Progressive Cavity Pump
This operating and assembly instruction is only
for general information.

Type
BN 025-12 XSto 1-6L

Issue 26.06.2017
Index

1 Safety ....................................................................................................................................................
Safety....................................................................................................................................................
....................................................................................................................................................11
1.1 General notes
1.2 Safety and warning notes
1.2.1 Warning notes
1.2.2 Danger symbols
1.2.3 Information symbols
1.3 Dangers that can be caused by the machine
1.4 Qualification of the personnel
1.5 Authorised people
1.5.1 Tasks and information for the owner/operators
1.5.2 Safety notes for maintenance, inspection and assembly work
1.6 Personal protective equipment
1.7 Safety and protective devices
1.8 Foreseeable misuse
1.9 Designated use
1.10 Warranty

2 Description of the pump ........................................................................................................................


pump........................................................................................................................
........................................................................................................................55
2.1 General description
2.2 Mode of action and pumping principle of the pump
2.3 Constructive design

3 Technical Data ......................................................................................................................................


Data......................................................................................................................................
......................................................................................................................................66

4 Transport, Intermediate storage, Disposal ............................................................................................


Disposal............................................................................................
............................................................................................88
4.1 Safety
4.2 Transport
4.2.1 Dimensions, weight and centre of gravity
4.2.2 Symbol
4.2.3 Lashing points (AP) for lifting devices
4.2.4 Unpacking the machine
4.3 Temporary storage/corrosion protection
4.4 Disposal
Index

5 Assembly / Installation ........................................................................................................................ 11


Installation........................................................................................................................
5.1 Mounting tools / lifting gear
5.2 Space requirement
5.2.1 Dimension for stator replacement
5.3 Assembly of the complete mounted pump
5.4 Power supply of the pump
5.5 Pipelines
5.5.1 Suction and pressure connection
5.5.2 Pipeline dimensions
5.5.3 Residue-free pipelines
5.5.4 Tension-free assembly

6 Commissioning / De-Commissioning ..................................................................................................


De-Commissioning.................................................................................................. 13
..................................................................................................13
6.1 Commissioning report............................................................................................................ 13
6.2 Measures before commissioning............................................................................................ 14
6.2.1 Checking pipelines
6.2.2 Protective devices on the pump
6.2.3 Electrical / hydraulic connections
6.2.4 Direction of rotation check
6.2.5 Additional devices - optional
6.3 Initial commissioning/repeated commissioning
6.3.1 Avoiding dry running of the pump
6.3.2 Pressure in the suction and pressure connection
6.4 De-commissioning
6.4.1 Switching off the pump
6.4.2 Emptying the pump
6.4.3 Dismantling the pump
6.4.4 Preservation/storage of the pump

7 Maintenance ....................................................................................................................................... 19
Maintenance.......................................................................................................................................
7.1 Preventative measures
7.1.1 Pump down-time
7.2 Lubrication
7.2.1 Joint grease
7.3 Inspection

8 Malfunctions, causes, rectification ...................................................................................................... 21


rectification......................................................................................................

9 Pump Dismantling / Reassembly ........................................................................................................


Reassembly........................................................................................................ 23
........................................................................................................23
9.1 Pump Dismantling / Reassembly........................................................................................... 23
9.1.1 Prepare the pump for dismantling
9.1.2 Dismantling
9.1.3 Reassembly
Index

9.2 Rotating unit – individual parts .............................................................................................. 29


9.2.1 Dismantling
9.2.2 Rotating unit (RTE) - prepare individual parts for reassembly
9.2.3 Rotating unit (RTE) - individual parts - reassembly
9.3 Holding band - assembly........................................................................................................ 33
9.3.1 Prepare the holding band
9.3.2 Check the holding band
9.3.3 Assembling the holding band
9.3.4 Correct tension for the holding band (HBD)
9.3.5 Cant up the holding band
9.3.6 Shear the holding band
9.3.7 Check the holding band after assembly
9.4 Mechanical seal ..................................................................................................................... 35
9.4.1 Safety
9.4.2 Application conditions and material version

10 Spare parts ......................................................................................................................................... 36


parts.........................................................................................................................................
10.1 Order template for spare parts............................................................................................... 38

11 Special tools ....................................................................................................................................... 41

12 Related documents .............................................................................................................................


documents............................................................................................................................. 42
.............................................................................................................................42

13 Appendix .............................................................................................................................................
Appendix............................................................................................................................................. 44
.............................................................................................................................................44
13.1 Manufacturer's documents / suppliers

Subsidiaries
1
Safety
1.1 General notes
¾ Always keep the operating and maintenance instructions close by the machine.
¾ If problems cannot be solved with reference to the operating and maintenance instructions,
please contact the manufacturer.
Observe the following points in addition to these operating and maintenance instructions:
• Prohibition, warning and mandatory signs, warning notes on the machine
• Relevant laws and ordinances
• Statutory provisions on accident prevention
• Corresponding harmonised standards and regulations

1.2 Safety and warning notes


¾ Comply with safety and warning notes for safe and efficient use of the product.
Signal words for specific dangers and (possible) consequences are explained below. These
are supplemented by symbols (pictograms) if necessary.

1.2.1 Warning notes

NOTICE
Caution for machine!
Possible danger.
Material damage can occur.

CAUTION

Caution for people and machine!


Possible danger.
Minor injury or damage to property can occur.

WARNING

Warning for people!


Possible danger.
Death or serious injury can occur.

DANGER

Danger for people!


Possible danger.
Immediate risk of sever or fatal injury.

1.2.2 Danger symbols

Warning: Warning:
Suspended load. Dangerous electrical
voltage.

Ausgabe
issue
D / 06.01.2014 Dokument
document
OM.SAF.01e Blatt
sheet
1 (4)
1
1
Safety
1.2.3 Information symbols

NOTICE

Ensure environmen- Wear eye protection.


tal protection.

