Concrete Block Manufacturing Report
Concrete Block Manufacturing Report
Concrete Block Manufacturing Report
PROJECT AT A GLANCE
2. Constitution : Proprietorship
2
13. Important Financial Indicators :
3
CHAPTER – 2
INTRODUCTION
2.01 Concrete bricks, pavers and hollow blocks are precast solid products. Bricks &
hollow blocks have an important place in modern building industry while precast
interlocking pavers, these days are used extensively in road construction in this part of
the country. Concrete bricks & blocks are effective & better alternative to burnt clay
bricks by virtue of their good durability, fire resistance, partial resistance to sound,
thermal insulation, small dead & high speed of construction. Concrete hollow blocks
being larger in size than normal clay building bricks less mortar is required and faster
construction is achieved. Also these types of bricks & blocks provides facility for
concealing electrical conduit, water & sewer pipes whenever so desired and requires
less plastering. Hence reduction in cost.
2.02 Bricks are one of the main stays of constructional activities and constitute about
15% of the cost of constructional materials. The gap in demand & supply of bricks is
envisaged to be considerable as there does not have any medium or large brick making
semi automatic & automatic plant in its neighbourhood so far. New industries are also not
coming up due to lack of motivation, investment capacity among the local entrepreneurs.
A new unit with automatic operation of brick & hollow blocks making using non traditional
materials available locally in a cost effective manner will go a long way to combat this
problem.
2.03 Condition of roads in this part of the country is generally very poor. At lot of facelift
is necessary to be given to roads, adjacent footpaths & road sides. Use of concrete
paver blocks is good for this job for their easy laying, better look & finishes and their
durability & cost effectiveness. So paver blocks, these days are used in the localities in
road construction and flooring in open areas of public offices, commercial building and
housing apartments. Further pavers cake be made in various shapes & sizes &
dimensions as per requirement of the customers (rectangular, square, round shape etc.)
2.04 The technology for construction of bricks, hollow blocks and pavers gives high
strength, precise size and light weight which are green building materials & perfect for
constructional activities.
Concrete brick & blocks gives high thermal and sound insulation because of
superior thermal insulation property of raw materials and good sound barrier materials. It
allows no water seepage from exterior to interior walls for absence of capillaries. These
are fire resistant, pest resistant & there does not have any chance of efflorescence.
From builders point of view, it is ease of working (lifting, drilling, cutting, chiseling,
rasping are easy & convenient & can be done with traditional tools). Other advantages
are faster construction, best finishing, less plastering which saves cost & increased
carpet area and reduces dead load resulting in saving of steel & concrete.
4
From social benefits point of view use of more concrete bricks & blocks save
fertile land. Manufacturing is energy efficient and reduces carbon emission. Thus it
brings social & environmental benefits. Concrete brick & blocks have some of technical
parameters as under.
Dry density : 500 – 600 kg/M3
Compressive strength : 90 – 250 kg/cm2
Thermal conductivity : 0.16 to 0.18 W/KOM
Wet density : 800 – 850 kg
It saves 33% plastering mortar, 60% joining mortar, 10% wastage, 10% steel
materials (less deal load) & 1.5% carpet area. Construction time is reduced by about
25% compared to clay bricks.
2.05 Vibro-Hydraulic technology is adopted for making concrete bricks, blocks &
pavers. The same machine is used for making these products. Operation is carried out
under a shed & can be continued throughout the year unlike manufacturing of traditional
clay bricks & tiles in open & operations are to be suspended in rainy season which
continues for about 5 to 6 months in a year in this region.
2.06 The decision taken by the promoter to choose this project is based on many
factors such as –
Availability of basic raw materials like sand, cement & stone dust *undersize of
stone aggregates generated in stone crushing) etc. in abundance & good quality at
reasonable price making finished product cost effective.
Site topography, environmental regulations, sizable local market.
Scopes for expansion & diversification.
2.07 The promoter of the project is a highly technically qualified person having
professional experience of working in IT sector since several years in the country &
abroad (USA). He has intended to avail financial assistance in the form of subsidy under
PMEGP (Prime Minister’s Employment Generation Programme) which is a central
scheme administered by the Ministry of Micro, Small & Medium Enterprises for new
projects to be set up.
