Buiding Maintenance and Management
Buiding Maintenance and Management
Buiding Maintenance and Management
Building management in Nigeria is still in an early learning cycle when compared with the
situation in Europe, USA etc where the practice has been on since the 1980’s. Some
corporate organizations are increasingly embracing the need for efficient facilities
management. Like any new venture, facilities management practice in Nigeria is expected to
also have its commencement problems. This study examines the role of the facilities manager
and highlights the problems that constrain effective facilities management. The research
adopted both survey and case study methods. The survey was used in data collection while
the case study was based on an intensive study of six selected drug, beverages and textile
manufacturing industries in Lagos. The sampling technique used was simple random
sampling. The sample of 240 respondents was drawn from the population parameters through
Taro Yamani model. A total number of 200 completed questionnaires representing 83.3% of
the distribution made were recovered and used for statistical analysis. The hypothesis of this
study postulates that facilities management problems do not have significant effect on
efficient productivity in an organization. The data collected were subjected to an inferential
statistical test using chi-square technique. The major problems identified include poor
funding and maintenance, bureaucracy and unavailability of skilled/right professionals. The
result of the statistical analysis obtained is shown as follows: X2cal
= 157.08 and X2tab = 7.82. This shows that the null hypothesis should be rejected in
favour of the alternative hypothesis, based on the decision rule to reject the null hypothesis if
the calculated value is greater than the table value. This work concludes that facilities
management problems have significant effect on efficient productivity in an organization.
Benchmarking, safety and security provision, good communication, continuous training
programs, adequate budgetary provisions, value-engineering application among others are
recommended.
TABLE OF CONTENT
Title Page i
Approval Page ii
Certification iii
Dedication iv
Acknowledgement v
Abstract vi
List of Tables xi
Chapter Two
3.0 Methodology 39
Chapter Four
Adequate? 52
Satisfied? 54
Chapter Five
Recommendations 62
5.2 Conclusion 64
5.3 Recommendations 64
References 70
Appendix 74
LIST OF TABLES
questionnaire 43
managed 47
facilities management 49
1.1 INTRODUCTION
By the nature of creation there is virtually nothing man-made that is indestructible, but the
usefulness of many such items can be extended by carrying out repair at regular intervals
through an activity known as maintenance. White (2009) defined maintenance as the “work
undertaken to restore every facility to an acceptable standard at an acceptable cost”. The use
and exposure to environmental conditions subjects machines, buildings and other service
these building maintenance unserviceable and brings them to a standstill. Firms and
organization, therefore has no choice but to attend to them from time to time, to repair and
recondition them so as to prolong their usefulness to the extent, they are economically and
services that will permit uninterrupted implementation of plans requiring their use.
Theoretically, maintenance should aim at keeping the machines and other facilities in a
condition that allows them to be used without any interruption and at their maximum profit
making capacity. (Adegoke, 2003).However, as adequate care is being taken to ensure the
reconditioning of the machine and building facilities back to their original state, a level at
which it will be able to perform the intended use, however cognizance should be taken of the
fact that, if it has to be done; it should be at minimum cost, with improved output, emphasis
the entire organization, and with every responsibility for quality of work output. (Iyagba,
and procedures guided by an organization’s mission and its available resources (Sanni, 1998).
Organizations may not be aware of the extent to which value for money in building
maintenance and management can be improved. This suggests that it is not the outcome that
needs to be looked at closely, but the decision making that leads to it. There are common
approaches to facilities management, regardless of the size and location of buildings, although
these may not necessarily result to common solutions to problems. In some cases, estate-
related and building maintenance services are outsourced (contracted out) and in others
retained in house for good reasons in each case. There are also many organizations that
operate what might be described as a mixed economy, where some services are outsourced in
In view of the above, this study is to critically examine the problems of building maintenance
Building maintenance and management in Niger State is still in an early learning cycle when
compared with the situation in other states like Lagos, Abuja, Kaduna etc, where the practice
has been on since the Millennium. Some corporate organizations are increasingly bracing the
need for efficient building maintenance and management. Like any new venture, building
maintenance and
Management practice is expected to also have its commencement critical challenges. It is
these critical challenges of building maintenance and management that this study intends to
find out.
