ESMF For Somali Electricity Access Project Somaliland 1
ESMF For Somali Electricity Access Project Somaliland 1
ESMF For Somali Electricity Access Project Somaliland 1
GOVERNMENT OF SOMALILAND
Public Disclosure Authorized
FINAL
© September 2018
Somali Electricity Access Project (SEAP) 2018
TABLE OF CONTENTS
TABLE OF CONTENTS .................................................................................................................. I
LIST OF TABLES .......................................................................................................................... III
ACRONYMS AND ABBREVIATIONS ......................................................................................... IV
EXECUTIVE SUMMARY ...............................................................................................................1
1 INTRODUCTION AND PROJECT CONTEXT .......................................................................8
1.1 PROJECT CONTEXT ........................................................................................................................ 8
1.2 PROJECT DESCRIPTION .................................................................................................................. 9
1.3 PROJECT DEVELOPMENT OBJECTIVES .......................................................................................... 9
1.4 PROJECT BENEFICIARIES ............................................................................................................... 9
1.5 PROJECT COMPONENTS ............................................................................................................... 10
1.5.1 Component 1: Electrification of households and small businesses through standalone solar
home systems....................................................................................................................................... 10
1.5.2 Component 2: Analytical work for enabling electrification through solar powered/hybrid
mini-grids ............................................................................................................................................ 13
1.5.3 Component 3: Technical assistance, capacity building and project management ............. 14
1.6 PROJECTS EXCLUDED FROM FINANCING ..................................................................................... 14
2 SCOPE AND METHODOLOGY OF THE ESMF .................................................................. 15
2.1 ESMF JUSTIFICATION ................................................................................................................. 15
2.2 ESMF PRINCIPLE ........................................................................................................................ 15
2.3 METHODOLOGY .......................................................................................................................... 15
3 POLICY, LEGISLATIVE AND INSTITUTIONAL FRAMEWORKS ................................... 17
3.1 SOMALILAND LAWS AND LEGISLATIONS ..................................................................................... 17
3.2 WORLD BANK SAFEGUARDS OPERATIONAL POLICIES ............................................................... 19
3.3 WORLD BANK GROUP EHS GUIDELINES .................................................................................... 20
4 PROJECT BIOPHYSICAL AND SOCIOECONOMIC SETTING ......................................... 21
4.1 CLIMATE...................................................................................................................................... 21
4.2 ENERGY RESOURCE .................................................................................................................... 21
4.3 SOLAR ENERGY ........................................................................................................................... 21
4.4 ENERGY ACCESS ......................................................................................................................... 21
5 CONSULTATION AND PUBLIC DISCLOSURE .................................................................. 22
5.1 ESMF DISCLOSURE ................................................................................................................. 22
6 KEY RISK AND IMPACT MITIGATION ............................................................................. 23
6.1 INTRODUCTION ............................................................................................................................ 23
6.2 SOCIAL BENEFITS, RISKS, AND IMPACTS ..................................................................................... 26
6.3 POSITIVE E&S IMPACTS ............................................................................................................... 26
LIST OF TABLES
TABLE 3-1 INSTITUTIONAL ARRANGEMENTS IN ENVIRONMENTAL DECISION MAKING............................................18
TABLE 6-1 KEY E&S CHALLENGES AND MITIGATION .............................................................................................23
TABLE 6-2 POTENTIAL E&S RISKS AND IMPACTS .....................................................................................................24
TABLE 10-1 ESTIMATED BUDGET FOR TECHNICAL ASSISTANCE & IMPLEMENTATION OF ESMF ............................41
Abbreviation Description
BP Bank Policy
GM Grant Manager
DA Designated Account
DC Direct Current
DG Director General
EU European Union
FM Financial Management
Abbreviation Description
IA Implementing Agency
LG Lighting Global
Abbreviation Description
OP Operational Policy
PP Procurement Plan
PV Photovoltaic
RE Recipient Executed
Abbreviation Description
TA Technical Assistance
EXECUTIVE SUMMARY
Introduction
This document presents the Environmental and Social Management Framework (ESMF) for the Somali
Electricity Access Project (SEAP) for the Government of Somaliland (GoSl). The ESMF ensures that the
project activities are compliant with the relevant requirements of national policies, regulations and
legislations as well as the World Bank Safeguards Policies and Procedures. The objective of this ESMF is
to set out the principles, rules, guidelines and procedure to assess the environmental and social impacts and
monitoring to ensure that environment and social aspects are duly considered.
This ESMF only applies to those activities that will be financed, either directly or indirectly, by SEAP, and
not to any other activities that a supported beneficiary may be otherwise involved in; all language in this
ESMF should be interpreted under this light.
Project Development Objective
The Project Development Objective is to expand access to electricity in targeted urban, peri-urban, and
rural communities in Somaliland.
The Project consists of three components as indicated below:
➢ Component 1: Electrification of households and small businesses through standalone solar
home systems
➢ Component 2: Analytical work for enabling electrification through solar powered/hybrid mini-
grids
➢ Component 3: Technical assistance, capacity building and project management
Project Description
Component 1: Electrification of households and small businesses through standalone solar home
systems
This component aims to reduce market barriers for the private sector to provide modern energy access
through solar home systems and targets (i) poorer households and small businesses in areas that cannot
afford to connect to mini-grid services; (ii) households and businesses in these areas that are not
sufficiently close to a mini-grid to be economically connected; (iii) isolated villages and smaller
settlements where mini-grids do not make economic sense; and (iv) nomadic pastoralists whose
livelihoods do not lend themselves to a fixed electricity connection.
This component will fund a range of market-building supply- and demand-side interventions in response to
these challenges. The proposed interventions (indicative allocations to each intervention are shown based
on initial analysis performed during project preparation, but are intended to remain flexible to react to
changing market needs) are:
at businesses specializing in solar home system distribution, but could also be available to MFIs,
local savings cooperatives, or other institutions looking to enter the solar distribution market.
b. Upfront Seed Grants1: Since effective results-based financing requires that recipients have access
to sufficient inventory, funding, and capacity to self-finance initial sales, a complimentary
window will offer small upfront (i.e. paid in advance rather than results-based) Seed Grants to
support the relatively long tail of smaller or less experienced Somali distributors who are either
already active in the solar market or who might enter the market given additional incentives.
Seed grants will enable these businesses to build up a minimum of inventory and infrastructure
to launch sales and access the results-based Expansion Grant above. In addition, Seed Grant
funding will be used to provide a range of business development services (mostly through
external consultants) to early-stage Somali business in the off-grid solar sector, including support
on designing and implementing off-grid business models (especially pay-as-you-go), preparing
financial statements and projections, and connecting and negotiating with international off-grid
solar equipment suppliers, industry bodies, and other service providers. Application for Seed
Grant eligibility will be streamlined but will nonetheless entail a more rigorous evaluation
process since funding is awarded before results are achieved. The funding for Seed Grants is
expected to be made available by the Japan Policy and Human Resources Development (PHRD)
technical assistance program window.
c. Quality assurance: Interventions to limit the availability of and demand for poor-quality and/or
counterfeit products, including TA activities for national and regional governments, potentially
in preparation for eventual adoption of Lighting Global quality standards. The prolonged conflict
in Somali region and absence of quality control regulations, standards and policies has turned
the country into a hotbed of counterfeit products and dumping site of sub-standard goods. This
component will support the recently established Somali Bureau of Standards as well as quality
control initiatives in Somaliland, among others.
Component 2: Analytical work for enabling electrification through solar powered/hybrid mini-
grids
This component will support the mini-grid sector in Somaliland. The objective of this Component is to
focus on supporting activities that will establish a pipeline of mini-grid projects and define
delivery/business models for their implementation. This component is expected to include the following
activities:
a. Detailed geospatial mapping to undertake a more comprehensive inventorying of the current mini-
grid situation in Somaliland, identify potential future sites, and estimate future location-specific
demand
b. Review of property rights and land issues pertaining to energy infrastructure investment;
1 The financing of this sub activity would be provided in a separate grant under the Japan PHRD
This component will support a range of activities to strengthen the capacity of the Ministry of Energy and
Water Resources of the Federal Government of Somalia and the Ministry of Energy and Minerals in
Somaliland for overall energy sector management, power and access planning, and implementation of
future development projects. These activities will include targeted technical assistance in the form of: (i)
energy sector studies; (ii) development of energy sector strategies; (iii) review/finalization of energy
policies; (iv) additional analytical work; (v) improvement of respective internal ministry infrastructure
and systems; (vi) capacity building through trainings, workshops, and study tours; and (vii) supporting
the establishment of Project Implementation Units (PIUs) in the respective ministries to oversee
Component 2 and potential future IDA-funded projects (see Annex 2 for more details on implementation
arrangements and PIUs).
Capacity building activities funded under this component will be preceded by a detailed needs assessment
exercise in the first year of the project to identify priority interventions. This assessment will build on
initial capacity building and TA needs identified during project preparation and as part of the Power Sector
Master Plan currently under preparation. These include TA to develop national engineering standards for
power generation and distribution, developing a power sector regulatory framework, and training ministry
staff on key policy issues, including:
i. Preparing energy sector policy and planning;
ii. Preparing and promulgating tariff setting and licensing regulations for mini-grid
operators;
iii. Establishing engineering standards such as electrical wiring and installation codes;
iv. Setting health and safety standards for workers and consumers in the electricity sector;
v. Conducting feasibility studies;
vi. Performing resource mapping and working with GIS;
vii. Environment and safeguards; and
viii. Fiduciary/Procurement processes.
Project Beneficiaries
The Project aims to provide unelectrified Somali households and small businesses in urban, peri urban
and rural areas with affordable and reliable energy access. The project is expected to reach 41,000
households, equivalent to around 246,000 people, around 22.5% of the current off-grid population. Of
this number, 122,000 are expected to be women.
