Water Test & Flushing Activity - Checklist

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Saudi CHECKLIST

WATER TEST / FLUSHING ACTIVITY Date:


Aircon
@ TADAWUL TOWER, KAFD

Activity type Water Test / Flushing / Gravity Test / etc.,


Trade HVAC / FF / PLU (Drainage / PLU (WS)
Level
Location / Area

Please ensure the following activities prior to commence of water testing / flushing activity;

Sl No., Activity Description YES NO N/A

1 Availability of Approved WIR for installation works.

2 Approved Drawings enclosed including highlighted section of pipework under test.

3 All pipe joints, fittings, couplings, are checked for required tightness / torque values.

4 Temporary supports provided for End caps, wherever applicable.

5 Air Leakage test conducted, monitored and successful.

6 Electrical panels and other sensitive items are protected adequately.

7 Water filling point is properly sourced.

8 Required Drain points are provided and connected to drain network.

9 Accessibility of Drain and Filling point.

10 Required resources are available to tackle the Emergency cleaning / draining if required
(like drums, sump pumps, manpower, watchman)…
11 Signages ?

12 Safety officer allocated.

13 Logistic team to be informed.

14 Electrical team to be informed.

15 Concerned Construction Engineer informed and checklist if signed

Remarks if any:

Checked and Ready

SAC (Representative) Sign: Remarks Date :

SCCE JV (Representative) Sign: Remarks Date :


HSE Team(Representative) Sign: Remarks Date :