Siwes Repor Writing
Siwes Repor Writing
Siwes Repor Writing
The Student Industrial Work Experience Scheme (SIWES), also known as Industrial
Training is a Skills Training Programme designed to expose and prepare students of Nigerian
Agriculture, for the industrial work situation they’re likely to meet after graduation. The scheme
also affords students the opportunity of familiarizing and exposing themselves to the needed
experience in handling equipment and machinery that are usually not available in their
institution.
In the earlier stage of science and technology education in Nigeria, students were
graduating from their respective institutions without any technical knowledge or working
experience. Before the establishment of the scheme, there was a growing concern among
background studies preparatory for employment in industries. Thus, employers were of the
opinion that the theoretical education in higher institutions wasn’t responsive to the needs of the
employers of labour.
SIWES introduction, initiation and design was done by the Industrial Training Fund
(I.T.F) in 1973 to acquaint students with the skills of handling employer’s equipment and
machinery. The Industrial Training Fund (I.T.F) solely funded the scheme during its formative
years. However, due to financial constraints, the fund withdrew from the Scheme in 1978. The
Federal Government, noting the significance of the skills training handed the management of the
1
scheme to both the National Universities Commission (N.U.C) and the National Board for
The management and implementation of the scheme was however reverted to the I.T.F by
the Federal Government in November, 1984 and the administration was effectively taken over by
the Industrial Training Fund in July 1985, with the funding solely borne by the Federal
Government. The scheme has a duration of 4 months for students in polytechnics before
commencement of their HND, while it runs for 6 months for students in the university.
The bodies involved are: The Federal Government, Industrial Training Fund (ITF). Other
supervising agents are: National University Commission (NUC), National Board for Technical
Federal Government being the major party in the establishment off SIWES; has ever since
been involved in the management of SIWES. Some of the roles played are:
Formulate policies and guideline for participating bodies and institutions as well as
To make it mandatory for all ministries, companies and parastatals to offer places of
amended in 1990.
To provide necessary and adequate funds to ITF through the Federal ministries of
industries.
2
1.2.2 Roles of ITF (Industrial Training Fund)
Supervise students at their places of attachment and sign their lob-book and IT forms
Vet and process student’s log-book and forward same to ITF Area office.
The Industrial Training Funds Policy Document No. 1 of 1973 which established SIWES
b. Prepare students for industrial work situations that they are likely to meet after
graduation.
c. Expose students to work methods and techniques in handling equipment and machinery
d. Make the transition from school to the world of work easier and enhance students’
e. Provide students with the opportunities to apply their educational knowledge in real work
f. Enlist and strengthen employers’ involvement in the entire educational process and
3
CHAPTER TWO
2. ESTABLISHMENTS PROFILE
organization operating in Nigeria since 2012 and it is located in No 21 Oba Amusa Estate
Agungi Ajiran Road Off Lekki-Epe Express Road, Lekki phase 2, Lagos. It is a single man
investment organization comprising of a little organisation structure but its influence in the
structural development sector of the location where it is domicile has brought about a shift and
an advantage. The organisation works with quite a number of building subcontracting expertise
in different sections of work as regarding building construction though the expertise are not
organization, directing and controlling of construction operations for the successful completion
of any proposed project on time with maximum desired outlook and safe working environment.
The firm designs, plans, contract and builds to its own desirability and then puts and
advertises it on sale to the public and any desired buyer is allowed to purchase the structure at
will. The organization builds to comfortability and produces structures well adaptable to the
environmental condition.
4
2.2 ORGANIZATION CHART OF THE ESTABLISHMENT
This real estate developer organisation has a few policies definitely annotated and
adhered to with compliance to improve and ascertain the quality of job to be done and delivered.
To enhance growth, meet standard of contemporary works trending in the construction sector and
also gratify the desire of its buyer. Below are some the policies;
This organization has committed itself to meeting all set goals prepared for by the
project. Hence, the team plans and controls the use of modern day construction technology for a
proposed project, as well as the determination and agreement of the construction methods to be
5
used for the site work. During construction execution, the project builder and supervisory staff
ensures a maximum and effective workman input in order to obtain a desired speed, quantity and
The company understands the importance of providing quality service and has built it
success and reputation on it. Because of this, the project builder, site manager and project
supervisory staff are motivated to input maximum effort in controlling and regulating the
functional and technical requirement of workmanship. They engage in daily examination of the
progressing project work, ensuring that the work is done appropriately as prescribed.
