2019 - Chapter 9 - Additions Alterations Repairs - ADA
2019 - Chapter 9 - Additions Alterations Repairs - ADA
2019 - Chapter 9 - Additions Alterations Repairs - ADA
Table of Contents
9 Additions, Alterations, and Repairs ............................................................................... 1
9.1 Introduction ........................................................................................................... 1
9.1.1 Additions ......................................................................................................... 1
9.1.2 Alterations ...................................................................................................... 2
9.1.3 Repairs ........................................................................................................... 2
9.2 What’s New in the 2019 Energy Standards ........................................................... 5
9.2.1 Mandatory Envelope ....................................................................................... 5
9.2.2 Mandatory Mechanical Ventilation .................................................................. 5
9.2.3 Prescriptive Additions ..................................................................................... 6
9.3 Compliance Approaches ....................................................................................... 6
9.3.1 Additions ......................................................................................................... 7
9.3.2 Additions and Alterations Combined............................................................... 8
9.3.3 Alterations Only .............................................................................................. 9
9.3.4 Wall Exceptions to Continuous Insulation ....................................................... 9
9.3.5 Accessory Dwelling Units (ADUs)................................................................. 10
9.4 Prescriptive and Mandatory Measures ................................................................ 13
9.4.1 Prescriptive Additions ................................................................................... 16
9.4.2 Water Heating System .................................................................................. 23
9.4.3 Alterations – Prescriptive/Mandatory Requirements ..................................... 23
9.4.4 Envelope Alterations..................................................................................... 24
9.4.5 Water Heating Alterations ............................................................................. 35
9.4.6 HVAC System Alterations ............................................................................. 37
9.4.7 Mechanical Ventilation .................................................................................. 44
9.4.8 Lighting Measures ........................................................................................ 44
9.5 Performance Approach ....................................................................................... 46
9.5.1 Performance: Addition Alone ........................................................................ 46
9.5.2 Performance Method: Additions and Existing + Addition + Alterations
Approach ................................................................................................................... 46
9.5.3 Existing + Addition + Alterations Without Third-Party Verification................. 48
9.5.4 Existing + Addition + Alterations With Third-Party Verification ..................... 49
9.5.5 Existing + Addition + Alterations as New Construction ................................. 49
9.5.6 Summary of Modeling Rules......................................................................... 49
9.1.1 Additions
An addition is any change to an existing building that increases conditioned floor
area and conditioned volume (including conditioning a previously unconditioned
space). See §100.1.
Examples of an addition include:
1. Adding a conditioned sunroom or other rooms to an existing house.
9.1.2 Alterations
An alteration is any change to a water-heating system, space-conditioning system,
lighting system, or envelope of a building that is not an addition. See §100.1.
Examples of alterations include:
1. Adding insulation to any existing exterior roof or ceiling, exterior wall, or raised
floor over a crawl space, garage, or unheated basement.
2. Replacing or installing a new top surface to an existing roof (reroofing) and
replacing portions of or the entire roof assembly.
3. Replacing existing fenestration or adding fenestration area (for example,
windows, bay windows, greenhouse/garden windows, dynamic glazing,
clerestories, or glass doors) to existing walls.
4. Replacing an existing skylight or increasing the area of skylight to an existing
roof.
5. Constructing an entirely new roof over an existing conditioned space.
6. Adding a loft within the existing conditioned volume of a home.
7. Replacing an existing heating system or adding a heating system (for example,
a furnace, wall heater, heat pump, or radiant floor). (NOTE: Adding heating to a
previously unconditioned space is an addition, not an alteration.)
8. Replacing an existing cooling system or adding a cooling system (for example,
an air conditioner or heat pump).
9. Extending or replacing an existing duct system or adding an entirely new duct
system.
10. Replacing the existing water heater or adding water heaters and/or hot water
piping.
11. Replacing existing lighting or adding new hardwired lighting fixtures.
12. Adding window film.
9.1.3 Repairs
A repair is “the reconstruction or renewal for the purpose of maintenance of any
component, system, or equipment of an existing building. Repairs shall not increase
the pre-existing energy consumption of the repaired component, system, or
Unconditioned Sunspace
Answer:
The mechanical and envelope requirements of the Energy Standards do not apply if the
space is not considered habitable or improved and, therefore, can be unconditioned as
defined in §100.1; however, per §100.0(c)2, the sunspace must still comply with the
applicable lighting requirements of §150.0(k). The sunspace is unconditioned if:
▪ The new space is not provided with heating or cooling (or supply ducts).
▪ All openings between the new space and the existing house can be closed off with
weather-stripped doors and windows.
▪ The addition is not indirectly conditioned space (defined in §100.1 under
CONDITIONED SPACE, INDIRECTLY).
A building official may require a sunspace to be conditioned if it appears to be habitable
space, in which case the Energy Standards apply.
Example 9-2
Question:
An existing duplex is remodeled, which includes only the installation of new faucets and
bathroom lighting. Do the Energy Standards apply?
Answer:
Yes, this remodel is considered an alteration. However, due to the limited scope of work
and since no new conditioned space is being created, the remodel must comply only with
the applicable mandatory measures described in §110.1 for appliances and §150.0(k) for
residential lighting.
9.3.1 Additions
Regardless of compliance approach selected, the following exceptions apply:
1. Additions of ≤ 300 ft2 do not require a cool roof product (if required by
§150.1[c]11) to be installed.
2. Whole-house fan (or ventilation cooling) does not apply to additions of
1,000 ft2 or less (if otherwise required by §150.1[c]12).
3. Existing space conditioning systems that are extended to provide
conditioning to an addition are not required to meet the Energy Standards
(§150.2[a] Exception 4).
4. Indoor air quality (IAQ) requirements (§150.0[o]1C, D, or F) do not apply to
additions of 1,000 ft2 or less that are not a new dwelling unit.
