Canada Line Final Project Report - 12april2006
Canada Line Final Project Report - 12april2006
Canada Line Final Project Report - 12april2006
Page i of ii
Figures
Appendices
ii of ii
Executive Summary
Project Description and Purpose of Value1 (NPV) less than the PSC. The
Final Project Report revenue and cost comparisons are based on
forward-looking information and consequently,
Canada Line is a 19km rail rapid transit the $92 million NPV differential is not an
system connecting downtown Vancouver, the absolute assertion and the difference may
Vancouver International Airport and Central be less or greater than expected based on
Richmond. It has 16 stations, two bridges actual costs and revenues achieved over the
and nine kilometres of tunnel. This is the final 35-year Concession Agreement.
report for the procurement stage of the
project. Its purpose is to assess value for The net cost differential should not be
money. It also includes a discussion of interpreted as a savings available to fund
project funding and compliance with public other government expenditures. Rather, the
agency funding conditions. net cost differential arises from a
comparison of forecasts of project revenue
The public funding agencies for Canada and costs with forecast of the revenues and
Line are: the Government of Canada costs associated with a hypothetical project
(Canada), the Province of British Columbia funded and managed solely by the public
(the Province), the Greater Vancouver sector (the PSC). The comparison is only
Transportation Authority (GVTA), Vancouver made to assist in concluding whether or not
International Airport Authority (VIAA) and the the project has delivered value to the
City of Vancouver. The procurement stage taxpayer.
began with the approval by the Province,
GVTA and VIAA to begin a competitive Within Approved Public Sector Funding
process to select a contractor to design,
build, partially finance, operate and maintain Project development funding was provided
the line. by the public agencies and project design
and construction is jointly funded by the
The procurement concluded with execution public agencies and the selected contractor,
of a contract (Concession Agreement), InTransitBC. Performance payments during
between Canada Line Rapid Transit Inc. the operating period are funded by GVTA
(CLCO), the company responsible for and the Province.
implementing the project for the public
sector, and the selected contractor,
InTransitBC.
CLCO concludes that value for money is 1 Costs and revenues of the project are expressed as
expected to be achieved based on an cash flow projections over the term of the Concession
analysis of the competitiveness and fairness Agreement (about 35 years). In order to reflect the
of the selection process undertaken by time value for money, such cash flows are often
CLCO and upon revenue and cost presented in Net Present Value (NPV) terms. An NPV
comparisons with a public sector comparator is calculated by applying a compounding discount rate
(PSC), which indicates the expected net to a stream of future cash flows. This calculation
cost of the project is $92 million Net Present reduces these cash flows to a single value reflecting
the time value of money. All NPV amounts in this
report, unless otherwise stated, are the result of
discounting annual costs and revenues to the year
2003, using a 6% nominal discount rate.
1 of 36
This report concludes that approved public History and Competitive Selection
sector funding together with InTransitBC’s
investment is sufficient to fund project In 2000, Canada, the Province, GVTA,
construction: VIAA, and the Cities of Vancouver and
Richmond agreed to participate in a three-
• $1,331 million (nominal) approved phase program to evaluate the potential to
public funds; build rapid transit in the Richmond-Airport-
Vancouver corridor by 2010. This concluded
• $720 million (nominal) InTransitBC with approval to begin the procurement.
investment;
CLCO commenced the procurement
process in November 2002 by issuing a
• total project cost within approved
Request for Expressions of Interest (RFEI).
funding of $2.05 billion (nominal),
Ten private sector consortia of firms
which is equivalent to $1.89 billion
submitted responses that detailed their
($2003 real)
relevant qualifications and experience. In
August 2003, CLCO issued a Request for
The approved funding does not fund the
Proposals (RFP) to four well-qualified
cost of those aspects of the project that are
proponents, each of whom CLCO concluded
directly funded and managed by GVTA and
were capable of designing, constructing,
the Cities of Vancouver and Richmond. This
financing and operating the line.
includes the provision of GVTA designated
policing units, certain operating period
One of the proponents withdrew in the fall of
insurance policies, GVTA and City funding
2003. The remaining three proponents
of major road construction, cost of trolley
submitted proposals in response to the RFP
wires, construction of bus loops and ticket
in January, 2004.
vending machines. The Provincial funding
contribution was conditional upon the project
In July 2004, CLCO issued invitations to two
being developed as a partnership between
proponent teams to participate in the Best
the public and private sectors (P3).
and Final Offer (BAFO) stage. Thereafter,
the Board of CLCO identified SNC-
GVTA will own the main line from Richmond
Lavalin/Serco as the preferred proponent. In
to Vancouver, and VIAA will own the line
December 2004, CLCO, with the approval of
from Bridgeport Station to the Airport.
GVTA, entered into final negotiations with
InTransitBC will own the rail cars. GVTA will
SNC-Lavalin/Serco. Subsequently, SNC-
set fares and collect for its account, all fare
Lavalin Inc. formed a limited partnership
revenues from the system.
company called InTransitBC, owned jointly
by SNC-Lavalin Inc., the British Columbia
Project Governance
Investment Management Corporation and
Caisse de dépôt et placement du Québec, to
CLCO, a wholly-owned and independently- design, build, partially finance, operate and
governed subsidiary of GVTA, managed the maintain the line. The finalization of project
competitive selection process and is documentation occurred on July 29, 2005
responsible for overall implementation of the (Financial Close) and InTransitBC began
project. CLCO was established to implement construction of the system shortly thereafter.
the project. Transportation policy supporting
the project is the responsibility of GVTA.
The total cost of the procurement phase was
$32 million (nominal).
On February 1, 2006 RAV Project
Management Ltd. changed its legal name to
Canada Line Rapid Transit Inc. (CLCO).
2 of 36
Fair Competitive Selection The key principle behind the design of the
Concession Agreement is that risk should,
Fairness Auditor, Mr. Ted Hughes, O.C., where possible, be allocated to the party
Q.C. confirmed that the competitive most able to manage and mitigate it. The
selection process was fair and unbiased. majority of the construction cost and
operating cost risks have been allocated to
Concession Agreement and InTransitBC. Any risks retained by CLCO
Allocation of Risk during construction including, for example,
property acquisition, unidentified contaminated
The commercial relationship between soils, and a share of utility relocation costs,
InTransitBC, CLCO and GVTA (the are covered by specific contingency funds.
“parties”) is governed by the Concession
Agreement which sets out the rights and While most of the operating cost risk has
obligations of each party in the delivery of been allocated to InTransitBC, GVTA retains
the project over 35 years. the majority of the ridership revenue risk.