The aim of this research is to examine the prospect and challenges of building maintenance
Building is a broad subject hence this study was restricted to maintenance and management
building/facilities managers.
papers, textbooks, internet materials, journals, magazines and recent works on the
subject.
2. H0: Resources allocated for building maintenance and management are not
adequate.
adequate.
This study will help to articulate the philosophy behind the idea (concept) of building
maintenance and management as an emerging field of study and area of specialization. The
study will bring to bear unforeseen problems on this emerging field presently and those that
are likely to spring up in the near future. It will also prepare the minds of future or
2. To what extent do the building and facilities compliment their basic function?
automation etc?
4. To what extent are the resources allocated for building maintenance and
management adequate?
5. To what extent are the building and facilities user’s requirements satisfied?
6. What are the major problems encountered by building and managers and how
The Niger State College of Education, Minna was established as an Advanced Teachers’
College by the defunct North Western State Government in 1st November, 1975 when there
was need to establish an additional Advanced Teachers’ College in order to meet the soaring
teachers needs in the State. In 1983, the College was upgraded to the status of College of
Education by the defunct Civilian Government in the Second Republic through the Niger
State Edict N.S.L.N Number 3 of 1983. With the College’s new status, the nomenclature of
the Principal of the College was changed to the Provost and that of the Administrative
Secretary to the Registrar. The Edit was amended under Niger State Edict No. 1 of 1988, and
The College took off in its temporary site in Bosso – Minna in November, 1975 with a
foundation Teaching Staff of nine (9), a total intake of one hundred (100) Students, and
sixteen (16) Administrative Staff. Late Dr. Umaru Sanda Ahmadu was the first Principal and
Provost of the College. Dr. Gambo T. Yusuf became the second Provost in 1988, Dr. Bukar
Emmanuel Naroka Dauda in 1993, Professor Ibrahim Adamu Kolo in 2001, Professor, Faruk
Rashid Haruna in 2009 and Professor Muhammad Yakubu Auna succeeded him in 2017 to
date.
Alhaji Muhammad Giwa was the first Administrative Secretary and Registrar of the College.
Alhaji Ismaila Mohammed Lawal succeeded him in August, 1993 followed by Alhaji Yusuf
Muhammad Makusidi in 2007, Alhaji Abdullahi Dalhatu Umar in 2009, and the current
The College offers several courses leading to the award of Nigeria Certificate in Education
(NCE). Other courses run by the College are Professional Diploma in Education (PDE) and
Undergraduate programmes in affiliation with Ahmadu Bello University, Zaria and Usmanu
CHAPTER TWO
2.0 LITERATURE REVIEW
2.1 CONCEPT OF BUILDING MAINTENANCE
Building maintenance has consistently been treated as the “poor relation” of the
construction industry, attracting only a tacit recognition of its importance, both within
the industry and among building owners (Barrie & Peter, 2007). This manifest itself in a
general lack of understanding of both its scope and its significance by all parties to the
of repair and maintenance work required to bring the country’s building stock to a
over the condition of the nation’s building stock has served to expose more clearly the
extent of the problem. Whilst effective maintenance policies are not by any means the
informed way and the fundamental relationship of the condition of a building’s fabric to
its total performance is examined more critically (Barrie & Peter, 2007).
organizing, monitoring and evaluating maintenance activities and their costs (Technical
with knowledgeable and capable maintenance staff can prevent health and safety
problems and environmental damage; yield longer assets life with fewer breakdowns
and result in lower operating costs and higher quality of life for the occupants and users
system. However, once it is in place, most of the data and calculations remain the same
from year to year. The appropriate work orders and schedule must be revised and the
labour, equipment, material and contract costs updated for the following year. There are
maintenance supervisor or manager must also monitor the work progress daily, weekly or
monthly depending on the nature of the situation and the potential impact of a service
breakdown to the users. The maintenance manager must not wait until the year end to
review the budget, as it would be too late to take any corrective action if it were
necessary. The supervisor should determine the cause of the variance and, where
possible, develop alternative solutions or actions to reduce time and costs. Taking these
steps will help improve the efficiency and effectiveness of the maintenance programme
(TID, 2000).
standardization of activities – acceptable standard to which the building and its services are
to be maintained.