Furthermore, the organization ensures that it is not being exploited by its suppliers of material by
checking out the quality and quantity on delivery. Moreover, means of improving work methods
The firm owes an overall duty of care to its entire workforce through a safety system of
working and so its objectives are established for the well being of both the people working on the
site and people visiting the site who are exclusive from the workers on site. The health and safety
personnel of the site is assigned with the responsibility of managing health and safety preceding,
6
CHAPTER THREE
During my industrial training with Obimzy Properties, I was privilege to witness the
construction of six different storey building located inside the same site space with almost the
same prototype of outlook and architectural design. The structure is located inside Oba Amusa
Estate Agungi Ajiran Road Off Lekki Epe Express Road Lekki, Lagos State.
The project is a developer project meant to be constructed and sold out at the desired
price of the project investor at completion. The building consists of two fully detach storey
building four bedroom each and then two semi detach storey building four bedroom each.
A fully detach building is a building that stands independently on its own without being attached
to any other structure while a semi detach building is a structure that stand erected but still
attached to another structure but there is a separation wall separating them from each other
creating a difference.
The site consists of two independently standing semi detach buildings, and each
consist of two buildings jointed together but having a separation wall making it four buildings in
two structures. In addition, with the two fully detach house making all six in whole. Inside each
of the buildings we have a first floor and a second floor making it a storey building. The first
floors consist of the living room, a kitchen, a guest room, and a guest toilet while the second
7
floors consist of the master bedroom with its closet and toilet, two other rooms with its toilets,
The building construction site space is duly protected although the space is not quite big
but proper organization is always done from time to time as the project work proceeds, internal
site protection and night security is made available in order to prevent thieves, vandals and
trespassers. Hence, access to the site is prohibited if you are not a staff or worker, visitors are
well informed about how to reach their recipients while the site security does a proper check up
I located the site personally by an environmental survey as there are quite a number of
manager was the one who admitted me and later introduced me to the project builder who was
my site supervisor. I was privilege to relate both with the project manager who gave me a
detailed summary of the project in progress and also permitted me to ask any question I would
like to ask both at the commencement of my training and as the training progresses, and also
with the project builder who happens to be my supervisor whom I report to on regular bases and
takes me through various practical work experience. I had the opportunity to relate with any
worker of any expertise, asking questions and gaining practical knowledge. Moreover, I was well
informed about the work ethics and code of conduct that I must adhere to during the construction
process.
8
Plate 3.1: The 3D design of the proposed project
Plate 3.2: A side and approach view of the construction site and structures
Standard work methods and strategies for achieving productivity under a safe working
9
1. Site layout consideration and planning.
1. Site layout consideration and planning: prior to the construction of the building,
crucial plans and tasks were performed directed and controlled so that the operatives have
there machines positioned and located to there advantage and also materials are stored in
the site storage house and are readily available on demand not interfering with the general
injuries and illness. This illness and injuries may result from contact with physical,
electrical and mechanical workplace hazards. The protective equipment includes hard hat,
3. Risk assessment and control of accident: control measures are put in place to reduce
risk and prevent harm. Risk assessment involves proper controlling of the site work
Safety occurs to be an important project objective and factor to planned and prepared for
in a construction project. There are quite a number of care and safety measures that must be fully
considered and both workers and staff management owe a right to take care to one another in
10
other to avoid or eliminate possibilities of and possible hazards. Because of this reason, specific
Below are some definite site rules that must be adhered to;
Do not use or operate any equipment or machine you lack the technical know how
Abstain from drunkenness or hard drug while working, most especially while working in
It must be attested to that the personnel is capable of doing the work being apportioned to
him.
Provide temporary support facilities for all exposed parts or areas of the building.
Stable and sufficiently rigid scaffolds and working platforms must be provided as needed.
Ensure every place of work at height is thoroughly inspected and examined before work
commences.
1. Hard hat [safety helmet]: this is a hard plastic protective head covering worn on the
head to shield it from any accidental injury due to falls of an individual or falling objects.
11
2. Safety jacket: it is a safety clothing with an highly reflective properties that can easily be
recognized from any distance because of its reflective capability. When worn, they can
site. The jacket can be of various colour like green, yellow, orange. With its reflective
3. Safety boots: these are protective foot wears worn to protect the feet or leg from injuries
Foundation is the lowest part of a structure which is in direct contact with the ground and
transmit the weight of the superstructural load to the ground. There are different types of
foundation depending on the soil bearing capacity of the land area. Some foundation construction
requires trench excavation while some doesn’t and maximum strength must be achieved in other
It takes the structure deep into the ground and increases its stability, preventing
overturning.
To prevent unequal and differential settlement and proper level surface for the
It helps to distribute the weight of the structure over a wide area to avoid
overloading.