This is because GVTA controls the majority
Under the terms of the Concession of the integrated Lower Mainland
Agreement, InTransitBC is responsible for transportation system, sets fare levels for
building the line. Payments to InTransitBC bus and rail systems, optimizes bus routes
and the project completion date are set out and integrates them with rail systems, and
in the Concession Agreement. InTransitBC markets transit to the public.
will be paid after achieving identified
milestones during the construction period.
During the operating period, payments will
be made to InTransitBC for the achievement
of performance targets that measure, for
example, train frequency, safety and
ridership.
3 of 36
1 Purpose of the Final Project Report
The Canada Line rapid transit system is being developed as a P3. CLCO made a commitment to
publicly report the final assessment of value for money expected to be achieved over the life of
the partnership. Value for money assessments capture a range of factors including analyses of
revenues and costs, risks retained by the public sector and the overall protection of public
interests. CLCO’s assessment of value for money includes an analysis of the competitive
selection process and a revenue and cost comparison of the project with a PSC. The PSC is a
hypothetical concept based on realistic assumptions intended to provide a risk-adjusted estimate
of the project cost with the use of conventional public sector procurement methods where the
system would be purchased, financed, operated and maintained by the public sector. The scope
of the assessment is limited to determining if the competitive selection process has delivered
value for money; it is not an assessment of whether or not the system is the best option for
addressing the transportation issues in the Richmond-Airport-Vancouver corridor.
CLCO requested that the Auditor General of British Columbia undertake a review of this Report.
CLCO provided the Auditor General with full access to all project information required to support
the review process. CLCO is accountable for the contents of this report, including the
reasonableness of the facts, assumptions and professional opinions that are presented. This
report discusses the assessment of value for money as at July 29, 2005 when the project
documentation and financial commitments were finalized (Financial Close).
4 of 36
2 History of the Project
Transportation systems for the Richmond-Vancouver corridor have been studied for over 30
years. In 1999, during the consultation program for the TransLink Strategic Transportation Plan
(1999), several government agencies expressed renewed interest in a rapid transit network to
connect Richmond and Vancouver. Increases in passenger and cargo traffic at Vancouver
International Airport prompted interest in a rail link to serve the growing employment base on Sea
Island and existing and future passenger terminals.
In September 2000 GVTA, the Province, VIAA, (Local Funding Agencies) and the Cities of
Vancouver and Richmond agreed to participate in a three-phase project to evaluate the potential
to build rapid transit in the corridor by 2010:
• Phase One – consisted of defining the organization of the project and its objectives;
• Phase Two – included an evaluation of the need to build the line, the potential to fund it
and the potential for private investment;
• Phase Three – Project Definition Phase, culminated in a Project Definition Report which
was delivered to the participating agencies in February of 2003. The purpose of the report
was to define the project and its financial implications to a level that would allow the Local
Funding Agencies to decide to proceed with the project. The Project Definition Phase
also marked the beginning of the procurement, or competitive selection process. During
this phase the agencies issued a Request for Expressions of Interest (RFEI) to determine
the level of interest in the market.
The Project Definition Report was the subject of a public consultation process which took place in
the spring of 2003. The agencies considered the Project Definition Report and the public
commentary. In mid 2003 GVTA, with input from the Local Funding Agencies, approved:
• continuing with the competitive selection process by issuing a Request for Proposals;
• the development of a Concession Agreement (the Agreement) that specified the terms and
conditions for the design, construction, finance, operation and maintenance of the system;
• establishing an independently governed subsidiary of GVTA to implement the project, with
directors nominated by each of the Province, GVTA and VIAA; and
• its initial financial contributions.
During negotiation of the funding arrangements, the Local Funding Agencies identified specific
elements of the project that they considered to be “essential”, which were to be included as
conditions of their participation. Collectively, these elements came to be known as the Essential
Elements of the project. The Essential Elements describe specific objectives, including travel
time, alignment constraints and a construction completion date of no later than November 30,
2009. In addition to the Essential Elements, the Province’s funding commitment was conditional
upon the project being structured as a P3.
The Request for Proposals (RFP) was issued in the summer of 2003 and was followed by
numerous agency approvals and procurement steps that culminated in the finalization of all
project documentation on July 29, 2005 (Financial Close) with InTransitBC, the private sector
partner. InTransitBC began construction of the system shortly thereafter.
5 of 36
2.1 Project Governance, Funding and Ownership
CLCO is a wholly-owned subsidiary of GVTA. The majority of its Board of Directors are
independent; the other directors are employees of GVTA and VIAA. The company’s mandate is
to oversee the development of the system including the procurement, design, and construction of
the line. GVTA has recently initiated an overall review of its strategy, including determination of
the best approach to managing the operating period of the 35-year Agreement.
The development and construction of the project is jointly funded by Canada, the Province,
GVTA, VIAA, the City of Vancouver and InTransitBC. Over the operating period, GVTA and the
Province will fund performance payments to InTransitBC. Each agency finances its contributions
differently and individually accounts for their cost of financing contributions to CLCO. GVTA, in
addition to its contributions to CLCO, is also funding additional costs related to the project, as
described in Section 3.1.2.
Once completed, the rapid transit system will connect three major commercial and population
centres; downtown Vancouver, Sea Island and the Airport, and Central Richmond. GVTA will own
the main line from Richmond to Vancouver, VIAA will own the line from Bridgeport to the Airport
and will provide an operating license to GVTA through to the end of the term of the Agreement.
InTransitBC will design, construct, partially finance the system, own the train vehicles, and
operate and maintain the entire system under an operating license from GVTA through to the end
of the Agreement. GVTA will collect all fare revenues and will continue to set system-wide
transportation policies and fare levels. As a condition of funding from Canada, the system is now
called “Canada Line” and on February 1, 2006, RAV Project Management Ltd. changed its legal
name to Canada Line Rapid Transit Inc. (CLCO).
6 of 36
2.2 Project Description
The north-south transportation corridor between downtown Vancouver, the Vancouver International
Airport, and downtown Richmond is one of the busiest in Greater Vancouver and is home to one-
third of the jobs and 20% of the people in the Lower Mainland. As the population in the corridor and
the surrounding region has increased, the corridor’s transportation network has suffered from
increasing congestion. There is a long history of analysis of various options to address congestion
and increase the capacity of the existing transportation network in this corridor.
The project will pick up and deliver passengers to existing rapid transit lines at Waterfront Station
and major east-west transit services in Vancouver and Richmond, expanding the transit network
serving the region. The project will, as illustrated in Figure 1, consist of:
7 of 36
3 Achieving Value for Money
CLCO’s assessment that it has delivered value for money via the competitive selection process is
based upon its belief that the:
• procurement process was fair and competitive and has delivered a good outcome in the
form of a Concession Agreement that efficiently and effectively allocates risk (see
Section 3.1); and
• project is expected to have lower net costs than the PSC (see Section 3.2).
The value for money assertion is further supported by CLCO’s belief that the project is expected
to deliver higher transportation benefits (see Section 3.3).