¾ Instruction to act/take measures


• List item

1.3 Dangers that can be caused by the machine


seepex machines are built in accordance with the state of the art.
Nevertheless, there is a residual risk, because the machine works with:
• Mechanical movements that pose a danger
• Electrical voltages and currents
We have used design measures and applied safety technology to minimise the risk to the
health of people posed by this danger.

1.4 Qualification of the personnel


This handbook is intended for:
• Owner
• Operators
• Setters
• Maintenance personnel

1.5 Authorised people


People authorised to undertake operation, set up and maintenance are instructed and trained
specialists employed by the owner/manufacturer.

Detailed technical knowledge is essential for performing any work on the machine.

The owner is responsible for:


• Personnel training
• Compliance with safety regulations
• Compliance with operating and maintenance instructions
The operator must:
• Have received instruction
• Read and understood the relevant parts of the operating instructions before starting work
• Know the safety devices and regulations

Ausgabe
issue
D / 06.01.2014 Dokument
document
OM.SAF.01e Blatt
sheet
2 (4)
2
1
Safety
1.5.1 Tasks and information for the owner/operators
¾ Regularly check and maintain the machine, replacing all parts in good time which no longer
guarantee safe operation.
¾ It is essential to comply with the procedure described in the operating instructions for shut-
ting down the machine.
• On completion of work, attach all safety and protective devices and make sure they are
functioning.

1.5.2 Safety notes for maintenance, inspection and assembly work


¾ Do not work on the machine or system unless it is stationary and depressurised.
¾ Switch off the master switch and pull out the power plug before starting work on live com-
ponents.
¾ Comply with the procedure for shutting down the machine as described in the Shut-down
chapter.
¾ Decontaminate (de-toxify) machines that are used for pumping media that can be harmful
to health.
¾ Refer to the Initial start-up chapter before repeated start-up of the machine.

1.6 Personal protective equipment


¾ Wear personal protective equipment and/or additional equipment for your own safety.
¾ Avoid/limit risks by the use of collective technical protective equipment or by organisational
measures at work.

1.7 Safety and protective devices


¾ Prior to start-up, bolt seepex machines onto a concrete foundation so as to ensure stability.
¾ Starting and stopping devices must be clearly recognisable. Take appropriate measures to
avoid defects.
• No protective device is necessary for checking and/or setting the shaft seal.
• Hot surfaces are identified with a danger symbol on the machine.

1.8 Foreseeable misuse


Serious personal injury and damage to property can be caused by:
• Incorrect use
• Incorrect installation or operation of the machine
• Impermissible removal of necessary protective equipment

Ausgabe
issue
D / 06.01.2014 Dokument
document
OM.SAF.01e Blatt
sheet
3 (4)
3
1
Safety
1.9 Designated use
• Only use seepex machines if they are in perfect condition and in compliance with the oper-
ating and maintenance instructions.
• Do not start up the machine unless the system in which the machine is installed is in accor-
dance with the provisions of the applicable guidelines and statutory regulations.
• Equivalent sustained sound pressure level at workplaces of operating personnel C75 dB
(A). Cavitation-free operation of the machine and screwed connection to concrete founda-
tion are essential.
• seepex machines are components that are exclusively intended for pumping media in ac-
cordance with the technical data (→ chapter 3). Written approval must be obtained from the
manufacturer before other media are pumped.
• Refer to the information on the type plate and the operating instructions for technical data
(→ chapter 3), and comply with them.
• The operating instructions are assigned to the seepex machine based on the commission
number.

Fig. 1-1 Similar illustration

1.10 Warranty
• Warranty in accordance with our terms and conditions of delivery and order confirmation.
• It is a condition of the machine warranty that the machine must correspond to the listed op-
erating instructions in accordance with the type plate/data sheet.
• All wearing parts are excluded from the warranty.
• These operating instructions are subject to copyright. Reproduction is not permitted and will
be punished. Contravention will be pursued through the courts.

Ausgabe
issue
D / 06.01.2014 Dokument
document
OM.SAF.01e Blatt
sheet
4 (4)
4
2
Description of the pump

2.1 General description


seepex pumps are members of the group of rotating displacement pumps.
• Characteristic features
– Special configuration/arrangement of the rotor and stator pumping elements.
– Motion sequence

2.2 Mode of action and pumping principle of the seepex pump


• Sealing bands are produced through geometric design/contact of both conveying elements.
• Sealing bands ensure a perfect fit between the suction and pressure side.
Result:
– Increased pump suction.
– Higher pressure build-up independent of speed possible.

2.3 Constructive design

No. Designation
ANT Drive
200 Lantern
307 Plug-in shaft
400 Coupling rod
SEA Shaft seal
500 Suction casing
600 Rotor
RTE Rotating unit
601 Stator
700 Pressure branch

Ausgabe Dokument Blatt


issue B / 12.11.2012 document OM.DES.01e sheet 1 (1) 5
6
3
Technical data

3.1 Data sheet

3.2 Characteristic Curves

3.3 Declaration

• Data sheet, characteristic curves and declarations are commission specific documents
and not part of this not binding operating and assembly instruction.

Ausgabe Dokument Blatt


issue A / 29.06.2017 document OM.TED.XXe sheet 1 (1) 7
8
4
Transport, Intermediate storage, Disposal
4.1 Safety

CAUTION

Damage to property/injuries due to incorrect transport


Slight injury or damage to property can occur
¾ Comply with the safety notes and transport notes on the packaging.
¾ Use suitable means of transport, lifting devices and tools.
¾ Use protective equipment.

4.2 Transport

4.2.1 Dimensions, weights and center of gravity


¾ Note the dimensional drawing (→ chapter 5.6).

4.2.2 Symbols
• Meaning of symbol

Top Fragile Against moisture Centre of gravity Lashing points


item protect

4.2.3 Sling points (AP) for lifting devices

WARNING

Warning of suspended load.


Death of serious injury can occur.
¾ Use the lashing points (AP) for lifting divices.
¾ Note the centre of gravity (→ dimensional drawing, chapter 5.6).

