Note- Solve any 4 from question no 1 to 5. Questions 6, 7 & 8 are compulsory.

1. Define modular construction it’s type, advantages and limitations in detail. [2.5 marks]
2. Write a short note on different types of foundation and explain the construction procedure for grillage foundation in detail. [2.5
marks]
3. Write a brief note on slip form construction technique, it’s features, components, application, advantages and disadvantage. [2.5
marks]
4. Write the difference between penalties and liquidated damages.
Or
Write down the difference between mechanised construction method and conventional construction method. [2.5 marks]
5. Write down the difference between CPM & PERT. [2.5 marks]
6. Draw the network diagram and determine the critical path for the following project: [3 marks]

Activity Time Activity Time


(weeks) (weeks)
1-2 5 5-8 2
1-3 6 6-8 5
1-4 3 7-9 6
2-5 5 8-9 4
3-6 7
3-7 10
4-7 4
7. A project consists of seven activities with the following time estimates. Find the probability that the project will be completed in 30
weeks or less. [3 marks]

Activity Predecesso to tm tp
r activity days days days
A - 2 5 8
B A 2 3 4
C A 6 8 10
D A 2 4 6
E B 2 6 10
F C 6 7 8
G D, E, F 6 8 10
8. Determine the earliest and latest times, the total float for each activity, the critical activities and the project completion time. [4
marks]

Activity Predecessor activity Duration (weeks)


A - 12
B A 7
C A 11
D A 8
E A 6
F B 10
G C 9
H D, F 14
I E, G 13
J H, I 16