It is important to note that all of the quantitative conclusions in this report are based upon forward-
looking information. CLCO has taken care in preparing its analyses; however, it is difficult to
forecast future events with certainty and it is not possible to absolutely assert that the project will
have lower net costs than the PSC or will meet the affordability tests described in Section 3.1.2
and in Appendix C. Throughout this report, words such as “believes”, “expects”, “forecast” and
other similar expressions have been used to identify forward-looking information.
• ridership revenue forecasts for the project and the PSC are based on the incremental
impact expected on the Lower Mainland integrated transit system;
• ridership revenue forecast during the operating period is based on assumptions that
compound over a period of time. Small changes in these assumptions can have a
material impact on the overall results, either increasing or decreasing the revenue levels
achieved. In addition, the project is part of the Lower Mainland integrated transit system.
Changes to this system would have an impact on revenues; and
• a material source of project operating phase funding is the net operating and capital cost
savings that GVTA expects to achieve by adjusting bus services in the corridor to improve
transit integration. Therefore, future adjustments by GVTA of bus services may impact
affordability.
CLCO and GVTA accepted the impact of this uncertainty in deciding to sign the Agreement, and
accepted that the cost of the project (over the life of the Agreement) and the revenue sources
available in the long-term may differ from those forecast at the time of Financial Close.
8 of 36
3.1 Competitive Selection Process
CLCO commenced the competitive selection process in November 2002 by issuing a Request for
Expressions of Interest. Ten private sector consortia of firms submitted responses that detailed
their relevant qualifications and experience. In August 2003, CLCO issued Requests for
Proposals (RFP) to four well-qualified proponents, each of whom CLCO concluded were capable
of designing, constructing, financing and operating the line:
• RAVLink Transportation: Fluor Canada Ltd., Siemens Canada Limited, MTR Corporation
Limited, and Balfour Beatty Capital Projects Limited;
• RAVxpress: Bombardier Inc., AMEC, Bouygues Travaux Publics, SA, and Bilfinger
Berger;
• SNC-Lavalin/Serco: SNC-Lavalin Inc. and Serco Limited; and
• RAVRail: Alstom Transport, SA; Ledcor Projects Inc.; Connex North America, Inc.; Karyo
Communications; Busby & Associates; and MKT Development Group.
RAVRail withdrew in the fall of 2003. The remaining three proponents submitted proposals in
response to the RFP in January 2004.
In July 2004, CLCO issued invitations to the RAVxpress and SNC-Lavalin/Serco proponent teams
to participate in the Best and Final Offer (“BAFO”) stage. Thereafter, the Board of CLCO identified
SNC-Lavalin/Serco as the Preferred Proponent. In December 2004, CLCO, with the approval of
GVTA, entered into final negotiations with SNC-Lavalin/Serco.
At the July 29, 2005 Financial Close, SNC-Lavalin/Serco transferred its interests in the project to
InTransitBC, a limited partnership owned equally by SNC-Lavalin, British Columbia Investment
Management Corporation and Caisse de dépôt et placement du Québec. Serco Limited will
participate in the operations of the project.
At the end of each of the RFP and BAFO stages, CLCO appointed formal evaluation committees
and sub-committees to evaluate each of the competing proposals. The sub-committees were
charged with the obligation of providing fair and unbiased assessments in the following areas:
design and construction/technical; operations and maintenance; finance; commercial and legal;
and consultation, all in accordance with the procurement instructions provided to the proponents
at each of the stages. The sub-committees reported to the evaluation committee, which in turn,
made recommendations (in the form of an evaluation report) to the CLCO Board. The committees
evaluated the proposals using the criteria included in the instructions; the most important of the
criteria being the “Net Cost of the System”, which considered the capital costs, operating costs,
ridership revenues and bus cost savings associated with the proposals. In addition, the
committees considered:
• safety; and
9 of 36
An important objective of the competitive selection process was to maximize competition while
ensuring that competing proponents had opportunities to optimize their proposals via consultation
with CLCO and GVTA and provide input into the various project requirements (including draft
Concession Agreements prepared at each of the RFP and BAFO stages). As a consequence,
there was a high degree of interaction between CLCO and the proponents at each of the RFP
and BAFO stages.
CLCO adopted several practices to ensure that the interaction during the bidding stages did not
compromise the fairness of the process by engaging:
• a Fairness Auditor.
The use of a single ridership forecasting consultant, accessible to proponents, was required as
each competing proposal had innovative designs and options resulting in differing levels of
ridership. The draft Concession Agreement provided during the selection process did not define
exactly how the system was to be designed. Rather, it primarily specified the performance that
the completed system must achieve. As a consequence, during the selection process each of the
proponents were free to propose innovative designs to maximize ridership or minimize cost, so
long as the designs conformed to the Essential Elements and were capable of meeting the
performance specifications.
It was critical that the individual proponents’ ridership forecasts be produced with the use of the
same model, with the application of a consistent modelling methodology with complete
confidentially to ensure comparability of the various forecasts and to provide proponents with the
confidence that their design innovations would not be shared with other proponents. The
consultant chosen by CLCO, via a competitive selection process, was Halcrow/TSi. Halcrow/TSi
is comprised of Halcrow Group Limited, based in the United Kingdom, and TranSys Consultants
International, a British Columbia firm with extensive experience in modelling the Lower Mainland
transportation system. The approach to the modelling reflected Halcrow/TSi’s international and
local experience.
Similar models are widely used throughout the world to help plan transportation infrastructure.
The inputs to these models include detailed descriptions of the region's roads and transit
systems, and the locations of population and employment. Travel demand, derived from this land-
use information, is assigned to different travel modes (car, bus, walking, etc.) and routes,
reflecting the relative attractiveness of each mode and route for an individual trip in terms of
journey times, costs and other factors. The models are both calibrated and validated to ensure
that they reasonably represent current travel choices and behaviour in the region.
Assumptions for a specific scenario (e.g., the specifics of the PSC reference design) are input
into the model, which then generates forecasts for the transport system, such as vehicle volumes,
average speed, and transit ridership for that scenario.
Modelling is a difficult and skilled task and all forecasts are inherently subject to uncertainty and
transport models are often complex, and thus are rarely error-free. Models are sensitive to both
general input assumptions and to specific information about local travellers' behaviour (such as
their sensitivity to changes in train frequency or station access time). Input assumptions, such as
how rapidly population will grow in a particular municipality in the future, often prove inaccurate.
10 of 36
Travel data is expensive to collect, and models sometimes have to use incomplete or dated
information.
