LNGC - Inigo Tapias - Machinery Systems Manual PDF
LNGC - Inigo Tapias - Machinery Systems Manual PDF
LNGC - Inigo Tapias - Machinery Systems Manual PDF
Document control is achieved by the use of the footer provided on every page
and the issue and update table below.
In the right hand corner of each footer are details of the pages section number
and title followed by the page number of the section. In the left hand corner
of each footer is the issue number.
Details of each section are given in the first column of the issue and update
control table. The table thus forms a matrix into which the dates of issue of the
original document and any subsequent updated sections are located.
The information and guidance contained herein is produced for the assistance of
certificated officers who by virtue of such certification are deemed competent
to operate the vessel to which such information and guidance refers. Any
conflict arising between the information and guidance provided herein and
the professional judgement of such competent officers must be immediately
resolved by reference to Naviera F Tapias Technical Operations Office.
Text
5.1
5.2
5.3
Colour Scheme
P1 P2
Stop Valve Pressure Reducing Valve Rose Box FB Foam Box
LNG Liquid
Angle Stop Valve Two-Way Cock Mud Box HB Fire Hose Box LNG Vapour
3-Way Valve Three-Way Cock (L-Type) Flexible Hose Joint Air Horn Inert Gas
Gate Valve Three-Way Cock (T-Type) Flow Meter Reciprocating Pump Spray Line
By-Pass Valve Foot Valve Flow Indicator Centrifugal Pump Superheated Steam
Swing Check Valve S Solenoid Valve Suction Bellmouth Eductor (Ejector) Fresh Water
Hydraulic Oil
Safety / Relief Valve Flow Control Valve Blind (Blank) Flange
Lubricating Oil
Angle Safety / Relief Valve Electronic Expansion Valve Orifice
Bilges
Instrumentation
Fire Pump
Foam Pump
Maker: Hamworthy KSE
Type: Vertical centrifugal
Model: CAC200-25 V48 AAN
Model: DPVF 10-70
Type: Vertical centrifugal pump, self-priming
Capacity: 5.18m3/h
Capacity: 240m3/h at 10kg/cm2
Discharge Pressure: 12kg/cm2
Motor: 106kW
Illustrations
1.0a Engine Room Arrangement - Tank Top Plan
Jockey Pump
Ballast Eductor
LO
Shaft Intermediate LO Transfer Drain LO
Bearing Shaft Pump Tank Filter
Sewage Plant
Main
Boiler
Turbine Generators
Escape Trunk
Diesel Generator
Water Heating Unit
Diesel Generator
Auxiliary Feed Water Pump
Cooling Unit Oil Filter
LO LO HFO Service
Renovating Storage Tank HFO Bunker
Tank Tank 222.5m3 Tank
45.1m 3 73.3m 3 1757.8m3
HFO Service
Chemical Products Room Tank
184.9m3
Boiler Burner
FO Unit
Inert Gas
Inert Gas Cooling Unit Drying Unit
440V Switchboard
Sanitary
Hot Water Unit
Steriliser
Store Area
Sanitary
Water Fog Pump Fresh Water Main Boiler
Unit
3.3KV Switchboard
440V Switchboards
Washbasin
Rope Store Area
Distilled Water LO Gravity Tank Diesel Generator LO Storage Tank 440V Switchboard
3
Tank 34m LO Tanks
Wires Store Area 151.7m
3 HFO Bunker
Tools Panel HFO Service Tank
Tank 3
Milling Machine 1757.8m
3
Tools Panel Grinding Machine 222.5m
Engine Store HFO Service
Pipe Bending
Tank
Machine 3
184.9m
Lathe
Overflow Tank
N2 Generator N2 Compressors 86.7m3
Inert Gas Inert Gas
Inert Gas and Nitrogen
Blower Blower
Generator Room
Spare Air Blower
and Spare Electric Motor
for Air Blower
Pipe Duct
N2 Receiver
Steering Gear
Air Exhaust
Electric Electric
Accomodation Workshop Store
Emergency Exit Air Conditioning
Units
Control Air
Lift
Receiver
Boiler Forced Draught Fan
Engine Control
Steering Gear Hatch - Bolted Service Air Room
Gas Room Compressor
Escape Trunk Garbage
Compactor
Garbage Storage
Incinerator Room Area
Rope Hatch
Acetylene Bottle Room
CO2 Room
Pipe Duct
Oxygen Bottle Room
Overflow Tank
Chemical Products Paint Store 86.7m3
Foam Room
Store
Deck Store
Fresh Air
Fans
Economiser
Garbage Chute
Economiser
Fresh Air
Fans
Deck
Store
Level 29,600mm
Level 33,000mm
Level 35,200mm Level 37,300mm
Diesel Generator
Silencer /
Spark Arrestor
Cargo
Low Temperature
Fresh Water
Deaerator Tank Expansion Tank Level 40,100mm
Deaerator Tank
Diesel Generator
Silencer / Exhaust Air Fan
Spark Arrestor
Lifeboat
Emergency
Switchboard
Emergency
Generator Room LO Storage
Tank
DO Storage
Tank
40,100mm
37,300mm
Diesel Generator
35,200mm Silencer / Spark Arrestor
Deaerator Tank
33,000mm
29,600mm
Steering Gear
Economiser
Steering Gear
Hydraulic Unit Main Deck
with Oil Tank
Steering DO GO
Gear Storage Storage Switchboard Room
Room Tank Tank Boiler Air Heater
2nd Flat
Main
Boiler
Diesel Generator
Aft Peak Escape
Tank Trunk
Turbine Generator
Turbine Feed Water Pump
1st Flat
Main Engine
Gland Condenser
Neutralising and
Washing Tank
Tank Top
Condensate Pump
LO Sump Tank Bilge Lower
Dirty Oil Tank Holding Sea
Stern Tube Oil Tank
Tank Chest
Illustrations
Internal Desuperheaters
Superheated steam from the outlet of each boiler is led to an internal
desuperheater fitted in the steam drum of each boiler. Superheated steam is led to
the internal superheater through valve 141B, which then allows a heat exchange
to take place between the superheated steam entering the desuperheater and the
saturated steam/water within the steam drum. Consequently the heat given up
by the previously superheated steam is recovered and no loss of energy should Illustration 2.1.2a Desuperheated Steam Systems
result. The desuperheated steam exits the internal desuperheater and is led to
the desuperheated steam system through a primary and a secondary stop valves From Main Turbine Bleeds
60kg/cm2 Steam from Boilers
145B and DS11/DS12. Both boilers feed a common range from which the LP IP HP
2.7kg/cm2 Header
To MT Glands
External Desuperheaters To TG Glands 2.7/0.1kg/cm2 PRV
To Key
To Deareator BS39 Main or Auxiliary
Two external desuperheaters are provided after the 60/9kg/cm2 reducing PIC
BS29 Condensers
Exhaust Steam
valve where the steam temperature is reduced to 190°C before supplying the PT
5205
auxiliary services. Feed water is taken from either the main or auxiliary feed Desuperheated Steam
lines, reduced in pressure at valve BF20 before being passed to the temperature To
0.1kg/cm2 Header
To
controlled feed injection valves BF48 and BF55. These valves inject feed LP FW FW Evaporator
Air
Heater Heaters
water directly into the steam pipes reducing the temperature of the steam
before it is directed to the auxiliary system. The desuperheater system is fitted Feed Water
with a recirculation orifice after the pressure reducing valve but before the feed
injection valves. This ensures that during times of low spray water demand,
there is no pressure build up in the pipework after the pressure reducing valve
which could damage the equipment.
The pressure reducing valve is provided with a bypass valve for use in an
emergency should the pressure reducing valve malfunction.
