Risk Assessment FOR: Over Head Crane Erection

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 9
At a glance
Powered by AI
The key takeaways from the risk assessment are to identify hazards from lifting, working at heights and load testing activities and suggest control measures to reduce risks from these hazards.

Some of the significant hazards identified in the risk assessment include lifting operations, working at heights using scaffolding or man lifts, sling loads, rigging of crane parts, and placing girder crane assemblies.

Control measures suggested to reduce risks include using certified operators and riggers, proper PPE, barricading work areas, inspecting lifting gears and slings, planning lifting activities carefully, and ensuring communication between operators and crews.

Health, Safety & Environment (HSE)

RISK ASSESSMENT
FOR Page 1 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 All personnel to be Project and Zone inducted.


 Ensure all approved controls and prevention measures are
discussed and RA is discussed with all persons involved in
Toolbox Talk,
People the work.
1 Risk Assessment (RA) & Approvals 2 2 4 L  All personnel to attend daily toolbox meetings prior to the
1 1 1 L
commencement of works.
 All personnel to wear mandatory PPE at all time.

 Work not to start until conditions are suitable.


Arrive on site and review work conditions  Revise as required to suit new conditions, safe access to be
2 People 2 2 4 L provided to working area at all times
1 1 1 L

 High visibility vest required.


 Ensure appropriate barricades & sign boards placed around
the area during lifting.
 Ensure the parking place is clean and free from loose or
ducts.
Lifting operation loading/unloading  Approved or certified mobile crane operator should
3 People 2 2 4 L operate the crane proper judgment is required. 1 1 1 L
Installation (girder) at height.  Worker undergo specific training of
 Secure the girder assembly tightly over the trailer upon the
stand and secured by chains and ensure correct path for
trailer movement without any much inclination to the
destination.
Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 2 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 Check the cranes.


 Check the cranes equipment certification.
 Operator shall check soil condition and see that outriggers
Setting up the crane.
are in correct position before starting lifting operation.
4 People 2 2 4  Certificate of color coding of equipment (lifting gear)
1 1 1 L
 Proper PPE to use.
 Obstruction must be removed.
 Certified rigger should handle the rigging.

 All scaffolders 3rd party certified.


Usage of scaffolding/man lifts/safety  Daily inspection of scaffolding.
5 harness for accessing crane beams/ during People 2 2 4 L  Use full body safety harness while working on higher 1 1 1 L
installation of the crane. elevation. Above 1.8m from long levels.
 Must be always flag man with man lift.

 Watch for pinch point


 Crane must be on steady position
 Check the equipment’s (sling) certification
 Check for the SWL(safe working load)
 Anti-two blocking device installed and operation
6 Sling load People 2 2 4 L  Sling softeners/protection from sharp edges must be
provide
 Barricade all working area
 Sling has been inspected and in good condition
Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 3 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 Certified operator & certified rigger inspect rigging


equipment by color coding prior to lift.
 Lifting gear shall have valid certified.
 Toolbox talk for crews involve in lifting.
 Lifting operation training as toolbox talk’s topic.
Lifting and rigging of crane  Daily crane inspection prior to start of work.
parts/equipment’s to be place on the  Crane shall have a valid certification
7 rail/and carriage beam. People 2 2 4 L  High visibility vest required. 1 1 1 L
 Only rigger shall signal crane.
 Planning of all lifting activities is critical to minimize risk to
people and property.
 Daily inspection of chain block prior to use and color
coded.
 Flag man must be present to control the traffic.

Placing of girder crane assembly just near


the erection area  All hanging electric cables need to be secured properly and
8 People 2 2 4 L before shifting or moving crane assembly (min. 7 feet up) 1 1 1 L
Care should be taken, during shifting.

Positioning of mobile crane and bring the  Ensure the parking place is clean and free from loose sand
lifting hook through the roof opening. or duct.
9 2 2 4 L  Approved or certified mobile crane operator should 1 1 1 L
operate the crane. Proper judgment is required during
operating.
Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 4 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 Working area should be clear from any abs truckle.


 Equipment should be check before each use.
 Use Proper PPE.
 Working area should be barricaded.
 Check safe working load.
 Material should be secure.
 Skill crew perform job.
 Fire extinguisher should be with Crane.
 Only authorize operator operate Crane.
Crane
 Rigger must be present with equipment.
operator,
Overhead crane erection work by Mobile  Do not stand and walk under suspended load.
Riggers and  Competent person should be present all time.
10 Crane. 2 2 4 1 1 1 L
all others  Provide signage.
working  Material should be secure.
underneath  Proper sling should be used and secure the material.
 Lifting gear and check for safe working load.
 Use proper lifting tool’s and tackle.
 Two tagline should be use.
 Only authorize rigger give signal.
 Do not stand and walk under suspended load and boom.
 Competent person should be present all time.
 Only qualified person operate equipment.
 Fallow safety rule and regulation.
Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 5 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 Toolbox talks for all crews involve in hot works.


 Hot work training as toolbox talks topic.
 Ensure appropriate barricade & sign boards placed around all hot
Hot work at height & on the ground. works activities.
 Provide adequate fire protection (provision of sand, fire blanket,
11 Welding ,cutting, grinding People 2 2 4 L
fire watch man and fire extinguishers.
1 1 1 L
 Daily inspection of welding machine & earthling prior to start of
work.
 Welder shall be trained & competent.
 Welding cables shall be inspected and color coding to ensure
good condition.