4. The life (functional) requirements of the buildings and their fittings and services.
According to Barrie and Peter (2007), maintenance departments are individuals liable for
in-house or, as is now much likely, may include independent bodies, such as consultants
relationships with these bodies and the rest of the business organization must therefore be
carefully taken into account. In a small firm, the functions may be undertaken by a member
of staff in addition to his other duties, while in a larger firm there would be a separate group
Organization and staffing are among the most crucial issues affecting maintenance works in
departments are structured based on work backlog. A maintenance backlog is the amount
measured in hours (Wireman, 2005). When calculating the backlog, it is expedient to know
the hours of maintenance work required and the current work force capacity. The formula
Backlog = identified work (in hours) ÷ manpower capacity per week (in hours)
Backlog stems from the amount of emergency or corrective work that occurs on a
weekly basis. In some institutions, emergency and corrective work makes up as much as
50% of the maintenance department’s work distribution each week (Wireman, 2005).
The technicians may also have routine assignments, meetings, absenteeism, vacations,
and training that may contribute to the duration of time in executing a maintenance
backlog. The maintenance department is staffed based on identified, not actual work. The
volume of maintenance backlog to be carried out may not be executed within the
specified duration if adequate resources are not available, in terms of man-power, funds
and materials. The maintenance department would fall back to a corrective approach
because current staff can never accomplish the required work in a proactive manner. It is
regular practice for many companies to remove small jobs from the maintenance backlog
or postponed to another time. Work should be identified and executed before it becomes
2.5 OUTSOURCING
supplier to perform a function that has previously been carried out in-house. This is often
peripheral functions in order to reduce costs in performing and managing what are
efficiency through the use of specialist providers. Each organization may develop its own
material and other items (such as contracts) required to do all work identified in the
Work Schedule (TID, 2000). A maintenance budget should identify the quantum of
funding a department requires to adequately address the key maintenance needs of its
buildings, to ensure that they continue to support the delivery of required services, to an
organization’s policy, asset management plan, the asset in question, current condition and
supervisor is responsible for monitoring the actual expenditures against the budget for the
year. He or she is also responsible for its yearly update using forecast labour rates, and
material and service contract costs. The updated budget would be used for determining the
operation and maintenance costs of the building’s physical assets. Maintenance personnel
maintenance objectives are not properly understood at top management level; therefore
maintenance objectives has connections with core organizational objectives, and must be
understood by the top management, strategic and operational level of management in order
to improve the allocation of resources for maintenance needs. The personality of the
maintenance manager and his dexterity come into play in giving maintenance budget its
place through proper awareness to management of the importance of maintenance and its
relationship with the organization’s objectives; provided that the budget has bearing on the
overall success of the organization.
SYSTEM (CMMS)
activities (Lee & Scott, 2009). CMMS promotes the management of building assets from
conception through completion by tracking work request, scheduling work orders and
reporting preventive maintenance tasks in great detail. It is used for improving building
maintenance operation processes in terms of cost savings in labour and material, storing of
problems before a failure occurs resulting in fewer failures and users complaints, achieve a
higher level of planned maintenance activities that enables a more efficient use of staff
resources, affecting inventory control enabling better spare parts forecasting to eliminate
CHAPTER THREE
METHODOLOGY
3.1 RESTATEMENT OF PROBLEM
Table 3.1
Population distribution of groups to be used for data generation.