12
During the construction, we employed a raft foundation for all the structures in the site,
a beam and slab raft foundation. In a beam and slab type of raft foundation, beams are laid in a
perpendicular direction inside of a formwork made with a marine board and all the beams
connected by raft slab. Columns are situated exactly on intersections of beams of the raft
foundation. This type of raft foundation is suitable when the columns are carrying unequal loads
The base of the raft slab which was used was 600mm wide which happens to be the
footing, while the thickness of the footing is 300mm. The beam of the raft has an height of
800mm with a reinforcement thickness of 150mm, all the columns are 225mm that is 9 inches
and different sizes of reinforcement were used 12mm and 16mm was used and 10mm as the
stirrup.
The formwork was first nailed by the carpenters using wood and marine after which the
iron benders cut the iron to desired length and then bent cold in accordance to the direction given
by the project builder as desired by the project developer, the formwork are then properly and
well reinforced to carry the load coming on it. After the reinforcement work, the formwork was
casted with a coarse aggregate with a mix ratio of 1;2;4, it was both done mechanically by the
use of a mixer to mix the concrete and manually poured into the formwork by unskilled
labourers, it was afterward compacted by a vibrator using a vibrating machine to have the
concrete evenly distributed and compacted inside of the formwork as an uneven distribution can
affect the strength and bearing capacity of the foundation. After the hardening of the concrete,
the formwork was removed and then the raft was filled both manually and mechanically using a
13
Unskilled labourers were hired to do the filling manually using a wheel barrow and
shovel while a payloader [font shovel] was hired to do the filling mechanically alongside the
unskilled labour. Furthermore, the filling was compacted using a rammering machine, after
which the damp proof membrane was put with a very light blinding and then the hardcore
reinforcement was layed using 12mm thick reinforcement both vertically and horizontally
Plate 3.3: Reinforcing of the raft Plate 3.4: Casting of the raft
Plate 3.5: Removal of formwork for the raft Plate 3.6: Raft filling using unskilled labour
14
Plate 3.7: Foundation filling using a pay-loader Plate 3.8: Compaction using a rammering machine
Plate 3.9: Use of damp proof membrane Plate 3.10: Blinding of DPM and laying
Blockwork refers to the construction of building units bonded together with mortar. It is
basically a walling material. On the basis of structural forms, block walls consist of two different
15
kind of walls which are simply load bearing walls and non-load bearing walls. Load bearing
walls are designed and constructed to carry superimposed loads from floors and roofs while non-
load bearing walls are such that carry no superimposed loads but are provided to serve as screen
for privacy.
specified for bricks with its height not exceeding either its length or six times its thickness.
Building blocks could be solid, hollow or cellular. At the construction site where I worked, we
made use of hollow concrete blocks with different standard sizes. They are:
Block setting and laying were one of the major site works carried out by bricklayers.
Proper speculation was used during this operation, 9 inches blocks were used for external walls
and separation walls while 6 inches blocks were used for internal partition walls. The external
walls are wholly and entirely load bearing walls while most of the internal walls are load bearing
walls and some are none load bearing walls. Before the commencement of the blockwork,
preliminary block setting out was done to divide the house into partitions differentiating the
rooms, the toilet, family lounge etc. Beginning from either the back side of the building or the
Cement mortar mix ratio of 1:6 are mixed with appropriate water ratio to be used for
bedding and jointing of the blocks. Moreover, stretcher bond block arrangement was adopted.
During my training, I had the privilege to learn and practice the block-laying process. This task
16
Preparation of cement mortar using 1:6 mix ratio
Placement of the ready mix mortar for the block bedding plane.
Placing of blocks at two extreme opposite sides of the space and tying of building lines to the
blocks on the same plane. Marking out of door openings where necessary.
Measurement of the distance between the blocks to check if it corresponds with the drawings
Alignment verification of the two blocks with the aid of steel lath as a range and spirit level
plumb.
Placing of the remaining blocks and alignment verification using range, spirit level and
The same procedure was repeated severally for all the floors of the building, and we have 10
courses of block from the surface of the hardcore or second floor slab to the lintel while there are 3
courses of block above the lintel before the roof beam and parapet .
17
Plate 3.12: Block laying for upper floor Plate 3.13: Block laying for fencing
3.3.3 STAIRS
large vertical distance by dividing it into smaller vertical distances, called steps. A stair can also
be defined as a series of steps suitably designed and constructed for the purpose of connecting
different floors of a building thereby providing quick access as well as rendering comfort and
safety to the users. Stairs may be made from such different materials as timber, brick, steel, plain
18
concrete or reinforced concrete. Based on mode of construction, stairs may be classified as
straight flight, half turn, quarter turn, open-newel, circular, geometrical and bifurcated stairs.
