES Offshore
Wind+FPV project on the left side and 1 MW “North Sea 2” project on the right side ,being the world´s first
offshore FPV system to be connected to the grid ,and enduring extreme sea conditions, including 6
consecutive storms in February 2022...................................................................................................................92
Figure 42- Annual installed capacity of Renewables, including solar PV, according to IRENA in 2022............100
Figure 47- Top ten floating PV markets from 2020-2024 (Source: IHS Markit).....................................................104
Figure 48- Capacity share of floating system providers in the top 50 FPV projects..............................................107
Figure 49- Cost break up for floating solar PV plants (Source: TERI).....................................................................115
Figure 50- Overview of proposed bids for various tendered FPV projects............................................................115
Figure 51- Investment cost for floating solar PV projects in India (Source: TERI)..................................................116
Figure 54- Global horizontal irradiation of the state of Odisha (Source: Solargis)............................................123
Figure 57- Water Spread Area at the lowest water level – using Google earth................................................134
Figure 81- Indicative layout of the infra-structured peer for floating PV assembly...........................................137
Figure 88- indicative layout of the proposed infra-structured peer for assembly of floating PV plants..........147
1. “Act” or “Electricity Act” or “Electricity Act, 2003” shall mean the Electricity Act, 2003 and include any
of its modifications, amendments and substitution from time to time.
2. “Buoyancy” shall mean Hydrostatic force acting on a partially or fully submerged body, equal in
magnitude to the volume of water displaced by the object
3. “Capacity Utilization Factor (CUF)” shall mean ratio of the actual energy supplied from the floating
solar plant over the year to the maximum possible energy that can be supplied against the declared
project capacity at delivery point in a year e.g. In any Contract Year, if ‘X’ MWh of energy has been
metered out at the Delivery Point for ‘Y’ MW Project capacity, CUF= (X MWh/(Y MW*8760)) X100%;
5. “Commissioning” with respect to the Project/ Unit as certified by GRIDCO shall mean when all
equipment as per rated capacity have been installed and energy has flown into the grid for the purpose
of commercial operation.
6. “Commercial Operation Date” with respect to the Project / Unit shall mean the date on which the
Project/ Unit is commissioned (as certified by GRIDCO) and available for commercial operation and such
date as specified in a written notice given at least 15 (ten) days in advance by the Successful Bidder to
GRIDCO.
8. “Delivered Energy” means the kilowatt hours of Electricity actually fed and measured by the energy
meters at the Delivery Point and as certified by Odisha SLDC. In case of net import of energy during a
month, the Successful Bidder shall be required to make payment to Discom at the rate of high-tension
temporary tariff as determined by Odisha Electricity Regulatory Commission (OERC) from time to time.
In case of net export of energy during a month, the Successful Bidder shall be eligible for the receiving
agreed tariff from GRIDCO for such net delivered energy.
9. “Delivery Point/ Interconnection Point” shall be the point or points of connection at which Electricity is
delivered into the grid system of the Odisha Power Transmission Corporation Limited (OPTCL) system.
11. “Electricity Laws” shall mean the Electricity Act, 2003 and the relevant rules, notifications, and
amendments issued thereunder and all other laws in effect from time to time and applicable to the
development, financing, construction, ownership, operation or maintenance or regulation of electric
generating companies and utilities in India, the rules, regulations and amendments issued by CERC/
OERC from time to time.
12. “Element” shall mean Individual float or interconnection which forms part of an FPV
13. “Energy Yield Assessment” shall mean modelling of the average yearly expected energy production of
an FPV system over the lifetime of the project
14. “Environmental Actions” shall mean any external phenomenon (e.g., Wind, waves, current) which may
cause a load on a structure
20. “Metering Point” shall be at the Grid-connected solar PV plant end switchyard. For the purpose
21. “Meteorological Measurement” Station shall mean setup of measurement sensors in one unit for the
measurement of meteorological parameters for input in the energy model MNRE: Shall mean Ministry
of New and Renewable Energy.
23. “Mooring” shall mean mooring system applied in a time-restricted period during building and
installation. Can include components that will be part of the final mooring system.
24. “Multibody Float” shall mean floating structure composed by multiple floats with internal
interconnections between them.
27. “Permit” shall mean Official document authorizing someone to do or build something
28. “Pooling Substation” shall mean an intermediary Substation where more than one Solar Floating PV
Project may connect for further connectivity through a common transmission line to STU / CTU System
for evacuation of power.
29. “Power Degradation” shall mean the operation of a unit at less than its rated maximum capability (at a
given time)
30. “Power Purchase Agreement” or “PPA” shall mean the power purchase agreement signed between
the Successful Bidder and GRIDCO project wise according to the terms and conditions of the standard
PPA enclosed with this RfS;
31. “SCOD” or “Scheduled Commercial Operation Date” shall mean the date as declared by the Successful
Bidder in the PPA which shall not exceed 18 (eighteen) months from the date of signing of PPA.
However, GRIDCO reserves the right to refuse the purchase of power 3 (three) months earlier to
Scheduled Commercial Operation Date.
34. “STU” shall mean the State Transmission Utility i.e., OPTCL.
35. “Voltage of Delivery” means the voltage at which the Electricity generated by the Project is required to
be delivered to the STU periphery.
Some of the reasons that come as a direct benefit from floating PV:
4. It can be an opportunity for countries and regions with significant number of bodies of water.
6. Hydro reservoirs are usually close to the grid and are available
The floating system, mooring/anchoring system, cables (underwater), and PV modules/inverters make up a
floating solar PV system. FPV plants are used in waterbodies and are frequently exposed to harsh
conditions. As a result, it's critical to examine suitable criteria to maintain the quality of FPV plant
components while also avoiding harming water quality and local biodiversity. There are no particular
standards for FPV and the same applicable to PV are used.
About 18,000 km2 of water surface area across several states has been identified as suitable for the
installation of FPV plants, with a capacity of around 280 GW being possible. The percentage of water surface
area covered, water level changes, the purpose of the water body, and the proposed plant location are all
aspects that go into calculating the total potential.
a. Support FPV deployment on otherwise unusable land and artificial water bodies, as opposed to
natural water bodies that may have a more complex environmental review process; and
b. Encourage RE deployment, including FPV deployment, via national targets and regional requirements
India now has 92 MW of installed FPV capacity, with another 1,700 MW under construction. India's water
reservoirs are expected to hold around 28,000 MW of FPV capacity. Multiple tax incentives and FPV-specific
auctions are available in India. Overall, India offers one lesson on encouraging FPV deployment:
With around 110 MW of installed capacity, the Netherlands leads Europe in FPV deployment. The
government backs FPV projects as part of its overall renewable energy plan, as well as through the
Sustainable Energy Production Incentive grant program. The difference between the cost of generating
electricity from the FPV system and the current wholesale market price is reimbursed under this program.
a) Providing direct financial incentives like production-based incentives can help de-risk FPV systems; and
b)Encouraging interagency cooperation can help encourage FPV development by reducing the
administrative hurdles to deployment.
To enhance the reliability and safety of FPV projects, industry players have agreed to adopt a set of shared
rules and procedures known as RP- Recommended Practices. These recommendations usually combine pre-
existing standards for solar PV equipment, like as IEC and ISO norms, with other relevant quality
requirements for floating structures, as well as the environmental concerns of FPV locations.
DNV, an international recognized registration and classification organisation based in Norway, was one of
the first entities in Europe to provide an RP for the floating PV sector. It has released a report titled "DNV GL
RP – Design, development, and operation of floating solar PV systems," which details the essential needs
and suggestions for the various stages of FPV park construction and equipment.
The International Electro-Technical (IEC) Commission, has not yet developed fully robust international
standards for the floating PV technology
French-based Ciel&Terre floating structure manufacturing has patented a water-based PV concept named”
Hydrelio”, that is certified for harsher environmental conditions and is a good example of specific compiled
standards into a FPV technology.
In the EU, several countries have implemented innovative forms to attract major private FPV stakeholders
and foster the RE intake coming from floating solar. To achieve the country’s solar energy generation
capacity goals, one of the major approaches done by the Portuguese government has been through
implementation and development of solar auctions. In 2021, the country launched an auction for 263 MW of
floating PV projects, for 7 pre-identified water reservoirs, located in major dams. All the reservoirs are public
waterbodies, with the beds and banks being private. Under the defined mechanism, the selected developers
will be allowed by the government to have the right to use the water for 30 years. The tender for floating PV
plants in Portugal included these main features: 1
Right of private use of a portion of the Public Water Domain, intended for the installation of a float -
ing solar plant, for electricity production, in public water reservoirs.
The installation, operation and conservation of the structures of the FPV and the required grid con-
nection needs.
The use of public water domain land allocated to the Concession.
In cases where the installation of the floating solar power plant implies the occupation of lands that are not
part of the Public Water Domain affected by the Concession, the Concessionaire will be responsible to
obtain the rights, bearing all the expenses of your hiring, service contract and/or indemnities.
The FPV technology is present in several R&I programs engaging the public and private sector. The main
ones, where several EU countries are major partners, include:
It is focused on tackling climate change, fostering the UN´s sustainability goals and increasing overall EU´s
competitiveness.
Floating PV is addressed in the area of sustainable, secure and competitive energy supply with main focus on
innovative foundations, floating substructures and connection systems for floating PV and ocean energy
devices. Several outcomes and actions were defined for the programme.
Defined as a joint roadmap of global innovation priorities, it was developed by several public-private
stakeholders worldwide in 2021, The main focus of the roadmap has been to define a pathway to guide large
scale R&I investment, energy policy and boost international cooperation towards a more sustainable future
1 https://apambiente.pt/sites/default/files/_SNIAMB_Agua/DLPC/Fotovoltaicos/Anexos/leil%C3%A3o-solar-flutuante-
caderno-de-encargos_dph.pdf
EU-India Clean Energy and Climate Partnership (CECP) Page 12
and a shift to clean energy, such as the floating PV. The joint roadmap identifies the top 100 global
innovation priorities necessary for a faster energy system reform and modernization and
solutions/challenges for the decarbonization of the society.
The roadmap addresses 3 key pillars, namely Affordable and reliable VRE, System flexibility and market
design, and data and digitalization for system integration. The mission has identified key Tipping Points (TP)
against each pillar which need to be met to achieve its goal.
3- EU-SCORES
The EU-SCORES is led by the Dutch Marine Energy Centre and will demonstrate the combination of offshore
wind-wave, and offshore wind - offshore floating solar PV, by the development of two demonstrations
composed of the hybrid RE systems.
These demonstrations will prove how the increased power output and capacity installed per km2 will help to
reduce the amount of marine space needed and will provide knowledge on how to effectively scale-up
offshore hybrid systems in Europe.
By the middle of 2019, India had roughly 2.7 MW of installed FPV capacity and 1.5 GW of projects in
construction. By 2022, the Indian government wants to have 10 GW of FPV capacity installed. FPV tender
Regarding solar irradiation, the western part of the state receives more GHI than the eastern part. Also, the
Indravati dam is located in a site with good GHI potential, making it prone to a good yield from solar PV
projects. To determine the GHI for the Indravati site, data obtained from different sources were analyzed
and compared.
Bathymetry analysis: not able to conduct the bathymetry studies and also not able to gather the relevant
data from the local water basin management office, despite the official requests and efforts conducted.
Thus, our analysis is based on the best available desktop assessment with the data provided by OHPCL in
terms of the water levels.
Seismic analysis: The site falls in Seismic Zone III of the seismic zone map of India – IS 1893-2002. The zone is
liable to MSK VII and is classified as the Moderate Damage Risk Zone. The IS code assigns a zone factor of
0.16 to this zone
Flooding analysis has shown that the Godavari basin does not flood substantially in Odisha and that the
tributary Indravati is also contained in the selected area.
Water quality analysis: The Indravati dam receives water mainly from the Indravati River. The water quality
seems to be potable or at least not polluted as the dam is used for the irrigation of land.
From the analysis of the data provided by the Indravati basin manager, the proposed catchment area
selected for the floating solar plant is adequate for installation of 160 MW Floating Solar Plant based on
available water spread area at the RL level of 627 m which is very close to the Dead storage level (625.00) of
the dam. Hence, the portion of water body selected above can be used for the development of the floating
solar plant.
Particulars Coordinates
The recommendation is for assembly point 2 as it is nearer to the site (marked as proposed assembly below)
and with a reasonable logistic access. However, the other assembly points are validated technically and
from the environmental and social perspective and may be used. A peer type is planned to provide support
the assembly area and to make it convenient to the operation and maintenance of the FPV plants.
2) Pooling station
Pooling area will require an area of about 1 – 2 hectares. The location of the recommended pooling area is
shown in the image below and is located at around 900 m from the floating PV site.
3) Grid substation
A meeting with Odisha Power Transmission company (OPTCL) was held to identify the existing
substations (132 kV and above) that could evacuate power from the Indravati site. After identification of
the substations, the Tentulikhunti 132kV substation has been selected at 18.5 km from the site and has
space for expansion. The Tentulikhunti substation as well as the alignment of the transmission lines can
be seen in the following figure.
To ascertain the applicability of relevant national, state level legislations and IFC Performance Stand -
ards from environmental and social safeguard point of view.
To understand the existing/baseline environmental and social elements of the proposed project site
and project influence area.
To map relevant stakeholders involved in the project and carryout primary consultation with these
identified stakeholders.
To identify the environmental and social impacts that may result due to the proposed project and pro -
pose measures to avoid, mitigate and reduce these impacts.
To outline an environmental and social management plan for implementation and monitoring of pro-
posed mitigation measures in difference stages of the project.
The environmental and social baseline profile of the project area is established through primary and
secondary study and analysis. The primary environmental monitoring is conducted to collect the information
with respect to attributes of the physical environment such as air quality, water quality, noise level and soil
quality of the project area. Whereas the information on other physical components and natural hazards such
as floods, and earthquakes were collected from literature reviews and stakeholders’ consultations. Further,
the field visit was carried out by the environmental and social specialist to understand the baseline profile of
the proposed site locations and to validate the findings of secondary study.
The area earmarked for the FSPV (floating solar photovoltaic) Plant on the Indravati reservoir is adjacent to
the villages of Talnagi and Murka, falling within the Thuamul Rampur block in the Kalahandi district. As per
the consultation with District Welfare Officer (DWO), due to the presence of higher number of Scheduled
Tribe population, the Thuamul Rampur block is designated as Schedule 5 area. Therefore, the villages of
Talnagi and Murka too fall under such areas as they fall under the TH Rampur block. The assembly point and
the pooling stations are all proposed to be located within the Talnagi village boundary. Areas proposed for
Pooling station 1 and 2 are currently being used for agricultural use by the local inhabitants. Also, the land
earmarked for Pooling Station 2, is situated in close proximity to the docking area for boats used by the local
people for travelling across the reservoir to villages on the other sides. Proposed Assembly Point 1 is located
very close to the reservoir boundary and as per the locals, is subsumed under water during the monsoons
when the reservoir is full. Proposed assembly point 2 not visited due to lack of access.
Around 10-15 households from the locality rely on fishing from the proposed FSPV area. Fishing activities are
carried out mostly in the monsoon months (July to October) as the rain brings the fish to the upper levels
making it easier to net them.
In consideration of proposed interventions and baseline findings, the potential E&S risks and impacts as well
as applicability of potential regulatory E&S norms were analysed. In the report, the approach to
manage/mitigate the negative Risks and Impacts and to maximize positive impacts are discussed. The broad
level action plan in form of Environmental and Social Management Action Plan (ESMAP) is also provided to
ensure implementation of various safeguard measures and its supervision in effective manner throughout
the project lifecycle.
Key recommendations given in the preliminary environmental & social assessment report, are
summarised below:
o ESIA & ESMP: It is recommended to undertake a detailed Environmental & Social Impact Assess-
ment (ESIA) in line with the requirement of IFC Performance Standards at detailed design stage
towards development of ESMP, RAP, Gender Action Plan, Livelihood Restoration Plan, Labour
Management Plan, Traffic Management Plan etc. as applicable based on the finding of ESIA.
o Detailed Ecological Study: Assessment of terrestrial (including bird) and aquatic ecology prior to ini-
tiation of site related activities as well as during implementation of project.
o Given the significant presence of scheduled tribes in the project area, the project proponent should
prepare an Indigenous Peoples Plan (IPP) in consideration of IFC PS 7 requirements.
o The project proponent should ensure robust Stakeholder Engagement and Grievance Redress
Mechanism throughout the project lifecycle in accordance with IFC PS.
o Environmental and Social Auditing (Construction & Operation phase) through external agency
should be carried out.
The physical construction of the system follows a modular approach, which is field-tested and is used for
appropriate delivery of power systems. The FPV plant is considered as 188 MWp of DC capacity and 160 MW
of AC capacity.
1) Modules:
The following model was used for energy yield estimation and project design. It is one of the TIER-1
manufacturers of PV modules. However, it is not meant to recommend this, or any model and the project
A total of 28 Modules in series will be attached to every string. Such strings will further form in 4 rows
making an array of 4 x 28 modules. These arrays will then join to form a 6 MWp island. Module capacity
considered for configuration is 550 Wp. Total number of PV modules that will be used for the whole plant is
341824 modules.
2) Inverters
Several branches of the array are connected together in parallel. The complete output of the array is
converted to AC through a single central solar power inverter and then fed to the grid. The inverter capacity
selection is done considering the size of islands and inverter DC load ratio (ILR). ). In order to carry out the
energy yield estimation, 5 MW rating of Siemens outdoor central inverters have been selected. These
inverters will be installed within each 5.88 MWp floating PV island. As the total number of islands are 32, the
total AC capacity of plant will be 160 MWac.
3) Transformers:
- 50 MVA 33/132 kV
Tilt (Degree’s) 5
No of modules 1069096
Inverter Siemens
Sinacon
Inverter Capacity 5 MW
No of Inverter 100
The losses in the Solar PV System depends on the Solar PV Module and Inverter technology used, efficiency
and quality of PV Modules, Inverter, Junction Boxes and cables, workmanship of installation and scheduled
maintenance and cleaning. The following table shows the technical losses used in the simulation.
Assembly point
1 Land Development and As- Lot 0.5 188 94 90 7
sembly works
2 Peer construction with hoists Lot 3896104 1 3896 3727 300
and other machinery for load-
ing and unloading
Pooling station
1 Transformers - Inverter & Lot 3896 360 1403 1342 108
Step up
2 Switchgear and Panels Lot 3247 360 1169 1118 90
3 SCADA, Surveillance, Fire Lot 10 188 1880 1799 145
Fighting, Safety, Monitoring
4 Buildings Lot 324675 1 325 311 25
5 Drains, Road, fencing and Lot 64935 1 65 62 5
gates
Grid connection
1 132 kV Double Circuit over- KM 51948 17 883 845 68
head line (21 km)
2 132 kV bays at Tentulikhunti Lot 77922 2 156 149 12
substation (with switches and
protections)
Add
Contingencies 3.00% 3626 3469 279
Local Area Development 1299 1243 100
Pre- Project development ex- 1299 1243 100
penses (permits and authoriz-
Based on the International Energy Agency definition of LCOE and with a 1,5% of the total installation CAPEX
as the OPEX and a loss of efficiency of the modules per year of 0,5%, the following results were obtained for
the LCOE; which are in line with the current tariffs for floating PV projects in India.
floating PV plant developed on the basis of the single IPP plants, which could even be done as
captive plants also. All the costs would be under the responsibility of the developers as well as
the potential interest of an off taker, which could be in the state, outside the state or a
private(s) customer. Multiples of 40 MW to be deployed.
floating PV park development with FPV plants being developed in the normal roll-out of PV
projects in solar parks as per the relevant Indian regulation. Not being the aim of this DPR to
detail the solar park scheme, the scheme could be used to avail up to 20 lakh/MW for the
external infrastructure of the solar park, while the rest could be charged from the IPPs as well
as the facilities for the assembly and O&M. Under the estimated cost of the project this could
mean 100 Cr of reduced cost, which is the cost of the grid connection part. Plots of 100 MW to
be auctioned.
An IPP develops a floating PV plant on a reservoir and sells power to the discom or through
open access to a customer in the Indian grid (captive power). This requires for securing the
license to install the FPV plant in a water body, the development of the FPV plant, obtain the
connection to the grid, sign a PPA and apply for a license to generate solar power.
The IPP develops a floating PV plant in a floating solar park. To be able to access the floating
park, the IPP would have to compete in tariffs to get in. The obligations in terms of licensing
would remain, but the PPA would be secured
3.1 PV modules
PV technologies are mainly divided into two types: non concentration technologies and concentrated
technologies (CPV). The non CPV types can be further divided into those that work based on fixed
mounting – usually at latitude tilts – and those that work on trackers.
For the CPV technologies the relevant solar irradiation component is the Direct Normal Irradiation (DNI)
while for non-Concentrating technologies and fixed mounting the relevant component is the Global
Horizontal Irradiation (GHI). For the technologies that use tracking both GHI and DNI are useful though
usually it is used the Global Normal irradiation (GNI) for two axis tracking or an adapted version of the
GHI for one axis tracking.
Non-commercial PV technologies are not going to be evaluated namely organic PV, nano cells, PV dyes
and other technologies under research.
PV stands for photovoltaic, and the effect described by Albert Einstein in 1905 as “the creation of
voltage or electric current in a material upon exposure to light”, which granted him the Physics Nobel
prize in 1921. Some elements in nature are able to maximize this photovoltaic effect and they are the
basis of PV solar cells. Those materials are silicon and germanium. The properties of silicon were
explored, and mono, poly and amorphous silicon are used as materials for PV cells, while later
combinations of gases and other elements yielded also good results and a new wave of PV modules
based on films rather than cells arrived to the market – CdTe (Cadmium Telluride) and CIGS (Copper
Indium Gallium Selenide). These promising technologies did not used silicon and could be manufactured
in large quantities at cheaper costs than silicon-based modules, based on the costs of silicon at the time.
Since then, the industry has undergone a revolution with costs falling rapidly leaving thin films with the
only option to increase its efficiency of risk being out of the market.
Melting of polysilicon to form ingots and slicing these ingots into wafers.
Wafer transformation into cells by creating p-n junctions, metal (silver) contacts and back-coating
(metallisation);
Cell assembly, connection and encapsulation into modules with protective materials (e.g., transparent
glass, thin polymers) and frames to increase module strength.
Figure 1- Detail of the components of a c-Si module and the assembly (source: Saint – Gobain)
› Coating of the substrate with a transparent conducting layer (TCO - Transparent conducting oxides)
› Deposition of the active layer by various techniques (e.g. chemical/physical vapour deposition)
› Encapsulation in a glass-polymer casing. Roll-to-roll techniques are often used with flexible substrates
to reduce production time and costs.
Amorphous-Si 4–8
CdTe 10 – 16
CI(G)S 7 – 12
A bifacial solar cell, in contrast with a mono facial solar cell, has identical metallic grids on both front and
back surfaces. The generation of additional electrical energy from the rear surface depends on the
materials properties of the reflecting surface and its location. Some of the key parameters for the
reflector include its slope with respect to the panel plane, distance from the panel, and reflection
efficiency. This is an important aspect to maximize the power output.
Simple polar trackers or horizontal trackers allow azimuth tracking though they may also have an
adjustment along a second axis (angle of declination). This allows to align the panel to face the sun
when it is higher in the sky (and further northward) in the summer, and to face it lower in the sky (and
further southward) in the winter (examples for the northern hemisphere). It might be set with manual
or automated adjustment, depending on the polar tracking device. If the angle of declination is not to be
used during the year, it is normally set to zero degrees, facing the panel perpendicular to the polar axis,
according to the mean path of the sun.
Tracking being an extra cost to the system requires that the additional generated electricity offsets the
additional capital cost, the electricity required to move the tracker and the maintenance of the tracker.
The competitiveness of PV trackers has been affected “negatively” because of the rapid drop in PV
panel prices. The price drop puts a direct demand on reduction of the tracker prices, so that the
investment in a tracker system makes economic sense.
IEC 61730 - Photovoltaic (PV) module safety qualification: Part 1: Requirements for construction; Part 2:
Requirements for testing
IEC 61215 - Terrestrial photovoltaic (PV) modules - Design qualification and type approval: Part 1: Test
requirements; Part 2: Test procedures
IEC 61215 - Terrestrial photovoltaic (PV) modules - Design qualification and type approval: Part 1-2: Special
requirements for testing of thin-film Cadmium Telluride (CdTe) based photovoltaic (PV) modules; Part 1-
4: Special requirements for testing of thin-film Cu (In,GA)(S,Se)2 based photovoltaic (PV) modules
IEC 62804 - Photovoltaic (PV) modules - Test methods for the detection of potential-induced
degradation: Part 1: Crystalline silicon
IEC 60068 - Environmental testing: Part 2-52: Tests - Test Kb: Salt mist, cyclic (sodium chloride solution)
IEC 62782 - Photovoltaic (PV) modules - Cyclic (dynamic) mechanical load testing
On-grid inverters control the voltage applied to the PV modules to extract power and also convert DC to
AC. When there is no grid, on-grid inverters will not work. On-grid inverters control and optimize the
voltage applied to the PV modules. Two main technologies are used:
PWM – Pulse width modulation. Currently the market does not offer this option for on-grid inverters.
MPPT – Maximum power point tracking control. Currently it is clearly the market option for on-grid
applications.
The DC/AC conversion can be made through two types, currently available in the market:
With transformers - providing a galvanic isolation between the PV DC input circuit and the AC Grid
output circuit. These inverters have a slight decrease of electromagnetic radiation (electrosmog)
compared with transformer less. They are robust and in the market for several years and its reliability is
well known.
Without transformers (mosfet and IGBT technologies) - transformer less inverter technology uses a
computerized multi-step process and electronic components to convert DC to high frequency AC, back
to DC, and ultimately to standard frequency AC transformer less inverters do not have electrical
The IEC 62109-2 safety standard for PV inverters requires that the isolating transformer is mandatory
when there is no double insulation on the output of the inverter. Transformer less inverters usually use
two contact relays connected in series to provide the same level of safety as with transformers.
Regarding the type of the AC waveform produced, inverters do also provide different options: square
wave, modified square wave, and sine wave.
Square wave inverters are inexpensive, but they typically provide poor output voltage control, limited
surge capacity, and significant amounts of harmonic distortion.
Modified square wave inverters utilize more complex circuitry to create a wave form more closely
approximating a true sine wave. They are capable of handling greater surge loads and have an output
with less harmonic distortion.
Sine wave inverters or power inverters are best for powering sensitive electronics that require a high-
quality wave form. They have little inherent harmonic distortion and typically have surge capacities of
double or greater the continuous output rating. This are the type of the on-grid inverters.
The system inverters typically provide power output at voltages of the order of 550 VAC. Electricity grids
operate at much higher voltages of the order of tens or hundreds of thousands of volts, so transformers
are incorporated to deliver the required output to the grid.
KNAN is a transformer that uses less flammable non-mineral oil such as silicone oil, synthetic ester or natural
ester (FR3) as the insulating fluid with natural air convection cooling. KNAF has same transformer oil as
KNAN but with external forced air cooling.
Traditionally transformers have used mineral oils, but industry has now acknowledged the drawbacks of
traditional mineral oil namely- flammability, poor biodegradability, low moisture tolerance and corrosive
Sulphur.
Transformer ester oils (non-mineral oils) can be classified in to two groups- Synthetic and Natural. Synthetic
esters are manufactured from raw materials and additives are added to tailor its performance to a specific
application (such as cold climates).
Natural esters are made from renewable materials such as canola, soybean etc. A common non-mineral
oil used in KNAN/KNAF transformers is FR3 which is formulated from edible vegetable oil along with
performance enhancing materials. It does not contain petroleum, halogens or other harmful materials.
FR3 has exceptionally high ignition point of 3600C and flash point of 330°.
Junction Boxes
In the Junction boxes, individual module strings are bundled and safely routed to the inverter. It is a
combination of an exact, well-organized string monitoring system and a safety concept adapted to the
PV technology.
The junction boxes will have suitable cable entry points fitted with cable glands of appropriate sizes for
both incoming and outgoing cables. They monitor the output of solar PV arrays. If the difference
between string outputs is too large, the operator is informed though monitoring system. Active
disconnection allows string voltages to be measured separately. These junction boxes are enclosed in IP
SCADA System
An integrated SCADA (supervisory control and data acquisition) is one which can communicate with the
Inverters and provide information of the entire Solar PV grid connect power plant. The SCADA provide
information of the instantaneous output energy and cumulative energy for each of the inverters as well
as for the entire power plant.
Weather Station is specifically designed for solar PV systems, providing comprehensive environmental
monitoring solution for users with a variety of sensors, including solar radiation, environmental
temperature and humidity, wind direction, wind speed and back-of-module temperature, etc.
The continuous monitoring of operating conditions at an FPV plant requires a robust PV system
monitoring solution.
These sensors measure critical meteorological parameters that are normally used to analyses the
performance of the PV system.
