Maintenance Department Snaglist Inspection Approval: X X X X X

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 2

Kingdom of Saudi Arabia ‫ السعودية‬%‫المملكة العربية‬

Ministry of Health ‫وزارة الصحة‬


King Fahad Medical City ‫ الملك فهد الطبية‬%‫مدينة‬
Operation And Maintenance Administration %‫إدارة التشغيل والصيانة‬

MAINTENANCE DEPARTMENT
SNAGLIST INSPECTION APPROVAL
PROJECT Community 11/6/201
New sub-station project LOCATION DATE
NAME Center 9
CONTRACTO SECTION
(Electrical, Civil,
R Mechanical)

COMPLETED DATE OF
S/NO SNAG REMARKS
YES NO COMPLETION

1 Connect the signal for ATS and synchronization panel


and fix one gallant for the cable
x

2 x
No tagging for the MDB panel and circuit breaker

3 x
Close the gap between the two power stations

4 x
One selector switch missing in ATS no 7

6 The voltage in all substation is 380V need to adjust the


volt for the new transformer to be 380V not 400V
x

7 Engine control switch missing in ATS no 9 x

8 One fuse holder broken in EMDB-9


x
No tagging and wiring of the pilot lamp for the
9 manual ON/OFF ESMDB-9 x
As built drawing and door paper holder for all
10 the ESMDB should be submitted x
11 Frame for the main circuit breaker missing
x
12 Some fuse missing for some breaker
x
One protection cover should be installed for
13 GH_SMDB cell #7 and cell#2 x
Testing and commissioning for GH_MDB 7 and
14 9 in auto & manual mode x
Test trip point (signal) between transformer
15 x
and RMU

16 No earthing system inside the substation


x
Check the motorized mechanism or the spare
17 circuit breaker in cell #02 x
All the cable ladder and cable tray should be
18 connect with ground system x
Earthing road should be fixed in the wall not
19 inside the trench x
The cable ladder should be bigger to let the
20 cable moved in proper way in the high voltage x
Kingdom of Saudi Arabia ‫ السعودية‬%‫المملكة العربية‬
Ministry of Health ‫وزارة الصحة‬
King Fahad Medical City ‫ الملك فهد الطبية‬%‫مدينة‬
Operation And Maintenance Administration %‫إدارة التشغيل والصيانة‬

side
The end of the cables of the medium voltage
21 should be grounded well with the body of
transformer x

22 No load schedule for the panel


x
Internal tagging for the outlet should be
23 making x
The fixture with battery for emergency should
24 be connected direct with the panel x
25 Some special screw missing for the new RMU
x
The label between new and old RMU and should
26 be edit x
27 No firefighting system in the new RMU
x
Connect the power supply for GH0-SMDB-7 in
28 the sub-basement x
29 No tagging for any pilot lamp
x
No access for the outgoing cables to the load
30 for new fabricated room x
31 No fire system in the new fabricated room
x
Need to check the door lock for the new
32 fabricated room x
Need to submit the keys for the MDB locks,
33 x
substation and RMU rooms
Remove the temporary cable outside
34 x
substation

35 Cover for small UPS broken need to change x

Prepared: Noted: Approved:

ZAHRAN Area Engineer ZAHRAN Head Engineer KFMC Engineer