The planning and designing of stairs, requires the consideration of various factors such
as location, safety, comfort and economy, and this factor were ultimately considered during the
construction of all the stairs inside the buildings on site. I had a stunning experience of seeing
and being part of turning detailed stair drawings into reality through calculation, sketches and the
construction process. While constructing, we determined and fixed the size of the risers and tread
of a step of every stair based on the length and height of the stair way. The numbers of the risers
is greatly influenced and also determined by the distance between the first floor and second floor
while the number of tread is also influenced by the length of the stairway. Most of the stairs we
constructed inside of the building were located in doorway, so the height of the door were greatly
considered in other to have the stairs above the door. All the stairs are actually a combination of
an half turn and spiral stairs. The stairs has no landing until the upper floor has being reached but
rather the area that’s supposed to be for the landing was constructed as a spiral. We ensured that
the riser and tread of each step in a stair were kept at uniform dimension as we marked out the
19
Plate 3.16: Spiral area of the stairs Plate 3.17: casting of the stairway
These are floors mainly constructed on site for the purpose of supporting their own
weight as well as carrying other dead and live loads. A few factors such as type of loading, span,
degree of sound insulation and fire resistance required, provision of services as well as speed of
erection and adaptability were considered while constructing this building element.
All of the upper floors constructed on the site are cantilever i.e it extends beyond the
normal wall coming from the first floor making the second floor more spacious and wider than
the first floor. Some sides of the cantilever are 1m, while 1.2m was used for the balcony area and
at the same time for some the building the left and right side of the building was 1.2m while the
balcony was 1.5m making it to have a more space area than the others. The upper floor are
usually allowed to harden for 21 days before removing the formwork. While constructing the
A Form work that is rigidly supported was made for the slab and beams
20
Prescribe mix was placed and compacted
Formworks were struck and removed in stages after a hardened floor slab is formed.
namely, concrete and steel forms in which the whole process is refer to as reinforcement work .
On the one hand, concrete has a considerable crushing strength, it is durable, has good fire
resistance but is fair in shear and offers little or no strength in tension. On the other hand, steel
has good tensile properties, poor resistance to fire and is very good both in shear and in
compression. So the combination of these materials both concrete and steel results in good
product which is rich in tensile and compressive strength, durability and resistance to fire.
The materials which can be used as reinforcement in reinforced concrete work should have the
following characteristics:
(iii) Concrete should not produce any harmful effect on the material.
21
(iv) It should be easily available.
Steel is seen as the only material that meets all the above requirements and it is used on
large scale in reinforced concrete works. Various types of steel can be used for making different
form of reinforcement and they include mild steel, medium tensile steel, high yield tensile steel
In the course of my internship, the steel reinforcing bars(rebars) were used in the
slabs, inside the parapet and also inside of the angle window although they could still be likened
to a beam, in addition to that the coping on the balcony are also reinforced.
Columns primarily are vertical or compression members that carry the loads from the
beams and slabs of a structure down to the foundation below. Fundamentally, they can be
categorized as (i) axially loaded columns (ii) columns subjected to uniaxial bending (iii) columns
subjected to biaxial bending. Column reinforcements were cut, bent and bound with binding
We instructed the iron benders on the bar sizes in diameter, number of rods, rod type
and spacing needed to prepare for every area required. While working on reinforced concrete
structures 4-Y12, 4Y16 or 6-Y12 rebars were used and stirrups with spacing of 200mm centres
were provided to prevent buckling. While, we make consistent checks to ensure that the columns
22
eventually act in a concentric manner in the areas where they are placed and that the adjacent or
To begin with, beams are horizontal or inclined structural members having spans
between supports and carrying lateral loads across their longitudinal axes. They are also capable
Slabs on the other hand, are structural members that support, transfer or share the
loads of a structure with columns and beams. They act as floor levels and also create platforms
for walls to be built. A combination of beam and slab reinforcements were assembled, erected
and placed on well-supported formworks on site. Just as we did for column reinforcement,
arrangement and placement of column reinforcement to different structures on site number and
sizes of rods as well as spacing to be used were given to the iron benders, the length of the
cantilever, the length of the return reinforcement {I was thought that the length of the return iron
above the cantilever is determined by the length of the cantilever multiply by 3.2}. The
reinforcement for structural beams and slabs were arranged in the form of a square with the
23
main(bottom) and secondary(top) fixed to links or stirrups that held them in position during
concrete placement, anchored them with the placed concrete as well as provide some resistance
to shear. Since all of the building were meant to carry the same and all equivalent proportion of
load the distribution and variation of sizes of iron are used similarly in all the building. The
regular 9 inches beam which is 225mmx225mm was majorly used, while we have a drop beam
mainly used in area where the distance of the columns perpendicular to the beam and parallel to
each other are far from each other for example in the living room and the size of the drop beam is
450mmx225mm, we also have some beams spanning above the 6inches block which made this
beam to 6inches as well which is 150mmx225mm. Meanwhile, most roof beams are
225mmx225mm in size as they provide support for the tie beam. Spacing of 200mm centres was
kept all through for the links. Moreover, in beam and slab reinforcement work, hidden or
concealed or rather secret beams were provided in order to evenly transfer the imposed loads on
the slab to the column and as well as allow for the usage of a greater span of the slab. In the same
vein, most slabs on site were arranged in a two-way spanning form, owing to the incoming
imposed loads with the bottom and top reinforcements separated and prevented from overlying
each other.
