Apartel Estimates
Apartel Estimates
Apartel Estimates
B
SUBJECT : COST BREAKDOWN ESTIMATES
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling 33.00 cu.m. 500.00
Grading and levelling works 54.00 sq.m. 250.00
Soil Poisoning 54.00 sq.m. 120.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 33.00 cu.m. 250.00
Storm Drainage Lines 12.00 cu.m. 250.00
Septic Vaults & Cistern 40.00 cu.m. 250.00
Catch Basins 3.00 cu.m. 250.00
SUB-TOTAL 2: EXCAVATION WORKS
3. STRUCTURAL WORKS
3 Column Footings / Columns
Formworks 120.00 sq.m. 420.00
Rebars
16mm dia. X 6m ### kgs. 45.00
10mm dia. X 6m 930.00 kgs. 42.00
Concrete
3/4", 28 days 15.00 cu.m. 5,066.00
G.I. Tie Wires 20.00 kgs. 80.00
3 Walls Footings
Formworks 24.00 sq.m. 420.00
Rebars
10mm dia. X 6m 426.00 kgs. 42.00
12mm dia. X 6m 500.00 kgs. 44.00
Concrete
G-1, 28 days 8.00 cu.m. 5,066.00
G.I. Tie Wires 10.00 kgs. 80.00
5 Tie Beams
Formworks 25.00 sq.m. 420.00
Rebars
16mm dia. X 6m 568.00 kgs. 55.00
10mm dia. X 6m ### kgs. 42.00
Concrete
3/4", 3000 psi 28 days 8.00 cu.m. 5,066.00
G.I. Tie Wires 15.00 kgs. 75.00
3 Suspended Slabs
Formworks 60.00 sq.m. 420.00
Steel deck 60.00 sq.m. 980.00
Rebars
12mm dia x 6m 320.00 kgs. 44.00
10mm dia. X 6m 568.00 kgs. 42.00
Concrete
3/4" 28days 10.00 cu.m. 5,066.00
G.I. Tie Wire 10.00 kgs. 75.00
3 On-Grade Slabs
Formworks 55.00 sq.m 420.00
Rebars
10mm dia. X 6m 468.00 kgs. 42.00
Concrete
G-1, 28 days 11.00 cu.m. 4,982.00
G.I. Tie Wires . 5.00 kgs. 75.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 450.00 sq.m. 563.00
Lintel Beams 20.00 l.m. 390.00
Stiffener Columns 9.00 l.m. 390.00
Plastering of structural surface 36.00 sq.m. 200.00
Plastering of CHB Wall 900.00 sq.m. 130.00
SUB-TOTAL 4: MASONRY WORKS
WINDOWS
W1, 1.2 x 1.2msliding analok glass window brown 6.00 set 11,000.00
frame and glass
W2, 0.4x1.20m awning Window , brown 8.00 sets 6,500.00
frame and glass
W3,0.60m x 0.60m Sliding Glass Window, Brown 6.00 sets 4,200.00
frame and glass
SUB-TOTAL 7 :DOORS AND WINDOWS
GRAND TOTAL
LABOR COST 30%
TOTAL COST
Prepared by:
AMOUNT
5,000.00
4,800.00
4,160.00
10,000.00
18,960.00
16,500.00
13,500.00
6,480.00
36,480.00
8,250.00
3,000.00
10,000.00
750.00
22,000.00
50,400.00
51,165.00
39,060.00
75,990.00
1,600.00
-
-
10,080.00
-
17,892.00
22,000.00
-
40,528.00
800.00
-
-
67,200.00
102,330.00
45,696.00
81,056.00
2,720.00
-
10,500.00
31,240.00
42,000.00
40,528.00
1,125.00
25,200.00
58,800.00
14,080.00
23,856.00
50,660.00
750.00
23,100.00
19,656.00
54,802.00
375.00
4,200.00
13,905.00
21,648.00
23,058.00
44,838.00
900.00
1,113,738.00
253,350.00