Lifting machine Industrial trucks

4.2.4 Unpacking the machine


¾ Comply with the symbols and notices on the packaging.
¾ Remove the screwed connection between the machine and packaging.
¾ Remove the machine with a lifting machine/industrial truck.

4.3 Temporary storage/Corrosion protection


• All seepex machines have corrosion protection applied as standard prior to transport.

Ausgabe
issue
D / 27.08.2012 Dokument
document
OM.TRA.01e Blatt
sheet
1 (2)
9
4
Transport, Intermediate storage, Disposal

NOTICE
Damage to property if corrosion protection is missing
Property damage can occur due to corrosion.
¾ Temporary storage must be in a dry, enclosed, frost-free room in order to provide protec-
tion against ambient influences.
¾ Contact seepex regarding the necessary corrosion protection for temporary storage.

4.4 Disposal

NOTICE
Environmental protection
Material damage can occur.
¾ Drain the pumping medium and dispose of it in accordance with the regulations.
¾ Dispose of the machine with regard to its composition and existing regulations.

Ausgabe
issue
D / 27.08.2012 Dokument
document
OM.TRA.01e Blatt
sheet
2 (2)
10
5
Assembly / Installation

5.1 Mounting tools / lifting gear

CAUTION

Pump falling over.


Slight injury or damage to property can occur.
¾ Adhere to the lifting tool’s starting point.
¾ Pay attention to the dimensions, weight and centre of gravity of the pump.
¾ Use suitable mounting tools/lifting gear.

5.2 Space requirement


The required space should be determined by considering the following factors:
• Dimensions and weight.
• Requisite transport and lifting equipment.
• Pipe routing – dismantling (dimension for stator replacement).

5.2.1 Dimension for stator replacement (P)


¾ Refer to the dimensional drawing.

5.3 Assembly of the complete mounted pump


¾ Assemble according to technical data (→ chapter 3.).
¾ Note dimensional drawing.

Tension-free mounting of the pump


¾ Balance unevenness with suitable supports.
• Applies to mounting on foundations/load-bearing elements.
• Total areas of all pump bearing areas are resting on the surface.

Correct position of the drives


• All drives are set up ready for operation and mounted.
• Correct displacements of the drive during transport/installation of the pump by adjusting/fix-
ing the drive.

CAUTION

Safety protection equipment.


Slight injury or damage to property may result.
¾ Connect safety protection equipment and activate.

Ausgabe Dokument Blatt


issue C / 11.10.2012 document OM.INS.01e sheet 1 (2) 11
5
Assembly / Installation
5.4 Power supply of the seepex pump

DANGER

Supply voltage and power frequency.


Death or serious injury will result.
¾ Heed type plate on the pump.
¾ Pay attention to manufacturer’s directions (→ chapter 13.).
¾ Pay attention to safety regulations.

5.5 Pipelines

5.5.1 Suction and pressure connection


• Refer to the dimensional drawing for the position, nominal width and standard.
• Note direction of rotation/flow direction.

5.5.2 Pipeline dimensions


• Adhere to specifications regarding pressure in the pressure respectively suction connec-
tion.
• Note technical data (→ chapter 3.).
• Nominal width of suction pipe = nominal width of suction connection of pumps.

5.5.3 Residue-free pipelines

NOTICE
Damage to property through assembly residue.
No claims under guarantee if violated.
¾ Keep all pipe work free of foreign objects.
¾ Remove weld spatters, screws, steel chips etc.

5.5.4 Tension-free assembly


¾ Assemble pipelines and other components in a tension-free manner on the pump.

Ausgabe Dokument Blatt


issue C / 11.10.2012 document OM.INS.01e sheet 2 (2) 12
6
Commissioning / De-commissioning
Master Copy

6.1 Commissioning report

Send commissioning report online to From:


www.seepex.com\
Must be specified with every order!
Commission: Model: Contact person: .............................................
Tel.: ................................................................
_________________________ _____________________ Fax: ...............................................................
E-mail: ...........................................................

Customer Service: Germany Phone:+49 2041.996-231 Address of plant:


seepex GmbH Fax: +49 2041.996-431 .......................................................................
Postfach 10 15 64 Rest of Phone:+49 2041.996-224 .......................................................................
D-46215 Bottrop Europe Fax: +49 2041.996-424 .......................................................................
[email protected] Outside Phone:+49 2041.996-120 .......................................................................
Europe Fax: +49 2041.996-432 .......................................................................

Delivery date:
Date of installation:
Assembly check carried out on:

Please enter operational data:


Conveying liquid:
Temperature:
Fuse level/motor protection or power
consumption

Frequency control no

yes If yes:

Supplied by seepex

Supplied by customer

Frequency:
Speed:
Power
consumption:

________________________________ _______________________________________
Place, date Signature / company stamp

Ausgabe
issue
B / 17.03.2006 Dokument
document
OM.COM.05e Blatt
sheet
1 (1)
13
14
6
Commissioning / De-commissioning
6.2 Measures before commissioning
 Note the technical data (chapter 3.).

6.2.1 Checking pipelines


 Check flange screwed connections (SCH).

 Check threaded connections (G).

NOTICE
Ensure the liquid can flow through without obstruction.
Malfunction and/or irreparable damage to the pump.
 Open all shut-off elements before switching on the pump.

6.2.2 Protective devices on the pump

DANGER

Missing protective device.


Danger of pulling in and crushing.
 Equip the pump with a protective device. Protective devices provided for preventing con-
tact with surfaces or moving parts must be regarded as suitable if contact is not possible
in a test involving a test finger, with regard to the penetration possibility, strength and shock
resistance.
 Comply with national protection regulations.
 In pumps with an open suction flange/feed hopper, attach touch protection. These safety
clearances protect those persons who are attempting to reach danger areas without addi-
tional help and under the conditions defined for various situations of reaching up, reaching
under or reaching through
In shaft seals, touch protection is only necessary if there are components on the rotating
shaft.