5. Photovoltaic (PV) requirements do not apply to additions/alterations.
A. Addition Alone
In this compliance scenario, the addition alone is modeled using the compliance
software, and the existing building is not modeled. This approach may work well
when the existing building is not undergoing alterations, and the permitted work
scope covers only the addition.
9.3.2.1 Prescriptive
When a low-rise residential project includes an addition and alterations, the
prescriptive requirements for each condition must be met. The addition may comply
with the appropriate prescriptive addition approach and documented with the
applicable form (for example, CF1R-ADD-01).
The alterations must also meet all prescriptive requirements and be documented
with the specific compliance documentation for alterations (for example, CF1R-ALT-
02).
9.3.2.2 Performance
The performance approach that includes both additions and may include alterations
is called “Existing + Addition + Alterations.” (See Section 9.5.2.) There are two
ways to analyze the building using this method: compliance with third-party
9.3.3.1 Prescriptive
Alterations may comply prescriptively by meeting all applicable requirements in
§150.2(b), which are explained further in Section 9.4. Several prescriptive alteration
requirements are specific to the building site climate zone. There are also several
exceptions based on either climate zone or other conditions.
It is important to note that every applicable prescriptive requirement must be met;
otherwise, the building must comply using a performance approach. However, the
energy budget is based on prescriptive requirements. So if one or more proposed
alterations do not comply, the other alterations must exceed prescriptive
requirements, or the project may not comply with the performance approach.
Under the prescriptive alteration approach, the appropriate certificate of compliance
(for example, CF1R-ALT-02) form is completed and submitted for a permit. If any
mandatory or prescriptive measures require HERS verification or testing (see
Section 2.5, HERS Field Verification and Diagnostic Testing of this manual), the
certificate of compliance must be completed and registered online with a HERS
provider (see Section 2.3 of this manual) before submittal to the enforcement
agency.
9.3.3.2 Performance
Alterations may comply using the performance approach by meeting the
requirements in §150.2(b)2. This is explained in Section 9.5. The main options are:
1. Existing + Alterations: If multiple components or systems are being altered or
if the proposed modification(s) exceed the prescriptive requirements, then the
existing + alterations performance approach may be used to make trade-offs.
2. Compliance Without Third-Party Verification: This option allows for
compliance of the alterations without the need for third-party inspection to verify
existing conditions being altered.
3. Compliance With Third-Party Verification: This option allows for compliance
of the alterations only with third-party inspection to verify existing conditions
being altered.
4. Existing + Alterations as new construction: This option is the most difficult.
extended wall also does not require continuous insulation; and (2) the existing
framing size may be kept.
This exception will typically apply to only one or two walls of an addition. Prescriptive
compliance for the walls that meet the criteria will require R-15 cavity insulation if the
existing framing is 2x4 or R-21 cavity insulation if the existing framing is 2x6 for the
extended wall(s). The energy budget for performance compliance will match the
prescriptive requirements.
1. HVAC
When adding an attached ADU to an existing home, the Mechanical Code does not
allow return air from one dwelling unit to be discharged into another dwelling unit
through a shared heating or cooling system. Systems without ducts are an option.
A system serving an ADU must have its own thermostat. Heating systems must be
capable of maintaining 68 °F at a point three feet above the floor and two feet from
the exterior walls in habitable rooms. Heating and cooling load calculations will
need to be provided per Title 24, Part 6, Section 150.0(h) to verify that any existing
and/or new system is properly sized,
Any addition that adds a new dwelling unit must meet all applicable IAQ ventilation
requirements of Sections 150.0(o)1C. A detached ADU must meet all applicable
IAQ ventilation requirements of Sections 150.0(o)1C. An attached ADU must also
meet all requirements if the dwelling units do not share a floor or ceiling. The whole
house ventilation airflow is to be based on the square footage of the new dwelling
unit.
Local exhaust for bathrooms and kitchens is required for any addition. See Table
9-7 in Section 9.4.2 for a more detailed summary of prescriptive HVAC system
requirements for additions.
2. Photovoltaics (PV)
Solar electricity generated by photovoltaics (PV) is not required if the ADU is an
addition. PV is required for detached, newly constructed ADUs.
Example 9-4:
Question:
An existing single-story residence has a 600 ft² attached unconditioned storage room that
the owner plans to turn into an accessory dwelling unit. The existing uninsulated walls
have 2x6 wood framing, and the owner plans to keep the existing exterior siding. For
prescriptive compliance, what wall insulation is required in the proposed ADU?
Answer:
The proposed ADU is considered an addition for Title 24, Part 6. The existing 2x6 walls
can be insulated with R-21 cavity insulation (§150.2[a]1Bvi) for prescriptive compliance.
Continuous insulation is not required for these walls.
Example 9-5:
Question:
Can the ADU in the previous example get energy compliance credit using HERS
verification of existing conditions for performance method compliance?
Answer:
Example 9-6:
Question:
In the ADU in the previous example, is solar electricity generated by PV required for
prescriptive or performance method compliance?
Answer:
No, PV is not required for Title 24 energy compliance for additions using any compliance
approach.
Example 9-7:
Question:
The existing residence in the previous example has a ducted forced-air furnace enough
heating capacity to heat the existing residence and the new ADU. Is this allowed for code
compliance?
Answer:
No. The California Mechanical Code does not allow return air from an existing forced-air
system to be discharged into another dwelling unit through the heating or cooling system.
Therefore, the existing ducted furnace may not serve the existing home and the proposed
ADU.
There are three prescriptive paths available for additions based on the total
conditioned floor area (CFA) of the addition. The total CFA of the addition may
include floor areas representing several physically separate additions to the building
under the same permit.
Table 9-2 summarizes the key features of the prescriptive envelope requirements for
the three prescriptive addition options in §150.2(a)1. Envelope requirements unique
to that type of prescriptive addition are shown in bold.
