Question Paper of Permit Holder Course Pdo

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Q1) what role is responsible for countersigning all class A permit and process isolation or

hydrocarbon system?

 1)productin coordinator B) Permit C) asset manager D)P.A ANS ;-A

Q2)A dynamic is conducted where?

 A) in the office B)at the point of work prior to undertaking an activity C)whenever you get
the chance D)Never ANS;-B

Q3) Area authority can only control?

 A) 6 validated class A Permit ;or 14 validated permit (classs A+B permit) B)1 Class A & 2
class B permit C) 7 class B permit D)7 of each class ANS ;A

Q4)What is the objective of PTW system?

 A) maintain employment B) Deliver accountability C) to ensure safety in routine job and


non routine hazardous activities D) To provide a system to ensure that non routine
hazardous activities can be worked in a safe manner. ANS;-D

Q5)For class A Permit who is responsible for examining the work site with the permit permit
applicant ,prior to permit authorization?

 A)Permit holder B)Contractor C) Contractor supervisor D)responsible supervisor ANS;-D

Q6)Who is required to validate a permit, following approval by the responsible supervisor?

 A)Permit holder B)area authority c)contractor supervisor D) contractor ANS;-B

Q7)Before authorizing any permit which role would review JOB HSE PLAN?

 A)Responsible supervisor B)Responsible manager C)Permit holder D)Permit applicant


 ANS;-A

Q8)Who would authorize class B permit?

 A) asset manager B) Contractor manager C)Contractor D)Responsible supervisor ANS;-D

Q9)Can PTW be reauthorized by area authority verbally?

 A)Yes, if the alarm was not caused by an actual alarm condition B)YES, every time C)No
under no circumstances D)Yes no reentry to the work. ANS;-A

Q10)A permit must be suspend if?

 A)The work complete B)the authorization period expired C)an unsafe situation develop D)A
facility inspection in progress ANS;-C

Q11)Once a permit is cancelled ,how long the permit and associated document must be kept in
archive file?

 A)One month B)three month C)Six month D)one year ANS;-C

Q12)A permit must be cancel if ;-

 A) an unsafe situation develop B)Reportable incident occur at site C)The validation period
expired D)The work to be done is different from decription ANS;-D
Q13)What is the maximum period for which a permit is allowed to be authorised?

 A) 12 hour B)24 Hour C)72 hour D) 14 days

Q14) HEMP is the technique to be used to identify hazard/risk & control?

 A) TRUE B)FALSE ANS;-A

Q15)The PTW training custodian is responsible for the requirement of the PTW training courses and
control and maintain standard of course delivery?

 A)TRUE B)FALSE ANS;-A

Q16)Who is responsible for the content of the PTW system ,its revision to delivery briefing on the
system & to ensure the audit is being completed?

 A)permit holder B)PTW custodian C)Asset custodian D)Permit issuer ANS;-A

Q17)A confined space is?

 A)A man made fabrication such as a pipe that only has a narrow hole/hatch B)PTW
custodian B)A man made fabrication such as pipe that only has rope access from the top C)
A man made that only has a ladder access D) A man made pipe or any enclosed area that
human can be exposed to be a risk of fire /explosion of loss of consciousness ANS;-D

Q18)The area authority must record all isolation where?

 A)On a piece of paper B)On permit location board C)On the wall D)IN a data base ANS;-B

Q19)In a process area ,a PTW should identify ,continuous monitoring ,if activity involves hot work?

 A)TRUE B) FALSE ANS ;-A

Q20)The principle of perimetry is?

 A)To document the PTW B)To issue the permit C)The process used to determine whether a
job need a permit to work or not D)To receive ANS;-C

Q21)Class A permit require what before issue?

 A)72 hour notice period B)JOB HSE PLAN C)Worksite examination by responsible supervisor
and permit applicant D)All of the above ANS;-D

Q22)Who would authorize class A & B permit?

 A)Asset manager B)Responsible supervisor C)control manager D)Contractor ANS;-B

Q23)What in a hydrocarbon area is at high risk?

 A)Hydrocarbon B)Hot work C)Confined space work D) All of the above ANS;-D

Q24)What should be completed prior to any work activity commencing?

 A)SHOC Card B)Tools put away C)TRIC Card D)Permit holder ANS;-A

Q25)A permit is required if the work is within?

 A)Process facility B)Hydrocarbon area C)Electrical installation D)All of the above. ANS;-D
Q26)Work without a permit is to authorized by responsible supervisor on a NO PERMIT JOB record
signed also by the worksite supervisor?

 A)TRUE B)FALSE ANS;-A

Q27)The area authority must receive on a daily basis , a list of the permits that he can validate that
day?

 A)TRUE B)FALSE ANS;-A

Q28)When should an area authority attend a TRIC TALK?

 A) All activities in his area B)Never C)None of the above D)For activities he consider may
hold a higher risk level ANS;-D

Q29)When work on a permit is finished or the permit reaches the end of its authorization period
,the area authority must?

 A)State on the permit if complete or not; worksite is left in a safe manner ,conduct check to
ensure equipment operating correctly ; cancel PTW B)write on the permit that all okay and
sign off C) Throw away the permit and unisolate everything D)all of the above. ANS;-A

Q30)Is PTW is a legal document?

 A)YES B)NO ANS;-A

Q31)How to decide the task need a permit or not?

 A)Permit holder to decide B)Ask area authority C)Referring permit manual D)Applicant and
responsible supervisor ANS;-D

Q32)What roles under license a responsible supervisor take in PTW system?

 A)Responsible supervisor B)Area authority C)permit holder D)permit applicant E)All of the
above ANS ;-E

Q33)Who must ensure the PTW is displayed at the worksite?

 A)Contractor B) Area authority C)Permit holder ANS;-C

Q34)It is permissible for a responsible supervisor to sign or responsible supervisor & area authority
on a single permit?

 A)Yes, in a emergency or during night time break down situation B)YES, whenever he can
save the other C)NO D)YES, in critical emergency situation only

Q35)What type of permit is required for confined space?

 A)Class C B)Class B C)Class A ANS;-A

Q36)In conducting the HEMP process ,the following aspect will be identified in preparation for the
issue of the permit and the work activities involved?

 A)Who need to sign on the TRIC presentation B)What need to be done ,how it done and
how long will it take C)Nothing pertinent to the activity D)The hazard identified ,who &
how people /plant or equipment may be harmed; evaluate the risk and the control to
migrate the risk. Record finding review periodically ANS;-D
Q37)Permit is suspended for a day, but work not finished new permit were required ?

 A)NO B)YES ANS;-A