Also, concrete spacers were provided to prevent the bottom reinforcing bars from lying
directly on top of the slab panel formwork, and also prevent the reinforcement from lying
Prior to placement of reinforcing bars on formwork, we ensured that they are free from
loose rust, oil or any coating that can impair the real performance of the steel with the concrete.
Also, we made sure that the bars were placed and maintained in accurate position and prevented
24
Plate 3.20: Fixing of reinforcement for slab and beam
A parapet is a barrier that is an extension of the room beam at the edge of a roof,
terrace, balcony or other structure. The word comes from an Italian word parapetto {parare
means ‘to cover’ while petto means ‘chest’}. A parapet may simply means a portion of an
exterior wall that continues above the edge line of the roof surface or may be a continuation of a
vertical feature beneath the roof. Parapets were originally used to defend buildings from military
attack, but today they are primarily used as guard rails to conceal roof top, reduce wind loads on
roof, and prevent the spread of fires. They are used in place of wooden wall plate.
25
3.3.6 FORMWORK
Formwork is the term used for the process of creating temporary mould into which
concrete is poured and formed after setting. Traditional formwork is fabricated using timber, but
it can also be fabricated from steel and other materials just that the cost is not cheap as engaging
the traditional method. A good formwork should satisfy the following main requirements:
(i) It should be strong enough to withstand all types of dead and live loads imposed on it
(ii) It should be rigidly constructed and efficiently propped and braced so as to retain its
(iii) The joints in the formwork should be tight against leakage of cement grout
(v) The material of the formwork should not warp or get distorted when exposed to sun,
(vi) The material of the formwork should be cheap, easily available and should be suitable
As it has been said earlier that formwork can be made of timber, plywood,
steel, precast concrete or fibre glass, used separately or in combination. The type of
material to be used for formwork depends on the nature of construction, availability and
cost of material.
easily workable timber products. The construction of formwork for the three main
26
structural members (column, beam and slab) are different from one another. Here, I also
called marine board (25mm thick) were cut and moulded to form the desired shape and
size able to retain the wet concrete and resist the initial hydrostatic pressure caused by
the wet concrete. Horizontal clamps were used at specific points in order to maintain the
thickness of the formwork material during concrete pour. Prior to this, concrete plinths
were made in other to determine the location of the form and also prevent grout loss
from the bottom of the column formwork. Also, struts were provided at some sides of the
formwork in other to prevent displacement or distortion during and after concreting. The
beam formworks were erected to box-like structure able to carry accommodate the
incoming reinforcing steel bars and concrete. The formwork, were made in a manner
able to resist able to resist the initial dead load of the wet concrete and all joints were
firmly fit to prevent grout leakage. Also, bamboos were made available to support the
formwork in order to prevent shear during the concrete operation and after the concrete
operation. The same timber wood used for the first three building that is the phase 1 of
the project were also used for the other three that is the phase 2 of the project just that
additional material had to be purchased to support the old ones. Various sizes of wood
were used for the formwork, we used 1 x 12, 1 x 9, 1 x 6, 1 x 3, 2 x 2. The wood sizes
varies from the area of use like the wood sizes used in making formwork for the parapet
are quite different from the addition wood used in constructing the formwork for beam,
slab and column. At the site, the formwork for the slab extends beyond the wall from
below which is being called cantilever to have a larger floor area and the formwork were
27
support vertically and there are stopper at the edges of the slab formwork to prevent the
concrete from discharging away from on top of the slab and gives it the proper shape.
The formwork for the beams and columns are often removed the second day to move
the project forward into the next stage of work. But the formwork constructed for the slab are
removed after 21 days when the concrete has been allowed to cure and attain maximum strength
28
3.3.7 CONCRETE WORK
mixing cement, fine aggregate and coarse aggregate with water in a suitable proportion and then
allowing the mix to cure producing a plastic mixture to form an hard mass. While onsite we
made use of cast in concrete which is a technology of construction of buildings where beams and
slabs of the building are cast at the site in a read made formwork.