6.2.3 Electrical/hydraulic connections

DANGER

Dangerous voltage.
Death or serious injury can occur.
 Note safety regulations.
 Disconnect motor from all sources of energy.
 Secure electrical connections against restarting.

Ausgabe
issue
C / 02.11.2012 Dokument
document
OM.COM.01e Blatt
sheet
1 (4)
15
6
Commissioning / De-commissioning
6.2.4 Direction of rotation check
flow direction
 The pump direction of rotation determines
the flow direction of the pumping medium.
 Note the direction of rotation arrow on the
type plate.
counter clockwise clockwise

6.2.5 Additional devices - optional


 Refer to additional devices (chapter 12.1).

6.3 Initial commissioning/repeated commissioning


 Start up the pump.

NOTICE
Dry running of the pump.
Malfunction and/or irreparable damage to the pump.
 Fill the suction casing with liquid in order to lubricate the pumping elements.

6.3.1 Avoid dry running of the pump

NOTICE
High temperature between rotor and stator.
Stator material burned.
Complete failure of the pump.
 Make sure that the suction-side conveying capacity does not cavitate.
 If this cannot be guaranteed on the machine side, assemble a seepex dry running
protection (TSE).

6.3.2 Pressure in the suction and pressure connection

CAUTION

High pressure.
Malfunction and/or irreparable damage to the shaft seal or pump.
 Maintain pressure in the suction connection in accordance with the technical data
(chapter 3.).

Recommendation:
 Assemble an oil-filled contact pressure gauge to monitor and deactivate the pump.

Ausgabe
issue
C / 02.11.2012 Dokument
document
OM.COM.01e Blatt
sheet
2 (4)
16
6
Commissioning / De-commissioning
6.4 De-commissioning
Protect the pump and additional devices against the following:
• Frost
• Deposit of solids
• Sedimentation from the liquid
• Corrosion of parts that come into contact with the medium

6.4.1 Switching off the pump

DANGER

Dangerous voltage.
Death or serious injury can occur.
 Note safety regulations.
 Disconnect motor from all sources of energy.
 Secure electrical connections against restarting.

6.4.2 Emptying the pump

CAUTION

Liquid draining out.


Minor injury or damage to property can occur.
 Wear suitable protective clothing.
 Refer to the technical data (chapter 3.) for the corresponding configuration of the pump
housing.

To drain the pump:


 If the pump housing has screwed plugs, remove the screwed plugs.
 Drain using a connection branch (suction casing, pressure branch) if the pump housing is
coated or the housing does not have screwed plugs.
 Drain the residual liquid from the pump housing.
 Drain the pipelines on the suction and pressure sides, or shut off behind the pump connec-
tions.

Ausgabe
issue
C / 02.11.2012 Dokument
document
OM.COM.01e Blatt
sheet
3 (4)
17
6
Commissioning / De-commissioning
6.4.3 Removing the pump

WARNING

Risk of pump tipping or falling.


Death or serious injury can occur.
 Support the drive unit to guarantee stability.

Pipeline dismantling

 Remove flange bolts (SCH) and flange


seals (DFL).
with/without base plate
 Remove bolts (SCH) from the pump feet.

Pipeline dismantling

 Remove threaded connections (G).


with/without base plate
 Remove bolts (SCH) from the pump feet.

6.4.4 Preservation/storage of the pump

NOTICE
Damage to property due to lack of corrosion protection.
Property damage can occur due to corrosion.
 Contact seepex to discuss suitable preservation measures.
– State the commission number of the pump.

Ausgabe
issue
C / 02.11.2012 Dokument
document
OM.COM.01e Blatt
sheet
4 (4)
18
7
Maintenance
7.1 Preventive measures

The maintenance personnel must have these operating instructions, follow them and also
require corresponding qualifications.

DANGER

Dangerous voltage.
Death or serious injury can occur.
 Note safety regulations.
 Disconnect pump from all sources of energy.
 Secure electrical connections against restarting.

7.1.1 Pump down-time

NOTICE
Pump down-time.
Production failure due to wear.
 Acquisition of a set of wearing parts and a set of gaskets.

7.2 Lubrication

No. Denomination Lubricant Lubricant change in Fill volume


operating hours
1 Pin joint seepex special grease 10000 h *
*
2 Pin joint seepex special grease 10000 h *
*
3 Drive Refer to manufacturer's documentation (chapter 13._)
Rotor/stator Conveying medium --- ---
Shaft seal Conveying medium --- ---

* Type and filling quantities are commission specific information.

Ausgabe Dokument Blatt


issue
A / 29.06.2017 document
OM.WTG.XXe sheet
1 (2)
19
7
Maintenance
7.2.1 Joint grease

NOTICE
Other grease types.
Malfunction and/or irreparable damage to the joints or the pump.
 Exclusively use seepex special grease.

7.3 Inspection

Component Interval Action


Joints Every 10,000 operating hours Renew joint grease
Stator Every week Visual check for leaks
Shaft seal Every week Visual check for leaks
Drive unit Every 3000 operating hours, Comply with manufacturer's
at least every 6 months documentation

Ausgabe Dokument Blatt


issue
A / 29.06.2017 document
OM.WTG.XXe sheet
2 (2)
20
8
Malfunctions, causes, rectification
Refer to technical data (chapter 3.) for application range of the pump.

Malfunction Causes Rectification

Pump seized / pump does not pump


Conveying capacity is not achieved
Pressure head is not reached

Pump is loud when running


Pump pumping unevenly

Pump does not start up

Premature stator wear


Pump is not sucking

Motor gets too hot

Shaft seal is leaky


X X X Static friction between sta- Apply lubricant (liquid soap)
tor/rotor too great. between stator and rotor.
X Incorrect direction of rota- Check direction of rotation
tion. and swap over motor con-
nections if necessary.
X X X X X Suction pipe or shaft seal Eliminate leaks.
leaking.
X X X X Suction head too great. Check the suction head, if
necessary increase pipe
cross section on suction
pipe and use a larger filter,
open suction-side valve
fully.
X X X Viscosity of conveying Check/adapt (data sheet).
product too great.
X X X Pump rotation speed Correct rotation speed (data
incorrect. sheet).
X X Avoid air bubbles in the
conveying product.
X X X X X Pressure head too great. Check pressure head with
pressure gauge, reduce
pressure head by using
larger pressure pipe
crossed section or shorten-
ing the pressure pipe.
X X X X X Pump running partially/ Check there is adequate
completely dry. conveying product avail-
able on the suction side.
Dry running protection DRP.
X X Check coupling. If necessary, move pump in
relation to drive, check wear
on coupling gear, re-adjust
coupling if necessary.
X X Rotation speed too low. Increase rotation speed for
low-viscosity media/large
suction volume.