The prescriptive requirements for additions are listed in §150.2(a)1. Unless
otherwise noted, the prescriptive requirements contained in §150.1(c) also apply.
Example 9-8
Question:
I am retrofitting an existing home that includes an 800 ft2 addition. Part of this addition
includes converting a 400 ft2 unconditioned garage to conditioned space and adding a
400 ft2 bedroom above the garage. If complying prescriptively, is QII required for this
addition?
Answer:
Yes. Because this addition, including the conversion of the garage, is greater than 700 ft2,
QII is prescriptively required. If the existing walls of the garage are remaining and the
exterior cladding is not being removed, the QII insulation requirements for window and
door headers in the garage walls and QII air-sealing requirements are not required. For
all new walls and walls that are being replaced, all aspects of QII must be met. If the
performance method is used for compliance, the QII requirements can be traded off with
other efficiency measures to meet compliance. The prescriptive wall insulation
requirements for existing wood framed walls in the garage are R-15 in 2x4 framing and R-
21 in 2x6 framing.
Example 9-9
Question:
Example 9-10
Question:
If I remove a window from the existing house and reuse this window in an addition to that
house, does the relocated window have to meet the prescriptive requirements?
Answer:
Yes, if using prescriptive compliance, in which case the relocated window must be treated
as a new window and must meet the U-factor and SHGC requirements of §150.1(c)3. If
you use this existing window in the addition, you must use the actual or default U-factor
and SHGC of the window in showing compliance. Therefore, meeting the prescriptive
requirements may not be possible, and performance compliance may be the only option.
Window certification and labeling requirements of §110.6(a) do not apply to existing used
windows.
Relocated windows must also meet the maximum area-weighted average U-factor in
§150.0(q) with the EXCEPTION of up to 10 ft² or 0.5 percent of conditioned floor area,
whichever is greater.
Prescriptive Mechanical Measures
For a summary and discussion of prescriptive mechanical requirements when
installing new or replacement space-conditioning equipment and/or ducts, see
Section 9.6.2.
Example 9-11
Question:
When using the performance approach for the addition alone, do the refrigerant charge
requirements in §150.1(c)7A and fan airflow and watt draw measurements in
§150.0(m)13 need to be met for existing air conditioners serving an addition?
Answer:
If existing equipment is used to serve the addition, the refrigerant charge, airflow, and
watt draw requirements do not need to be met as specified by Exception 5 to §150.2(a).
However, if added ducts to serve the addition are more than 40 linear feet and they are in
unconditioned space, then the ducts must be tested and verified by a HERS Rater as
described in §150.2(b)1D. All installed ducts regardless of length and location shall be
sealed and meet insulation levels as described in §150.0(m) Items 1 through 6.
If a new system is installed to serve the addition, it must meet all of the requirements for
space conditioning in a new home.
Component Additions ≤ 400 ft2 Additions > 400 and Additions > 700 ft2
≤ 700 ft2
CZ 1, 11-16: R-38
Roof/Ceiling Same as ≤ 400 ft2 Option B or C
Insulation CZ 2-10: R-30 [C = require ducts and
air handler to be in
conditioned space]
(see Table 9-3
below).
Roof Products Steep Slope (≥2:12): Same as ≤ 400 ft2 Steep-Sloped (≥2:12):
(Cool Roof) CZ 10-15: Reflectance = CZ 10-15:
0.20 and Emittance = Reflectance =
0.75; or SRI = 16 0.20 and Emittance =
0.75; or SRI = 16
Low-Sloped (<2:12):
CZ 13&15: Reflectance = Low-Sloped (<2:12)
0.63 and Emittance = CZ 13&15:
0.75; or SRI = 75 Reflectance = 0.63
and Emittance =
Exception: Additions ≤ 300 0.75; or SRI = 75
ft2 exempt from cool roof
requirements
Radiant barrier CZ 2-15: Radiant barrier Same as ≤ 400 ft2 CZ 2-15: Radiant
above attic above attic spaces barrier above attic
spaces except when
complying with Option
B (see §150.1(c)2)
Roofing Tile roof or other product Tile roof or other product Tile roof or other product
with an air space with an air space with an air space
Table 9-4: Envelope Door and Glazing Requirements for Prescriptive Additions
Allowable total Up to 75 ft2 or 30% of Up to 120 ft2 or 25% of Up to 175 ft2 or 20% of
glazing area conditioned floor area, conditioned floor area, conditioned floor area,
