Method Statement FOR Swimming Pool & Lazy River Works: Reference No: GESB/PLOTH/SITE/C&S/MS/012/00 Date: 18/5/2021

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 10

Ref.

No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 1 of 10

METHOD STATEMENT
FOR
SWIMMING POOL & LAZY RIVER
WORKS

Reference No : GESB/PLOTH/SITE/C&S/MS/012/00

Date : 18/5/2021

Action Name Designation Signature

Approved by GOH CHOO LENG Senior Project Manager

Reviewed by RAYMOND TAN Assistant Manager

MOHAMAD NAZRI BIN


Reviewed by SHE Manager
ABDUL MUIN

SYERIFAIZAL BIN
Reviewed by QAQC Manager
MUSTAPHA

TAHIRRUDDIN BIN
Prepared by SHE OFFICER
OMAR

Prepared by CHIN HAO QIAN QAQC Engineer

1|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 2 of 10

CONTENTS

1.0 SCOPE OF WORKS 3


1.1 General Description 3
1.2 Reference 3
1.3 Materials 3
1.4 Plant and Equipment 3
1.5 Manpower 3
1.6 Construction Procedures 4

2.0 SAFETY AND HEALTH REQUIREMENT


2.1 Job Safety & Health Analysis 5
2.2 Information to Personnel 5
2.3 Emergency Arrangements 6
2.4 Permit Requirements 7

3.0 ENVIRONMENTAL ISSUES


3.1 Environmental Aspects, Impacts & Control Measures 7

4.0 QUALITY ASSURANCE & QUALITY CONTROL


4.1 Contractual Requirement 8
4.2 Inspection and Testing 8
4.3 Follow up and Evaluation 8

5.0 APPENDICES 8

2|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 3 of 10

1.0 SCOPE OF WORK

1.1 General Description


This Method Statement (MS) describes the method of swimming pool and lazy river
construction at Plot H Serviced Residence.

1.2 Reference
i) Technical data sheet
ii) Construction Drawings
iii) Qualified Engineer and Supervisor
iv) In-process Inspection and Testing
v) Inspection and Test Plan
vi) Project Specification
vii) Inspection Checklist
viii) Request for Inspection Forms
ix) Project Filing Index

1.3 Materials
No Material Brand

1.2.1 Lampang Tiles GNG - refer Appendix A for Details


1.2.2 Tiles Adhesive Bed Mapei - refer Appendix A for Details
1.2.3 Tiles Grout Mapei - refer Appendix A for Details
1.2.4 Penetron Sealcoat Elastic flexible
Waterproof
cementitious

1.4 Plant and Equipment/Tools


Ite Description Usage Purposes
m
1. Electric Mixer For material mixing
2. For cleaning and application of
Brush/Broom/Roller
waterproof
3. Tile cutting tool For tile cutting
4. Square Ruler For checking squareness
5. Measuring tape For measuring
6. Trowel For adhesive application
Please check font size

1.5 Manpower
Ite Designation Responsibilities

3|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 4 of 10

1. Site Engineer To monitor site progress as per schedule. To plan


for daily works

2. Site Supervisor Supervise site works complying to SHE and


Quality requirements and coordinate work
inspection with COW

3. Surveyor To carry out survey works

4. Tiler To carry out physical works

5. Waterproof applicator To carry out physical works

5. Site Safety Supervisor To ensure site work are adhere to SHE plan and
requirement

6. QAQC Engineer To ensure the works commenced are adhering to


quality standards

1.6 Construction Procedures


1.6.1 Surface Preparation
1.6.1.1 The concrete floor, wall and stepping concrete surface shall be wash and
clean using a water jet / water sprayer pump nozzle to remove any foreign /
loose / unwanted residue or laitance. Hacking using spade chisel can be
arrange to remove stubborn cement / concrete laitance (if any).
1.6.1.2 Rectify all concrete honeycomb, crack lines, shrinkage cracks, etc. using
non-shrink grout (if any).
1.6.1.3 Carry out surface preparation joint-inspection with client’s representative
and waterproofing specialist and make arrangement for rectification on
imperfection (if any) prior to applying swimming pool waterproofing material.

1.6.2 Waterproofing
1.6.2.1 Before the waterproofing work start, protect the working area from rain and
direct sunshine. Erect tentage and maintain temporary drainage system. Allow
installation to cure properly in dry environment. (what is tentage?)Is it
Khemah?if its really a tent, do site really want to erect it?Please discuss
among the project teams.
1.6.2.2 Waterproofing to be used is Penetron Sealcoat Elastic flexible cementitious
waterproofing slurry for 2 coats at approximately 1.0kg/coat/m2
1.6.2.3 Apply 25mm x 25mm angle fillet at the straight edges (all corner between wall
& floor) before receiving waterproofing compound.
1.6.2.4 Refer Appendix A for water proofing product description.