FO FO BS21
Line Line
P P P P
BS BS
BS08
P BS4244 P BS2244 P BS6244 2226 1226 P BS5244 P BS1244 P BS3244
2 2
BS07
BS BS BS To 2.7kg/cm To 2.7kg/cm BS BS BS
4209 2209 6209 BS04 System System BS03 5209 1209 3209 To
To
Atmospheric Atmospheric From Main
Drain Condenser
Drain Tank BS36
Tank
PT PI T
PTP PS PT From General PT PS PT PI PT
7323 2251 3
2323
232 2243 2242 To Atmospheric To Atmospheric 1242 1243 1323 1251 5323
Service Air Line
PAL PI ESA Drain Tank Drain Tank ESA PI PAL Ejector
Condenser TI XA
4215 5236
To 2.7kg/cm2 TIC PI
BS15 System 6217 4214
TI PI
4213 4212
PT
6123
BS51 BS17 PI
BF48 P PS
To Low To Atmospheric 0031
Drain Tank PT TI
Temperature 0123 Main Condensate
0142
9kg/cm2 BS33 BS43 PI Line
Steam Line P 0123 TT TI
0142
A further non-return valve is fitted at the 16/9kg/cm2 make-up reducing valves e) Ensure that cooling condensate is being supplied to the main air
for the same purpose. ejector (see section 2.2.1).
The bleed steam valves can also be manually operated from the main turbine f) Check that the steam to the fresh water generator air ejectors
emergency control panel, which will override control from other locations. isolating valve BS9 is shut.
g) Check that the air ejector steam inlet valves and vacuum
Operation of the High Pressure Bleed System drawing valves are all open.
The bleed valve can be opened or closed from the machinery console, but h) Gradually open the warming through valve DS46 until it is
automatic operation will normally be selected. All drain traps’ isolating valves fully open. This should take at least 30 minutes. Check that the
on the system should be opened. The 16/9kg/cm2 make-up reducing valves condenser vacuum starts to rise in this period. Check that the air
have two line isolating valves BS16 and BS20 which should be checked open ejector is operating normally.
prior to use. These valves should be left open at all times.
AS40
AS50 AS52
AS36 AS38 AS37
AS22
AS26 AS20 S.C. Lower AS54 S.C. Lower AS55 AS28 AS34 AS24
AS30 AS32 To Observation AS41 To Observation
HT3 HT4 Filter Tank Filter Tank
To Forward
Fuel Oil Tank
To Fuel Oil Heavy Fuel Oil
Line Tracing Overflow
AS18 AS12 Bunker Tank Oily Bilge Holding Dirty Oil
Lubricating Oil Diesel Oil Lubricating Oil Steam Tank
Sludge Tank Sludge Tank Renovating Tank Water Tank Tank Tank
TC
4306 To Fuel Oil
Line Tracing HT5
AS13 Steam
AS68 AS48 AS69 AS10
HT6
Key
Desuperheated Steam
AS39
Air
Electrical Signal
Overflow Heavy Fuel Oil IMO
Diesel Oil
Tank and Fuel Oil AS7 AS58 Heavy Fuel Oil AS3 AS9
Bunker Tank
Lubricating Oil TC TC
Tank 4305 4307
Spray Line from Main Feed
AS5 AS67 AS47 AS66 AS1 AS63 AS45 AS62
AS40
AS50 AS52
AS36 AS38 AS37
AS22
AS26 AS20 S.C. Lower AS54 S.C. Lower AS55 AS28 AS34 AS24
AS30 AS32 To Observation AS41 To Observation
HT3 HT4 Filter Tank Filter Tank
To Forward
Fuel Oil Tank
To Fuel Oil Heavy Fuel Oil
Line Tracing Overflow
AS18 AS12 Bunker Tank Oily Bilge Holding Dirty Oil
Lubricating Oil Diesel Oil Lubricating Oil Steam Tank
Sludge Tank Sludge Tank Renovating Tank Water Tank Tank Tank
TC
4306 To Fuel Oil
Line Tracing HT5
AS13 Steam
AS68 AS48 AS69 AS10
HT6
Key
Desuperheated Steam
AS39
Air
Electrical Signal
Overflow Heavy Fuel Oil IMO
Diesel Oil
Tank and Fuel Oil AS7 AS58 Heavy Fuel Oil AS3 AS9
Bunker Tank
Lubricating Oil TC TC
Tank 4305 4307
Spray Line from Main Feed
AS5 AS67 AS47 AS66 AS1 AS63 AS45 AS62
When sufficient drainage and warming through has taken place the system
should be at the desired pressure and temperature with the drains closed in to
allow sufficient flow to keep the system clear of water and the isolating valve
fully opened. With the isolating valve fully open, the drain valves can now be
closed.
Turbine Generator
Permanent Line Drain Permanent Line Drain BS42 BS0502
from Burner Atomising from Burner Atomising BS55
To Main Main Turbine TI XA
Condenser 4215 5236
BS11 BS1001 BS1002 Warming Through To Atmospheric
Steam Drain Tank TIC PI
Turbine Generator Gland 6217 4214
Steam System TI PI
PI PT PI PAL Condensate Cooled
To 4213 4212
2004 2003 Fresh Water
Atmospheric Generator
PT PIC SS22 BS40
2016
Drain Tank
SS23
BST26
Turbine Generator
To Main
Condenser BS38 VLV
BS10 BS2001 BS2002 5277
To
BS13 BS39 BS27 Main
PT PI
PI TT 5205 4205 Condenser
2 PIC
2.7kg/cm ZS BS49
PT TT
2484 2485 PCV 5238
E To
PIC PT PT PI PT PI PAL PAH Main BS32
1281 6128 0128 0125
BS22 BS24 BS26 BS30 Turbine
PT PIC Glands
5329 To Atmospheric To Atmospheric
To Main PI
PT PIC Drain Tank Drain Tank
Condenser PT
5204
PT 6125 TI
0125 0144
PAH
5206 PI
PI PT PI PT 0125 TT TI
PI BS33 BS43 BS31 BS44 0124 0124 6124 0144
266B P
4204
HP
BS35 BS29 Turbine
P TT TI LP BS34
9/2.7kg/cm2 Steam 0143 0143 Turbine
PRV. Dump Valve TI
BS14
Boiler
TI Air BS37 BS25
2274 To Main
Heater Condenser
269B Key
From 9kg/cm2 Steam 2.7kg/cm2 Dump steam Line Drain to To Main To Drain Chamber
System To Main or Auxiliary Main or Auxiliary Condenser LP
Exhaust Steam PT PI
Condenser Condenser Feed Water Heater 0136 0021
Air
Turbine Generator
Permanent Line Drain Permanent Line Drain BS42 BS0502
from Burner Atomising from Burner Atomising BS55
To Main Main Turbine TI XA
Condenser 4215 5236
BS11 BS1001 BS1002 Warming Through To Atmospheric
Steam Drain Tank TIC PI
Turbine Generator Gland 6217 4214
Steam System TI PI
PI PT PI PAL Condensate Cooled
To 4213 4212
2004 2003 Fresh Water
Atmospheric Generator
PT PIC SS22 BS40
2016
Drain Tank
SS23
BST26
Turbine Generator
To Main
Condenser BS38 VLV
BS10 BS2001 BS2002 5277
To
BS13 BS39 BS27 Main
PT PI
PI TT 5205 4205 Condenser
2 PIC
2.7kg/cm ZS BS49
PT TT
2484 2485 PCV 5238
E To
PIC PT PT PI PT PI PAL PAH Main BS32
1281 6128 0128 0125
BS22 BS24 BS26 BS30 Turbine
PT PIC Glands
5329 To Atmospheric To Atmospheric
To Main PI
PT PIC Drain Tank Drain Tank
Condenser PT
5204
PT 6125 TI
0125 0144
PAH
5206 PI
PI PT PI PT 0125 TT TI
PI BS33 BS43 BS31 BS44 0124 0124 6124 0144
266B P
4204
HP
BS35 BS29 Turbine
P TT TI LP BS34
9/2.7kg/cm2 Steam 0143 0143 Turbine
PRV. Dump Valve TI
BS14
Boiler
TI Air BS37 BS25
2274 To Main
Heater Condenser
269B Key
From 9kg/cm2 Steam 2.7kg/cm2 Dump steam Line Drain to To Main To Drain Chamber
System To Main or Auxiliary Main or Auxiliary Condenser LP
Exhaust Steam PT PI
Condenser Condenser Feed Water Heater 0136 0021
Air
The LP feed heater is used to boost the feed heating of the condensate prior to b) Once the turbine has reached XXX load, crack open the LP
entry into the deaerator. This helps achieve the optimum deaeration effect of bleed valve BS34. Allow a sufficient period for the pipework to
the feed water at the deaerator. The LP feed heater is fitted with a safety valve warm through.
to protect the heater in the event of an overpressurisation of the system.
c) Slowly and gradually open the bleed valve over a period of
not less than 20 minutes. Once open check that the pressure
reducing valves are compensating for the additional supply.