whichever is greater whichever is greater whichever is greater
Glazing U-factor & All CZs: U = 0.30 All CZs: U = 0.30 All CZs: U = 0.30
SHGC1 CZ 2, 4 & 6-15: SHGC = CZ 2, 4 & 6-15: SHGC = CZ 2, 4 & 6-15: SHGC =
0.23 0.23 0.23
Exterior framed CZ 1-5, 8-16: U = 0.051 Same as ≤ 400 ft2 Same as ≤ 400 ft2
wall1 insulation - CZ 6-7: U = 0.065
multifamily
Extension of
existing wood-
framed wall
Or
R-15 in 2x4 wood framing
Same as ≤ 400 ft2 Same as ≤ 400 ft2
R-21 in 2x6 wood framing
Existing wood-
framed wall with
exterior siding (or
cladding) to remain
Raised floor1 All CZs: R-19 or U = 0.037 Same as ≤ 400 ft2 Same as ≤ 400 ft2
insulation
Slab floor1 CZ 1-15: No requirement Same as ≤ 400 ft2 Same as ≤ 400 ft2
CZ 16: R-7 or U = 0.58
perimeter
insulation
1. See Table 150.1-A and 150.1-B for requirements for floors and walls including mass walls.
Adding new space All prescriptive requirements Same requirements All except requirement for
conditioning as ≤ 400 ft2 ducts in conditioned space2
system(s)
Replacing existing All prescriptive requirements Same requirements All except requirement for
space conditioning as ≤ 400 ft2 ducts in conditioned space2
system(s)
Adding all new All prescriptive requirements Same requirements All except requirement for
complete duct as ≤ 400 ft2 ducts in conditioned space2
system(s)
Extending existing All duct insulation, duct system Same requirements All duct insulation, duct system
duct system(s) by > sealing, and HERS verification as ≤ 400 ft2 sealing, and HERS verification,
40 feet Except requirements for ducts
in conditioned space2
1. (Note: also, mandatory mechanical ventilation per ASHRAE 62.2 with HERS verification for additions >
1,000 ft2)
2. For more information about ducts in conditioned space, see Section 3.5.3.5.
Adding ceiling
Ceiling w/ attic and roof
insulation to an
rafters: R-19, U=0.054
existing roof; or a N/A N/A
§150.0(a)
new roof on an
existing building
In 2x4 framing: R-13, U=0.102
Adding exterior
In 2x6 framing: R-20, U=0.071
framed wall Same as mandatory N/A
insulation Exception: 2x4 framing
already insulated to R-11
or greater per §150.0(c)1
Mass/concrete See §150.1(c) for Same as mandatory N/A
walls applicable climate zone
(a) Air space 1.0" between
roof deck and bottom of
roofing product
(b) Profile ratio of rise to
width of 1:5 for >50% width
of roofing product.
Replacing > 50% of (c) Existing ducts in attic
existing roof surface, insulated and sealed per
Steep-Sloped (≥ 2:12):
including adding a §150.1(c)9.
§110.8(i) CZ 10-15: Reflectance ≥ 0.20 and
new surface layer on Emittance ≥ 0.75; or SRI ≥ 16
top of existing (d) Roof has ≥ R-38 ceiling
exterior surface insulation.
(e) Roof has a radiant
barrier per §150.1(c)2.
Table 9-8: For Residential Alterations, Summary of Mandatory and Prescriptive Measures (continued)
If the aged value for the reflectance is not available in the CRRC Rated Product
Directory, the equation below is used.
Equation 9-1: Aged Reflectance
Aged Reflectancecalculated = (0.2+β[initial – 0.2])
Where:
initial = Initial Reflectance listed in the CRRC Rated Product Directory
β = soiling resistance value listed in Table 9-10
Table 9-10: Soiling Resistance Value β, by Product Type
PRODUCT TYPE β
Field-applied coating 0.65
Other 0.70
Since this is not a mandatory requirement, if prescriptive compliance for a given roof
slope and climate zone require a minimum reflectance and emittance, you can either
meet one of the exceptions above or use the performance compliance approach to
use some other building feature to trade off the requirement.
Example 9-12
Question:
There is a Victorian building that has been converted into an office building and needs to
have a shake roof replacement. This building has a vented unconditioned attic with the
insulation on the ceiling. Would I need to meet §150.2(b)Hi?
Answer:
No, this section does not apply. The occupancy type has been changed to nonresidential.
Since the Victorian building has a shake roof and is considered a steep-sloped roof,
§141.0(b)2Bib for nonresidential buildings would apply.
Example 9-13
Question:
On an existing building, 50 ft2 of 85 ft2 of vertical glazing is being removed from an
existing south-facing wall and new glazing will be replaced as part of the alteration in the
same opening. What requirements apply?
Answer:
Since 50 ft2 is “replacement” fenestration and 35 ft2 is existing, the replaced fenestration
must comply with the §150.2(b)1B. For this example, Exception 1 to §150.2(b)1B can
used. This allows vertical fenestration no greater than 75 ft2 to meet have a U-factor no
greater than 0.40 in Climate Zones 1-16 and an SHGC of 0.35 or less in Climate Zones 2,
4, and 6 through 15.
2. Existing 2x4 exterior walls that already have R-11 insulation installed in framed
walls are exempt from the mandatory minimum R-13 wall insulation required by
§150.0(c)6; or
3. R-19 in raised floors over crawl spaces, over open outdoor areas, unheated
basements, and garages.
9.4.4.3 Fenestration
A. Replacement Fenestration
Any fenestration (i.e., windows, skylights, clerestories, and glazed doors) that is
being removed and replaced in an exterior wall or roof is considered “replacement
fenestration.”
Replacement fenestration is an area of new fenestration that replaces an equal or
lesser area of glazing removed in the same existing wall or roof area. It is labeled as
“altered” fenestration, and it need not occur in the same openings as the glazing
being removed as long as it is being installed in the same existing wall or roof
surface that remains a part of the existing building. Any added fenestration area that
is larger than the total altered glazing area is labeled as “new.”
C. Greenhouse Windows
Greenhouse or garden windows are special windows that project from the façade of
the building and are typically five-sided structures. An NFRC-rated U-factor for
greenhouse windows is typically high and may not meet the mandatory requirements
for the fenestration U-factor of 0.58.
To meet this mandatory measure, greenhouse windows:
1. Must have a maximum U-factor of 0.58 or better; or
2. Must use the area-weighted average for all new and replacement fenestration
with a combined mandatory maximum of 0.58 U-factor as per §150.0(q)2; or
3. Must meet the Exception 1 to §150.0(q)1 for up to 10 ft2 or 0.5 percent of CFA,
whichever is greater.
Example 9-15
Question:
For additions and alterations that include a greenhouse window (also known as garden
window), how do I measure the fenestration area? What U-factor and SHGC
requirements apply to a greenhouse window?
Answer:
The area of a greenhouse windows is the rough opening in the wall.
The default U-factor for greenhouse windows does not meet the mandatory maximum
fenestration U-factor of 0.58 (there is no mandatory SHGC requirement). A metal-framed
greenhouse window from Table 110.6-A has a 1.40 U-factor and the default SHGC from
Table 110.6-B is 0.73 (for fixed, clear glass). By comparison, fenestration in prescriptive
additions has to meet the prescriptive U-factor of 0.30 for all climate zones and an SHGC
of 0.23 in all climate zones except 1, 3, 5, and 16, which have no SHGC requirement.