Name of group Population of
groups
1 Emzor pharmaceuticals 80
2 Doyin pharmaceuticals 96
3 Consolidated foods limited 120
4 Chi Limited 85
5 Nichemtex 119
6 Ok foods Limited 100
Total population of study 600
Source: Author’s Field Survey 2006
Table 3.2
Constitution format for the sample size
Contribution
Population % Age
Names of Group to sample
size Contribution
size
1 Emzor 80 40% 32
2 Doyin pharmaceutical 96 40% 38.4
3 Consolidated food 120 40% 48
limited
4 Chi Limited 85 40% 34
5 Nichemtex 119 40% 47.6
6 OK foods Limited 100 40% 40
TOTAL 600
Source: Author’s Field Survey 2006
CHAPTER FOUR
4.0 PRESENTATION AND ANALYSIS OF DATA
Data were statistically analysed and presented in this
chapter based on the research questions and hypothesis that
guided the study.
Interpretation:
Table 4.1 shows that 28 questionnaires were distributed to
the staff of Emzor Pharmaceutical representing 11.67% of 240
questionnaires distributed while 23 questionnaires representing
9.5% were correctly filled and returned. Twenty seven (27)
questionnaires representing 11.25% of the 240 questionnaires
were distributed to the staff of Doyin Pharmaceutical while 22 of
them representing 9.2% were correctly filled and returned. Fifty
(50) questionnaires representing 20.83% of the 240 questionnaires
were distributed to Consolidated Food Ltd, 46 questionnaires
representing 19.2% of the entire questionnaires distributed were
correctly filled and returned. Thirty nine (39) questionnaires
representing 16.25% of the total questionnaires were distributed to
Chi Ltd, out of this number 32 questionnaires representing 13.3%
were correctly filled and returned. Sixty one(61) questionnaires
representing 25.42% of the entire questionnaires distributed were
distributed to NiChemtex Ltd and 50 representing 20.8% were
returned. Thirty five (35) questionnaires representing 14.8% of the
total questionnaires were distributed to OK Foods Ltd, out of this
number, 27 representing 11.3% were returned. The correctly filled
and distributed questionnaires totaling 200 represent 83.3% of the
total number of questionnaires distributed. The rate of return is
statistically high and justifies its use in the data analysis. Each
group or company contributed 40% of its population in the sample
constituted, thus guaranteeing uniformity of opinions in the data
collected and analysed.
4
5
Interpretation:
Table 4.2 shows that 13 respondents representing 6.5% are
of the opinion that their facilities compliment its functions. Twenty
(20) respondents believe that their facilities compliments its
functions to a large extent representing 10% of the respondents.
Fifty three (53) respondents representing 26.5% of respondents
said their facilities compliment its functions at a low extent. As
4
6
Interpretation:
Table 4.3 shows that 177 respondents representing 88.5%
affirmed that their facilities are being managed while 23
respondents representing 11.5% asserted that their facilities were
not being managed.
Interpretation:
Table 4.3.1 shows that 17 respondents representing 8.5
opined that their facilities are effectively managed to a good extent.
39 respondents representing 19.5% are of the opinion that their
facilities are effectively managed to a fair extent. 83 respondents
representing 41.5% says facilities management in their
organizations is poor. The last group consisting of 61 respondents
representing 30.5% responded that facilities management is very
poor in their organizations.
Effective facilities management is indicated in the
management provisions which are sufficiently adequate in areas of
finance, modern automation and skilled personnel (staff).
Funding of maintenance is dependent on how efficient
management is and their over-all maintenance policy, due to poor
or lack of good maintenance culture in Nigeria, organizations
became reactive instead of proactive. The absence of modern
automation in the production stages is a direct consequence of low
output.
Skilled staff is important in facilities management as they
determine the quality and effectiveness of management. There is
an acute storage of skilled staff (professionals) for the facilities and
the few available are over-stretched, over-worked, under-paid or
engaging themselves in the fight for the right discipline/
professional for facilities management.
Ideally, the management approach to maintenance should be
planned-preventive maintenance method but due to logistics
problems like funds and availability of spare parts, this is usually
not feasible and management reverts to ad-hoc maintenance.
49
4.4 Are Resources Allocated for Facilities Management
Adequate?
Table 4.4 Adequacy of Resources Allocated for Facilities
Management
Response options Frequencies Percentage
Adequate 13 6.5%
Inadequate 187 93.5%
Total 200 100%
Source: Author’s Field Survey 2006
Interpretation:
Table 4.2.4 shows that 13 respondents representing 6.5%
are of the opinion that resources allocated for facilities
management are adequate while 187 respondents representing
93.5% opined that resources allocated for facilities management
are inadequate.
