001 - JSA For Back Filling - TCF Area
001 - JSA For Back Filling - TCF Area
001 - JSA For Back Filling - TCF Area
For
Back Filling for TCF area
Doc. No. PTJ.JSA.001
All work activities shall comply with the requirements of all applicable SA General Instructions Standards and Procedures.
Contractor ensures that all work is in full compliance with the requirement of Saudi Aramco Construction Safety Manual (CSM) and with the
provision of Saudi Aramco certification applicable. Changing Conditions and Emergency Procedures: Stop Work, Switch off all equipment,
Supervisors must direct all personnel to the nearest Emergency Exit and Assembly point.
Page 1 of 5
Job Safety Analysis
For
Back Filling for TCF area
Doc. No. PTJ.JSA.001
Written by: S.A. ElDayem Subcontractor Name (if applicable): PETROJET/ Al aqeeel
Page 2 of 5
Job Safety Analysis
For
Back Filling for TCF area
Doc. No. PTJ.JSA.001
Page 3 of 5
Job Safety Analysis
For
Back Filling for TCF area
Doc. No. PTJ.JSA.001
Move the injured personnel to the nearest “Rest Shelter”. Foreman/ Supervisor
9
Working during daily Heat Stress Emergency While waiting for the medical response team, provide cold drink water. Safety person
hours Cases
Remove clothes and cool the injured person by fan, until medical response team arrives. All concern persons
PERTROJET.
Salah A Dayem (HSE) – 0547055154
Khaled Mosad (const.MGR) – 0547287205
Mohamed Mamdouh ( project MGR)- 0539086838
Page 4 of 5
Job Safety Analysis
For
Back Filling for TCF area
Doc. No. PTJ.JSA.001
By Signing this attendance sheet, I confirm that I have attended the JSA Briefing by my
Job Supervisor & I understand in my own language the content of this Job Safety Analysis
(JSA).
Sr. No. Name Trade ID Badge # Signature
Page 5 of 5