The hardened concrete resembles stone in weight, hardness and strength to a great extent. The
properties of concrete depend on the quantity and proportion of the materials used and this
While on site, we used a few set of concrete grade mixes depending on the nature of
work and the intended purpose of the concrete structure. These grade mixes are: C15(1:3:6),
C20(1:2:4), C15 was used for casting columns and lintel areas, C20 was used for casting
depending on the output required, discharge height and the method of transporting the mixed
concrete. The method happens to be the nominal site mix through the use of small batch tilting
drum mixer. Small batch mixers were hand loaded and are used where time is not really
considered and there is easy means of placing the concrete at the required position, the concrete
were loaded and transported to the second floor in buckets which is equivalent to an head pan by
The concrete are then compacted or vibrated by a vibrator using a vibrating machine in
other for the concrete to settle and compact properly so that we can have well leveled surface
29
On the site where I did my training, the formwork for the lintels and column are
always removed the second day of the casting of the concrete without defect, as the concrete
would have attained enough strength to carry imposed load. So block work comes on the
concrete the second day. But for the slab floors, though block work begins the second day but the
Plate 3.24: Use of mixing machine and transporting of the concrete to the upper floor
3.3.8. SCAFFOLDING
Scaffold in building construction, are temporary platform used to elevate and support
workers and materials during construction, repair, or cleaning of a structure, use of a machine or
30
installation. Allows mason to work at different stages of a structure, to raise material for use even
at an extreme height.
Since we dealt with the construction of high rise buildings. The scaffolding for each
building was done ones and was never removed until it use was completely exhausted. This
temporary structure was made available at every point of need for such building works as
observed and acquired a worthwhile knowledge in the construction process of this temporary
structure and the need for it being safe to work on. We used just one type of scaffold on the site
where I worked as a trainer which is the timber type of scaffold constructed with the use of
bamboos. The bamboos were jointed together using 5inches nails and binding wires to held it
firmly jointed together for safety. The bamboo was erected both parallel and perpendicular to
Mechanical work refers to the laying, installation, alteration of water pipes, taps, tanks,
and fitting for water supply system in building. It also and deals with sanitary discharge pipes
31
and sanitary appliances like water closet, urinal, Wash hand basin also called toilet bowls. In
general it deals with the supply of clean water, the management system of the water both in
toilet, bath and kitchen and also the discharge of both fowl and soil water outside of the building.
At the construction site where I did my training, I was opportune to look upon the
stages and progression of the mechanical work as it is not a work that can be done once and off.
Beginning from the foundation to the second floor to when tiling was being done and to the time
when different appliances and fixture were being fixed. The waste pipe, were casted alongside
the raft and also alongside the concrete slab floor. Various inches of pipe were used depending
on the substance its carrying, pvc {polyvinyl chloride} pipes were used for the waste water while
ppr{polypropylene random copolymer} pipes were used for the clean water supply. The pvc
pipes were connected together using gum to have it firmly stick together while the ppr pipes
The ppr pipe has a better long lasting quality than the pvc pipe. I saw the installation of
appliances, like the concealed water closet system which is being fixed into the wall, the water
heater, the shower system with the combination of a tap. Taps were fixed into the compound area
32
Plate 3.27: water and waste pipe work
The pipes were installed inside of the formwork for foundation and slab after
which the concrete was casted which means we made use of conduit method of pipe
installation. And after which we had the concrete casted over it.
The conceal system is fixed permanently into the wall, the closet that takes the
waste is attached and it suspends above the ground unlike the regular one by the right that
sits on the ground. The concealed is more expensive than the regular but it gives room for
33
Plate 3.29: Installation of wash hand basin.
every work done both internal and external of a building in other to supply electricity and power
electric appliances either it is through the public light or a personal private generating system.
It involves the use of different kinds of appliances, different sizes of cables, boxes and pipes.
During my training, the electrical work commenced after the block work with fixing of
electrical boxes. The walls were chiseled and the box were position base on specification.
Factors like where the TV wall will be in all the rooms were considered before chiseling the
wall. The electric pipe was connected to the box making it is a conduit installation as well, but
the kind of pipe differs from that use in water distribution, electric pipes are lighter than water
distribution pipes.
