Method Statement FOR Swimming Pool & Lazy River Works: Reference No: GESB/PLOTH/SITE/C&S/MS/012/00 Date: 18/5/2021
Method Statement FOR Swimming Pool & Lazy River Works: Reference No: GESB/PLOTH/SITE/C&S/MS/012/00 Date: 18/5/2021
Method Statement FOR Swimming Pool & Lazy River Works: Reference No: GESB/PLOTH/SITE/C&S/MS/012/00 Date: 18/5/2021
No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 1 of 10
METHOD STATEMENT
FOR
SWIMMING POOL & LAZY RIVER
WORKS
Reference No : GESB/PLOTH/SITE/C&S/MS/012/00
Date : 18/5/2021
SYERIFAIZAL BIN
Reviewed by QAQC Manager
MUSTAPHA
TAHIRRUDDIN BIN
Prepared by SHE OFFICER
OMAR
1|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 2 of 10
CONTENTS
5.0 APPENDICES 8
2|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 3 of 10
1.2 Reference
i) Technical data sheet
ii) Construction Drawings
iii) Qualified Engineer and Supervisor
iv) In-process Inspection and Testing
v) Inspection and Test Plan
vi) Project Specification
vii) Inspection Checklist
viii) Request for Inspection Forms
ix) Project Filing Index
1.3 Materials
No Material Brand
1.5 Manpower
Ite Designation Responsibilities
3|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 4 of 10
5. Site Safety Supervisor To ensure site work are adhere to SHE plan and
requirement
1.6.2 Waterproofing
1.6.2.1 Before the waterproofing work start, protect the working area from rain and
direct sunshine. Erect tentage and maintain temporary drainage system. Allow
installation to cure properly in dry environment. (what is tentage?)Is it
Khemah?if its really a tent, do site really want to erect it?Please discuss
among the project teams.
1.6.2.2 Waterproofing to be used is Penetron Sealcoat Elastic flexible cementitious
waterproofing slurry for 2 coats at approximately 1.0kg/coat/m2
1.6.2.3 Apply 25mm x 25mm angle fillet at the straight edges (all corner between wall
& floor) before receiving waterproofing compound.
1.6.2.4 Refer Appendix A for water proofing product description.
4|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 5 of 10
b. After application of the slurry, proceed with screed immediately when the
slurry coat is still fresh.
Note : Screeding on a slurry coat that has already dried may result in
debonding
c. Apply a screed in the following mix ratio, and finish it with a wooden float to the
correct fall and direction.
5|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 6 of 10
b. Allow the splash coat to dry for at least 24 hours before applying a render in
the following mix ratio:
Mix Ratio PLANICRETE SP Water Portland Cement Sand
Proportion by wt 1 3 8 24
1.6.4.6 A lean coat of Kerabond T will be apply using smooth side of the trowel on
the floor screed and rendered wall and immediately after apply thickness of
Kerabond T using toothed side of the trowel onto lean coat to form groove
lines.
1.6.4.7 Apply and back scratch the tile base in single direction and lay the tile with
parallel groove direction.
1.6.4.8 Before Before laying the tile, ensure that skinning has not formed on the
surface of the adhesive. Should a skin have formed, the adhesive must be re-
notched. Then lay the tile onto the adhesive with a firm pressure.
6|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 7 of 10
1.6.4.9 Tap and adjust the tiles to level. Clean the edges of the tile with excessive
cement to ensure neat jointing.
1.6.4.10 Protect the finished surface and let the adhesive set for at least 48 hours
before from disturb by footprint/step or rain splashing.
Please standardize the spacing, font, size etc.
1.6.5 Tiles Grouting
1.6.4.1 Material to be used Ultracolor Plus (Joint Grout)
1.6.4.2 The joint must be clean and free from debris.
1.6.4.3 Prepare the joint be before grouting wait until the installation adhesive has
completely hardened. The joint must be clean, free of dust and raked back to
at least 2/3 of the tiles thickness.
1.6.4.4 While stirring, pour Ultracolor Plus into container containing 20-26% by weight
of water. Mix the grout using mechanical mixer until a smooth paste is
obtained.
1.6.4.5 Let the mix stand for 2-3 minutes and stir again briefly before use. Use the mix
within 20-25 minutes of its preparation.
1.6.4.6 Applying the grout with fill the joints completely with Ultracolor Plus using the
appropriate rubber/grout float, making sure the joint are completely
compacted with no unevenness. Remove excess of grouting by moving the
float diagonally to the joints while still fresh.
1.6.4.7 Rinse and wash the sponge regularly to ensure uniform colour of the tile
grout.
1.6.4.8 Floor are set to light foot traffic after 24 hours. Swimming pool can be filled 7
days after grouting.
7|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 8 of 10
Equipment (PPE):
2.2.4 Safety helmets, Safety vest, Safety boots, Hand gloves and any other
additional PPE required in JSA or advised by SHE Department.
2.2.5 Monthly SHE Committee meeting shall be held with all the contractors related
to the works.
2.2.6 All workers are compulsory to attend the daily pre task briefing and weekly
toolbox meeting conducted by the SHE Department/Representative and
attendance shall be recorded.
2.2.7 All site personnel are highly required to comply to Site COVID-19 Pandemic
arrangements:
SHE Instruction – COVID-19 Preventive Measures
Emergency Response Plan – COVID-19 Virus Transmission (FC17).
2.3.6 In the event of emergency, the site management staffs must evaluate the
situation and commence the necessary procedures as follow:
Raise the alarm
Stop works
Remain composed.
Make sure notifications of emergency or evacuation are in place for all
workers surrounding the vicinity.
Make sure all workers are assembled at designated assembly point.
Make sure first aid kits are prepared at assembly point.
All workers are told not to leave the assembly point until clear sign is
issued.
Headcount shall be conducted
8|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 9 of 10
9|Page
Ref.No:GE/PLOTH/GE
PLOT H SERVICED RESIDENCE N/F/0001/0
Rev : 0
METHOD STATEMENT Date: 5th Apr 2019
Page: 10 of 10
3.1.3 Housekeeping
Housekeeping is an essential part of SHE for the daily routine. Housekeeping
would include the following items:
5.0 APPENDICES
* As per attachments
10 | P a g e