There are two options to meet the mandatory U-factor requirement: (1) up to 30 ft2 is
exempt (§150.0[q], Exception 2), and (2) a weighted-average U-factor with other
fenestration products is allowed.
For additions and alterations, Exception 1 to §150.2(b) allows any dual-pane greenhouse
window to meet the prescriptive U-factor requirement (separate from the mandatory
requirement). This makes it possible for greenhouse windows to comply as part of a
prescriptive alteration if there is no SHGC requirement (Climate Zones 1, 3, 5, and 16).
For climate zones with an SHGC requirement, if other windows are being altered, a
weight-average SHGC may be calculated, or performance compliance is an option for
achieving compliance. Compliance will likely depend on higher-than-average energy
efficiency for some other components of the project to offset the poor performance of the
greenhouse windows.
For other alternatives, see Chapter 3.
Example 9-16
Question:
An existing house in Climate Zone 12 has all single-pane windows. Most of the windows
(300 ft2 total) will be replaced within existing openings. One existing 30 ft2 window is
being replaced with a pair of 40 ft2 French doors. What requirements apply to this project?
Answer:
For prescriptive compliance, replacement fenestration (equal to or less than the area of
existing windows in each wall being altered) and added fenestration area must meet the
U-factor (0.30) and SHGC (0.23) in Table 150.1-A or B. There are only 10 ft2 of added
fenestration, so the project meets Exception 1 to §150.2(b)1A and is not required to meet
the prescriptive total glazing area requirement. All installed fenestration also must meet
applicable mandatory measures.
For performance compliance:
(a) Using the Existing + Alterations approach without third-party verification, replacement
fenestration that achieves the fenestration values in Table 150.2-C of the Energy
Standards is compared to those same values in the standard design. Replacement
fenestration that does not reach these values is penalized.
(b) Using the Existing + Alterations approach with third-party verification, replacement
fenestration that achieves the fenestration values in Table 150.2-C of the Energy
Standards is compared to Tables 110.6-A and 110.6-B default values for the existing
fenestration condition. Replacement fenestration that does not reach these values is
penalized.
Example 9-17
Question:
An existing building has all single-pane, metal-frame windows. A proposed remodel will
replace all the windows; no other work is being done as part of the remodel. What
applies?
Answer:
All replacement windows must meet the prescriptive requirements (§150.2[b]1B), and
new fenestration must meet applicable mandatory measures of §110.6, §110.7, and
§150.0.
If the prescriptive requirements cannot be met, the Existing + Alteration performance
method can be used.
Example 9-18
Question:
An existing building has all single-pane, wood-framed windows. In addition to replacing
more than 75 ft2 of window area, two double-pane, metal-frame greenhouse windows will
be added. How should the greenhouse windows be shown to comply using the
prescriptive standards?
Answer:
Example 9-19
Question:
Why is the low-sloped roofing products requirement listed for only Climate Zones 13 and
15?
Answer:
These two climate zones are the only climate zones that show energy cost-effectiveness
for having a low-slope roofing product (cool roof) requirement.
Example 9-20
Question:
Why are there so many exceptions to the addition and alterations section that can be
considered equivalents to roofing products?
Answer:
There are several energy features that are equivalent or having a greater impact on
energy savings than the roofing products. For example, older homes often have ducts
under the house, and newer homes may have materials slightly below current
requirements or equal to one of the items considered to be equivalent. If the ducts are
insulated and air leakage controlled to meet current requirements, energy savings are
expected to be at least equal the benefit of reflective roof coverings.
Example 9-21
Question:
What happens if I have a low-slope roof on most of the house but a steep-sloped roof on
another portion? Do I have to meet two criteria for the roofing products?
Answer:
Yes. If your house is in Climate Zone 13 or 15, you will need to meet the low-slope criteria
for the areas with low slope. The areas with the steep-slope roof will need to meet the
other cool roof criteria.
Example 9-22
Question:
I am replacing my existing wood shake roof with asphalt shingles. Would this be
considered a repair?
Answer:
No. A repair is defined as a reconstruction or renewal for maintenance of any component,
system, or equipment of an existing building. A replacement of any component (i.e., roof-
top), system, or equipment for which there are requirements in the Energy Standards is
considered an alteration and not a repair.
Example 9-23
Question:
If a radiant barrier is required for my addition, where does it need to be installed?
Answer:
The radiant barrier needs to be installed only on the underside of an attic roof assembly
and the gable wall ends associated with the addition.
Example 9-24
Question:
I am considering reroofing my house. Under what conditions will I be required to put on a
cool roof?
Answer:
Cool roof requirements are triggered when 50 percent or more of the roof area is being
replaced. Prescriptive requirements are waived if one of the exceptions to §150.2(b)1H
below applies:
Prescriptive Exceptions for Steep-Sloped Roofs
1. Air-space of 1.0 inch (25 mm) is provided between the top of the roof deck and the
bottom of the roofing product.
2. The installed roofing product has a profile ratio of rise to width of 1 to 5 for 50 percent
or greater of the width of the roofing product.
3. If existing ducts in the attic are insulated and sealed according to §150.1(c)9.
4. Buildings have at least R-38 ceiling insulation.
5. Buildings have an attic radiant barrier meeting the requirements of §150.1(c)2.
6. Buildings have no ducts in the attic.
7. Buildings are in Climate Zones 10-15, R-2 or greater insulation above the roof deck.
Prescriptive Exceptions for Low-Sloped Roofs
1. Buildings have no ducts in the attic.
Example 9-25
Question:
I am building a 450 ft² addition on my house. Do I have to meet cool roof requirements in
the prescriptive package?
