SATIP-H-002-05 Epoxy For Atmospheric Up To 150C

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)

SATIP No. APPROVED DATE DISCIPLINE:


SAUDI ARAMCO TYPICAL INSPECTION PLAN
Epoxy Coating System for Atmospheric Services
SATIP-H-002-05 11-Apr-04 COATING
(Up to 150C) - APCS 1A/B/C/D
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

1.0 DOCUMENT REVIEW

1.1 Coating Procedure SAIC-H-2042 RH1 RH1


Coating Personel Qualification and /or SAIC-H-2010
1.2
Testing SATR-H-2007
RH1 RH1

2.0 MATERIAL RECEIVING

S. Aramco shall inspect the first batch of delivered


Verification and Visual Inspection of
2.1
Paints and abrasives
SAIC-H-2024 H1 W2 paints and abrasives, after which random inspection
will be conducted.
Storage and Handling of Paints and
2.2
Abrasives
SAIC-H-2025 H1 S
SAIC-H-2026
2.3 Equipment Inspection
SATR-H-2004
H1 H1

3.0 APPLICATION

3.1 Pre-Cleaning Inspection SAIC-H-2014 H1 W1


Surface Preparation & Pre-Application of SAIC-H-2043
3.2
Coating Inspection SATR-H-2005
H1 W1
Zinc Silicate Primer Application (when
3.3 Refer to SATIP-H-002-07
required)
SAIC-H-2044
3.4 First & Intermediate Coat Inspection
SATR-H-2005
H1 S
Top Coat Inspection (Visual Inspection- SAIC-H-2045
3.5
Completed Paint) SATR-H-2005
H1 W1

4.0 PAINT REPAIR

Surface Preparation Inspection of repair SAIC-H-2046


4.1
areas SATR-H-2005
H1 W1
SAIC-H-2044
4.2 First, Intermediate and Top Coat Inspectio SAIC-H-2045 H1 W1
SATR-H-2005

Page 1 of 2
SAUDI ARAMCO 9000-ENG (10/03) 726-400 (ID/PID)
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Epoxy Coating System for Atmospheric Services
SATIP-H-002-05 11-Apr-04 COATING
(Up to 150C) - APCS 1A/B/C/D
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

CHECKLIST INSPECTION RESPONSIBILITY


ITEM and/or QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. TEST RECORD SAUDI
CNTRCTR
RECORD ARAMCO

Color Coding and Equipment


4.3
Identification
SAIC-H-2031 H1 W1

5.0 PRE-COMMISSIONING

SAIC-H-2034
5.1 Final Coating Inspection by contractor
SATR-A-2011
H1 W1
Final Inspection for Mechanical
5.2
Completion
SA-6133 H1

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4
attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1 100% Witness Inspection/Test H2 Sample Hold Point for QC Inspection or Test RH1 100% Review and Approval of Documents
W2 Sample Witness Inspection/Test R1 100% Review of Documents RH2 Sample Review and Approval of Documents
H1 100% Hold Point for QC Inspection or Test R2 sample Review of Documents S Surveillance

Page 2 of 2