Proposed project is a new one in manufacturing sector. The location of the project
is in rural area (XXXXXXXX on XXXXXXXX Kathal road under GP & XXXXXXXX
Development Block in industrially backward district of XXXXXXXX, in the State of
XXXXXXXX). XXXXXXXX district is a hill & border district having international boundary
with Bangladesh is about 50 KM away from the proposed location. Further the promoter
of the project belongs to OBC category & beneficiary. Hence he is eligible for subsidy of
35% of project cost under the scheme and promoter’s contribution for the project is 5% of
project cost (capital expenditure and margin money of working capital). As per the
5
guidelines of scheme, the proposed project will have term loan from Bank/Financial
Institutions etc. to the extent of 95% of the project cost which will be disbursed fully for
setting up of the project. Subsidy amount when released by the Nodal Agency of the
scheme wil be routed through the lending bank & adjusted against the term loan
disbursed.
The promoter is also eligible for a host of recurring subsidies on power tariff,
captive power plant installation, stamp duty, working capital interest subsidy, GST
exemption etc. from XXXXXXXX Govt. as per their incentives offered to small & medium
industries.
2.08 The promoter of the project – XXXXXXXXXXXXXXXXXX after extensive inquiries
& consultation with the experts in the field has selected to purchase multipurpose vibro
hydraulically operated machine for this purpose. The machine is easy to operate with
high efficiency, equipped with inbuilt equipment and accessories and hs the flexibility to
utilise the same machine to produce fly ash bricks as well as other precast solid
materials like bricks, paver blocks, solid hollow concrete blocks etc.
2.09 Various moulds can be used for fitting to the mahal for making products of
different dimensions & different shapes. Maximum product density can achieved and
output is high with less labour strength compared to operations in traditional brick making
operations.
2.010 In view of market study of demand & supply requirement, locally and in adjoining
hill states and considering other relevant aspects relating to plant location vis-à-vis
infrastructural facilities available, output of products qualitatively and quantitatively, cost
and profitability projections of the proposed unit and other socio economic benefits.
Setting up of an automatic plant for production of bricks, pavers & hollow blocks with
locally available materials like sand, stone dust & cement is considered to be a techno
economically viable proposition. The same products can be made by this machine using
fly ash instead of stone dust but fly ash is to be bought from the sources outside the
state. An indepth analyais of various such factors is presented in the following chapters
for proper appraisal & evaluation of the project.
6
CHAPTER – 3
PROMOTER
3.01 The project is being implemented in name & style of “H.D. CONCRETE
INDUSTRY” having its works and commercial office located at XXXXXXXX on
XXXXXXXX Kathal Road. The location is in rural area under Ambikapur Gao Panchayat
& XXXXXXXX Development Block in XXXXXXXX district of XXXXXXXX. XXXXXXXX
district in southern XXXXXXXX is a border district.
The proposed industrial unit in manufacturing sector is a new one & promoted by
an individual XXXXXXXXXXXXXXXXXX. Constitutionwise it would be a proprietorship
unit.
XXXXXXXXXXXXXXXXXX
7
CHAPTER – 4
MARKET REVIEW
4.01 Brick is one of the major constructional materials for construction of buildings,
bridges & other civil construction work. In terms of expenditure and labour deployment
construction industry is the single largest factor in the country’s economy.
Brick industry is one of the oldest industries in the country. Present production of
bricks in India is estimated at 110 billion nos. approximately. Production units have been
scattered over but majority of them make bricks manually using traditional materials like
clay. Drying of clay bricks is done in sunrays. Operation of brick kilns is suspended in
rainy season. Hence clay brick industries work 5 to 6 months only in a year in this part of
the country.
Quality of bricks from small brick fields is indifferent. Inferior grades are sold as
grade II & grade III etc. Because of use of coal in dust form for bricks production
environment pollution causing health hazard is always a matter of concern.
4.02 Cement concrete hollow blocks are modern constructional materials and as such
used in residential, commercial and industrial building construction. Construction industry
is a growing sector. The demand for this product is always high in cities & other urban
centres due to construction of residential apartments, houses for different income groups
under Prime Minister Abash Yojana etc. & other commercial & industrial buildings.
8
bus stands etc. In recent times cement concrete paver blocks of different shapes &
different dimensions have become very popular for their use mainly in construction of
roads in this part of the country. It is preferred over traditional bitumen road because of
their strength, durability and other advantages, particularly in places where rainfall is high
& water logging is frequently experienced due to poor drainage system.