DC cables from series connected modules are planned to be taken into junction boxes for parallel
connection, where in the amperage of string are increased without increasing already designed higher
system voltage. These junction boxes are of IP65/IP54 depending upon location and environment. The
above compliance will help in achieving location and environment. The above compliance will help in
achieving fulfilment of requirements like dust free, vermin free and weatherproof. The junction box
could be either made from MS sheet metal, aluminum die cast or thermoplastics. Low diameter DC
cables with cable glands from strings will be fed into I/P side and higher diameter DC cables from O/P
side of junction boxes.
The Solar PV Power Plant should be provided with Lightning and over voltage protection. The main aim
of over voltage protection is to reduce the over voltage to a tolerate level before it reaches the PV or
other subsystem components. The source of over voltage can be lightning or other atmospheric
disturbance.
Cables
As solar farms are exposed to varying atmospheres, the cables will be exposed to ultraviolet rays. This
reduces the life span of the cable. So, cables with UV protection must be used. Companies like Polycab,
Havells, and RPG etc., are manufacturing these cables. Cables and necessary connectors will be sourced
from these companies. Sizing of cable are estimated based on design parameters like voltage, current,
losses. Etc. Normally the cables used are bare copper conductors and per DIN standard and IEC codes
they should be flame, oil, ozone, UV resistant and should be halogen free. Solar cables are extremely
robust and resist high mechanical load and abrasion. High temperature resistance and excellent weather
proofing characteristics provide a long service life to the cables used in large scale projects. The
Transmission Pole
The supporting structure for overhead lines is required to keep the bare conductors at a suitable level
above the ground. These may be various types of poles or towers.
The following are main types of Poles and Towers For Transmission Lines generally used in the overhead
system:
Steel poles
R.C.C. poles
Steel towers
The choice of line support for a particular case depends upon the line span, x-sectional area, line voltage,
cost and local conditions.
Rail poles
Tubular poles
Rolled steel joists
The Rail poles are of the shape of track used for railways. Tubular poles are of round x-section generally
having three diameters for 1/3rd of the length of the pole and rolled steel joists are of ‘I’ cross-section.
These poles possess greater mechanical strength and thus permit the use of longer spans (60 to 80
metres). These poles have the longer life (more than 40 years) which can further be increased by regular
painting. At the bottom (the portion which is buried underground), these poles are set in concrete muffs
in order to protect them from chemical reactions. Tubular poles having a height of 9 to 11 meters are
generally used for distribution purposes in the cities to give better look.
The steel rail poles in height of 11 meters to 13 meters are used for 11 kV and 33 kV lines respectively.
However, these poles are very costly and require painting.
Floating PV plants are an emerging form of photovoltaic systems. There are installations in several
countries in Europe as well as in Asia mostly in Japan, and South Korea with a recent interest from China
that rapidly became the world leader. The interest is growing and there is already a demand for Floating
PV in India, USA, Australia and Morocco.
Figure 1- Example of a floating PV system in Japan ((Hyogo prefecture, Japan - 1,076 kWp)
Some of the reasons that come as a direct benefit from floating PV:
4. It can be an opportunity for countries and regions with significant number of bodies of water;
6. Hydro reservoirs are usually close to the grid and are available
Land/water surface Does not compete for land Suitable/affordable land may be
use with agricultural, far away from load centers,
industrial, or residential requiring costly transmission
infrastructure.
projects.
Requires change in land use,
Often easier to find sites
which can be time consuming.
near densely populated
Competes for land with city
areas.
dwellings, industrial
Potential integration with
development, and agriculture,
aquaculture though in certain cases
integration is possible
Power system 1. Synergy with existing
benefits electrical infrastructure (such
Costs of grid interconnection are
as hydropower plants)
2. Possible hybrid operation with often borne by project developer and
can be prohibitively high
hydropower
Engineering design
Technical Harder to access and replace parts Generally easy to access and
Wave action increases mechanical replace parts
wear and tear More vegetation
Biofouling likely Easier to deploy automated cleaning
routines
High-humidity environment
may accelerate corrosion/ Less maintenance for civil work and
oxidation of metal parts ground foundations
More maintenance for structural
elements
Easier access to water for cleaning
Lower risk of theft/vandalism
Safety Constant movement of floats poses Generally safe, with stable ground
walking hazards for walking
Risk of personnel falling into
water
India has done a remarkable job in terms of deployment of RE-based installation, growing almost 3.55
folds in the last 5-6 years, most of which have occurred in the onshore wind (37.27 GW) and solar PV
(32.53 GW) sector. The majority of this growth in solar has been triggered by the launch of Jawaharlal
Nehru National Solar Mission (JNNSM) on January 11, 2010. The target set under the mission was to
achieve 20 GW of grid-connected solar power by the year 2022, which was later revised in the year 2015.
The new targets under the mission are to achieve 175 GW RE capacities of which 100 GW is from solar by
2022. Out of this, 40 GW of the target is for installation of solar rooftop and 60 GW is for large-scale solar
plants. To achieve its targets the Government of India has also taken various innovative policy measures
such as viability gap funding (VGF), development of solar parks and solar renewable purchase obligation
(RPO), etc.
At present India’s grid-connected solar PV sector is majorly dominated by the ground-based installations
(93%) and rest is contributed by rooftop based solar PV installations. The installation cost of utility-scale
solar PV in the country has declined by 84% between 2010-2018, making India the world’s topmost
country in achieving the lowest installation cost for utility-scale solar PV.
However, the pace of utility scale solar PV deployment in the country has been reducing. Among several
reasons, challenges related to the availability of land and delay in land acquisition are considered as one
of the key reasons behind this slow pace. Hence, in order to achieve the targets, set under the JNNSM, it
is a must to explore the other alternatives. Deployment of solar PV at distribution transformer (DT) level
and floating solar PV (FSPV) are some of the alternative solutions that are emerging to boost solar
installation. FSPV has an advantage in deploying solar PV as it is not dependent on land availability.
There are more than 400,000 km 2 of the reported man-made reservoirs in the world out of which India
has a share of about 70,000 km2. This shows a vast potential that can be trapped for clean energy
generation.
Solar PV modules: standard crystalline solar PV modules are used for floating solar systems. Some
bifacial modules have been used. The PV modules must follow more stringent requirements than
land-based modules due to exposure to wet and corrosive environments, high quality sealants
should be used. Specially in projects installed on saline water, the PV modules will be required to
resist the long-term salt mist exposure. Metal will corrode over time and therefore anti-corrosive
coatings are required.
Pontoon/Floating System - A pontoon is flotation structure and has the capacity to support a heavy
load. This floating structure is designed to hold a number of panels.
Cabling: Generated power from the solar array is transported to land. The cables can be kept above
water or be under water. When cables are kept above water, they must be specifically designed to
be resistant against UV irradiation, extremely high temperature fluctuations and are unaffected by
the weather. If the cables are underwater, they should have also high temperature resistance,
excellent weather proofing characteristics and IP68 standard for underwater cables.
Several technical solutions of Floating Systems are presented below, from some reference suppliers.
MDPE and HDPE solution (source: NRG HDPE solution (source LG CNS)
energia)
Some of the plastic manufacturing companies, which produce under Blow Molding process and whose
main products portfolio are floating pontoon, floating fridge and floating dock, usually also include PV
Floating solutions. An example is provided below.
The open solutions promise a higher convection potential, as for example the reinforced fibre.
SOLARISFLOAT, a Portuguese company has already developed and marketed a two-axis tracking
floating PV solution. Tracking is achieved by rotating the entire floating platform to follow the sun from
east to west. The following figure shows the SOLARISFLOAT two axis tracking floating PV solution.
The anchoring at the bottom is the most widely used, with plate anchor or with dead weight.
Critical
As shown in Figure below, the cleaning techniques are categorized into water-based and water-free
approaches. Each individual technique has its own merits and demerits, which can come in handy in
cleaning FPV systems, but the lack of comprehensive analysis is obvious for the selection of the best
solution. Therefore, this section provides a critical analysis for applying the techniques to FPV
systems. Some of the described techniques use chemical solutions to reach more effective cleaning,
and accordingly, the techniques should be analyzed from an environmental point of view. The
water quality of the reservoir and water shortage in the region lead to different approaches.
Rainfall
Rainfall can help the cleaning process, but it is not accurately predictable and does not follow a
regular pattern. Moreover, the rainfall cannot completely remove the accumulated soil, and
usually, a complimentary washing step is needed. It must be noted that a cloudy and rainy
environment is usually not suitable for a PV system. Furthermore, many PV and FPV systems are
located in arid regions with low or inadequate rainfall. Therefore, in such regions, other cleaning
techniques should be applied to provide higher output power. From an economic point of view,
considering the fact that this technique does not need any apparatus for cleaning, it may seem to
be cost-effective. In some countries, such as Japan, where the application of FPV systems is
widespread, the precipitation is more than in arid regions and it may be enough for cleaning.
Manual Cleaning
The most crucial reason for using manual cleaning is the simplicity of its application, which is
desirable for many utility operators. The human laborers employed for this job need to be
professionals because of the risks and the need for selecting the right materials. Constant use of
some chemicals for cleaning may decrease the performance of PV panels. Also, the leakage of such
materials into the water reservoirs has a harmful impact on the environment. In addition, in this
technique, the amount of wastewater is relatively high, which makes it costly for arid regions with
non-fresh water reservoirs or in the case of installing FPV systems with the aim of water
evaporation reduction. Nevertheless, this technique may have other limitations for FPV systems,
including the difficulties in accessing panels and the need for weight-bearing floating structures.
Self-Cleaning
As mentioned before, both water and air can be used in self-cleaning techniques. Sprinklers are a
water-based approach. Although this system is suitable for arid regions because of its cooling
effect, it cannot spray the whole surface of PV panels. As a result, it cannot infiltrate all crevices of
PV panel surfaces. It has the same cleaning effect as rainfall and can clean PV panels at a relatively
EU-India Clean Energy and Climate Partnership (CECP) Page 53
low cost. However, there is a significant water wastage during the operation of sprinkler cleaning
systems for land-based PV panels because the nozzles spray the water a few meters outside the
panel perimeter. For FPV systems located on the surface of the freshwater reservoir, most of the
sprayed water returns to the reservoir and can be reused.
Robotic
This technique can also be categorized as water-based or water-free. One downside of utilizing
robotic techniques is their high total cost consisting of high maintenance cost for repairing,
operating, and monitoring and controlling the robots. Nevertheless, considering the true cost of
water, labor, and frequency of cleaning, it is found that the installation of robotic systems can be
cost-effective. In addition, this system can effectively decrease the wastage of water.
Deliberation of movement of FPV systems on the surface of the water reveals a key issue for
utilizing robots. These movements are unpredictable because they are highly dependent on the
buoyancy force, as well as on continuous regular and irregular oncoming waves, unlike existing
land-based systems. Considering the impossibility of installing fixed rails on PV panels, due to the
independent movement of each floating structure, any sudden movement of the FPV system can
detach the robot from the PV panel surface, and drown it into water or take it into a position,
which is not planned. Hence, it reduces the reliability of the system. In addition, using robots,
vehicles, or mechanically integrated mechanisms for cleaning purposes increases the possibility of
damage to the PV panel surface that has been cleaned.
Airflow
Airflow improves dust removal of PV panels, mainly in the regions with water short- age. A low-
speed airflow is desirable for FPV systems due to the low dust density of the air on water
reservoirs. However, high-speed winds hit the surface of the PV panel with sand particles that may
scratch the surface. Long-term exposure to such a wind creates problems of random scratches on
the PV panel surface, which results in a reduction of irradiation transmission and reflection.
Meanwhile, wind can create small cracks on PV panels via differential pressure, which in turn
results in lower efficiency. This problem is intensified for FPV systems due to their offshore
installation and higher repair costs.
Coating
Although coating prevents soil from sticking on the PV panel surface, it requires water for soiling
removal. By using this technique in arid regions, the volume of water utilized for washing is
decreased, while regular washing is required. Nevertheless, because of the humidity upon the
water reservoir’s surface, this technique is adequately efficient. Moreover, the coating surfaces
can provide other features, such as anti-icing, stability due to heavy rainfall, anti-reflecting,
photocatalysis reaction (this process can chemically break down the organic dirt through the
reaction to UV light), and anti-fogging. It is noted that coatings accumulate more soiling when the
coating deteriorates due to UV light.
EDS
The EDS technique is distinctively faster than other techniques. This technique has shown proper
efficiency in arid regions, but it has been shown that it is not effective for wet or cemented dust.
Besides, its efficiency is low for fine particles. Due to the proximity of water with PV panels in some
applications and high humidity, the ESD is not a proper option for these cases. Moreover, as
illustrated before, the traveling wave method is not cost-effective for both large-scale PV and FPV
systems.
The vibration method is used periodically, and accordingly, this technique consumes negligible
amounts of power in comparison with other active cleaning techniques. The advantages of the
piezoelectric actuator are its lightweight and compact structure, which makes it feasible for
utilization in FPV systems. It is noteworthy that as time passes, the vibration can increase the risk
of creating major cracks on the PV panel surface. These cracks may lead to the disconnection of
cells and a total loss of generated power.
Low efficiency
No cleaning cost
Not accurately predictable
Water- Doesn’t need any reformation
Rainfall No specific falling patterns
Based No electrical power consumption
Low access in arid and desert
Cooling effect
regions
EDS Water- High efficiency for desert regions Low efficiency for wet, cemented,
Free
High efficiency
Surface Water- Risks of PV panel damaging due to
Vibration Free Low electrical power the vibrations
consumption
High maintenance cost
For FPV systems that are developed for water evaporation reduction, using the airflow technique in
conjunction with a high stability coating layer is preferred.
For FPV systems that are developed for energy generation, in addition to the abovementioned
solution, using manual or self-cleaning water-based techniques leads to cooling and higher
efficiency.
Considering above following steps would be advisable to finalize the most suited cleaning system
for Floating solar system:
1~5 23 15.513
6~10 19 12.815
11~15 17 11.466
16~20 15 10.117
21~25 12 8.094
26~30 7 4.721
Standard Description
I Solar PV module
1 IEC 61215-1 Ed. 1.0 Terrestrial photovoltaic modules – Design
qualification and type approval - Part 1: Test
requirements
2 IEC 61215-1-1 Ed. 1.0 Terrestrial photovoltaic modules – Design
qualification and type approval - Part 1-1: Special
requirements for testing of crystalline silicon
photovoltaic modules
3 IEC 61730-1Ed. 2.0 Photovoltaic module safety qualification Part 1:
Requirements for construction
4 IEC 61730-2 Ed.2 Photovoltaic module safety qualification Part 2:
Requirements for testing
5 IEC 61701 Ed.2 Salt mist corrosion testing of photovoltaic
modules (applicable for coastal and marine
DNV, the independent energy expert and assurance provider has published the world’s first
recommended practice (RP) for floating solar power projects. The Recommended Practice (DNV-RP-
0584) will provide commonly recognized guidance based on a list of technical requirements for
accelerating safe, sustainable and sound design, development, operation and decommissioning of
floating solar photovoltaic (FPV) projects.
Each floating solar photovoltaic system is being studied with comprehensive monitoring infrastructure,
including 500 parameters. The floating systems are being compared against a reference PV roof-top
system. The objective being to compare the options in a Singaporean context as land-based PV is not
suitable. Comparison charts have been made available publicly that allow for unbiased analysis and
assessment of the different floating PV systems.
There are differences of 6ºC, but also of only 0,5ºC in some cases, from March to July.
However, the air on the water is always cooler than the air on land.
Another parameter that influences the PV module efficiency is the wind speed.
Figure 1- Comparison between the wind speed (weighted wind speed: OnS – land, OffS – water)
There are differences of 2.5 m/s and of just 0.5 m/s. The wind is always stronger in the
water versus the land.
Figure 1- Comparison between the air humidity (weighted average humidity: OnS – land, OffS –
water)
The humidity can be 10% different and almost the same. It is clear that it is always more
humid in the water than in land.
The albedo of the water surface versus rooftop shows an obvious difference and the water does not act
as a mirror for the sun rays, but actually as a sink.
Figure 1- Albedo for 15 Mar 2017 and similar to the average (OnS – land, OffS – water)
The albedo is rather small, 5~6% according to the measurements and lower than in land.
Free Standing
Very Good convective
cooling
Small Footprint
Good convective cooling
Large Footprint
Water surface partially
blocked
Not good convection
The cooling effect, indicated by the heat loss coefficient, is thus dependent on the type of the floating
structure as provided in the graph below.
The differences are of 50% in terms of the heat loss coefficients for different floating PV
systems.
The system performance ratio (from Apr 2017 to Mar 2018) shows about 10-15% higher outputs than
typical rooftop PV systems in Singapore (with a PR of 77%).
It would be expected a lower difference in PR towards ground mounted as there is some natural
ventilation rather than being on a rooftop where temperatures are higher.
The FSPV sector is evolving very rapidly and will become an alternate popular way to generate solar
energy very soon. However, very little knowledge is available at the moment thus posing many
challenges, which need to be addressed properly. Some of the key challenges associated with the FSPV
are presented below.
The demand for electricity in the country has been growing at a rapid rate and is expected to grow
further in the years to come. To meet the increasing requirement of electricity, massive addition to the
installed generating capacity in the country is required. The country, though rich in coal and abundantly
endowed with renewable energy in the form of solar, wind, hydro and bioenergy has very small
hydrocarbon reserves.
In the Paris Agreement India has committed to an Intended Nationally Determined Contributions target
of achieving 40% of its total electricity generation from non-fossil fuel sources by 2030. The country is
aiming for even more ambitious target of 57% of the total electricity capacity from renewable sources by
2027 in Central Electricity Authority's strategy blueprint. According to 2027 blueprint, India aims to have
275 GW from renewable energy, 72 GW of hydroelectricity, 15 GW of nuclear energy and nearly 100 GW
from “other zero emission” sources.
India was the first country in the world to set up a ministry of non-conventional energy resources
(Ministry of New and Renewable Energy (MNRE)), in the early 1980s, and its public sector undertakings
the Solar Energy Corporation of India is responsible for the development of solar energy industry in
India. Hydroelectricity is administered separately by the Ministry of Power and not included in MNRE
targets.
India is running one of the largest and most ambitious renewable capacity expansion programs in the
world. In 2019 at UN climate summit, India announced that it will be more than doubling its renewable
energy target from 175GW by 2022 to 450GW of renewable energy by the same year. Newer renewable
electricity sources are projected to grow massively by nearer term 2022 targets, including a more than
The government target of installing 20 GW of solar power by 2022 but it was achieved four years ahead
of schedule in January 2018, through both solar plants as well as roof-top solar panels. India then set a
new target of achieving 100 GW of solar power, 60GW of wind power, 10GW of biomass and 5GW of
small hydro power by 2022.
Unlike most countries, until 2019 India did not count large hydro power towards renewable energy
targets as hydropower was under the older Ministry of Power instead of Ministry of New and
Renewable Energy. This system was changed in 2019 and the power from large hydropower plants is
since also accounted for. This was done to help the sale of the power from the large Hydropower plants,
as this reclassification has made such plants able to sell their power under the Renewable Energy
Purchase Obligation. Under the Renewable Energy Purchase Obligation, the DISCOMs (Distribution
Company) of the various states have to source a certain percentage of their power from Renewable
Energy Sources under two categories Solar and Non-Solar. The power from the large Hydropower plants
now classifies under the Non-Solar Renewable Energy Category.
Energy in India is at the cusp of disruption, transitioning from rapid reforms in the sector, that is,
enhanced energy availability, accessibility and reliability to leapfrogging towards sustainable energy
transformation, digitization of the energy value chain and adopting breakthrough models for
sustainable mobility. India saw the first inflection point for renewable energy generation in 2016-17 when
the capacity addition in Renewable energy was higher than the capacity addition for conventional
energy sources.
92,9 106,0
87,0
75,1
There has been a visible impact of solar energy in the Indian energy scenario during the last few years.
Solar energy based decentralized and distributed applications have benefited millions of people in
Indian villages by meeting their cooking, lighting and other energy needs in an environment friendly
manner. Further, solar energy sector in India has emerged as a significant player in the grid connected
power generation capacity over the years. It supports the government agenda of sustainable growth,
while, emerging as an integral part of the solution to meet the nation’s energy needs and an essential
player for energy security.
National Institute of Solar Energy has assessed the Country’s solar potential of about 748 GW assuming
3% of the waste land area to be covered by Solar PV modules. Solar energy has taken a central place in
India's National Action Plan on Climate Change with National Solar Mission as one of the key Missions.
National Solar Mission (NSM) was launched on 11th January 2010. NSM is a major initiative of the
Government of India with active participation from States to promote ecological sustainable growth
while addressing India’s energy security challenges. It will also constitute a major contribution by India
to the global effort to meet the challenges of climate change. The Mission’s objective is to establish
India as a global leader in solar energy by creating the policy conditions for solar technology diffusion
across the country as quickly as possible. The Mission targets installing 100 GW grid-connected solar
power plants by the year 2022. This is line with India’s Intended Nationally Determined Contributions
(INDCs) target to achieve about 40 percent cumulative electric power installed capacity from non-fossil
fuel-based energy resources and to reduce the emission intensity of its GDP by 33 to 35 percent from
2005 level by 2030.
In order to achieve the above target, Government of India have launched various schemes to encourage
generation of solar power in the country like Solar Plant Scheme, VGF Schemes, CPSU Scheme, Defence
Scheme, Canal bank & Canal top Scheme, Bundling Scheme, Grid Connected Solar Rooftop Scheme etc.
Various policy measures undertaken included declaration of trajectory for Renewable Purchase
Obligation (RPO) including Solar, Waiver of Inter State Transmission System (ISTS) charges and losses
for inter-state sale of solar and wind power for projects to be commissioned up to March 2022, Must run
status, Guidelines for procurement of solar power though tariff based competitive bidding process,
Standards for deployment of Solar Photovoltaic systems and devices, Provision of roof top solar and
Guidelines for development of smart cities, Amendments in building bye-laws for mandatory provision
of roof top solar for new construction or higher Floor Area Ratio, Infrastructure status for solar projects,
Raising tax free solar bonds, Providing long tenor loans from multi-lateral agencies, etc.
India achieved 5th global position in solar power deployment by surpassing Italy. Solar power capacity
has increased by more than 20 times in the last seven years from 2.6 GW in March,2014 to 55 GW in
December 2021. Presently, solar tariff in India is very competitive and has achieved grid parity.
The total installed capacity of renewable energy sources in India (including hydr0) as of April 2022
surpassed 158,121 MW representing 39.4 % of the total installed capacity of 401 GW. However, India’s
Solar; 55,3
Coal; 204
Hydro; 47
Nuclear; 7
Other Thermal; 7
Gas; 25
Despite increasing renewable share in the energy mix, there exists huge gap in the current installed
capacity of 111 GW as on Apr’22 against the identified target of 175 GW by end of FY 2022. Various policy
and institutional level initiatives are expected to give boost to this sector to help achieve the set vision.
At the United Nations Climate Action Summit in September 2019, the Hon’ble Prime Minister of India
had declared that India will be raising its Renewable Energy installation targets to 450 GW by 2030 from
175 GW by 2022. In Nov’21, at the COP26 Climate Conference in Glasgow, Hon’ble Prime Minister
announced that India will achieve net zero carbon emissions by 2070 2 and 500 gigawatts (GW) of non-
fossil electricity capacity, half of energy from renewables, a reduction of emissions by one billion tones
and emissions intensity of the GDP by 45% by 2030. The sector wise breakup on current installed capacity
as on April’22 and potential for Renewable Energy sources is as shown below:
Installed
Capacity
v/s Hydro Power* Solar Wind Bio Energy
51.3 GW 55.3 GW 40.5 GW 10.6 GW
Potential
v/s v/s v/s v/s
250 GW 750 GW 695 GW (at 120 m) 26GW
Presently, solar tariff in India is very competitive and has achieved grid parity. In India, more than 30GW
of solar PV capacity has been bid out since 2017, with tariffs in the range of INR 2.36-3.98Rs/kWh. In 2017,
~4.5 GW capacity was bid out with a weighted average tariff of 3.02 Rs/ kWh. In 2018, around ~12.5 GW
capacity was bid out with the weighted average tariff falling to 2.76Rs/kWh. In 2019, the weighted
Tariff (Rs./kWh)
Capacity (MW)
This scheme was rolled out to overcome the challenges of installing scattered small projects. Some of
these challenges include high project cost per MW and higher transmission losses, followed by
significant expenses in site development, drawing separate transmission lines to nearest substation,
procuring water and in creation of other necessary infrastructure. It also takes a long time for project
developers to acquire land, get change of land use and various permissions, etc. which delays the
project. Thus, this scheme for ‘Development of Solar Parks and Ultra-Mega Solar Power Projects’ was
rolled out in December 2014 with an objective to facilitate the solar project developers to set up projects
in a plug and play model. The timeline for this scheme has been set up to 2022-23 envisaging a capacity
addition of 40GW (in place of 20GW planned earlier) in the form of Solar Parks. Minimum capacity of
each park is set at 500MW. The implementing agency for these parks shall be Solar Power Park
Developer (SPPD), the selection process of which is detailed out in the scheme document.
In this scheme, CFA (Central Financial Assistance) of INR 25 lakh per park is provided for DPR (Detailed
Project Report) preparation, INR 20 lakh/MW for achieving project milestones. Further CFA of
20lakh/MW apportioned on 60:40 basis proposed towards development of internal structure and
external transmission infrastructure.
As of Nov’21, 52 solar parks have been sanctioned with a cumulative capacity of 37.92 GW in 14 states 3.
The Government, on 19th February 2019 approved Phase-II of ‘Grid Connected Rooftop and Small Solar
Power Plants Programme’ for achieving cumulative capacity of 40 GW RTS plants by Dec’ 22. The
objective of the scheme is to create additional RTS capacity of 33.4 GW in the country by 31.12.2022. The
major components of this phase II of the programme are: -
3 https://pib.gov.in/PressReleaseIframePage.aspx?PRID=1785808
4 https://mnre.gov.in/solar/schemes
EU-India Clean Energy and Climate Partnership (CECP) Page 77
Component A: Setting up of 4000 MW of grid connected rooftop solar projects in residential sec-
tor with Central Financial Assistance (CFA)
CPSU (Central Public Sector Undertaking) Scheme Phase II for setting up 12,000MW grid-connected
Solar PV power projects by Government Producers with VGF (Viability Gap Funding) support 6
The scheme aims at setting up solar PV projects through Government Producers using domestic cells %
modules in WTO compliant manner to facilitate national energy security and environment stability for
Government purpose. The scheme is planned between 2020-2023. Government Producers (PSUs/ Govt.
Organisations.) which are under administrative control or have 50% shareholding of Central / State Govt
are only eligible for this scheme. Maximum VGF of upto Rs. 70 lakhs/ MW will be provided and actual VGF
will be decided through bidding. There is also a criteria for Domestic Content Requirement .
The Energy and Resources Institute (TERI), in its report published in 2020, found that India’s reservoirs
have 18,000 sq. km of area with the potential to generate 280 GW of solar power through floating solar
projects. This translates to India’s entire installed solar capacity goal for 2030.
5 https://mnre.gov.in/the-ministry/physical-progress
6 https://pib.gov.in/PressReleasePage.aspx?PRID=1725054
EU-India Clean Energy and Climate Partnership (CECP) Page 78
Scenario 1 – 4104 MW
Scenario 2 – 17755 MW
No. of reservoirs – 142
Cumulative Reservoir area (in
km2) - 877
The Odisha Renewable Energy Development Agency (OREDA), a state nodal agency under the science
and technology department, is working towards use of renewable energy resources in the state. The
state government has reported that expenditure of Rs. 17.29 crore has been incurred on solarization of
the government institutions like schools, health institutions, fire stations and mines. 313 solar plants
have been installed for solarization of fire stations by spending Rs 7.36 crore. The total is 1727.69 kW of
power. Similarly, the government has set up 189 plants for solarization of more than Rs 5.78 crore. These
plants have 2,595 kW.
An amount of Rs. 154 crores have been spent for installation of 29 solar plants in Kasturba Gandhi Balika
Vidyalays. While large scale power generation projects are being installed to achieve the ambitious
target of 100 GW of solar power generation by 2022, it has been planned to simultaneously develop
decentralized solar energy and other renewable energy generation plants of capacity up to 2 MW.
According to MNRE, Odisha has an installed solar power capacity of 451.24 MW 7 as on April, 2022 and
accounts for approximately 8% of India’s total installed solar power. The Government of Odisha is
implementing measures to promote solar energy development in the state and the Odisha Renewable
Energy Policy, 2016 sets a target of 2,200 MW of additional solar generation by 2022; this includes
7https://mnre.gov.in/the-ministry/physical-progress
EU-India Clean Energy and Climate Partnership (CECP) Page 79
generation through roof-top solar and other non-land based solar projects. The Renewable Energy
Policy 2016 aims to contribute to long term energy security of the State as well as ecological security by
reduction in carbon emission and create skilled & semi-skilled manpower resources through promotion
of technical and other related training facilities. The Policy facilitates development of manufacturing
units and Research & Development in the Renewable Energy sector.