4|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 5 of 10

1.6.2.5 Waterproofing compound to be applied on concrete surface, the concrete


must be cured at least 28 days.
1.6.2.6 Fins, sharp projections and exposed edges on surfaces shall be repaired
before application of waterproofing compound.
1.6.2.7 Oil, grease, dust, loose particles, form oil, curing compound and other surface
contaminants shall be removed by sanding or grindings.
1.6.2.8 All voids, cracks and honeycombs shall be repaired before applications of
waterproofing compound.
1.6.2.9 The surface shall have no puddle of water before application.
1.6.2.10 Damp the substrate surface with clean water until saturated but no water
ponding and then apply the 1st coat using, brush, roller or broom.
1.6.2.11 Apply the 2nd coat evenly after a minimum of 8 hours after application of 1 st
coat.
1.6.2.12 Allow to cure for period of time as per relevant product manufacturer’s
recommendation.
1.6.2.13 If present of pin holes/bug holes after apply waterproofing, rectification work
should be done before proceed for next step.
1.6.2.14 Post-waterproofing water ponding test shall be carried out for minimum of 3
days and to check for any leakage through the slab to slab joint. Rectify any
leakages before proceed with next stage of work.
1.6.2.15 Screeding and rendering shall proceed as soon as possible to protect the
waterproofing from being damaged.

1.6.3 Screeding and Rendering


1.6.3.1 Level the concrete floor substrate the screed mortar comprising of Ordinary
Portland Cement + Sand (1:3) mixed with Mapei’s Planicrete SP (diluted 1:3
with clean water). For improvement adhesion of screed binder to the floor
substrate, apply layer of fresh slurry bond with Portland cement mixed with
Mapei’s Planicrete SP just before laying the screed mortar. Allow screed
mortar to cure for 3 days per 10mm thickness before proceed the tile
installation.
1.6.3.2 Screeding to pool base
a. Apply a slurry coat in the following mix ratio onto the receiving substrate:
Please describe what methods site team want to measure the mix ratio. By timber yellow pale?
paint pale?
Mix ratio PLANICRETE SP OPC
Proportion by wt 1 1 to 1.5

b. After application of the slurry, proceed with screed immediately when the
slurry coat is still fresh.
Note : Screeding on a slurry coat that has already dried may result in
debonding
c. Apply a screed in the following mix ratio, and finish it with a wooden float to the
correct fall and direction.

5|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 6 of 10

Mix Ratio PLANICRETE SP Water Portland Cement Sand


Proportion by wt 1 3 8 24

d. Reduce amount of water dilution if the sand is wet.


e. Insert non-oxidising wire-mesh reinforcement when the screed is thicker than
50mm. wire-mesh to be put 2/3 from bottom screed.

1.6.3.3 Rendering to pool wall


a. Apply a splash coat in the following mix ratio onto the receiving concrete
substrate.
Mix Ratio PLANICRETE SP Portland Cement Sand
Proportion by wt 1 1 1

b. Allow the splash coat to dry for at least 24 hours before applying a render in
the following mix ratio:
Mix Ratio PLANICRETE SP Water Portland Cement Sand
Proportion by wt 1 3 8 24

c. Reduce amount of water dilution is the sand is wet.


d. Finish the render with a wooden float and allow it to cure for at least 7 days.

1.6.4 Tiling Work


1.6.4.1 To carry out hollowness check of the back screed/rendering prior to any
installation of tiles.
1.6.4.2 Material to be used KERABOND T GREY + ISOLASTIC 50.
1.6.4.3 Refer Product Data Sheet (attached) for product description and application.
1.6.4.4 Dampen the surface of screed/render by using hand splashing of water.
1.6.4.5 Mix Kerabond T Grey + ISOLASTIC 50 in the following ratio with a low-speed
mechanical mixer until a uniform paste are obtained without lumps. Leave the
paste to slake for few minutes and remix before use.

Mix Ratio KERABOND T GREY ISOLATIC 50


Proportion by weight 25kg 8kg

1.6.4.6 A lean coat of Kerabond T will be apply using smooth side of the trowel on
the floor screed and rendered wall and immediately after apply thickness of
Kerabond T using toothed side of the trowel onto lean coat to form groove
lines.
1.6.4.7 Apply and back scratch the tile base in single direction and lay the tile with
parallel groove direction.
1.6.4.8 Before Before laying the tile, ensure that skinning has not formed on the
surface of the adhesive. Should a skin have formed, the adhesive must be re-
notched. Then lay the tile onto the adhesive with a firm pressure.

6|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 7 of 10

1.6.4.9 Tap and adjust the tiles to level. Clean the edges of the tile with excessive
cement to ensure neat jointing.
1.6.4.10 Protect the finished surface and let the adhesive set for at least 48 hours
before from disturb by footprint/step or rain splashing.
Please standardize the spacing, font, size etc.
1.6.5 Tiles Grouting
1.6.4.1 Material to be used Ultracolor Plus (Joint Grout)
1.6.4.2 The joint must be clean and free from debris.
1.6.4.3 Prepare the joint be before grouting wait until the installation adhesive has
completely hardened. The joint must be clean, free of dust and raked back to
at least 2/3 of the tiles thickness.
1.6.4.4 While stirring, pour Ultracolor Plus into container containing 20-26% by weight
of water. Mix the grout using mechanical mixer until a smooth paste is
obtained.
1.6.4.5 Let the mix stand for 2-3 minutes and stir again briefly before use. Use the mix
within 20-25 minutes of its preparation.
1.6.4.6 Applying the grout with fill the joints completely with Ultracolor Plus using the
appropriate rubber/grout float, making sure the joint are completely
compacted with no unevenness. Remove excess of grouting by moving the
float diagonally to the joints while still fresh.
1.6.4.7 Rinse and wash the sponge regularly to ensure uniform colour of the tile
grout.
1.6.4.8 Floor are set to light foot traffic after 24 hours. Swimming pool can be filled 7
days after grouting.