7,800.00
3,510.00
7,200.00
117,000.00
388,860.00
28,600.00
38,220.00
10,530.00
630.00
1,980.00
468.00
2,340.00
1,170.00
2,912.00
702.00
2,826.00
645.00
91,023.00
28,050.00
2,548.00
2,912.00
15,600.00
1,508.00
323.00
525.00
4,200.00
1,092.00
840.00
57,598.00
49,200.00
10,800.00
66,000.00
52,000.00
25,200.00
203,200.00
40,150.00
19,250.00
7,500.00
115,200.00
3,200.00
14,400.00
7,500.00
3,000.00
210,200.00
72,000.00
72,000.00
57,600.00
7,200.00
57,600.00
13,200.00
6,000.00
285,600.00
26,390.00
26,390.00
11,407.50
5,985.00
70,172.50
9,295.00
3,328.00
780.00
780.00
572.00
429.00
1,248.00
1,248.00
585.00
175.50
975.00
780.00
468.00
1,456.00
416.00
253.50
175.50
702.00
-
60,000.00
6,760.00
312.00
624.00
1,248.00
208.00
728.00
338.00
702.00
4,992.00
7,605.00
1,144.00
1,144.00
2,496.00
1,560.00
1,560.00
3,146.00
936.00
936.00
1,040.00
1,040.00
1,560.00
585.00
1,950.00
197.60
296.40
257.40
19,200.00
39,000.00
13,800.00
5,400.00
6,000.00
210,431.90
19,500.00
6,675.00
3,375.00
3,750.00
4,125.00
1,575.00
1,575.00
675.00
2,000.00
4,062.50
1,687.50
1,050.00
1,132.50
310.00
300.00
2,400.00
2,860.00
13,500.00
15,200.00
148.20
1,092.00
1,404.00
5,408.00
1,248.00
11,700.00
106,752.70
Php2,976,366.10
Php892,909.83
3,869,275.93
OCTOBER 10,2023
B 73.79
SUBJECT : COST BREAKDOWN ESTIMATES Err:520
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling 12.00 cu.m. 250.00 3,000.00
Grading and levelling works 75.00 sq.m. 250.00 18,750.00
Soil Poisoning 80.00 sq.m. 120.00 9,600.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS 31,350.00
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 20.00 cu.m. 250.00 5,000.00
Storm Drainage Lines 12.00 cu.m. 250.00 3,000.00
SUB-TOTAL 2: EXCAVATION WORKS 8,000.00
3. STRUCTURAL WORKS
3.1 Column Footings / Columns
Formworks 16.00 sq.m. 650.00 10,400.00
Rebars
16mm dia. X 6m 40.00 lengths 757.00 30,280.00
10mm dia. X 6m 28.00 lengths 298.00 8,344.00
Concrete
Portland Cement 15.00 bags 225.00 3,375.00
Fine Sand 1.00 cum 1,200.00 1,200.00
gravel 3/4" 2.00 cum 1,800.00 3,600.00
G.I. Tie Wires 5.00 kgs. 80.00 400.00
-
3.2 Walls Footings -
Rebars -
10mm dia. X 6m 15.00 lengths 289.00 4,335.00
Concrete -
Portland cement 14.00 bags 225.00 3,150.00
Fine Sand 1.00 cum 1,200.00 1,200.00
3/4" Gravel 2.00 cum 1,800.00 3,600.00
-
3.3 Beams / Roof Beams -
Formworks 67.00 sq.m. 650.00 43,550.00
Rebars
16mm dia. X 6m 35.00 lengths 757.00 26,495.00
10mm dia. X 6m 60.00 lengths 298.00 17,880.00
Concrete
Portland cement 53.00 bags 225.00 11,925.00
Fine Sand 3.00 cum 1,200.00 3,600.00
3/4" Gravel 6.00 cum 1,800.00 10,800.00