Answer:
Yes. Once the addition exceeds 300 ft2, if using prescriptive compliance is in a climate
zone with a cool roof requirement, the roof must meet the requirements for the type of
roof slope. To avoid the cool roof requirements for this addition, you may use the
performance approach and trade-off against other energy efficiency features of the
addition alone or the existing building by using the Existing + Addition + Alterations
approach.
4. In Climate Zones 1-15, a single heat pump water heater, (1) located in an
unconditioned space like the garage or in conditioned space, (2) placed on an
incompressible (rigid) surface that is insulated to a minimum R-10, and (3)
installed with a communication interface (demand control device) meeting
§110.12(a).
If a recirculation system is installed, then it must be a demand recirculation system
with a manual on/off control to meet the prescriptive requirements.
Example 9-26
Question:
I want to install an additional water heater to a single-family home with an existing natural
gas water heater. Does this comply?
Answer:
It depends on the type of water heater. An instantaneous gas or propane water heater
complies with §150.2(a)1D. For prescriptive compliance, the same options allowed for
new construction are allowed for an addition (See Chapter 5). Otherwise performance
compliance may be used to demonstrate compliance.
Example 9-27
Question:
An existing 1,500 ft² single-family home is getting a 500 ft² addition. A new 50-gallon gas
water heater will replace the existing water heating system. How do the water heating
requirements apply?
Answer:
Because this is an alteration or replacement (§150.2[b]1H) of an existing water heating
system, this proposed replacement meets the requirement of §150.2(b)1Hiiia.
Example 9-28
Question:
An existing 2,000 ft² single-family house has one 50-gallon gas water heater, and a 600
ft² addition with a new instantaneous gas water heater is proposed. How does this
comply?
Answer:
When there is an increase in the number of water heaters with an addition, the Energy
Standards allow addition-alone compliance in certain circumstances. An instantaneous
gas water heater is one of those circumstances. Compliance with applicable mandatory
requirements is also needed.
The alternative to show compliance is by using the existing-plus-addition or whole-
building compliance.
Example 9-29
Question:
An existing single-family home with one electric water heater has a 500 ft² addition with a
30-gallon electric water heater proposed. Does this comply with prescriptive addition
requirements?
Answer:
No. When there is an increase in the number of water heaters with an addition, the
prescriptive compliance option is to meet the same requirements as for new construction.
The only electric option is a heat pump water heater. (See §150.1[c]8iv or v for a full list of
requirements, or Chapter 5 of this manual.)
Performance compliance may be possible. There is a significant penalty for electric
resistance water heating.
When more than 40 linear feet of ducts are installed in conditioned space, the ducts
must be insulated to the minimum mandatory insulation level of R-4.2 and be verified
to be in conditioned space by both visual verification and diagnostic testing in
accordance to RA3.1.4.3.8.
D. Duct Sealing
Duct systems meet duct sealing requirements found in Table RA3.1-2.
A new duct system may include an existing air handler, which leaks substantially
more than new equipment. If the 5 percent leakage rate criteria cannot be met, a
smoke test should be performed to verify that the excess leakage is non-accessible
and not from other accessible portions of the duct system. The protocol for the
smoke test for accessible-duct sealing is given in RA3.1.4.3.7.
If 40 feet of duct are being added or replaced, this work alone can trigger the
requirement for duct sealing and field verification. The system would have to meet
one of the leakage criteria for “altered existing systems” cases in Table RA3.1-2.
All climate zones require that existing duct systems must be sealed by the installer
and verified by a HERS Rater when portions of the heating and cooling system are
altered.
When an air handler is installed or replaced, ducts must be sealed (as described
below) under any of the following conditions:
1. An outdoor condensing unit of a split system air conditioner or heat pump is
installed or replaced.
2. A packaged system is completely replaced.
3. A cooling or heating coil is installed or replaced.
4. More than 40 feet of new or replacement ducts are installed.
If a residence has more than one duct system, only the ducts connected to the
altered equipment need to be sealed and verified.
There are three options for showing compliance for existing duct systems listed
below. The HERS Rater or installing contractor must at least attempt compliance
with the first option (15 percent leakage); then any of the other options can be used:
1. Total leakage is less than 15 percent of nominal system fan airflow
(RA3.1.4.3.1).
2. Leakage to the outside is less than 10 percent of system fan airflow
(RA3.1.4.3.4).
3. If the first option (15 percent) leakage target cannot be met, then compliance
can be achieved by sealing all accessible leaks verified by a HERS Rater
inspection. When using this option, sampling is not allowed (RA3.1.4.3.5-7).
• HERS field verification is required for all options listed above. For Options 1, and
2, verification can be accomplished through sampling as described in Sampling
for Additions or Alterations below. For Option 3, sampling is not allowed; a
certified HERS Rater must do the visual inspection and the smoke test on every
house.
• Since test equipment must be set up for Option 1, it may be most efficient to test
and record the results and then attempt to meet each option sequentially until
compliance is achieved.
• There are a few cases where duct sealing and duct leakage verification are not
required. These exceptions include:
o Ducts that have already been sealed, tested, and certified by a HERS
Rater.
o Duct systems with less than 40 feet of duct.
o Duct systems that are insulated or sealed with asbestos.
If altered ducts, heating or cooling equipment, or plenums are in a garage, the duct
sealing requirements (not limited to 40 feet of new duct) are one of the following:
E. Accessible Ducts
Some judgment is required in determining if ducts are accessible. The local code
enforcement agency will have the final say when it is not immediately obvious.
F. Refrigerant Charge Verification
In Climate Zones 2 and 8 through 15, when a refrigerant-containing component of an
air conditioner or heat pump is replaced or installed in an existing building,
Example 9-30
Question:
Do I have to seal the ducts if I replace the outdoor units in my house without changing the
indoor unit?
