WHT - UAD-Commissioning Report - 14th Jul
WHT - UAD-Commissioning Report - 14th Jul
WHT - UAD-Commissioning Report - 14th Jul
TOTAL
SL.NO SUB SYSTEM NAME
LOOPS PENDI PENDI
NUMBER TOTAL DONE PENDING TOTAL DONE PENDING TOTAL DONE PENDING TOTAL DONE PENDING TOTAL DONE TOTAL DONE
NG NG
completed
1. ZIRK Integration and OTP part pending.
2. ESD Cause & Effect checks to be done( vendor to be
transferred from UAS on 4th July).
completed
1. ZIRK Integration and OTP part pending. Remaining FTRs to
be deleted. PMC req. Engineering approval.
completed
completed
completed
OTP SIGNED
1. ZIRKU Integration
2. FTRs and OTP Outstanding to be done
1. ZIRKU Integration
2. FTRs and OTP Outstanding to be done
1. ZIRKU Integration
1.
2. INTERFACE
FTRs and OTPTEST with ZIRKU,
Outstanding to be done
2. 66 KV GIS- A01 – Disconnector Q9 mechanism to be fixed.
3. CB watch – A03 Communication ethernet switch slot to be
fixed.
4. Mechanical key installation & interlock function test for
GIS
Mechto interlock
be completed.
key to be installed
2.Mech interlock key to be installed/Rest FTRs to be closed
with ZIRKU integration.
2. RMU to VFD functional checks to be done (Awaiting VFD
vendor).
Mech interlock key to be installed
completed
completed
completed
completed
OTP SIGNED
completed
OTP SIGNED
OTP SIGNED