5. ROOF FRAMING
Assorted Angle Bars
2"x2"x1/4" 21.00 lgts. 1,572.00 33,012.00
2.5x2.5x1/4" 24.00 lgts. 1,620.00 38,880.00
C-Purlins, 100x50x12.5x1.9mm 19.00 lgts. 1,030.00 19,570.00
10mm dia. Sag Rod 5.00 lgts. 289.00 1,445.00
12mm dia. Cross Bracings 4.00 lgts. 330.00 1,320.00
12mm dia. Turn Buckle 8.00 pcs. 58.50 468.00
Welding Rod 5.00 box 246.00 1,230.00
Cut-off Blade 2.00 pcs. 585.00 1,170.00
Grinding Disk 10.00 pcs. 364.00 3,640.00
Sand Paper 100 8.00 shts. 58.50 468.00
Red Oxide Metal Primer 2.00 gals. 845.00 1,690.00
Paint Thinner 2.00 gals. 546.00 1,092.00
SUB-TOTAL 5 :ROOF FRAMING 103,985.00
6. ROOFING WORKS
ga. 26Prepainted Rib-type Roofing 73.00 sq.m. 780.00 56,940.00
Wall end flushing 12.00 l.m. 182.00 2,184.00
Roof Gutter Pre fabricated GA. 14 12.60 cum 800.00 10,080.00
Teck Screw, 2 1/2" 450.00 pcs. 2.60 1,170.00
Blind Rivets, 1/8" x 1/2" 1.00 box 280.00 280.00
Ga. 16 G.I. Tie Wires 3.00 kgs. 75.00 225.00
10mm PE Foam with one side Alum. 1.00 roll 3,200.00 3,200.00
Touch-up Paint 3.00 cans 364.00 1,092.00
Silicone Sealant 2.00 bottles 320.00 640.00
SUB-TOTAL 6 :ROOFING WORKS 75,811.00
WINDOWS
W1,0.40 x 1.5 awning and fixed glass, Brown 10.00 set 4,200.00 42,000.00
frame and glass
W2, 0.4 x.6m awning Window , brown 1.00 set 4,500.00 4,500.00
frame and glass
SUB-TOTAL 7 :DOORS AND WINDOWS 149,900.00
9. TILEWORKS
600 x 600 mm non skid floor tiles 212.00 pcs 200.00 42,400.00
Toilet Wall, 60x60cm glazed wall tiles 12.00 pcs 200.00 2,400.00
Tile Adhesive 15.00 bags 520.00 7,800.00
Portland cement 25.00 bags 223.00 5,575.00
Fine sand 3.50 cum 1,200.00 4,200.00
Tile Trims 35.00 l.m. 50.00 1,750.00
SUB-TOTAL 9 :TILE WORKS 70,053.00
PLUMBING STRUCTURES
Grease Trap 1.00 set 7,000.00 7,000.00
B
SUBJECT : COST BREAKDOWN ESTIMATES
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling 200.00 cu.m. 500.00
Grading and levelling works 200.00 sq.m. 250.00
Soil Poisoning 200.00 sq.m. 120.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 30.00 cu.m. 250.00
Storm Drainage Lines 12.00 cu.m. 250.00
Septic Vaults & Cistern 40.00 cu.m. 250.00
Catch Basins 3.00 cu.m. 250.00
SUB-TOTAL 2: EXCAVATION WORKS
3. STRUCTURAL WORKS
3 Column Footings / Columns
Formworks 218.00 sq.m. 420.00
Rebars
16mm dia. X 6m 3,233.00 kgs. 45.00
10mm dia. X 6m 1,111.00 kgs. 42.00
Concrete
G-1, 28 days 3.00 cu.m. 4,982.00
3/4", 28 days 19.00 cu.m. 4,982.00
G.I. Tie Wires 16.00 kgs. 80.00
3 Walls Footings
Formworks 30.00 sq.m. 420.00
Rebars
10mm dia. X 6m 515.00 kgs. 42.00
12mm dia. X 6m 455.00 kgs. 44.00
Concrete
G-1, 28 days 30.00 cu.m. 4,982.00