In order to make the forecasts from the models as accurate as feasible, the modelling approach
used for this project involved:
• further development and use of an existing local model of the region covering the peak
hours. This model had been previously used for other projects and proven to give
reasonable results;
• extensive travel surveys in the project corridor to ensure that the travel data (used in the
development of the models) were both comprehensive and recent;
• testing the models with past changes in the region's transport systems to see how well
they were able to forecast the observed changes in travel behaviour;
• benchmarking the forecasts against existing similar transit systems to be found elsewhere
in the world; and
• Sensitivity testing of key assumptions and a risk analysis to identify the level of uncertainty
associated with the forecasts.
In addition, the model and modelling approach were peer-reviewed by Booz Allen Hamilton, a
consultancy firm with extensive international ridership forecasting experience, and assessed by
staff of GVTA and other agencies as well as by staff of each of the bidding consortia.
CLCO appointed John Haythorne, a senior partner of the law firm Bull, Housser & Tupper, to
assist with the identification and elimination of conflicts of interest with CLCO, the Agencies, and
the proponents. In addition, CLCO appointed former Justice Ted Hughes, O.C., Q.C., as a
Fairness Auditor with responsibility to review the evaluation process at each stage in the selection
process. Mr. Hughes’ reports were positive and are referenced in Appendix A.
The total cost of the procurement phase was $32 million (nominal). These costs are included in
the CLCO costs described in section 3.2. The procurement began in December 2002 and ended
with Financial Close at the end of July 2005.
11 of 36
3.1.1 The Concession Agreement
The project is governed by the Agreement signed by CLCO, GVTA and InTransitBC (the “parties”)
which sets out the rights and obligations of each party in the delivery of the line over 35 years.
Under the Agreement, InTransitBC (see Figure 2) has an obligation to design, construct, operate,
maintain, and partially finance the project in accordance with the specifications set out in the
Agreement and has the right to receive payments for fulfilling these obligations.
CLCO
Nord LB
CONTRACTS bcIMC
InTransitBC is obliged to construct the line for a fixed price (with the exception of costs
associated with risks that are retained by CLCO) and is required to invest additional capital to
fund cost overruns for which it is responsible. CLCO will make construction period payments to
InTransitBC upon the attainment of defined milestones. These payments will be insufficient to
meet the full cost of constructing the line. This funding shortfall requires that InTransitBC raise
sufficient private capital (equity and debt) to fund the remaining construction costs. This private
capital is critical to the completion of the project and to ensuring effective transfer of risk to
InTransitBC over the term of the Agreement. InTransitBC expects to recover its capital during the
operating period from performance payments from GVTA and the Province.
During the operating period, performance payments are made to InTransitBC based on
achievement of operating specifications defined in the Agreement. The performance payments
are used by InTransitBC to meet operating costs and to repay and provide a return on
InTransitBC’s capital. The performance payments paid to InTransitBC during the operating phase
12 of 36
will not increase if InTransitBC experiences construction or operating cost overruns that are to its
account.
The key principle behind the design of the Agreement is that risk should, where possible, be
allocated to the party most able to efficiently manage and mitigate the risk in a cost-effective
manner. Allocating risks to InTransitBC that it is not able to efficiently manage or mitigate would
increase the overall cost of the project. An example is the acquisition of property, where failure to
acquire a site on schedule can have a much larger impact on project cost than the cost of the site
itself. In this circumstance, land acquisition risk better resides with CLCO and GVTA – particularly
given that GVTA can exercise powers of expropriation not available to InTransitBC.
Another example is ridership risk. Ridership will be influenced by factors that relate to the entire
transportation system as well as the specific operation of the project. GVTA controls the majority
of the integrated Lower Mainland transportation system, sets fare levels for bus and rail systems,
optimizes bus routes and integrates them with rail systems, and markets the various modes of
transit to the public. The majority of the ridership risk is therefore logically allocated to GVTA.
InTransitBC is responsible for the operating and maintenance costs of the system. It receives
payments that reflect achievement of performance measures for on-time arrivals and quality.
Since its performance also influences ridership, it also carries a part of the risk of actual ridership
being different than the forecast ridership. During the operating period, 70% of each payment
from GVTA to InTransitBC is based on availability, 20% on quality of the service delivered and
10% on achievement of ridership forecasts.
The ridership forecasts are to be established for every five years of operations as well as at the
commencement of the first year and at the end of the second year of operations. The ridership
forecasts may be adjusted once per year in response to events that could reasonably be
expected to have a material effect on the forecast ridership. Such events include changes in
GVTA bus services, the addition of stations and increases in fare levels.
In the unlikely event that InTransitBC fails to meet its obligations over the 35-year term of the
Agreement such that it would be declared in default due to non-performance, CLCO could elect to
terminate the Agreement. In such an event, CLCO needs to be certain that InTransitBC would
have sufficient capital at risk to fund CLCO’s costs to complete or refurbish the project. Given that
the risks transferred to InTransitBC are significant, the Agreement is structured such that its
capital is at risk if the project suffers cost overruns or poor operating performance. In addition to
the at-risk capital, there are corporate guarantees and financial letters of credit to secure the
performance of InTransitBC and its construction contractor (SNC-Lavalin) during the construction
and operating periods. The presence of the at-risk capital, guarantees, and letters of credit should
ensure that the risks transferred to InTransitBC will remain with InTransitBC (see Appendix D for
more detail).
13 of 36
3.1.2 The Essential Elements and the Affordability Tests
The Local Funding Agencies established in their funding agreements numerous commercial and
technical specifications for the project. The Concession Agreement complies with each of the
Essential Elements, with a few minor exceptions, as noted in Appendix B.
GVTA also set requirements for affordability that had to be met before they would approve the
project. There are two tests:
1. a construction period test that involves comparing the total forecast construction period
costs to the forecast of funding available during that period; and
2. an operating period test that compares the net present value of CLCO’s payments to
InTransitBC during the operating period, plus the cost of managing the Agreement, to
the net present value of the project’s reasonably forecast sources of funding over the
operating period.
The tests exclude the cost of those aspects of the project that are directly funded and managed
by GVTA and the Cities of Vancouver and Richmond. This includes the provision of GVTA
designated policing units, certain operating period insurance policies, GVTA and City funding of
major road construction, cost of trolley wires, construction of bus loops and ticket vending
machines. Given that the tests exclude these costs, they cannot be, and are not intended to be
interpreted as comprehensive tests of overall affordability.
It should be noted that each of these tests is based on forecasts and assumptions and is subject
to uncertainty as discussed in the introduction to Section 3. At Financial Close, CLCO determined
that the tests had been met. A detailed discussion of the tests is provided in Appendix C.
14 of 36
3.1.3 Total Construction Cost and Funding
The total construction period cost of the project at Financial Close was $1,889 million ($2003) or
$2,050 million (nominal), and is summarized in Figure 3. CLCO’s funding of $1,331 million
(nominal) and InTransitBC’s $720 million (nominal) capital investment will cover the total cost.
