Cold Start-Up DCS Test
Cold Start-Up DCS Test
Cold Start-Up DCS Test
COURSE- RO PLANT
COLD START-UP TEST
NAME
JOB No.
Plant LOCATION
Final MARKS %
Page 1 of 6
Name
Line No.
Location
No. Subject X √
Electrical system Line-up
1 Transformer Cooling Fan into Auto
2 Transformer loop into Auto TR-C 110/13.8 KV
3 AUTOMATIC BUS TRANSFER 13.8 V
4 Bus bar SWGR C & D = 13.8 KV
5 Closing all the CB- Feeders 13.8 V
6 Transformer loop into Auto TR-C 13.8 /4.18 KV
7 Closing all the CB- Feeders- 480 V
8 AUTOMATIC BUS TRANSFER 480 V
9 AUTOMATIC BUS TRANSFER 4.18 KV
10 Closing all the CB- Feeders- 4,18 KV
Page 2 of 6
No. Subject X √
Page 3 of 6
Chemical Group system Line-up
Sodium Hypochlorite Dosing System
1 Tank Level INT IN
2 Back Flow Pump Stoke
3 Back Flow Pump Operation - Pump Selector to be ASL IN
4 Brine Trench Pump Stoke
5 Brine Trench Pump - Pump Selector to be ASL IN
6 LOOP PLATE MENUE – Activate system
Subject X √
Page 4 of 6
DMF system Line-up
1 Log to screen
2 Seawater Supply Flow Control
3 DMF activate all valve into Auto
4 DMF Back Wash Timer
5 DMF Back Wash Timer – Manual/ Auto - Mode
6 Air Scoring Blower system Line up
7 BW Pump ready
8 Back Wash Waste Ready
9 DMF - REGENERATION MODE monitoring
10 DMF - Out of service apply
11 Brine Transfer System to be in AUTO
12 Filtered water clear well level
13 Filtered water clear well Pump running
RO system - STARTUP
Pre-Requisites
1 Electrical Distribution System is in service
2 Service Air System is in service
3 Instrument Air System is in service
4 Cooling Water System is in service
5 Pretreatment System is in service
6 Filtered Water Pump is in service at least 1 Pump running
7 Group Sequence Control Logic executes
8 START UP PERM activated
9 Activate the RO Train Running
10 All Steps -6- Fully completed & RO in service within 110
Minutes.
11 Recovery % is met For 1st Pass
12 Recovery % is met For 2nd Pass
13 Recovery % is met For 3rd Pass
Page 5 of 6
Subject X √
PRODUCT WATER SYSTEM Line up
1 Log to screen
2 DESALINATED WATER TANK LEVEL
3 DESALINATED WATER PUMP START
RO system SHUTDOWN
1 Log to screen
2 Asking why we need to do – Permissive available
3 Activate eight (12 ) steps in the shutdown of RO Train
4 All Steps -12 - Fully completed & RO in Out service within 180
Minutes.
General Remarks
1 Work independent
2 Question / assistance rate
3 Logic reading for minor events
4 Monitoring the Alarm screen
5 Focusing in his work
6 Respond time rate to Alarm
7 Mobile Playing
Page 6 of 6