Prior to the concrete slab casting, electrical pipes and boxes were installed above the
formwork for the slab and the pipes were eventually buried inside of the concrete for connection
After the formwork has been reinforced, concrete biscuits were positioned beneath the
reinforcement to raise the irons up in other to fix the pipe and boxes. The pipes were bent to the
34
appropriate direction using the bending spring. Various factors such as where the dining table
will be positioned, the surveillance camera, were considered for the lighting box and camera
boxes. The diameter of the cables use for different fixtures was also a determinant factor in
The electrical personnel did a whole lot of job in making sure that there is proper
connection, the lighting fixture were fixed after the pop ceiling has been fixed even though the
cable connection has been done before that. From the distribution board the connection spans to
different fixture. Two different distribution board were used for each building, one distribution
board for the first floor and another distribution board for the second floor. This was done
because of the density of electrical load supply coming into each floor.
Plate 3.30: Installation of electric pipes above the formwork for slab floor.
Plate 3.31: Fixing of electric socket Plate 3.32: Control switch Plate 3.33: Drilling of ceiling for installation .
35
Plate 3.34: Fixing of electric boxes
provided over the top of a building with a view to provide protection from the weather elements
and the adverse effects of these elements. Rather, a roof structure is essentially the frame your
roofing sheet will be attached to. It consists of the various members including the tie beam,
The choice of a type of roof for a building could be made after paying due
consideration to the climatic conditions, the nature of building as well as the availability of
materials. In addition, a well-planned roof should satisfy the following main requirements:
I. It should be strong enough and structurally sound to carry the intended dead and live
loads safely.
II. The roof should be durable against adverse effects of weather elements.
36
In general, roofs can be broadly classified to the following main types:
During the construction work I witnessed at obimzy properties, the type of roof we used
was a pitched roof. The roof structure was constructed traditionally with the use of timber hard
wood. Of all the roof members the roof structure was void of one which is the facial board and
the parapet happened to be the replacement for the facial board which is a best option for
Below are the roof members and sizes of wood used for the construction:
V. Rafter 2x4
VI. Noggings 2x 2
The kingpost was pitched to a height of 5.5metres and another of the building pitched to
a height of 6metres. The carpenters were properly supervised to ensure that the job was done
according to specification, and the workmanship were able to satisfy the requirement. After the
roof members has been constructed, the roofing sheet was attached to it using nail and the
roofing used was the coated bond roofing sheet locally called gerad, it is much more durable
than the regular aluminum roofing sheet. In addition, roof gutters were attached strategically to
37
different parts of the roof structure in other to regulate the flow of water down pour flowing from
the roof. It greatly prevents the effect of water on the wall and wall paint.
There are three main finishes provided to the wall which are plastering, screeding and
painting. Before the commencement of the plastering process, the wall surfaces were chiseled to
have it leveled together to have a smooth plastering surface. The surface was cleaned of dusts
38
and loose mortar joints or bed that protruded during the block-laying process, and then
moistened with water. Afterwards the level of the surface was taking and nails in a rectangular
manner was attached across the surface and then a line was attached also to get a specific
thickness. And then, patches of plaster were applied horizontally and vertically over the entire
surface. Mortar being laid on wooden float was then applied on the wall with the aid of a trowel.
Pure cement was applied on the surface of the plastering as it progresses so the plaster
can stand firm on the wall to reduce wastage of falling concrete from the wall. After all the
After the plastering process had been accomplished and the surface has dried, the
screeding operation commences by scrapping the wall surface using a scraper and then a mixture
of screeding paint, top bond and cement in accurate proportion was used to prepare the surface
which is the first layer and then the pure screeding paint was used on the surface making it
39
Plate 3.37: Screeding process progression.
Also, the painting itself which is done in various layer, the primer, the undercoat and
finally the finishing coat. The color of the paint used was white.
Finally, tiling was done to some part of the walls like the front view of the buildings for
40
The window spaces provided for in the building were exceptional and well planned for as
they are cross ventilated windows. Most of the windows are 1m in breadth and spans from the
third course of block to the lintel except for the angle windows and toilet windows. The angle
window comprises of aluminum and glass making it of great quality. The window was made up
of 12mm iron reinforcement in place of the regular burglary fixed into the wall for security
purpose. The angle windows were positioned in the master bedroom situated at the forefront of
Also, outside and around the window area we have the window hood which is a kind of
concrete design, purposed to give more aesthetic to building, it was molded in a precast form and
41
Plate 3.40: Molding and fixing of the window hood.
At the site where I did my training we made use of two different ceiling finish, the first is
the pop ceiling finish which was used for the inward part of the building. It was quite an
exciting part of the job but also a tedious as the pop ceiling mold were casted first using the
To do the molding, an aluminum iron which has been cut to the desired length was placed
in a rectangular manner on a set smooth table made of a marine timber board, and then a liquid
soap mixed with vegetable oil was poured on the table to reduce friction and allow ease of
removing the mold after hardening, after which the flax was use to spread the soap evenly on the
board within the space where the pop cement will be poured. The wet mix of the pop cement was
poured within the aluminum space on the timber board, afterwards the flax which acts as the
reinforcement was added and the mix was allow to harden, it takes less than 10 minutes for it to
harden. The fixing too was done using the water level to get an appropriate level for the finish.