Turbine Generator
ES6
Astern Ahead
Valve Valve BS1002 BS1001 BS11
To Main
Condenser
ES16 ES26
POS
POS
BST BST BST
BST29
302 26 303
Gland Leak-Off Turbine Feed Water Pump Make-Up
Reservoir Leak-Off
Leak-Off
From 2.7kg/cm2
System
ES17 BST27
The main turbine manoeuvring valve outer glands and extra nozzle valve outer In the case of the HP rotor HP gland, the labyrinth is fitted with two extra
glands also drain to the gland steam leak-off reservoir. inner glands on these inner leak off points. These leak-off points are led to the HP turbine at a
valves are led to the HP/LP crossover pipe where the pressure is lower than the position where the leak off will always be drawn towards the turbine whilst
gland. From the gland leak off reservoir, the steam is drawn to the gland steam it is operating. These extra leak-off points reduce the gland pressure from full
condenser by the gland steam fan, described below. boiler pressure to a level where it is in line with the gland pressures elsewhere
in the turbine system.
Turbine Generator
ES6
Astern Ahead
Valve Valve BS1002 BS1001 BS11
To Main
Condenser
ES16 ES26
POS
POS
BST BST BST
BST29
302 26 303
Gland Leak-Off Turbine Feed Water Pump Make-Up
Reservoir Leak-Off
Leak-Off
From 2.7kg/cm2
System
ES17 BST27
The turbine generator gland sealing is supplied in a similar manner to the main The main feed pump turbine shaft glands, control valve steam glands will
turbine with desired pressure maintained in the gland packing steam receiver always be under positive pressure when operating and therefore no make-up
by make-up and spill valves. Excess pressure is dumped to the respective steam is necessary. Leak off steam is drawn away from the glands to the gland
turbine exhaust line. The reservoir is constantly drained to the exhaust line via condenser.
an orifice. The leak off from the glands, main stop valve glands and regulating
valve glands are drawn to the gland condenser.
Procedure to Put the Main Feed Pump Gland Leak-off into
Operation
Procedure to Put the Turbine Generator Gland Steam System
into Operation Prior to bringing the steam turbine driven pump gland steam system into
operation ensure that all the drain trap isolating valves are open.
Prior to bringing the generator gland steam system into operation ensure that
all the drain trap isolating valves are open, the turbine generator LO system is a) Ensure that the main condensate system is operating normally
in use and the turbine is turning on the turning gear. This procedure should be and cooling water supplied to the gland steam condenser. The
read in conjunction with the procedure for starting a turbine generator outlined gland steam condenser fan will already be running.
in section 2.11.1
b) Open the gland leak-off valves, ES16 on the port feed pump and
a) Ensure that the supply from the medium exhaust steam system ES17 on the starboard feed pump.
is available. Open all available line drains.
The gland leak-off valves should remain open during normal operating
b) Ensure that the instrument and gauge valves are open and that conditions so that the off-line feed pump is ready to start immediately.
instrument air is supplied to the control units.
The gland steam system is now operational. This system can be used to assist
warming through the turbine but is usually carried out in conjunction with the
starting up procedure for the turbine generator. This will slightly modify the
above procedure. Refer to section 2.11.1 for details of this procedure.
SV02
Silencer SV3038
Set at Set at
Silencer 78kg/cm2 SV1038 77.5kg/cm2
60/16kg/cm2
Main Boiler P.R.V.
P
To Main
Near Scupper
Steam System
71B SS1079 SS1077
73B 74B SS OD
SV1037 Set at
1078 01
10kg/cm2
SV01
Deaerator 141B
To Desuperheater
60/9kg/cm2
P.R.V.
Near Scupper
Near Scupper
SV4038
Set at Set at
SV2038 Set at
78kg/cm2 77.5kg/cm2 5kg/cm2
From
Atmospheric Condenser Main Boiler SV03
Vents
P
To Main
Steam System
71B SS2079 SS2077
Set at 65kg/cm2 4kg/cm2
Set at Set at P.C.V.
5kg/cm2 5kg/cm2 SS2 OD
SV2037
077 02
73B 74B
SV04 SV05 Near Scupper
Superheated Steam
• Feed water economiser outlet: 1 set • Deaerator safety valve (set at 3.8kg/cm2)
• Steam drum shell: 2 sets • 16kg/cm2 range safety valve
• Superheated steam outlet: 1 set • 9kg/cm2 range safety valve
• 4kg/cm2 range safety valve
The valves are the full bore type which open fully at the set pressure. This
• Main dump desuperheater safety valves
is achieved by the design of the valve disc allowing steam to leak past the
seat into a steam collecting chamber when the set pressure is reached. This
The vents from the atmospheric condenser are also led into one of the waste
rapidly increases the lifting force on the spring and lifts the disc clear of the
pipes from the system safety valves. Waste pipelines are constructed in a
seat. The superheated steam outlet safety valves open at a lower pressure than
similar manner to the boiler safety valve waste pipes.
the steam drum safety valves, thereby maintaining a steam flow through the
superheater tubes in the furnace when the boiler reaches the safety valves
There are two waste pipes for the steam systems each receiving three of the
opening pressure.
above exhausts.
The economiser feed safety valves are described in section 2.2.3.