4.04 To meet evergrowing demand of bricks, hollow blocks, paver blocks etc, the
scientists & engineers have explored alternative materials for making of these products
as per availability in the localities. Stone dust, sand, lime powder, cement, flyash etc.
have found use as alternative to clay have been found for use.
4.05 From statistics, as furnished above it is evident the XXXXXXXX& adjacent hill
states of Mizoram, Manipur, Tripura etc. has a sizeable market for concrete bricks,
blocks & pavers enjoying & lucrative price. The proposed industry would have installed
capacity of 20,16,000 no. concrete bricks, 2,88,000 no. paver blocks & 3,60,000 no.
hallow blocks working in single shift of 8 hours & 300 working days in a year (150 days of
working for bricks, 50 days of working for pavers & 100 days of working of concrete
hollow blocks). Above production figure constitutes only a small fraction of demand &
supply existing at present in the aforesaid market. Demand will however be much more
than the projected figures in view of anticipated closer of many clay bricks making units
because of nonavailability of clay deposits, pollution problem & shortage of manual
labour. Pace of construction activities is expected to be accelerated due to emphasis by
Government on infrastructure development like construction of roads, bridges, irrigation
projects, extension of railways etc.
CHAPTER – 5
9
PRODUCTION CAPACITY AND PRODUCT MIX
5.01 The production capacity of plant & machineries for manufacture of concrete
products namely bricks, hollow blocks and pavers have been recommended by supplier
of machineries and technical consultant of the project on the following considerations.
Availability of infrastructural facilities at the work site like power, water, road,
5.02 Out of the above factors, product mix plays an important role. In the given
proposal products considered for sale turnover are solid concrete bricks (75mm), hollow
concrete blocks (100mm) & paver blocks – I shape (75mm). From the consideration of
demand aspects in the locality it is decided that out of total working days of 300 in a year
– production of bricks, pavers & hollow blocks will be taken up for 150 days, 50 days &
100 days respectively. This product mix can be changed at any time based on market
demand of the product, profitability and other important factors.
5.03 Optimum production capacity of the plant based one aforesaid production pattern
is worked out in the following manner.
(A) Undersize from boulder crusher to product solid bricks made from cement, sand &
stone dust in specified proportion.
Size : 230mm x 110mm x 75mm
Cycle time : 15 – 20 seconds
Pieces per mould : 7
Pieces per minute : 28
Optimum production per hour = 28 x 60
= 1680
Optimum production for 8 hours = 1680 x 8
= 13440 nos.
Optimum production in 150days = 20,16,000 nos.
(B) Production of paving blocks with the same ingredients as bricks
Size : 200mm x 100mm x 75mm
Cycle time : 50 seconds
10
Pcs per mould : 10
Production per minute = 60 x 10 / 50 = 12
Optimum production per hour = 12 x 60 = 720
Optimum production per day = 720 x 8 = 5760 no.
Of 8 hours working
Optimum production in 50 days = 5760 x 50
In a year = 288000 nos.
(C) Concrete hollow blocks to be made with the same ingredients as bricks & pavers
11
CHAPTER – 6
MANUFACTURING PROCESS
6.01 The process of manufacture of cement concrete bricks, hollow blocks and pavers
involves the following five stages.
i) Proportioning
ii) Mixing
iii) Compacting
iv) Curing
v) Drying
The determination of suitable amounts of raw materials needed to produce
concrete of desired quality under given condition of mixing, placing & curing is known as
proportioning.
Objective of through mixing of aggregate after screening, sand, cement & water is
to ensure that cement water paste completely covers the surface of sand & aggregates.
The purpose of compacting is to fill all air pockets with concrete as a whole
without movement of free water through concrete. Excessive compacting will result in
formation of water pockets or layers will higher water content and poor quality of product.
After removed from moulds products are protected until they are sufficiently
hardened to permit handling without damage and then are cured in a curing yard to
permit complete moisturisation for 21 days minimum by immersing them in water tanks.
Concrete shrinks slightly with loss of moisture. It is therefore essential that after
curing is over products should be allowed to dry out gradually in shade so that the initial
drying shrinkage is completed before they are used in construction work stacking is done
with their cavities horizontal to facilitate through passage of air. Generally a period of 7 to
15 days of drying will bring the materials to the desired degree of dryness.