The project further aims to support the private standalone solar sector, which has become the main agent
of energy service provision, with little or no support from the government. Lastly, the project supports
the development of SMEs contributing to job creation in a nascent economy.
this report describes the overall baseline condition of Somaliland in terms of biophysical environment and
the socio-economic context. Existing environmental and socio-economic conditions will, in many cases,
provide a basis for predicting impacts of the project components and sub-components. The project
activities will be implemented within premises of existing firms and will therefore not have any direct
interactions with indigenous people lands and territories.
In recent years Somaliland has effected a constitution within which article 12 addresses: Public Assets,
Natural Resources and Indigenous production. Although there are no Environmental Policy and Act in
place, an Environmental and Social Assessment Framework has been produced through the SDF program.
Protection and use of Somaliland water resources is the responsibility of the Ministry of Water Resources
that has put a policy, act and regulatory framework in place.
negative impacts of the project are prevented and/or mitigated appropriately, and positive impacts are
enhanced.
The activities envisaged under SEAP are low-risk. All products to be procured under the project must
adhere to the quality standards and testing methods developed by Lighting Africa/Global2. Criteria for the
selection of SHS companies to participate in the project will be developed and Lighting Africa/Global
compliance clauses will be included in funding agreements with the private sector. The criteria and
compliance to Lighting Africa/Global quality assurance frameworks will form the E&S requirements to be
established by the Grant Manager under component 1 of the project.
The Grant Manager will ensure qualified SHS companies sell and/or install SHS as per the funding
agreement and will be required to have an ESMS that will focus on key risks for this component (labor
issues, battery/waste management, and OHS issues).
The project will also be monitored to ensure that it puts adequate safeguards in place to address governance
issues. The project’s Task Teams will be required to consider as best practice, putting in place transparent
and accessible selection criteria that will ensure that companies owned by women, youth and people with
disabilities, have equal chance for consideration for funding under the project through the Grant Manager.
The ESMF incorporates aspects related to solid waste from solar PV systems and a project-specific
environmental code of practice (ECoP) has been developed as a guidance on approach for the collection,
transport, storage and disposal of spent batteries, with the aim of ensuring that risks to the environment and
human health are prevented or mitigated. Apart from providing approaches to the management of spent PV
batteries, the ECOP also seeks to inform discussion and build awareness of all stakeholders, including rural
community members, vendors/suppliers of products and service providers, around safe management of used
batteries.
The project will be implemented by The Ministry of Energy and Minerals (MoEM), Government of
Somaliland (GoSl). GoSl will competitively procure independent Grant Managers to manage the
Expansion Grants and Seed Grants under Component 1a and Component 1b. GoSl will be fully responsible
for procurement activities in order to foster project ownership, including preparation of Terms of
References, developing evaluation criteria for selection of firms, and review of deliverables. The Grant
Manager to be procured by the respective PIUs to manage Component 1a and Component 1b will have a
qualified Environmental and Social Management Specialist in his/her team in accordance with the
minimum qualifications provided for in Annex 4 of the ESMF. The E & S Specialist of the Grant Manager
will be responsible for the E & S screening of proposals for Component 1a and Component 1b and in
ensuring that the E & S requirements set forth in the ESMF for the grant recipients are complied with
Project Implementation Units (PIUs) will be established within the Department of Energy at the Ministries
of Energy and Minerals in Hargeisa. They will have the overall responsibility for project management,
coordinating project implementation, monitoring and evaluation and reporting of results to stakeholders
and developing environment and social safeguards frameworks and plans. PIU staff for the project will
either be seconded from government or hired as consultants, through a competitive process. Short-term
2 https://www.lightingglobal.org/where-we-work/lighting-africa/
local and international consultants will be recruited to support the PIU as needed. The capacity in the PIUs
will be enhanced through on-the-job training and mentoring by the Bank’s technical staff working on
fiduciary and safeguards and the task team leader. In areas such as procurement, it may be a challenge to
find a specialist already familiar with Bank policies and guidelines; as such, a procurement specialist from
an existing Bank-assisted project, SCORE, will be used in the interim while the project procures a specialist.
During implementation, an individual consultant will be hired for the first year of the project to the build
capacity of the new specialist. The implementing entities will develop a Project Implementation Manual
(PIM) to govern technical, financial and procurement functions of the project at the implementing agencies
level.
Component 1: Electrification of households and small businesses through standalone solar home
systems
Safeguard arrangements for component 1 will be implemented by the Grant Manager (GM). The GM will
screen and approve proposals for funding. The GM will set environmental and social (E&S) standards to
be met by grant recipients implementing activities under SEAP; and ensure the requirements are met during
the grant application, selection, agreement, and operationalization stage. During the grant agreement stage
the GM will ensure Environmental and Social Management Systems (ESMS), clean E&S track records,
and exclusion criteria are incorporated. During the operationalization stage, the GM will also conduct
periodic reviews and performance checks as needed, on a sample of the SHS companies, to assess their
ESMS and capacity to implement the safeguards arrangements.
The minimum E&S qualifications for the safeguard arrangements under component 1 are attached in Annex
4 of the ESMF.
Component 2: Analytical work for enabling electrification through solar powered/hybrid mini-grids
Component 2 will be implemented by the Project Implementation Units (PIUs). The minimum E&S
qualifications for the safeguard arrangements for this component are similar to those under component 1.
The minimum E&S qualifications for the safeguard arrangements under component 2 are attached in Annex
4 of the ESMF.
The ESMF has assessed the implementing agencies capacities and has proposed measures to enhance
safeguards capacity to improve environmental and social performance during project implementation; this
will include safeguards training for PIU. The budget proposed to enhance safeguard capacity is a total of
USD 110,000 for GoSl.
The budget will cater for capacity building of the PIU related to safeguard compliance, incorporate E&S
requirements (ESMS, clean track E&S record, applies Exclusion Criteria for SHS Companies, and
Contractors) into application, grant agreements and conduct review of SHS companies ESMSs, Monitoring
& Evaluation and Implementation of ESMF.
Grievance Redress Mechanism
The PIU will establish and manage a Grievance Redress Mechanism (GRM) to enable beneficiaries to
communicate their concerns regarding the Project. More specifically, the GRM will detail the procedures
that communities and individuals, who believe they are adversely affected by the Project or a specific
subproject, can use to submit their complaints. Further, it will also detail the procedures to be used by the
PIU and their implementing partners, to systematically register, track, investigate and promptly resolve
complaints.
The electricity access rate is estimated at 15 percent, meaning that around 11 million Somalis lack access
to electricity services. Access depends significantly on demographic variables, with urban access estimated
at 33 percent, and rural access at 4 percent. With an average household size of 5.9, this translates to
approximately 1.7 million un-electrified households nationwide. Private sector players supply more than
90 percent of power in urban and peri-urban areas using local private mini-grids, having invested in diesel-
based systems of between 500 kVA to 5000 kVA installed capacity per mini-grid. These mini-grids are
usually zoned, with each operator building, owning, and operating the generation, transmission, distribution
and maintenance, as well as collecting tariffs. Thus, more than 68 percent of urban/peri urban households
receive electricity service, though at a high cost that might reach a maximum of $1/kWh, making Somali
region one of the costliest places in the world to buy power. The latest ESMAP Regulatory Indicators for
Sustainable Energy (RISE) report found that Somali region ranks in the upper 5% globally for power cost,
and in the upper 15% globally for power expenditure as a share of GNI per household. As a result, access
levels remain low despite many households living near mini-grid power lines.
The proposed project aims to focus on improving energy access via standalone solar solutions for both
households and small enterprises given the country and sector context, as well as the modest financing
envelope. This will take the form primarily of providing a package of incentives to support local
entrepreneurs to develop new ventures or scale up existing activities. The project will especially target
existing “first movers” who have already demonstrated independent interest and capability in the solar
home systems sector. A smaller allocation for mini-grid activities will focus on studies aimed to
complement and build upon ongoing DFID and EU-led initiatives around this technology, and the findings
of the Master Plan that is currently under preparation with World Bank financing. The project will also
focus on building capacity within government agencies, while recognizing the need for robust third-party
support to deliver the project activities.
In addition to providing increased energy access, the project will set an invaluable precedent for Somali
energy sector development as well as international donor engagement. The project design draws on a
number of current best-practice off-grid interventions, including: (i) it constitutes a pilot engagement on
standalone solar home systems that is anticipated to further prove and develop the market for future public
and private sector engagement; (ii) it brings a public sector intervention to scale-up private sector delivery
of energy services; (iii) it contributes to the further scaling up the World Bank / IFC ‘Lighting Africa’ model
Environmental and Social Management Framework (ESMF) 8
Somali Electricity Access Project (SEAP) 2018
for achieving off-gird electrification, particularly on quality assurance; and (iv), by mobilizing external debt
from private-sector financial institutions, it provides an important example of Maximizing Finance for
Development (MFD) implementation in a fragile context.
The Project will be implemented across the entire Somaliland. While there are tremendous needs with
respect to energy access, the fragile and complex operating environment necessitates a selective approach
to supporting the effective delivery of affordable and sustainable energy services. Somali’s private sector
has impressively stepped up to deliver basic energy services in the aftermath of the protracted conflict of
the 1990s. Nevertheless, these enterprises often lack the capital and latest technical, financing, and business
model insights to scale their businesses. The core proposition of this project is that by leveraging these
incumbent capabilities and activities, the overall quality of services they offer to their customers will be
improved, especially as they are provided with technical and financial resources needed to deepen and
broaden their geographic footprints.
The Project Development Objective is to expand access to electricity in targeted urban, peri-urban, and
rural communities in Somaliland.
• People provided with new or improved electricity service (Core Indicator; 246,000 people); and
• Generation capacity of energy constructed or rehabilitated (Core indicator, 0.34 MW).
The Project aims to provide unelectrified Somaliland households and small businesses in urban, peri
urban and rural areas with affordable and reliable energy access. The project is expected to reach
41,000 households, equivalent to around 246,000 people, around 22.5% of the current off-grid population.