Broad summary of the policy highlighting the key aspects is tabulated below 8.
5 Incentives a. Industrial land and government land will be made available for
RE projects.
b. Infrastructure beyond the interconnection point will be the re-
sponsibility of the DISCOM
c. No cross-subsidy charges will be levied and only 20% of wheel-
ing charges will be applicable for sale of power through open
access.
6 Tax d. Exemption from electricity duty and cess for a period of 5 years
Exemptions from the date of commissioning.
e. Testing charges of Engineer-in-Chief are waived.
f. Supervision charges by Odisha Power Transmission Company
Limited (OPTCL) are reduced to 5% from 20% of the capital cost.
8 https://admin.gedcol.com/Notification/Renewable%20Energy%20Policy-2016.pdf
EU-India Clean Energy and Climate Partnership (CECP) Page 80
5.3.3 Renewable Purchase Obligation (RPO):
Distribution licensee (or any other entity procuring power on their behalf) or any person consuming
electricity (a) generated from conventional Captive Generating Plant having capacity of 1 MW and above
for his own use and or (b) procuring conventional generation through open access and third party sale
are identified as Obligated Entities.
These Obligated entities are liable to purchase a certain quantity of their consumption from renewable
sources a s detailed below. Quantum of obligation as Proposed.
Year-wise target Solar Source (%) Non-Solar sources (%) Total (%)
OREDA has been designated as the State Designated Agency (SDA) for implementation of RPO in the
state on behalf of OERC:
So far 62 obligated entities have been identified in the state which are mainly industries having Captive
Generating units. Apart from these open access consumers also come under the RPO regime whose
number changes every month. Of the above only 12 entities are fully or partially complying to their
obligation while 8 have moved the Hon’ble High Court contesting imposition of RPOs and their cases are
lying un-resolved.
OREDA regularly monitors the compliance of RPOs by different entities and submits reports to OERC.
China
China has the largest installed capacity (~1.3 GW) of FPV systems, and this has largely been driven by its
national RE targets and specific solar PV policies. Existing RE targets set under national policies has
driven the demand for new RE projects as China’s 2019 renewable portfolio standard requires the
country source 20% of primary energy from non-fossil fuel sources by 2030. Utilities in every state must
therefore develop capacity expansion plans that ensure they meet the renewable portfolio standard
(Zhu and Song 2020). These national energy targets, in addition to environmental pollution laws in some
provinces, have encouraged deployment of RE, including FPV systems.
China has quickly become one of the largest deployers of FPV systems. China offers lessons on
encouraging FPV deployment:
a. Support FPV deployment on otherwise unusable land and artificial water bodies, as opposed to
natural water bodies that may have a more complex environmental review process; and
b. Encourage RE deployment, including FPV deployment, via national targets and regional requirements.
India
India has ~92 MW of installed FPV capacity, and over 1,700 MW is under development. The Energy and
Resources Institute (2019) estimates that India’s water reservoirs could host approximately 28,000 MW
of FPV capacity. India offers multiple tax incentives and FPV- specific auctions. For eg, in January 2020
the Solar Energy Corporation of India issued tenders for 4MW of FPV with 2MW/1MWh of battery
storage in the Andaman Islands (Tom Kenning 2020).
Overall, India offers one lesson on encouraging FPV deployment: Support FPV deployment through
economic incentives.
Japan
Japan has also become a leader in FPV, with at least 260 MW of FPV installed and the creation of a local
job creating FPV industry. Japan’s interest in FPV systems has largely been due to its unique power
system needs, mountainous geography, and land constraints. Various institutions such as the Japan
International Cooperation Agency (JICA) and the Asian Development Bank (ADB) have supported solar
PV deployment in and outside of Japan through technical support and project financing.
The Netherlands
Netherlands leads FPV deployment in Europe with about 110 MW of installed capacity. The government
supports FPV projects as part of its larger RE strategy. In 2017, the country’s Ministry of Infrastructure
and Water Management created a consortium called “Zon op Water” (“Sun on Water”) to work toward
developing 2,000 MW of FPV by 2023. The Netherlands also supports RE development under the
Sustainable Energy Production Incentive grant program. This program reimburses the difference
between the cost of generating energy from the FPV system and the prevailing wholesale market price
(van de Ven 2019).
Providing direct financial incentives like production-based incentives can help de-risk FPV
systems; and
Encouraging interagency cooperation can help encourage FPV development by reducing the
administrative hurdles to deployment.
A full chapter on best practices from Europe is presented in the next chapter.
South Korea
South Korea supports solar PV deployment as part of its broader power sector decarbonization
strategy. FPV systems have emerged as an attractive alternative to land-based PV systems because the
government has faced some public opposition to using forest and agricultural land for solar
developments. This focus on FPV systems has made South Korea a leader in FPV deployment (with at
least 120 MW of FPV installed); the country recently announced a $3.96 billion (€3.79 billion), or 2,100-
MW of offshore FPV projects (PV Magazine 2019).
1. Encouraging FPV adoption can create a local, job-creating FPV industry as well as help avoid land-
energy conflicts caused by land-based PV systems competing with other land use needs; and
2. Encouraging FPV technology adoption requires multiple approaches including R&D and deployment
support.
Taiwan
Incentives for FPV systems must be carefully designed to not over-incentivize participation;
and
Enabling policies for FPV deployment must be coordinated with grid integration studies and
proactive transmission planning to ensure that the grid is well-positioned to integrate large
shares of solar generation. This is especially true for FPV systems and other emerging energy
technologies, where the profitability of early projects is a key signal to developers.
As of 2018, in Europe the top 30 European solar plants cumulatively held 16.1 MW capacity, with the UK 10
having a share of 65 % ,has seen in the following figure.
These projects have been commissioned in recent years, with the size and number of solar FPV projects
in the region growing at a fast rate.
One of the first large scale FPV plants in Europe was Queen Elizabeth II reservoir solar project. This
project was completed in March 2016 and was connected into the Thames Water´s private network.
Developed by Lightsource bp, the project has 6.3 MWp capacity and the 23,046 solar panels were
installed in a platform composed of 61,000 floats. The floating PV currently supplies 20% of the water
plant needs and is part of the main goal of Thames Water´s private network to self-generate a third of its
energy.
9https://www.europarl.europa.eu/thinktank/en/document/EPRS_BRI(2021)698781
10At this time, the UK was still part of EU, thus it is considered here. A s of 31 January of 2020, the UK left the European
Union .
11https://www.solarplaza.com/resource/11954/top-30-floating-solar-pv-plants-europe/
EU-India Clean Energy and Climate Partnership (CECP) Page 85
Figure 1 – 6.3 MWp Queen Elizabeth II reservoir solar project in operation since 2016 12
Currently, the largest and 2nd largest floating solar plant in Europe are located in the Netherlands. The 2
facilities have capacities of 41.1 MWp and 29.8 MWp, with a total combined capacity of 70.9 MWp. They
were built by Dutch developer Groenleven, a unit of German RE company BayWa re, one of the main
renewable energy companies in Europe.
Figure 1 – A sight of Sellingen solar plant with 41 MW DC. The 72,000 solar modules have a west-
east orientation. The plant is located in a former sand extraction lake.
The Netherlands are one of the countries in Europe with the highest floating PV potential given its
52,000 ha of shallow inland water.
12 https://www.lightsourcebp.com/uk/projects/queen-elizabeth-ii-reservoir-solar-project/
EU-India Clean Energy and Climate Partnership (CECP) Page 86
In a near future, however, the biggest FPV plant is set to be located in Portugal. The country is one of
the leaders in the EU, in terms of renewable energy integration in the mix, representing 66 % 13 of total
electricity capacity. Portugal, located south-west of Europe has one of the highest levels of solar
irradiance in the region and the government´s energy policies towards higher RE intake have led,
recently, to realize solar FPV auctions in the biggest dams of the country. The government awarded the
rights to develop 263 MW of floating PV capacity, with 7 lots being auctioned. EDP renewables, secured
the highest lot with 70 MW capacity in the biggest dam in Portugal, Alqueva. To secure the right for grid
connection, however, the company will pay 4 euros per MWh, for the period of 15 years, to the
Portuguese electrical system, a negative value for the company 14. The water reservoir concession lasts
for 30 years, and the business model is based on the opportunity to increase the FPV solar capacity
through repowering and the incorporation of a wind park in hybrid mode, selling the added capacity at
the spot market price.
Figure 1 – Alqueva dam in Portugal, where 70 MW of Floating PV are set to become the largest FPV
plant in EU
13 https://www.irena.org/IRENADocuments/Statistical_Profiles/Europe/Portugal_Europe_RE_SP.pdf
14This is not a mistake. It is indeed a negative value taken into consideration the possibilities under the Portuguese
legislation, namely hybridization and repowering (both in solar and wind).
EU-India Clean Energy and Climate Partnership (CECP) Page 87
In Europe one of the first entities providing a RP for the floating PV sector is DNV, being an international
accredited registrar and classification society based in Norway. It has provided a RP called “DNV GL RP –
Design, development and operation of floating solar PV systems”, where it outlines the major
requirements and recommendations for the several stages of the development and equipment of a FPV
park, thus including:
Current;
Fouling;
Ecology;
Water depth;
Waterproofing system;
Ground conditions;
Earthquakes
Optical losses;
PV module losses;
Inverter losses;
Electrical losses;
Functional requirements;
Design considerations;
Performance criteria;
impact
PV modules;
The DNV RP is mainly focused on FPV systems located in sheltered, in-land water bodies and also near-
shore waterbodies. Off-shore locations or locations with harsher conditions are not included.
Apart from this RP, floating PV developers are also contributing to ensure that safety and quality
requirements are in place and adopted internationally. French-based Ciel&Terre floating structure
manufacturing is a good example of this. Founded in 2006, and with more than 120 projects worldwide
to this date, it has patented a water-based PV concept named” Hydrelio”, that is certified for harsher
environmental conditions and is a good example of specific compiled standards into a FPV technology.
Example of safe, quality and environmental requirements and specific standards for a Floating PV
plant – “Hydrelio” technology designed by Ciel&Terre15
Snow resistance Design compliant with UL273 -tests performed up to 10000 N/m2 snow
load;
15 https://www.ciel-et-terre.net/hydrelio-technology/our-hydrelio-solutions/
EU-India Clean Energy and Climate Partnership (CECP) Page 89
Example of safe, quality and environmental requirements and specific standards for a Floating PV
plant – “Hydrelio” technology designed by Ciel&Terre
High irradiation 40,000 h cumulative UV testing according to ASTM G154 and ISO 4892-2;
The International Electro-Technical (IEC) Commission, however, has not yet developed fully robust
international standards for the floating PV technology. For the time being, the abovementioned RP and
the most experienced developers in the FPV sector are the main guides for other FPV stakeholders to
follow in terms of technical, environmental and social requirements.
For the floating PV technology, the private sector is becoming very dynamic, competitive and creative,
with more diversified floating PV technologies appearing in the market. It is also becoming more
affordable given the increase in scalability at the production level and proven benefits in relation to
other RE technologies for specific environments.
Several challenges are presented, however, for the FPV technology to be more competitive and relevant
in relation to other renewables. Being most commonly located in waterbodies near shore and inland,
permissions and environmental/social constraints can represent a major setback, along with the
availability of grid injection points, grid requirements and the financial agreement for the sale of the
generated electricity. The public sector is, therefore, vital in providing the necessary conditions and
opportunities for the FPV development.
In the EU, several countries have implemented innovative forms to attract major private FPV
stakeholders and foster the RE intake coming from floating solar.
In 2019, the Portuguese Government changed the legal framework of the electricity sector, reforming
the methodology for allocating power generation licenses. The present licensing process requires the
producer to request the granting of a grid capacity title (“RESP Title” 17) before applying for a power
plant production license. This title can be obtained in three ways18:
These public solar tenders are a way to provide an answer to one of the main issues that the country
faces: the low availability of network capacity along with the growing interest by the private sector to
invest in the renewable energy sector 19. These tenders function through a system of auctioning grid-
connection points where there is availability or is projected grid expansion, fostering solar market
competition and achieving the lowest tariff rates for the national grid, that consequently lowers the
price in the energy market and for the end-consumer. The Portuguese government goal is to carry out
two tenders per year,20 awarding a total capacity of 1 GW per annum.
17 RESP : The Portuguese Public Grid and stands for: Rede Eléctrica de Serviço Público
18 Source: https://www.macedovitorino.com/xms/files/20210323-At_a_Glance_Portugal_and_Spain_Solar_Auctions.pdf
Right of private use of a portion of the Public Water Domain, intended for the installation of a float -
ing solar plant, for electricity production, in public water reservoirs.
The installation, operation and conservation of the structures of the FPV and the required grid con-
nection needs.
The use of public water domain land allocated to the Concession.
In cases where the installation of the floating solar power plant implies the occupation of lands that
are not part of the Public Water Domain affected by the Concession, the Concessionaire will be re -
sponsible to obtain the rights, bearing all the expenses of your hiring, service contract and/or indem-
nities.
21 https://apambiente.pt/sites/default/files/_SNIAMB_Agua/DLPC/Fotovoltaicos/Anexos/leil%C3%A3o-solar-flutuante-
caderno-de-encargos_dph.pdf
EU-India Clean Energy and Climate Partnership (CECP) Page 92
7.3.2 Case study: Netherlands
The country has one of the highest renewable energy capacities coming from floating PV parks,
accounting for 12.9 % of total EU FPV parks in 2018, being also one with the highest floating PV potential
given its 52,000 ha of shallow inland water. One of the reasons for this growth is the lack of land
availability, therefore, FPV represents one of the main vehicles to increase Netherlands share of
renewables with the country planning to add 2 GWp floating PV capacity by 2023 22.This target has been
set by the National Consortium Sun on Water 23, a platform comprising 35 parties, including local
governments, science institutions and companies working on specific projects.
Following these objectives and with the aim to reduce CO2 emissions by 49% until 2030, compared to
1990 the Dutch government has introduced a scheme called SDE++ 24, that stands for Stimulation of
Sustainable Energy Transition and Climate Transition. The scheme facilitates the production of
sustainable energy supply such as the FPV and the application of CO2 emissions reduction techniques in
the country.
≥ 1 MWp floating;
c) Permits:
a. Environmental permit;
b. Public Works and Water Management Act permit. If conducting activities on or around
public works or water management structures, such as roads, motorways, viaducts, tunnels,
bridges or dykes;
c. Water permit. If your solar PV facility requires a permit under the Water Decree according to
the Dutch legislation;
d. Large-scale energy connection: “The Solar PV category applies solely to systems connected
to a large-scale grid connection.
22 https://solaredition.com/the-netherlands-plans-to-add-2-gw-floating-solar-power-plant-by-2023/
23 https://zonopwater.nl/home
24 https://debreed.nl/en/financing-form/sde/
EU-India Clean Energy and Climate Partnership (CECP) Page 93
Figure 1 – SDE ++ scheme for floating PV in 2020: Ranking and phases by maximum category base
amount25
Due to this scheme, floating solar PV developers in the Netherlands were able to acquire support for 500
MW capacity.26
25 https://english.rvo.nl/sites/default/files/2020/11/Brochure%20SDE%20plus%20plus%202020.pdf
26https://www.spglobal.com/marketintelligence/en/news-insights/latest-news-headlines/with-ambitions-offshore-
floating-solar-makes-its-first-splashes-in-europe-59512639
27 https://www.pv-magazine.com/2020/09/22/floating-solar-pv-gains-global-momentum/
EU-India Clean Energy and Climate Partnership (CECP) Page 94
One of the biggest floating solar plants in France was developed through this scheme and is called O
´MEGA 1 project. It was the winner of the CRE4 tender in 2017 and the first Akuo Energy´s Project
based on floating solar technology, using the Hydrelio water-based PV system by Ciel et Terre floats.
Located on the commune of Piolenc, in the department of Vaucluse, the FPV site is situated in a old
quarry site, an artificial lake that was restored for the solar floating project and will be in operation for
a period of at least 20 years.
Figure 1 - O'MEGA1 was one of the first large solar PV plant in Europe based on floating solar
technology (Hydrelio@ from Ciel y Terre) 28 Source: Akuo
Other FPV projects are emerging fast in the country. A 14.7 MWp FPV is soon to be implemented in
southern France by Canadian RE developer Boralex. It will consist of 43,000 PV panels assembled in a 12-
hectare island, formerly a gravel pit and will produce around 22 GWh per year. EDF Renewables has also
kicked off the construction of a 20-MW floating solar photovoltaic (PV) plant on a hydropower reservoir
in France’s Hautes-Alpes department. The PV array will be installed on a reservoir powering of the Lazer
hydroelectric plant in the municipality with the same name.
28 https://www.euractiv.com/section/energy/news/europes-largest-floating-solar-plant-opens-in-france/
29 https://www.nrgisland.com/data_n_layout.html
30 https://interestingengineering.com/floating-photovoltaic-systems-banned-on-reservoirs-in-italy
EU-India Clean Energy and Climate Partnership (CECP) Page 95
land issues can condition the growth of floating PV. In the near future, the government might solve this
issue, given its climate and energy goals. Recently, a subsidiary of the Italian oil group Eni New Energy
has been developing the first utility scale floating solar plant in Italy, with 14 MW capacity. It will be
located on an artificial water basin in Brindisi, located in the southern region of Apulia, Italy.
Ciel&Terre – A French company founded in 2006, Ciel &Terre is one of the leaders of the field and
with the highest expertise in the floating solar market. In the first years it was specialized in roof
mounted solar PV systems, and a decade ago decided to shift to the water-based PV systems by
inventing one of the first FPV patents: Hydrelio®. Currently, the Ciel&Terre has participated in the
construction of 230 projects, representing approximately 575 MWp31. Laketricity, a part of Ciel&Terre
Group is the main entity responsible for developing projects and conceiving solutions to develop
more reliable and secure floating solar PV parks. Since 2015, it has developed more than 90 projects
from 100 kWp to 20 MWp.
Akuo – Created in 2007 and based in Paris, this company has expertise in solar, hydro and wind
renewable energies. A developer and an operator of its own assets, has an installed capacity in
operation until 2021 of 1,4 GW. One of its subsidiaries, Akuo Industries manufactures and distributes
the HYDRELIO® floating structure solution developed by the french company Ciel & Terre
International.
Lightsource BP – Considered one of the largest solar developer in the world, Lightsource BP is a
British company with headquarters in London. Founded in 2010, it launched the largest FPV park in
Europe in 2016 with 6.3 MWp, at the Queen Elizabeth II reservoir for the Private Thames Water
31 https://laketricity-fpv.com/about-us/
32 https://www.akuoenergy.com/var/fichiers/one-page-hydrelio-nov2019-en.pdf
33 https://www.baywa-re.com/en/cases/emea/making-waves-in-solar-energy
EU-India Clean Energy and Climate Partnership (CECP) Page 96
Network. Until 2018, the solar developer has commissioned 1,3 GW of solar capacity and manages
around 2 GW of solar capacity.
ENI – An energy company based in Rome, Italy, has assets in the natural gas & LNG, refining and
chemical industry and in renewable energy, among others. With a target set of 15 GW of installed
renewable capacity by 2030 and 60 GW by 2050, the company is focused on solar and wind. Floating
PV with its many advantages and promising growth, has become one of the RE investments of the
company. A subsidiary of the Italian oil group Eni New Energy has been developing the first utility
scale floating solar plant in Italy, with 14 MW capacity.
EDP renewables (EDPR) – majority owned by the Portuguese company EDP, this Madrid based
company manages a global portfolio of 12.2 GW of installed capacity, has added 1,580 MW in 2020
and has 6 GW already secured for 2021-2026 period the coming years, as of December 2020. It has
now secured the rights to develop 70 MW of FPV in Alqueva, Portugal.
The Green Powered Future Mission: 34 Defined as a joint roadmap of global innovation priorities, it was
developed by several public-private stakeholders worldwide in November 2021, with the core members
being China, Italy and the United Kingdom. The main focus of the roadmap has been to define a
pathway to guide large scale R&I investment, energy policy and boost international cooperation
towards a more sustainable future and a shift to clean energy, such as the floating PV.
The joint roadmap identifies the top 100 global innovation priorities necessary for a faster energy system
reform and modernisation and solutions/challenges for the decarbonisation of the society. It addresses
3 key pillars:
i) “Affordable and reliable VRE: reduce cost and increase efficiency, resilience and reliability of VRE
technologies in various climates and system configurations.
ii) System flexibility and market design: develop the much-needed flexible solutions to meet
network infrastructure needs, to be supported by regulation and innovative markets design.
34 http://mission-innovation.net/wp-content/uploads/2021/11/Power-Mission-Joint-Roadmap-of-Global-Innovation-
Priorities.pdf
EU-India Clean Energy and Climate Partnership (CECP) Page 97
accelerate the digitalisation of energy systems through development of interoperable data
exchange and effective system integration to unlock the full value of VRE.
iii) Data and digitalisation for system integration: accelerate the digitalisation of energy systems
through development of interoperable data exchange and effective system integration to
unlock the full value of VRE.”
Following this, the mission has identified key Tipping Points (TP) against each pillar which need to be
met to achieve its goal:
The floating PV technology is presented in Pillar 1: Affordable and Reliable VRE. The
challenges of the design of FPV, such as reaching efficient operation and a lack of
mooring specialists in the field are identified as one of the barriers to achieve the tipping
point, being rated as a mid-priority, in the field of innovative PV solutions included in
the top 100 global innovation priorities.
Figure 1 – Challenges in the floating PV technology are defined as one of the barriers to meet the
goals of Pillar 1: Affordable and Reliable VRE
The EU-SCORES is led by the Dutch Marine Energy Centre and will demonstrate the combination of
offshore wind-wave, and offshore wind - offshore floating solar PV, by the development of two
demonstrations composed of the hybrid RE systems.
Several advantages are presented by these hybrid systems, such as increased power system stability and
resiliency, increased capacity factor and an expected lower total cost per MWh. These demonstrations
will prove how the increased power output and capacity installed per km2 will help to reduce the
amount of marine space needed and will provide knowledge on how to effectively scale-up offshore
hybrid systems in Europe, contributing to the clean energy transition and the EU targets of reaching 230-
440GW and 40GW installed capacity of offshore wind and ocean energy by 2050, respectively. 35
The offshore FPV + Wind demonstration will be a 3 MW grid-connected offshore solar PV system
developed by Oceans of Energy (a dutch-company specialized on offshore floating PV systems). This
company is at the forefront of offshore floating PV technnology, after the development of one of the
first solar offshore FPV systems (“North Sea 1”) in the world in the Dutch North Sea and a further scale-
up for a 1 MW offshore FPV system (“North Sea 2”).
Figure 1 – Dutch Offshore FPV specialized company “Oceans of Energy” projects: EU-SCORES Offshore
Wind+FPV project on the left side and 1 MW “North Sea 2” project on the right side ,being the world´s first
offshore FPV system to be connected to the grid ,and enduring extreme sea conditions, including 6
consecutive storms in February 2022
35 https://oceansofenergy.blue/2021/09/01/eu-scores-project-aims-to-deliver-world-first-bankable-hybrid-offshore-
marine-energy-parks/
EU-India Clean Energy and Climate Partnership (CECP) Page 99
The demonstration will be installed 2 km off the Belgian coast at the Blue Accelerator test site and will
focus on:
ii) Deployment & Deployment of the The construction of the offshore solar PV
Testing (2022- offshore solar PV system will be finalized and deployed.
2024) system;
The floaters will be designed and built in the
Design of the floating Netherlands. Subsequently, the floaters will
structure; be transported to the Port van Oostende in
Belgium, where local contractors will be
2 years deployment and hired to deploy the system early 2023.
testing in Belgium
The new export cable and the needed
floating electrical infrastructure will be put
in place. The deployment is planned to last
for approximately two years. It will
continuously deliver electricity to the local
Belgium grid.
iii) Scale-up Development of large- After the previous phase, a scale-up phase
(2024-2025) scale hybrid offshore shall follow where multiple large-scale
Wind+FPV systems. projects will be developed by the relevant
offshore hybrid RE stakeholders.
Horizon Europe Framework Programme (HORIZON): The FPV is also one of the
technologies presented in the EU funding programme for research and innovation called
HORIZON. It is focused on tackling climate change, fostering the UN´s sustainability
goals and increasing overall EU´s competitiveness.
36 https://euscores.eu/#solar-wind
EU-India Clean Energy and Climate Partnership (CECP) Page 100
Floating PV Research & Innovation – Main Outcomes and Actions defined in the EU key funding R&I program- HORI -
ZON
Outcomes:37 Actions:
Improved overall lifetime, reliability, operability Test and validate the potential benefits of new circular
and maintainability of marine substructures, me- materials in offshore floating PV and/or ocean energy sub-
chanical joints and energy connection systems for structures, foundations and if relevant mooring and an-
ocean energy devices and/or offshore floating PV choring systems whilst ensuring structural integrity and
to reduce degradation and failure rates and thus durability considering very high wind (speed >25 m/s), cur-
investment risk. rent (>1.2 m/s) and wave (height >14 m) loads and corro-
gineering of devices’ specifications. Test and validate new prototype components and materi-
Contribution to the objectives one of the 5 main tant to the marine environment.
modeling tools.
37 https://ec.europa.eu/info/funding-tenders/opportunities/portal/screen/opportunities/topic-details/horizon-cl5-2021-
d3-03-10
EU-India Clean Energy and Climate Partnership (CECP) Page 101
8 BARRIERS TO FLOATING PV DEVELOPMENT AND HOW TO
ADDRESS THEM
The following table summarizes the barriers and their impacts on FSPV deployment and proposes the
best practices to consider when addressing those barriers.
Table 1 Barriers and Best Practices (Source - Enabling floating solar photovoltaic (FPV) deployment, USAID-NREL June 2021)
Asia accounted for 60% of new capacity in 2021, increasing its renewable capacity by 154.7 GW to reach
1.46 TW (48% of the global total). A huge part of this increase occurred in China (+121 GW). Capacity in
Europe and North America expanded by 39 GW (+6.4%) and 38 GW (+9.0%) respectively, with a notably
large expansion in the USA (+32 GW). Africa continued to expand steadily with an increase of 2.1 GW
(+3.9%), slightly less than in 2020. Oceania is no longer the fastest growing region (+5.2%), although its
share of global capacity is small and almost all of this expansion occurred in Australia.
Solar and wind energy continued to dominate renewable capacity expansion, jointly accounting for 88%
of all net renewable additions in 2021. Along with the higher growth of geothermal, this growth in wind
and solar led to a high annual increase in renewable generating capacity.
Solar energy: With an increase in new capacity in all major world regions in previous years, total global
solar capacity has now outgrown wind energy capacity. Expansion in Asia was 76 GW in 2021 (compared
to +77 GW in 2020), with major capacity increases in China (+53.0 GW) and India (+10.3 GW). Japan also
added 4.4 GW and Republic of Korea expanded solar capacity by almost 3.6 GW.
Outside Asia, the United States added 19.6 GW of solar capacity in 2021, Brazil and Germany respectively
added 5.2 GW and 4.7 GW and the Netherlands and Spain added more than 3 GW.
EU-India Clean Energy and Climate Partnership (CECP) Page 107
Figure 1- Solar PV deployment by country in GW in 2030, according to IRENA.
The different types and applications of PV systems is shown below, where floating PV has joined the PV
applications recently and is currently being buzzed across the world.
A rapid grow of floating solar projects has been seen worldwide. Thanks to FPV technological
enhancements and an increase in FPV capabilities, new capacity records continue to be broken. Indeed,
South Korea is developing the world’s biggest floating solar power plant with a capacity of 2.1 GW while
in India, a 600 MW FPV project is to be constructed at Omkareshwar dam in Khandwa district. Many of
the largest planned installations are facing delays with tenders, site challenges, and financing, but
expectations are high for record-breaking floating PV systems to begin construction shortly. The
following figure shows the top ten floating PV markets from 2020 to 2024.
An overview of the top 50 operating floating PV systems in the world have been mapped in the table
below. As it can be seen, Sungrow Floating and Ciel & Terre are the two dominant floating system
providers in the market, with more than 50% market share together.