Ausgabe
issue
B / 11.09.2007 Dokument
document
OM.REC.01e Blatt
sheet
1 (2)
21
8
Malfunctions, causes, rectification

Malfunction Causes Rectification

Pump seized / pump does not pump


Conveying capacity is not achieved
Pressure head is not reached

Pump is loud when running


Pump pumping unevenly

Pump does not start up

Premature stator wear


Pump is not sucking

Motor gets too hot

Shaft seal is leaky


X X X Rotation speed too high. Reduce rotation speed for
high-viscosity media, risk
of cavitation.
X Joint play too large. Check mounting of cou-
pling rod bushing.
X X X X X Foreign objects in pump. Dismantle pump, remove
foreign bodies, replace
defective parts.
X X X X Stator/rotor worn. Dismantle pump and
renew defective parts.
X X X X Joint parts worn. Renew joint parts, use
seepex pin joint grease.
X X X X Suction pipe blocked. Clean the suction pipe.
X X X X X Temperature of pumping Check temperature, use
liquid too high. an undersize rotor.
X X X X X Gland packing too firm/ Loosen packing gland or
worn. tighten. Renew unusable
packing rings.
X X X X Solid content and/or grain Reduce pump speed,
size too great. install screen with permit-
ted mesh width. Increase
liquid proportion.
X X X X Sedimentation/gumming of Rinse through and clean
solids when pump station- the pump immediately.
ary.
X X X X X Conveying product hard- Heat the pump.
ens when the temperature
drops below a certain limit.
X X X X Stator swollen and unable Select a suitable stator
to withstand conveying material, use an under-
product. size rotor.
X X Bearings in pump drive Renew bearings.
housing or drive unit
defective.
X Mechanical seal defective. Check sliprings and O-
rings for wear/resistance,
renew if necessary.

Ausgabe
issue
B / 11.09.2007 Dokument
document
OM.REC.01e Blatt
sheet
2 (2)
22
9
Dismantling / Reassembly
9.1 Pump Dismantling/Reassembly
Range: BN
Size: 025-12 up to 1-6L

9.1.1 Preparing the pump for dismantling

DANGER

Dangerous voltage.
Death or serious injury can occur.
 Note safety regulations.
 Disconnect motor from all sources of energy.
 Secure electrical connections against restarting.

 Empty pipelines.
 Allow pipelines to cool down.
 Remove pipeline connections (suction
side/pressure side).
 Note decommissioning (chapter 6.4).

9.1.2 Dismantling

WARNING

Risk of pump tipping or falling.


Death or serious injury can occur.
 Fasten the lantern (200) to secure the
pump.

9.1.2.1 Pressure branch (700) - Dismantling

 Prop up stator (601) with a support (S).


 Remove screw fitting (604, 606).
 Remove pressure branch (700).
 Remove tie bolt (602).

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
1 (6)
23
9
Dismantling / Reassembly
9.1.2.2 Stator (601) - Dismantling

 Raise/move splash ring (310).


 Remove the plug-in shaft pin (309).
 Insert tool (WS).
 Turn tool (WS) upwards.

Tool (W2/chain wrench)

 Add lubricant (GM) to the opening on


pressure branch side between the rotor
(600) and the stator (601).
 Turn the stator (601) in the “leftt” rotating
direction and remove.
– Use tool (W2).
 Prop up the rotor (600) with support (S).

9.1.2.3 Suction casing (500) - Dismantling

 Provide rotor (600) with protective cover


(SH).
 Prop up rotor (600) with support (S).
 Dismantle the suction casing (500).
 Remove tool (WS).

9.1.2.4 Rotating unit (RTE) - Dismantling

Tool (W10/dismantling tool)

Tool (W9/mounting lever)

with flush connection

 Remove the flush connection (SSÜ) on the


shaft seal casing (SEA).

 Assemble tool (W10/dismantling tool).

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
2 (6)
24
9
Dismantling / Reassembly

 Pull the rotating unit (RTE) with shaft seal


(SEA) off from the output shaft of the drive
(ANT).
– Use tool (W9/mounting lever).

 Dismantle tool (W10/dismantling tool).

 Pull off the splash ring (310).


 Pull off the shaft seal casing (SEA).
– Note dismantling shaft seal
(chapter 9.4).

without flush connection

 Assemble tool (W10/dismantling tool).

 Pull the rotating unit (RTE) with shaft seal


(SEA) off from the output shaft of the drive
(ANT).
– Use tool (W9/mounting lever).

 Dismantle tool (W10/dismantling tool).

 Pull off the splash ring (310).


 Pull off the shaft seal casing (SEA).
– Note dismantling shaft seal
(chapter 9.4).

9.1.2.5 Rotor (600), coupling rod (400), plug-in shaft (307) - Dismantling

 Joint (G) dismantling note rotating unit -


individual parts (chapter 9.2).

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
3 (6)
25
9
Dismantling / Reassembly
9.1.2.6 Lantern (200)/drive (ANT) - Dismantling

CAUTION

Falling or tilting drive.


Slight injury can occur.
 Secure the drive (ANT).

 Remove the screw fitting (210, 212, 213).


 Remove the drive (ANT).

9.1.3 Reassembly

WARNING

Risk of pump tipping or falling.


Death or serious injury can occur.
 Fasten the lantern (200) to secure the
pump.