Of this number o beneficiaries, 122,000 are expected to be women. These numbers would increase
substantially with co-financing from other donors, i.e. from the Japan Policy and Human Resources
Development (PHRD) technical assistance program window. Technology funded through the project will
provide an average of around 8W of generation capacity to each household reached, amounting to a total
of around 0.344 MW in expected new capacity. Rural areas in Somali regions are characterized by low
density of population, high levels of poverty, and nomadic lifestyles. These areas have extremely low or
no connectivity to electricity as they are not deemed economically feasible targets for grid extension.
The project aims to support the private standalone solar sector, which has become the main agent of
energy service provision, with little or no support from the government. There is very limited financing
or credit offered along the energy supply chain Importers are unable to access loans and therefore buy goods
with cash up front, limiting their ability to scale and reach new market segments. Manufacturers and
foreign-based distributors perceive Somali businesses as high risk, and do not typically offer supplier credit.
For consumers, finance for solar off-grid products is undeveloped.
The project supports the development of SMEs contributing to job creation in a nascent economy.
Somali region has the building blocks in place to develop a strong private sector-based market for off-grid
solar products. There is a demonstrated demand and need for electricity and off-grid solar products, and a
variety of companies have already demonstrated strong capacity to reach off-grid consumers. Moreover,
there is also a strong foundation of entrepreneurial capacity among Somali business people and leaders that
can drive this initiative. Therefore, public resources will be used to harness private sector efficiencies by
creating appropriate incentives to mitigate the risks of doing business in the country. Such an initiative can
also create jobs directly contributing to economic productivity and security in the region.
The market for solar home systems in Somali region has significant potential. A study conducted in
preparation for this project estimated current demand at around 140,000 – 180,000 units for a total value of
around US$ 14 million per year. The total potential (non-annualized) market size for solar home systems
up to 500W was estimated at US$ 108.4 million, corresponding to around 1.1 million units, and US$ 79.6
million for systems up to 100W. This demand is further expected to rise as populations grow, off-grid
mobile phone usage increases, and more and more Somalis become aware of the potential benefits of solar
technology as a substitute or complement to conventional lighting sources such as candles, kerosene,
flashlights, and unreliable (mini-)grid connections.
Nonetheless, the current market situation remains well below its potential. The vast majority of sales to date
have come from low-quality, unreliable, and unsustainable imitation products. These are typically brought
in via the UAE or Oman as part of general goods orders by informal, non-specialized traders with limited
knowledge of quality solar products and few incentives to promote quality in a highly informal, unregulated,
and price-driven market. A small but growing supply side for quality-approved solar devices has begun to
Environmental and Social Management Framework (ESMF) 10
Somali Electricity Access Project (SEAP) 2018
emerge as local entrepreneurs have started to capitalize on growing demand for more durable, higher-
performing products. To date, these distributors have managed to sell on the order of a few hundred systems
(partnering with subsidiaries of established providers of Lighting Global-certified off-grid solar home
system products), and have in some cases launched small initial pilots for alternative consumer financing
arrangements such as pay-as-you-go to tackle consumer affordability constraints for their products. In
addition to these dedicated off-grid distributors, a long tail of more generalist distributors continues to offer
off-grid lighting products of variable quality on a more opportunistic basis.
Though the early activity of these companies shows promise for the Somali off-grid market, local
distributors continue to face significant barriers to scale, including: (i) competition and market spoilage
from low-quality imitation products; (ii) low levels of consumer awareness around solar technology,
particularly regarding the long-term benefits of high-quality products and how to identify these; (iii) low
affordability among end-consumers, exacerbated by limited access to consumer finance; (iv) high costs of
rural distribution due to Somaliland’s large size, low population density, and poor transport infrastructure;
and (v) limited access to capital for inventory and investing in business infrastructure, as local banks still
prefer lower-risk, safer returns from more established industries.
Neither local nor international credit is currently available to Somali solar distributors due to the perceived
high risk of doing business in the country. There are several reasons for this, including: (i) unfavorable
loan terms and conditions; (ii) lack of capacity and limited understanding of customer needs amongst
financial institutions; and (iii) lack of competition among banks. Many individuals and businesses report
that they do not have enough or sufficiently reliable information for banks to assess their credit worthiness
and cannot meet banks’ strict collateral requirements to manage credit risk. As a result, businesses and
individuals are largely self-financing and circumvent the formal sector for their financial needs.
This component will fund a range of market-building supply- and demand-side interventions in response to
these challenges. The proposed interventions (indicative allocations to each intervention are shown based
on initial analysis performed during project preparation, but are intended to remain flexible to react to
changing market needs) are:
a. Results-based Expansion Grants: Results-based grants to off-grid solar distributors, with payment
based on the number of new Lighting Global-approved units sold. These grants will provide
distributors with much-needed capital to build internal capabilities, invest in sales and distribution
infrastructure, pilot new and innovative businesses and customer service models (including pay-as-
you-go models that enable customers to pay in installments, thus spreading out payment over longer
periods of time and improving affordability), and build up liquidity to act as collateral for future
debt finance from local banks. Expansion Grants will be primarily targeted at businesses
specializing in solar home system distribution, but could also be available to MFIs, local savings
cooperatives, or other institutions looking to enter the solar distribution market.
b. Upfront Seed Grants: Since effective results-based financing requires that recipients have access
to sufficient inventory, funding, and capacity to self-finance initial sales, a complimentary window
will offer small upfront (i.e. paid in advance rather than results-based) Seed Grants to support the
relatively long tail of smaller or less experienced Somali distributors who are either already active
in the solar market or who might enter the market given additional incentives. Seed grants will
enable these businesses to build up a minimum of inventory and infrastructure to launch sales and
access the results-based Expansion Grant above. In addition, Seed Grant funding will be used to
provide a range of business development services (mostly through external consultants) to early-
stage Somali business in the off-grid solar sector, including support on designing and implementing
off-grid business models (especially pay-as-you-go), preparing financial statements and
projections, and connecting and negotiating with international off-grid solar equipment suppliers,
industry bodies, and other service providers. Application for Seed Grant eligibility will be
streamlined but will nonetheless entail a more rigorous evaluation process since funding is awarded
before results are achieved. The funding for Seed Grants is expected to be made available by the
Japan Policy and Human Resources Development (PHRD) technical assistance program window.
c. Quality assurance: Interventions to limit the availability of and demand for poor-quality and/or
counterfeit products, including TA activities for national and regional governments, potentially in
preparation for eventual adoption of Lighting Global quality standards. The prolonged conflict in
Somalia and absence of quality control regulations, standards and policies has turned the country
into a hotbed of counterfeit products and dumping site of sub-standard goods. This component will
support the recently established Somali Bureau of Standards as well as quality control initiatives in
Somaliland, among others.
The bulk of grant funding to businesses will be deployed in the form of results-based financing (RBF) under
the Expansion Grant. Well-administered RBF schemes are increasingly popular tools for both catalyzing
and cleaning up off-grid solar markets. They work by offering clear financial incentives to distributors for
the sale of high-quality (i.e., Lighting Global quality-verified) products on a first-come, first-served basis.
This incentivizes distributors to shift away from the sale of ineligible low-quality products, and to expand
their distribution networks to capture a larger share of the available funding. Distributors are also
incentivized to expand as rapidly as possible as funding is capped and not pre-allocated. There are a variety
of customization options available, including the specific formula for incentive calculations, the eligibility
criteria for firms and product sales, and reporting and after-sales service requirements. For instance, the
size of the incentive might be linked to the size of the system (as defined by SE4ALL’s multi-tier energy
access tracking framework) or whether sales are in urban or rural areas. Firms will be required to keep and
share complete records of product sales and commit to providing after-sales service that meets Lighting
Global requirements. An independent verification agent (IVA) will be tasked with ensuring companies meet
their obligations to customers and correctly report sales submitted to the Expansion Grant.
The Expansion Grants and Seed Grants will be managed by a single Grant Manager, but separate Grant
Managers will be procured for Somalia and Somaliland. Eligibility for grant funding will reflect regional
considerations (e.g. accessing RBF funds in one region will require evidence that the sale occurred in that
region). Procuring independent and experienced third-party Grant Mangers will address Government
technical capacity gaps, regional and clan dynamics, and the need to remain impartial and neutral in
delivering a successful project. Separate Grant Managers for the two territories will ensure ownership and
capacity building for each of the respective governments. Grant Managers will also be required to provide
basic ongoing business development services to grant applicants to help strengthen applications and
business models and ensure grant funds are being used effectively. Grant Managers for both regions will
be expected to cooperate, exchanging market intelligence and information on prospective grant recipients
as needed.
Outcomes under these activities will be complemented and strengthened by the Somalia Capacity
Advancement, Livelihoods and Entrepreneurship through Digital Uplift Program (SCALED-UP)-P168115,
currently under preparation by the World Bank’s Finance, Competitiveness & Innovation (FCI) Global
Practice. SCALED-UP will work with local Somali banks to stimulate commercial lending to underserved
sectors (including the off-grid energy sector) through the provision of credit enhancement in the form of
guarantees and/or low-cost lines of credit. This enhancement will unlock private debt by buying down
lender risk in Somalia’s still nascent off-grid solar market. In addition, SCALED-UP activities will include
assistance to local banks in building a pipeline of both potential lenders and borrowers, making
introductions and linkages between banks and businesses, supporting distributors in making loan
applications, and supporting financial institutions in performing diligence and evaluating loan applications.
As limited access to debt for working capital is a crucial constraint for Somali off-grid companies, SEAP
will benefit greatly from enhanced participation of Somali banks in the off-grid sector. Conversely, funding
provided through the SEAP grants is expected to strengthen the financial position and growth prospects of
local solar distributors, thereby making them less risky clients for local banks. The SEAP team will closely
collaborate with FCI during SCALED-UP preparation and implementation to provide technical inputs and
ensure harmonization of approaches.