 Before lifting should check SWL Capacity, and use standard


lifting gear only. And need safety lock Latch.

 Use .lift the materials proper way. Proper softness near sharp
edge locations.
12 Using by chain puller/ chain block, People 2 2 4 L 1 1 1 L
 Competent person should be present all time.

 Use proper softness near sharp edge locations.


Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 6 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 Bench workers shall be trained & competent.(working at height


training)
 Workers crews will use appropriate PPE.
 Toolbox talks for all crews.
Working on heights ascending/descending People  Safety full body harness (double lanyard) required for fall
13 2 2 4 L protection 100% tie off.(color coded)
1 1 1 L
 Tools will be used only for their intended purpose & inspect daily
prior to start of work.
Safe working platform must be provided.

Connecting main power to crane and energizing.


 LOTO- Procedure Shill Be Follows All will be trainee on logout- tag
14 People 2 2 4 L 1 1 1 L
out

 All workers area must be kept clean and tidy at all time.
 Employees have a duty to keep their immediate work area clean
Housekeeping. as possible.
15 People 2 2 4 L  Routes must be kept clear from obstructions.
1 1 1 L
 All spillages in the work area must be cleaned up immediately.
Health, Safety & Environment (HSE)
RISK ASSESSMENT
FOR Page 7 of 9
OVER HEAD CRANE ERECTION

Significant Initial Risk Residual Risk


Who or what
S/N Hazards and Environmental Risk Control Measures Risk
is at risk S L R S L R
Aspects Level Level

 calibrated or calculated or certified known load should be used


Full load test
 Experienced testing crew will be working for this job. All loads
need to be arranged in proper way and it should be ensured
16 People 2 2 4 L before lifting. 1 1 1 L
 All test block should be lifted and shifted with proper and suitable
slings to avoid any type of accidents.

 All calibrated load shall be used for over load test


 All load blocks should be properly secured with each other as a
solid section while lifting.
 Safety working gloves should be wearer during working.
0ver load test.
17 People 2 2 4 L  All slings should be in good condition, kinked ropes, open link 1 1 1 L
chains and damaged webbing sling are not allowed to use.
Proper communication shall be ensured between crane operator
and erection crew during arranging test loads by appointing a
sling person to direct the crane operators.

Severity (S) Values: 1-5 Likelihood (L) Values: 1-5 Risk (R) = S x L
Risk Level: 1 – 4 = Low (L) 5 – 12 = Medium (M) 15 – 25: High (H)

Note: Use the Risk Assessment Matrix (RAM) when determining the values of S and L
Health, Safety & Environment
(HSE)
RISK ASSESSMENT
FOR
OVERHEAD CRANE ERECTION Page 8 of 9

Risk Assessment Matrix (RAM)


LIKELIHOOD
CONSEQUENCE
1 2 3 4 5
Incident
Happens
SEVERITY

Never has Happens


several
heard of Heard of in occurred several
times per
in industry/ in times per
year in
industry/ company industry/ year in a
industry/
PEOPLE ASSETS ENVIRONMENT company Activity is company location
company
Activity taking place Activity Activity is
Activity
is taking occasionall is taking taking place
is taking
place y place continuousl
place
rarely frequentl y
regularly
y

First aid case, Property


1 no stoppage damage Causes slight damage 1 (L) 2 (L) 3 (L) 4 (L) 5 (M)
to work <$5,000

Property
Medical damage Causes minor damage,
2 Treatment between can be rectified with 2 (L) 4 (L) 6 (M) 8 (M) 10 (M)
Case $5,000 and minor resources
$100,000
Property
Restricted Causes moderate
damage
Work Case, damage, can be
between
3 temporary rectified with 3 (L) 6 (M) 9 (M) 12 (M) 15 (H)
$100,000
disruption to moderate resources
and
work (e.g. Tier 1 response)
$200,000
Lost time Property
accident, damage Serious, often long-
chronic between term damage, rectified
4 with significant 4 (L) 8 (M) 12 (M) 16 (H) 20 (H)
illness, stop $200,000 resources, potential
work for 2 and legal implications
days or more $500,000

Causes severe, long-


Fatality, life- term damage, may
threatening Property require evacuation,
5 illness, damage needs local authorities 5 (M) 10 (M) 15 (H) 20 (H) 25 (H)
permanent >$500,000 involvement (e.g. Tier
disability 3 response), certainly
has legal implications
Health, Safety & Environment
(HSE)
RISK ASSESSMENT
FOR
OVERHEAD CRANE ERECTION Page 9 of 9

Risk = Severity x Risk

Multiply the severity (1-5) by the likelihood (1-5) to ascertain the risk level.
Resulting action is detailed in table below.

Risk Rating Action Required

Record hazard, record risk ratings, recommend upgrades


1-4
to risk control measures if the risk rating is not as low as
(Low)
reasonably practicable

Record hazard, record risk ratings, record the


5-12
recommended risk control measure needed to reduce the
(Medium)
risk rating below 4 or as low as reasonably practicable

Stop the activity immediately and seek further advice to


15 – 25
reduce the risk rating below 4 or as low as reasonably
(High)
practicable.

TABLE 2

You might also like