The amounts in Figure 3 exclude costs, as outlined in the construction period affordability test,
that are outside of CLCO’s scope and that are being funded and managed directly by GVTA and
the Cities of Vancouver and Richmond.
1The City of Vancouver received a $7.8 million (nominal) grant from the Province in support of the redevelopment
objectives of the South East False Creek area, which is where the False Creek South Station is to be located.
15 of 36
3.2 Net Cost of the Project and the Public Sector Comparator (PSC)
To assist with its assessment of value for money, CLCO developed a methodology for comparing:
• the forecast net cost of the Agreement, including all public sector costs.
The methodology is based on financial and statistical modelling of costs and revenues and
associated risks over a 35-year period.
The evaluation criteria established during the competitive selection process was structured to
take these differences into account; in particular, to consider the differing amounts of incremental
ridership revenues generated relative to the revenues that would be generated if the system was
not built. This was achieved by comparing the net cost of the proposals (their gross cost less
their forecast incremental ridership revenue) over the 35-year term of the Agreement. For
example, a system that cost $1,600 million and that generated $300 million of incremental
ridership revenue would have a net cost of $1,300 million. This proposal would be preferred to a
system that cost less to build and operate, say $1,550 million but which only generated $200
million of incremental ridership revenue, resulting in a net cost of $1,350 million; $50 million more
than the first system (all figures expressed as net present values (NPV)2). The assessment of
value for money has been conducted on this basis.
2 Costs and revenues of the project are expressed as cash flow projections over the term of the Agreement (about 35
years). In order to reflect the time value of money, such cash flows are often presented in Net Present Value (NPV)
terms. NPV is calculated by applying a compounding discount rate to a stream of future cash flows. This calculation
reduces these cash flows to a single value reflecting the time value of money. All NPV amounts in this report, unless
otherwise stated, are the result of discounting annual costs and revenues to the year 2003, using a 6% nominal
discount rate.
16 of 36
The analysis compares the range of forecast net costs of the project and of the PSC after
considering estimates of:
• CLCO and GVTA management costs;
• construction costs, including expected (at the 50th percentile) impact of risk;
• operating costs, including (at the 50th percentile) impact of risk;
• the cost of private capital; and
• incremental ridership revenues (at the 50th percentile).
The construction and operating costs include costs within CLCO’s scope as well as costs that are
outside of CLCO’s scope, including GVTA and City managed costs, such as the cost of major
road construction, cost of trolley wires, construction of bus loops and ticket vending machines, the
cost of designated policing units, and ticket vending machine maintenance costs. The value for
money analysis does not account for the cost of public funding, because each of the PSC and the
project do not bear the cost of financing public sector funding. Nor does the analysis consider the
net bus costs saved by GVTA, as these are assumed to be the same for the PSC and the project.
The PSC is a public sector benchmark for the procurement, design, construction, and operation
of the project. Given that the provincial funding was conditional upon the project being developed
as a P3, the PSC is a hypothetical concept intended to provide a reasonable comparison with the
net cost of the project. The PSC is based on a conceptual design and procurement approach (or
reference project) developed by a team of over twenty experienced professionals including
transportation engineers and planners, transit system operations experts, quantity surveyors and
ridership experts. The PSC team developed the cost and revenue estimates for the PSC and
CLCO retained PricewaterhouseCoopers (PwC), a major international consulting firm with
significant P3 experience, to model and compare the net cost of the PSC with the project.
The reference project used for the PSC was peer-reviewed and value engineered by a panel of
experts from Canada, the US and the UK to ensure it was capable of being constructed and
operated efficiently. The value engineering of the reference design resulted in reductions in the
PSC construction and operating costs. Overall costs and risks were then assessed based on this
reference project and a public sector approach to procurement.
The procurement approach for the reference project assumed the use of several major design-
build contracts for tunnelling and elevated guideway construction, with design, price and
completion schedule risks allocated to private sector contractors. The remaining construction
work, including stations, was assumed to have been completed under separate contracts for
design and construction, with the majority of risks retained by the public sector. Responsibility for
integration of the civil works and electromechanical systems, operations and maintenance, and all
other related risks, were assumed to remain with the public sector.
The cost of the reference project was reviewed and amended at each stage of the procurement
process to reflect changes in scope, and more refined estimates of cost and risk as they became
available (e.g. property costs were updated following detailed research on property pricing by
CLCO). The PSC was effectively competing with the proposals put forward by the private sector
proponents during each of the stages of the procurement. Consequently, the PSC was not adjusted
to reflect InTransitBC’s innovations. In particular, the PSC does not include higher midday train
frequencies, the elimination of a station at the airport, the single tracking of the line in Richmond and
17 of 36
at the airport and the specific alignment and mixture of construction techniques in Vancouver and
Richmond. The PSC ridership forecast, as is discussed in Sections 3.2.7 and 3.2.8, is lower than
the project forecast. Had the PSC actually been constructed as designed, it is possible that the PSC
ridership could be increased by increasing midday train frequencies (but not by improving station
access times, as they cannot be materially improved once stations are constructed).
The PSC methodology was reviewed by KPMG, a major international firm with significant P3
experience, and by a former Auditor General for the Province, Mr. George Morfitt (see Appendix
A for detail).
The net costs of the PSC and the project will vary depending on the allocation and impact of risk.
The allocation of risk assumed for the PSC and agreed by contract for the project is summarized
in Figure 4.
Figure 4 shows that, under the Agreement, significantly more risk is transferred to InTransitBC
than would be transferred under the PSC approach.
18 of 36
3.2.4 Risk Assessment of the PSC
For the PSC, each risk retained by the public sector was assessed in detail by a team that included
representatives of CLCO, GVTA, Partnerships BC, Anthony Steadman and Associates
(professional cost estimators), British Columbia Rapid Transit Corporation (a subsidiary of GVTA
and the operator of the Expo and Millennium Lines), and experts in transit construction and
operations. Halcrow/TSi provided ridership forecasts using the same models and methodology used
to assess the proposals put forward by the various proponents. The purpose of this team was to
establish a consensus view that represented the best professional judgement of the participants of
the potential impact of each risk on cost and incremental revenue on a probabilistic basis.
For each cost item, the combined impact of risk was expressed as a premium over a risk-free
estimate. The risk-free estimates did not include any allowances for risk, contingency or margin.
The risk-free estimates can be considered as the lowest possible price that could be achieved
assuming contractors would not charge for risk and that the most optimistic results were achieved
in all circumstances.