1.5.2 Component 2: Analytical work for enabling electrification through solar powered/hybrid
mini-grids
This component will support the mini-grid sector in Somaliland. The information available on existing
mini-grids is scant, even though they are the default energy provider throughout the country. While the
ongoing Power Master Plan Study (Master Plan), financed by the World Bank, will provide some clarity
regarding the status quo, additional sector studies will be required to define the appropriate way forward
for mini-grid technology. While the Master Plan will provide the long-term vision for the sector, key
development partners already have activities underway to support the scale up of mini-grids in Somaliland.
For instance, DfID supports the £20MSomalia. These include DfID’s £20 million ESRES Program, which
in its first phase is supporting the hybridization of six mini-grid sites with a £5 million budget. Phase 2 will
kick off in 2018 and will deploy the remaining £15 million. The EU has just completed another 6
community micro grid installations via the ADRA-implemented Somali Energy Transformation (SET)
Project. With the considerable activities currently underway by other donors, the objective of this
Component is to focus on supporting activities that will establish a pipeline of mini-grid projects and define
delivery/business models for their implementation.
a. Detailed geospatial mapping to undertake a more comprehensive inventorying of the current mini-
grid situation in Somaliland, identify potential future sites, and estimate future location-specific
demand
b. Review of property rights and land issues pertaining to energy infrastructure investment;
c. Pre-feasibility studies for hybridization, operational enhancements, and densification of
brownfield (existing) mini-grid sites
Environmental and Social Management Framework (ESMF) 13
Somali Electricity Access Project (SEAP) 2018
Capacity building activities funded under this component will be preceded by a detailed needs assessment
exercise in the first year of the project to identify priority interventions. This assessment will build on
initial capacity building and TA needs identified during project preparation and as part of the Power Sector
Master Plan currently under preparation. These include TA to develop national engineering standards for
power generation and distribution, developing a power sector regulatory framework, and training ministry
staff on key policy issues, including:
PIU and the Grant Managers will use and refer to this ESMF during implementation of the Project. Where
appropriate, Environmental and Social Management Plans (ESMPs) will be prepared during project
implementation following guidelines in the ESMF. It remains the responsibility of the safeguards officers
of PIU and Grant Managers to ensure that the necessary mitigation plans are developed and adhered to by
the beneficiaries.
2.3 METHODOLOGY
The ESMF was prepared through literature review and stakeholder discussions. The consultant undertook
a review of the Project Appraisal Document and Integrated safeguard datasheet (ISDS) for the SEAP, as
well as a review and analysis of relevant national legislation, policies, and guidelines, including the World
Bank Operational and Safeguards Policies related to this Project.
Consultation with key stakeholders in the application and implementation of the ESMF for the Project was
conducted on May 22, 2018. The main points outlined in the consultative meetings with key stakeholders
are in chapter 5 and documentation in Annex 5.
In all Somali territories policy and legislation with respect to the environment is evolving, in terms of
assessing the potential impact of such policies on the environment, or how they could contribute to
environmental conservation and sustainable livelihood improvement.
In recent years Somaliland has effected a constitution within which article 12 addresses: Public Assets,
Natural Resources and Indigenous production. Although there are no Environmental Policy and Act in
place, an Environmental and Social Assessment Framework has been produced through the SDF program.
Protection and use of Somaliland water resources is the responsibility of the Ministry of Water Resources
that has put a policy, act and regulatory framework in place.
For Somaliland the institutions at National, Regional and District Levels responsible for the implementation
and monitoring compliance of both national and international agreements are shown below and include:
• The Minister, in consultation with the Parliamentary Environment committee and civil society
organizations working in the environment shall establish Environmental Watch Councils at
National level (NEWC).
• The Ministry of Environment and Rural Development (MoERD) in Somaliland in consultation with
Regional Authorities, the civil society at the Regional level and communities, shall establish the
Regional Watch Councils (REWC).
• The MoERD in consultation with the Local Government Councils/ District Governor, local
Community-Based Organizations (CBOs) and the community shall establish the District
Environment and Environment Watch Council (DEWC).
• The members of the Council shall come from both genders and should be Somaliland citizens in
good standing in the community and are environmentally conscientious. The council shall serve
five-year terms at a time and can be re-appointed.
The environmental licensing process in Somaliland is regulated by the Ministries. The key principles are:
• a. The MOERD (Somaliland) or any person authorized by him/her may grant any of the licenses
enumerated. Every license shall be subject to such conditions as may be specified therein.
• The Minister or any person authorized by him/her may at any time cancel or suspend any license
granted by or on behalf of the Minister, the holder of which has been on reasonable grounds
suspected by the Minister or such other authorized person, to have infringed any of the conditions
upon or subject to which said license has been granted, and may at any time vary the conditions of
any such license.
• Any person aggrieved by any order under this Article may appeal to the Minister of MOERD for
Somaliland whose decision shall be final.
The scope of activities requiring licenses include charcoal production, mining and quarrying, collection of
plants and grasses, collection of gums and resins, and investment projects including sectors such as waste,
wastewater, roads, and energy infrastructure.
For the project implementation the E&S management will fully rely on WBG environmental and social
standards.
Table 3.1 gives a brief overview on roles and responsibilities on environmental management.
Institution Mandate
Council of Ministers Approves National Strategic Climate Strategy
Parliament Approval of Environment Acts and Laws
Central Level • Prepares Strategic Climate, Environment
MoERD (Somaliland) and Social Strategy
• Environmental Policies / Plans
• Guidelines - Approves EAs
• Liaison with Regional level Institutions
• Monitoring and Evaluation
The Project is classified as Environmental Assessment Category B and triggers OP/BP 4.01 given that
potential impacts associated with financing of small-scale activities under components 1a and 1b. The
project receives this classification since project activities have the potential to cause localized negative
environmental impacts, which can be identified and managed using standard approaches. Projects and
activities have yet to be fully defined.
Under the Project, only one World Bank safeguard policy was triggered, namely the Environmental
Assessment Operational Policy (OP/BP 4.01).
In accordance with OP/BP4.01, This ESMF sets out the principles, rules, guidelines and procedures to
assess the environmental and social impacts. It contains measures and plans to reduce, mitigate and/or offset
adverse impacts and enhance positive impacts, provisions for estimating and budgeting the costs of such
measures, and information on the agency or agencies responsible for addressing project impacts.
No social impacts related to IPs or involuntary resettlements are anticipated under any of the activities
proposed for implementation under the three components of the project. This is because the activities will
be implemented within the premises of existing firms. For this reason, the project has not triggered the
Social Safeguard Policies, OP/BP 4.10 (Indigenous Peoples) and OP/BP 4.12 (Involuntary resettlement).
4.1 CLIMATE
The Somali climate is hot, arid to semi-arid. There are two wet seasons (Gu April to June, and Deyr October
to November) with approximately 500 mm rainfall annually in the northern highlands, 50-150mm along
coast, and 300-500 mm in the southwest. With the impact of climate change extreme weather patterns such
as droughts and floods (see also natural disasters) are likely to increase in frequency and magnitude.
3Based on data from the European Commission’s African Renewable Energy Technology Platform (AFRETEP), http://capacity4dev.
ec.europa.eu/afretep/minisite/maps-and-data-sources. Calculations based on an average six-hour day of electrification in a 365-day year
Stakeholder engagement is important because it will give the project stakeholders and the potentially
Project Affected Person(s) the opportunity to contribute input and feedback information, aimed at
strengthening the development process and avoiding negative impacts or mitigating them where they
cannot be avoided. Effective and close consultation with them is a pre-requisite for the successful running
and execution of the SEAP.
The PMU will establish a grievance redress mechanisms (GRM) that will allow general public in the
project area, affected communities or individuals to file complaints and to receive responses in a timely
manner. The system will also record and consolidate complaints and their follow-up. This system will, be
designed for handling complaints perceived to be generated by the project or its personnel. It may also
include disagreements about compensation and other related matters.
Stakeholder‘s engagement and public consultation would be an on-going activity taking place throughout
the entire project process. Public participation and consultation would take place through meetings, radio
programs, requests for written proposals/comments, filling in of questionnaires, explanations of project
to the locals, making public documents available at the local levels.
During the project preparation process, discussions were held with the project implementing agency
(MoEM) on the project activities and components.
Consultations with stakeholders will be held continuously with the beneficiaries throughout the course of
project implementation.
The ESMF will be disclosed to stakeholders in Somaliland and on the World Bank’s external website, after
the World Bank review, as final draft versions. In-country disclosure of the ESMF will utilize appropriate
communication channels such as on the websites of the implementing agencies and/or as hard-copies in a
location and format easily accessible to public, and other public places of project intervention areas) as well
as on the World Bank external website.
The proposed activities under component 1 will involve plug and play solar systems as well as installed
solar systems where panels will be placed on the rooftops and within the existing property of households,
small business premises, or firms. These activities are expected to have limited, temporary and for the most
part reversible environmental and social impacts. No physical displacement or potential impact on
livelihoods is anticipated. Therefore, the World Bank Operational Policy on Involuntary Resettlement (OP
4.12) is not triggered, and the project will exclude any activity that will require land acquisition.
Component 2 activities will only focus on analytical work where a consultancy firm will be engaged to
carry out a pre-feasibility study that will identify and develop a pipeline of mini-grid projects to be financed
in the future.
Overall, the project will undertake consultations for broader stakeholder support, buy-in and ensure social
and gender-related considerations are met.
Specific E&S risks for each project component are mainly linked to processes and capacities of key
stakeholders for E&S risk management.
Table 6-1 Key E&S Challenges and Mitigation
Given the fragile context of the country, the low capacity of the Borrower particularly on safeguards, and
the potential social risks that might result from weak labor practices (child and forced labor) and OHS risks;
the overall E & S risk for the project is rated substantial.
