PGE 407 2022. Presentation 6. Alternative Methods of Pressure Buildup Analysis.
PGE 407 2022. Presentation 6. Alternative Methods of Pressure Buildup Analysis.
PGE 407 2022. Presentation 6. Alternative Methods of Pressure Buildup Analysis.
Bounded Reservoirs
2
Bounded Reservoirs
A solution of the pressure behaviour of a well in a bounded cylindrical reservoir:
…. (2.13
…. (2.14)
Bounded Reservoirs
For small ∆t,
…. (2.15)
…. (2.16)
4
Bounded Reservoirs
Comparing Eqn (2.16)
…. (2.16)
…. (2.2)
we see that p* has the same meaning in an equation written for a bounded
reservoir as does pi in an equation written for an infinite reservoir.
6
Pressure Buildup.
Two - or Three-Phase Flow
Note the following:
1. Gas flows when the reservoir pressure goes below the bubble point
4. the pressure in the oil phase in a given pore in the reservoir will
almost be the same as that in the gas phase in the same or an
adjacent pore
Consider the the buildup in the oil phase as the buildup in the single
phase situation:
The single phase methods could be applied with the use of total
compressibility and total mobility instead of single phase quantities.
….
(2.17)
.…. (2.18)
10
…. (2.19)
…. (2.20)
11
from Eqn (19) and (20), the slope of the two-phase curve may be used to:
1. calculate the permeability to oil ko
2. calculate the permeability to gas kg
12
13
Pressure Buildup in Gas Wells
These Pressure Buildup methods may be applied to gas wells.
The buildup equation can be expressed as:
…. (2.21)
…. (2.22)
14
15
…. (2.23)
From Eqn (21), the plot of pws vs log should be a straight line if the
product oBo is constant.
16
𝛍
17
Well Test Analysis Techniques
□ Muskat Methods
□ MHD Analysis
□ Extended Muskat Method
□ Horner Analysis
□ Pressure Derivative Based Techniques
■ Type Curves Analysis
■ Numerical Simulation
18
Muskat Method
Muskat proposed that
The mathematical analysis was for incompressible flow, but have been found
to be applicable to compressible flow.
Used for pressure buildup in fractured limestone wells and falloff behaviour
in injection wells.
19
20
Alternative Methods of Pressure Buildup Analysis
3. consider
21
5. the average pressure is obtained for no-flow over the outer boundary
(curve A)
23
24
Alternative Methods of Pressure Buildup Analysis
.. (1.24)
25
3. close-in the well such for a time such that all but one of the
exponential terms in Eqn (1.24) above die out
4. superpose Eqn (1.24) for these flowing and production terms, and
introduce the relation between average and initial pressures
26
.… (2.24)
27
28
8. value of well bore damage can also be obtained by using the semi-
steady form of Eqn (1.24) together with this kh value
29
1. a good check is
30
31
5. the method is best applied when the buildup is long enough that the
‘bend over’ from the straight line is observed
6. if the well is not closed-in log enough for the bend-over to be
observed, the value of must be accurately known or the drainage
volume may be subject to large error.
32
33
Type Curve Analysis: Unmatched Overlay
34
Type Curve Analysis: Matched in Pressure
35
Type Curve Analysis:
Matched in Both Pressure & Time
36
37
Exercise 6
38
Examples
39
Example-6.1
Example-6.1
Solution 6.1
Solution 6.1
Solution 6.1
Cartesian Plot of Multi-Rate Test Data
Solution 6.1
Variable-Rate Gas Flow Test with Smoothly
Changing Rates
• A strictly constant producing rate is impractical
or impossible to maintain.
• A more probable mode of operation is
production at a constant surface pressure, and
if tubing friction effects are negligible, the BHP
also is constant.
• At early times, however, both BHP & bottom
hole rate may be changing rapidly.
• Data obtained under these nonideal test
conditions can be analyzed accurately with a
simple modification of the transient flow
equation for constant-rate production.
Example-6.2
Example-6.2
Solution 6.2
Solution 6.2
Solution 6.2
Solution 6.2
Solution 6.2
Example-6.4
Solution-6.4
(Analysis Using Pressure Variables)
Solution-6.4
(Analysis Using Pressure Variables)
Horner Plot Using Pressure
Solution-6.4
(Analysis Using Pressure Squared Variables)
Solution-6.4
(Analysis Using Pressure Squared Variables)
Horner Plot Using Pressure Squared
Solution-6.4
(Analysis Using Adjusted Pressure Variables)
Solution-6.4
(Analysis Using Adjusted Pressure Variables)
Horner Plot Using Adjusted & Adjusted
Horner Time Ratio
PURSUING STUDENT OPPORTUNITIES
Internship - Search For Opportunities
fi
fi
fi
fi
Questions 47
NEXT TOPIC
69