G.I. Tie Wires 15.00 kgs. 80.00
5 Tie Beams
Formworks 40.00 sq.m. 420.00
Rebars
16mm dia. X 6m 384.00 kgs. 55.00
10mm dia. X 6m 3,182.00 kgs. 42.00
Concrete
3/4", 3000 psi 28 days 30.00 cu.m. 4,982.00
G.I. Tie Wires 23.00 kgs. 75.00
3 Suspended Slabs
Formworks 145.00 lot 420.00
Steel deck 145.00 sq.m. 520.00
Rebars
12mm dia x 6m 1,040.00 kgs. 44.00
10mm dia. X 6m 1,088.00 kgs. 42.00
Concrete
3/4" 28days 22.00 cu.m. 4,982.00
G.I. Tie Wire 25.00 kgs. 75.00
3 On-Grade Slabs
Formworks 140.00 sq.m 420.00
Rebars
10mm dia. X 6m 800.00 kgs. 42.00
Concrete
G-1, 28 days 22.00 cu.m. 4,982.00
G.I. Tie Wires . 15.00 kgs. 75.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 980.00 sq.m. 563.00
Lintel Beams 30.00 l.m. 390.00
Stiffener Columns 9.00 l.m. 390.00
Plastering of structural surface 53.00 sq.m. 200.00
Plastering of CHB Wall 980.00 sq.m. 130.00
SUB-TOTAL 4: MASONRY WORKS
WINDOWS
W1,2.6x1.5 awning and fixed glass, Brown 1.00 set 15,000.00
frame and glass
W2, 0.6x1.20m awning Window , brown 5.00 sets 3,500.00
frame and glass
W3,0.40mx1.50m Sliding Glass Window, Brown 2.00 sets 4,200.00
frame and glass
SUB-TOTAL 7 :DOORS AND WINDOWS
PLUMBING STRUCTURES
Grease Trap 1.00 set 4,500.00
Catch Basin 4.00 sets 810.00
Water tank 350 1.00 set 15,000.00
GRAND TOTAL
LABOR COST 20%
Prepared by:
GENEVEVE L. COLASITO
ARCHITECT
73.79
Err:520
AMOUNT
3,000.00
3,600.00
3,600.00
10,000.00
17,200.00
100,000.00
50,000.00
24,000.00
174,000.00
7,500.00
3,000.00
10,000.00
750.00
21,250.00
91,560.00
145,485.00
46,662.00
14,946.00
94,658.00
1,280.00
-
-
12,600.00
- 0.35 0.35 0.1225
21,630.00 0.12 52.00 6.37
20,020.00
- 42.00 3.72 156.24
149,460.00 0
1,200.00 0
-
-
16,800.00
148,635.00
519,918.00
149,460.00
1,875.00
-
16,800.00
21,120.00
133,644.00
149,460.00
1,725.00
60,900.00
75,400.00
45,760.00
45,696.00
109,604.00
1,875.00
58,800.00
33,600.00
109,604.00 15.50
1,125.00 38.00
53.50
4,200.00
13,905.00
21,648.00
23,058.00
44,838.00
900.00
2,409,851.00
551,740.00
11,700.00
3,510.00
10,600.00
127,400.00
704,950.00
7,150.00
7,644.00
2,145.00
6,435.00
630.00
1,980.00
468.00
2,340.00
1,170.00
1,456.00
468.00
3,380.00
1,092.00
36,358.00 576 2 1152
7.2 4.5 32.4
40,700.00 32.4 2 64.8
4,550.00 64.8 25000 1620000
5,200.00 32.4 2 64.8
9,280.00
1,508.00
323.00
525.00
3,300.00
1,092.00
840.00
67,318.00
66,000.00
12,600.00
3,800.00
3,600.00
15,000.00
17,500.00
8,400.00
126,900.00
32,850.00
15,750.00
3,500.00
21,600.00
3,200.00
22,500.00
1,200.00
60
100,600.00 46
36
36 80 25000
178 7.2 6
25,500.00 60 7.4
25,500.00 356
20,400.00
7,200.00
20,400.00
5,280.00
6,000.00