6.02 Raw materials used in making cement concrete bricks is 60 – 62% stone dust, 30-
32% sand and 8 to 10% OFC cement. While for paver blocks the following ingredients
are used.
12
Crushed stone dust : 45%
Stone chips : 10%
6.03 Mixing & grinding of the ingredients in specified proportion is done in PAN
MIXTURE which is specially designed for thorough mixing of stone dust, stone chips &
sand etc. in powder form. Heavy cast iron rollers revolving on bearings with metal seals
are provided in the pan mixture to facilitate grinding of the materials in desired size and
shape by mixing blades made of special alloy steel with hard faced tips. A collection
hopper is provided below the discharge gate of the mixture in order to collect & stock the
mixed material from pan mixture and discharge the required quantity on the belt
conveyor.
6.04 The mixed ground materials is conveyed by the belt conveyor to the automatic
brick/hollow block/paver making machine. The conveyor belt is made of nylon materials
with rubber tips. Power is transmitted from electric motor to conveyor through reduction
gears. In order to prevent ingress of stone dust friction less idlers are provided with seals
on both sides of the conveyor.
Hydraulically operated pallet feeder takes pallet one after another from the pallet
magazine and feed to the top of the vibrating table. Compressed materials are
continuously produced & taken to the curing site where products are cured with water
spray for early strength.
6.06 An automatic cement batching system having motorized screw conveyor with
suitable length to discharge predetermined quantity of cement to the separate cement
weighing hopper is to be installed as an additional equipment which further discharges
the weighted material into the pan mixer.
6.07 Cement concrete bricks, blocks & interlocking pavers have compressed strength
achievable to 90.250 kg/cm sq., water absorption of 6 – 15%, density 1.75 gm/cc. These
are resistant to water sleepage, has heat insulation properties. It has affinity to crystal
growth between brick & cement mortar and highly durable as its strength increases with
time.
13
CHAPTER – 7
LOCATIONAL ASPECTS
7.01 While selecting the site for the proposed project the following interrelated factors
were considered & carefully evaluated.
Communication facilities.
Site characteristics, soil conditions, contour of the site, room for expansion.
Regulatory laws.
bodies.
7.02 The factor which weighs heavily in favour of selecting the site at XXXXXXXX
under XXXXXXXX Block in XXXXXXXX district of XXXXXXXX is availability of land at
reasonable cost, proximity to raw material source and market.
Raw materials like sand, stone chips & crushed stone dust are available in
abundance in the locality. Few cement factories are also existing at a distance of 100 KM
from the factory site. As there are about 50 stone crushers & a good number of brick
kilns making day bricks in the district availability of skilled & unskilled labour will not pose
any problem.
The unit being located in rural areas of the border district will attract subsidy from
the Central Govt. and a host of graded incentives from the State Government.
14
CHAPTER – 8
Raw materials required for production cement concrete bricks, hollow blocks and
pavers are cement, sand & crushed stone dust & stone chips.
While cement & sand can be procured from local suppliers/dealers stone dust &
stone chips are to be purchased directly from stone crushers. There are about 40/50
stone crushers operating in different areas of XXXXXXXXdistricts. Availability of huge
quantity of crushed stone dust generated in crushers is sold at a low price which is a
definite advantage for the project. Sand is also quite cheap here compared to the
different places in the place. Both sand & stone dust are available in abundance in the
locality. There are also few cement factories within a radius of 100 KM of the project
area.
8.02 The promoter of the project will install a multipurpose automatic vibro hydraulic
machine with necessary accessories and auxiliary equipment from the reputed supplier
on turnkey basis for production of cement concrete bricks, hollow blocks & interlocking
pavers. The same machine can also be utilized for production of fly ash bricks, solid
concrete blocks etc. by changing moulds of desired shape & size.
8.03 Power and water are the two main utilities. The requirement of electricity is about
5 KW which will be provided by the State Power Distribution Company.
A deep tube well along with necessary equipment like installation of submergible
water pump, water reservoir & overhead water tank will be erected at project site.
Requirement of water will be about 10 KL/day.
8.04 In order to have smooth & trouble free operations it is necessary to execute timely
repair & maintenance work which can be done in a series of trade workshop working
near the project area. Machine supplier will take necessary steps to supply timely
replacement parts and provide after sale service.
Necessary measures will be taken to install fire fighting devices at the vintage
point of the factory although industry of this type is not involve any potential fire hazard.