Table 6.2 summarizes potential negative E&S impacts for each SEAP component. Beyond the mitigation
measures discussed below it will be important to adopt waste management principles (Source reduction,
reuse and recycling) at all time
Social risks associated with the potential exclusion of poor and vulnerable households, including female-
headed households and internally displaced people (IDP), will be mitigated by targeting rural and peri-
urban areas with particular attention paid to reaching first-time borrowers and by ensuring that
beneficiaries’ eligibility criteria will be transparent and part of the communication campaign. Risks
associated with the potential exclusion of small retailers from lists of prequalified suppliers will be
mitigated by relying as much as possible on the local supply chain and by targeting SMEs
• Reduced lighting costs to project beneficiaries: Electricity access will replace kerosene lamps
which are expensive to operate. Kerosene is costly both for low income households that buy it, and
for governments that subsidize it. In parts of Africa, for instance, kerosene costs make up 10-25%
of household monthly budgets according to a report by Lighting Africa market trends report 2013.
Comparing to these costs, the consumption electricity bills seem to be cheaper than using kerosene
for lighting significantly. Therefore, this project means greater savings on the part of the
households.
• Positive expected impact on poverty alleviation: With more affordable and stable electricity in
the otherwise off-grid areas, the beneficiaries will be engaging in income generating activities
hence improving their economic status.
• Provision of employment: Although minimal this project will have a positive impact on both
direct and indirect employment levels in the country translating into incomes at the household
levels which will trigger other spending and demand in the local economy.
• Improved standard of living: The implementation of this project will result in connecting about
28,700 to the off grid electricity. Access to electricity will change the standard of living of the
people as they can use domestic appliances like, fridges, television sets, to mention but a few. Use
of electricity for lighting implies that the people will not be exposed to smoke arising from use of
kerosene lamps which predisposes people to respiratory diseases.
• Communications: Access to electricity will lead to improved communication for the beneficiaries.
This will be enabled by the fact that charging of mobile phones will be easier and cheaper. Access
also to mass media like radio and T.V will provide opportunity for the households to access a wide
range of information which is useful for decision making.
• Gender Considerations: Electricity is a basic service especially for lighting but is still a luxury
for many rural women and men. Access to modern electricity will go a long way towards alleviating
the daily household burdens of women, giving them more time, improving their health and
enhancing their livelihoods. Available literature on gender and energy suggests that providing
electricity to communities and homes will promote gender equality, women‘s empowerment, and
women‘s and girls‘ access to education, health care, and employment. Indeed, most gender benefits
of the project will occur because women tend to spend more time at home, are responsible for
household chores that can be carried out more productively with electricity, and because certain
Environmental and Social Management Framework (ESMF) 26
Somali Electricity Access Project (SEAP) 2018
tasks are culturally defined as women‘s work. The first and strongest impacts of the project shall
occur via lighting and TV.
Electricity will definitely displace more expensive candles and kerosene lamps, thereby reducing
indoor air pollution, fire, burn risk and providing higher quality light. Women and girls will benefit
more from air pollution of kerosene lamps because they spend more time in the kitchen. Lighting
and television will improve access to information, the ability to study, and extend the effective
working day. This is more so because children can have extended time of study. The women will
also benefit more due to access of information, especially on health and nutrition since they also
spend more time at home. The project will also enhance security in the rural areas as most homes
will be lit up, a benefit that is more appreciated by women.
The successful implementation of the ESMF depends on the commitment of PIU, the private sector and
related institutions, and the capacity within the institutions to apply or use the ESMF effectively, and the
appropriate and functional institutional arrangements, among others. The sections below describe the
detailed roles and responsibilities of the key institutions involved in the implementation of the ESMF by
project components.
Project Implementation Unit (PIU) will be established within the Department of Energy at the Ministry of
Energy and Minerals in Hargeisa. The PIU will have the overall responsibility for project management,
coordinating project implementation, monitoring and evaluation, and reporting of results to stakeholders
and developing environment and social safeguards frameworks and plans. PIU staff for the project will
either be seconded from government or hired as consultants, through a competitive process. Short-term
local and international consultants will be recruited to support the PIU as needed. Each PIU will have a
qualified E & S Specialist selected in accordance with the minimum qualifications set forth in Annex 4 of
the ESMF.
The capacity in the PIU will be enhanced through on-the-job training and mentoring by the Bank’s technical
staff working on fiduciary and safeguards and the task team leader.
PIU will also provide overall responsibility for safeguards due diligence, and compliance monitoring.
Further, PIU will be responsible for the overall coordination of the project implementation and oversight.
Grant Manager.
This component will support the deployment of stand-alone solar systems ranging in different sizes and
levels of service. SHS standards are described in the SHS Operations Manual in detail.
Based on the qualification criteria established by Grant Manager GoSland submitted to the World Bank for
clearance; which include E&S requirements, SHS distributors will need to be qualified before they can
submit application for grants under this component. Once a SHS distributor becomes a qualified distributor,
it can then submit grant application, which once approved, will cover aspects of increase enterprise liquidity
by investments into business functions such as marketing, training, and after-sales support. Once the grant
agreement has been signed, the distributor will start the installation/distribution. Grant Manager is
responsible for verifying distributors ‘qualification, installation performance, overall compliance and
maintaining a GRM for both the public and the distributors for project related feedback.
The project will ensure that terms of reference for hiring the Grant Manager for implementation of
Component 1 contain clauses that relate to safeguards and occupational health and safety competencies
and specific tasks related to safeguard monitoring and enforcement. This will ensure safeguard capacity
within GM team to review beneficiary, applications, review and monitor the grants, and work in close
collaboration with the PIU safeguard focal person to manage the execution of the ESMF. The minimum
staffing qualification for GM safeguard capacity is provided in annex 4 of the ESMF. The selected
grant manager will be responsible for coordinating and supporting the implementation of safeguards
and will prepare a Project Implementation Manual (PIM) that will include a checklist for project
activities including potential threats, and mitigation measures as well as capacity building for
safeguards implementation and compliance monitoring. The Grant Manager will submit the PIM to the
GoSl for review, who will be required to submit to the Bank for clearance. Thus, any bidders for any
of the funding available under this component will have to indicate, in their respective bids, how they
intend to address environmental and social sustainability issues that could be associated with the
provisions of those services. The selected bidders will be responsible for implementing the safeguards
on the ground, including ensuring compliance with occupational health and safety imperatives and
dealing with de-manufacturing of out-of-use solar devices, e-waste disposal, and recycling.
Specifically, in terms of E&S risk management under component 1, the Grant Manager will be responsible
for:
• Overall oversight of the E&S risk assessment, management, and monitoring processes component
1 tools safeguard tools provided in this ESMF;
• Putting in place and implementing a reporting system from private sector entities to PIU on
implementation of E&S requirements;
• Ensuring that the private sector entities are implementing E&S component 1 requirements as set
out in the ESMF consistently;
• Assuming responsibility for citizen engagement, maintaining adequate stakeholder engagement
and grievance redress mechanism and ensuring that private sector entities maintain the same at their
level. The Grant Manager facilitate liaise with CBOs, NGOs and project affected communities;
The select Grant Manager will have safeguard capacity within its team to review beneficiary, applications,
review and monitor the grants. The GM will report to the PIU and the PIU will request for Bank clearance
on the implementation of safeguard requirement under component 1 by preparing regular consolidated
report on E&S performance of all subprojects.
The key players for ESMF implementation under component 1 will be the GM and the standalone solar
system (plug and play solar home system, or installed SHS) companies. GM roles during grant
application and operation stages are described in the sections below.
The Grant Manager will establish and publish the qualification criteria for SHS distributors to apply to
become ―Qualified Distributor under this project component. Specific E&S requirements are:
• Have a good E&S track record, meaning no E&S related fines, violation record, litigation, or
pending litigations in the past three years;
• Have an institutional ESMS that meets GM requirements – ESMS here is defined as a number of
key policies and procedures prepared and implemented by an SHS Provider (see Annex 2);
• Have the intuitional capacity to implement such ESMS; and
• Be willing to participate in E&S capacity building activities hosted by Grant Manager should GM
deems necessary.
Interested distributors can submit its completed Qualification Application Form and supply all required
documentation for application, including E&S documents, as part of application.
Grant Manager will review and verify the application before making the decision.
After verification, GM and the SHS distributer would sign the Grant Agreement, which should include clear
E&S requirements, such as:
c) Post-Installation
After the SHS has been installed and is in use, the distributor is still responsible to maintain in good
compliance to overall requirements, provide good customer service, and participate in battery
disposal/recycle program.
• Monitoring E&S compliance by independent company (under TOR for general monitoring of SHS
companies);
• Maintain project related GRM issues; and
• Prepare strategy for battery disposal / recycling (Lithium ion).
7.2.2 E&S AREAS FOR COMPONENT 2: Analytical Work for Enabling Electrification
Through Solar Powered/Hybrid Mini-grids
This component will support the mini-grid sector in Somaliland. The objective of this Component is to
focus on supporting activities that will establish a pipeline of mini-grid projects and define
delivery/business models for their implementation.
• Detailed geospatial mapping to undertake a more comprehensive inventorying of the current mini-
grid situation in SomalilandSomalia, identify potential future sites, and estimate future location-
specific demand
• Review of property rights and land issues pertaining to energy infrastructure investment;
• Pre-feasibility studies for hybridization, operational enhancements, and densification of
brownfield (existing) mini-grid sites
• Pre-feasibility studies for greenfield (new) sites identified in geospatial mapping
• Developing structuring options for the financing, operation, and ownership of new mini-grids
• Defining legal, institutional and financing arrangements for developing mini-grids.
The consultant to be engaged for component 2 must have a safeguard capacity within its team. The
minimum safeguard staffing qualification within the consultant’s team is provided in annex 4 of the ESMF.