It is established that the main responsibilities of the facilities
management team should include planning, developing and
delivering services conforming to international standards of safety,
health and environmental issues. Due to lack of adequate funding,
machineries and resources for routine and miscellaneous duties
are often over-looked and the quality level of products and
services provided suffers.
.
4.4.1 Statement of Hypothesis 1
H0: Resources allocated for facilities management are not
adequate.
H1: Resources allocated for facilities management are adequate.
50
Table 4.4.1
Observed Frequency Table for Hypothesis 1
Response Emzor Doyin Consolidate Nichemte
options pharm. pharm. d Foods. Ltd x Ltd
Adequate 2 2 2 3
Inadequate 21 20 44 47
Total 23 22 46 50
Response OK Foods Chi Totals
options Limited Limited
Adequate 2 2 187
Inadequate 25 30 13
Total 27 32 200
Source: Author’s Fieldwork, 2006.
21 21.5 2
20 20.6 44 43 30 29.9
2 2 2
21.520.64329.9
47 46.8 2
25 25.2 2 1.5 2 1.43
2 2 2
46.825.21.51.43
0.01 0.02 0.02 0.00 0.00 0.00 0.17 0.23 0.33 0.00 0.02 0.03 0.83
Interpretation:
Table 4.5 shows responses on facilities users requirement
satistaction. Fifteen (15) respondents representing 7.5% are of the
opinion that their requirements as user of the facilities are satisfied
while as many as 185 respondents asserted that facilities users
requirements are not satisfied.
Facilities users here include production staff/machineries
operators, distributors and consumers. Most of their requests are
not met. Most times bureaucracy stands on the way of facilities
users requirement satisfaction efforts.
53
Table 4.5.1 Extent of Facilities Users Requirements
Satisfaction
Response options Frequencies Percentage
Very large extent 6 3%
Large extent 9 4.5%
Very low extent 103 51.5%
Low extent 82 41%
Total 200 100%
Source: Author’s field survey,2006
Interpretation:
Table 4.5.1 shows the extent of facilities users requirement
satisfaction. Six (6) respondents representing 3% affirmed that
facilities users requirements are satisfied to a very large extent
while 9 respondents representing 4.5% are of the view that
facilities users requirements are satisfied to a large extent on the
other hand, as many as 103 respondents representing 5.5% are of
the opinion that facilities users requirements are satisfied to a very
low extent while 82 respondents representing 41% asserted that
facilities users requirements are satisfied to a low extent.
Collectively 185 respondents representing 92.5% responded
negatively to facilities users requirements satisfaction. This was a
peculiar problem in all manufacturing industries sampled. This has
a direct effect on attitude to work and level of production.
54
Interpretation:
Table 4.2.6 reveals that 7 respondents representing 3.5%
affirmed that their facilities are fully modern automated. As many
as 168 respondents representing 84% are of the opinion that their
facilities are not fully modern automated while 25 respondents
representing 12.5% asserted that their facilities are not modern
automated.
The use of computer and sound modern technology in all
production stages is very low. This will invariably affect the level of
production negatively. Some one on one interviews conducted
reveals that some of these manufacturing industries sometimes
import sophisticated machines to aid production but lack
competent professionals to operate them, in no time the machines
pack up and are abandoned. Some others say they can not afford
the fees required by professionals to run these machines and
service them at appropriate times.
5
5
Interpretation:
It was observed that 72.5% of the respondents have their
facilities functional. The remaining 27.5% have some of their
facilities under repairs, obsolete or due for replacement.
There is need for all the facilities to be in good condition and
functional at each point in time to keep production steady. It should
not be a situation where production can not be predicted due to
inconsistencies in the functioning of the facilities. The
manufacturers instructions regarding the useful life and
maintenance pattern of facilities should be strictly adhered to. This
will alert the users at what point in time the facilities need to be
serviced and also at what age arrangements should be made for
the replacement of a facility before it starts breaking down regularly
and finally packs up. Improved production level is directly
dependent on the efficiency of facilities used in the production
process.