110,280.00 9. TILEWORKS
Ground floor tiles (60x60mm)
Second floor tiles (60 x 60)
Toilet Floor, 60x20cm non-skid floor tiles
17,400.00 Toilet Wall, 60x60cm glazed wall tiles
10,150.00 Tile Trims
SUB-TOTAL 9 :TILE WORKS
6,142.50
5,985.00
39,677.50
9,295.00
3,328.00
780.00
780.00
572.00
429.00
1,248.00
1,248.00
585.00
175.50
975.00
780.00
468.00
1,456.00
416.00
253.50
175.50
702.00
-
35,000.00
6,760.00
312.00
624.00
1,248.00
208.00
728.00
338.00
702.00
4,992.00
7,605.00
1,144.00
1,144.00
2,496.00
1,560.00
1,560.00
3,146.00
936.00
936.00
1,040.00
1,040.00
1,560.00
585.00
1,950.00
197.60
296.40
257.40
4,500.00
3,240.00
15,000.00
3,200.00
7,400.00
2,300.00
900.00
1,100.00
1,100.00
1,500.00
142,271.90
3,250.00
1,112.50 APRIL 13,2022
1,125.00
1,875.00 PROJECT TITL : PROPOSED ONE STOREY RESIDENTIAL BUILDING
4,125.00 LOCATION :BRGY. HIGHWAY, ALABAMA , DULAG LEYTE
1,137.50
787.50
225.00 SUBJECT : BILL OF QUANTITIES
1,500.00
4,062.50 A. GENERAL REQUIREMENTS
1,687.50 MOBILIZATION
1,050.00 B. CONSTRUCTION REQUIREMENTS
1,132.50 1. SITE DEVELOPMENT PLAN WORKS
310.00 2. EXCAVATION WORKS
300.00 3. STRUCTURAL WORKS
2,400.00 4. MASONRY WORKS
5. ROOF FRAMING
6. ROOFING WORKS
2,860.00 7. DOORS AND WINDOWS
13,500.00 8. CARPENTRY WORKS(CEILING,TV RACK,)
15,200.00 9. TILEWORKS(LIVING,DINING,KITCHEN,T&B)
148.20 10. PAINTING WORKS
11. SPECIALTY WORKS
TERRACE,RAILINGS,MOULDING & EXTERIOR
728.00 DESIGN ACCESSORIES(STONES)
1,664.00 12. PUMBING WORKS
936.00 13. ELECTRICAL WORKS
546.00 14. SOIL POISONING,SOIL TREATMENT
2,496.00
832.00
13,000.00
77,990.20 PRESENTED BY:
Php4,189,996.60
Php837,999.32
ARCHITECT
5,027,995.92
5,027,995.92
2000000
43.2
2000043.2
60607.3697
33.00 sq.m. 1,200.00 39,600.00
44.00 sq.m. 1,200.00 52,800.00
32.00 sq.m. 1,200.00 38,400.00
24.00 sq.m. 1,200.00 28,800.00
35.00 l.m. 50.00 1,750.00
161,350.00
SIDENTIAL BUILDING
APPROVED:
OWNER
OCTOBER 10,2023
B 73.79
SUBJECT : COST BREAKDOWN ESTIMATES Err:520
B. CONSTRUCTION REQUIREMENTS
1. SITE DEVELOPMENT WORKS
Lot embankment/filling 32.00 cu.m. 250.00 8,000.00
Grading and levelling works 60.00 sq.m. 250.00 15,000.00
Soil Poisoning 50.00 sq.m. 120.00 6,000.00
SUB-TOTAL 1: SITE DEVELOPMENT WORKS 29,000.00
2. EXCAVATION WORKS
Building Column Footings / Walls Footings 45.00 cu.m. 250.00 11,250.00
Storm Drainage Lines 12.00 cu.m. 250.00 3,000.00
Septic Vaults & Cistern 12.00 cu.m. 250.00 3,000.00
Catch Basins 3.00 cu.m. 250.00 750.00
SUB-TOTAL 2: EXCAVATION WORKS 18,000.00
3. STRUCTURAL WORKS
3.1 Column Footings / Columns
Formworks 70.00 sq.m. 650.00 45,500.00
Rebars