The role of the safeguard consultant under component 2 is, among others, to detail an E&S scope that will
mainstream following into the analytical work and output documents:
• E&S risks
• Potential mini grid placing or siting
• Land acquisition
• Access
• Site selection process
• E&S Issues to be taken up during the subsequent phases
7.3 E&S AREAS FOR COMPONENT 3: Technical Assistance, Capacity Building and
Project Management
Implementation of safeguards under component 3 will be the responsibility of the Project Implementation
Units (PIUs). To ensure the safeguards-related support, including setting health and safety standards for
workers and consumers in the electricity sector and the Bank safeguard policy requirements and WBG EHS
Guidelines are met, short-term local and international consultants will be recruited to support the PIU as
needed. The capacity in the PIU will also be enhanced through on-the-job training and mentoring by the
Bank’s technical staff working on fiduciary and safeguards and the task team leader.
The GoSl will be responsible for the preparation of the ToRs that will be used during the implementation
of SEAP, and GoSl will be required to submit ToRs to the Bank for clearance, particularly including the
selection of the Grant Manager. As guided by ESMF, the ToR for GM will outline E&S actions to be
implemented by the GM against a proposed timeframe, and this will be reviewed by the PIUs.
Subprojects with any of the above attributes will not be eligible for support under the Project.
o Will the subproject lead to unplanned use of the infrastructure being developed?
o Will the subproject lead to long-term or semi-permanent destruction of soils in cleared
areas not suited for agriculture?
o Will the subproject lead to the interruption of subsoil and overland drainage patterns (in
areas of cuts and fills)?
o Will the subproject lead to landslides, slumps, slips and other mass movements in road
cuts?
o Will the subproject lead to erosion of lands below the roadbed receiving concentrated
outflow carried by covered or open drains?
o Will the subproject lead to long-term or semi-permanent destruction of soils in cleared
areas not suited for agriculture?
o Will the subproject lead to health hazards and interference of plant growth adjacent to
roads by dust raised and blown by vehicles?
o Will the subproject lead to induced settlements by workers and others causing social and
economic disruption?
o Will the subproject lead to environmental and social disturbance by construction camps?
o Will the subproject cause economic displacement?
o Will the subproject temporarily displace squatters, economically or physically, or other
informal groups?
o Will the subproject cause a loss in productive assets or income source?
o Will the subproject restrict access to resources?
o Will the subproject affect the livelihoods or vulnerable people, such as persons with
disabilities, widows or the elderly?
o Will the subproject create social conflict over the distribution of benefits or resources?
The Grant Manager or the focal points in the implementing partners might need to conduct field visits to
determine if any of the above impacts might be triggered. Any subproject triggering any of the above
impacts will require an Assessment of the triggered impacts, and a Plan to mitigate the specific impacts.
Environmental and social safeguards instruments will be prepared where the screening checklist identifies
existence of the itemized risk in 8.1.3 above. Findings of this instruments will be collated together and
included in the project ESMP and C-ESMP. The implementing agency will be obligated to review and
comply with the developed ESMP and C-ESMP. These will be also be referenced and included in the
bidding document and the contracts to be executed between the implementing agencies and the grantees
and suppliers. The Bank and the implementing agency’s safeguards team will support and monitor the
ESMP and C-ESMP compliance through the project cycle and ensure it remains responsive to the project
risk.
The signed screening form will be passed on by the Grant Manager to the Program Manager and the
relevant subproject engineer for further processing.
This chapter describes the Grievance Redress Mechanism (GRM) that the PIU and GM will establish and
manage to enable beneficiaries to communicate their concerns regarding the Project. More specifically, the
GRM details the procedures that communities and individuals, who believe they are adversely affected by
the Project or a specific subproject, can use to submit their complaints, as well as the procedures to
systematically register, track, investigate and promptly resolve complaints.
The PIU and GM will have the overall responsibility to address Project activity-related complaints from
Project affected communities or individuals regarding any environmental or social impacts due to
subproject activities. PIU/GM will recruit a dedicated focal point in its Office to handle Project activity-
related complaints. Each of the Implementing Partners will designate a GRM focal point.
Grievances can be brought up by affected people in case of: (i) non-fulfillment of contracts or agreements;
(ii) compensation entitlements; (iii) types and levels of compensation; (iv) disputes related to destruction
of assets or livelihoods; (v) disturbances caused by construction activities, such as noise, vibration, dust or
smell. Anonymous complaints will be admissible.
The Implementing Partners and Project contractors will also keep a log of issues brought directly to their
attention verbally or in writing by Project affected communities or individuals, and relay these concerns in
writing to PIU/GM on a next day basis. PIU/GM will determine if these concerns rise to the level of a
complaint.
PIU/GM will register the complaint in a dedicated log, including a copy of the complaint and supporting
documents. A draft template for registering grievances is found in Annex 6.
PIU/GM will record and document complaints received in the subproject file and the subproject progress
reports, including the number and type of complaints and the results of their resolution.
inform the plaintiff if the complaint is accepted or rejected within one week of receiving the
complaint; any technical input from Project engineers; if necessary the response will require
input from Project engineers
if the complaint is accepted, send the plaintiff an officially stamped review card indicating:
• plaintiff name or legal representative
• plaintiff address
• complaint title
• review date
• list of annexes submitted with the complaint
work with engineers, implementing partners, and contractors to resolve the complaint within 28
days of its submission
PIU/GM will include the log of complaints to the World Bank as part of PIU/GM quarterly reporting to the
World Bank.
The GRS accepts complaints in English or the official language of the country of the person submitting the
complaint. Submissions to the GRS may be sent by:
Email: [email protected]
Fax: +1-202-614-7313
Letter: The World Bank
Grievance Redress Service (GRS)
MSN MC 10-1018
1818 H St NW
Washington, DC 20433, USA
Environmental and Social Management Framework (ESMF) 38
Somali Electricity Access Project (SEAP) 2018
The Panel has authority to receive Requests for Inspection, which raise issues of harm as a result of a
violation of the Bank’s policies and procedures from:
• Any group of two or more people in the country where the Bank financed project is located who
believe that, as a result of the Bank’s violation of its policies and procedures, their rights or interests
have been, or are likely to be adversely affected in a direct and material way. They may be an
organization, association, society or other group of individuals;
• A duly appointed local representative acting on explicit instructions as the agent of adversely
affected people;
• In exceptional cases, a foreign representative acting as the agent of adversely affected people;
• An Executive Director of the Bank in special cases of serious alleged violations of the Bank’s
policies and procedures.
Provision of information. All workers should be informed about the grievance mechanism at the
time they are hired, and details about how it operates should be easily available, for example,
included in worker documentation or on notice boards.
Transparency of the process. Workers must know to whom they can turn in the event of a
grievance and the support and sources of advice that are available to them. All line and senior
managers must be familiar with their organization's grievance procedure.
Keeping it up to date. The process should be regularly reviewed and kept up to date, for example,
by referencing any new statutory guidelines, changes in contracts or representation.
Confidentiality. The process should ensure that a complaint is dealt with confidentially. While
procedures may specify that complaints should first be made to the workers’ line manager, there
should also be the option of raising a grievance first with an alternative manager, for example, a
human resource (personnel) manager.
Non-retribution. Procedures should guarantee that any worker raising a complaint will not be
subject to any reprisal.
Reasonable timescales. Procedures should allow for time to investigate grievances fully but
should aim for swift resolutions. The longer a grievance is allowed to continue, the harder it can
be for both sides to get back to normal afterwards. Time limits should be set for each stage of the
process, for example, a maximum time between a grievance being raised and the setting up of a
meeting to investigate it.
Right of appeal. A worker should have the right to appeal to PIU or national courts if he or she is
not happy with the initial finding.
Right to be accompanied. In any meetings or hearings, the worker should have the right to be
accompanied by a colleague, friend or union representative.
Keeping records. Written records should be kept at all stages. The initial complaint should be in
writing if possible, along with the response, notes of any meetings and the findings and the reasons
for the findings.
Relationship with collective agreements. Grievance procedures should be consistent with any
collective agreements.
Relationship with regulation. Grievance processes should be compliant with the national
employment code.
Despite the current low level of safeguard capacity within the agencies responsible for the power sector in
Somaliland, there is some nascent capacity in those government’s agencies responsible for environmental
matters. Given the relatively low to minimal level of environmental and social impacts anticipated by small-
scale solar installations under this project, the addition of one or two knowledgeable and engaged safeguard
specialists to a dedicated PIU or the staff of agencies responsible for electricity sector oversight could
adequately cover safeguard requirements for this project. Under Component 3, additional capacity building
for safeguard focal points and implementing agencies' technical staff could also serve as the base for
strengthening their safeguards oversight capacity for possible future larger power projects. The frameworks
will assess in more detail the staffing and capacity of the implementing agencies and propose a course of
action to fill the staffing and capacity gaps during implementation.
The ESMF has assessed the implementing agencies capacity and has proposed measures to enhance
safeguards capacity to improve environmental and social performance during project implementation; this
will include safeguards training for MOEM (SL). The budget proposed to enhance safeguard capacity is
110,000USD for GoSl.
The budget will cater for Capacity building of the PIU related to safeguard compliance, strengthening E&S
capacity, community engagement and sensitization, gender action implementation, battery recycling and
Implementation of ESMF.
The budget remains open for revision and improvement as and when needed. A breakdown of the budget
for GoSl is provided below.
Table 10-1 Estimated budget for technical assistance & implementation of ESMF
11 ANNEXES
Subproject name
Subproject location
Implementing Partner
Is OP 4.01 applicable?
Is the subproject eligible (yes/no)?
Field Visit (yes/no; include date)
Observations/comments
Signature of Grant Manager
Applicability
Is the subproject likely to have direct or indirect environmental or social impacts?
Yes Continue to Step 2
No Go to bottom of page and sign the screening form
• Major resettlement
• Greenfield projects
Solid Waste
Labor
• Activities a high risk of significant adverse impacts related to labor influx, child or forced labor.