5
6
Interpretation:
Table 4.8 shows the method of facilities management
adopted by different organizations. 133 respondents representing
66.5% asserted that their organizations make use of their in-house
maintenance crew to manage their facilities. 18 respondents
representing 9% says some of their facilities are managed by out-
sourced professionals while 49 respondents representing 24.5%
says their facilities are managed by both in-house maintenance
crew and out-sourced professionals depending on the facility and
the magnitude of repairs needed.
Oral interviews revealed that most organizations make use of
in-house maintenance handled by technicians because it is
cheaper and keeps maintenance cost at its minimum. They make
use of out-sourced professionals when their in-house maintenance
crew are not capable of handling certain complex maintenance
works that needs experienced professionals. Because this is
usually very expensive, it is only used for highly specialized
facilities.
5
7
Interpretation:
Table 4.9 reveals different reasons that determines the
method of facilities management adopted by each organization. 28
respondents representing 14% are of the opinion that the size of
facility and sophistication of service it provides determines the
method to be adopted. 113 respondents representing 56.5%
asserted that the method adopted is the one which minimized cost
greatly and this is that of the in-house maintenance. 23
respondents representing 11.5% declared that the method adopted
depends on the uniqueness of the service the facility provides. 20
respondents representing 10.5% confirmed that the method
adopted is that which will minimize risk to facility users or
operators. While the remaining 16 respondents representing 8%
says the method adopted is dependent on owner’s requirements.
58
Interpretation:
The above stated facilities management problems were
confirmed by management personnel interviewed. They were seen
as constrains to efficient facilities management.
100
90
80
70
60 52%
50
40
30
20
5%
10
Poor Funding/Maintenance
0
Bureaucracy
14%
6% 9% 7.5% 5%
1.5%
EnvironmentalEffec
Safety/Health
Unavailable
Automation
Difficulty in
Materials
Inflation
ts
ofSkilled/RightProfessionals
Procurement
60
x2 Oij Eij 2
Eij
61
Decision Rule:
Reject H0 if the x² calculated is > x² table value otherwise accept
H0.
Decision:
Since x² calculated value of 157.08 is > x² table value of 7.82, we
reject the Null hypothesis and accept the alternative hypothesis.
Conclusion:
We therefore conclude that facilities management problems
constrain efficient productivity in an organization.
6
2
CHAPTER FIVE
SUMMARY OF FINDINGS, CONCLUSION AND
RECOMMENDATIONS
5.1 SUMMARY OF FINDINGS
Having presented and analyzed the data extracted from the
questionnaires, interviews and personal observations, some
principal findings, conclusion and recommendations could be
made.
The facilities compliment their functions at a very low extent.
The facilities used for production are either sub – standard or
performing under capacity thereby reducing the quantity and
quality of products, which is one of the reasons consumers, opt for
foreign commodities. The basic facilities provided are either out of
use or performing poorly, these include the air – conditioners,
telephones, generators/plants etc.
Though there is an above average affirmation of facilities
management in the selected manufacturing industries, but a further
probe into the effectiveness of management showed a very high
degree of poor facilities management. Further enquires made
during the oral interviews revealed that effective facilities
management depends on the overall maintenance policy of each
manufacturing industry. Besides, there is poor or lack of good
maintenance culture in Nigeria, organizations are reactive instead
of proactive .
Some other interviewees mentioned inadequate finance, Lack of
modern automation and skilled personnel as reasons for poor
facilities management.
Data analysis confirmed that resources allocated for facilities
management are inadequate. This data was used to test
6
3
5.2 CONCLUSION
5.3 RECOMMENDATIONS
2. SKILLED PERSONNEL
The staff strength of the maintenance crew and engineering
departments should be strengthened to enable them cope with the
work of keeping the facilities in good shape.
This should be backed up with engaging services of special
facilities management consultants when the need arises to handle
special or complex facilities. Management should invest in staff
training and sponsoring programs, which will contribute to
competence in executing tasks. All the maintenance staff must be
proficient and professionals in their different fields.