Necessary steps will be initiated for safe disposal of solid & liquid waste. Proper
drainage system will be constructed at project site for liquid waste disposal safely.
15
CHAPTER – 9
9.01 For smooth and efficient operation, the unit will have to qualified, trained and
capable set of staff & workers.
9.02 For making traditional clay brick by brick kiln manpower requirement is very high
as the operations are manual but in making concrete bricks, pavers & blocks operations
are done by automatic machines, this manpower requirement is drastically reduced
which is a definite advantage from the point of view of cost effectiveness & quality
assurance.
9.03 Production manager, an experienced person in the trade will be at the helm of
affairs and will be responsible for day to day working of the unit. He will report to the
promoter of the project daily and appraise him of all the important matters regarding
working of the unit. Under the manager there will be accountant cum cashier, store
keeper, purchase & sale personnel, production supervisor and a host of skilled &
unskilled workers.
9.04 Salary & wages for staff & workers will be fixed in consistency with wage structure
for similar job prevailing locally. Beside monthly salary/wages they will get the benefits of
PF, Gratuity, medical aids, incentives, bonus etc.
9.05 The manning pattern for the unit has been proposed on the basis of
9.06 Availability of manpower at reasonable cost will not pose problems as adequate
number of trained persons are available in the region in view of a large number of
traditional brick fields & stone crushers are existing here since long.
16
CHAPTER – 10
The capital cost of the project has been estimated on the basis of unit having
installed capacity of the plant for production of 20,16,000 no of cement concrete bricks,
2,88,000 of paver blocks and 1,92,000 no. of hollow blocks on single shift of working for
300 working days in a year. Out of 300 working days in a year, production of bricks,
pavers & hollow blocks of specified dimensions & shape will be taken up for 150 days, 50
days and 100 days respectively.
The capital cost of the project including margin money for working capital for one
cycle of operation is Rs. 25.00 lakhs as detailed in Annexure ‘A’.
Source of finance will be mainly raised from Promoter’s contribution of Rs. 1.25
lakhs at the rate of 5% of the capital expenditure, subsidy from the Govt. under PMEGP
of Rs. 8.75 lakhs at the rate of 35% of the project cost & remaining 60% of the project
cost amounting to Rs. 15.00 lakhs will be financed by Bank/Financial Institution as term
loan on normal lending terms for SSI. Bank will initially finance 95% of the project cost.
Subsidy amount will be routed through bank when released, by the Nodal Agency of the
scheme, KVIC or DICC which will be adjusted against term loan.
Debt equity ratio has been worked out to 1.86 : 1, subsidy amount being
considered as per of equity.
Beside subsidy on capital expenditure of the project, the unit is eligible for
recurring subsidy/incentives eg. Stamp duty, GST, interest on working capital loan,
power tariff, captive power installation, incentive for employment generation etc. from the
State Government. The unit being located in border district in southern XXXXXXXX and
the entrepreneur is first generation entrepreneur. The beneficiary is a technical
entrepreneur having rich professional experience in the country & abroad. He belongs to
OBC category. He has not availed benefits of the scheme under any other scheme.
The entrepreneur has taken on lease rent basis land measuring about 29000 sq.ft.
at Budirail. Land is already developed and site preparation work is more or less
completed. Ready built work shed taken on rental basis covering about 100 sq.m. built
up area will accommodate plant & machineries and other miscellaneous assets/utilities.
17
10.04 Plant, Machineries & Utilities
Promoter of the project has selected automatic hydraulically operated concrete
brick, paver & hollow blocks making machine along with required accessories. The
machine has flexibility and can suitably change over for fly ash bricks also.
Since power requirement will exceed 20 KW the promoter will buy one 63 KVA
Transformer. Erection of Transformer, providing service connection & commissioning of
the Transformer will be done by XXXXXXXX Power Distribution Company (formerly
XXXXXXXX State Electricity Board).
A deep tube well along with water pump, water reservoir & overhead water
storage tank will be installed to meet uninterrupted supply of water requirement by the
unit.
10.05 Miscellaneous Fixed Assets
Under this head items included are furniture, fixtures, equipment, movable tools &
appliances etc. as shown in Appendice A4.
10.06 Contingency & Cost Escalation
To provide against price rise of major assets due to inflation during
implementation period a small amount of fund as percentage of the cost of the assets
has been provided.