• Activities requiring the involuntary taking of private land and relocation of PAPs
• Activities that require the relocation of encroachers or squatters
YES NO
A. Zoning and Land Use Planning
1. Will the subproject affect land use zoning and planning or conflict with prevalent
land use patterns?
2. Will the subproject involve significant land disturbance or site clearance?
3. Will the subproject land be subject to potential encroachment by urban or
industrial use or located in an area intended for urban or industrial development?
B. Utilities and Facilities
4. Will the subproject require the setting up of ancillary production facilities?
5. Will the subproject require significant levels of accommodation or service
amenities to support the workforce during construction (e.g., contractor will need
more than 20 workers)?
C Water and Soil Contamination
6. Will the subproject require large amounts of raw materials or construction
materials?
7. Will the subproject generate large amounts of residual wastes, construction
material waste or cause soil erosion?
8. Will the subproject result in potential soil or water contamination (e.g., from oil,
grease and fuel from equipment yards)?
9. Will the subproject lead to contamination of ground and surface waters by
herbicides for vegetation control and chemicals (e.g., calcium chloride) for dust
control?
10. Will the subproject lead to an increase in suspended sediments in streams affected
by road cut erosion, decline in water quality and increased sedimentation
downstream?
11. Will the subproject involve the use of chemicals or solvents?
12. Will the subproject lead to the destruction of vegetation and soil in the right-of-
way, borrow pits, waste dumps, and equipment yards?
13. Will the subproject lead to the creation of stagnant water bodies in borrow pits,
quarries, etc., encouraging for mosquito breeding and other disease vectors?
D. Noise and Air Pollution Hazardous Substances
14. Will the subproject increase the levels of harmful air emissions?
SHS Provider will have in place an HR policy that expresses its commitments, at a minimum to: (1) comply
with all relevant national labor laws and regulations; (2) promote the fair treatment, non-discrimination,
and equal opportunity for workers; (3) establish, maintain, and improve the worker-management
relationship; (4) allow workers‘ organizations and collective bargaining; (5) have in place a grievance
mechanism for workers; (6) not to employ forced labor or child labor, including not hiring workers below
minimum age, as defined by national law and not employ children in hazardous work4.
SHS Provider will adopt and implement human resources policies and procedures appropriate to its size
and workforce that set out its approach to managing workers consistent with the requirements of national
law. It will provide workers with documented information that is clear and understandable, regarding their
rights under national labor and employment law and any applicable collective agreements, including their
rights related to hours of work, wages, overtime, compensation, and benefits upon beginning the working
relationship and when any material changes occur. It will provide and inform workers of an internal
grievance process to raise their workplace concerns.
Collection of Batteries by SHS Companies: SHS Provider representatives will make arrangement to
collect the battery units from the consumer and store it in the local offices. SHS Provider will take necessary
measures to ensure safe storage of the batteries. It may be feasible for SHS Provider to send the warranty
expired batteries to a central location.
Buy-back arrangements with manufacturers: SHS Provider can put in place buy-back arrangements
with the battery manufacturers and ensure safe transportation of the batteries to the manufacturer. SHS
4 Employees may only be taken if they are at least 15 years old, as defined in the ILO Minimum Age
Convention (C138, Art. 2). Children under the age of 18 will not be employed in hazardous work. Children
will not be employed in any manner that is economically exploitive, or is likely to be hazardous to, or to
interfere with, the child's education, or to be harmful to the child's health, or physical, mental, spiritual,
moral, or social development
Provider and manufacturers can mutually decide on cost sharing of collection and transportation of expired
batteries, for example sign a Memorandum of Understanding signed between them;
Recycling at own facilities: SHS companies may consider establishing their own recycling facilities.
Recycling of lithium ion batteries is possible but, according to research and practice, makes little economic
sense. Lithium ion batteries can be recycled, but only at specified locations. Projects are currently underway
in Europe, the United States and Japan to develop effective and feasible recycling technologies with a
complete life cycle analysis of recycling;
Recycling at centralized locations in the country: If recycling facilities for lithium ion batteries exist,
SHS companies must use those that meet Lighting global SHS quality standards and are considered safe
and complainant with national regulations and World Bank standards;
Disposal: Lithium ion batteries may qualify as household hazardous waste. SHS Provider will ensure that
the batteries are disposed in a particular designated area ensuring environmental and occupational health
and safety in line with World Bank E&S standards and Environmental, health, and Safety Guidelines of the
World Bank Group. SHS Provider will also comply with the government regulations, if any, regarding
disposal of any of the components used in the battery units
a) Would you consider this business dangerous to your health and environment?
b) How long have you been in this business?
c) Have you observed any health challenges?
d) What other waste does the business produce?
e) How do you intend to dispose or manage the (se) other waste(s)?
The below criteria will be included in the ToRs for component 1 and component 2 for minimum safeguard
staffing qualifications within the consultants’ teams.
The safeguard resource shall have at least a Masters’ degree in Environmental Science/Environment
Studies/Environmental Engineering or related discipline with a minimum of 5 years of experience in
environmental management and report preparation; thorough understanding of the legislative and
regulatory requirements of Somaliland, World Bank operational policies and proven report writing skills.
Topic Comments
Min 1/18 Remarks
Welcome address and H.E DG Abdirahman acknowledged to the Department of energy for
introductions developing and organizing the ESMF presentation and stakeholder
H.E Engineer consultation. The DG introduced the ESMF and its importance for the
Abdirahman Abdeeq, Somali Electricity Access Project which is going to start in 2018.
Director General of
Energy and Minerals
ESMF Expectations and Outcomes were described and participants
invited to provide their feedback and recommendations.
Some of the expectation of the ESMF included:
1. To provide information about scope of adverse E&S risks and impacts
expected during subproject planning, construction and operation,
describe the approach to mitigation and monitoring actions to be taken;
and cost implication, provide the project implementers with an E&S
screening process and risk management procedures that will enable them
to identify, assess and mitigate potential E&S impacts of subproject
activities
Eng. Guled Ahmed Eng. Ahmed presented the ESMF and elaborated in greater detail the major
Energy Technical issues as follows:
Consultant 1. Environmental and social management framework purpose
2. The specific objective of the ESMF
3. Somaliland electricity access project components and beneficiaries
4. Safeguard policy and triggers
5. Positive impacts of the project
6. Negative impacts of the project
7. ESMF implementation
8. Grievance and redress mechanism
Review/Resolution
Date of Conciliation Session: ______________________________________
Was Filer Present? Yes No
Was field verification of complaint conducted? Yes No
Findings of field investigation:
_____________________________________________________________________________________
_________________________________________________________________
Issues:
___________________________________________________________________________
Signed: ___________________________
Independent Observer
Date: ___________________________
A central component of any remote solar power system such as those used in ‘plug and play’
systems and proposed under Component I of the Project is the use of rechargeable batteries. These
batteries store the power generated during the daylight hours for later use. Rechargeable batteries
include lithium ion Li-ion), nickel metal hydride (NiMH), nickel cadmium (Ni-Cad) and lead acid
batteries (LAB).
Accordingly, this ECOP applies specifically to LAB and Ni-Cad batteries. These batteries, if
improperly transported, stored and disassembled/recycled, can create long lasting environmental
impacts due largely to the chemical and heavy metals such as mercury, lead, cadmium and nickel
which are central components of these batteries. If released into the environment (via incineration
and/or leakage and leeching etc.) these chemicals and heavy metals can create a number of health
impacts including headaches, abdominal discomfort, seizures and comas. The main components
of a lead-acid battery are lead (Pb) electrodes and lead dioxide (PbO2) electrodes immersed in a
solution of water and sulphuric acid. These are generally contained in a plastic case made from
polypropylene. In addition to lead which can create to a wide range of biological effects (including
upon the kidneys, gastrointestinal tract, reproductive system and the nervous system) and is a
recognized developmental and reproductive toxicant1, lead acid batteries also contain sulfuric acid
which is highly corrosive and can cause burns and damage to skin, eyes or the respiratory system.
Both nickel and cadmium which are the central components to Nickel-Cadmium (Ni-Cad) batteries
have potential negative impacts on both the environment and on human health. While the effects
of nickel are generally less severe (in the absence of long term exposure to airborne nickel dust)
and limited to skin irritations, cadmium is a carcinogen, which can lead to renal dysfunction and
bone defects. Effective management of batteries can ensure that these potential negative impacts
are not realized as a result of this Project. Indeed, through the increased awareness activities
proposed, it is expected that the project, guided by this ECOP, will have the potential to have long-
term positive impacts on communities and public health since many batteries of this type are used
by these communities outside this project.
The approach adopted seeks to avoid the potential environmental impacts created by improper
management of LAB and Ni-Cad batteries. Mitigation measures proposed comprise two
fundamental stages or approaches namely (i) Community and user awareness and (ii) Direct
management of used nickel cadmium (Ni-cad) and lead acid batteries (LABs) by the system
suppliers.
As part of an initiative of informing the community of the risks associated with batteries under this
Project, the PIU will carry out a broad battery awareness campaign. This campaign will not only
focus on project participants and beneficiaries. Instead, the campaign will target all community
members and as such will result in improved knowledge of the environmental issues associated
with spent batteries, whether they are from people’s cars, or other power supplies etc. Importantly,
the communication campaign will include information on all the main battery types, irrespective
of whether they are high toxicity (such as NiCad and LAB) or lower toxicity batteries (such as
AA, or AAA batteries etc). The type of information to be included in the information campaign is
included in Annex.
A campaign will be designed by the Project; however, it is expected that it will include initiatives
such as:
• Information on the implementing agencies website on disposal of all battery types;
• Appropriate local information campaigns including distribution of flyers and information
sheets in local communities, awareness raising at community meetings and notices at shops
selling batteries; and
• A media campaign including advertisements and awareness pieces in local newspapers.