3. MATERIAL PROCUREMENT
The procurement of materials for facilities maintenance might
entail importation of components from abroad. The facilities and
equipments might also be so out-modeled and obsolete that it
would be impossible to get spare parts of the components. In
designing facilities all these should be taken into consideration.
6
6
4. LEVEL OF AUTOMATION
Investment should be made in computers and software
packages that are relevant to space and data management. This
will enhance management performance and introduce modern
technology in tackling facilities management problems. Automation
aids the evaluation of performance and monitoring of control
operations. It will hasten response to facilities problems and save
labour - hours thereby reducing operation costs.
7. BUREAUCRACY
The management of facilities and quality of services
rendered is usually a reflection of the policy source, ie board of
directors. For a well balanced facilities management, top quality
management objectives should be put in place comprising of
seasoned professionals who have a stake in the operation of the
facilities and public representatives to represent the interest of
users at board level.
There should be autonomy in taking maintenance decisions so that
delays in action are eliminated and savings in down – time of
broken down components are achieved.
8. INFLATION
Inflation has an effect on the cost of materials and
components of facilities. This can be reduced by stocking materials
that are recuringly maintained or replaced in advance. This way
the organization can benefit from bulk – purchase instead of
buying on a need – arisen basis. Inflation can also be reduced by
making allowance for it in the budgetary provisions. Components
pricing is not stationary, so efforts should be directed towards
updating the prices from time to time.
6
8
9. BENCHMARKING
Benchmarking should be employed to help identify trends
and the changes you need to make to be more competitive or to
more effectively support the mission of the overall organization.
Benchmarking will help to identify the gaps between your current
practices (where you are now) and best practices(where you want
to be).Benchmarks may be established for operating cost and
environmental performance standards, or they may document the
practices and costs of your toughest competitors or industry
standards, and those of leaders in any industry performing similar
functions. Benchmarking facilities performance involves looking at
the best companies and finding out what they are doing better than
you are. Facilities managers should use benchmarking to measure
their performance and obtain data for targeting opportunities for
improvement.
REFERENCES
Adedeji, O.(2006) M2 Marketing and Management Journal, Vol. 2
Issue 11, July 30.
Akiolu, F.O (2005) Facilities management in the banking industry.
(A case study of selected Banks in Victoria
Island, Lagos) Unpublished M.Sc Thesis,
university of Lagos.
Alan, P. (1998) Facilities Management: An Explanation. Macmillan
Press Ltd., London.
Alexander, K. (1996) “Facilities management: Theory and practice
management”, VOL. 2, No. 1: The Emergence of
facilities management in the U.K
Ayoola, F. (2006) M2 Marketing and Management journal, vol. 2
Issue 11, July 30.
Barrett, P.S. (1995) Facilities Management : Towards Best
Practice. Blackwell Science, Oxford, London.
Brian, A.,Adrian B. (2000) Total Facilities Management. Blackwell
Science Ltd., London.
Brauer, L. (1986) Facilities Planning American Management
Association New York, USA.
Camp, R.C. (1989) Benchmarking--- The Search For Industry Best
Practice that Leads to Superior Performance.
Quality Press, Milwaukee.
Covey, S. R. (1989) The 7 Habits of Highly Effective People.
Simon & Schuster, New York.
Dell’lsola, A. (1997) Value Engineering: Practical Applications.
Means Co., Inc, Kingston.
7
1
www.ciob.org.uk
7
4
APPENDIX
Department Of Estate Management
University of Nigeria, Enugu Campus.
Dear Sir/Madam
RESEARCH QUESTIONNAIRES
The undersigned is a postgraduate student in the above
named institution, carrying out a research on the problems of
facilities management in corporate organizations (A case study of
some selected manufacturing industries within Lagos state).
This questionnaire is therefore prepared towards the
research in partial fulfillment for the award of Master of Science
(M.Sc.) in Estate management.
. I hereby assure you that all information supplied in this
questionnaire will be treated confidentially.
