8 - Manual Well Boring For Utility Water For Compression Project
8 - Manual Well Boring For Utility Water For Compression Project
8 - Manual Well Boring For Utility Water For Compression Project
Area of Work Considered: PROCUREMENT, CONSTRUCTION & PRE-COMMISSIONING Job No: PPL-
JSA Date: July 21,2022
WORKS FOR GAMBAT (GPF-IV) COMPRESSION PROJECT - GAM-22-SD-07
Residual
Task / Activity Responsibilit
Hazard Hazard Effect Risk Rating Control Measures Risk
Description y
Rating
Mobilization Of Un inducted Injury / asset Ensure inducted and medically fit and approved people should enter Gasco
Personnel & people
Damage the working area
Equipment Emergency response requirements, Emergency access, Muster
3D Points, and other relevant protocols as per standard of PPL 2A
Workers unaware
(Tripod, Mini of access & Emergency Protocol shall be reinforced during toolbox meeting.
Biller, chain block, protocols Discuss work scope with team
wrench, Pipes) Conduct the daily Toolbox Meeting before the job start
Fuel & Oil Drips / Environmental 3C Visual inspection shall be done to check any leakage. 1A
Oil contaminated soil shall be removed & disposed of at designated
Leakages Issues
place.
Continuous Gas testing
Job Safety Analysis
B2 1A
Contact with Get excavation/penetration certificate from PPL
Un-identification of
underground
Underground Conduct final walk around to ensure workers understand the scope of
services and
services the excavation/penetration and the hazards in the work area.
damage
Gasco
Manual Well Cordon off area 1A
B2
Boring for Water Conduct the daily toolbox meeting before start the job
Tripod can Person being Tripod to be set on firm ground level and area maintain clean and
collapse struck clear
Personnel injury Non-essential persons remain clear working area
Only inspected rope shall be used