Illustrations
CW48
PI Exhaust Steam
4242 Grease
PD
4245
Make-Up Extractor
Valve CW31
From Feed Water SC
CW57 Analysis System Sample
P 3341
SAH
CW46 CW30 CW61 CW29
VLV
ESLD LIC 5273 Atmospheric
CW26 Condenser
LAL CW25 CW24 CW23
CW18 CW27 CW20
TT TI PS
0161 TT
LAH 5219 4210 5236
PI PI 5216
CW22 4219 4220
CW87 CW19 Changeover
CW66 SC
LT AOC VOI VCI
PI CW CW LIC 4341
0161
4224
CW3 CW93 CW8 86 85 5209 Sample CW
P SAH 11 PI PI
IS IS Low Duty Condensate TI TI
4226 4229
59 64 Pump (30m3/hour) 0042 0041
CW88 CWT56 CW21
LS PI PI Atmospheric LAH
4215 4217
CW94 Drain Tank CW12 CW15
Gland TI (7m3)
5235
PI PI
LSB LSH Dump Steam Box Condenser 4209 LS 4227 4230
0161 Main CW5 CW92 CW7 Pump Start 5208
Condenser CW Main Condensate LI
LSC IS IS
65 9 63 Pumps (100m3/hour) LS
4208
Pump Stop CW13 CW16
5207 PI PI
IS61 IS LT 4228 4231
LI PI IS PI SC TI TT LAL
TI TT IS CW 62 75 4221 5214
5233
4216 4218 1341
0161
1461 1461 60 10 PT
5208
Sample SAH 5215 CW95 CW14 CW17
CW68 CW4 CW91 CW6 CW
Overflow 90 Drain Drain Tank Extraction Pumps
CW67 CW58 (42m3/hour)
CW48
PI Exhaust Steam
4242 Grease
PD
4245
Make-Up Extractor
Valve CW31
From Feed Water SC
CW57 Analysis System Sample
P 3341
SAH
CW46 CW30 CW61 CW29
VLV
ESLD LIC 5273 Atmospheric
CW26 Condenser
LAL CW25 CW24 CW23
CW18 CW27 CW20
TT TI PS
0161 TT
LAH 5219 4210 5236
PI PI 5216
CW22 4219 4220
CW87 CW19 Changeover
CW66 SC
LT AOC VOI VCI
PI CW CW LIC 4341
0161
4224
CW3 CW93 CW8 86 85 5209 Sample CW
P SAH 11 PI PI
IS IS Low Duty Condensate TI TI
4226 4229
59 64 Pump (30m3/hour) 0042 0041
CW88 CWT56 CW21
LS PI PI Atmospheric LAH
4215 4217
CW94 Drain Tank CW12 CW15
Gland TI (7m3)
5235
PI PI
LSB LSH Dump Steam Box Condenser 4209 LS 4227 4230
0161 Main CW5 CW92 CW7 Pump Start 5208
Condenser CW Main Condensate LI
LSC IS IS
65 9 63 Pumps (100m3/hour) LS
4208
Pump Stop CW13 CW16
5207 PI PI
IS61 IS LT 4228 4231
LI PI IS PI SC TI TT LAL
TI TT IS CW 62 75 4221 5214
5233
4216 4218 1341
0161
1461 1461 60 10 PT
5208
Sample SAH 5215 CW95 CW14 CW17
CW68 CW4 CW91 CW6 CW
Overflow 90 Drain Drain Tank Extraction Pumps
CW67 CW58 (42m3/hour)
CW48
PI Exhaust Steam
4242 Grease
PD
4245
Make-Up Extractor
Valve CW31
From Feed Water SC
CW57 Analysis System Sample
P 3341
SAH
CW46 CW30 CW61 CW29
VLV
ESLD LIC 5273 Atmospheric
CW26 Condenser
LAL CW25 CW24 CW23
CW18 CW27 CW20
TT TI PS
0161 TT
LAH 5219 4210 5236
PI PI 5216
CW22 4219 4220
CW87 CW19 Changeover
CW66 SC
LT AOC VOI VCI
PI CW CW LIC 4341
0161
4224
CW3 CW93 CW8 86 85 5209 Sample CW
P SAH 11 PI PI
IS IS Low Duty Condensate TI TI
4226 4229
59 64 Pump (30m3/hour) 0042 0041
CW88 CWT56 CW21
LS PI PI Atmospheric LAH
4215 4217
CW94 Drain Tank CW12 CW15
Gland TI (7m3)
5235
PI PI
LSB LSH Dump Steam Box Condenser 4209 LS 4227 4230
0161 Main CW5 CW92 CW7 Pump Start 5208
Condenser CW Main Condensate LI
LSC IS IS
65 9 63 Pumps (100m3/hour) LS
4208
Pump Stop CW13 CW16
5207 PI PI
IS61 IS LT 4228 4231
LI PI IS PI SC TI TT LAL
TI TT IS CW 62 75 4221 5214
5233
4216 4218 1341
0161
1461 1461 60 10 PT
5208
Sample SAH 5215 CW95 CW14 CW17
CW68 CW4 CW91 CW6 CW
Overflow 90 Drain Drain Tank Extraction Pumps
CW67 CW58 (42m3/hour)
The distilled water tanks can be discharged overboard through drain valves Each process line will be in use for approximately 24 hours. Once the process
Operation
which are fitted with spectacle blanks. These would only be used if the tanks line has been in use for this period, it is automatically shut down and the
were contaminated or if the tanks had been undergoing maintenance and standby line will commence operation. The newly shut down process line will The valves are pneumatic in operation and the process, once commissioned, is
required flushing. Each tank has a sample valve to allow tests to be carried then undergo a regeneration cycle. automatic. The deioniser unit is in constant use whilst the condensate system
out. is operating and is only ever bypassed as an emergency measure.
During the regeneration cycle, the cation bottle is flushed through with a 5%
The supply line to the condensate system has a branch which supplies the cold solution of hydrochloric acid (HCL) which reactivates and cleans the resin. This could be achieved by handjacking the deioniser spill valve CW46 and
start feed pump. This connection is only used during the flashing up from cold The flushing sequence is controlled by the system controller which operates closing the deioniser outlet valve CW51. However, to do this is to short circuit
procedure outlined in section 1.2 To Prepare Main Plant for Operation (Raising the hydraulically actuated directional valves fitted to the top of the resin the spill function of the condensate system leaving the system unable to spill
Steam). bottles. The internal piston valve inside this unit directs the flushing water flow excess water as it would immediately return to the system through this valve.
through washing, normal and chemical draw cycles, drawing the HCL solution Therefore this action should only be considered in an extreme case and only
The distilled water is passed through a deioniser unit prior to supply to from its storage drum located within the deioniser unit. as a short term measure.
the condensate system. The outlet from the deioniser unit is fitted with a
recirculation valve which opens if the make up valve should close. In this way The sequence of the washing cycles is controlled by the control unit. Waste Once the system has been activated, the duty pump should be selected using
the deioniser unit can run continuously whether the condensate system is in solution is disposed of through an electrically operated dump valve which the selector switch on the control panel and the duty process line should be
make-up or spill mode. dumps the water to the neutralising and washimng tank. This dump valve is similarly selected. The system will then operate entirely automatically with
also operated by the controller during normal operation to dump processed the only operator interaction being monitoring of measured values/alarms,
The spill line joins the recirculation line from the deioniser unit thus any excess water which does not fall below the set limits. refilling of regeneration chemical tanks and the occasional replacement of
water will return to the distilled water tanks. resin bottles.
The anion regeneration cycle is identical to the cation cycle, save that the
chemical used is a 6% solution of sodium hypochlorite (NaOH). It is important The outlet conductivity level alarm value should be set to 1µS with the unit in
Ion Exchange Unit that the levels of chemicals are topped up between regeneration cycles as the full operation.
storage drums only hold enough solution for one regeneration cycle.
Maker: Peter Taboada Technologia
Type: C/319 Preparation of the Main and Auxiliary Condensate Systems
Over time, the resins will lose their effectiveness and will have to be replaced.
Capacity: 2.0m3/hour The replacement of these resins and disposal/storage of waste/replacement for Use
products is a specialist subject and the manufacturers guidelines should be
strictly adhered to during these processes. The following procedure covers preparation of the systems prior to and during
The deioniser unit consists of two identical process lines of ion exchange lighting of the boilers. The auxiliary system is to be prepared first as this will
units. One of the process lines will be in use whilst the other is regenerating, be used to fill the boilers. During the first stages of starting the plant, the
providing continuous operation. There are two supply pumps which can supply The control unit houses all necessary functions to provide the deioniser unit
with fully automatic operation. The control unit has a programmable controller exhaust steam and drains normally led to the main condenser will be led to the
water to either process line through a 1 micron filter. Water is drawn from the auxiliary condenser and to the atmospheric drains tank.
in-line distilled tank through a dedicated line, treated and then delivered into fitted which is pre-programmed to control the various functions of the deioniser
the make-up line to the atmospheric drain tank. Should the rate of delivery unit, such as regeneration cycles et. This unit is set up at installation and should
not be interfered with without reference to the manufacturer’s manual. a) Ensure that the instrument and gauge valves are open and that
exceed the make-up required to the atmospheric drain tank, then the water is instrument air is supplied to the control units.
spilled back to the distilled tank thus ensuring good distribution of the treated
water. The control unit also has the following functions/equipment:
b) Check that all services and bypass valves on the condensate
• Inlet and outlet water quality meters system are shut.
