Project: Name
Gas Fired Boiler House Ventilation

Job no. RDXXXX


Plant: BH1

Calculation Based on CIBSE Section B13, with check against BS 6644:1991.

Design Criteria: Winter Autumn Summer


Toi 10 15 28 (Deg C)
Tai (CIBSE recommends a max. of 32 Dec C) 32 32 32 (Deg C)
Boiler output (Must be over 60 kW) 495 165 0 (kW)
Burner type (at or pj) pj pj pj
Ventilation louvre height difference. 1.00 (m. Centre line to centre line)

Heat Gains:
Fabric gain/loss (+ or -) (kW)
Boiler Casing (kW)
Flue (kW)
Pipework (kW)
Pump Motors (kW)
Lighting (kW)
Misc. (kW)
Total 0.00 0.00 0.00 (kW)

Combustion airflow rate 0.30 0.11 0.01 (cum/s)


Ventilation airflow rate 0.00 0.00 0.00 (cum/s)
Combined airflow rate 0.30 0.11 0.01 (cum/s)

CIBSE Calculated BS 6644:1991


Calculated H/L natural ventilation opening 0.00 0.00 0.00 0.12
Calculated L/L natural ventilation opening 0.37 0.15 0.04 0.25

Selected H/L natural ventilation opening 0.12 (sqm)


Selected L/L natural ventilation opening 0.37 (sqm)

Mechanical supply airflow rate 0.30 0.11 0.01 (cum/s)


Mechanical extract airflow rate 0.00 0.00 0.00 (cum/s)
10:09:51 472092416.xls 04/24/2020

d Boiler House Ventilation

Rev. 0

BS 6644:1991
(sqm)
(sqm)