Guqiao Huainan/
China coal 150.00 China 2018 Sungrow Asia
subsidence
Yingshang coal
mining subsidence 130.00 China 2018 Mixed Chinese Asia
area
Xinji Huanian/ China
102.00 China 2017 Sungrow Asia
coal subsidence
Weishan Jining/
China large-scale 100.00 China 2018 Sungrow Asia
waters
Anhui Cecep,
Lianghuai mining 70.00 China 2019 Ciel & Terre Asia
subsidence area
China coal
subsidence
Da Mi hydropower
47.50 Vietnam 2019 Narime-Qihua Asia
reservoir
Coal mining
subsidence area of 40.00 China 2016 Sungrow Asia
Huainan City
Coal mining
subsidence area of 32.69 China 2017 Ciel & Terre Asia
Huainan City
Weishan Jining/
China coal 31.00 China 2018 Sungrow Asia
subsidence
PV-Floating /
Bomhofsplas 27.40 Netherlands 2020 Europe
Zimmermann
Reservoir in Goheung
county (Jeollanam
25.00 South Korea 2020 Scotra Asia
province)
Xinyi/Anhui Province/
20.00 China 2016 Sungrow Asia
Coal subsidence
PV-Floating /
Kloosterhaar 15.70 Netherlands 2020 Europe
Zimmermann
PV-Floating /
Sekdoorn 14.50 Netherlands 2019 Europe
Zimmermann
Yamakura solar
13.74 Japan 2018 Ciel & Terre Asia
power plant
PV-Floating /
Nij Beets 13.50 Netherlands 2020 Europe
Zimmermann
Mining subsidence in
13.00 Malaysia 2020 Sungrow Asia
Dengkil
Zimmermann
PV-Floating /
Dessel 7.00 Belgium 2020 Europe
Zimmermann
Hirotani Ike Floating Takiron
6.80 Japan 2018 Asia
Solar Plant Engineering
Queen Elizabeth II
6.34 UK 2016 Ciel & Terre Europe
Reservoir
Bui hydropower
5.00 Ghana 2020 NA Africa
reservior
Sayreville, New North
4.40 USA 2019 Ciel & Terre
Jersey America
Sujang Reservoir
3.00 South Korea 2017 Seaflex Asia
Solar Park
Godley Reservoir
2.99 UK 2016 Ciel & Terre Europe
Floating Solar PV
Flooded quarry in
Saint-Maurice-la- 2.70 France 2020 Akuo Industries Europe
Clouère
EU-India Clean Energy and Climate Partnership (CECP) Page 113
Name of plant/region Size Country Operational Floating System Contine
(MW) Year Provider nt
Deoku Reservoir,
Myeoku Reservoir (3 2.70 South Korea 2016 NA Asia
plants in total)
In terms of systems providers, the charts below give an overview of the wide disparity in the market
currently and the lack of serious competitors. The market is dominated by two companies, and one
clearly has a more diversified commercial reach.
Figure 1- Capacity share of floating system providers in the top 50 FPV projects
The lack of a substantial number of floating PV system providers limits the development of the market,
the choice for sponsors/developers and EPC contractors as well as lenders’ confidence on the
technology. In terms of integrators and EPC contractors, the table presented below, is based on the
World Bank/SERIS report.
Table 1- List of FPV system suppliers with EPC services offered (based on SERIS report, 2018)
The landscape of experienced EPC contractors is again limited, but there are more options and
companies with experience in the MW for floating PV systems. Thus, the recommendation at this stage
of the market development is to have an EPC contractor with capacity in PV and desirably in floating PV
using floating PV structures with track record. The following table includes for all top 50 FPV projects,
the respective EPC contractors.
Name of Operational
Size (MW) Country EPC Contractor
plant/region Year
Guqiao Huainan/
China coal 150.00 China 2018 Sungrow
subsidence
Three Gorges New
Anhui province 150.00 China 2018
Energy CO
Yingshang coal
mining subsidence 130.00 China 2018 Trina Solar
area
Xinji Huanian/ China
102.00 China 2017 Sungrow
coal subsidence
Weishan Jining/
China large-scale 100.00 China 2018 Sungrow
waters
Anhui Cecep,
CCECST -
Lianghuai mining 70.00 China 2019
CEEGSEPDI
subsidence area
Huancheng Jining /
China coal 50.00 China 2018 Sungrow
subsidence
Da Mi hydropower
47.50 Vietnam 2019 DHD
reservoir
Coal mining
subsidence area of 40.00 China 2016 Sungrow
Huainan City
Coal mining
subsidence area of 32.69 China 2017 NA
Huainan City
Weishan Jining/
China coal 31.00 China 2018 Sungrow
subsidence
Reservoir in
Goheung county
25.00 South Korea 2020 Scotra
(Jeollanam province)
Xinyi/Anhui
Province/ Coal 20.00 China 2016 NA
subsidence
Akuo/ Bouygues
O'mega1 17.00 France 2019
Energies Services
Yamakura solar
13.74 Japan 2018 Kyocera
power plant
Agongdian
7.67 Taiwan 2018 NA
Extension
Sujang Reservoir
3.00 South Koreai 2017 Seaflex
Solar Park
Godley Reservoir
2.99 UK 2016 Forrest
Floating Solar PV
JFE Plant
Hyoshiga Ike 2.70 Japan 2019 Engineering
Corporation
Flooded quarry in
Akuo Industries/
Saint-Maurice-la-
2.70 France 2020 GSM
Clouère
Deoku Reservoir,
Myeoku Reservoir (3 Solkiss
2.70 South Korea 2016
plants in total)
Sungrow, Trina lead in size while Ciel et Terre has also developed some of the FPV plants.
Sr. Capacity
Owner Project name Water body Status
No (MW)
Raw Water Reservoir of
1 NTPC Kawas 1 In operation July 2019
thermal project
Raw Water Reservoir of In operation since March
2 NTPC Kayamkulam 0.1
thermal project 2017
Raw Water Reservoir of
3 NTPC Simhadri 25 Under execution
thermal project
Raw Water Reservoir of
4 NTPC Ramagundam 100 Under execution
thermal project
India had about 2.7 MW of installed FPV capacity by the middle of 2019, and projects with a combined
capacity of 1.5 GW capacity under development. The Indian government has set a target to achieve 10
GW of FPV capacity by 2022. Investment costs and bid prices for FPV tenders have also been rapidly
declining. As a result, India achieved the lowest cost for FPV projects at ₹35 ($0.5)/watt during the bid
for 70 MW FPV capacity in Kerala.
India is a leader in clean energy—the country aims to install 175 GW of renewable energy by 2022 and
450 GW by 2030. Interest in FPV is growing in India with several water bodies across the country. FPV
taps the country’s large water reservoirs to overcome some of the persisting issues of ground-mounted
solar, such as the lack of levelled land, evacuation infrastructure and performance degradation due to
high operating temperatures. India could potentially build 280 GW of FPV capacity by utilizing about 30%
(nearly 1,800 kms2) of its medium and large water reservoirs.
State-owned hydropower giant NHPC has signed a pact with Green Energy Development Corporation of
Odisha to form a joint venture to set up 500-megawatt floating solar power projects in Odisha. The joint
venture (JV) will make an initial investment of over Rs 2,000 crore to set up 300 MW floating solar
projects, which would generate 600 million units (MU) per annum.
In the first stage, 300 MW floating solar capacity will be installed in the reservoir of the Rengali HE
project. The project will be implemented under Ultra Mega Renewable Energy Power Park (UMREPP),
Mode 8 of Solar Park Scheme.
Damodar Valley Plans 1.7 GW of Floating Solar Projects in West Bengal and Jharkhand
The hydel power generator would execute the floating solar projects in four dams
DVC has already proposed 1,776 MW of floating solar projects in four of its dams in West Bengal and
Jharkhand. These two states jointly own the corporation along with the Union government.
DVC would execute the floating solar projects in the four dams of Maithon, Tilaya, Konar, and Panchet. It
would complete these projects in three phases, and the first will be a 50 MW project.
DVC had already floated the tender for a 50 MW solar project at Panchet (Jharkhand).
Indian companies have also started to get interested in floating solar PV and its development. Within
recent years many companies working on the floating system industry started to shift their interest on
floating solar systems and started manufacturing them locally. Among those companies we can find:
VARI PONTOON PVT LTD: an Indian origin company formed in 2017 who manufactures floating solar
panel systems in India using HDPE. They offer a wide range of services namely design and
development, manufacturing, installation and commission and turnkey project.
WAAREE ENERGIES LTD: is an EPC and PV module manufacturer in India. They also offer floating PV
systems made in India.
JAIN IRRIGATION SYSTEMS LTD: the company has manufacturing plants of plastic pipes, precision-
irrigation products and PV panels. The company has also developed floating HDPE structure for
floating PV solar power plants where they manufacture in house.
ADTECH SYSTEMS LTD: an Indian company focusing on Integrated Electronic Security Systems and
Non-Conventional Energy Solutions. The company offers services related to the design and
engineering of FPV, supply and sale of floating structures (Ferrocement and HDPE) and integration
of FPV projects.
SUNIBOAT LTD: the company offers services related to the development of FPV projects, EPC for
floating solar plants and the O&M of the floating arrays.
YELLOW TROPUS PVT LTD: the Indian based company focuses on the development of FPV power
plants offering three technologies namely, Seahorse technology, Stingray technology and dual axis
technology. The services offered by the company ranges from feasibility studies to Operation and
Maintenance. They offer also the manufacture and supply of the components as well as the
installation and commissioning,
PV modules prices in 2020 were around 0,22 eur/Wp from 0,33 eur/Wp in 2017 and have since then
maintained its value. EPC prices are believed to be actually around 550 eur /kWp in Europe. Inverter
prices in the other hand are negotiated at a regional level. Their prices follow the same decline as the
panel prices. The estimated average price of central inverters for a solar PV system of about 50 MWp is
about $0.06/Wp (€0.057/Wp). Recent cost estimates of pure HDPE floating structures (including
anchoring and mooring) range between $0.14/Wp (€0.13/Wp) and $0.22/Wp (€0.21/Wp).
Figure 33 gives an overview of proposed bids for various tendered FPV projects worldwide. India is very
competitive regarding CAPEX than other countries. Aggressive bidding by developers is considered to
be the main reason for the low bids.
As figure 37 shows, prices in India are declining with approximately a 45% decrease in cost from 2016 to
2018. The lowest cost of floating solar power was indeed achieved for the 70 MW Kayamkulam project.
The Indian FPV market is considered to be one of the most competitive in the world.
Figure 1- Investment cost for floating solar PV projects in India (Source: TERI)
The Indravati River is a stream of the river Godavari. Its starting point, found to be the Ghats of
Dandakaranya, range from a hilltop village Mardiguda of Thuamula Rampur Block in the Kalahandi
district of the state of Odisha. Due to the amalgamation of three streams, The River follows a westerly
path and enters Jagadalpur in the state of Chhattisgarh. The river moves from here in a southern route,
before eventually uniting with the Godavari at the borders of three states. They are the state of
Chhattisgarh, Maharashtra and Telangana. The river at a variety of stages of its course forms the
boundary between Chhattisgarh and Maharashtra. The river Indravati is also known as the oxygen of the
Bastar district of state of Chhattisgarh. This district is one of the greenest and eco-friendly districts,
found in the whole of India. A total number of five hydroelectric projects were planned on the river
Indravati. They were namely the Kutru I, the Kutro II, the Nugru I, Nugru II and the Bhopalpatnam.
However, the plan misfired and did not see the light of the day due to ecological reasons. The Indravati
The Indravati rise on the western slopes of Easter Ghats. The highest Elevation is 3125. This river flows
from the height of 914 m in the district of Kalahandi district of the state of Odisha, located on the slopes
of the Eastern Ghats. It covers a length of 164 km, while flowing past the districts of Koraput, Kalandi
and Nabarangapur after creating a boundary, between the states of Odisha and Chhattisgarh. A total of
length added up to 9.5 km, entering the district of Bastar district of the state of Chhattisgarh. Here, the
river covers a distance of 233 km inside Chhattisgarh.
From there, the river Indravati swings towards the south and moves to the boundaries of the states of
Chhattisgarh and Maharashtra. Then, after flowing for 129km, joins the Godavari, at the boundaries of
Maharashtra, Chhattisgarh and Andhra Pradesh.
The sub basin of the river Indravati is spread over an area of about 40625 sq km. Its catchment area is
about 7535 sq km in the state of Odisha. The length of the river is about535.80 km. It originates in the
hills of Kalahandi and joins the river Godavari at Bhadrakali, a village in the Bijapur district of the state of
Chhattisgarh. The journey from the start to the finish is a well-defined course.
The river begins in a South-East direction as a small rivulet, in the state of Odisha. Lat-er it takes a
westerly direction through Bastar district of the state of Chhattisgarh. From here the river then takes a
The river’s bed level at its union with the Godavari River is R.L. 82.3 m as compared to the level in
Kalahandi. It takes off at 914.4 m. The Indravati and the Sabari rivers are it is also interconnected in the
state of Odisha. The waters of the Indravati overflow into the Sarbari, via the Jaura Nallah.
Table 1- Salient features, reservoir capacity and water spread of Indravati Dam
19°16′34.8″N 082°49′42.4″E
Coordinates
19°16′34.8″N 082°49′42.4″E
Construction began 1978
11.2 Connectivity
Air
Utkela Airstrip (VEUK) is present near the city (22 km, 14 mi) which is scheduled to be operational with
daily flights to state capital Bhubaneshwar and Raipur in this year by private air service provider Air
Odisha under UDAN scheme by Ministry of Civil Aviation, Govt. of India. Another one, Lanjigarh Airstrip
(FR44733) (58 km, 36 mi) is private airstrip conducting VIP and chartered planes. Swami Vivekananda
Airport at Raipur, Chhattisgarh is 262 km (163 mi) away. Biju Patnaik International Airport in the state
capital, Bhubaneswar is 427 km away by road and 631 km by rail.
Bhawanipatna Bus Stand is one of the biggest bus stands in Odisha present on NH-26. Both Private and
Govt. buses are available from here. Bhawanipatna is one of the divisions of Odisha State Road
Transport Corporation (O.S.R.T.C.) that runs Govt. Buses from Bhawanipatna to Bhubaneshwar,
Vishakhapatnam, Sambalpur, Berhampur, Cuttack, Jeypore. Private Buses (A/C Sleeper Coaches) provide
transportation facility to different cities in Odisha and Raipur, Durg etc. in Chhattisgarh. Newly added
taxi facility and auto facility including Biju Gaon Gadi throughout Bhawanipatna and villages nearer to it,
is adding an advantage to the transport facility.
Rail
It can be seen that the western part of the state receives more GHI than the eastern part. Also, the
Indravati dam is located in a site with good GHI potential, making it prone to a good yield from solar PV
projects. To determine the GHI for the Indravati site, data obtained from NREL, NIWE, NASA, SolarGIS
and Meteonorm were analyzed and compared.
Month Gh Gk Dh Bn Ta Td FF
Global
Global tilt Diffuse Beam Dew point Wind
horizontal Temperature
irradiation radiation radiation temperature speed
irradiation
[kWh/m²] [kWh/m²] [kWh/m²] [kWh/m²] [°C] [°C] [m/s]
Jan 154 165 41 202 20.1 12.3 0.3
Feb 159 167 45 179 23.2 13.3 0.5
Mar 181 186 73 160 26.6 15.2 0.5
Apr 191 193 73 168 29.4 18 0.7
May 199 198 89 151 30.6 19.7 0.7
Jun 146 144 85 82 27.7 22 0.7
Jul 122 121 81 58 25.3 22.7 0.6
Aug 127 127 86 58 24.9 22.6 0.6
Sep 130 132 69 90 25.6 22.4 0.5
Oct 153 159 63 141 24.7 20.1 0.4
Nov 145 154 49 165 21.7 15.8 0.3
Dec 132 142 47 158 20.7 12.2 0.4
PARAMETER JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC ANN
0.58 0.66 0.6 0.56 0.55 0.36 0.37 0.4 0.39 0.54 0.52 0.52 0.49
All Sky Insolation Clearness Index
(dimensionless)
24.97 19.72 28.17 49.69 62.48 84.96 89.98 91.33 91.66 57.6 57.74 42.18 58.55
Cloud Amount (%)
0.61 0.67 0.63 0.64 0.66 0.6 0.63 0.62 0.65 0.63 0.62 0.6 0.63
Clear Sky Insolation Clearness Index
(dimensionless)
7.58 8.6 9.72 10.52 10.86 10.91 10.83 10.56 9.92 8.9 7.8 7.22 9.46
Top-Of-Atmosphere Shortwave
Downward Irradiance (kW-hr/m^2/day)
9.39 12.58 12.7 13.71 15.07 10.15 10.65 11 10.6 11.67 9.48 8.19 11.26
All Sky Surface UVA Irradiance (kW-
hr/m^2/day
0.23 0.31 0.34 0.38 0.44 0.3 0.32 0.33 0.31 0.3 0.23 0.2 0.3
All Sky Surface UVB Irradiance (kW-
hr/m^2/day)
0.12 0.12 0.12 0.12 0.13 0.13 0.16 0.16 0.14 0.12 0.12 0.12 0.13
All Sky Surface Albedo (dimensionless)
4.37 6.29 4.99 4.12 4.42 2.02 1.82 1.82 1.99 3.54 3.1 3.53 3.49
All Sky Surface Shortwave Downward
Direct Normal Irradiance
(kW-hr/m^2/day)
4.36 5.63 5.86 5.9 5.98 3.94 3.96 4.2 3.9 4.82 4.03 3.74 4.69
All Sky Surface Shortwave Downward
Irradiance (kW-hr/m^2/day)
4.6 5.77 6.13 6.75 7.25 6.55 6.88 6.58 6.45 5.6 4.83 4.36 5.98
Clear Sky Surface Shortwave Downward
Irradiance (kW-hr/m^2/day)
78.34 101.8 105.33 109.96 115.67 77.69 78.3 82.56 77.07 91.32 75.04 67.41 88.3
All Sky Surface PAR Total
(kW-hr/m^2/day)
1.76 1.6 2.33 2.72 2.58 2.36 2.54 2.8 2.43 2.4 2.14 1.72 2.28
All Sky Surface Shortwave Diffuse
Irradiance (kW-hr/m^2/day)
83.09 104.43 109.76 123.87 137.39 124.28 131.94 125.7 124.65 105.88 90.24 79.09 111.7
Clear Sky Surface PAR Total
(kW-hr/m^2/day)
19.3 21.36 28.82 32.18 31.51 28.12 25.8 25.39 24.93 23.65 21 17.33 24.96
Earth Skin Temperature (C)
19.7 21.37 27.68 30.02 29.95 27.25 25.46 25.22 24.83 23.6 21.01 17.71 24.49
Temperature at 2 Meters (C)
8.48 6.53 6.65 10.01 14.22 16.97 18.31 18.68 18.62 16.78 14.4 10.5 13.37
Specific Humidity at 2 Meters (g/kg)
58.88 42.38 29.75 40.25 53.44 72.19 84.75 87.75 89.19 86.75 87.12 78.12 67.69
Relative Humidity at 2 Meters (%)
1.91 2.31 2.51 2.62 3.35 3.83 3.77 3.04 2.89 2.05 2.3 2.2 2.73
Wind Speed at 10 Meters (m/s)
2.77 3.27 3.6 3.88 4.66 5.3 5.32 4.51 4.32 3.16 3.52 3.28 3.97
Wind Speed at 50 Meters (m/s)
10.41 6.15 6.4 12.41 18.14 21.32 22.51 22.91 22.82 21.13 18.62 13.39 16.4
Dew/Frost Point at 2 Meters (C)
15.06 13.76 17.04 21.22 24.05 24.28 23.99 24.07 23.82 22.37 19.81 15.55 20.45
Wet Bulb Temperature at 2 Meters (C)
29.75 34.24 40.52 39.87 39.03 37.01 31.53 30.07 29.98 30.08 28.19 25.69 40.52
Temperature at 2 Meters Maximum (C)
11.44 11.24 15.9 19.88 21.08 21.96 21.63 21.45 21.3 15.37 11.57 6.8 6.8
Temperature at 2 Meters Minimum (C)
19.7 21.37 27.68 30.02 29.95 27.25 25.46 25.22 24.83 23.6 21.01 17.71 24.49
Temperature at 2 Meters Range (C)
4.73 4.81 6.15 6.6 10.37 9.73 8.82 7.35 9.23 5.66 5.75 6.47 10.37
Wind Speed at 10 Meters Maximum
(m/s)
0.05 0.08 0.04 0.05 0.23 0.16 0.63 0.71 0.16 0.05 0.22 0.22 0.04
Wind Speed at 10 Meters Minimum
(m/s)
6.98 7.02 8.22 8.73 13 12.08 11.19 8.95 12.4 6.89 7.3 8.07 13
Wind Speed at 50 Meters Maximum
(m/s)
0.08 0.11 0.08 0.16 0.12 0.2 0.99 1.35 0.12 0.1 0.23 0.3 0.08
Wind Speed at 50 Meters Minimum
(m/s)
4.67 4.73 6.11 6.55 10.14 9.58 8.19 6.64 9.06 5.61 5.53 6.25 10.33
Wind Speed at 10 Meters Range (m/s)
6.9 6.91 8.14 8.57 12.88 11.88 10.2 7.59 12.27 6.79 7.06 7.77 12.92
Wind Speed at 50 Meters Range (m/s)
343.75 335.2 374.61 406.27 416.6 419.96 417.93 417.89 413.94 396.95 375.61 348.91 389.25
All Sky Surface Longwave Downward
Irradiance (W/m^2)
Bathymetry survey is important for choosing a position for the floating island and designing the
mooring and anchoring systems. Bathymetry is the mapping of the water body bed, with depth
contours providing the size, shape, and distribution of under- water features. A bathymetry report
should include the topographic map, boring logs, and detailed relief of the waterbed. To make it cost-
effective, bathymetry could be conducted with a large grid size while identifying a suitable area within
the water body. Once a suitable area is identified, then a study with a smaller grid size is conducted.
We were not able to conduct the bathymetry studies and also not able to gather data from the local
water basin management office, despite the official requests and efforts conducted. Thus, our analysis is
During the monsoon, the Godavari river spills its banks in the lower reaches downstream of confluence
of river Indravati with Godavari causing floods. In Maharashtra, the problem is confined to the Nanded
Town situated on the banks of the river as also to the agricultural lands on the banks of the river in
Nanded and Parbhani districts and those on the banks of the Wardha and Wainganga in the Vidharbha
region. The parts of the basin lying in Madhya Pradesh, Odisha and Karnataka generally have no serious
flood problem. The flooding of deltaic areas has been prevented by construction of embankments.
The lower reaches of river Godavari also have significant free catchment areas and two major left bank
tributary namely, Taliperu and Sabari and one right bank tributary Kinnersani confluences river Godavari
in this reach. The flood forecasting stations this reach are Eturunagaram, Dummagudem, Bhadrachalam,
Kunavaram, Rajahmundry Railway Bridge and Dowlaiswaram Barrage. The back water effect into river
Sabari in case of high flood in Godavari and the constriction in the river near Papi Hills are the significant
features of the river in the lower reaches.
The flooding analysis shows a very low impact to the project development.
Indravati at
1 3948 08.7.2021 2:10 PM 25 7.6 7.2
Nwarangpur
FS,
Sl. BOD,
Name of Station COD, mg/L TC, MPN/100 mL FC, MPN/100 mL MPN/ WQI
No. mg/L
100 mL
Indravati at Satisfac-
2 1.2 7.7 3500 1400 NA
Nwarangpur tory
The water levels keep changing and we need to consider catchment area at DSL (Dead Storage
Level).
Surface area of water body to be considered at DSL.
Approximately 1.1-hectare Water body surface area is required for installation of 1 MWp Floating
Solar Plant.
Drag force acting on each island (reducing that value by using a low tilt).
Installation of floating islands should be far away from dam gates, so as to avoid high water
current will not affect the floating islands during opening of discharge gates.
Dam dead storage is the volume of water which is below the level of the spillway or other outlet. In
other words, the volume of water that cannot be released from a dam (unless the dam wall bursts). The
capacity, volume or storage of a Dam is usually divided into distinguishable areas.
Dead or inactive storage refers to water in a Dam that cannot be drained by gravity through a dam’s
outlet works, spillway or power plant intake and can only be pumped out. Most dams have multiple
options for discharge. The Dead Storage Level of Indravati dam is RL (625’) from MSL.
Data provided by the Basin manager and the chief engineer of the dam:
As per above data, the lowest water level occurrence in Indravati dam happened in year 2018 with the
level RL 627m and the date of occurrence was 01-07-2018. With the help of google Earth using the
timeline, the water surface area of the Indravati dam was superimposed and water surface area of that
particular patch was measured and reproduced as below.
Figure 1- Water Spread Area at the lowest water level – using Google earth
From the analysis of the data provided by the Indravati basin manager, the proposed catchment area
selected for the floating solar plant is adequate for installation of 160 MW Floating Solar Plant based on
available water spread area at the RL level of 627 m which is very close to the Dead storage level
(625.00) of the dam. Hence, the portion of water body selected above can be used for the development
of the floating solar plant.
• Assembly point: The access to the water is required not only for construction, but also for operation
and maintenance. Each island is assembled on land and then pushed into the water and tugged by
boat. Thus, a sufficiently large access to the water is required to reduce time and costs and also to
provide a secured water access point, which can be used to perform O&M activities. This aspect is
key for floating PV projects. For very large utility scale floating solar PV plants the option to have
inverters floating is the only feasible option. It was considered thus assembly areas with at least
300m to allow for 2 islands to be assembled in parallel. It was also envisaged that this assembly
point would have at least 2 hoists and slides into the water that will be moored,
• Pooling area: this point does not need to be the same as the assembly point but needs to be located
in the vicinity of the body of water to allow for the AC cables to be pooled in a switching gear and
stepped up to the adequate level of transmission to connect to the nearest grid substation. These
areas pose some challenges to be found near to the body of water as they need to be flat and dry all
year.
• Floating PV site: this site is selected near to the pooling area and not really dependent on the
assembly point, as boats will tug the islands to the desired place. The biggest concern is to have
contiguous areas of water that will not get islanded during dry season, avoiding high depths and is
possible not far from the margins of the water body.
There were 3 assembly points analyzed, which are included in the table below along with their
coordinates.
Their locations are shown in the image below. The recommendation is for assembly point 2 as it is nearer to
the site (marked as proposed assembly below) and with a reasonable logistic access. However, the other
assembly points are validated technically and from the environmental and social perspective and may be
used.
A peer type is planned to provide support the assembly area and to make it convenient to the operation
and maintenance of the FPV plants. It is provided below a drawing with the proposed infrastructure.
• Control room
• 33/132 kV transformers.
The location of the recommended pooling area is shown in the image below and is located at around
900 m from the floating PV site.
15.1 MODULES
The following model was used for energy yield estimation and project design. It is one of the TIER-1
manufacturers of PV modules. However, it is not meant to recommend this, or any model and the
project developers may choose the technology/ supplier/ manufacturer etc. using their own techno-
commercial approach at the project implementation stage.
Total 28 Modules in series will be attached to every string. Such strings will further form in 4 rows
making an array of 4 x 28 modules. These arrays will then join to form a 6 MWp island. Module capacity
considered for configuration is 550 Wp. Total number of PV modules that will be used for the plant is
341824 modules.
15.3 TRANSFORMERS
The description of the transformer used is provided below.
No. of Unit: 04
No. of Unit: 04
10. Cooler Details (Radiators, Unit Coolers , Water Coolers) Radiators (ONAN)
11. Temperature-rise
b) Windings, 0 C 55K
No. of Unit: 04
It is well established that the energy generation through solar PV module is essentially govern by the
amount of incident solar irradiance over its surface. In order to augment the incident irradiance over the
solar PV modules; the solar PV modules are arranged in inclined, seasonal adjustment, single or double
axis tracking mode specially to reduce the angle of incidence of solar irradiance over the surface of the
module and increase in the incident solar irradiance. Hence the benefit of the tilt angle or tracking
depends upon the geography (latitude and longitude) of any location, solar irradiation and wind speeds.
In fact, the wind load plays a vital role in deciding the quantum of drag force being induced on the
mounting structure. In case of FSPV plants, this is even of much importance, as a high angle of tilt can
induce high drag forces potentially causing severe damage to the entire plant structure. In order to
reduce the cost of anchoring, floating structures, the operation and maintenance activities and auxiliary
energy consumption the fixed axis (without tracking and any seasonal adjustment) is mostly preferred.
In this project the fixed axis and fixed tilt angle has been adopted for entire solar PV power project of
160 MW capacity with a tilt angle of 5°, to reduce the drag force.
The following table shows the PVsyst simulation for the 188 MWp/160 MWac Indravati FPV plant.
Tilt (Degree’s) 5
No of modules 341824
Inverter Capacity 5 MW
No of Inverter 32
The losses in the Solar PV System depends on the Solar PV Module and Inverter technology
used, efficiency and quality of PV Modules, Inverter, Junction Boxes and cables, workmanship
of installation and scheduled maintenance and cleaning. The models of Solar PV Module as
well as the Inverter selected for the simulation process comply with relevant international
standards. The simulation results for different associated losses in the solar PV power project
under the conditions of fixed tilt at the proposed location are given in table below.