2.0 SAFETY AND HEALTH REQUIREMENT

2.1 Job Safety & Health Analysis (JSA)


Job Safety & Health Analysis shall be carried on the project site. Cautions and
hazards signs shall be established at location of works. The hazards in a particular
activity and the control measures implemented shall be briefed to the workers during
SHE induction, tool box talk and JSA Briefing. Please refer to the attached
Appendix B.

2.2 Information to Personnel


2.2.1 All workers employed in the project site must have CIDB green card.
2.2.2 All new workers and staff to attend the SHE Training or SHE Induction Course
before commencing works at site and attendances shall be recorded in an
induction checklist.
2.2.3 All site personnel are mandatory wear proper Personnel Protective

7|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 8 of 10

Equipment (PPE):
2.2.4 Safety helmets, Safety vest, Safety boots, Hand gloves and any other
additional PPE required in JSA or advised by SHE Department.
2.2.5 Monthly SHE Committee meeting shall be held with all the contractors related
to the works.
2.2.6 All workers are compulsory to attend the daily pre task briefing and weekly
toolbox meeting conducted by the SHE Department/Representative and
attendance shall be recorded.
2.2.7 All site personnel are highly required to comply to Site COVID-19 Pandemic
arrangements:
 SHE Instruction – COVID-19 Preventive Measures
 Emergency Response Plan – COVID-19 Virus Transmission (FC17).

2.3 Emergency Arrangements


2.3.1 Project Emergency Response Plan and Procedure shall be established.
2.3.2 The potential hazards during the Tiling Work are below:
i. Accident due to machinery/equipment failure and movement
ii. Fall from height, contact with sharp edges/protruding rebar and
etc.
2.3.3 An Emergency Response Team shall be formed at the site.
2.3.4 Please refer to the Appendix B for Safety, Health & Environmental
Emergency Response Flow Chart.
2.3.5 The organization chart, list of emergency contact person and relevant
authorities with their contact numbers shall be showed in the Notice Board.

2.3.6 In the event of emergency, the site management staffs must evaluate the
situation and commence the necessary procedures as follow:
 Raise the alarm
 Stop works
 Remain composed.
 Make sure notifications of emergency or evacuation are in place for all
workers surrounding the vicinity.
 Make sure all workers are assembled at designated assembly point.
 Make sure first aid kits are prepared at assembly point.
 All workers are told not to leave the assembly point until clear sign is
issued.
 Headcount shall be conducted

8|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 9 of 10

 First aiders shall attend to the injured workers


 Prepare assessment reports for the losses

2.4 Permit Requirement

No Description Person or Authorities in- Remarks


charge
1 SHE permit to work such as SHE Department
Crane and Lifting Operation
permit, Excavation permit, Night
work permit, Hot work permit
and etc.
2 MPS’s Work Permit MPS
3 Outside normal working hours MPS
work’s permit

3.0 ENVIRONMENTAL ISSUES


3.1 Environmental Aspects, Impacts & Control Measures
The significant environmental impacts associated with the tiling work have been
identified and listed in Appendix C.

3.1.1 Air Quality and Noise Level


Machineries shall be in well maintain and in good working condition to reduce
emission of soot, smoke and noise.
The following measures shall be implemented if the above mentioned (soot,
smoke and noise) is deteriorating:

 Increase maintenance frequency.


 Replace to better equipment if necessary.
 Switched-off equipment if not in used
 Supply workers on-site with proper PPE (i.e. ear plugs and mask).

3.1.2 Waste Management


All wastes shall be removed from site regularly.
Scheduled waste from maintenance works of machineries, vehicles and tools
will be placed in designated areas. Proper oil tray or drum shall be placed to
prevent the oil spillage all over the place. Subsequent waste shall be collected
and transfer to area as assigned.

9|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 10 of 10

3.1.3 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:

 Maintain the access way to all working area.


 Proper material arrangement.
 Park the machineries in orderly manner.
 No littering around the site.

4.0 QUALITY ASSURANCE AND QUALITY CONTROL

4.1 Contractual Requirement


4.1.1 Qualified supervising staff & worker from sub-contractor

4.2 Inspection and Testing


4.2.1 Inspection and Test Plan – to refer Appendix D

4.3 Follow Up and Evaluation


4.3.1 Inspection form and checklist.

5.0 APPENDICES
* As per attachments

10 | P a g e