For construction costs, the risk-free estimates were based on the project cost estimate, after
value engineering, less the contingencies included in the cost estimates. For example the cost of
constructing elevated guideway was assessed as having a risk-free cost of $162 million ($2003)
and the risks allocated to the public sector in respect of elevated guideway were projected to
have a minimum impact on cost of 5% (at the 5th percentile), an expected impact of 15% (at the
50th percentile) and a maximum impact of 25% (at the 95th percentile). Based on this example,
the range of cost for elevated guideway assessed in the PSC in $2003 was $170 million, $186
million and $203 million at the 5th, 50th and 95th percentile of risk.
CLCO developed a registry, the structure of which is based on precedents developed by the
provincial Risk Management Branch, of identified risks associated with the project. The registry
was developed with the input of CLCO staff, Local Funding Agency representatives, and
management representatives from other major infrastructure projects. CLCO engaged the
Performance Improvement and Risk Management Practice of PwC to review the registry and the
approach to identifying and estimating risks. The registry was updated throughout the
procurement and reflected the specific risk allocation to CLCO in the Concession Agreement at
Financial Close. The registry includes descriptions of the potential impact of each risk on cost,
delay and incremental revenue.
The aggregate impact of all risks identified and quantified for each of the PSC and the project
was assessed using statistical techniques which combine the impact of risks on the net cost of
each of the PSC and the project. This type of modelling methodology is widely accepted as valid.
The statistical analysis allows the impact of risks that are expressed in different ways and to
differing levels of confidence to be combined or aggregated into an overall risk distribution. For
example, many risks have been assessed at the 5th, 50th and 95th percentile (such as the impact
of risk on the cost of the guideway) while others, such as ridership, have been assessed at the
19 of 36
20th, 50th and 80th percentile. The statistical analysis expresses a combined risk impact
distribution as a range that covers 0 to 100th percentile of risk, even when some specific risks
cannot be precisely measured. The 5th and 95th percentile of risk have been chosen as the limits
to the distribution of risk as the 0 to 5th percentile range and 95th to 100th percentile range include
results that do not have any credible likelihood of occurring.
The PSC and the project cash flows are forecast over the 35-year duration of the Concession
Agreement. To take account of the time value of money and to provide a reasonable comparable
value, these cash flows have been discounted at a rate of 6% nominal to generate a net present
value of cost. Figure 5 shows the build up of the net cost of the PSC and the project in NPV terms.
The gross cost for the PSC, after accounting for the expected impact of risk (at the 50th percentile)
and the cost of private capital, but before accounting for expected incremental ridership revenue (at
the 50th percentile), is $56 million (NPV) lower than the project. The net PSC cost, after accounting
for incremental ridership revenue (at the 50th percentile), is $1,750 million (NPV).
Project PSC
3
CLCO Costs 120 98
4
Construction Costs
Risk-free Estimate 1,382 1,263
Risk & Contingency 30 242
1,412 1,505
4
Operating Costs
Risk-free Estimate 577 559
Risk & Contingency 0 21
577 580
3CLCO Costs include procurement, management, and net property costs. The CLCO Costs under the project are
expected to be $22 million (NPV) higher than for the PSC.
4 PSC Construction and Operating Costs, as discussed in Section 3.2.4 include estimates of retained risk and
contingencies. Construction and Operating Costs for the project include risks that are retained and funded by CLCO.
Risk on Construction Period Costs is expected to have a material impact ($242 million (NPV)) under the PSC and a
much smaller impact on project costs ($30 million (NPV)) because construction risks have been substantially
transferred to InTransitBC.
5 Cost of private capital includes the cost of interest payments on debt and return on equity capital.
20 of 36
The net cost of the project, including the expected impact of risk (at the 50th percentile) is $1,658
million, or $92 million (NPV) less than the net cost of the PSC. The expected (at the 50th
percentile) incremental ridership revenue of the project is $148 million NPV greater than with the
PSC. The higher forecast ridership revenue for the project at both peak and midday hours is due
to more accessible station designs (shorter access times from the station entrance to the train,
e.g., fewer stairs to climb), train design and more frequent train service. Specifically, the higher
midday ridership for the project (about one-third higher) is due to more frequent train service at
midday.
The range of impact of risk at the 5th and 95th percentile of risk for both the PSC and the project is
shown in Figure 6.
2,100
2,000
1,900
268
1,800
95th Percentile 50th Percentile
1,748
1,750
1,700 90
50th Percentile
1,658
229
90
1,600 5th Percentile
5th Percentile
1,568
1,500
1,521
1,400
Project PSC
0
Project PSC
Figure 6: Range of Expected Cost of the PSC and Project ($ million NPV)
• risk can be expected to have less combined impact on the net cost of the project than of
the PSC (illustrated by the narrower range of costs above) because more risk is
transferred to InTransitBC. This means that there is more certainty on the forecast net
cost of the project than of the PSC;
21 of 36
• at the expected level of risk impact (the 50th percentile of risk, shown in the central boxes)
the project has a forecast net cost of $1,658 million, which is $92 million lower than the
PSC’s forecast net cost of $1,750 million;
• if the impact of risk is large (at the 95th percentile for both PSC and the project) the
forecast net cost of the project is $270 million less than the PSC’s forecast net cost; and
• if the impact of risk is small (at the 5th percentile for both the PSC and project) the forecast
net cost of the project is $47 million more than the PSC’s forecast net cost.
Incremental ridership is the difference between the number of transit users that are forecast to
use the overall Greater Vancouver transit system with or without the project. The NPV of
incremental ridership revenue forecast of the project and of the PSC is $581 million and $433
million respectively, a difference of $148 million. It should be noted that the assessment of
ridership on an incremental basis tends to exaggerate the differences between the project and
the PSC ($148 million is a 34% difference). For example, the total ridership revenue in the
corridor is determined by adding the estimate of the base ridership revenue, which would
otherwise be generated in the corridor if the line was not built, to the estimated incremental
ridership revenue.
900
806
800
700 658
600
500 581
Incremental
Ridership
433
400
300
200
Base Ridership
100 225 225
0
Project PSC
Figure 7 shows the same difference of $148 million, but the difference is now equivalent to 22%
more than the PSC. Finally, it is important to note that the difference between the ridership
delivered by the project and the PSC is 2.3% when assessed in terms of the impact on the overall
integrated GVTA system.
22 of 36
2,100
1,900
221
1,800
1,748 95th Percentile 50th Percentile
1,750
65
1,700
50th Percentile
25 25 182
1,658
25 25
1,600 65 5th Percentile
5th Percentile
1,568 47
1,500
1,521
1,400
Project PSC
0
Project PSC
In Figure 8, the range of expected cost at the 5th and 95th percentiles of risk before the inclusion of
ridership risk is shown in blue for the project and brown/yellow for the PSC. The amount shown in
green is the difference in the overall risk estimate generated by the statistical analysis with and without
including a risk range for ridership revenue of plus or minus 15% at the 20th and 80th percentile.