Taking into account all technical losses the annual CUF is above the benchmark value of 19%
considered by Central Electricity Regulatory Commission (CERC), Government of India for
annual tariff determination for grid connected solar PV power projects. CUF for the 160MW
Floating Solar Plant is 20.81%.
Chief Electrical Inspector of Government (CEIG): approval of the PV plant and power evacuation
Transmission company: permission for construction of the transmission line between the pooling
area and the grid substation
State Pollution Control Board: consent to Establish (CtE) for all sites, based on the Air (Prevention
and Control of Pollution) Act, 1981 and Water Prevention and Control of Pollution) Act, 1974.
Archaeological Dept. GoI: seek approval and modify project siting as necessary, based on the
Ancient Monuments and Archaeological Sites and Remains Act, 1958
Forest and Environment Department: seek approval before felling any trees, pay for compensatory
tree plantation.
State pollution control board: Consent to Operate for emissions to the air and discharging treated
effluent from labour camps and construction activities, based on the Air (Prevention and Control of
Pollution) Act, 1981 and Water Prevention and Control of Pollution) Act, 1974
State Pollution Control Board: authorization and carry out Waste Segregation and Disposal, based
on the Solid Waste (Handling and Management) Rules, 2016
State Pollution Control Board: conduct monitoring and ensure that noise generation is within
threshold The Noise Pollution (Regulation and Control) Rules, 2000
District Labour Commissioner and Buildings Inspector: ensure all contractors have BOCW
Registration as applicable and are following requirements, based on the Building and Other
Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996
The following is required to be conducted yearly and during the lifetime of the project:
The communication of a Qualified Control Agency (QCA) for the PV plant, based on the CERC -
Procedure for implementation of framework on forecasting, scheduling and imbalance handling,
2017
State pollution control board: maintain records of electronic and electrical waste generation and
disposal and file annual returns, based on E-waste (Management) Rules, 2016
Motor Vehicle Dept. / RTO: follow requirements of CMV Rules such as PUC, based on Construction
and Other Vehicles Central Motor Vehicle Act, 1988
4 Mobilization at site 6 8
5 Preparatory works 8 10
7 Civil Works 10 40
8 Inspection of material 16 30
13 Erection of Floaters 26 36
14 Erection of Modules 32 40
15 Cabling work 36 42
Assembly point
1 Land Development and As- Lot 0.5 188 94 90 7
sembly works
2 Peer construction with hoists Lot 3896104 1 3896 3727 300
and other machinery for load-
ing and unloading
Pooling station
1 Transformers - Inverter & Lot 3896 360 1403 1342 108
Step up
2 Switchgear and Panels Lot 3247 360 1169 1118 90
3 SCADA, Surveillance, Fire Lot 10 188 1880 1799 145
Fighting, Safety, Monitoring
38 The whole project was priced jointly, but it is recommended that multiples of 100 MW are considered, as per the
suggested technical design.
EU-India Clean Energy and Climate Partnership (CECP) Page 166
FPV plant Unit Quantity Amount in Amount in Million
costs Thousand Thousand INR
(USD) USD EUR
4 Buildings Lot 324675 1 325 311 25
5 Drains, Road, fencing and Lot 64935 1 65 62 5
gates
Grid connection
1 132 kV Double Circuit over- KM 51948 17 883 845 68
head line (21 km)
2 132 kV bays at Tentulikhunti Lot 77922 2 156 149 12
substation (with switches and
protections)
Add
Contingencies 3.00% 3626 3469 279
Local Area Development 1299 1243 100
Pre- Project development ex- 1299 1243 100
penses (permits and authoriz-
ations)
GRAND TOTAL 127089 121592 9786
Profit margin 10% 12709 12159 979
139798 133752 10764
Price per MW in Million Rs. 67.27
20.2 LCOE
Based on the International Energy Agency definition of LCOE and with a 1,5% of the total installation
CAPEX as the OPEX and a loss of efficiency of the modules per year of 0,5%, the following results were
obtained for the LCOE; which are in line with the current tariffs for floating PV projects in India.
Figure 15: Variation of the LCOE with the CAPEX considering 8% of discount factor.
The hard cost of the FPV system comes out to be Rs 58.17 Mn/MW and the soft costs are Rs 5.25 Mn/MW for
a total project cost of Rs 63.42 Mn/MW. The project cost is assumed to be funded by a mix of debt and
equity with DER of 3:1.
MAT Rate %
Nil
Equity IRR Project IRR Tariff (INR/ kWh) Avg. DSCR Payback period
floating PV plant developed on the basis of the single IPP plants, which could even be done as
captive plants also. All the costs would be under the responsibility of the developers as well as
the potential interest of an off taker, which could be in the state, outside the state or a
private(s) customer.
floating PV park development with FPV plants being developed in the normal roll-out of PV
projects in solar parks as per the relevant Indian regulation 39. Not being the aim of this DPR to
detail the solar park scheme, the scheme could be used to avail up to 20 lakh/MW for the
external infrastructure of the solar park, while the rest could be charged from the IPPs as well
as the facilities for the assembly and O&M. Under the estimated cost of the project this could
mean 100 Cr of reduced cost, which is the cost of the grid connection part.
An IPP develops a floating PV plant on a reservoir and sells power to the discom or through
open access to a customer in the Indian grid (captive power). This requires for securing the
license to install the FPV plant in a water body, the development of the FPV plant, obtain the
connection to the grid, sign a PPA and apply for a license to generate solar power.
The IPP develops a floating PV plant in a floating solar park. To be able to access the floating
park, the IPP would have to compete in tariffs to get in. The obligations in terms of licensing
would remain, but the PPA would be secured.
Table 1- Summary of the business models for the implementation of the project
Solar Park scheme Phase development Solar power park Generated kWh or
of 40 MW multiples developer (SPPD), electricity unit-based
per each phase as the solar power payment regulated
39 https://mnre.gov.in/solar/schemes
EU-India Clean Energy and Climate Partnership (CECP) Page 173
Value proposition Stakeholders Revenue Model
Technical
Yield is lower than expected due to High High Keep the CAPEX as low as possible to avoid
water temperature lower productions than expected and utilize
floating structures as open as possible to
improve the natural convection.
The floating islands are too close to High Low The clearances considered seems sufficient,
each other but a larger footprint may be considered or
reduce the DC/AC ratio.
Logistics to access the water are not High Medium The peer concept to enable infra-structured
sufficient access to the water at all times during
construction and O&M seems sufficient, but
the peer may need to be larger, or more than
one peer may be required due to space
constraints. Several other sites for the
assembly points were assessed to allow that.
The pooling station is not big enough High Low The proposed power evacuation concept is
sound, but in alternative floating
transformer can be used to reduce the
number of cables and transformers at the
pooling station.
Alignment of the 132 kV line is not High Low The recommended alignment follows
technically viable existing infrastructures, which allow for
effective ROW, but in alternative other
routes more inland are possible and may be
explored if needed along the corridor to
Tentulikhunti substation.
Safety
Danger while working in the water High Medium When working near, in or on water, workers
reservoir. shall never work alone. Life vests shall be
always worn. In case of operations by divers
are expected, divers shall be properly trained
and certified professionals. Other personnel
Drowning risk due to material or High High Risk of crushing or drowning due to
equipment used (defective) boats or accidents shall be
mitigated by periodic controls of the status
of the boats after placing them into the
water. Boats shall be manoeuvred at safe
speed. Risk of injury due to sharp edges and
rough surfaces can be limited by having
adequate first aid equipment and first aid-
trained personnel shall be always present on-
site during work, in order to promptly react
to mitigate injuries due to sharp edges and
rough surfaces.
Fire risk Medium Medium A fire risk assessment shall account for the
presence of flammable system components,
moving parts, varying mechanical loads and
changing weather conditions that affect
both the risk of fire and the effectivity of
extinguishing operations. Risk of fire caused
by electrical failures shall be inherently
minimized by complying to the electrical
requirements
Environmental
The FPV plants harm the ecosystem in High Low Indravati is a very large reservoir and we are
the reservoir using a very small portion of it, which is
unlikely to have such effects. However, more
spaced islands may be considered to
Social
Local fishermen cooperatives have High Low It is unlikely that fishing will be impacted due
reduced income from fishing due to to the large area of Indravati. However,
the FPV opportunities to do O&M of the FPV plants
may supplement fishing activities. Possibility
to develop cages to trap the fish in case they
reside below the floating islands.
Financial
Cost of floating systems increases Medium Low Development of a local industry on floaters
may solve the price and also encourage
industry development
Cost of PV components increases due Medium low India has already a well-developed supply
to the international situation chain in India in the PV sector, which may
limit the impact of external shocks.
Regulation
Permits to use the reservoir are not High Medium Indravati is a restricted area and though
granted authorities have been open to the idea of
granting the development, this remains a
risk. This DPR and the workshop to present
the results and the inherent benefits is an
active mitigation to this issue.
To ascertain the applicability of relevant national, state level legislations and IFC Performance
Standards from environmental and social safeguard point of view;
To understand the existing/baseline environmental and social elements of the proposed project
site and project influence area;
To map relevant stakeholders involved in the project and carryout primary consultation with
these identified stakeholders;
To identify the environmental and social impacts that may result due to the proposed project
and propose measures to avoid, mitigate and reduce these impacts;
To develop an environmental and social management guideline for implementation and
monitoring of proposed mitigation measures in difference stages of the project;
To ensure the consideration of budgetary provisions for implementation of proposed mitigation
measures and continuous monitoring of environmental and social safeguard during project
implementation phase.
The following activities have been followed to undertake the preliminary environmental and social
assessment:
Desktop Research: Secondary literature review and review of project related documents/reports to
understand the project elements and current site condition;
Regulatory Review: Study of applicable regulatory norms pertaining to environmental and social
safeguard and establishment of regulatory framework;
Reconnaissance Survey: Preliminary survey by environmental and social specialists to record the
sensitivity of the site, to identify the hotspots (if any) and ground-truthing of secondary data obtained
through literature review;
Baseline Monitoring: To establish baseline condition site specific baseline environmental monitoring
(Ambient Air, Noise, Soil, Ground and Surface Water) has been carried out from suitable locations.
Stakeholders’ Consultation: To ensure inclusion of stakeholders in project planning stage, to make
the project more beneficial and to foresee significant consequence (if any) due to the proposed
project.
Collation and Analysis of Data: The data base generated from various primary and secondary source
has been compared and collated to establish the most authentic baseline scenario.
Assessment of potential Impact and Proposal for Mitigation: The impact due to the proposed
development has been assessed and suitable mitigation measures has been proposed to negate
adverse impact over environment to the maximum extent possible.
Page 182
Floating PV plant in Indravati, State of Odisha, India – Detailed Project Report
Page 183
This publication has been produced with the assistance of the European Union. The contents of this publication are the sole responsibility of the
author and can in no way be taken to reflect the views of the European Union or the EU Delegation. This publication has been prepared for general
guidance on matters of interest only and does not constitute professional advice. You should not act upon the information contained in this
publication without obtaining specific professional advice. No representation or warranty (express or implied) is given as to the accuracy or
completeness of the information contained in this publication, and, to the extent permitted by law, PwC, its members, employees and agents accept
no liability, and disclaim all responsibility, for the consequences of you or anyone else acting, or refraining to act, in reliance on the information
contained in this publication or for any decision based on it.
This publication contains certain examples extracted from third party documentation and so being out of context from the original third-party
documents; readers should bear this in mind when reading the publication. The copyright in such third-party material remains owned by the third
parties concerned, and PwC expresses its appreciation to these companies for having allowed it to include their information in this publication. For a
more comprehensive view on each company’s communication, please read the entire document from which the extracts have been taken. Please
note that the inclusion of a company in this publication does not imply any endorsement of that company by PwC nor any verification of the accuracy
of the information contained in any of the examples.
Version 7.2.14
PVsyst TRIAL
Project: Indravati new
Variant: New simulation variant
No 3D scene defined, no shadings
System power: 188.0 MWp
Kinchamanda - India
PVsyst TRIAL
PVsyst TRIAL
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
Project summary
Geographical Site Situation Project settings
Kinchamanda Latitude 19.26 °N Albedo 0.20
India Longitude 82.84 °E
Altitude 631 m
PVsyst TRIAL
Time zone UTC+5.5
Meteo data
Kinchamanda
Meteonorm 8.0 (1996-2015), Sat=100% - Synthetic
System summary
Grid-Connected System No 3D scene defined, no shadings
Simulation for year no 1
System information
PVsyst TRIAL
PV Array Inverters
Nb. of modules 341824 units Nb. of units 32 units
Pnom total 188.0 MWp Pnom total 160.0 MWac
Pnom ratio 1.175
Results summary
Produced Energy 291 GWh/year Specific production 1549 kWh/kWp/year Perf. Ratio PR 82.81 %
Table of contents
Project and results summary 2
General parameters, PV Array Characteristics, System losses 3
Main results 5
Loss diagram 6
PVsyst TRIAL
Special graphs 7
P50 - P90 evaluation 8
CO₂ Emission Balance 9
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 2/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
General parameters
Grid-Connected System No 3D scene defined, no shadings
PV Field Orientation
Orientation Sheds configuration Models used
PVsyst TRIAL
Fixed plane No 3D scene defined Transposition Perez
Tilt/Azimuth 5/0° Diffuse Perez, Meteonorm
Circumsolar separate
PV Array Characteristics
PV module Inverter
Manufacturer Generic Manufacturer Generic
Model JAM72S30-550/MR Model Sinacon PV5000
(Custom parameters definition) (Original PVsyst database)
Unit Nom. Power 550 Wp Unit Nom. Power 5000 kWac
Number of PV modules 341824 units Number of inverters 32 units
PVsyst TRIAL
Nominal (STC) 188.0 MWp Total power 160000 kWac
Modules 12208 Strings x 28 In series Operating voltage 1006-1500 V
At operating cond. (50°C) Pnom ratio (DC:AC) 1.18
Pmpp 171.9 MWp
U mpp 1053 V
I mpp 163261 A
Array losses
PVsyst TRIAL
Array Soiling Losses Thermal Loss factor DC wiring losses
Loss Fraction 3.0 % Module temperature according to irradiance Global array res. 0.11 mΩ
Uc (const) 50.0 W/m²K Loss Fraction 1.5 % at STC
Uv (wind) 0.0 W/m²K/m/s
Serie Diode Loss LID - Light Induced Degradation Module Quality Loss
Voltage drop 0.7 V Loss Fraction 2.0 % Loss Fraction -0.8 %
Loss Fraction 0.1 % at STC
PVsyst TRIAL
IAM loss factor
Incidence effect (IAM): User defined profile
0°
1.000
30°
1.000
50°
1.000
60°
1.000
70°
1.000
75°
0.985
80°
0.943
85°
0.840
90°
0.000
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
System losses
Unavailability of the system Auxiliaries loss
Time fraction 2.0 % Proportionnal to Power 3.0 W/kW
7.3 days, 0.0 kW from Power thresh.
3 periods
PVsyst TRIAL
Inv. output line up to MV transfo
Inverter voltage
Loss Fraction
Inverter: Sinacon PV5000
Wire section (32 Inv.)
690 Vac tri
2.86 % at STC
MV line up to Injection
MV Voltage 33 kV
Average each inverter
Wires Copper 3 x 300 mm²
Length 100 m
PVsyst TRIAL
Loss Fraction 0.01 % at STC
AC losses in transformers
MV transfo
Grid voltage 33 kV
Operating losses at STC
Nominal power at STC 185271 kVA
Iron loss (24/24 Connexion) 23.16 kW/Inv.
Loss Fraction 0.10 % at STC
Coils equivalent resistance 3 x 0.21 mΩ/inv.
Loss Fraction 1.00 % at STC
PVsyst TRIAL
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 4/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
Main results
System Production
Produced Energy 291 GWh/year Specific production 1549 kWh/kWp/year
Performance Ratio PR 82.81 %
PVsyst TRIAL
Normalized productions (per installed kWp) Performance Ratio PR
PVsyst TRIAL
January
GlobHor
kWh/m²
152.3
DiffHor
kWh/m²
39.89
Balances and main results
T_Amb
°C
19.81
GlobInc
kWh/m²
163.4
GlobEff
kWh/m²
158.2
EArray
GWh
27.68
E_Grid
GWh
24.52
PR
ratio
0.798
February 156.0 43.93 23.17 164.0 158.9 27.35 26.17 0.849
March 185.8 66.67 27.04 191.1 185.0 31.36 30.02 0.836
April 194.7 68.61 29.04 196.2 189.9 31.83 28.09 0.762
May 194.0 92.57 30.56 192.5 186.3 31.35 30.06 0.831
June 137.8 84.19 27.45 136.1 131.6 22.57 21.68 0.847
July 116.7 83.71 25.65 115.6 111.7 19.41 18.66 0.858
August 119.9 77.52 25.10 119.7 115.7 20.06 19.26 0.856
PVsyst TRIAL
September 140.8 69.49 25.35 142.8 138.1 23.80 22.82 0.850
October 145.1 65.42 24.84 150.4 145.5 25.14 21.43 0.758
November 140.4 47.99 21.62 149.2 144.5 25.17 24.12 0.860
December 139.1 43.03 19.38 150.0 145.2 25.49 24.45 0.867
Year 1822.6 783.01 24.92 1871.0 1810.8 311.19 291.29 0.828
Legends
GlobHor Global horizontal irradiation EArray Effective energy at the output of the array
DiffHor Horizontal diffuse irradiation E_Grid Energy injected into grid
T_Amb Ambient Temperature PR Performance Ratio
GlobInc Global incident in coll. plane
GlobEff Effective Global, corr. for IAM and shadings
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 5/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
Loss diagram
1823 kWh/m² Global horizontal irradiation
+2.7% Global incident in coll. plane
PVsyst TRIAL
-0.23% IAM factor on global
-2.10%
-1.03%
-1.19%
LID - Light induced degradation
PVsyst TRIAL
-0.01% Night consumption
307.5 GWh Available Energy at Inverter Output
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 6/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
Special graphs
Daily Input/Output diagram
PVsyst TRIAL
PVsyst TRIAL
System Output Power Distribution
PVsyst TRIAL
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 7/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
PVsyst TRIAL
Year-to-year variability(Variance) 0.5 % Degradation uncertainty 1.0 %
Specified Deviation
Climate change 0.0 %
Probability distribution
PVsyst TRIAL
PVsyst TRIAL
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 8/9
Project: Indravati new
Variant: New simulation variant
PVsyst V7.2.14
VC1, Simulation date:
12/05/22 17:40
with v7.2.14
PVsyst TRIAL
Replaced Emissions
Total: 8179517.7 tCO₂
System production: 291293.36 MWh/yr
Grid Lifecycle Emissions: 936 gCO₂/kWh
Source: IEA List
Country: India
Lifetime: 30 years
Annual degradation: 1.0 %
PVsyst TRIAL
Item
Modules
Supports
LCE
1713 kgCO2/kWp
6.24 kgCO2/kg
System Lifecycle Emissions Details
Quantity
24009 kWp
436520 kg
Subtotal
[kgCO₂]
41120009
2725247
Inverters 619 kgCO2/ 4.00 2474
PVsyst TRIAL
PVsyst TRIAL
12/05/22 PVsyst Evaluation mode Page 9/9
GEDCOL/Odisha
Logo of SunBD
Disclaimer: This publication has been produced with the assistance of the European Union. The contents of this
publication are the sole responsibility of the authors (SunBD and PwC) and can in no way be taken to reflect the
views of the European Union or the EU Delegation.
TABLE OF CONTENTS
1 INTRODUCTION......................................................................................................................................2
1.1 An Overview.......................................................................................................................................2
1.2 Objective of the Study.......................................................................................................................2
1.3 Adopted Methodology......................................................................................................................2
2 PROJECT DESCRIPTION..........................................................................................................................3
2.1 Assembly point...................................................................................................................................3
2.2 Pooling station...................................................................................................................................5
2.3 Grid substation and Transmission Line..............................................................................................5
3 LEGISLATIVE REGULATION AND POLICY CONSIDERATION.................................................................7
3.1 Legal Framework...............................................................................................................................7
3.2 Applicability of Performance Standards (PS)..................................................................................21
4 DESCRIPTION OF ENVIRONMENTAL AND SOCIAL BASELINE CONDITIONS.....................................28
4.1 Introduction.....................................................................................................................................28
4.2 Location and Study Area..................................................................................................................28
4.3 Methodology for Assessment of Baseline Condition.....................................................................29
4.4 Physical Environment.......................................................................................................................30
4.4.1 Topography......................................................................................................................................30
4.4.2 Climatology.......................................................................................................................................31
4.4.3 Natural Hazards................................................................................................................................31
4.4.4 Land use............................................................................................................................................32
4.4.5 Drainage Pattern..............................................................................................................................33
4.4.6 Soil Characteristics...........................................................................................................................34
4.4.7 Ambient Air and Noise Quality........................................................................................................36
4.4.8 Surface Water Environment............................................................................................................37
4.4.9 Ground Water Resources................................................................................................................40
4.5 Biological Environment....................................................................................................................43
4.5.1 Protected Area under Wildlife Act, 1972/Ecologically Important Area...........................................43
4.5.2 Forest...............................................................................................................................................44
4.5.3 Habitat Types, Flora & Fauna..........................................................................................................46
4.6 Social Environment...........................................................................................................................51
4.6.1 Social baseline: District level overview............................................................................................52
4.6.2 Social baseline: Village/s in the Direct Impact Zone of the FSPV....................................................53
4.6.3 Scheduled Tribes in the project Area...............................................................................................57
1.1 An Overview
This report pertains to Preliminary Environmental and Social Assessment (PESA) for the proposed Floating
Solar Photovoltaic Plant at Indravati Reservoir and associated facilities proposed in Kalahandi and
Nabarangpur Districts of Odisha state.
To ascertain the applicability of relevant national, state level legislations and IFC Performance
Standards from environmental and social safeguard point of view;
To understand the existing/baseline environmental and social elements of the proposed project site
and project influence area;
To map relevant stakeholders involved in the project and carryout primary consultation with these
identified stakeholders;
To identify the environmental and social impacts that may result due to the proposed project and
propose measures to avoid, mitigate and reduce these impacts;
To outline an environmental and social management plan for implementation and monitoring of
proposed mitigation measures in difference stages of the project;
To ensure the consideration of budgetary provisions for implementation of proposed mitigation
measures and continuous monitoring of environmental and social safeguard during project
implementation phase.
Desktop Research: Secondary literature review and review of project related documents/reports to
understand the project elements and current site condition;
Regulatory Review: Study of applicable regulatory norms pertaining to environmental and social
safeguard and establishment of regulatory framework;
Reconnaissance Survey: Preliminary survey by environmental and social specialists to record the
sensitivity of the site, to identify the hotspots (if any) and ground-truthing of secondary data
obtained through literature review;
Baseline Monitoring: To establish baseline condition site specific baseline environmental monitoring
(Ambient Air, Noise, Soil, Ground and Surface Water) has been carried out from suitable locations.
• Assembly point: The access to the water is required not only for construction, but also for operation
and maintenance. Each island is assembled on land and then pushed into the water and tugged by
boat. Thus, a sufficiently large access to the water is required to reduce time and costs and also to
provide a secured water access point, which can be used to perform O&M activities. This aspect is
key for floating PV projects. For very large utility scale floating solar PV plants the option to have
inverters floating is the only feasible option. It was considered thus assembly areas with at least
300m to allow for 2 islands to be assembled in parallel. It was also envisaged that this assembly
point would have at least 2 hoists and slides into the water that will be moored,
• Pooling area: this point does not need to be the same as the assembly point but needs to be located
in the vicinity of the body of water to allow for the AC cables to be pooled in a switching gear and
stepped up to the adequate level of transmission to connect to the nearest grid substation. These
areas pose some challenges to be found near to the body of water as they need to be flat and dry all
year.
• Transmission line: transmission line is required to connect to the nearest grid substation
• Floating PV site: this site is selected near to the pooling area and not dependent on the assembly
point, as boats will tug the islands to the desired place. The biggest concern is to have contiguous
areas of water that will not get islanded during dry season, avoiding high depths and is possible not
far from the margins of the water body.
There were 2 assembly points analyzed, which are included in the table below along with their coordinates.
Particulars Co-ordinates
Their locations are shown in the image below. The recommendation is for assembly point 2 as it is nearer to
the site (marked as proposed assembly below) and with a reasonable logistic access. However, the other
assembly points are validated technically and from the environmental and social perspective and may be
used.
A peer type is planned to provide support the assembly area and to make it convenient to the operation and
maintenance of the FPV plants. It is provided below a drawing with the proposed infrastructure.
• Control room
• 33/132 kV transformers.
The location of the recommended pooling area is shown in the image below and is located at around 900 m
from the floating PV site.
The project relevant/applicable national legislation have been identified based on the secondary research
and interactions with the relevant government authorities and stakeholders. The following sections discuss
the various regulatory requirements associated with the project. However, the same needs to be re-
established by Project Proponent prior to implementation of project during detailed Environmental and
Social Impact Assessment.
1 The applicability of various regulation needs to be reassessed prior to the commencement of the project and project
proponent need to secure required permits/clearances as applicable.
EU-India Clean Energy and Climate Partnership (CECP) Page 10
S. Law / Applicability Reason for Implementing /
Relevance
No Regulation / (Yes/No) Applicability/Non Responsible
Guidelines -Applicability Agency
Protection and
improvement of the
environment.
Establishes the
standards for emission
of noise in the Pollution
atmosphere. Control Board
(CPCB) and
It also set forth the State Pollution
provisions to Control Board
designate an area with (SPCB)
varying degrees of
protection such as
ecologically sensitive
zones/ eco-sensitive
zones.
2.
The EIA The EIA notification No The MoEFCC MoEFCC; State
Notification, 2006 and subsequent Office Environmental
2006 & amendments lists out Memorandum Impact
subsequent type of projects that dated; 13th May Assessment
amendments requires EIA and 2011 exempts Authority
Environmental solar power (SEIAA)
Clearance from project from
MoEF&CC or State EIA obtaining prior
Authority prior to Environmental
commencement of Clearance from
any developmental the regulatory
work or project authorities. But,
expansion. The under the
notification gives provision of
stage-wise guidance MoEF&CC office
for processing of memorandum
Environmental dated 30th June
Clearance. 2011, requisite
permission is
required to be
obtained from
competent
authority for
water and land
usage.
on land-based
management of
ground water
resources”.
abstraction
(With effect These guidelines Resources,
from 16.11.2015) specify the provisions Government of
& subsequent to be followed for Odisha (GoO)
amendments obtaining permission
towards abstraction
of ground water in
Notified/Non-Notified
areas.
Proposed TL is
passing through
Conservation and
the Reserved
Forest definition of forest
Forest (RF).
(Conservation) areas. Diversion of State Forest
Additionally,
7. Act, 1980 & forest land follows the Yes Department,
Revenue Forest
subsequent process as laid by the MoEFCC
land parcels are
amendments Forest conservation
also likely to be
Act.
diverted for the
project.
Coastal MoEFCC/
Regulatory Zone The project area Odisha Coastal
Notification, Protect and manage doesn’t fall under Zone
8. No
2019 & coastal areas the designated Management
subsequent coastal zone Authority
amendments (OCZMA)
10.
Notification of ESZs are of significant No The project area Forest
Eco Sensitive ecological importance, does not fall in Department,
Zones (ESZs) and to conserve and declared ESZ GoO and
protect the natural MoEFCC
resources and living
beings, several zones
are declared in the
country as eco
sensitive zones by
notifications.
around protected
areas (national park,
wildlife sanctuaries
etc.,) are also declared
as ESZ in this
notification.
Indian Wildlife
(Protection) Act,
The National
1972 amended
No protected Board for
1993 and Rules Protection of wildlife
area, Eco Wildlife
1995; Wildlife in sanctuaries and
11. No sensitive zone of (NBWL), State
(Protection) National
protected area in Board for
Amendment Park/protected area.
the project area Wildlife
Act, 2002 &
(SBWL), Odisha
subsequent
amendments
12.
The Odisha This Act provides for Yes The project site Directorate of
Cooperative the registration, falls within the Fisheries, GoO
Societies Act, operation and Indravati dam
1962 management of co- reservoir, which
operative societies in is used by
The Odisha Orissa. fishermen under
cooperative registered PFCS
Societies Rules, The registration of (Khambeshwari)
1965 Primary Fishermen for their fishing
Cooperative society activities.
(PFCS) is done as per
the provisions of this These PFCS
act. which are
registered under
Ancient
Monuments and
To protect and No notified Archaeological
Archaeological
conserve cultural and archaeological Survey of India,
14. sites & remain No
historical remains site in the vicinity State Dept. of
Act 1958 &
found. of project site Archaeology
subsequent
amendments
15.
The Motor Empowers State Yes All vehicles used State Motor
Vehicle Act. Transport Authority to for construction Vehicles
1988 & enforce standards for will need to Department
subsequent vehicular pollution. comply with the
amendments From August 1997 the provisions of this
"Pollution Under act.