Answer:
Yes. Replacing the outdoor unit (or indoor unit) by itself will trigger the duct sealing and
verification requirement. The alteration requirements differ from new construction
requirements. (See §150.2[b]1Ei through iii for the requirements and exceptions.)
Example 9-31
Question:
I have an existing electric furnace and I’m adding a new bedroom. Can I extend the
existing ducts to the new room and use the existing furnace?
Answer:
Yes. If ducts are extended from an existing space-conditioning system, §150.2(b)1Diib
includes three options for showing prescriptive compliance when more than 40 feet of
new duct work is installed. The existing furnace must have adequate heating capacity to
meet California Building Code requirements for the additional space.
Example 9-32
Question:
I am adding a bedroom to a house that has a central forced-air natural gas furnace. I
would like to heat the room with an electric resistance baseboard heater rather than
extend the existing ductwork to reach the new space. Is this allowed?
Answer:
Not using prescriptive compliance. This is only possible if using performance compliance
and the relatively high energy consumption of the electric resistance heater is made up by
reductions from other energy efficiency measures in the addition or in an accompanying
alteration.
Note: If there are more than 40 linear feet of added ducts, the ducts must be sealed,
tested, and verified as sealed by a HERS Rater.
Example 9-33
Question:
My central gas furnace stopped working. If I get a new efficient unit rather than repair the
existing one, what are the requirements?
Answer:
Mandatory requirements apply to the components being replaced. The furnace must meet
minimum efficiency requirements, but all systems sold in California should already meet
the minimum efficiency requirements. If the new system includes mechanical cooling, and
the existing thermostat is not a setback thermostat, it must be replaced with a setback
thermostat (§150.2[b]1Fi).
All new ducts must meet insulation and construction requirements. All existing and new
ducts must be sealed and HERS-verified, as specified §150.2(b)1E.
Prescriptively, the new heating unit must be natural gas or a heat pump. A CF1R-ALT-02
or 03 form can be completed by you or your mechanical contractor. If HERS requirements
apply this is done at the HERS Provider’s web-site.
Example 9-34
Question:
As part of an upgrade in an existing house, one of the ducts is being replaced because of
deterioration of the insulation. What requirements apply to the replacement duct?
Answer:
This is an alteration to the space-conditioning system; therefore, the mandatory measures
for ducts apply. If more than 40 feet of the duct is altered, the requirements of
§150.2(b)1D trigger diagnostic testing and HERS verification of the duct system.
Example 9-35
Question:
Example 9-36
Question:
What is meant by the term "air handler"?
Answer:
The term "air handler" is used to identify the system component that provides the central
system forced-air movement for the ducted heating or cooling space-conditioning system.
The term "air handler" may be properly used to identify various types of central system
forced-air-moving components that must meet the functional requirements for different
types of space-conditioning systems. For instance, a "gas furnace" air handler includes a
gas combustion heat exchanger and the central system fan, but does not include a direct
expansion (DX) cooling coil; an "electric furnace" air handler has electric heating coils and
the central system fan, but does not include a DX cooling coil; a "fan-coil unit" air handler
for a split system heat pump has a DX cooling/heating coil and a central system fan; a
“hydronic heat pump” air handler includes the air-side DX coil, compressor, water-cooled
condenser, and the central system fan. There are other air handler configuration
variations as well.
Example 9-37
Question:
I have a residential building that was constructed in the 1920s. It has a freestanding gas
furnace, and I want to change it to an electric wall heater. Is this permitted?
Answer:
No. Section 150.2(b)1Cii states that the new space-conditioning system be limited to
natural gas, liquefied petroleum gas, or the existing fuel type. The only electric option is a
heat pump.
Example 9-38
Question:
Example 9-39
Question:
In the kitchen above, I am replacing one of the recessed downlight luminaires. Must the
new downlight luminaire be high-efficacy?
Answer:
Yes, newly installed luminaires must be high-efficacy and meet the requirements in
§150.0(k). Screw-based sockets are not permitted for newly installed recessed downlight
luminaires in ceilings.
Example 9-40
Question:
I am completely remodeling my kitchen and putting in an entirely new lighting system.
How do the Energy Standards apply to this case?
Answer:
When an entirely new lighting system is installed, it is treated like new construction. The
new lighting system must comply with all the mandatory lighting requirements in
§150.0(k)1 and (k)2.
Example 9-41
Question:
I am replacing my incandescent bath bar in the bathroom. Must the new luminaire meet
the Energy Standards requirements?
Answer:
The new luminaire is the altered component and must meet requirements in §150.0(k),
including the high-efficacy luminaire and lighting control requirements. The 2019 Energy
Standards now allow the installation of Joint Appendix JA8-compliant lamps in screw-
based fixtures as a way to comply with the high-efficacy lighting requirements as long as
the luminaire is not a recessed downlight in ceiling. See Sections 6.2 and 6.3 of this
manual for details.
The table below summarizes the basic rules for modeling a low-rise residential building
using the existing + addition + alterations performance approach. For more detailed
information, see Section 9.4 or the software user manual.
Table 9-13: Modeling Rules for Existing + Addition + Alterations
Type of Component or System Standard Design Without Third- Standard Design With Third-
Modeled Party Verification of Existing Party Verification of Existing
Conditions Conditions
EXISTING – Components or Model each component or system Model each component or system
systems to remain unchanged as “Existing” as “Existing”
NEW—Components or systems
Model each component or system Model each component or system
being added (did not previously
as “New” as “New”
exist)
REMOVED—Components or
These components omitted from These components omitted from
systems being removed and not
the model the model
replaced
Example 9-42
Question:
A 1,600 ft² house built in 1980 in Climate Zone 12 is being renovated as follows:
1. A 500 ft² room will be added, including 120 ft² of new windows.
2. A 200 ft² wall and 100 ft² of old window will be removed.
3. Attic insulation in the existing house will be upgraded to R-38.
4. The addition will be connected to the existing HVAC and duct system.
If the performance approach is used to demonstrate compliance, how does the
compliance software establish the standard and proposed designs?
