Technical Specification: Design, Fabrication, Supply, Testing and Commissioning of D.M Water Plant
Technical Specification: Design, Fabrication, Supply, Testing and Commissioning of D.M Water Plant
Technical Specification: Design, Fabrication, Supply, Testing and Commissioning of D.M Water Plant
TECHNICAL
SPECIFICATION
Design, Fabrication, Supply, Testing and
commissioning of D.M water plant
CONTENTS
SPECIFICATION FOR DEMINERALISED WATER PLANT.................................................. 3
1. SCOPE ....................................................................................................................................... 3
2. DESIGN BASIS ......................................................................................................................... 3
3. SCOPE OF SUPPLY ................................................................................................................. 5
4. MATERIAL OF CONSTRUCTION ......................................................................................... 7
5. LAYOUT CONSIDERATIONS ................................................................................................ 7
6. DRAWINGS .............................................................................................................................. 7
7. SCHEDULES ............................................................................................................................. 7
8. APPROVAL OF FABRICATION DRAWINGS: ..................................................................... 7
9. APPLICABLE CODES AND STANDARDS ........................................................................... 8
10. INSTRUMENTATION ........................................................................................................... 13
11. CLEANING OF EQUIPMENT & PIPING ............................................................................. 14
12. DOCUMENTATION............................................................................................................... 14
13. SHIPMENT .............................................................................................................................. 14
14. GUARANTEE ......................................................................................................................... 15
15. INFORMATION TO ACCOMPANY THE OFFER:.............................................................. 15
16. VENDOR EVALUATION CRITERIA ................................................................................... 16
17. THE ENCLOSED FIGURES .................................................................................................. 16
18. SCOPE OF THE PURCHASER .............................................................................................. 16
19. SPECIFIC REQUIREMENT & INSTRUCTION TO THE CONTRACTOR ........................ 16
Annexure – I...................................................................................................................................... 17
TECHNICAL DATA PROFORMA ................................................................................................. 17
Annexure-II ....................................................................................................................................... 23
(Commercial Part) ............................................................................................................................. 23
Break-up of the total cost for 1 Nos of D.M plants ........................................................................... 23
Break-up of the total Installation and commissioning ...................................................................... 25
Annexure III ...................................................................................................................................... 28
Annexure IV ...................................................................................................................................... 29
SPECIFICATION FOR DEMINERALISED WATER PLANT
1. SCOPE
This specification covers
a) Design, layout preparation, approval of drawing, fabrication, shop inspection and testing at
manufactures work, delivery at site (INRP-Kalpakkam).
b) Erection, testing, commissioning with performance guarantee and relevant documentation
for safe, trouble free and continuous operation of one DMW plant.
The DMW plant shall comprise of the following hardware components and the initial charge of
filtering media and resin:
• Raw water pumping system comprising of centrifugal pump, drive- motor & starter to
maximum flow required by the system
• Mixed Media Sand Filter with internals and piping
• Activated Carbon Filter with internals and piping
• Strong Acid Cation (SAC) Exchange Column with internals and piping
• Strong Base Anion (SBA) Exchange Column with internals and piping
• Mixed Bed Polisher Column with internals and piping
• Degasser tower with internals
• Regeneration system with mode of acid and alkali injection and associates storage tanks for
acid and alkali required for regeneration
• Instrumentation and control system
• Initial charge of resin and filter media.
2. DESIGN BASIS
The design basis for the DM water plant will be based on the following:
3. SCOPE OF SUPPLY
The scope of supply shall cover following hardware components and the initial charge of
filtering media and resin for the DMW plant.
The table below list the hardware required for the DMW plant
S No ITEM Quantity
3.1 Raw water pumping system comprising of centrifugal pump, drive- 2 (one working + one
motor & starter to provide maximum flow required by the system. stand- by)
Preferred Make
Pump: Kirloskar Brothers / Johnson/ Grundfos equivalent
Motor: Kirloskar/Siemens/Crompton/Johnson/Grundfos equivalent
3.2 Multigrade sand filter with internals, associated piping, valves and 1
initial charge of media.
3.3 Activated Carbon Filter with internals, frontal piping, valves and 1
initial charge of filtering media (Granular Activated Carbon)
3.4 Strong Acid Cation (SAC) Exchange Column with internals 1
associated piping, valves.
First charge of SAC resin. 1 Charge
3.5 Degasser Tower (Air Blower, Packing material and DG water transfer 1
Pump)
3.5 Strong Base Anion (SBA) Exchange Column with internals 1
associated piping, valves.
First charge of SBA resin. 1 Charge
3.6 Mixed bed polished column with internals, associated piping, valves. 1
First charge of Cation resin
First charge of Anion resin 1 Charge
1 Charge
3.7 Regeneration system
Acid measuring tank for SAC Exchange Column 1
Mixed bed polishing system 1
Acid Ejectors 2
Caustic measuring tank for SBA Exchange Column 1
Mixed Bed polishing Column 1
Caustic Ejectors 2
3.8 Maintenance tool kit 1 Set
3.9 Interconnecting piping, fittings, valves, accessories, structural pipe, 1 Set
supports etc.