Control Certificate is
issued to reduce
vehicular emissions
Public Liability
Protection to the
and Insurance Hazardous
general public from
17. Act,1991 & No materials not SPCB
accidents due to
subsequent likely to be used
hazardous materials
amendments
Protection to the
Hazardous and
general public against The hazardous
other Wastes Yes
improper handling waste generated
(Management &
and disposal of needs to be
Transboundary (Authorizati
18. hazardous wastes. disposed through SPCB
Movement) on under
authorized
Rules, 2016 & this act not
Authorization under vendor as per the
subsequent required)
the provisions of this CPCB guidelines
amendments
act.
Chemical
Accidents Handling of
(Emergency Protection against hazardous District & Local
Planning, chemical accident (flammable, toxic Crisis Group
19. Preparedness while handling any Yes and explosive) headed by the
and Response) hazardous chemicals chemicals during District
Rules, 1996 & resulting construction and Magistrate
subsequent operation
amendments
Employing Labour /
workers
Employment of
The Building & The provisions in this labours
Other act are to ensure
Construction The provision of
safety, health and
Workers this act will be
welfare of Ministry of
(Regulation of applicable during
construction workers. Labour and
Employment & the construction
These acts specify the Employment
21. Conditions of Yes and operation
requirement of
Service) BOCW phase and are to
provisions such as District Labour
Act, 1996 & be followed by
wage payments, basic Commissioner
subsequent contractor &
sanitation, drinking
amendments developer of the
water, first aid,
project.
canteens and
temporary living
quarters within or
near the work site.
24.
The Scheduled The Act grants legal Yes The FSPV location Ministry of
Tribes and Other recognition to the falls within Tribal Affairs
Traditional rights of traditional Thuamul Rampur Tribal Welfare
Forest Dwellers forest dwelling block of the
4 https://pib.gov.in/Pressreleaseshare.aspx?PRID=1579747
EU-India Clean Energy and Climate Partnership (CECP) Page 19
S. Law / Applicability Reason for Implementing /
Relevance
No Regulation / (Yes/No) Applicability/Non Responsible
Guidelines -Applicability Agency
adversely affects
the wild animals,
forest and the
biodiversity are
complied with.
The act gives powers
to the Panchayats in
case there is any
grievance arises by
the project. There is Gram Sabha/
Provision for The proposed Panchayat/Loca
The Panchayati application of consent project falls l administration
26. Raj Act 1994 and from the respective Yes under (Tahasil
its amendments. panchayat village/panchayat Office/District
body/village jurisdiction. Administrative
administrative officer office)
etc., for project
development and
during the project
lifecycle
27.
Panchayats Under section 4(d) of Yes The proposed Gram Sabha/
(Extension to Panchayats (Extension project locations Panchayat/Loca
the Scheduled to the Scheduled have significant l administration
Areas) Act, 1996 Areas) Act, 1996. scheduled tribe (Tahasil
& subsequent "every Gram Sabha population. Office/District
amendments shall be competent to Administrative
safeguard and office)
preserve the
traditions and
customs of the
people, their cultural
identity, community
resources and the
customary mode of
dispute resolution.
To be read in
conjunction with the
above S. No.23 – 26
acts.
29.
The Contract The Act provides for Yes Applicable to all Labour Welfare
Labour certain welfare construction Board, GoO
(Regulation and measures to be works.
Abolition) Rules, provided by the Chief Labour
1971 Contractor to contract The act Commissioner,
labour and in case the mandated the GoO
Contract Labour Contractor fails to requirement to
(Regulation and provide, the same are obtain a
Abolition), 1973 required to be Certificate of
Registration as
provided by the
Principal Employer by
Law. The principal
employer is required
to take Certificate of
Registration and the
Contractor is required the principal
& subsequent to take a License from employer.
amendments the designated
Officer. The Act is
applicable to the
establishments or
Contractor of principal
employer if they
employ 20 or more
contract labour
30.
Minimum Wages This Act provide for Yes The provision of Labour Welfare
Act, 1948 fixing minimum rates this act will be Board, GoO
of wages in certain applicable during
& subsequent employments and the construction
amendments requires the employer and operation
to provide to every phase and are to
worker engaged in a be followed by
scheduled contractor &
employment to be developer of the
paid wages at a rate project.
not less than the
minimum rate of
wages fixed by such
notification for that
class of employees in
that employment
without any
deductions except as
may be authorized
within such time and
subject to such
conditions as may be
prescribed.
32.
Inter-state The objective of the Yes The ISMW is Labour
Migrant act is to regulate the applicable if the Department,
Workers (ISMW) employment of inter- project deploys GoO
Act, 1979 & State migrant labours from
subsequent workmen and to outside of Odisha
amendments provide for their state during
conditions of service construction
and for matters phase.
connected therewith.
Every establishment
that is recruiting
interstate migrant
workmen will be
required to be
registered with
registering officers
and every contractor
who employ interstate
migrant workmen
need to obtain a
licence from the
specified authority
both of the State i.e.
home state (from
where belongs) and
the host state (where
to be employed).
To ensure that the project design and implementation take the IFC Performance Standards (IFCPS) (2012) as
a benchmark, the relevant performance standards that are potentially applicable for development of the
proposed project are discussed below:
Performance Safeguard
Objective Likely Applicability
Standard (PS) Documents/Compliances
PS 1: PS1 emphasizes on the The proposed FSPV project (a) Conducting environmental
Assessment importance of will have environmental and and social assessment
and managing social risks/impacts
Management environmental and associated with the project (b) Establish and maintain an
of social performance such as impact on livelihood ESMS. The ESMS should
Environmental throughout the life of of fishermen, noise include policy statement,
and Social a project. It also instils generation during identification of risks and
Risks and the need for a robust impacts, management and
mitigation programs,
organizational capacity and
competency, and emergency
construction activities etc. management plants and
ESMS establishment procedure.
Impacts
for the client. Thus, PS 1 is applicable to the
project. (c) E&S Audit/Due Diligence
Including development of
corrective action plan, costs,
and schedule.
PS 4: PS4 addresses the This PS addresses potential (a) Evaluate and assess the
Community client’s responsibility risks and impacts to the risks and impacts to the health
Health, Safety to avoid or minimize affected communities, and safety of the affected
and Security the risks and impacts properties, and structures communities during the
to community health, throughout the project life project life cycle.
safety, and security cycle.
that may arise from (b) Proposing mitigation
project related The proposed FSPV project measures in line with
activities, with requires transportation of preventive and control
particular attention to material to the assembly measures, GIIPs, WB EHS
vulnerable groups. points and also involves Guidelines and national
movement of construction regulatory norms.
machinery which may pose
safety and security risks to (c) Developing an Action Plan
the nearby residents/ for disclosure to project
communities. affected communities via
community consultations.
The project also envisages
labor influx during the
PS 7: PS7 recognizes that The Performance Standard is (a) Ensure the timely and
Indigenous Indigenous Peoples, as applicable to groups and/or equitable delivery of agreed
Peoples social groups with communities of Indigenous measures to the Affected
identities that are Peoples who, by virtue of Communities of Indigenous
distinct from their economic, social, and Peoples as per the mitigation
mainstream groups in legal status and/or their hierarchy in ESMS
national societies, are institutions, custom, culture
often among the most and/or language may be (b) Preparation of community
marginalized and characterized as distinct development plan with
vulnerable segments from mainstream society and separate components for
of the population. PS7 who may be disadvantaged Indigenous Peoples.
requires avoidance of in the development process
(c) Preparation of an
adverse impacts of as a result of their identity.
Indigenous Peoples Plan (IPP)
projects on Indigenous
The proposed FSPV is located outlining the actions to
Peoples, or when
adjacent to the villages of minimize and/or compensate
avoidance is not
Talnagi and Murka – falling for adverse impacts in a
possible, to minimize,
within the administrative culturally appropriate manner
mitigate and/or
jurisdiction of Thuamul and as per the requirements of
compensate for such
Rampur block of the IFC PS and national legal
impacts
Kalahandi district. This entire requirements.
block falls under Schedule V
(d) Ensuring participation of IP
area.
in consultation process,
The immediate vicinity of the information disclosure, and
project (Talnagi and Murka providing sufficient time for
villages) and the villages Indigenous People decision-
through which the making processes.
transmission line passes are
(e) Obtain the FPIC from the
predominantly tribal
affected communities of
(Schedule Tribes) in
indigenous peoples during
population.
project design, and
Any negative or positive implementation phase.
impact of the project will be
felt by these tribal
communities; thus, PS 7 is
EU-India Clean Energy and Climate Partnership (CECP) Page 30
Performance Safeguard
Objective Likely Applicability
Standard (PS) Documents/Compliances
4.1 Introduction
This chapter describes the existing environmental and social settings of the project area and its immediate
surroundings. This includes physical environment (comprising air, water and noise components etc.),
biological environment and socio-economic environment.
8 Air, Noise, Soil and Water Quality Onsite monitoring and analysis of field samples
The district Kalahandi comprises diverse landforms consisting of rugged hill ranges, plateaus, undulating
plains dotted with residual hills and mounds and fertile erosional plains and valleys. A gently undulating
terrain with a vast stretch of cultivable land characterizes the major parts west of Bhawanipatna in the
district. The elevation of the hills located in the southeastern and southern parts ranges from 953 to 1229 m
above mean sea level. In Arupani – Koksara – Junagarh tract the elevation of land surface varies from 220 m
to 325 m above MSL. In Bhawanipatna – Utkela – Kesinga tract the elevation of land surface ranges from 186
m to 350 m above MSL. In the undulating plains the general topographic slope is towards northeast. The
proposed project is located towards South-Western side of Kalahandi District where the elevation is ~700m
above mean sea level. Whereas, in case of Nabarangpur, the proposed project area lies in the plain of
Indravati basin.
4.4.2 Climatology
The climate of the Kalahandi District is of extreme type. It is dry except during monsoon. The maximum
temperature of the District is 45+ degree Celsius, whereas the minimum temperature recorded is 4 degree
Celsius. The District experiences the average annual rainfall as 1378.20 mm 5. The summer season extends
from March to middle of June followed by the rainy season from June to September. The winter season
extends from November till the end of February. Humidity is high during middle of June and it’s less in post-
monsoon period. The average relative humidity in the district varies from 27% to 80% throughout the year.
The mean monthly potential evapo-transpiration value ranges from 45mm in December to 470 mm in May.
Wind is generally light to moderate. During summer and Southwest monsoon months wind velocity
increases. The mean annual wind speed is 3.0 km/hr. record of Last 5 years rainfall furnished in the below
table.
Table 4: Monthly Arithmetic Average Rainfall statistics (in mm) for Kalahandi district 6
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2016 0 0.9 14 1 21.8 119.2 361.8 299 324.7 132 0 0
2017 0 0 22 2.1 21.2 191.4 466.7 349.6 184.3 119.6 1 0
2018 0 0 0 13.9 32.1 91.7 612.9 782.9 199.4 63.9 0 84.2
2019 1.1 6.5 9.7 7.2 28.4 129.5 372.4 589.6 274.2 99 4.3 0
2020 7.6 24.5 65.8 38 45.3 290.3 258.5 350.4 195.6 133.2 0.3 0
As per the district wise multi-hazard mapping done by Odisha State Disaster Management Authority
(OSDMA), proposed project area (in Nabarangpur and Kalahandi districts) fall under Wind and Cyclone
Moderate Damage Risk Zone B (39m/s). The project area falls under No Flood Zone. Further, the district falls
under Earthquake Low Damage Risk Zone II.
The proposed Floating Solar Photovoltaic Plant is proposed on waterbody i.e. Indravati reservoir. The land
use type for the associated facilities like Pooling Station and Assembly Area is
Barren/unculturable/Wasteland, Scrubland in nature. However, in the proposed pooling station area some
agricultural activities (mainly monsoon dependent) are noticed. The proposed transmission line passes
through Barren/unculturable/Wasteland, Scrubland, Agriculture-Cropland, Rural Built-up areas. The line
crosses Reserve Forest at 2 locations.
7 Bhuvan-NRSC
EU-India Clean Energy and Climate Partnership (CECP) Page 36
Source: Bhuvan
Figure 7: Land use Map of the Project Area
The Indravati River is the most important river system and source of water in the project area. The Indravati
emerges from the mountain range of Thuamul Rampur of the Kalahandi district. It consists of three
perennial water streams and flows down from north to south ward covering Kalahandi, Nabarangpur and
Chattishgarh and merges in the Godavari River. Due to the construction of Indravati Dam, the flow of water
quantity through the Indravati is substantially decreased 8.
Source: NIC
Figure 8: Drainage Map
Soil types of the Kalahandi district may be classified into 5 groups namely Inceptisols, Alfisols, Vertisols,
Histosols and Entisols. Inceptisols are the Red soils are the most predominant soil type in Kalahandi district
covering about 45 % of the total area. These soils occur in foothills terrain and as capping over the hillocks.
These soils are poor in nitrogen, phosphate, potassium and organic matters. These soils are light textured
and the pH ranges from 4.5 to 6.0. The soil type of proposed project area is of this kind.
Soil samples were collected by NABL accredited laboratory in the month of April/May-2022 to assess the
existing soil conditions of the project area. 4 soil samples were drawn from the project surrounding area
towards conducting the assessment of soil quality. The samples were collected from a depth of 6-12 inches.
The sealed samples were sent to laboratory for further analysis. The method of analysis and characteristic of
the soil samples collected from 4 different locations are furnished in Table below, whereas the sampling
location map and photographs are provided in Annexure 1.
Results
Location-3 Location-4
Sl. Location-1 Location-2
Parameter Method of Analysis (Paraja (Gaura
No. (Nagi): (Khatiguda):
Deopali): Deopali):
19°16'12.67"N, 19°14'15.86"N,
19°16'44.77"N, 19°15'56.95"N,
82°50'9.06"E 82°47'9.98"E
82°49'4.23"E 82°48'43.96"E
IS 2720 (Part 26):
1. pH at 25 °C 6.75 7.48 7.31 7.08
1987(RA 2011)
Electrical
IS 14767 :2000, RA
2. Conductivity, 3160 3040 4260 3340
2016
µS / cm at 25 °C
Moisture IS: 2720 (Part 2)
3. 1.1 3.4 2.8 3.1
Content, % 1973 RA 2015
The proposed FSPV site, ancillary facilities as well as Transmission line is proposed in very sparsely populated
area. No such industrial activity or pollution generating source identified from the project area. As per the
stakeholder consultation, the ambient air and noise quality is quite satisfactory. To assess Ambient Air
Quality and Nosie Level, primary study was also carried out. The details are provided in the subsequent
sections.
To assess Ambient air quality of the project area, baseline samples were collected by NABL accredited
laboratory in the month of April/May-2022 from 2 different locations of the project surrounding area. From
each location, 2 samples were drawn. Monitoring was conducted for the parameters like Particulate Matters
(PM10 & PM2.5), Sulphur Dioxide (SO2), Nitrogen Dioxide (NO2) and Carbon monoxide (CO). During the
sampling it was ensured that the equipment was placed at a height of at least 3 to 4m above the ground
level at each monitoring station, for negating the effects of windblown ground dust. The equipment was
placed at open space free from trees and vegetation which would otherwise act as a sink for pollutants
resulting in lower levels in monitoring results. The monitoring was carried out as per the latest CPCB and
MoEF&CC guidelines. The analysis technique adopted for the study of various parameters and results are
furnished in following table, whereas the sampling location map and photographs are provided in Annexure
1.
Results
USEPA CFR-40,
PM2.5(µg/m3) 41 46 38 33 60 Part-50, Appendix-
L
CO (µg /m3) 572 686 629 572 2000 IS: 5182 (Part-10):
1999, RA-2014
Source: Primary Monitoring
The analysis results revealed that all the pollutant parameters measured were well below the national
Ambient Air Quality Standards as stipulated by CPCB for all the locations.
To assess Ambient Nosie Level of the project area, baseline samples were collected by NABL accredited
laboratory in the month of April/May-2022 from 4 different locations of the project surrounding area.
Automatic sound level meter (SLM 100) was used for measuring the noise levels. The noise level was
recorded continuous for 24 hours at an interval of 1 hour. The monitoring results are furnished in following
table, whereas the sampling location map and photographs are provided in Annexure 1.
Nagi:
30.04.2022-
19° 16' 8.3568" N,82° 50' Residential 52.6 55 43.3 45
01.05.2022
20.1438"E
Near Khatiguda:
30.04.2022-
19° 14' 18.3258" N,82° 47' Residential 46.4 55 37.5 45
01.05.2022
24.7128"E
Indravati River and Indravati Reservoir are identified as key surface water resource from the project area. It
is expected that the water requirement during construction and operation phase shall be catered from
Indravati Reservoir. The Indravati dam and reservoir was developed in nineties on Indravati River and its
tributaries. Beside catering the requirement for Upper Indravati Hydroelectric Project, the reservoir is
currently being used as medium for transportation by the local populace of surrounding villages and as a
source of fishing activity to some moderate extent. However, fishing is restricted within monsoon period
only. The wetland map of Kalahandi and Nabarangpur district is provided below.
4 samples were drawn from the Indravati Reservoir (from the closer proximity of proposed FSPV site) to
assess baseline Surface Water quality of the project area. The samples were collected by NABL accredited
laboratory in the month of April/May-2022. Water sampling was done by following standard CPCB guidelines
for physical, chemical and bacteriological parameters. Analysis of the surface water samples were carried
out as per established standard methods and procedures prescribed by CPCB, IS 3025 Codes and APHA 23rd
Edition, 2017. The analysed results are furnished in following table, whereas the sampling location map and
photographs are provided in Annexure 1.
Result
Location 1: Location 2: Location 3: Location 4: Class B
Sl. 19°16'1.81"N, 19°13'47.23"N, 19°16'39.30"N, 19°15'49.23"N, Standards: as
Parameters
No. 82°50'26.59"E 82°48'49.68"E 82°49'15.02"E 82°51'0.03"E per IS
Type: Indravati Type: Indravati Type: Indravati Type: Indravati 2296:1982
Reservoir Reservoir Reservoir Reservoir
Physicochemical Parameters
The analysed results were compared with Class B Standards: as per IS 2296:1982 i.e., Outdoor bathing. Most
of the parameters are found well within the standard. However, it was noticed that DO value is marginally
low at Location 1 and BOD is higher than stipulated standard in Location 1 and 3.
As per CGWB report The Annual replenishable ground water resources in the district are computed as
74911 Ham, out of which the existing Ground Water Draft for irrigation is 9618 Ham. The ground water
draft for irrigation is through dug wells and tube wells. A large number of hand pumps fitted bore wells
and tube wells also cater to the rural and urban water supply needs. So far ground water development
in the district has been meager, and all the blocks fall under the safe category. The stage of ground
water development varies from 9.53 % (Th. Rampur) to 29.64% (Narla). The overall Stage of
Groundwater development of the district is 18.49 %. The proposed FSPV Plant and ancillary facilities are
located in Th. Rampur block. As per CGWB report, the water level in the district remains within 2-4mbgl
in pre-monsoon and 0-2mbgl in post-monsoon. Nabarangpur District is also does not have any Over
Exploited/Critical/Notified block
4 ground water samples were drawn from the vicinity of proposed project area to assess baseline Ground
Water quality of the area. The samples were collected by NABL accredited laboratory in the month of
April/May-2022. Samples for chemical analysis were collected in polyethylene carboys. Samples collected for
metal content were acidified with 1 ml HNO3. Parameters like dissolved oxygen (DO) and pH were analysed
at the time of sample collection. The basic precautions were taken care to avoid any contamination during
the sampling. Analyses of the water samples were carried out as per established standard methods and
procedures prescribed by CPCB, IS 3025 Codes and APHA 23rd edition, 2017. The analysed results are
furnished in following table, whereas the sampling location map and photographs are provided in Annexure
1.
Result IS 10500:2012
Location: Location: Paraja Location: Guru
Location: Nagi;
Khatiguda; Deopali; Deopali;
Sl. 19°16'12.67"N,
Parameters 19°14'15.85"N, 19°16'45.08"N, 19°15'56.95"N, Desirable Permissible
No. 82°50'9.06"E
82°47'10.00"E 82°49'4.31"E 82°48'43.96"E Limit Limit
Type: Type: Type: Type:
Handpump Handpump Handpump Handpump
Physicochemical Parameters
pH Value at No
1. 7.06 7.78 7.20 6.87 6.5-8.5
25C Relaxation
2. Temperature 27.3 28.2 27.8 28.1 --- ---
Turbidity in
3. <1.0 <1.0 <1.0 <1.0 1 5
NTU
Electrical
Conductivity
4. 151 382 279 346 --- ---
in µS /cm at 25
0
C
5. Total 86 228 170 208 500 2000
The analysed results were compared with IS 10500:2012 i.e., National Drinking Quality Standard. All the
parameters tested are found well within the desirable limit of IS 10500:2012.
There is no protected (under Wildlife Act. 1972) area located in the vicinity of proposed FSPV site and
ancillary facilities. Karlapat Wildlife Sanctuary, the nearest Protected Area from the proposed project area is
located at about 42 Km distance towards North-Eastern direction. The Index Map for Protected Areas of
Odisha State and nearest protected area from proposed site is presented in below figure.
4.5.2 Forest
According to State of Forest Report, 2021 by FSI the forest cover in Odisha state is 52155.95 km 2 constituting
33.50% of its total geographical area. Below table and figure presents the comparative details of forest cover
of project districts and Odisha State and forest map of state respectively.
The proposed project site is falling within the administrative jurisdiction of South Kalahandi and
Nabarangpur Forest Division. Proposed alignment of Transmission Line is crossing Reserve Forest (RF)
Patches in the following locations.
Table 11: Reserve Forest Area Crossed by the Proposed Transmission Line
Addition to the abovementioned RF patches, as informed by concerned stakeholders the proposed project
(including FSPV site ancillary facility and Transmission Line), is located on revenue forest patches at multiple
locations. Pertinent to state that, the acquisition of such revenue forest patch will also be attracting Forest
Clearance.
The proposed project site is in Indravati Reservoir, a lentic aquatic ecosystem as well as in the areas having
terrestrial ecosystem like Reserve Forest, open mixed jungle, open scrub jungle, agricultural field,
plantation, orchards, minor settlements.
As stated by concerned forest department, general characteristics of vegetation in the project area region is
tropophilous i.e. the forest mostly belongs to tropical both dry and moist types. It ranges from tropical
evergreen forest to dry deciduous scrubs. There is no rain forest. The predominant tree species of the forest
areas in the project area region are Shorea robusta (Sal). The summer makes the forest leaf less, but the
greenery is restored in the monsoon. The other tree species found in the area are planted Teak (Tectona
grandis), Bija (Pterocarpus marsupium), Sahaja (Terminalia tomentosa), Dhaura (Annogeissus latifolia), Arjuna
(Terminalia arjuna), Salai (Boswellia serrata), Moi (Lannea coromandelica), Mahula (Madhuca latifolia), Kendu
(Diospyros melanoxylon), Chara (Buchanania lanzan), Karda (Clestanthus collinus), Bhalia (Semicarpus
anacardium), Kasi (Bridelia retusa) etc.
The list of key fish species reported from Indravati Reservoir are furnished below
Other than domesticated mammals, the key species recorded from the project area are listed below
The detailed checklist of flora and fauna recorded by Kalahandi South Forest Department is furnished in
Annexure – 2.
To understand species richness, the Phytoplankton, Zooplankton and Benthos Samples were drawn from 4
different locations of Indravati Reservoir. The analysed results are furnished in following table, whereas the
sampling locations and location wise findings are provided in Annexure 1.
Phyto Plankton
Euglena sp.
Cladophora sp.
Chlorella sp.
1. Chlorophyta Spirogyra sp.
Spirulina sp.
Ulothrix sp.
Closterium sp.
Navicula sp.
2. Bacillariophyta
Pinnularia sp.
Anbaena sp.
Oscilatoria sp.
3. Cyanophyta
Nostoc sp.
Microcystis sp.
Zoo Plankton
Amoeba sp.
Euglypha sp.
Arcella sp.
1. Protozoa
Paramoecium sp.
Opercularia sp.
Metopus sp.
Polyarthra sp.
2. Rotifera Trichocera sp.
Monostyla sp.
Moina sp.
Ceriodaphnia sp.
3. Cladocera
Bosmina sp.
Daphnia sp.
Cyclops sp.
4. Copepoda Nauplii sp.
Mesocyclops sp.
Benthos
Polydora sp.
1. Annelida Hirudo sp.
Nereis sp.
Amphibalanus sp.
Amphiops sp.
Ranatra sp.
2. Arthropoda Squilla sp.
Panulirus sp.
Panopeus sp.
Charybdis sp.
Mollusca Corbicula sp.
3. Umbonium sp.
Natica sp.
To summarize, the FSPV location itself lies in the Kalahandi district and the transmission line will cover two
districts – Kalahandi and Nabarangpur. The floating solar PV panels will be situated on the reservoir and will
not require any land. However, the pooling stations and the assembly points will require small parcels of
land, which are located in the village Nagi (or Talnagi, as referred to locally).
The socio-economic baseline has been gathered from secondary and as well as primary sources. The
secondary sources include the state and district census data, district handbooks, and other published
information. The primary data includes site survey and consultations conducted amongst with the district
and block level authorities, as well as consultations with the communities in the project area, i.e. in the
village of Talnagi in Thuamul Rampur block (Kalahandi district). The site survey and consultations were
conducted to get a more site-specific picture of the project site and surrounding area and the potential
impacts of the project on the surroundings.
Note: The socio-economic baseline is limited to the villages impacted by the project directly (by virtue of it
physically being located in their vicinity) and to a district overview to give an idea of the population profile in
general. Due to the nature of the project – its limited use of construction activities, non-intensive in terms of
labour, no large land requirement causing largescale displacement (physical or economic), and the limited
impact on site surroundings – the impacts of the social environment is expected to be limited to only the
direct impact zone (immediate vicinity) of the project and any long-term, high-magnitude adverse impacts
on the social environment are not envisaged.
The literacy rate of the two districts is lower than that of the state of Odisha (72.9%) and for both districts
women form a major portion of marginal and non-worker categories.
Particulars Nabarangpur District (TL passing through) Kalahandi District (Location of FSPV)
Population
Male Female Total Male Female Total
profile
Urban
44,041 43,584 7.18% 62,455 59,532 7.7%
population
Population
- - 19.03% - - 18.07%
Growth Rate %
Childs
104.077 103,834 207,911 113,726 108,844 222,570
Population (0-6)
681,173 449,456
Economic
Male Female Total Male Female Total
activities
Main Workers 227,544 51,571 279,115 (45.7%) 299,835 76,922 376,757 (50.1%)
Marginal 216,694
331,791 115,097 147,455 227,718 (49.9%) 375,173
Workers (54,3%)
Category of
Male Female Total Male Female Total
workers
Agriculture
72,307 49,029 23,278 100,376 43,497 143,873
Labor
4.6.2 Social baseline: Village/s in the Direct Impact Zone of the FSPV
The Two Villages where the FSPV and associated infrastructure (pooling station ad assembly point) are
located have been described below. These two villages fall under the administrative jurisdiction of the
Thuamul Rampur Block of Kalahandi district. The village level profiles are provided to give a baseline of the
constitution of population especially presence of tribal/indigenous groups, their livelihood activities and
economic reliance on their surroundings.
1. Nagi/Talnagi village: The FSPV location on the reservoir is adjacent to the village of Talnagi. The
assembly point and the pooling stations are all proposed to be located within the Talnagi village
boundary. Apart from the statistical data taken from the 2011 census, qualitative data presented below
has been surmised from consultations at the community and institutional levels.
Demographic details:
Population: According to the 2011 census data, the total geographical area of the village is 684 hectares.
Nagi has a total population of 477 peoples, out of which male population is 241 while female population
is 236. There are about 136 houses in Nagi village. In consultations with the community, it was
understood that there are currently about 200 households in the village, including the hamlet of
Luthgudi, which has about 21 households. The people residing in the hamlet of Luthgudi do not own
these lands but rather have been using them for cultivation, subsistence farming and residence for more
than 30 years. The hamlet is closer to Pooling station options 1 and 2 and right beside the land parcel
identified for the Pooling Station 1.
Schedule Tribes: The census 2011 mentions that 41.72% of the population is identified as scheduled tribes
in the village. However, in consultations with the community and the Revenue Inspector (Mohul-Patna),
it was apprised that majority (almost 70%) of the village population was composed of Schedule tribes
and the rest are mostly Scheduled castes. As informed by the Revenue Inspector and by the District
Welfare Officer (DWO), most of the tribes belong to communities identified as ‘Jharia Parja’ and some
minor population of ‘Majhi’ tribe. The Thuamul Rampur block falls under designated Schedule 5 area as
per consultations with the District Welfare Officer (DWO). Therefore, the villages of Talnagi and Murka
too fall under such areas as they fall under the TH Rampur block.