16mm dia. X 6m 874.00 kgs. 55.00 48,070.00
10mm dia. X 6m 1,384.00 kgs. 42.00 58,128.00
Concrete
G-1, 28 days 3.00 cu.m. 4,393.00 13,179.00
3/4", 28 days 12.00 cu.m. 4,393.00 52,716.00
G.I. Tie Wires 25.00 kgs. 80.00 2,000.00
-
3.2 Walls Footings -
Formworks 36.00 sq.m. 650.00 23,400.00
Rebars -
10mm dia. X 6m 120.00 kgs. 42.00 5,040.00
Concrete -
G-1, 28 days 14.00 cu.m. 4,393.00 61,502.00
G.I. Tie Wires 15.00 kgs. 80.00 1,200.00
-
3.3 Beams / Roof Beams -
Formworks 114.00 sq.m. 650.00 74,100.00
Rebars
16mm dia. X 6m 889.00 kgs. 55.00 48,895.00
10mm dia. X 6m 828.00 kgs. 42.00 34,776.00
Concrete
3/4", 3000 psi 28 days 30.00 cu.m. 4,393.00 131,790.00
G.I. Tie Wires 25.00 kgs. 75.00 1,875.00
4. MASONRY WORKS
100mm thk. CHB Laying, incl. Rebars 160.00 sq.m. 685.00 109,600.00
Lintel Beams 15.50 l.m. 390.00 6,045.00
Stiffener Columns 9.00 l.m. 390.00 3,510.00
Plastering of structural surface 53.00 sq.m. 200.00 10,600.00
Plastering of CHB Wall 220.00 sq.m. 200.00 44,000.00
SUB-TOTAL 4: MASONRY WORKS 173,755.00
5. ROOF FRAMING
Assorted Angle Bars
2"x2"x3/16" 10.00 lgts. 715.00 7,150.00
1 1/2"x1 1/2"x3/16" 12.00 lgts. 637.00 7,644.00
1"x1"x3/16" 6.00 lgts. 357.50 2,145.00
C-Purlins, 50x100x1.0mm 11.00 lgts. 585.00 6,435.00
10mm dia. Sag Rod 15.00 kgs 42.00 630.00
12mm dia. Cross Bracings 25.00 kgs 44.00 1,100.00
12mm dia. Turn Buckle 8.00 pcs. 58.50 468.00
Welding Rod 5.00 box 246.00 1,230.00
Cut-off Blade 2.00 pcs. 585.00 1,170.00
Grinding Disk 4.00 pcs. 364.00 1,456.00
Sand Paper 100 8.00 shts. 58.50 468.00
Red Oxide Metal Primer 4.00 gals. 845.00 3,380.00
Paint Thinner 2.00 gals. 546.00 1,092.00
SUB-TOTAL 5 :ROOF FRAMING 34,368.00
6. ROOFING WORKS
ga. 26Prepainted Rib-type Roofing 44.00 sq.m. 550.00 24,200.00
Wall end flushing 12.00 l.m. 182.00 2,184.00
Wall Capping 33.00 l.m. 208.00 6,864.00
Roof Gutter concrete 6.00 cum 4,393.00 26,358.00
Teck Screw, 2 1/2" 580.00 pcs. 2.60 1,508.00
Blind Rivets, 1/8" x 1/2" 380.00 pcs. 0.85 323.00
Ga. 16 G.I. Tie Wires 7.00 kgs. 75.00 525.00
10mm PE Foam with one side Alum. 50.00 l.m. 60.00 3,000.00
Touch-up Paint 3.00 cans 364.00 1,092.00
Silicone Sealant 2.00 bottles 320.00 640.00
SUB-TOTAL 6 :ROOFING WORKS 66,694.00
WINDOWS
W1,2.6x1.5 awning and fixed glass, Brown 1.00 set 17,000.00 17,000.00
frame and glass
W2, 0.6x1.20m awning Window , brown 5.00 sets 4,500.00 22,500.00
frame and glass
W3,0.40mx1.50m awning Window, Brown 2.00 sets 4,200.00 8,400.00
frame and glass
SUB-TOTAL 7 :DOORS AND WINDOWS 133,900.00
PLUMBING STRUCTURES
Grease Trap 1.00 set 4,500.00 4,500.00
Catch Basin 4.00 sets 810.00 3,240.00