3.10 Any other equipment or accessories which the supplier feels necessary
for the satisfactory performance of the system
Instrumentation and Controls * (Refer Figure – 1)
3.11 Pressure gauge 9 Nos.
3.12 Differential pressure transmitter 2 nos.
3.13 Flow Totalizer (magnetic and vortex type) 1 each
3.14 Flow Meter with local display 2 Nos
3.15 On line pH meter with transmitter (4 – 20 mA) having 2 Sets
local display
3.16 Online Conductivity meter with transmitter (4 – 20 mA) 2 Sets
having local display.
3.17 Level gauges 5 Nos.
3.18 Differential Pressure Gauges 2 Nos.
3.19 Fully enclosed epoxy painted Instrument panel (floor 1 Nos.
standing) to house all the above instruments.
3.20 Any additional instrumentation required which the
supplier feels necessary for the satisfactory performance of
the system.
3.21 MCC panel (3 starter and power for instruments) 1 Nos.
4. MATERIAL OF CONSTRUCTION
Material of Construction for SAC, SBA, MB, piping, accessories etc. shall be made of MS pipe
lined with Rubber. The material of construction for Sand bed filter and activated charcoal filter shall
be made of MSEP.
5. LAYOUT CONSIDERATIONS
The plant is proposed to be located indoors in an area of 33.5 m x 8.5 m (approx.). Bidder has
to prepare the layout to fit in the available space .
6. DRAWINGS
After placement of Purchase Order the supplier has to submit detailed flow sheet (with stream
flow rates, pressure etc.), P&ID (showing all equipment, pipe sizes, MOC details,
instrumentation and controls and interlocks), and fabrication drawings indicating Equipment
details, BOQ, which when approved in writing by the purchaser shall form a part of this
specification.
7. SCHEDULES
The supplier shall clearly indicate a firm time schedule immediately after receiving the purchase
order giving the break-up of different activities (as mentioned below) for the job execution from the
date of receipt of purchase order.
- Preparation of GA, equipment & piping drawings.
- Submission of these drawings for approval at different stages of fabrication and inspection
of equipment / vessel.
- Procurement of raw material / resins, valves, instruments etc.
- Assembly of equipment at supplier place.
- Delivery at site and commissioning.
9.3 Piping:
• The piping design shall satisfy the requirements of applicable section of ASME-ANSI B
31.3.
• Structural steel for pipe supports and other requirements shall conform to IS 2062.
• Flanges shall be of 150 # pressure rating as per ANSI B-16.5. Pipe threads shall generally
be to ANSI B 2.1 / IS-554. Threading of pipes shall be done after any bending operations.
• Pipe lines shall be of MS with corrosive protective coating either with Rubber/ FRP lined
as per BS 6374 part V.
• Where both the internal and external surfaces of the pipe comes in contact with corrosive
fluid the piping shall be of MS rubber lined.
• Velocities in pressurised lines shall not exceed 2.4 metres/second. In pump suction line
velocities shall not exceed 1 metre/second.
• Piping shall be routed to avoid interferences. If interferences are noticed at site, piping shall
be suitably modified and rectified by the contractor at no extra cost to the purchaser.
Layout shall follow good engineering practice.
• Effective precautions such as capping or sealing shall be taken to protect ends of all pipes,
fittings, valves against ingress of dirt and damage during transit or storage. Flange gasket
contact surfaces shall be suitably protected against damage.
• All piping shall be cleaned and purged with air blast or flushed with water to remove all
rust, mill scale etc from inner surface. Rotary wire brush may be used for cleaning of
unlined pipes of sizes above 300 mm. The method of cleaning shall be such that no
material is left on the inner surface, which may affect the serviceability of the pipe.
• Piping shall be routed in a manner so as to avoid hindrance of movement of men and
materials.
• Pipeline shall be routed in a manner that it is short and with minimum bends, in plumb
when vertical or parallel to walls when horizontal; with necessary slope (1:100 minimum)
to avoid any hold up of liquid, as well as to avoid any interference with other piping,
equipment and structure.
• All valves and on-line indicator type instruments shall be located at a height so that they
can be conveniently operated or observed. In case the same is not feasible necessary
platforms with ladders shall be fabricated and installed by the contractor.
9.4 Welding:
• All SS plates, piping & structural members shall be welded using full Shielded Metal arc
welding (SMAW) process.
• All welding procedures shall be approved by the Engineer prior to start of any welding
activity (prefabrication or installation) covered under those procedures. The information
contained in each welding procedure specification (WPS) and procedure qualification
record (PQR) shall include, but not be limited to, the information contained in Section IX
of ASME Boiler and Pressure Vessel Code. WPS and PQR shall be performed both at the
works of the contractor and at plant site.
• The cost of performing the procedure and performance qualifications shall be borne by the
contractor including materials, consumables and required testing. The welder’s deployed
by the contractor should have adequate experience on similar type of welding works.