Work profile: As per census 2011, 214 were engaged in work activities in the village of Nagi. 48.13 % of
workers describe their work as Main Work (Employment or Earning more than 6 Months) while 51.87 %
were involved in Marginal activity providing livelihood for less than 6 months. Of 214 workers engaged in
Main Work, 42 were cultivators (owner or co-owner) while 27 were Agricultural labourer.
Economic Activities:
Agricultural cultivation: During consultations it was surmised that the major activity conducted
within the village was that of cultivation. The produce however is not enough for substantial
income but rather for subsistence. Women too are majorly involved in agricultural activities.
Land Requirement for the proposed project: The solar PV panels will be floated onto the water in the
reservoir, covering roughly 200 Hectares of water area. The PV panels will not require any land for
operation. Small parcels of land will be required for the assembly points and the pooling stations (details
given below), and all of these are located in the village Talnagi.
EU-India Clean Energy and Climate Partnership (CECP) Page 59
As informed by the Revenue Inspector who accompanied the E&S team in the site visit, most of the lands
around the river and majority of the lands of the Talnagi village have been acquired by the Upper Indravati
Hydroelectric Power Project (Dam authority as referred to locally) during the construction of the dam. The
village was supposed to be flooded during the dam construction, but portion of the village managed to
remain above water and evacuated people and tribes resettled on these lands without any formal
ownership.
Pooling station 1: Located near/in Luthgudi hamlet. The amount of land required for the pooling
station is approximately 2.46 acres. The land parcel is currently being used for agricultural use by the
inhabitants of the Luthgudi hamlet. The crops grown are mostly maize for self-consumption as well
as selling in the Nabarangpur mandi market. In most likelihood, the land parcel belongs to the Upper
Indravati Hydroelectric Power Project, however land records need to be verified and land ownership
needs to be confirmed prior to project initiation. Using this land for construction of the pooling
station would trigger IFC PS 5: Land acquisition and Involuntary Resettlement as it will restrict land
use for the inhabitants of the Hamlet and may also lead to loss of livelihood as the land is used for
cultivation.
Pooling Station 2: The amount of land required is approximately 1.67 acres. This land is situated in
close proximity to the docking area for boats used by the local people for travelling across the reservoir
to villages on the other sides. There was a docket boat noted at the site (pictures below).
Assembly Point 1: The amount of land required is approximately ~4,5 acres. The land is located very
close to the reservoir boundary and as per the locals, is subsumed under water during the monsoons
and when the reservoir is full (Picture below):
Assembly Point 2: This assembly point could not visited due to lack of access. The amount of land
required for this is approximately ~4,5 acres. According to the locals, the land is covered with shrubs and
is not used for any purpose. There are no pictures for this assembly point.
2. Murka Village: The floating PV panels will lie adjacent to the boundaries of the village of Murka.
However, none of the associated structures fall within this village. The E&S team was unable to
access the FSPV site adjacent to the village of Murka. The villagers of Nagi and Murka often carryout
activities like fishing and selling agricultural produce to markets together.
Demographic Details:
Murka is a medium size village located in Thuamul Rampur Block of Kalahandi district, Orissa with total
132 families residing. The Murka village has population of 423 of which 200 are males while 223 are
females as per Population Census 2011.
In Murka village population of children with age 0-6 is 62 which makes up 14.66 % of total population
of village. Average Sex Ratio of Murka village is 1115 which is higher than Orissa state average of 979.
Child Sex Ratio for the Murka as per census is 824, lower than Orissa average of 941.
Murka village has lower literacy rate compared to Orissa. In 2011, literacy rate of Murka village was
44.32 % compared to 72.87 % of Orissa. In Murka Male literacy stands at 63.86 % while female literacy rate
was 27.69 %.
Scheduled Tribes: Most of the village population is from Schedule Tribes (ST), which constitutes 67.38 %
while Schedule Caste (SC) were 18.91 % of total population in Murka village. As mentioned above, the
village of Murka falls within designated Schedule 5 area as it is within the administrative jurisdiction of
the Thuamul Rampur block.
Work Profile: According to the 2011 census record, 237 people were engaged in work activities in the
Murka. 48.95 % of workers describe their work as Main Work (Employment or Earning more than 6
Months) while 51.05 % were involved in Marginal activity providing livelihood for less than 6 months. Of
237 workers engaged in Main Work, 2 were cultivators (owner or co-owner) while 105 were Agricultural
labourer.
Economic Activities:
EU-India Clean Energy and Climate Partnership (CECP) Page 61
The economic activities of Murka are similar to that of the residents of Nagi. Murka has about 6-8
Chuppus (small boats/dinghys used for fishing) which are also used by the residents of Nagi village.
Cultivation and faming activities are conducted and the produce is either sold locally, in Khatiguda or
at the Nabarangpur Mandi depending on the quantum of produce.
Administration: The village Nagi falls under the Talnagi Gram Panchayat, in Thumul Rampur block –
Kalahandi district of Odisha. The district headquarters are situated in Bhawanipatna.
There are approximately 18 villages/ hamlets/Settlement falling within the transmission line route,
originating at Talnagi pooling station and ending at the existing 122kV Tentulikhunti substation in
Nabarangpur. The TL is passing through the tribal areas of the district of Nabarangpur and will past through
forest lands (both reserve and revenue), government lands and private lands. Apart from forest clearances,
NOCs will also have to be taken from the village level panchayats and gram Panchayats through a
consultative process.
As per GoI rules and regulations, lands below the transmission towers are not acquired but there are
impacts in terms of temporary restriction in land use. Potentially affected people (APs) are provided
compensation for any damages caused during the construction or any loss faced due to the temporary
restriction in land use (compensation for crops and plantations). As TLs are linear projects, last minute
changes in alignment are made to account for any APs are not agreeable to the line passing over their
property.
The FSPV and its associated infrastructure are located in the districts of Nabarangpur and Kalahandi.
According to the 2011 census, 59 percent of Nabarangpur’s and 29 percent of Kalahandi’s population is
characterized as belonging to Schedule tribes. Consultation with the ITDA and DWO yielded that the tribes
EU-India Clean Energy and Climate Partnership (CECP) Page 62
present in the project area include Bhattoda (in majority), Kandha Gouda, Jharia Parjas (also known as
Paroja, Jodia Paroja, Konda Paroja, etc), Gond (in some pockets through which the TL is passing), Kharia,
and to a lesser extent, Santhal.
The immediate vicinity of the FSPV location – villages of Talnagi and Murka – in the Thuamul Rampur block
of Kalahandi district contain tribal settlements majorly from the Jharia Parjas (Jodia Parojas) and to some
extent from the Kandha tribes. The Kandha tribes are further categorized as those living on hill tops –
Dangoria Kandha – and those living at the foothills – Kutiya Kandha. These two subsections of the Kandha
tribes are also listed as PVGTs. They speak languages known as Kuvi, Kandha, Paroja, however most also
have functional knowledge of desi Odia which is used for markets and dealings for economic activities. The
tribal inhabitants of the project area mostly rely on farming, forest foraging and relying on their natural
surroundings for their subsistence. The level of literacy is lower than that of the state as a whole.
Mondei is a local festival being widely celebrated in the Nabarangpur District. The word Mondei is derived
from the Hindi word ‘Mondi’ which means a small market. This festival is celebrated by large number of
people worshipping a common deity among pre- historic rituals. Fair and entertainment activities with folk
dances and tribal opera can be seen for the whole night in the festival. Mondei is usually celebrated after
harvesting of crops. The festival is observed at different popular locations throughout the District gathering
men and women of the area and far off.
Kalahandi District is famous for its unique wood craft which is made by highly skilled artisans of Khairpadar,
Dharmagarh, Rengalpalli, Jaipatna and Bhawanipatna. Teak wood is the basic raw material and products like
statue of Sri Ganesh, Laxmi, Rhinoceros, Bull fighting, Elephant and tribal arts, utility items etc. can be
customized in respect of shape, size and design as per requirement. Part from this, there is terracotta
figurines that are made as part as one of the oldest crafts in the area. Bamboo craft is carried out by artisans
particularly form the area of Narla and Karlapat forest areas.
Due to the large number of tribals residing in both districts, there are multiple dance forms and cultural
festivities in the area. Kalahandi itself has over 18 distinct art forms (dance, music) like the Ghumara dance
that takes place during Dusshehra, Singha Baja wherein specially trained musicians perform, Madli – a dance
form of the Gond tribe and many others.
5.1 Introduction
This section provides the stakeholder identification and analysis as well as a brief understanding of the
engagement process for the project. “Stakeholder” refers to those who have plausible stake in the
environmental/social impacts of the project or activity are ascertained with a view to taking into account all
the material concerns in the project or activity design as appropriate. It is highly desirable for all key
stakeholders to arrive at a consensus on sensitive features, impacts and remedial actions. Stakeholder
identification was done by examining the potential impacts of the project in terms of:
5.2 Objective
The main objective of the consultation process is to minimize negative impacts of the project and to
maximize the benefits from the project to the local populace. The objectives of stakeholders’ consultation
as part of this project are:
Promote public awareness and improve understanding of the potential impacts of proposed projects
Identify alternative sites or designs, and mitigation measures
Solicit the views of affected communities / individuals on environmental and social problems
Improve environmental and social soundness
Clarify values and trade-offs associated with the different alternatives
Identify contentious local issues which might jeopardise the implementation of the project
Establish transparent procedures for carrying out proposed works
Inform the affected populace about the entitlement framework and to settle problems with mutual
consent
Create accountability and sense of local ownership during project implementation; and
To obtain information on baseline environment.
Mrs. Prashanti
02-May-22 Department of Fishery Assistant Fishery Officer
Kalahandi
Points of Discussion:
Information about the type of fish species found in the Indravati Reservoir
Information about livelihood, dependency on fishing
Details about fishermen community registered in the project area
Department of Water Resource Mr. Ujjwal Jain
30-Apr-22
(Irrigation Department) PA - Chief Construction Engineer, Mukhiguda
Points of Discussion:
Information rainfall and flooding pattern
Availability of water in the Indravati Reservoir
Bidhos B Paul
28-Apr-22 Department of Soil Conservation
TE- Watershed, Nabarangpur District
Points of Discussion:
Soil type and quality of project area
Cropping pattern
Prakash Chandra Pani
District Agriculture Officer
02-May-22 Department of Agriculture
Suvendu Kara
Soil Chemist
Points of Discussion:
Cropping pattern
Type of crops grown
Dependency on agriculture as an option for livelihood.
Mr. NK Naik
Upper Indravati Hydroelectric Project GM-Operation, Mukhiguda
27-Apr-22
Upper Indravati Hydroelectric Project Mr. Lambodar Puhan
Exen- Mechanical, Khatiguda
Points of Discussion:
Discussions about the project interventions
Disclosure about the siting of various project components
Provided free access to site for site assessment works
Extended support to organize Stakeholder Consultations
Community Stakeholders
01-May-22 Local Community Luthgudi Hamlet (Nagi Village)
01-May-22 Local Community Talnagi (Nagi) Main Village
Points of Discussion:
Photographs and attendance sheets for Community Stakeholder consultations are provided in Annexure 4.
6.1 Introduction
This section assesses the nature, type and magnitude of the potential impacts on the various relevant
physical, biological and social components due to the proposed development and its suitable mitigation.
Towards the assessment of impacts, the baseline information based on the field visits and the primary
surveys for various environmental and social components were carried out. The impacts on the various
environmental and social components were assessed considering following stages of the project planning
and implementation:
Preconstruction stage
Construction stage and
Operation stage
The description of impacts for the various environmental and social components as envisaged for
the project are presented in the following sections along with proposed mitigation measures 10.
Impacts as envisaged
The land requirement for Floating SPV project is significantly less in comparison to the ground mounted
solar park since the majority of the Floating SPV component i.e., Floating Solar PV panels are proposed on
waterbodies. However, during construction phase, impact on land use is anticipated due to change of land
use for the proposed development of associated infrastructure such as assembly points, pooling stations,
transmission towers, access road etc.
In the proposed project solar PV panels will be located on ~200 Ha area of Indravati reservoir. The pooling
stations are proposed on the areas where presently agricultural activity is taken up. The proposed assembly
points are proposed on barren lands. Beside this, the proposed transmission line and towers are also
passing through reserve forest, revenue forests, barren scrub forest areas as well as agricultural land. The
current land use will change after the development of project and associated infrastructure. The impact is
expected to be of long term and permanent in nature, but impact will be restricted within limited areas only.
10 Based on detailed Environmental and Social Assessment Study outcomes, the mitigation measures may further be strengthened
at later phase by the project proponent.
Develop the project and associated infrastructure/components on the barren land to the extent possible
Using existing roads to access the site and associated facility to the extent possible.
Minimum diversion of forest area/land should be ensured by adopting wise design. Prior clearance from
concerned authority should be secured before taking up any activity related to the project and all the
stipulated conditions by the authority should be strictly adhered to.
Prior permission from village council should be secured before commencement of any activity on the
field.
On completion of construction activities, land used for temporary facilities should be restored to its
original condition or as desired by concerned landowner.
Site preparation activities should be performed by causing minimum elevation of the land or blocking or
altering natural drainage channels in the project site. Provision for adequate drainage should be kept if
any alteration of contour level or blocking or altering natural drainage channels is caused.
Adequate provisions should be kept for collection of surface runoff from the project site to prohibit exit
of runoff from the project site in the adjacent areas.
As a best practice, site clearance, piling, excavation, and access road development/maintenance work
should not be carried out during the monsoon season to minimize erosion and run-off.
Robust waste and effluent/sewage management plan should be prepared.
Impacts as envisaged
During the construction phase, the topsoil will be susceptible to soil erosion to some extent due to site
clearance activities. The removal of stabilized topsoil would result in slope destabilization and increase in
soil erosion. As for soil compaction, the strengthening of internal access roads and excavation and collection
of soil will lead to soil compaction. Thus, increasing surface run-off and decreasing the percolation rate of
the soil is anticipated.
Topsoil Loss, Soil Contamination due to spill of civil construction material/waste and dumping of
construction material outside the Project construction area, Soil Erosion and compaction are the perceived
impacts likely to be associated with preconstruction and construction stage.
Mitigation Measures
Provide appropriate storage of topsoil in an isolated and covered area. Topsoil that has been stripped of
should be stored for landscaping of the site.
Allow only covered transportation of topsoil within project site, specifically sub-station & approach road
area
Construction materials and wastes should be stored in designated areas and managed properly to avoid
any accidental spill.
In case of any accidental spill, the soil will be cut and stored securely for disposal with hazardous waste.
Impacts as envisaged
The operational phase of the project will have limited impacts on soil in the form of waste generation
and soil contamination due to accidental spillages/ leakages. During operation phase, the waste
generated from Project will include domestic solid wastes at SCADA building and substation and
hazardous wastes like waste oil from DG sets and transformers, and oil containing jutes and rags. The
quantity of hazardous waste generated will be much lesser than the quantity expected to be generated
during the construction stage. Therefore, the receptor sensitivity and impact magnitude assessed as low
and small respectively at operation stage in comparison to preconstruction/construction stage.
Mitigation Measures
Oil/ lubricants should be stored on impervious floor in the storage area having secondary containment
Use of spill control kits to contain and clean minor spills and leaks during O&M activities; and
The mitigation measures as mentioned in the Solid /Hazardous Waste Disposal section should be
implemented
The solid waste generated by the Project is expected to contain domestic solid waste from temporary site
office and labour camps, construction debris, hazardous waste such as waste oil, lubricants, oil
contaminated rags, electronic waste like broken PV module etc. During the construction phase, non-
hazardous solid waste will likely generate mainly from activities including site clearance and preparation,
land excavation. Notably, the project will not cause major excavation works, thus the solid waste generated
from excavation works will be minimal. In the construction phase, the majority of domestic solid waste is
expected to be generated from labour camp which will be majorly biodegradable in nature. During
operational phase there will be generation of broken/damaged solar panel, scrap material generated from
Substation and Transmission Line maintenance works; as well as hazardous waste such as transformer
waste/burnt oil etc.
Mitigation Measures
Excavated soil may be used for backfilling/road development at required areas of project site. The
unused excavated soil should be disposed of to the designated areas (should be identified in prior).
Impacts as envisaged
Mitigation Measures:
To mitigate the construction impacts, project proponent should have contract agreements with contractors
as well as sub-contractors to ensure implementation of mitigation measure as mentioned below-
Impacts as envisaged
During operational phase, it is expected that there will be minimum vehicular movement for O&M purpose
and provision for a standby DG sets, which will be used during power failure. Since major source of emission
into the ambient air will be absent during the operational phase, therefore impact can be termed as
insignificant. Central Pollution Control Board also characterized the Solar Projects as ‘White Category’
projects due to its non-polluting nature11.
Mitigation Measures
Impacts as envisaged
Pre-construction phase will involve site preparation activities. Operation of various machineries and
equipment for construction activities, running of heavy load traffic for construction materials
transportation, and regular traffic movement may generate noise during the site preparation and
construction period. Noise generation due to various construction works are also envisaged. The heavy
equipment, machineries, transportation, DG Set operation, earthworks used for the construction activities,
and specific machines used for float manufacturing process are expected to be major sources of noise
generation.
Mitigation Measures
The following mitigation measures should be implemented to minimize potential noise impacts during
preconstruction and construction phases:
Impacts as envisaged
Any significant noise generating activity during operation of solar power plant is not envisaged (except
standby DG set for power back up and vehicular/water transport movement due to O&M works). Therefore,
impact in terms of increase in ambient noise level is not anticipated during the operational phase of the
project.
Mitigation Measures
Impacts as envisaged
Construction water requirements during preconstruction and construction phase are expected to be
met from Indravati reservoir. Potable water needs during these phases is expected to be catered
through local tankers/approved vendors.
Mitigation Measures
Restoration plan should be chalked out to accommodate the loss of surface/ ground water through
feasible water conservation measures like rainwater harvesting, water recycling etc.
Records of daily water consumption should be maintained to rule out any possibility of wastage of
water resource.
Water quality of the reservoir and nearby waterbodies should be monitored regularly, and immediate
action should be taken to control water pollution in case any deterioration in water quality is noticed.
Periodic monitoring should also be carried out to ensure that the wastewater is not finding its way into
ground or surface water.
Approval/NOC from competent authority should be obtained for abstraction and/ or utilization of
ground or surface water.
Paved impervious surface and secondary containment should be used for fuel storage tanks
Provision for adequate drainage should be made to avoid possibility of surface run-off and water
logging.
Wastewater holding tanks / septic tank should be located away from bore wells or any other
underground water holding tanks after taking view of environmental expert/ concerned authority.
Regular collection of wastewater from septic tank/s should be ensured.
Construction of adequate nos. of toilets and proper sanitation system for workers should be ensured to
prevent open defecation.
Impacts as envisaged
It is envisaged that the project will not use groundwater for any project related activity during operation
stage. Water demand for PV modules cleaning is expected to be catered from Indravati reservoir.
Wastewater from the cleaning activities will be discharged directly to the reservoir. However, the nature
is wastewater is expected to be non-polluting in nature.
Accidental leakage/spillage of transformer waster oil & bottom sludge (can occur during transmission
line and substation operation) may impact surface or ground water. However, substation transformers
will be located within secure and impervious areas (secondary containment). Therefore, the possibility
of impact on surface water / ground water during the operation phase is minor.
During the operation phase, the floating solar power system will be regularly checked and maintained.
During operations, the PV panels would already be installed and expected not to cause any incidents
related to dropping of battery panels or wires into the reservoir to affect the water environment.
The installed PV panels on reservoir area are expected to reduce water evaporation, reduce solar energy
absorption, lower water temperature, and impact on the dissolved oxygen concentration in reservoir
water. Pertinent to state that PV Panels will be spread over an area of ~ 204 ha and such impacts are
perceived within that limit only.
Mitigation Measures
Following measures should be adopted during operation phase to minimize impacts on water resource:
Water quality of reservoir should be monitored regularly, and immediate action should be taken to
control water pollution in case any deterioration in water quality is noticed.
Feasibility of constructing rainwater harvesting system at site should be explored.
Impacts as envisaged
The impact on the Ecology and Biodiversity components as envisaged to be associated with preconstruction
and construction phases are delineated below-
Removal of vegetation covers and trees due to site preparation and levelling of land, laying of
transmission towers and transmission lines, Creation of access roads
Possible habitat loss and habitat disturbance due to erosion and removal of topsoil.
Disturbance to wildlife due to noise generated from construction works and movement of construction
equipment and vehicles.
Migration of project personals, who are not accustomed to the natural environment and local wildlife of
the project area, may increase the potentiality of man animal conflict.
As per consultation with concerned Forest Department it was understood that there is no Protected (under
Wildlife Conservation Act, 1972) Area like National Park-Sanctuary-Biosphere Reserve etc. not located in the
proximity to the proposed project area12. However, there are a number of reserve forest areas are present in
the project surrounding area from where various Schedule 1 13 species like Sloth Bear, Pangolin, Leopard,
Chousingha (Four-horned antelope), Honey Badger were recorded in past.
The site preparation activities for FSPV associated infrastructure such as access road, assembly points,
storage yards, transmission line etc. is expected to cause clearance of vegetation and tree cover which
eventually will lead to direct impact on herpetofauna-smaller mammals – avifaunal and arboreal species due
12 Karlapat Wildlife Sanctuary, the nearest Protected Area from the proposed project area is located at about 42 Km
distance towards North-Eastern direction.
13 Under Wildlife Protection Act, 1972
EU-India Clean Energy and Climate Partnership (CECP) Page 77
to habitat loss. Disturbance to wildlife due to noise generated from construction works and movement of
construction equipment and vehicles are also perceived.
In consideration of the above fact, it is prominent that even though the project area is not located in the
vicinity of Protected Wildlife Area, the impact on ecology and biodiversity could be of significant in nature if
no adequate mitigation measure is taken.
Mitigation Measures
The following mitigation measures may be taken up to reduce extent of impact on the ecology and
biodiversity of project surrounding area-
Impacts as envisaged
The impacts in operational and maintenance phase are expected to be from transmission line due to
potential of collision and electrocution of roosting and nesting avifauna. The impacts on local ecology have
been assessed with respect to the following activities:
It has been observed globally that several avifaunal species utilize the transmission lines and transmission
towers for roosting, nesting or using the height of the manmade structures as a lookout for predators. All
these structures have electrical components and therefore electrocution risk for these species needs to be
assessed during process of finalizing Transmission Route Alignment.
Mitigation Measures
Periodic bird mortality counts should be undertaken at least for the first two years of operation) to
determine if there is any mortality risk of important bird or arboreal species. The mitigation measures
should be revised based on the results of the monitoring
A detailed and long-term monitoring of bird species should be planned. This will help identify the high-
risk areas of the transmission line stretch and the mitigation measures can be revised/updated based on
the outcomes of the regular studies.
Regular checking of the vacuums or holes in the towers should be done to avoid nesting by any of the
birds.
Waste materials should not be left lying around and should be cleared immediately so as to not attract
birds
Records of feeder trips due to bird electrocution should be maintained with feeder number, bird
species, time of electrocution, location, etc. These should be shared with an expert ornithologist for
identification of the species.
Benefits of floating solar technology are recognised, such as avoidance of land for project development,
avoidance of acquisition of property and assets etc. However, little is known of the negative effects of
floating solar PV on biodiversity, especially on aquatic ecosystems and water quality. For example,
operational floating solar plants block sunlight penetration into waterbodies consequently inhibiting algal
Since Floating SPVs will be deployed on water surfaces, it is also thought to be beneficial in reducing
evaporation by covering the surface of water body by limiting its interaction with wind.
As per secondary sources16, Ecologists and conservationists are concerned about the long-term impacts of
largescale Floating SPV projects on freshwater ecosystems. They caution that in absence of any reported
data or studies available, these projects may lead to an irreversible loss of biodiversity by causing harm to
aquatic life.
Spatial extent of the solar panels can alter the amount of sunlight entering the system. This can interfere
with various levels of food chain and biogeochemical cycles (water cycle, carbon cycle, nitrogen cycle) of
the aquatic ecosystem. With less sunlight available, photosynthetic activities inside the water is expected to
decrease. Low rate of photosynthesis may lead to loss of Phytoplankton (microscopic plants), macrophytes
(aquatic plants that can be submerged or emergent) and less Dissolved Oxygen inside the water body.
Declining floral population may further affect aquatic fauna that feed upon them. On one hand,
decomposition of this organic matter may lead to increase in temperature, thereby depleting the DO. This
rise in temperature and release of nutrients such as inorganic nitrates and phosphates can set off
eutrophication process (excess nutrients inside a water body) giving rise to algal bloom. Loss of aquatic
fauna may also affect the faunal community of higher trophic level i.e. birds-mammals dependent on aquatic
fauna of the water body. Thus, the impacts could include habitat disturbance/loss, fragmentation, formation
of algal bloom, food availability etc. Therefore, necessary mitigation measure is required to offset the
potential negative impact on aquatic ecosystem.
Mitigation Measures
14 https://portals.iucn.org/library/sites/library/files/documents/2021-004-En.pdf
15 https://portals.iucn.org/library/sites/library/files/documents/2021-004-En.pdf
16 https://india.mongabay.com/2021/03/solar-projects-on-water-could-come-at-a-cost-to-the-environment-alert-experts/
EU-India Clean Energy and Climate Partnership (CECP) Page 80
enforced through contractual obligations with EPC contractor/sub-contractors.
General awareness regarding wildlife and nature conservation should be enhanced.
Strict prohibition on discharge of wastewater containing oil-other hazardous materials-pollutants to the
surrounding soils and waterbodies should be imposed.
Water quality of the reservoir and nearby waterbodies should be monitored regularly, and immediate
action should be taken to control water pollution in case any deterioration in water quality is noticed.
Occupational health and safety need to be monitored for several activities anticipated for the Project
o Working at height during erection of, transmission towers and establishment of transmission lines
o During the installation of the Floating SPV system, the PV panels will be set up on the reservoir and
workers may face with the risk of falling into water.
o Working in confined spaces at pooling substation or excavated areas.
o Working with rotating machinery including the rollers and layers.
o Working with live electrical components – transmission towers, lines and internal electrical parts;
and
o Potential risk from unhygienic conditions at site including contaminated drinking water for workers.
The Project will also need to plan for and implement proper measures for fire safety, public accessibility,
falling objects, structural safety and any unforeseen emergency situations.
Various site-preparation and construction activities may pose threat to worker health and safety. During the
construction phase, an occupational health and safety policy should be prepared and implemented by the
contractor/developer. As part of this policy, wearing Personal Protective Equipment (PPE), such as hard
hats, safety gloves, hearing protection devices, and safety boots, should be mandated for undertaking
construction and maintenance works, and appropriate measures to manage sun and heat exposure should
be implemented. In addition, all contractors’ workers should perform their field work under the supervision
of concerned experts and must comply with occupational health and safety norms.
In the construction phase, there are several possible reasons for causing fire exploration, such as electric
shock, loose electricity wires or lighting strike. These incidents may occur during the construction phase at
the transformer station and transmission line. To minimize such unforeseen events, all workers and
operators will be required to complete the training courses on safety measures.
Risk of Electrocution is anticipated during the operational phase of the project, which could be mitigated
through fencing (at Grid Substations) and restricted entry in project site.
Taking all these points in consideration, with distribution buffer area, duration short and intensity low, the
significance of impact can be minimized to an acceptable level.
Mitigation Measures
Land impacted by construction of pooling stations: The land identified for the pooling station (both 1 and
2) fall within the village of Nagi (or Talnagi). As discussed in section 4.6.2, pooling station 1 is located
near the hamlet of Luthgudi and is used for cultivation by the inhabitants of Luthgudi even though they
have no ownership of the land. Pooling station 2 is located near the boat docking area within Nagi
village and there were signs of cultivation and grazing in this patch.
Land impacted by building of Assembly Points: Assembly point 1 is located very near the water boundary
of the reservoir (almost within the reservoir) and according to the locals, this area is submerged under
water when the reservoir level rises. Assembly point 2 could not be visited due to lack of last mile
connectivity but consists of shrubs and is not used by the locals for any purpose.
In consultation with the revenue inspector and the locals, it was surmised that none of the above
parcels of land were owned privately but are rather owned by the Upper Indravati Hydroelectric Power
Project (Dam authority as referred to locally), however this will have to be confirmed with title records
prior to any initiation of FSPV activities.
Land impacted by Transmission towers: As per GoI rules and regulations, lands below the transmission
towers are not acquired but there are impacts in terms of temporary restriction in land use. Potentially
affected people (APs) are provided compensation for any damages caused during the construction or
any loss faced due to the temporary restriction in land use (compensation for crops and plantations).