Figure 8 shows that the range of expected net cost of the PSC and the project overlap. However,
a significant proportion of the variation relates to incremental ridership revenue. The variability of
the forecasts of plus or minus 15% applies equally to the project and the PSC. It would be
unreasonable to assume that the minimum cost could be achieved for the project (assuming
maximum revenue) while the maximum cost is achieved for the PSC (assuming minimum
ridership revenue), or vice versa.
Figure 8 also shows that the risk range of the project is narrower than that of the PSC and that:
• ridership revenue risk is greater for the project (by approximately one third) because it is
projected to generate around one third more ridership revenue;
• of the total risk ranges shown at the 5th and 95th percentiles, 72% of the variability of the net
cost of the project relates to ridership revenue risk compared to around 19% for the PSC;
and
23 of 36
• risks other than ridership could have an impact of plus or minus $25 million on the net cost
of the project, compared with a range of plus $221 million to minus $182 million for the
PSC.
Based on this analysis, the net cost of the project, before considering ridership revenue risk,
appears considerably more certain than that of the PSC, reflecting the enhanced risk transfer of
the project.
The assessment of net cost in this report has been prepared using a discount rate of 6% nominal,
which is the rate GVTA uses to assess the economics of various transportation capital projects6.
To assess whether the net cost analysis is sensitive to the discount rate, sensitivity analysis has
been performed using two discount rates:
• 5% nominal; and
The impact of the change in discount rate on cost is greater for the project than the PSC. This is
because a greater proportion of the project’s costs occur over the operating period as a portion of
capital costs are financed with private capital whereas the full cost of building the line is paid
during construction in the PSC.
Figure 9 shows that the difference in Net Cost between the project and the PSC is sensitive to the
discount rate utilized; however, the expected (at the 50th percentile) Net Cost of the project
remains lower than that of the PSC throughout the sensitivity range.
Discount Rate Net Cost Project Net Cost PSC Difference in Cost
6 In 2004, GVTA lowered its capital analysis discount rate from 7% to 6%.
24 of 36
3.3 Transportation Benefits
CLCO also evaluated the transportation benefits generated by the project and the PSC and
concluded that the project can be expected to provide greater transportation benefits to the
Canada Line corridor transportation users than the PSC.
Transportation benefits provide an indication of the relative benefits to users of implementing one
system versus another system without performing a detailed benefit/cost analysis. The benefits
are measured by assigning an aggregate value to the time that transportation system users would
save as a result of the impact of each of the project and the PSC on the corridor transportation
system. The transportation benefits are $773 million in NPV terms for the PSC and $849 million in
NPV terms for the project over the 35-year term. The project generates $76 million, or 10% more
transportation benefits than the PSC. The difference in transportation benefits is related to the
expected difference in estimated ridership between the project and the PSC.
25 of 36
Appendix A External Scrutiny of CLCO’s Work
• the Methodology as documented in the PwC January 20, 2004 PSC Report [the report
summarizes the methodology used to construct the PSC, the scope of the PSC and the
cost and revenue for the PSC] is appropriate to the project;
• the PSC project team appear to have followed sensible processes for developing the
assumptions of the PSC;
26 of 36
• the assumptions driving the PSC have been
"... the methodology as documented appropriately and consistently applied; and
in Appendix 1 of the PSC Report
follows sensible processes for • the PSC as documented in the PSC Report
developing the assumptions in represents a reasonable basis for the
the PSC"; estimation of the potential public sector costs
and risks and the assessment of value for
"... the PSC as documented in the money. Proper value for money analysis will
require a like-to-like comparison of the PSC
PSC Report represents a
and the cost of the P3 proposal. Careful
reasonable basis for the
consideration is needed in reconciling cost
estimation of the potential public
and risk profiles between the PSC and the P3
sector costs and risks for the proposal to ensure that the comparison is
purpose of assessing value for valid.
money"; and
In addition, in April 2004, CLCO asked George
"... the conclusions of the PwC draft Morfitt, former Auditor General for the Province of
report dated March 30, 2004, British Columbia, to review the PSC and RFP
entitled 'RAV Project: Value for Stage Value for Money Report.
Money' are reasonable."
George Morfitt,
April 2004
27 of 36
Appendix B The Essential Elements
Essential Elements
Milestone Payments set out in a BAFO Submission must not exceed the Agency funding contributions.
The net new revenues generated by the System together with the operating and debt service
savings from reduced bus services and other Contributing Agency contributions, will cover the
Availability Payments and Quality Payments during the Operating Period as described in a
BAFO Submission.
For a partially grade-separated system, at-grade pedestrian and vehicle crossings must be
maintained at Cambie and 49th, 57th and 59th Avenues, with additional at-grade pedestrian
crossings in the vicinities of 54th and 62nd Avenues. For a fully grade-separated system, grade-
separated pedestrian and vehicle crossings must be maintained at Cambie and 57th and 59th
Avenues, with additional pedestrian crossings in the vicinities of 54th and 62nd Avenues.
There will be no net loss of green space on the Cambie Heritage Boulevard in Vancouver and the
Heritage landscape and urban design values of the Cambie Heritage Boulevard should be
retained. Any trees removed must be replaced with trees of a species and diameter approved by
CLCO.
28 of 36
Essential Elements
The System will deliver a capacity that is 15% greater than the forecast peak demand at the
maximum load point (defined as the AM peak leading into the Broadway Station in the
northbound direction).
The System must be capable of expansion to 15,000 passengers per hour per day without
significant changes to the existing physical infrastructure.
Stations will be designed to accommodate the possible future installation of ticket gates.
7 2nd Avenue Station has since changed its name to False Creek South.
29 of 36
Essential Elements
Modal Integration:
a) off-street bus facilities will be provided at the following Stations:
• Marine Drive Station;
• Bridgeport Station;
• Richmond City Centre Station
b) the layout of other Stations will be such as to facilitate easy transfer to on-street buses
c) a 1,200 car park-and-ride will be provided at Bridgeport Station
d) the Broadway Station must be designed so as to allow for a future transfer connection to
either an underground extension of the existing “Millennium Line” or an at-grade light rail line
on Broadway.
Every train will have dedicated spaces for two bicycles, and bicycle storage at Stations including
racks and lockers will be provided where it is appropriate given the likely demand and available
space.
GVTA will market and brand the System and specify the System identifiers that will be located at
Stations and on Vehicles.
The first level of security will be provided by the concessionaire. A second level of security such
as policing will be provided by GVTA or some other competent authority as determined by
GVTA.
The Richmond Terminus Station will be designed in a manner that will not preclude a future extension of
the System.
At Stations on the Airport Connector YVR will maintain control of advertising and commercial
activities and receive associated revenues.
There will be no charge to passengers for rides that start and end on Sea Island.
Uniform and consistent pricing must be applied to similar works across all Cost Centres.