This campaign will run for the life of SEAP and will address issues such as:
- The differences between the battery types in terms of battery life and reliability;
- The safe handling of batteries including installation, removal, transport, storage and
disposal;
- The environmental and health aspects of poor battery disposal; and
- Focused information on the environmental and health issues associated with high toxicity
batteries and explanation as to why they must be stored, transported and disposed of in
certain ways and therefore why it is in the interests of individuals, the community, the
environment (and therefore future generations in communities) that the methods outlined
in this ECOP be followed.
Direct management of used nickel-cadmium (Ni-cad) and lead acid batteries (LAB) by
the system suppliers
The disposal and management of used batteries from solar PV systems will follow the provisions
of this ECOP, which is to require the vendors of the systems to make arrangements to collect used
Ni-Cad and LAB batteries and to properly dispose of them. Notwithstanding this, the direct
management process outlined below is focused on Li-ion, nickel-cadmium (Ni-cad) and lead acid
batteries (LABs) as these batteries represent the greatest risk to human and environmental health
if incorrectly managed. The vendors will provide a Battery Management Plan which details
arrangements for the collection, transport, storage and disposal of batteries for those systems
proposed to be eligible under the Project as part of the product registration process. The DoE will
assess these processes for compliance with the guidelines set out in this ECOP and may refuse to
register vendors’ products if they do not comply with the guidelines. A vendor may be refused
registration by the DoE under the vendor registration program if the vendor fails to provide
evidence on the arrangements for collecting/recycling batteries and redundant solar systems, or
failure to compliance with this ECOP.
The Implementation Agreement (Legal Agreement) will require the vendors to comply with this
ECOP as a condition of participation of the program. The Grant Manager will monitor
compliance with the ECOP.
The World Bank Team, as part of its supervision mission of the Project, will conduct random
checks on the Project’s compliance to battery disposal and management consistent with the ECOP.
This ECOP may be superseded by national legislation and detailed regulations on the disposal of
batteries, if the requirements of the legislation and regulation meet or exceed the requirements of
this ECOP.
The systems must be installed by qualified and experienced tradespeople in order to avoid or
minimize electrocution and other health and safety issues such as keeping bystanders away from
work areas, working at height and working with hazardous materials such as batteries.
The project operations manual sets out the minimum requirements for Vendor qualifications and
product standards for work on this Project.
Most systems will be installed on the landowner or occupier’s property (roof top or pole), and
there will be no land related issues. Micro-grids may need to distribute electricity between
buildings and may cross third party land. Beneficiaries will be required to seek and confirm
permission before works begin.
Lifting and moving batteries needs to be undertaken with care so as to avoid personal and
environmental harm. Key principles include:
Battery Disposal
For Lead Acid and NiCad batteries, the supplier will ensure that a system is in place to obtain and
properly dispose of these batteries at the time of battery replacement.
Recycling
Lead recycling operations require a high degree of control because of the potential hazards from
air emissions and wastewater discharges.
If recycling of batteries is not chosen or possible, disposal in a secure landfill is the next preferred
option. The acid should be removed from the casing and neutralized. Empty battery cases must be
disposed of carefully because they can still contain significant amounts of lead. Batteries should
then be wrapped in heavy duty plastic or encapsulated with concrete. The concrete and plastic
serves the purpose of ensuring that lead will not leach out and become mobile in landfill leachate,
thus reducing the environmental risk.
As part of the capacity building to be provided for implementation of the proposed operations, the
vendors and implementing agencies staff will receive training in the ECOP’s application. The
World Bank will monitor and provide guidance in the implementation of the ECOP. Grant
Manager will be responsible, besides other functions, to monitor and supervise the implementation
of the ECOP by Vendors.
Disclosure
This ECOP will be shared with all relevant stakeholders, relevant line departments, concerned
nongovernmental organizations, and development partners. Subsequently, it will be disclosed in
English and Somali language by PIU, and made available on their websites. Copies will also be
held at public buildings, such as libraries and offices of regional authorities, for the rural
communities to access.
Introduction
Most homes and businesses contain many pieces of equipment such as portable computers, cell
phones, power tools, standby or backup power systems, cameras, security equipment, radios,
torches, etc. that depend on batteries to operate. As a result, batteries have become integral to the
functioning of our economy and support many aspects of modern lifestyles. These households and
businesses use a number of different types of batteries which have different chemistries.
Non-rechargeable, single-use batteries used in clocks, toys, cameras and remote controls can be
either alkaline and zinc-carbon (AA, AAA, D, C, 9-volt dry cell), mercuric-oxide (button,
cylindrical and rectangular) or lithium (AA, C, button, 9-volt). These batteries are also known as
“primary” or single use batteries because they are normally not recycled and are disposed of after
use.
Rechargeable batteries (also referred to as “secondary” batteries) use lithium-ion (Li-ion), nickel
metal hydride (NiMH) or nickel cadmium (NiCd) chemistry. These are found in such products
high end products as camcorders, mobile phones, laptops and cordless power tools, shavers, and
electric toothbrushes.
Lead-acid batteries are the oldest type of secondary batteries. They are used to supply electrical
power to cars, trucks, tractors, motorcycles, and boats. Small sealed lead-acid batteries are used
for emergency lighting and uninterruptible power supplies.
Used batteries, whether primary or secondary, are potentially hazardous, so they need to be stored
and handled carefully. Some of the materials inside a battery are toxic and may damage skin and
clothes if the battery is damaged or leaking. Used batteries require careful handling to minimize
safety hazard such as explosion and fire and good management to avoid pollution of soil, surface
water and groundwater by storing them under cover and in a bunded area. The three main types of
batteries in common use in solar energy systems are described below
Lithium Batteries
There are two types of lithium batteries in common use: (i) primary (non-rechargeable) metallic
lithium (Li) batteries, which are small in size and have a long life and are used to power toys and
small electronic devices; and (ii) secondary (rechargeable) lithium ion (Li-ion) batteries, which are
one of the lightest rechargeable batteries available and which are found in more expensive products
such as laptops, cameras, mobile phones, power tools and now increasingly in solar powered
devices. Large lithium batteries are found in other applications such as backup power, electric cars
Environmental and Social Management Framework (ESMF) 63
Somali Electricity Access Project (SEAP) 2018
and some newer air planes. Lithium batteries use lithium in its pure metallic form while Li-ion
batteries use lithium compounds which are much more stable than the elemental lithium used in
lithium batteries.
Both types of lithium batteries can be recycled. During collection, they can be mixed with other
battery types in the collection container as long as certain packaging requirements are met. Larger
lithium batteries (>500g) batteries can be collected but require separate storage from smaller
handheld batteries. The risks associated with lithium battery recycling include the potential for a
fire or explosion if batteries become over-heated from sun or for example, if they short-circuit.
Nickel-Cadmium (NiCd) batteries were the first reasonably priced rechargeable consumer
batteries. They are being superseded by new rechargeables Nickel-Metal Hydride (NiMH)
batteries. Nickel-metal Hydride batteries are related to sealed nickel-cadmium batteries and only
differ from them in that instead of cadmium, hydrogen is used as the active element at the anode.
The energy density of NiMH is more than double that of Lead acid batteries and 40% higher than
that of NiCd. Like NiCd batteries, Nickel-metal Hydride batteries are susceptible to a "memory
effect" although to a lesser extent. They are more expensive than Lead-acid and NiCd batteries,
but they are considered better for the environment.
The main components of a lead-acid battery are lead (Pb) electrodes and lead dioxide (PbO2)
electrodes immersed in a solution of water and sulphuric acid. These are generally contained in a
plastic case made from polypropylene. While LAB has a history of reliability, is available
worldwide, and is widely recycled, it is also bulky and heavy, prone to gassing, and sulphation.
The heavy metal element (lead) of the battery makes the battery toxic and improper handling and
disposal of the acid and lead can be hazardous to health and the environment.
Why Recycle?
Batteries pose a risk to human health and the environment if disposed of inappropriately. They
contain heavy metals that are toxic to human health and/or have eco-toxicity impacts if they exceed
certain minimum concentrations in the natural environment. Lead, mercury and cadmium are
particularly toxic, but other metals such as nickel can also be of concern if they leach into surface
or ground water. Batteries also contain valuable metals such as cadmium, lead, zinc, manganese,
cobalt and rare earth metals that can be recovered to minimize the use of natural resources and to
reduce impacts on the environment which occur in the production, distribution and end-of- life
phases of the battery life-cycle.
Single-use batteries have significant environmental impacts at every stage of their life cycle. The
manufacture of batteries requires use of chemicals to purify metals, extraction of resources by
mining (with potential destruction of wildlife habitat) and production of power by burning fossil
fuels; which in turn contribute to global warming, and creation of air and water pollution. The
importation / transport of batteries requires yet more infrastructure development and energy usage.
In landfills, the chemicals inside batteries can leach from their casings and pollute soil and water
with toxic heavy metals if the batteries are not properly recycled.
The technology for recycling secondary (rechargeable) batteries are well known and widely
deployed in developed and some developing countries. Used LABs are widely collected and
recycled (almost 96% collection in North America). NiCad and Lithium batteries are only now
being recycled. However, in most developing countries, the economics of battery recycling is not
sustainable. The cost of handling batteries (collection, storage, packaging), and transport,
especially in rural areas, far exceed the cost of recycling the batteries. As a result, in most
developing countries, lacking recycling facilities, used batteries are invariably discarded to the
environment. Sometimes used LABs are collected, packaged and exported overseas for recycling,
the economics depending on the price of lead and cost of transportation.
The technology for recycling primary (single use) batteries though available is not widely used,
largely because of cost of recycling and because of battery collection (supply) problems. It is only
now being deployed in North America, Europe and other developed countries.
Although recycling may not be a near term option, batteries – primary and secondary – should be
collected and safely stored for transport to an environmentally safe and secure location for future
processing or to a recycling facility.