Impacts as envisaged:
Loss of landed asset will be a permanent and irreversible loss which should be avoided, to the extent
possible. So far, the possibility of impacting private land is low but this needs to be verified prior to
project initiation. The plots identified for pooling station 1 should be avoided (if possible) as it is
currently used for cultivation purposes for both subsistence and livelihood.
Loss of income derived from land in the form of agricultural and related activities. Depending on the
type of activity – for subsistence or for commercial – loss of land could either have threats of food
security in the absence of alternative land for subsistence activities, or it could cause loss of livelihood.
Pooling station 1 is used by the tribal inhabitants of Luthgudi hamlet to conduct agricultural activities.
The construction of transmission towers and drawing of transmission line could cause temporary
restriction in land use and lead to potential risk of crop damages.
Loss of grazing land could be an associated impact of loss of land, as could be the case for Assembly
point 1.
Loss of access routes (to the reservoir, boat docking area and elsewhere) due to construction activities
and constructed structures associated to the project. Proposed Pooling Station Point 2 and the existing
Mitigation Measures:
A proper socio-economic survey prior to construction should be done to identify the loss of landed
assets and the extent & magnitude of loss of livelihood. A census survey will also be required to record
the inventory of loss to be faced by the potentially affected persons.
Prior to acquiring private lands/any lands (of any kind) used by the local communities for their purposes,
a proper entitlement matrix in accordance to national laws, state laws and IFC performance standards
should be formulated. The same needs to be disclosed and consent in accordance to FPIC needs to be
taken from the surrounding communities and their Gram Panchayat, prior to any construction.
Loss of land (private) will require either provision of equivalent amount of land or compensation at full
replacement cost. The cost of land will be decided as per assessment of the concerned local
administrative department.
To the best possible extent, private lands and lands used for subsistence or commercial agricultural
activities should be avoided. In case avoidance is not possible, PAPs should be given adequate
notification to harvest their crops and find alternative land parcels with the help of the local
administration to conduct their subsistence farming and mitigate any threat of food security.
Additionally, the entitlement matrix in the Resettlement Action Plan (to be prepared after detailed ESIA)
should incorporate adequate compensation measures to make up for the loss of annual livelihood of the
Scheduled Tribes (and other vulnerable groups) who practice cultivation on these lands.
Community should be consulted on the existing transport routes on the reservoir so that adequate
measures can be taken to avoid any impacts on these while finalizing the design of the FSPV. In case
avoidance is not possible, alternative routes should be identified in consultation with the communities.
In case, the construction of Pooling Station 2 causes loss of access to the boat docking area, an
alternative boat docking area needs to be identified – which should be easily accessible, not too far
away from the existing docking area, and accessible to the people – in consultation with the community.
In case access route and some minor construction work is required for the newly identified docking area
then that too should be undertaken by the project proponent prior to construction work for the FSPV
and its associated infrastructure.
The entitlement matrix should also factor any temporary damages caused to standing or sowed crops,
or private properties during the operation and maintenance phase of the project and during the
construction and maintenance of the transmission line.
The Indravati reservoir supports some local fishing activities. Around 10-15 households that rely on fishing, in
Talnagi village. Fishing activities are carried out mostly in the monsoon months (July to October) as the rain
brings the fish to the upper levels making it easier to net them. On average each fishing involved household
catches up to 15-50Kg of fish and the average price of per kg is INR 120/-. There are about 11 fishermen who
have been registered from the village with the Khambeshwari Primary Fishermen Cooperative (PFC), which
leases a certain portion of the reservoir. Other households too conduct fishing activities at a smaller scale
and only for subsistence.
Impacts as envisaged:
The floating solar panels will be situated on the Indravati reservoir using approximately 200 hectares of
the reservoir surface area. This can adversely impact the fishing activities conducted in this particular
reservoir part by the villages adjacent to it (Murka and Talnagi) and as well as fishermen from the
Khambeshwari PFCS. Any adverse impact on fishing activity will also impact upon the livelihood and
food resource of the local communities. The income derived from fishing in the monsoon months (July –
October) is considerable with catch per fishing household going up to 100kg per day at prices of
INR15o/kg (approx.).
Apart from adverse impact on fishing, the reservoir is also used for transport – either to travel across the
reservoir to reach villages or to access fishing areas. The siting of the solar panels could cause routes to
lengthen, thereby increasing the time of transport and commute.
Since the lands around the reservoir are used of agricultural activities, the associated infrastructure like
pooling station, assembly points and transmission line could adversely impact cultivation activities. The
pooling station and assembly points will be permanent constructions and will change the land use
whereas for the construction of transmission towers, there will be temporary disturbance to agricultural
activities (damages to crops, land or landed assets).
Mitigation measures:
A socio-economic survey will be required to understand the extent and magnitude of adverse impacts
on the economic activities of the people dependent on the reservoir for their livelihoods. Additionally,
efforts need to be made to identify the vulnerable PAPs (women headed HHs, indigenous HHs, disabled
HHs, aged HHs, etc.) amongst the PAPs. The number of PAPs need to be established in the socio-
economic survey – majorly those who may face economic displacement, as chances of physical
displacement due to land acquisition are slim. A resettlement action plan, livelihood restoration plan and
Indigenous Peoples Plan may be required and should be determined basis the socio-economic survey. It
should be noted that population sizes of Talnagi and Murka villages are quite small and mostly consist of
Scheduled Tribes and then Scheduled Castes – both of which are to be considered as vulnerable
populations. All surveys and consultations will have to be done in accordance to IFC PS 7 – Indigenous
Peoples and FPIC requirements.
Consultations with the Khambeshwari PFCS and the surrounding communities need to be conducted to
understand the extent of adverse impact on livelihood from fishing activities. It will also be pertinent to
consult with the PFCS to understand the exact catchment area vis-à-vis the siting of the floating panels.
Post the survey, an entitlement matrix in accordance to the nation laws, state laws and IFC performance
standards needs to be formulated and disclosed to the people for their acceptance and comments, prior
Given the significant presence of scheduled tribes in the project area, the project will trigger IFC
Performance Standard 7 (Indigenous Peoples) and its requirements f FPIC and other considerations. The
project proponent should prepare an Indigenous Peoples Plan (IPP) outlining the actions to minimize and/or
compensate for adverse impacts in a culturally appropriate manner and plan for enhancing positive impact .
Depending on local circumstances, a free-standing IPP may be prepared, or it may be a component of a
broader community development plan where Affected Communities of Indigenous Peoples exist in the
same area with other similarly Affected Communities or where the Indigenous Peoples are integrated within
a larger affected population.
Impacts as envisaged:
Scheduled tribes will fall under vulnerable categories of PAPs and any adverse impact on them require
due consideration. The project may pose adverse impacts on their means of livelihoods (fishing and
cultivation) as well as their access and commute routes on the reservoir.
Indigenous people traditionally rely on their natural surroundings for their livelihood. Scheduled tribes
are further characterized by their low levels of literacy, low penetration of information and technology
and their reliance on traditional means of living and working. This would mean that any adverse impact
on their source of livelihood, their mode of transport causing them increased time, or lack of access to
lands which they were earlier cultivating for subsistence – would further increase their vulnerability.
Mitigation measures:
The entitlement matrix should also factor any temporary damages caused to standing or sowed crops,
or private properties during the operation and maintenance phase of the project. The vulnerabilities of
the Scheduled tribes residing in the hamlet of Luthgudi and in the villages of Nagi and Murka and any
losses to them should be factored into the entitlement matrix.
Impacts as envisaged:
Key components of the Project including floating solar area, pooling station, transmission line, and
assembly points will be located in the village surrounding the reservoir. During the construction of these
components, it is expected that a considerable number of workers will be employed by the Project and
apart from the unskilled construction workers, most of the skilled workers will be migrant labour
brought in from other parts of the country. These workers will be accommodated in camps near/around
the project site. The presence of these workers in the lowly populated villages of Talnagi and Murka,
with limited resources and dependency on their natural surrounding may cause conflict over resource
sharing, create pressure on local infrastructure, increase of commodity and goods prices,
conflict/tension between migrant and local people, increased risk of infectious diseases including sexual
transmitted infection and general disturbance (alcohol and drug abuse) in the project vicinity.
The influx of labour may also lead to risks of safety and security amongst the existing communities.
Large number of migrant labour population with cultural differences with the existing communities
could cause tensions and conflicts with the host community over access to scarce resources and
exacerbate gendered risks like Gender Based Violence (GBV). The presence of cash due to work could
increase the potential for sex work in the fringes and increase the risk of communicable and sexually
transmitted diseases.
The local community may be exposed to health and safety risks resulting from construction activities of
the Project components including noise, dust, and traffic safety and drowning potential due to curiosity
for the floating solar panels.
The existence of the floating solar modules on the lake may attract the people from local area and/or
other place (tourists) who want to visit the project area and access to the lake to observe the floating
solar. Such actions could lead to the increase of drowning and other safety (due to construction
activities of other components nearby) potential to the visitors and disturbance to the daily activities of
local community who live near the Project area.
Other Impacts:
Construction materials and workers will be transported to and from the Project site. The transportation
and existing roads may be busier during the short period of construction of the project, especially during
the transportation of the floatation devices and panels which are to be assembled near the project site.
Influx of labour and establishment of labour camps could cause additional waste generation in the area.
The waste management practices of the existing communities and utilities available may not be able to
handle the burden of the additional municipal waste leading to indiscriminate dumping including into
the reservoir.
Increase in tourism (indirect) could be an impact with people wanting to see floating solar panels.
Mitigation Measures:
Migrant workers and workers in general will be provided with mandatory and periodic training centered
on proper behavior around host community, use and destruction of surrounding areas, use and overuse
of forest produce (like firewood), prevention of STDs and communicable diseases, waste management
and disposal practices, etc. The siting of labor camps should be done in consultation with the Gram
Panchayat to avoid any conflict.
The labor camps need to be equipped with proper accommodations, sanitation facilities, and utilities in a
manner that pressure on existing utilities is low or negligible. The contractor will need to ensure these
basic facilities at the labor camp/s. Any open defecation or disposal of municipal waste in the
surrounding or village peripherals should be strictly prohibited by the contractor and the labor camps
should be monitored for adherence of the rules.
All fossils, coins, articles of value of antiquity, structures and other remains or archaeological interest
discovered on the site shall be the property of the Government and shall be dealt with as per provisions
of the relevant legislation.
The Contractor will take reasonable precautions to prevent his workmen or any other persons from
removing and damaging any such article or thing. He will, immediately upon discovery thereof and
before removal acquaint the Environmental Specialist PIU or PIC of such discovery and carry out the
PIU/PIC instructions for dealing with the same, waiting which all work shall be stopped.
The PIU/PIC will seek direction from the Archaeological Survey of India (ASI) before instructing the
Contractor to recommence the work in the site. The Archaeological structures identified along the route
alignment of the Transmission line should be protected/ preserved or enhanced as per the law.
S. No. Aspect/Activity Key Potential Impacts/Risks Mitigation Measures – Action Plans Timelines of Implementation Responsibility
Detailed Design, Construction (including Site preparation/Preconstruction) and Operation and Maintenance (O&M) Phases
2. Preparation of Inadequate Please Refer ‘Chapter 8: Conclusion Prior to Site Preparation Detailed Design
Safeguard & Recommendation’ Primary: Consultant & Developer
information about potential
Documentations like Secondary: GEDCOL & GEDCOL Partner
impact
Detailed ESIA/ESMP,
plan for mitigating the risk
Biodiversity Plan etc.
budget for implementation of
safeguard measures
3. Safeguard Please refer to Section 6.2 of the Please refer to Section 6.2 of the Construction (including Site Primary: Contractor/ Developer
implementation for report report preparation/Preconstruction) Phase Secondary: GEDCOL & GEDCOL Partner
Land use &
Topography
4. Management of Soil Please refer to Section 6.3 of the Please refer to Section 6.3 of the Throughout Construction (including Primary: Contractor/ Developer
Resource report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
5. Management of Solid Please refer to Section 6.4 of the Please refer to Section 6.4 of the Throughout Construction (including Primary: Contractor/ Developer
and Hazardous Waste report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
6. Mitigation of Air Please refer to Section 6.5 of the Please refer to Section 6.5 of the Throughout Construction (including Primary: Contractor/ Developer
Pollution report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
7. Mitigation of Noise Please refer to Section 6.6 of the Please refer to Section 6.6 of the Throughout Construction (including Primary: Contractor/ Developer
Pollution report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
8. Conservation and Please refer to Section 6.7 of the Please refer to Section 6.7 of the Throughout Construction (including Primary: Contractor/ Developer
pollution control of report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
water resources Phase
9. Conservation of Please refer to Section 6.8 of the Please refer to Section 6.8 of the Throughout Construction (including Primary: Contractor/ Developer
Terrestrial Ecosystem report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
10. Conservation of Please refer to Section 6.9 of the Please refer to Section 6.9 of the Throughout Construction (including Primary: Contractor/ Developer
Aquatic Ecosystem report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
Phase
11. Managing Please refer to Section 6.10 of the Please refer to Section 6.10 of the Throughout Construction (including Primary: Contractor/ Developer
Occupational health report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
and safety aspects Phase
12. Offsetting Potential Please refer to Section 6.11 of the Please refer to Section 6.11 of the Prior to Site Preparation GEDCOL & GEDCOL Partner
Impact on land and report report
assets (also
enhancement)
13. Offsetting Potential Please refer to Section 6.12 of the Please refer to Section 6.12 of the Prior to Site Preparation GEDCOL & GEDCOL Partner
Impact on livelihood
14. Offsetting Potential Please refer to Section 6.13 of the Please refer to Section 6.13 of the Prior to Site Preparation GEDCOL & GEDCOL Partner
Impact on Indigenous report report
people and their
surroundings (also
enhancement)
15. Managing Potential Please refer to Section 6.14 of the Please refer to Section 6.14 of the Throughout Construction (including Primary: Contractor/ Developer
Impact on community report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
health and safety Phase
16. Managing Potential Please refer to Section 6.15 of the Please refer to Section 6.15 of the Throughout Construction (including Primary: Contractor/ Developer
Impact on culture and report report Site preparation/Preconstruction) Secondary: GEDCOL & GEDCOL Partner
heritage Phase
17. Management of Soil Please refer to Section 6.3 of the Please refer to Section 6.3 of the Throughout Operation and Primary: Contractor/ Developer
Resource report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
18. Management of Solid Please refer to Section 6.4 of the Please refer to Section 6.4 of the Throughout Operation and Primary: Contractor/ Developer
and Hazardous Waste report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
19. Mitigation of Air Please refer to Section 6.5 of the Please refer to Section 6.5 of the Throughout Operation and Primary: Contractor/ Developer
Pollution report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
20. Mitigation of Noise Please refer to Section 6.6 of the Please refer to Section 6.6 of the Throughout Operation and Primary: Contractor/ Developer
Pollution report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
21. Conservation and Please refer to Section 6.7 of the Please refer to Section 6.7 of the Throughout Operation and Primary: Contractor/ Developer
pollution control of report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
water resources
22. Conservation of Please refer to Section 6.8 of the Please refer to Section 6.8 of the Throughout Operation and Primary: Contractor/ Developer
Terrestrial Ecosystem report report Maintenance stage Secondary: GEDCOL & GEDCOL Partner
23. Conservation of Please refer to Section 6.9 of the Please refer to Section 6.9 of the Throughout Operation and Primary: Contractor/ Developer
Aquatic Ecosystem report report Maintenance Stage Secondary: GEDCOL & GEDCOL Partner
24. Managing Please refer to Section 6.10 of the Please refer to Section 6.10 of the Throughout Operation and Primary: Contractor/ Developer
Occupational health report report Maintenance Stage Secondary: GEDCOL & GEDCOL Partner
and safety aspects
25. Offsetting Potential Please refer to Section 6.11 of the Please refer to Section 6.11 of the Throughout Operation and GEDCOL & GEDCOL Partner
Impact on land and report report Maintenance Stage (if applicable)
assets (also
enhancement)
26. Offsetting Potential Please refer to Section 6.12 of the Please refer to Section 6.12 of the Throughout Operation and GEDCOL & GEDCOL Partner
Impact on livelihood report report Maintenance Stage (if applicable)
and economic
activities (also
enhancement)
27. Offsetting Potential Please refer to Section 6.13 of the Please refer to Section 6.13 of the Throughout Operation and GEDCOL & GEDCOL Partner
Impact on Indigenous report report Maintenance Stage (if applicable)
people and their
surroundings (also
enhancement)
28. Managing Potential Please refer to Section 6.14 of the Please refer to Section 6.14 of the Throughout Operation and Primary: Contractor/ Developer
Impact on community report report Maintenance Stage (if applicable) Secondary: GEDCOL & GEDCOL Partner
health and safety
29. Managing Potential Please refer to Section 6.15 of the Please refer to Section 6.15 of the Throughout Operation and Primary: Contractor/ Developer
Impact on culture and report report Maintenance Stage (if applicable) Secondary: GEDCOL & GEDCOL Partner
heritage
Recommended
S. No. Aspect Source of Potential Impact Monitoring Parameters Executing Agency Enforcement Agency
Frequency17
A Preconstruction and Construction Phase
Local Manpower Contractor’s report GEDCOL & GEDCOL
1. Construction Works Quarterly Contractor/Developer
Absorption No. of people working in the project Partner
Excavation, disposal, cut & fill GEDCOL & GEDCOL
Survey & observation; Extent and
and land clearing activities for Partner
2. Soil Erosion degree of erosion; Structures for Monthly Contractor/Developer
site levelling and internal
controlling soil erosion
roads, disposal
Survival rate of species planted; GEDCOL & GEDCOL
3. Greenbelt Development - Half Yearly Contractor/Developer
Density of vegetation Partner
Survey & observations; GEDCOL & GEDCOL
Transportation of construction Quarterly (Except
Concentration Levels for various Partner
4. Air Quality materials, various construction monsoon season) Contractor/Developer
pollutants as recommended by
works at 2 locations
CPCB
Restoration of disposal sites Status of mitigation measures; GEDCOL & GEDCOL
5. Waste Management Quarterly Contractor/Developer
and construction areas Waste management practice Partner
Transportation of construction Ambient Equivalent continuous GEDCOL & GEDCOL
materials, various construction Sound Pressure Levels (Leq) at day Partner
6. Noise Level Monthly Contractor/Developer
works, operation of and Night-time at 4locations
equipment and DG Sets
All physio-chemical & biological Quarterly from 2 GEDCOL & GEDCOL
7. Ground Water Contamination due to seepage Contractor/Developer
parameters locations Partner
All relevant physio-chemical & GEDCOL & GEDCOL
Transportation of construction Once in each
biological parameters for the Partner
8. Surface Water materials, various construction season at Contractor/Developer
sample drawn from reservoir and
works, runoff from camp 4locations
other waterbody
17 number of sampling location and location of sampling should be finalized in discussion with Environmental Experts of Executing Agency as well as Enforcement Agency
EU-India Clean Energy and Climate Partnership (CECP) Page 96
Recommended
S. No. Aspect Source of Potential Impact Monitoring Parameters Executing Agency Enforcement Agency
Frequency
Ecology / Biodiversity Ecological impacts -Vegetation Avifauna /Arboreal species GEDCOL & GEDCOL
Clearance/ Transmission Line; monitoring; Terrestrial and aquatic Partner
9. Quarterly Contractor/Developer
development of FSPV island in habitat and species assessment
reservoir (richness and diversity)
Grievance Redress Construction works; material GEDCOL & GEDCOL
Details of grievance registered,
and waste handling/disposal; Contractor/Developer & Partner
10. nature of grievance, adequacy of Quarterly
access issue; land requirement GEDCOL & GEDCOL Partner
resolution
for the project; labour influx
B Operation and Maintenance Phase
Ambient Equivalent continuous Once in each GEDCOL & GEDCOL
Noise levels compliance with
1. Noise Levels Sound Pressure Levels (Leq) at day season at 4 Contractor/Developer Partner
respect to CPCB standards
and Night-time at 4 locations locations
Survival rate of species planted; GEDCOL & GEDCOL
2. Greenbelt Development Half Yearly Contractor/Developer
Density of vegetation Partner
Avifauna /Arboreal species GEDCOL & GEDCOL
Operational Transmission line
monitoring; Terrestrial and aquatic Partner
3. Ecological Environment and Floating SPV island on Half Yearly Contractor/Developer
habitat and species assessment
reservoir
(richness and diversity)
Once in a year at Contractor/Developer GEDCOL & GEDCOL
Concentration Levels for various
2 locations Partner
4. Ambient air quality O&M works pollutants as recommended by
(Except monsoon
CPCB
season)
All physio-chemical & biological Quarterly from 1 Contractor/Developer GEDCOL & GEDCOL
5. Ground water quality Contamination due to seepage
parameters location Partner
All relevant physio-chemical & Contractor/Developer GEDCOL & GEDCOL
Quarterly from 4
6. Surface water quality O&M works on reservoir biological parameters for the Partner
locations
sample drawn from reservoir
Details of grievance registered, GEDCOL & GEDCOL
Contractor/Developer &
7. Grievance Redress O&M works nature of grievance, adequacy of Quarterly Partner
GEDCOL & GEDCOL Partner
resolution
These reports should also be forwarded to financial institution (if applicable) for approval and disclosure.
Contractors ESMP.
Documented Environment Management System.
Legal Register.
Operation control procedures.
Work instructions.
Incident reports.
Emergency preparedness and response procedures.
Training records.
Monitoring and Review Reports.
Complaints/Grievance register and given resolution.
Note: The costs are approximate and need calibration at the time of detailed design and estimation stage. If there is
need of any specific mitigation according to E&S study during detailed design/Construction/Operation phase, the
cost for the same will be additional
Also, as per CPCB industry classification, Solar power project falls in White category due to its non-polluting
nature. Therefore, no ‘Consent to Establish’ or ‘Consent to Operate’ from concerned State Pollution Control
Board is required for this kind of projects.
However, to comply with Safeguard Requirements of IFC, it is important for the project proponent to
ensure implementation of the suggested mitigation measure as outlined in the Chapter 7 i.e., Environmental
and Social Management Action Plan (ESMAP) chapter and comply with the regulatory frameworks as
detailed out in Chapter 3 i.e., Legislative Regulation and Policy Consideration. Based on the preliminary
environmental & social assessment, the ESMAP is prepared, which outlines specific mitigation measures and
recommendations for further studies.
Based on the preliminary environmental & social assessment, Key recommendations are summarised
below:
o ESIA & ESMP: It is recommended to undertake a detailed Environmental & Social Impact
Assessment (ESIA) in line with the requirement of IFC Performance Standards at detailed design
stage towards development of ESMP, RAP, Gender Action Plan, Livelihood Restoration Plan,
Labour Management Plan, Traffic Management Plan etc. as applicable based on the finding of
ESIA.
o Detailed Ecological Study: Assessment of terrestrial (including bird) and aquatic ecology prior to
initiation of site related activities as well as during implementation of project.
o Given the significant presence of scheduled tribes in the project area, the project proponent should
prepare an Indigenous Peoples Plan (IPP) in consideration of IFC PS 7 requirements.
o The project proponent should ensure robust Stakeholder Engagement and Grievance Redress
Mechanism throughout the project lifecycle in accordance with IFC PS.
o Environmental and Social Auditing (Construction & Operation phase) through external agency
should be carried out.
SL No
Scientific Name Family
01 Oryza rufipogon Poaceae
02 Bethriochlooa pterma Poaceae
03 Imperata arundinaceae Poaceae
04 Cynodon dactylon Poaceae
05 Cymbopogon martini Poaceae
06 Aristida setacecea Poaceae
07 Vetiveria zizaniodes Poaceae
08 Eragrostis coaretata Poaceae
09 Thysanolaena maxima Poaceae
10 Eragrostis unioloides Poaceae
11 Eulaliopsis binata Poaceae
12 Heteropogon contortus Poaceae
13 Sacharrum spontaneum Poaceae
Fauna
List of Herpetofauna of Kalahandi South Division
ANURANS
Scientific Name Common Name Habitat
Bufonidae
1 Duttaphrynus melanostictus Common toad Near human habitation and
hill treams
2 Bufo fergusonii Agricultural fields
3 Bufo species Toad (unidentified) Near hill stream
Ranidae
4 Fejervarya sp Unidentified Paddy fields, swamps,
ditches and near hill
streams
5 Fejervarya sihyadrensis Paddy field frog Paddy fields, near hill
streams, swamps and
ditches
6 Fejervarya orissaensis Paddy field frog Paddy fields, swamps,
ditches and near hill
EU-India Clean Energy and Climate Partnership (CECP) Page 117
streams
7 Hoplobatracus tigerinus Indian bull frog Paddy fields, swamps,
ditches and near hill
streams
8 Hoplobatracus crassus Jerdon’s bull frog Paddy fields, swamps,
ditches and near hill
streams
9 Euphlyctis cyanophlyctis Skipper frog Swamps, ditches and near
hill streams
10 Ramanella variegate Paddy fields, swamps,
ditches and near hill
streams
11 Rana malabarica Hill streams, inside caves
and tree holes near hill
streams
12 Spaerotheca rolandae Paddy fields, swamps,
ditches and near hill
streams
13 Spaerotheca breviceps Burrowing frog Paddy fields, swamps,
ditches, hill streams and
forest floor
14 Spaerotheca dobsonii Burrowing frog Paddy fields, swamps,
ditches, hill streams and
forest floor
Microhulidae
15 Microhyla ornata Ornate frog Paddy fields, swamps,
ditches, hill streams,
grass lands and forest
floor
16 Uparodon systoma Balloon frog Ditches, ponds and
temporary water deposit
areas
17 Uparodon globulosum Balloon frog Ditches, ponds and
temporary water deposit
areas
18 Calaula pulchra Painted frog
Rachophoridae
19 Polypedates macdulatus Tree frog Busy forest, on trees and
near hill streams
20 Phillaotus sp. Bush frog Busy forest and near hill
(Unidentified) steam
LIZARDS
Sl No Scientific Name Common Name Habitat searched
01 Calodactylus aureus Golden gecko Caves and rock boulders
near hill streams
02 Geckoella nebulosus Leopard gecko Forest floor and leaf litters
03 Geckoella jeyporensis Jaipur hill gecko Forest floor and leaf litters
04 Eublepharis hardwikii Fat tailed Gecko Forest floor and leaf litters
05 Hemidactylus brookii Brook’s gecko Forest floor, trees and leaf
litters
06 H. leschenaultia Bark gecko Forest floor, trees and leaf
litters
07 H. frenatus Southern House Gecko Forest floor, trees and leaf
litters
08 H. subraidrus Termite Hill Gecko Forest floor and boulder
deposit areas.
09 Sitana ponticeriana Fan throated lizard Forest floor, open field
Location Code: AE 2
Location Code: AE 4
Euglena sp.
Cladophora sp.
Chlorella sp.
1. Chlorophyta
Spirogyra sp.
Spirulina sp.
Closterium sp.
Navicula sp.
2. Bacillariophyta
Pinnularia sp.
Anbaena sp.
Oscilatoria sp.
3. Cyanophyta
Nostoc sp.
Microcystis sp.
Location Code: AE 1
Amoeba sp.
Euglypha sp.
1. Protozoa Paramoecium sp.
Opercularia sp.
Metopus sp.
Polyarthra sp.
2. Rotifera Trichocera sp.
Monostyla sp.
Moina sp.
3. Cladocera Ceriodaphnia sp.
Daphnia sp.
Cyclops sp.
4. Copepoda Nauplii sp.
Mesocyclops sp.
Location Code: AE 3
Location Code: AE 4
Location Code: AE 1
Polydora sp.
1. Annelida
Nereis sp.
Amphibalanus sp.
Squilla sp.
2. Arthropoda Panulirus sp.
Panopeus sp.
Charybdis sp.
Corbicula sp.
Umbonium sp.
Natica sp.
Acrilla sp.
Melanoides sp.
3. Mollusca
Pisidium sp.
Neverita sp.
Turritella sp.
Gyrineum sp.
Indothais sp.
Location Code: AE 2
Location Code: AE 3
Polydora sp.
1. Annelida Hirudo sp.
Nereis sp.
Amphibalanus sp.
Amphiops sp.
Squilla sp.
2. Arthropoda Panulirus sp.
Ranatra sp.
Panopeus sp.
Charybdis sp.
Corbicula sp.
Umbonium sp.
Natica sp.
Pila sp.
3. Mollusca Lymnaea sp.
Melanoides sp.
Pisidium sp.
Gyrineum sp.
Indothais sp.
Location Code: AE 4
This publication contains certain examples extracted from third party documentation and so being out of context from the original third-party
documents; readers should bear this in mind when reading the publication. The copyright in such third-party material remains owned by the third
parties concerned, and PwC expresses its appreciation to these companies for having allowed it to include their information in this publication. For a
more comprehensive view on each company’s communication, please read the entire document from which the extracts have been taken. Please
note that the inclusion of a company in this publication does not imply any endorsement of that company by PwC nor any verification of the accuracy
of the information contained in any of the examples.