Answer:
Table 9-13 summarizes the Modeling Rules for Existing + Addition + Alterations, which
must be followed to have the compliance software accurately set the standard design and
model the proposed design. Under the 2019 standards performance rules, the removed
wall and window are not included in the energy model and have no effect. The standard
design for the added conditioned floor area is set using the prescriptive requirements of
§150.1(c). If the existing duct system is extended by 40 linear feet or more, the standard
design assumes duct alterations with 15 percent duct leakage requirements.
The standard design assumptions for the existing house follow the rules summarized in
§150.2(b)2 and Table 150.2-C based on whether there is third-party verification of the
existing conditions. Without third-party verification, upgraded energy components in the
existing house are modeled as fixed assumptions that represent reasonably expected
levels of efficiency for each altered component. If optional third-party verification is
selected for the components in the existing house that are to be upgraded, the standard
design assumes the existing conditions specified by the software user. These features
must be verified before construction begins and before application of the permit.
The standard design assumptions for the 500 ft2 addition is based on the features of
§150.1(c), Table 150.1-A.
The existing space conditioning system, as defined by the software user, is modeled in
both the standard and proposed design. The duct system is made up of new ducts as an
extension of the existing ducts.
Example 9-43
Question:
For the 1980 house in the examples above, an operable single-pane metal window is
replaced with a 0.55 U-factor window. Does this alteration result in a compliance credit?
How about the case where the existing window is replaced with a window that has a U-
factor of 0.35?
Answer:
As explained in Example 9-42, altered components that receive compliance credit must
exceed the requirements of Table 150.2-C. Windows in the addition must have a U-factor
of ≤ 0.30 and SHGC ≤ 0.23 to receive credit (Climate Zone 12). Replacement windows in
the existing house must have a U-factor of ≤ 0.40 and SHGC ≤ 0.35 to receive credit.
A window replacement with a 0.55 U-factor will receive a penalty compared with a 0.40 U-
factor standard design assumption for that window. Without third-party verification of
existing conditions, a 0.35 U-factor window replacement will receive a credit compared
with a 0.40 U-factor standard design assumption for that window. With third-party
verification of existing conditions, either window replacement will receive a credit as
compared with a 1.28 U-factor standard design assumption for an operable single-pane
metal existing window.
Example 9-44
Question:
An addition of 590 ft² is being added to a 2,389 ft² single-family house. How do you
demonstrate compliance using the Existing + Addition + Alterations method?
Answer:
The steps are the following:
1. Collect accurate envelope and mechanical information about the addition and existing
building from scaled drawings (plans, sections, and elevations); determine what
components, (HVAC, ducts, water heating, etc.) are being altered as part of the permitted
scope of work.
2. Enter the information about the addition and the existing building into the compliance
software program, identifying each modeled feature as “existing,” “altered,” or “new,” as
summarized in Table 9-13. Proper identification of these inputs is critical to correctly and
accurately determining compliance.
3. Run the compliance software to determine if the proposed building TDV energy is
equal or less than the standard design TDV energy.
4. If the project does not comply, modify the energy features of the addition and/or the
existing building until compliance is achieved.
5. If features of the existing building are being modified, consider the option of verifying
existing conditions. When using this option, this inspection by a HERS Rater must be
completed before construction begins and before the project registration (Step 6) can be
completed.
6. All projects that include energy measures requiring HERS field verification and
diagnostic testing--which represent almost all buildings under the 2019 Energy
Standards--must be registered online with a HERS Provider as explained in Section 2.3 in
order to obtain a valid CF1R to apply for a permit.
7. Print the registered CF1R for permit application submittal.
Example 9-45
Question:
When using the existing-plus-addition performance approach, do the mandatory
requirements, including airflow, watt draw measurement, etc. (§150.0[m]13) need to be
met for space-conditioning equipment serving an addition? What about the prescriptive
requirement for refrigerant charge verification (or one of the alternatives to §150.1[c]7)?
Answer:
Example 9-46
Question:
When using the E+A+A performance method, can compliance credit be gained by sealing
the existing ducts when it was not required for prescriptive compliance?
Answer:
No. Once the status of the ducts is “altered” the standard design assumes the duct
sealing is required.
Example 9-47
Question:
When using the existing-plus-addition performance compliance method, can credit be
gained by installing a radiant barrier in the existing house attic?
Answer:
No. Once the attic/roof is “altered” the standard design becomes equivalent to Table
150.1-A or B
Example 9-48
Question:
I am adding a room to and altering an existing building in Climate Zone 12. I am
upgrading an existing single-pane clear glass window with a U-factor of 1.2 and SHGC of
1.0 to a dual-pane window with a U-factor of 0.50 and SHGC of 0.45. Do I receive credit
toward the addition compliance for installing this window?
Answer:
Example 9-49
Question:
I am planning to install R-19 insulation in the attic of an existing house built in 1970. Can I
use this added insulation as a credit for trading with the energy features of an addition?
Answer:
No. When insulation is added to an attic, it must comply with §150.0(a), which sets a
mandatory minimum for attic insulation of R-22. Since R-22 is a mandatory minimum a
lower insulation cannot be installed.
Example 9-50
Question:
I am planning to install R-25 insulation in an uninsulated vaulted ceiling without an attic
space in an existing house built in 1970. Can I use this added insulation as a credit for
trading with the energy features of an addition?
Answer:
Only if you choose verified existing conditions (see Example 9-44) and even then it will
depend on the climate zone. Because the prescriptive approach has no provision for
vaulted roofs, once the roof is altered, the standard design becomes an attic/roof meeting
Option B. If Option B has no below roof deck insulation, it is possible to get credit for