The process lines both consist of three resin ionic exchange units. The first
unit is a cation unit which attracts and retains any metallic ions in the water. • Flow meter
c) Fill the atmospheric drains tank from one of the distilled water
The second unit is a anion unit which attracts and retains any non-metallic • Process line regeneration selector switches/indication tanks. Set the system valves as follows:
minerals. The third unit is a mixed bed of both anions and cation resins. Since
• Pump failure alarms/selector switch
the water reaching the third unit will already be of very high quality, it is not
necessary to use this unit unless the performance of the unit is in some way • Feed pressure low/high alarms Position Description Valve
suspect or if a part of the process line is undergoing maintenance and the other • Mains isolator switch Open Distilled water tank suction CW43 or CW44 or CW45
process line is unavailable.
Closed Cold start feed water pump BF33
CW48
PI Exhaust Steam
4242 Grease
PD
4245
Make-Up Extractor
Valve CW31
From Feed Water SC
CW57 Analysis System Sample
P 3341
SAH
CW46 CW30 CW61 CW29
VLV
ESLD LIC 5273 Atmospheric
CW26 Condenser
LAL CW25 CW24 CW23
CW18 CW27 CW20
TT TI PS
0161 TT
LAH 5219 4210 5236
PI PI 5216
CW22 4219 4220
CW87 CW19 Changeover
CW66 SC
LT AOC VOI VCI
PI CW CW LIC 4341
0161
4224
CW3 CW93 CW8 86 85 5209 Sample CW
P SAH 11 PI PI
IS IS Low Duty Condensate TI TI
4226 4229
59 64 Pump (30m3/hour) 0042 0041
CW88 CWT56 CW21
LS PI PI Atmospheric LAH
4215 4217
CW94 Drain Tank CW12 CW15
Gland TI (7m3)
5235
PI PI
LSB LSH Dump Steam Box Condenser 4209 LS 4227 4230
0161 Main CW5 CW92 CW7 Pump Start 5208
Condenser CW Main Condensate LI
LSC IS IS
65 9 63 Pumps (100m3/hour) LS
4208
Pump Stop CW13 CW16
5207 PI PI
IS61 IS LT 4228 4231
LI PI IS PI SC TI TT LAL
TI TT IS CW 62 75 4221 5214
5233
4216 4218 1341
0161
1461 1461 60 10 PT
5208
Sample SAH 5215 CW95 CW14 CW17
CW68 CW4 CW91 CW6 CW
Overflow 90 Drain Drain Tank Extraction Pumps
CW67 CW58 (42m3/hour)
CW48
PI Exhaust Steam
4242 Grease
PD
4245
Make-Up Extractor
Valve CW31
From Feed Water SC
CW57 Analysis System Sample
P 3341
SAH
CW46 CW30 CW61 CW29
VLV
ESLD LIC 5273 Atmospheric
CW26 Condenser
LAL CW25 CW24 CW23
CW18 CW27 CW20
TT TI PS
0161 TT
LAH 5219 4210 5236
PI PI 5216
CW22 4219 4220
CW87 CW19 Changeover
CW66 SC
LT AOC VOI VCI
PI CW CW LIC 4341
0161
4224
CW3 CW93 CW8 86 85 5209 Sample CW
P SAH 11 PI PI
IS IS Low Duty Condensate TI TI
4226 4229
59 64 Pump (30m3/hour) 0042 0041
CW88 CWT56 CW21
LS PI PI Atmospheric LAH
4215 4217
CW94 Drain Tank CW12 CW15
Gland TI (7m3)
5235
PI PI
LSB LSH Dump Steam Box Condenser 4209 LS 4227 4230
0161 Main CW5 CW92 CW7 Pump Start 5208
Condenser CW Main Condensate LI
LSC IS IS
65 9 63 Pumps (100m3/hour) LS
4208
Pump Stop CW13 CW16
5207 PI PI
IS61 IS LT 4228 4231
LI PI IS PI SC TI TT LAL
TI TT IS CW 62 75 4221 5214
5233
4216 4218 1341
0161
1461 1461 60 10 PT
5208
Sample SAH 5215 CW95 CW14 CW17
CW68 CW4 CW91 CW6 CW
Overflow 90 Drain Drain Tank Extraction Pumps
CW67 CW58 (42m3/hour)
Open No.1 and No.2 main feed water pump j) Allow the main turbine and condenser to cool down before
mechanical seal cooling/flushing stopping the main sea water circulating pump.
control valve inlet and outlet valves V12 (x4)
Open No.1 and No.2 main feed water pump k) Isolate the condensate recirculation valve CW24 and the astern
mechanical seal cooling/flushing cooling spray valve CW156.
control valve bypass valves CW52, CW53
l) Stop the main sea water circulating pump, jack and lock the
Operational No.1 and No.2 main feed water pump
main condenser inlet and overboard valves.
mechanical seal cooling/flushing
control valves V8 (x2)
m) Stop the condensate extraction pumps and ensure that the
Closed No.1 and No.2 main feed water pump condenser does not start to fill up.
mechanical seal cooling/flushing
outlet line vents IS82, IS83 n) Once the sea water side has been completely drained, it is
possible to proceed with the slow and careful removal of the
waterbox access plates.
Procedure to Shut Down the Main Condenser If checking for leaking tubes, it is possible to leave the air ejector operating
on and use cling film on the tube plate to locate the damaged tube. This check
a) Start the auxiliary sea water circulating pump and circulate the can also be done the conventional way, by filling the condensate side with a
atmospheric condenser. water/fluorescein mixture and checking the tube plate with a fluorescent lamp
from the sea water side.
b) Reduce electrical load on the turbine generator to a minimum
and transfer the load to either: When using a water/fluorescein mixture, the condenser must be thoroughly
rinsed out before returning to service, in order not to contaminate the boilers.
• The remaining turbine generator set up to run with the exhaust
running to the atmospheric condenser (Note: Before entering the sea water side of the condenser, open the doors and
or use a portable fan to aerate the chamber, leaving the forced ventilation
in place during the time that personnel are inside.)
• The diesel generator
(Note: If the intention is to enter the steam side of the condenser, it must be
c) Shut down the off-load turbine generator.
remembered that in several steam lines to the condenser there is only
single valve separation, depending on the method of condenser shut
d) Change the main dump steam over to the auxiliary condenser
down.)
and shut down the main dump steam system.
f) Stop the main engine, shut the steam stop valves, engage
the turning gear and do not put on the main turbine warming
through steam.