10.07 Preliminary and Preoperative Expenses
The expenditure on this head has been detailed in Appendice A6. The main
ingredient of cost is payment of interest on Term Loan disbursed during preoperation
period.
10.08 Margin Money for working capital
Margin money for working capital has been estimated on the basis being made
available as working capital to the extent of 75% of working capital requirement for the
project. Yearwise working capital required is estimated based on utilization of installed
plant capacity.
10.09 On the basis of production programme and utilization of optimum plant capacity as
envisaged, estimate of profitability has been worked out in Annexure ‘D’. As indicated the
project will earn profit right from 1st year of operation and will improve over the years as
percentage of plant capacity utilization would go up gradually.
10.10 Principal raw materials as sand, cement, stone dust & stone chips are available
locally in abundance at reasonable cost. Details about cost of raw materials & other
consumables, annual production & sale as epr product mix followed by sales realization
have been presented in Appendice D1 & D2.
10.11 Depreciation of assets has been calculated both by straight line as well as WDV
method.
18
10.12 Interest on term loan at the rate of 11.5% per annum & on working capital loan at
the rate of 14% per annum have been calculated and annexed to the report.
10.13 Financial analysis of the project shows that all the important financial indicator
depict a healthy & sound liquidity position of the project like Break Even Capacity at
66.40%, Payback period of 2 years 6 months, Debt Service Coverage Ratio if 4.31, Debt
Equity Ratio of 1.5:1 against norm of 3:1, Internal Rate of Return at 42%.
As reflected in Cash Flow Statement the unit will generate sufficient surplus as as
to meet easily all the working expenses of the unit including loan repayment obligations
fully. The project is economically viable, technically feasible and financially favourable.
19
CHAPTER – 11
11.02 Time schedule for each element of major activities involving implementation
schedule of the unit has been drawn & presented below.
All efforts will be directed for timely completion of the project. It will take 6 to 8
months to complete implementation of the project & start running production on
commercial scale. Day to day progress of work regarding implementation schedule of the
project will be monitored to avoid over running of time & cost budget.
IMPLEMENTATION SCHEDULE
20
6 Procurement of 63 KVA Transformer and 2nd month 5th month
its installation and providing service
connections to machineries & other points
as necessary
7 Arrangement of water as erection of deep 2nd month 4th month
tube well, installation of submergible pump,
pipeline & fitting, construction of water
reservoir & overhead water tank
8 Trial run of machineries (empty run) 5nd month 6th month
9 Procurement of raw materials & 6th month 6th month
consumables
10 Trial run of machineries 6th month 7th month
11 Commencement of production on 7th month onwards
commercial scale
21
ANNEXURE – A
4 Utilities 5.01
22
ANNEXURE – B
(Rs.in lakhs)
b) Initially bank is to provide to the extent of 95% of project cost, the amount being
Rs. 23.75 lakhs as term loan. Subsidy amount when released by the Government
through Nodal Agency will be routed through Bank & adjusted against term loan.
23
ANNEXURE – C
(Rs.in lakhs)
(Rs.in lakhs)
24
ANNEXURE – D
25
ANNEXURE – E
(Rs.in lakhs)
26
ANNEXURE – F
27
ANNEXURE – G
28
ANNEXURE – H
(Rs.in lakhs)
B Variable Cost
Utilities 1.13
D Fixed Costs
Depreciation 3.21
29
ANNEXURE – I
(Rs.in lakhs)
12.64
= 2 year 6 months
30
ANNEXURE – J
(Rs.in lakhs)
Sl. Item Particulars 1st 2nd 3rd 4th 5th 6th 7th
Interest on Term Loan 1.72 1.51 1.23 0.94 0.65 0.37 0.08
B Interest on Term Loan 1.72 1.51 1.23 0.94 0.65 0.37 0.08
C Debt Service Coverage Ratio 3.20 2.28 3.39 4.57 5.15 5.48 6.10
31
ANNEXURE – K
(Rs.in lakhs)
Sl. Item Particulars Preoperation 1st year 2nd year 3rd year 4th year 5th year 6th year 7th year
Period
2 Total cash inflow - 5.52 9.18 12.66 15.75 15.75 15.75 15.75
3 Net cash receipt (-) 22.35 (+) 5.52 (+) 9.18 (+) 12.66 (+) 15.75 (+) 15.75 (+) 15.75 (+) 15.75
4 Present value discounted @ (-) 22.35 3.88 4.55 4.42 3.87 2.60 1.81 1.22
42%
32
APPENDICE – A1
APPENDICE – A2
An open shed having covered area of 200 sq.m. having length of 20M, breadth 10M
& height 4.5M would be taken on rental basis. Construction of the shed is likely to be
commenced soon.
