06 - ProcessGroup - Sample Questions
06 - ProcessGroup - Sample Questions
06 - ProcessGroup - Sample Questions
? Your company has just presented its new five-year strategic plan.
You have received a new product request from a customer that is
in line with the previous five-year strategic plan, but it does not
meet the objectives of the new plan. The product description
seems to have a valid business driver and to be a straightforward
development effort. As project manager, what is the BEST course
of action?
I 2
2
I 4
3
I 1
4
? Your customer has asked for a 2000 call capacity for the new call
center project. However, one of your company's technical experts
believes a 3000 call capacity can be reached. Another thinks that
based on the technical needs of the customer, the capacity needs
to be only 1500 calls. What is the BEST thing to do?
I 1
5
I 4
6
P 2
7
P 3
8
? A project manager knows that she can delay the start of certain
activities within the project schedule to coincide with the mitigation
of a known risk. She knows exactly the mitigating task & duration
needed, should the risk event occur. She is confident that the finish
date will not be impacted by the time delay. Which of the following
aspects of schedule development has the project manager used in
this situation?
P 3
9
? While resource planning for your project, you visited the functional
manager of engineering many times but she refused to supply
resources for the project. First, the excuse was that her
department was too busy. The next time, the department was
undergoing a reorganization. This is causing your project to slip
the schedule. The lack of which of the following is the MOST
probable reason for her lack of support?
A. Project plan
B. Resource assignment matrix
C. WBS
D. Project charter
P 4
10
? Your boss has asked you for a cost estimate for the project, but it
is early in the project creation process and there is very little
project information. In this circumstance, what is the BEST way to
estimate this project?
A. Do a parametric estimate
B. Ask the team for estimates of each task
C. Define the complete WBS
D. Calculate an estimate using a computer based model
P 1
11
A. Bottom up
B. Analogous
C. Parametric
D. Top-down
P 1
12
A. Mitigation
B. Acceptance
C. Transference
D. Avoidance
P 2
13
E 3
14
A. Quality analysis
B. Quality assurance
C. Quality control
D. Quality planning
E 2
15
E 3
16
E 3
18
C 1
19
C 4
20
C 3
21
A. SQC Report
B. Fishbone diagram
C. Control chart
D. Pareto chart
C 2
22
Cl 3
23
Cl 2
24
? Your manager gives you a scope of work and asks you to begin
working immediately and provide her with a schedule. What
should you do FIRST?
P 2
25
Cl 1
26
A. Crashing
B. PERT
C. Performance reporting
D. Cost estimating
C 3