Tut-6-Project Management-Solution
Tut-6-Project Management-Solution
Tut-6-Project Management-Solution
1. The R&D department is planning to bid on a large project for the development of a
new communication system for commercial planes. The table below shows the project
to be scheduled using CPM.
a. See above.
b. A-B-D-E-H
c. 15 weeks, 1+4+2+5+3.
d. C: 3 weeks; F: 1 week; and G: 1 week.
Page 1 of 6
2. A project is broken down into the following 9 activities:
a. See above. Note that G has both D and F as immediate predecessors. However, D
is redundant because F has D as an immediate predecessor (D→G is not needed).
b. A-C-F-G-I and A-D-F-G-I.
c. E is not on a critical path and has slack of 4; therefore, do not shorten E as it will
not change the project completion time. Shorten C, D, and I two days each. C and
D are on parallel critical paths, reducing them will only reduce project completion
time by 2 days. Below is an illustration. Shorten C&D first then I. The sequence
of shortening does not affect Part d answer.从后往前 1 天 1 天 shorten
process
Activity Shortened day I I C&D C&D
ABEI 14 13 12 12 12
ACFGI 18 17 16 15 14
ADFGI 18 17 16 15 14
ADHI 13 12 11 10 9
d. A-C-F-G-I and A-D-F-G-I. Project completion time is reduced from 18 to 14 days
Page 2 of 6
3. Daily Bakery is building a new automated bakery in Tai Po. The following table
contains the activities that need to be completed to build the bakery and install the
equipment.
9 17 24 29
B (8) D (5)
0 9 20 28 28 33
33 35
A (9)
F (2)
0 9
9 24 24 33 33 35
C (15) E (9 )
9 24 24 33
a. See above.
b. See the table below.
c. See the table below.
Page 3 of 6
6 11 16 19
B (5) D (3)
0 6 12 17 17 20
20 21
A (6)
F (1)
0 6
6 16 16 20 20 21
C (10) E (4 )
6 16 16 20
Activity Crashed E E E E A A A C
LENGTH
ABDF - 24 24 24 24 24 23 22 21 21
ACDF - 31 31 31 31 31 30 29 28 27
ACEF - 35 34 33 32 31 30 29 28 27
Crash cost 2500 2500 2500 2500 3000 3000 3000 4000
Cumulative Cost 2500 5000 7500 10000 13000 16000 19000 23000
Page 4 of 6
4. Assume the network and data that follow:
Activity Immediate Normal Time Normal Cost Crash Time Crash Cost
Predecessor
A None 5 $7000 32 $13000
B A 10 12000 73 18000
C A 8 5000 7 7000
D B 6 4000 51 5000
E C 7 3000 6 6000
F C 4 6000 3 7000
G D,E,F 4 7000 31 9000
a.
Page 5 of 6
Activity Normal Normal Cost Crash Time Crash Cost NT-CT Cost/week
Time (NT) (NC) (CT) (CC) to expedite
A 5 $7,000 3 $13,000 2 $3,000
B 10 12,000 7 18,000 3 2,000
C 8 5,000 7 7,000 1 2,000
D 6 4,000 5 5,000 1 1,000
E 7 3,000 6 6,000 1 3,000
F 4 6,000 3 7,000 1 1,000
G 4 7,000 3 9,000 1 2,000
Crash cost 不能直接用 CC-NC/NT-CT
Activity Crashed D G A
ABDG 25 24 23 22
ACEG 24 24 23 22
ACFG 21 21 20 19
Crash Cost $ 1,000 $ 2,000 $ 3,000
Page 6 of 6