Shed to be constructed will have iron posts, beams, pucca floor, CI sheet roofing
supported on (steel) tubular trusses.
33
APPENDICE – A3
(Rs. in lakhs)
Sl. Item Particulars Quantity Cost
1 Brick/paver/hollow block making multipurpose automatic
machine equipped with an integrated control panel
complete with conveyor belts, pan mixer suitable for
casting sand, stone dust & cement for bricks & hollow
blocks & pavers made of stone chips sand and cement in
appropriate proportion. Motors – 5 HP for hydraulically 1 no. 8.25
operated main machine, 7.5 HP motor for pan mixture and
2 HP motor for colour mixture
2 Moulds with lamping heads
For hollow blocks 4 nos. 1.00
For pavers 3 nos. 1.20
3 Vibrotable having 2000 sq.ft. capacity fitted with 3 HP 1.00
motor
4 Automatic water dozing system incorporating auto 0.45
discharge of predetermined quantity of water into the drum
with digital display and electrically operated pump
Total Cost 11.90
Add : GST @18% on machineries cost 2.14
Add : Freight, insurance (in transit), packing, forwarding, handling cost 0.86
Add : Installation cost along with cost for civil works of foundation of 0.60
machine @5% of machine cost
Total Cost of Plant, Machineries & Utilities 15.50
4 UTILITIES AND PLANT SERVICES
Purchase of a 63 KVA transformer, erection/installation & transformer, 4.21
providing service connection to machineries & other sections including
cost of security money
Erection of a deep tube well for water supply and installation of 0.80
submergible pump, pipe, fitting, water reservoir & overhead tank etc.
Total Cost of Plant, Machineries & Utilities 5.01
34
APPENDICE – A4
APPENDICE – A5
(Rs. in lakhs)
Sl. Item Particulars Original Provision for Amount
Cost contingency
and cost
escalation
35
APPENDICE – A6
36
APPENDICE – D1
(Rs. In lakhs)
Sl. Item Particulars Annual Production Unit Rate Total Sale
No. and Sale Realisation
(Rs. In lakhs)
37
APPENDICE – D2
38
Cost of 1000 no. hollow block production
Cost of cement @ Rs. 9.10 per kg = Rs. 7371.00
Cost of crushed stone dust @ Rs. 1.20 per kg = Rs. 4320.00
Cost of sand @ Rs. 0.96 per kg = Rs. 3542.00
Cost of stone aggregate @ Rs. 11.50 per kg = Rs. 10350.00
= Rs. 25583.00
1st 60 141.70
2nd 70 165.30
rd
3 80 188.95
4th & onwards 90 212.50
39
APPENDICE – D3
40
APPENDICE – D4
COST OF UTILITIES
A Power requirement = 25 KW
(Rs. In lakhs)
41
APPENDICE – D5
(Rs.in lakhs)
42
APPENDICE – D6
(Rs. In lakhs)
43
APPENDICE – D7
INTEREST ON LOAN
44
APPENDICE – D8
(Rs.in lakhs)
Sl Item Particulars Rate of Original 1st yr 2nd yr 3rd yr 4th yr 5th yr 6th yr 7th yr
Dep. Cos
1 Plant & 15% 15.50 2.33 2.33 2.33 2.33 2.33 2.33 2.33
machineries
2 Utilities 15% 5.01 0.77 0.77 0.77 0.77 0.77 0.77 0.77
3 Misc. fixed assets 20% 0.55 0.11 0.11 0.11 0.11 0.11 0.11 0.11
B By WDV Method
Sl Item Particulars Rate of Original 1st yr 2nd yr 3rd yr 4th yr 5th yr 6th yr 7th yr
Dep. Cost
1 Plant & 30% 15.50 4.65 3.25 2.28 1.60 1.12 0.78 0.55
machineries
2 Utilities 30% 5.01 1.50 1.35 0.95 0.66 0.47 0.33 0.23
3 Misc. fixed assets 20% 0.55 0.11 0.09 0.07 0.06 0.05 0.04 0.03
45