9.1.3.1 Lantern (200)/drive (ANT) - Reassembly

 Clean the flange bearing surfaces (FLS),


bolt circle (ZD) and the output shaft of the
drive unit (ANT).
 Mount the drive (ANT) to the lantern (200)
with screw fittings (210, 212, 213).

9.1.3.2 Rotor (600), coupling rod (400), plug-in shaft (307) - Reassembly

 Joint (G) reassembly note rotating unit -


individual parts ( chapter 9.2).

9.1.3.3 Rotating unit (RTE) - Reassembly

 Slide on shaft seal casing (SEA).


– Note reassembly shaft seal
( chapter 9.4).
 Moisten splash ring (310) and plug-in shaft
(307) with antiseize graphite petroleum.
 Slide splash ring (310) onto plug-in shaft
(307).
– Observe fitting position of splash ring
(see lettering).

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
4 (6)
26
9
Dismantling / Reassembly

 Apply antiseize graphite petroleum to the


output shaft of drive (ANT).
 Slide on rotating unit (RTE).

with flush connection

 Mount the flush connection (SSÜ).

9.1.3.4 Suction casing (500) - Reassembly

 Provide rotor (600) with protective cover


(SH).
 Prop up rotor (600) with support (S).
 Slide on casing gasket (501).
 Assemble suction casing (500) and adjust.
– Use spirit level (W).
 Remove protective cover (SH).

9.1.3.5 Stator (601) - Reassembly

 Insert tool (WS).


 Turn tool (WS) down.

Tool (W2/chain wrench)

 Moisten outer surface of the rotor (600)


with lubricant (GM).
 Moisten inner surface of the stator (601)
with lubricant (GM).
 Prop up stator (601) with support (S).
 Turn stator (601) in the “right” rotating
direction and slide onto rotor (600).
– Use tool (W2).
 Remove tool (WS).
 Slide in plug-in shaft pin (309).

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
5 (6)
27
9
Dismantling / Reassembly

 Pay attention to the position of the splash


ring (310).
 Insert the splash ring collar at a distance of
0.5 mm from the lantern (200).

9.1.3.6 Pressure branch (700) - Reassembly

 Prop up stator (601) with a support (S).


 Insert tie bolts (602) loosely into the
lantern (200).

 Push pressure branch (700) on to the


stator (601).
 Insert tie bolts (602) loosely in the
pressure branch (700).
 Remove the support (S).

 Mount screw fitting (604, 606).


 Tighten tie bolts (602) equally.

Ausgabe
issue
E / 22.04.2013 Dokument
document
OM.MAI.01e Blatt
sheet
6 (6)
28
9
Dismantling/reassembly
9.2 Rotating unit individual parts

9.2.1 Dismantling

9.2.1.1 Holding band (406) - dismantling

CAUTION

Danger of injury.
Parts might be thrown out.
 Wear safety glasses.

 Detach holding band loop (SCL).


– Use suitable tool (WM).
 Push out parts of holding band loop (SCL).
 Remove holding band (406).

Tool (W15/mounting plate)

 Pull back universal joint sleeve (405).


 Secure tool (W15).

9.2.1.2 Retaining sleeve (401) - dismantling

 Knock back retaining sleeve (401).


– Use suitable tool (WM).

9.2.1.3 Detach joint

 Eject coupling rod pin (402)


 Remove coupling rod (400).

Tool (W4/assembly mandrel)

 Knock out guide bushings (403) using tool


(W4).

Ausgabe
issue
C / 30.08.2012 Dokument
document
OM.PJT.01e Blatt
sheet
1 (4)
29
9
Dismantling/reassembly
9.2.2 Rotating unit (RTE) - prepare individual parts for reassembly

9.2.2.1 Rotor (600)

 Remove any damage.


 Clean rotor (600).

Tool (W4/assembly mandrel)

 Press in guide bushings (403)


(depth = 2/3).
– Use tool (W4).

9.2.2.2 Coupling rod (400)

 Clean coupling rod (400).


 Check bore head for wear.
– If wearing is detec on the bore head,
renew coupling rod (400).

9.2.2.3 Plug-in shaft (307)

 Remove any damage.


 Clean rotor (600).
Tool (W4/assembly mandrel)

 Press in guide bushings (403)


(depth = 2/3).
– Use tool (W4).

9.2.3 Rotating unit (RTE) - individual parts - reassembly

NOTICE
Malfunction of the joints.
Malfunction and/or destruction of joints.
 Replace coupling rod pins (402) and guide bushings (403) jointly.

9.2.3.1 Coupling rod (400) - reassembly


 Slide the universal joint sleeve (405) and holding bands (406) onto coupling rod (400).
 Adapt diameter and width of the holding band to the universal joint sleeve.
 Fill the joint head with seepex joint grease.

Ausgabe
issue
C / 30.08.2012 Dokument
document
OM.PJT.01e Blatt
sheet
2 (4)
30
9
Dismantling/reassembly
Rotor (600)

 Insert coupling rod pins (402).


 Slide on retaining sleeve (401).
 Connect rotor/coupling rod.

Plug-in shaft (307)

 Insert coupling rod pins (402).


 Slide on retaining sleeve (401).
 Connect plug-in shaft/coupling rod.

9.2.3.2 Retaining sleeve (401) - reassembly

Tool (W4/assembly mandrel)

 Knock back retaining sleeve (401).


– Use tool (W4).

 Secure retaining sleeve (401) in a dis-


placed manner (2x180°).
– Use suitable tool (WK).

Ausgabe
issue
C / 30.08.2012 Dokument
document
OM.PJT.01e Blatt
sheet
3 (4)
31
9
Dismantling/reassembly
9.2.3.3 Universal joint sleeve (405) - reassembly

 Moisten the surface of coupling rod (400) /


inner surface of universal joint sleeve
(405) with joint grease (maintenance
chapter 7.).
 Slide on universal joint sleeve (405).

 Remove air from the inside of the joint.


– Use suitable tool (WS).

 Assemble the holding band.