Also, the ceiling was hung to the tie beam using a wet mix of the cement and flax.
42
Plate 3.41: POP ceiling work.
Secondly was the suspended wooden ceiling finish which was made of hard wood and
it was used for the outward part of the building like the balcony.
Plate 3.42: Suspended wooden ceiling finish {cutting and fixing of the wood}
Floor tiling was the only finish done on the floor surface for the whole of the buildings.
The tiles were all ceramic product of various sizes, patterns and colors. The tiling process was
43
achieved by laying a floor screed using the mixture of sand and cement and a little quantity of
water evenly spread and well compacted using a ranging pole, the floor tiles were then laid on
the screed from the center of the area towards the edges.
Doors are majorly for security purpose and the doors that were used at the site were all
wooden door made of hard wood including the door at the main entrance which is a security. The
wooden doors to me looks quite better than the even many doors made of steel. The subframe of
44
the doors were fixed during the plastering and after the painting and tiling the doors were being
The program has been very inspiring to me and it has updated and upgraded my
knowledge and perspective on how projects are executed on site. The experience is quite
different from the theoretical class and it is much more enlightening and preparatory for
proficiency in the built industry. The experiences gained are not just limited to the site activities
and operation but also learning how to interact with people in an organization and settling of
1. Setting out for block work: one of the experiences gained was that I was given a chance
to do the setting out for the second floor of a whole building. I was giving a standard to
use and it was to partition the building into various compartment by transferring the
measurement used in another building and then set out using the measuring tape, line and
45
builder square, though the process was overseen by my supervisor but I was given the
chance to practicalize what have seen and thought over and over again within the site.
measurement of some work items on site. At most cases, I was assigned the duty of
measuring work done such as blockwork. The actual sizes of these works are compiled
needed this present day. I observed and interacted with my boss on the project
management principles being adopted in order to deliver a quality project, within budget
in a safe working environment and on time. Also, I had a glimpse of orientation on how
to assign work to site operatives in a way that will meet these project objectives and given
PROVIDED
The road to the site is often flooded with water imposing risk of life.
Misunderstanding between the project developer and the project manager on taking
The work is quite stressful because we work all days of the week except that I was
46
As a student I had challenges in coordinating the actions of some site workers
also be insulting.
There are times when the project was slow because of reluctancy of site operatives
due to lack of payment for jobs that had been done as a result of funds not being
released.
Solutions provided:
The site workers were motivated to work more efficiently and effectively.
Funds were released to pay the workers in other for the construction to progress.
Patient in dealing with the site operatives, made them more receptive and
obedient to instruction.
Sometimes incentives in monetary form were given out to motivate the workers.
CHAPTER FOUR
4.1 CONCLUSION
industry is becoming more sophisticated and professional with a high level of development, the
constructive effects of the Students Industrial Work Experience Scheme (SIWES) on students
cannot be under rated and under estimated. Throughout the past months, the scheme has
47
transformed me from the state of curiosity in quest for an invaluable experience in my field to be
an experienced and refined student that has been trained and set on the track of professional
advancement in the diverse course of construction technology. All through my stay with the
and methodology behind advanced construction technology, the pertinent task required planing,
organizing, directing and controlling of the construction operations for the successful completion
The internship period, though stressful and rigorous is nevertheless interesting and a
basic means of contact between the student and his or her anticipated professional career and it
would help the student to view the industrial world with sense of responsibility.
Finally, it is a platform that provides the experience that which helps an individual to
discover his or her present self, what he is capable of and void of as well as determine how the
future will be as such an individual sail through the course of life. Hence, it should be taken with
utmost seriousness by every student who intends to be a change agent and pacesetter in his or her
4.2 RECOMMENDATIONS
The SIWES program has been of a great advantage as it has help in giving an exceptional
experience to any passionate student. However, there are a few things I recommend about the
1. The Federal Government should provide industries and organizations to encourage and
48
2. The Industrial Liaison office and Students’ Departmental Supervisor(s) should endeavor
to regularly visit students on site to solve some relevant problems and for adequate
evaluation.
Experience Scheme. This will contribute to the success of the program as students could
be offered placement from school instead of them seeking for months before finding a
suitable organization.
4. Finally, students themselves must be willing and ready to learn at the period of the
training.
REFERENCES
49