Yours sincerely;
Oladejo, Esther I. (MRS)
75
SECTION 1
1. Name (optional)
2. How old are you ?
(a) under 30 years (b) 31-40years
(c) 41-50 years (d) above 50 years.
3. What is your qualification ?
(a) FSLC (b) WASC/GCE
(c) Diploma (d) Degree
4. In which organization do you work?
(a) Emzor pharmaceutical (b) Doyin Pharmaceutical
(c) Consolidated Food Ltd (d) Chi Limited
(e) Nichemtex (f) Ok foods Limited.
5. What do you produce?
(a) Food and Beverage (b) Textile
(c) Pharmaceuticals
6. What are the types of facilities owned by your organization?
(a) Real Estate (b) Machinery & Equipment
SECTION II
8. Are your facilities being managed?
(a) Yes (b) No
9. Do you have a department or unit in your organization
responsible for the management of your facilities?
(a) Yes (b) No
7
6
24. What are your suggestions on how these problems can be solved?
-------------------------------------------------------------
6. REFERENCES
Adejimi, A. (2005). Poor building maintenance in Nigeria; Are architects free from blame? Presented paper, ENHR
International conference, Iceland. Retrieved December 15, 2012, from http://www.goggle.arayela.
Adewunmi, Y., Famuyiwa, F., & Harrison, E. (2009). Post occupancy evaluation of hostel facilities in Nigerian
private universities: A case study. In A. Dainty (Ed.), Proceedings of 25th Annual ARCOM Conference, 7-9
September 2009 (505 – 514), Nottingham, UK: Association of Researchers in Construction Management.
Adewunmi, Y., Omirin, M., Famuyiwa, F., & Farinloye, O. (2011). Post-occupancy evaluation of post graduate
hostel facilities. Facilities, 29(3), 149 – 168.
Akinsola, O.E., Hussaini, P.O., Oyenuga, S.O., & Fatokun, A.O. (2012). Critical factors influencing facility
maintenance management of tertiary institutional buildings in South West Nigeria.
Mediterranean Journal of Social Sciences, 3(11), 489 – 496.
Barrie, C., & Peter, S. (2007). Building maintenance management (2nd ed.). Oxford, United Kingdom:
Blackwell Publishing.
Buys, F., & Nkado, R. (2006). A survey of approaches to maintenance management in tertiary institutions in
South Africa. Construction Management and Economics, 24, 997 – 1005.
Buys, F., Cumberledge, R., & Crawford, G. (2009). Comparative analysis of the performance of tertiary
institutions in managing its assets. RICS COBRA Research Conference (pp. 658-671). University of
Cape Town, 10-11th September 2009.
Cobbinah, P.J. (2010). Maintenance of buildings of public institutions in Ghana. Case study of selected
institutions in the Ashanti region of Ghana (Unpublished Msc Thesis). Department of Planning,
Kwame Nkrumah University of Science and Technology, Kumasi, Ghana.
Cohen, L., Manion, L., & Morrison, K. (2005). Research methods in education (5th ed.). London: Taylor &
Francis e-library.
David, M., & Sutton, C.D. (2004). Social research: The basics (1st ed.). California: Sage Publications Inc.
Haigh, R. (2008). Interviews: A negotiated partnership. In A. Knight. & L. Ruddock, Advanced research
methods in the built environment. UK: Wiley-Blackwell Publishing Limited.
Hesse-Biber, S.N., & Leavy, P. (2011). The practice of qualitative research (2nd ed.). US: Sage.
Khalil, N., & Husin, H.N. (2011).Sustainable building rating tool towards learning improvement in Malaysia’s
higher institution: A proposal. International Conference on Social Science and Humanity, 5. IACSIT
Press, Singapore.
Lateef, O A, Khamidi, M. F., & Idrus, A. (2010). Building maintenance management in a Malaysian university
campuses: A case study. Australasian Journal of Construction Economics and Building, 10(1/2), 76‐
89.
Lee, H.H., & Scott, D. (2009). Overview of maintenance strategy, acceptable maintenance standard and
resources from a building maintenance operation perspective.