General Commissioning Requirements TA1056 MBI Sampang Agung Brewery Extension 019113 - 1
General Commissioning Requirements TA1056 MBI Sampang Agung Brewery Extension 019113 - 1
General Commissioning Requirements TA1056 MBI Sampang Agung Brewery Extension 019113 - 1
PART 1 - GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
other Division 01 Specification Sections, apply to this Section.
B. OPR and BoD documentation are included by reference for information only.
1.2 SUMMARY
A. Section includes general requirements that apply to implementation of commissioning without regard to
specific systems, assemblies, or components.
B. Related Sections:
1.3 DEFINITIONS
A. BoD: Basis of Design. A document that records concepts, calculations, decisions, and product selections
used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The
document includes both narrative descriptions and lists of individual items that support the design process.
D. OPR: Owner's Project Requirements. A document that details the functional requirements of a project
and the expectations of how it will be used and operated. These include Project goals, measurable
performance criteria, cost considerations, benchmarks, success criteria, and supporting information.
E. Systems, Subsystems, Equipment, and Components: Where these terms are used together or separately,
they shall mean "as-built" systems, subsystems, equipment, and components.
A. Members Appointed by Contractor(s): Individuals, each having the authority to act on behalf of the entity
he or she represents, explicitly organized to implement the commissioning process through coordinated
action. The commissioning team shall consist of, but not be limited to, representatives of Contractor,
including Project superintendent and subcontractors, installers, suppliers, and specialists deemed
appropriate by the CxA.
1. CxA: The designated person, company, or entity that plans, schedules, and coordinates the
commissioning team to implement the commissioning process. Owner will engage the CxA under
a separate contract.
2. Representatives of the facility user and operation and maintenance personnel.
3. Architect and engineering design professionals.
A. Provide the OPR documentation to the CxA and Contractor for information and use.
B. Assign operation and maintenance personnel and schedule them to participate in commissioning team
activities.
C. Provide the BoD documentation, prepared by Architect and approved by Owner, to the CxA and
Contractor for use in developing the commissioning plan, systems manual, and operation and
maintenance training plan.
A. Contractor shall assign representatives with expertise and authority to act on its behalf and shall schedule
them to participate in and perform commissioning process activities including, but not limited to, the
following:
1. Evaluate performance deficiencies identified in test reports and, in collaboration with entity
responsible for system and equipment installation, recommend corrective action.
E. Verify the execution of commissioning process activities using random sampling. The sampling rate may
vary from 1 to 100 percent. Verification will include, but is not limited to, equipment submittals,
construction checklists, training, operating and maintenance data, tests, and test reports to verify
compliance with the OPR. When a random sample does not meet the requirement, the CxA will report the
failure in the Issues Log.
I. Compile test data, inspection reports, and certificates; include them in the systems manual and
commissioning process report.