– Holding band assembly
(chapter 9._).

Ausgabe
issue
C / 30.08.2012 Dokument
document
OM.PJT.01e Blatt
sheet
4 (4)
32
9
Dismantling / Reassembly
9.3 Holding band - assembly

9.3.1 Prepare the holding band

 Only use prefabricated double-band holding bands may.

9.3.2 Check the holding band


• Bent-over holding band (HBD) is in con-
tact with holding band loop (SCL) to avoid
damaging universal joint sleeve.

 Press on holding band (HBD) using tool


(WZ) if necessary.

9.3.3 Assemble the holding band

 Use tool (W3/mounting tool)

 Feed holding band into tool (W3).

 Hold ends of holding band with the eccen-


tric lever (EX).

 Turn the crank (KU) until the holding band


is strained and lies against the holding
band loop (SCL).

 Carefully pull the holding band together


until it is in contact with the circular groove
of universal joint sleeve.

9.3.4 Correct tension of holding band (HBD)


Correct
The holding band (HBD) has drawn in the out
shape of the universal joint sleeve and is
firmly seated.

Incorrect
The holding band (HBD) is too loose, can slip
off.

Incorrect
The holding band (HBD) is too tight, univer-
sal joint sleeve will be damaged/sheared off.

Ausgabe
issue
D / 05.08.2013 Dokument
document
OM.HBD.01e Blatt
sheet
1 (2)
33
9
Dismantling / Reassembly
9.3.5 Cant up the holding band
 Swivel mounting tool (W3) approx. 60° up-
wards.

 Loosen crank (KU) by a half turn.

 Swivel cutting lever (SH) forward until the


pressure piece is lying behind the holding
band loop (SCL).

9.3.6 Shear the holding band (material: 1.4301; 1.4401)


 Hit the cutting lever (SH) with the inside of
your hand.
– Cant up and shear the end of the
holding band behind the loop (SCL).
– Carefully straighten up the holding
band (HBD) if it rises up on the
sheared side.

NOTICE
Universal joint seal damage.
Pin joint grease can emerge.

 Avoid hammering or striking.

9.3.7 Check the holding band after assembly


 The holding band must lie in the groove of
the universal joint sleeve.

 Replace the holding band if the holding


band slips back through the loop.

Ausgabe
issue
D / 05.08.2013 Dokument
document
OM.HBD.01e Blatt
sheet
2 (2)
34
9
Dismantling / Reassembly
9.4 / 9.5 Shaft sealing

9.4.1 Safety

WARNING

Shaft seal is leaky.


Leakage may escape into the atmosphere.
 Take safety measures to protect persons and the environment.
 Wear suitable protective clothing.
 Dispose of leakage appropriately.
 Note applicable regulations when handling hazardous substances.

9.4.2 Operating conditions and material combination


• Adjust to the relevant application
– Design variants you will find at http://www.seepex.com/en/service/downloads/.

Ausgabe Dokument Blatt


issue
A / 29.06.2017 document
OM.SEA.XXe sheet
1 (1)
36
10
Spare parts
10.1 Spare parts list

Ausgabe
issue
B / 29.03.2011 Dokument
document
OM.SZG.02e Blatt
sheet
1 (1)
37
38
10
Spare parts
Version for copying

10.1 Spare parts list

Spare parts can be ordered online or requested from Type: BN 025-12 to 1-6L
www.seepex.com\

Request Order Sender:

Must be included in every order or enquiry!


Commission: Type: Contact: .........................................................
Tel.: ................................................................
_________________________ _______________________ Fax: ...............................................................
E-mail: ...........................................................

Customer service: Germany Tel +492041.996-231 Delivery address:


seepex GmbH Fax +492041.996-431 .......................................................................
Postfach 10 15 64 Rest of Europe Tel +492041.996-224 .......................................................................
D-46215 Bottrop Fax +492041.996-424 .......................................................................
[email protected] Outside Europe Tel +492041.996-120 .......................................................................
Fax +492041.996-432 .......................................................................

No. Quantity Component Material Comment

Minor set of wearing parts

301 1 Set of packing rings according to data sheet (chapter 3.1)


330 1 Mechanical seal according to data sheet (chapter 3.1)
601 1 Stator

Major set of wearing parts

301 1 Set of packing rings according to data sheet (chapter 3.1)


307 1 Plug-in shaft
330 1 Mechanical seal according to data sheet (chapter 3.1)
400 1 Coupling rod with coupling
rod bushings
402 2 Coupling rod pin
403 4 Guide bushing
405 2 Universal joint sleeve
406 2 Holding band, large
600 1 Rotor
601 1 Stator

__________________________________ _______________________________________
Place, date Signature / company stamp

Ausgabe
issue
D / 23.08.2010 Dokument
document
OM.WPS.01e Blatt
sheet
1 (2)
39
10
Spare parts
Version for copying

No. Quantity Component Material Comment

Set of gaskets

301 1 Set of packing rings according to data sheet (chapter 3.1)


310 1 Splash ring according to data sheet (chapter 3.1)
330 1 Mechanical seal
501 1 Casing gasket
503 3 Sealing ring

Plug-in shaft & shaft seal

301 Set of packing rings according to data sheet (chapter 3.1)


307 Plug-in shaft
309 Plug-in shaft pin
310 Splash ring according to data sheet (chapter 3.1)
330 Mechanical seal according to data sheet (chapter 3.1)

Coupling rod & joint parts

400 Coupling rod with coupling


rod bushings
401 Retaining sleeve
402 Coupling rod pin
403 Guide bushing
405 Universal joint sleeve
406 Holding band, large
401-406 Complete set of joint parts

Conveying elements

600 Rotor
601 Stator

Miscellaneous parts

501 Casing gasket


098 Pin joint grease 1 cartridge = 300 g (approx. 315 cm³)
Grease quantity according to maintenance
(chapter 7.0)

__________________________________ _______________________________________
Place, date Signature / company stamp

Ausgabe
issue
D / 23.08.2010 Dokument
document
OM.WPS.01e Blatt
sheet
2 (2)
40
11
Special tools
Version for copying

Spare parts can be ordered online or requested from Sender:


www.seepex.com\
Must be specified with every order!
Commission: Mark tool! Contact: .........................................................
Tel.: ................................................................
__________________________ X Fax: ...............................................................
E-mail: ...........................................................