BF27
BF1013
Main Boiler Desuperheater
BF BF ZS
E BF1020 TI
1064 1065 BF58 BF57 BF56
4113
BF1026
TT
FT BF1001 BF50 5114
From Distilled Water Tanks
1030 ZS
BF61 BF60 BF59 SC SAH
BF1029 BF25
BF1011 2341
BF52
BF49 BF34
From Hydrazine Injection Unit
PAL PI PT
PT TI
0034
6034 4114 ZS ZS ZS
BF68
PI BF33 BF15 BF3 BF2 BF1
0028 PI PI
BF BF To Seal Control To Seal Control
1004 2004
32 31 BF64 BF63 BF62 PDI Valve Valve
Protection 4117
PI PI PI PI
Ring BF2029
4109 4107 1005 2005
FT
2030
E E T T
BF67 BF66 BF65 BF2001
BF2011 Cold Start Feed Electric Feed Turbine Feed Turbine Feed
BF2026 Water Pump Water Pump Water Pump Water Pump
PI
ZS
E BF2020 4110 PI PIC PS PIC PS
BF2013
4108 1009 1008 2009 2008
PIC
BF14 5108 PI PI
1006 2006
BF2008 BF17 BF18
BF BF BF2007 BF16
2064 2065 TT BF30
5136 BF37 BF36
TI BF29
4116 BF2003 BF41 BF42
BF2012 BF2004 BF Economiser BF43 BF44 BF45 BF46
2021
BF BF
2061 2062 BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Main Boiler Key
BF47 Feed Water
BF BF To Sample Cooler Instrumentation
2006 2005
Desuperheater Steam
10 22 21 21 22 22
1 18 22 12 13 14 15 16 12 17
2
20
6
3
9
4 19
Key
13 - 1st Stage Impeller
7 8 1 - Governor
6 10 16 - Balance Piston
4 - Hydraulic Servomotor
17 - Thrust Collar
5 - Valve Spindle
18 - Coupling
6 - Overspeed Weight
19 - Extra Nozzle
7 - Overspeed Trip Lever
5 20 - Turbine Rotor
8 - Hand Trip Lever
9
21 - Labyrinth Gland
4 9 - Main Gear LO Pump
22 - Bearings
10 - Governor Drive Shaft Worm Gear
12 - Cooling/Sealing Box
+ - Press Switch
Close
Press Switch
To Turbine For High Back For High Back
Nozzle Pressure Trip Pressure Trip
Plug Plug
Pressure Oil From Transmitter For Tachometer Pressure Oil From Transmitter For Tachometer
Main Lubricating Oil Line (1.0 - 1.5kg/cm2) Main Lubricating Oil Line (1.0 - 1.5kg/cm2)
BF27
BF1013
Main Boiler Desuperheater
BF BF ZS
E BF1020 TI
1064 1065 BF58 BF57 BF56
4113
BF1026
TT
FT BF1001 BF50 5114
From Distilled Water Tanks
1030 ZS
BF61 BF60 BF59 SC SAH
BF1029 BF25
BF1011 2341
BF52
BF49 BF34
From Hydrazine Injection Unit
PAL PI PT
PT TI
0034
6034 4114 ZS ZS ZS
BF68
PI BF33 BF15 BF3 BF2 BF1
0028 PI PI
BF BF To Seal Control To Seal Control
1004 2004
32 31 BF64 BF63 BF62 PDI Valve Valve
Protection 4117
PI PI PI PI
Ring BF2029
4109 4107 1005 2005
FT
2030
E E T T
BF67 BF66 BF65 BF2001
BF2011 Cold Start Feed Electric Feed Turbine Feed Turbine Feed
BF2026 Water Pump Water Pump Water Pump Water Pump
PI
ZS
E BF2020 4110 PI PIC PS PIC PS
BF2013
4108 1009 1008 2009 2008
PIC
BF14 5108 PI PI
1006 2006
BF2008 BF17 BF18
BF BF BF2007 BF16
2064 2065 TT BF30
5136 BF37 BF36
TI BF29
4116 BF2003 BF41 BF42
BF2012 BF2004 BF Economiser BF43 BF44 BF45 BF46
2021
BF BF
2061 2062 BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Main Boiler Key
BF47 Feed Water
BF BF To Sample Cooler Instrumentation
2006 2005
Desuperheater Steam
SC
6302
SAH From Evaporator
Feed Water Heater
SC60 E
P
SC2 BS34
Turbine Feed Water Pump 2.7kg/cm2 SC
SC4 6303
Steam
E H.P. SAH
Turbine SC20 SC
P 6304
P SAH
SC6 P
SC15
Main Condenser SC19 P
From Evaporator
P Ejector Condenser
SC16
P
To Main Air Ejector
To Exhaust Steam
Dump Valve
SC36 P
Gland
SC48 Condenser
P
SC37
Purge Steam
P 16/9kg/cm2
SC55
2.7kg/cm2
SC38 Atomising E SC17
Steam 294B
SC56
SC18
363B
SC62 2
9kg/cm
Boiler 365B 365B 60/9kg/cm2
P System
SC51 Inert Gas Room Atmospheric
Steam Air Heater
DS2285 Drain Tank
2
Soot Blower Steam Header Low 2.7kg/cm
Temperature Main Dump Valves System
BS17 Auxiliary Steam From P
SC52 Boiler SC50
• Evaporator drains The combined gland steam condenser/air ejector unit has two drains which are
• LP feed heater led to different destinations. In line with air ejector practice , the first stage air
ejector drains are led directly to the main condenser and the final stage drains
• Inert gas system are led to the atmospheric drain tank. Neither drain has an isolating valve. The
design of the pipework is such that in the event of a sudden loss of ejector
Many of the drains (although not all) are fitted with drain traps. In order to steam, it is impossible for water to be drawn back through the pipework to the
obtain maximum benefit from steam as a heating medium it is allowed to main condenser.
condense in the steam service as this recovers the latent heat of evaporation in
the steam. Drain traps are fitted at the outlets from such heating coils so that Casing drains on the HP turbine are led through orifice plates to the main
only water is allowed to pass. Some drain traps are fitted with bypass valves to condenser. These drains are controlled by pneumatically operated valves
provide continued service should the drain trap malfunction. Others are fitted which are controlled via the IAS. Other drains from around the turbines are led
with drains to bilge. These services are the high pressure services, where direct directly to the main condenser via orifice plates to provide permanent drainage.
supply to the atmospheric drains tank through a bypass is inadvisable, but A drain trap is fitted to the high pressure bleed line which is led to the main
guaranteed service is essential. Low priority drains where other drain traps are condenser to deal with the larger potential volume of drains that will collect in
available elsewhere in the line have no bypass at all. this relatively large bore pipe.
After passing the drains trap, the drains from the two steam air heaters are The sootblower system line drains are led directly to the bilge. This is due to
both directed to the LP feed heater, where they are used to maintain a level in the intermittent and limited nature of the use of this system and the possibility
the unit. Due to the large volume of drains which are produced by the LP feed of solid contaminants such as rust or carbon entering the feed system.
heater when operating on the 0.1kg/cm2 system, a level control valve is used in
preference to a drains trap. A level is maintained in the unit to guarantee that no
steam passes directly into the drains lines. The drain water from the steam air
heaters is used to guarantee this level during periods where the LP feed heater
is not in use. The steam air heater drains can be bypassed around the LP feed
water heater during periods when the feed heater is not in use. The level control
valve also has a bypass valve for use in emergencies.
Drains from the LP feed heater can be directed to either the main condenser
or the atmospheric drains tank. Pneumatically operated valves SC19 and SC20
are used to control which of the two destinations is in use. These valves are
controlled from IAS and are normally set to the atmospheric drains tank. Two
further line valves are fitted, one valve SC15 at the main condenser and one
valve SC17 at the atmospheric drains tank. Valve SC17 is a non-return valve
to prevent water from the atmospheric drains tank being drawn backwards to
the main condenser.
De-Oiler
CD20 CD21
PI
CD24 CD25 Fuel Oil 4405 CD53
Bunker Tank
IMO
Tank
CD22
CD54 CD55 CD46 CD47 CD48
CD28
CD23 CD63
De-Oiler
CD20 CD21
PI
CD24 CD25 Fuel Oil 4405 CD53
Bunker Tank
IMO
Tank
CD22
CD54 CD55 CD46 CD47 CD48
CD28
CD23 CD63
(Note: Chemicals are not to be used in cleaning the deoiler as they will
prohibit the coalescing of the oil.)
a) Open the deoiler bypass valve CD54 and close the inlet valve
CD53 and discharge valve SSK9.
b) Close all the valves on the deoiler including oil gauge valves,
air vent cocks and outlet valves.
c) Open the back washing steam valves AS23 and AS25 to the
deoiler.
e) Repeat the process in d) for the 2nd and 3rd stages. Close the
valve when the discharge is clean.
f) On completion of the 3rd stage back wash, open the air vent
cock and drain valve on each stage element and close the steam
inlet valves AS23 and AS25.
h) Open the discharge valve SSK9 and close the bypass valve
CD54.