All work will comply with the requirements of all Permits including those of YVR.
Design and operation of the System will consider the needs of airline passengers, including the
accommodation of baggage.
Design of the System will consider the use of the System by cruise ship passengers moving
between the Airport and cruise ship terminals.
30 of 36
Appendix C The Affordability Tests
The first of the two tests is an assessment of whether the funding available to CLCO is sufficient
to meet all of CLCO forecast costs over the construction period. The funding available to CLCO
during the construction period from each of the agencies, the City of Vancouver and sale of
excess Bridgeport Parkade parking capacity is shown in Figure 11.
Figure 11 shows that $1,331 million (nominal) of construction period funding is committed to
CLCO. The Province has committed to contingent funding of an additional $15 million (nominal),
provided that GVTA match this amount, for a total of $30 million. The contingent funding is not
included in the $1,331 million (nominal) of construction period funding and is intended to fund
extraordinary cost of risk in excess of the $41 million (nominal) CLCO funded risk contingency
discussed below.
CLCO uses of funds (see Figure 11) during the construction period include:
• CLCO costs, including construction period management costs, property acquisition costs
and overall construction period risk contingency; and
• the milestone payments paid, as scheduled in the Agreement, to InTransitBC for the
construction of the project.
Costs related to the project, but not included in the Construction Period Test include Major Road
Network costs, cost of trolley wires, construction of bus loops and ticket vending machines. These
activities are not being managed by CLCO; rather they are being managed and funded directly by
GVTA. The Cities of Richmond and Vancouver also fund and assist with the management of the
Major Road Network.
CLCO is not exposed to construction cost overruns incurred by InTransitBC, so does not carry a
contingency to fund such overruns. Rather, CLCO is exposed to and has funds for a $41 million
(nominal) contingency for construction delay costs that may arise from CLCO’s own actions or the
actions of other public sector authorities, higher-than-anticipated property acquisition costs, and
other risks retained by CLCO (see Figure 4). CLCO’s construction period costs, including
management, property acquisition and the risk contingency, are expected to be $186 million
(nominal).
CLCO’s expected net cash position over the construction period, as shown in Figure 11, is
$1 million (nominal), confirming that CLCO expects to have sufficient funding to meet its costs
over the construction period and thereby meeting the construction period test.
31 of 36
$2003 Nominal
Figure 11: CLCO Sources and Uses of Funds - Construction Period ($ million)
32 of 36
The second of the two tests is an assessment of whether CLCO’s costs are equal to or less than
CLCO’s sources of funding during the operating period. This test has been performed on a NPV
basis (see Appendix E for a detailed discussion) using a discount rate of 6% nominal to discount
cash flows back to April 1, 2003. This discount rate is used by GVTA in the economic analyses of
its capital projects. The net present value of CLCO’s sources of funding and costs is shown in
Figure 12.
NPV
Net Funding 9
The operating period test excludes costs that are funded and managed directly by GVTA (i.e.
outside of the affordability test set out in the Agency funding agreements), including the cost of
certain insurance policies, designated policing units, and the collection of fares. Based on this
analysis, CLCO forecasts a funding surplus of $9 million in NPV terms during the operating
period. The operating period affordability test has therefore been satisfied.
8 This amount of $181 million is the NPV of payments forecast to be made by the Province in support of the investment
by InTransitBC of $166 million (nominal) of capital during construction, including interest during construction and
reflecting InTransitBC’s cost of capital. This report describes the contributions CLCO receives from the Province and
the other agencies; it does not describe how the agencies themselves formally account for their contributions to CLCO.
33 of 36
Appendix D Capital At-Risk
Under the Agreement, CLCO is primarily insulated from risk of InTransitBC’s failure to perform by
the $720 million of private capital invested by InTransitBC. The value of this capital over the 35-
year term of the Concession Agreement is shown in Figure 13. The amount of capital at-risk
decreases during the operating period as a portion of each performance payment is used to
repay the private capital. This reduction in capital at-risk is acceptable given that CLCO’s
exposure to a default by InTransitBC also declines with time.
800
700
600
500
400
300
200
100
0
2005
2007
2009
2011
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
Figure 13: Value of InTransitBC’s Investment ($ million) 2039
34 of 36
Additionally, CLCO has a security interest in the support arrangements in place between
InTransitBC, its equity investors and its sub-contractors. The design and construction sub-
contractor to InTransitBC is SNC-Lavalin Inc. The security arrangements (see Figure 14) include:
• a $600 million construction guarantee from SNC-Lavalin Group Inc.9, which is further
supported by a $159 million letter of credit;
• a $50 million operating guarantee from SNC-Lavalin Group Inc., which is further
supported by a $10 million letter of credit.
800
700
600
500
400
300
200
100
0
2005
2007
2009
2011
2013
2015
2017
2019
2021
2023
2025
2027
2029
2031
2033
2035
2037
2039
If InTransitBC defaults and is terminated during construction, the minimum amount of at-risk
capital available to CLCO is $720 million, the sum of the invested capital and the InTransitBC
support arrangements (this at-risk capital is in addition to SNC-Lavalin’s construction contract
contingency and profit which would most likely be spent by SNC-Lavalin Inc. in its efforts to avoid
a default and termination). If, during the operating phase, a default occurs and InTransitBC is
terminated due to sustained under-performance, the $720 million of at-risk capital declines after
2010. The minimum amount of at-risk capital is the sum of the $720 million of equity and debt
and the then current value of CLCO’s security interest in the InTransitBC support arrangement.
35 of 36
Appendix E Discounting
The costs of the project are expressed as cash flow projections over the term of the Agreement.
In order to reflect the time value of money such cash flows are often presented in NPV terms. An
NPV is calculated by applying a compounding discount rate to a stream of future cash flows. This
calculation reduces these cash flows to a single value reflecting the time value of money. The
rate that is used to discount future cash flows is therefore important.
Figure 15 shows that a dollar received in five years’ time, using a discount rate of 5%, is worth 78
cents today.
Amounts can be expressed in “nominal” or “real” dollars. Nominal amounts are stated in the
current dollars of the day and include the effects of inflation. Real amounts are stated in the
currency of a specific year and remove inflation. For example, if inflation is 2.1% per annum, a
real amount of $1,000 in 2003 would be equivalent to a nominal amount of $1,021 in 2004.
The discount rate applied therefore needs to match the currency of the cash flows being
discounted. A cash flow of nominal amounts would be discounted using a nominal rate of 6%,
whereas the same cash flow expressed in real terms (i.e. before the impact of inflation) would be
discounted at 3.8% (calculated as 106%/102.1% - 1).
All NPV figures in this report are in net present values discounted back to April 01, 2003 using a
nominal rate of 6.0% unless otherwise stated.
36 of 36