• A weld map with weld descriptions and a table or fabrication drawing (sketch) that
specifies where each procedure will be used , shall be submitted to the Engineer along with
the WPS and PQR documents for each equipment and piping system.
• All welding including tack, temporary and repair welds shall be carried out only by
qualified welders.
• The test records of all welders and welding operators shall be available at all times at the
work location for review by the Engineer. Engineer shall have the right to retest of any
welder at any time.
• All intersecting and abutting parts to be welded shall be joined by full penetration groove
welds.
• Welding shall not be done when surfaces are wet or damp exposed to rain or snow or when
the welders are exposed to inclement conditions. Any wet damp surfaces shall be dried by
heating and shall be warm to the hand before welding.
• Weld faces shall be cleaned by acetone prior to root pass and after every pass.
• All joints and faying surfaces shall be seal welded by a continuous fillet weld, unless
specified otherwise.
• Pressure-retaining welds shall be separated from other ( pressure or no pressure) welds by
no less than 20 mm or three times the joint thickness, whichever is greater. This
requirement is intended specifically for nozzles and other attachments that are added onto
or adjacent to an existing joint.
• When the inside surfaces of items are inaccessible for welding or fairing any offset within
the tolerances provided shall be faired to at least 3: 1 taper by grinding. For circumferential
joint, the inside diameter shall match each other within 1.6mm. When the items are aligned
concentrically, a uniform mismatch of 0.8 mm all around the joint.
• All grinding wheels used shall be free from iron oxide, zinc and other harmful impurities
and should not be based on carbide materials and shall be subject to the approval of the
Engineer before being put to use.
• The filler wire and welding electrodes shall be as per the following specifications:
a) For welding MS materials: Filler wire: E 7018 (AWS/ASME A 5.1)
• Electrodes which have been exposed to rain or which have been otherwise exposed to
water however shall be discarded. Re-baking of such contaminated electrode shall not be
permitted.
10. INSTRUMENTATION
• The contractor shall supply the instrumentation and other accessories (Refer fig-1) as
specified in 3.13 of this section, which is the minimum essential instrumentation for the
plant. Over and above this, if the bidder provides additional items, it shall be assumed that
these extra items are necessary for the satisfactory operation and maintenance of the plant
and no credit shall be given for these items at the time of bid evaluation.
• All instruments shall have permanent stainless steel tag plates, fixed on the body,
indicating service.
• Supplier shall provide technical specifications of different sensors & instruments to be used in
this plant before the Supply of the plant.
11. CLEANING OF EQUIPMENT & PIPING
• Equipment, pipes, fittings etc. shall be cleaned off mill scale, dirt, grease, foreign matter,
paints etc. prior to fabrication and installation by using suitable chemical reagents/ metal
brushes. Local passivation of stainless pipes/ components shall be carried out whenever
these are mechanically worked or welded. Use of halogen free detergents could also be
made for cleaning operations. Oil-free compressed air shall be employed for cleaning of
pipes.
• Edge preparation shall be carried out in a manner so as to avoid filings falling inside the
equipment.
• Marking tape/crayon, and paint marks shall be cleared from surface. Acetone, diethyl ether
or methyl alcohol are some of the solvents which could be used for this purpose.
• All areas of installation as well as all equipment and piping shall be kept dust free.
Pipelines shall be flushed of all of filings, dirt & dust etc. by using a dry and clean cotton
liner.
• As far as possible, all openings in equipment and piping shall be kept suitably closed by
blind flanges or plugs.
• The procedure for cleaning shall be submitted by the contractor for approval.
12. DOCUMENTATION
Each System shall be supplied complete with two sets of full documentation covering:
• The detailed plant piping layout including PFD and P&ID and their reproducible
tracings.
• The equipment drawing approved by the purchaser.
• The installation, maintenance and operation manuals for the system with sufficient
details.
• Test report on the DP, hydrostatic, weld and spark tests carried out.
• Material test certifications.
• Test certificates and maintenance schedule for pumps, instrumentation etc.
• Performance characteristics for pumps and motors.
• Manufacturer’s literature on the operation and maintenance instructions for the bought
out items.
Note: The supplier shall provide the AutoCAD drawings also on Re-writable / non rewritable
Compact discs.
13. SHIPMENT
The water treatment units will be shipped to WIP stores, Kalpakkam only after obtaining a
shipping release from the purchaser or his authorized representatives. The supplier shall be
fully responsible for protective measures to ensure the safe delivery of the equipment and
associated components.
14. GUARANTEE
The supplier shall guarantee that the goods furnished by him are in full accordance with the
requirement of these specifications.
The supplier shall provide the warrantee that the goods are new and of quality meeting the
standards / codes and constructional requirements are free from defects in design, material of
workmanship or materials, the supplier shall at his own cost, take steps to carry out the repair
or replacement of such goods or parts thereof after obtaining due approval of the purchaser.
Annexure – I
(Commercial Part)
Break-up of the total cost for 1 Nos of D.M plants (To be Uploaded as a document)