Illustrations
Deck
TT TI PT TT PS
0132 0131 5016 5107 5106
CS19 CS13 CS31 CS32 H
CS18
TI Msin Condenser TI
Lubricating Oil Backflushing Return 0132 0131
Coolers to Ballast System H
BB60 BB33 Backflushing Supply
from Ballast System CS78
CS28 CS26 H
TI TI CS77
0161 0163 CS70
PI PI
Sawdust 4023 4024
From H Atmospheric H
Injector
Ballast Condenser
Pump CS23 CS17
TI TI TI TI
0162 0164 CS69 4109 4110
To
CS29 CS30 Reciprocating To Sea Water To Sea Water To Sea Water
From Sea Water Bilge Pump Cooling Pump Cooling Pump Cooling Pump
PI Cooling Pumps
5015
H PI
5007
Key To Fresh Water To Fresh Water
CS14 Generator Pump Generator Pump
H CS12 H CS11 H CS10 H CS15
Sea Water
PI PI PI PI
4008 4010 4012 4022
Main Main Main Steam Circulating
Circulating Circulating Circulating Auxiliary
E Pump E Pump E Pump E Pump
(8000m3/h (8000m3/h (8000m3/h Electrical Signal (600m3/h
PI 5mth) PI 5mth) PI 5mth) PI 2.5 bar)
4007 4009 4011 4021
Instrumentation
CS16
H
CS8 CS7 H
CS48 To
H
To Fire Fighting/
Bilge Pump
VA25 Steam H VA64
High Sea Chest To Ballast Pump High Sea Chest
CS62 CS2
To Inert Gas To Sea Water
VA24 Cooling Pump Cooling Pump VA63
To
Spray To Fire Fighting Steam
Starboard H H H Pump Jockey Pump Port
Low Sea Chest Low Sea Chest
TT PI
5001 5002
H P H
Deck
TT TI PT TT PS
0132 0131 5016 5107 5106
CS19 CS13 CS31 CS32 H
CS18
TI Msin Condenser TI
Lubricating Oil Backflushing Return 0132 0131
Coolers to Ballast System H
BB60 BB33 Backflushing Supply
from Ballast System CS78
CS28 CS26 H
TI TI CS77
0161 0163 CS70
PI PI
Sawdust 4023 4024
From H Atmospheric H
Injector
Ballast Condenser
Pump CS23 CS17
TI TI TI TI
0162 0164 CS69 4109 4110
To
CS29 CS30 Reciprocating To Sea Water To Sea Water To Sea Water
From Sea Water Bilge Pump Cooling Pump Cooling Pump Cooling Pump
PI Cooling Pumps
5015
H PI
5007
Key To Fresh Water To Fresh Water
CS14 Generator Pump Generator Pump
H CS12 H CS11 H CS10 H CS15
Sea Water
PI PI PI PI
4008 4010 4012 4022
Main Main Main Steam Circulating
Circulating Circulating Circulating Auxiliary
E Pump E Pump E Pump E Pump
(8000m3/h (8000m3/h (8000m3/h Electrical Signal (600m3/h
PI 5mth) PI 5mth) PI 5mth) PI 2.5 bar)
4007 4009 4011 4021
Instrumentation
CS16
H
CS8 CS7 H
CS48 To
H
To Fire Fighting/
Bilge Pump
VA25 Steam H VA64
High Sea Chest To Ballast Pump High Sea Chest
CS62 CS2
To Inert Gas To Sea Water
VA24 Cooling Pump Cooling Pump VA63
To
Spray To Fire Fighting Steam
Starboard H H H Pump Jockey Pump Port
Low Sea Chest Low Sea Chest
TT PI
5001 5002
H P H
Deck
TT TI PT TT PS
0132 0131 5016 5107 5106
CS19 CS13 CS31 CS32 H
CS18
TI Msin Condenser TI
Lubricating Oil Backflushing Return 0132 0131
Coolers to Ballast System H
BB60 BB33 Backflushing Supply
from Ballast System CS78
CS28 CS26 H
TI TI CS77
0161 0163 CS70
PI PI
Sawdust 4023 4024
From H Atmospheric H
Injector
Ballast Condenser
Pump CS23 CS17
TI TI TI TI
0162 0164 CS69 4109 4110
To
CS29 CS30 Reciprocating To Sea Water To Sea Water To Sea Water
From Sea Water Bilge Pump Cooling Pump Cooling Pump Cooling Pump
PI Cooling Pumps
5015
H PI
5007
Key To Fresh Water To Fresh Water
CS14 Generator Pump Generator Pump
H CS12 H CS11 H CS10 H CS15
Sea Water
PI PI PI PI
4008 4010 4012 4022
Main Main Main Steam Circulating
Circulating Circulating Circulating Auxiliary
E Pump E Pump E Pump E Pump
(8000m3/h (8000m3/h (8000m3/h Electrical Signal (600m3/h
PI 5mth) PI 5mth) PI 5mth) PI 2.5 bar)
4007 4009 4011 4021
Instrumentation
CS16
H
CS8 CS7 H
CS48 To
H
To Fire Fighting/
Bilge Pump
VA25 Steam H VA64
High Sea Chest To Ballast Pump High Sea Chest
CS62 CS2
To Inert Gas To Sea Water
VA24 Cooling Pump Cooling Pump VA63
To
Spray To Fire Fighting Steam
Starboard H H H Pump Jockey Pump Port
Low Sea Chest Low Sea Chest
TT PI
5001 5002
H P H
Deck
TT TI PT TT PS
0132 0131 5016 5107 5106
CS19 CS13 CS31 CS32 H
CS18
TI Msin Condenser TI
Lubricating Oil Backflushing Return 0132 0131
Coolers to Ballast System H
BB60 BB33 Backflushing Supply
from Ballast System CS78
CS28 CS26 H
TI TI CS77
0161 0163 CS70
PI PI
Sawdust 4023 4024
From H Atmospheric H
Injector
Ballast Condenser
Pump CS23 CS17
TI TI TI TI
0162 0164 CS69 4109 4110
To
CS29 CS30 Reciprocating To Sea Water To Sea Water To Sea Water
From Sea Water Bilge Pump Cooling Pump Cooling Pump Cooling Pump
PI Cooling Pumps
5015
H PI
5007
Key To Fresh Water To Fresh Water
CS14 Generator Pump Generator Pump
H CS12 H CS11 H CS10 H CS15
Sea Water
PI PI PI PI
4008 4010 4012 4022
Main Main Main Steam Circulating
Circulating Circulating Circulating Auxiliary
E Pump E Pump E Pump E Pump
(8000m3/h (8000m3/h (8000m3/h Electrical Signal (600m3/h
PI 5mth) PI 5mth) PI 5mth) PI 2.5 bar)
4007 4009 4011 4021
Instrumentation
CS16
H
CS8 CS7 H
CS48 To
H
To Fire Fighting/
Bilge Pump
VA25 Steam H VA64
High Sea Chest To Ballast Pump High Sea Chest
CS62 CS2
To Inert Gas To Sea Water
VA24 Cooling Pump Cooling Pump VA63
To
Spray To Fire Fighting Steam
Starboard H H H Pump Jockey Pump Port
Low Sea Chest Low Sea Chest
TT PI
5001 5002
H P H
H CS3 H CS4
TI TI TI TI
4102 4104 4106 4108
TI TI TI TI
4101 4103 4105 4107
PT PT
5005 5006
Key
To Saw Dust CS72
Injector
Sea Water
Steam
CS53 CS52 CS45 CS44
Electrical Signal
PI PI PI PI
4004 4002 4007 4014
Cargo Cargo Machinery Machinery Instrumentation
Sea Water Sea Water Sea Water Sea Water
E Cooling E Cooling E Cooling E Cooling
Pump Pump Pump Pump
PI (650m3/h PI (650m3/h PI (100m3/h PI (100m3/h
4003 2 bar) 4001 2 bar) 4015 2 bar) 4013 2 bar)
VA24 VA63
To To Fire Fighting
Spray Jockey Steam
Starboard H H H Pump Pump
Low Sea Chest Port
TT PI Low Sea Chest
5001 5002
H P H
SW PUMP FOR FW COOLER FOR DECK HYD EQUIP?? c) Set the valves as in the following table. b) Ensure that all instrumentation root valves are open and that all
Introduction instruments are operating correctly.