Customer service: Germany Tel +492041.996-231 Delivery address:


seepex GmbH Fax +492041.996-431 .......................................................................
Postfach 10 15 64 Rest of Europe Tel +492041.996-224 .......................................................................
D-46215 Bottrop Fax +492041.996-424 .......................................................................
[email protected] Outside Europe Tel +492041.996-120 .......................................................................
Fax +492041.996-432 .......................................................................

For installation of: Packing gland Stator Universal joint


sleeve

Tool no. W1 W2 W15

Denomination: Packing puller Chain wrench plus Mounting plate


spare chain
Order no. PKZ KRZ MTP

For installation of: Rotating unit


Holding band Joint Plug-in shaft

Tool no. W3 W4 W10

Denomination: Mounting tool Drift Dismantling tool


Order no. MHB MTD AZV

Ausgabe
issue
A / 22.09.2006 Dokument
document
OM.STO.01e Blatt
sheet
1 (1)
41
42
12
Associated documents

12.1 Accessories/Technical information

• Accessories and technical information are commission specific


documents not part of this not binding operating and assembly instruction.

Ausgabe Dokument Blatt


issue A / 29.06.2017 document OM.ZUG.XXd sheet 1 (1) 43
44
13
Appendix
13.1 Manufacturer's and supplier's documents

• Manufacturer's and supplier's documents are commission specific documents


and not part of this not binding operating and assembly instruction.

Ausgabe Dokument Blatt


issue
A / 29.06.2017 document
OM.MDS.XXe sheet
1 (1)
45
46
47
SEEPEX GmbH
Scharnhölzstraße 344
46240 Bottrop
Postfach 10 15 64
46215 Bottrop
Germany

Tel +49.2041.996-0
Fax +49.2041.996-400
[email protected]
www.seepex.com

Great Britain Austria Belgium Denmark


SEEPEX UK Ltd. SEEPEX GmbH SEEPEX GmbH SEEPEX Nordic A/S
3 Armtech Row Vertriebsbüro Österreich Bureau België Krakasvej 7C
Houndstone Business Park Obermüllergasse 18 Industriezone Klein Gent-Link 21 3400 Hillerød
Yeovil Somerset BA22 8RW 3003 Gablitz Welvaartstraat 14-1 bus 15 Tel +45.49.192200
Tel +44.1935.472376 Tel +43.2231.61085 2200 Herentals Fax + 45.49.193200
Fax +44.1935.479836 Fax +43.2231.6108520 Tel +32.14.501471 [email protected]
[email protected] [email protected] Fax +32.14.501461
[email protected]

France Hungary Irland Italy


SEEPEX France SARL SEEPEX GmbH SEEPEX UK Ltd. SEEPEX Italia S.r.l.
1, Rue Pelloutier Magyarországi iroda Branch Office Ireland Via Alberto da Giussano 23
77183 Croissy Beaubourg Hecskó Tamás okl.vill.mérn. 29 Lackenfune 20145 Milano (MI)
Tel +33.1.64114450 Éva utca 5. Dungarvan Tel +39.02.36569360
Fax + 33.1.64114489 7632 Pécs Co. Waterford Fax +39.02.92877855
[email protected] Tel +36.205806134 Tel +353.860450439 [email protected]
Fax +36.72952587 [email protected]
[email protected]

Poland Sweden Spain The Netherlands


SEEPEX GmbH SEEPEX Nordic A/S SEEPEX GmbH SEEPEX GmbH
Przedstawicielstwo w Polsce Hamndalsvägen 58 Officina de Representación en España Bureau Nederland
ul. Romana Maya 1 61633 Åby C/Copenhague, 12 Visbystraat 13
61-371 Poznan Tel +46.1166940 Edif. Tifan Oficina 207 7418 BE Deventer
Tel +48.61.6469270 Fax +46.1166941 28232 La Rozas Tel +31.570.516644
Fax +48.61.6469271 [email protected] Madrid Fax +31.570.516077
[email protected] Tel +34.91.6361353 [email protected]
Fax +34.91.6409371
[email protected]

Russia USA China India


SEEPEX Ltd. Ugreshskaya SEEPEX Inc. SEEPEX Pumps (Shanghai) Co., Ltd. SEEPEX India Pvt. Ltd.
Str. 2 Bldg. 23 511 Speedway Drive Xuanzhong Rd. 399, Building 13 Office No. 305.
115088 Moscow Enon Nanhui Industrial Area Raheja Arcade Building
Tel +7.495.2874830 Ohio 45323 201300 Shanghai Sector 11, C.B.D. Belapur
Fax +7.495.2874830 Tel +1.937.8647150 Tel +86.21.38108888 Navi Mumbai 400614
[email protected] Fax + 1.937.8647157 Fax +86.21.38108899 Tel +91.22.40240434/35
[email protected] [email protected] Fax +91.22.40240436
[email protected]

Japan Malaysia Australia


日本シーペックス株式会社 SEEPEX (M) Sdn. Bhd. SEEPEX Australia Pty. Ltd.
5-2-44 Onna, Atsugi-shi, No. 2, Jalan 51/203A Unit 3, 4 Bounty Close
Kanagawa-ken, 243-0032 Kaw. Perindustrian Tiong Tuggerah Business Park
Tel +81.46.2595931 Nam Seksyen 51 NSW 2259
Fax +81.46.2595941 46050 Petaling Jaya Selengor Tel +61.2.43554500
[email protected] Darul Ehsan Fax +61.2.43554022
Tel +60.3.88009988 [email protected]
[email protected]

More SEEPEX sales partnes in Europe,


America, Asia, Africa and Oceania
you willl find on our website.

48

You might also like