Position Description Valve
The central cooling sea water system comprises two independent but c) Set the valves as in the following table.
interconnected cooling systems, one for the machinery in the engine room Open Line suction valve from sea water crossover main CS49
and the other for the cargo machinery; the engine room machinery system Closed Pneumatically operated suction valve from auxiliary Position Description Valve
also supplies water to the sawdust injector which is used for injecting sawdust suction main CS5
into the main condenser for leakage control. Each system has two cooling sea Open Line suction valve from sea water crossover main CS49
water pumps, one acting as the duty pump and the other acting as the standby Open No.1 machinery cooling sea water pump suction valve CS51
Closed Pneumatically operated suction valve from auxiliary
pump, and two fresh water coolers. Apart from the overboard discharge valves Open No.1 machinery cooling sea water pump discharge suction main CS5
all system valves are manually operated. The pumps for each system normally valve CS52
take suction from the sea water crossover main via manually operated valve Open No.1 cargo cooling sea water pump suction valve CS46
Open No.2 machinery cooling sea water pump suction valve CS50
CS49 but they may also take suction from the port low sea chest auxiliary main Open No.1 cargo cooling sea water pump discharge valve CS44
via valve CS5; valve CS5 is normally closed. Open No.2 machinery cooling sea water pump discharge
valve CS53
H CS3 H CS4
TI TI TI TI
4102 4104 4106 4108
TI TI TI TI
4101 4103 4105 4107
PT PT
5005 5006
Key
To Saw Dust CS72
Injector
Sea Water
Steam
CS53 CS52 CS45 CS44
Electrical Signal
PI PI PI PI
4004 4002 4007 4014
Cargo Cargo Machinery Machinery Instrumentation
Sea Water Sea Water Sea Water Sea Water
E Cooling E Cooling E Cooling E Cooling
Pump Pump Pump Pump
PI (650m3/h PI (650m3/h PI (100m3/h PI (100m3/h
4003 2 bar) 4001 2 bar) 4015 2 bar) 4013 2 bar)
VA24 VA63
To To Fire Fighting
Spray Jockey Steam
Starboard H H H Pump Pump
Low Sea Chest Port
TT PI Low Sea Chest
5001 5002
H P H
The machinery and cargo cooling sea water cooling pumps normally take d) Sawdust will be discharged from the sawdust injector into the
suction from the sea water crossover main. However, in an emergency the main sea water flow to the main condenser.
pumps may take suction from the auxiliary sea water suction main connected
to the port low sea chest. e) When the sawdust has been discharged, close the sawdust
injector outlet and inlet valves.
a) Ensure that the auxiliary sea water suction main is flooded as
described in section 2.3.1 above. f) Check the effectiveness of the sawdust sealing system.
(Note: In the event of an engine room fire the interconnection valve between Although the inert gas cooling sea water system is not strictly part of the
the fire fighting system and the sea water cooling system CS5 should central cooling sea water system, the inert gas cooling pump takes suction from
be closed from the fire control station. This provides a dedicated sea the sea water crossover main. There is one inert gas sea water cooling pump
water supply to the fire fighting pumps. If maintenance is to be carried but the inert gas cooling system may also be supplied in an emergency from the
out on the port lower sea chest filter, valve CS5 would be opened to ballast system. The pump can be started and stopped from the IAS. The pump
provide a supply to the fire fighting pumps. Under normal operations will automatically start when the IAS receives an Auto Start command from
the suction for the fire fighting system is through the sea water filter the IG control uni,t but the pump has to be stopped manually
via valve CS61 and the suction for the sea water cooling system is
made from the sea water crossover valve CS49.) a) Ensure that the sea water crossover main is flooded as described
in section 2.3.1 above.
c) The machinery and cargo cooling sea water pumps now take
suction from the auxiliary sea water main. b) Ensure that all instrumentation root valves are open and that all
instruments are operating correctly.
DF49 a TI
C
Instrumentation
C TI
TI
Electrical Signal Distillate
Distillate
Cooler
Pump Heater
Sea Water F
From
Main Condensate
System Chemical
Injection Tank
From Power From Power
Supply Supply M
SC
To Atmos.
To Main M Drain Tank
Condenser
SC
Brine
C To Bilge
Pump
To Bilge
To Bilge Overboard
From
Ejector
Steam PI
T Feed Water Heater C
a S Ejector
Condenser
TI C From
Salinity Main/Auxiliary
Indicator Condensate Pump
From Power
Discharge
Supply TI TI e
a
C C From Power
SC TIC Supply
From Heating
Distillate
Steam
Cooler C 2ND 1ST SC
M
Stage Stage
C
T
Distillate To Bilge
Chemical
Pump Chemical To Vacuum
Cleaning
Cleaning Condenser
C To Atmos. M Pump To Clean
SC Tank
Drain Tank Drain Tank
Chemical From
Injection Tank Brine Power
Pump To Bilge Supply
H
VA64
CS41 CS42 CS62 CS2 High Sea Chest
VA25 To
PI PI
To Cargo To Machinery 4018 Fresh Water 4020 Fresh Water To Fire Fighting
High Sea Chest Fresh Water Fresh Water Spray Generator Generator Jockey VA63
To Ballast Pumps To Inert E E
Coolers Coolers Pump Pump Pump Pump Steam
Steam Gas Generator (7.0m3/h (45m3/h
VA24
Cooling PI
4 bar)
PI
4 bar) Port
4017 4019
The brine which is discharged from the fresh water generators connects at a
common discharge pipe which has an overboard discharge valve. Each fresh
water generator has its own brine pump which removes the brine from the fresh
water generator and passes it to the overboard discharge line.
Illustrations
LI TI LAL
CF78 CF76 CF60 CF58 CF85 CF81 CF87 CF83 CF53 CF51 LI TI LAL LI TI LAL
4075 4079 5005 4073 4076 5004 4074 4078 5003
CF
136
TI TI TI TI TI TI TI TI TI TI
4067 4066 4071 4070 4013 4012 4017 1 4021 4020
CF97 CF95 Filling CF75 CF74 Filling CF117 CF118
Filling
Line CF79 CF77 CF61 CF59 CF86 CF82 CF88 CF84 CF52 CF50 line line
FS FS
5026 5028
N2 Compressors Accommodation Service Air Compressors Control Air Compressors Refrigeration Machinery
Air Condensers Condensers
Pre-
heater
PS TI TI
Cooler for Hydraulic TI 0460 0422 0402
Deck Machinery Sample Coolers
CF122 0452 Air Cooler PI
0451
TI CF46
4051 TI PI TT TSH
CF 4050 Oil Cooler TI 0451 0402 0402
123 0472
TI TI
4023 4022 FS TI TI
CF CF CF47 Alternator Cooler 5029 4043 4042
TI TI Turbine TI 125 124 TI
CF99 CF98 4080 4081 Generator 1003 1002
CF64 CF62
HT
CF126 TI Cooler TI
4056 4054
Oil Coolers for Feed Water Pumps Stern Tube LO
TI CF48
Drain Coolers 4053 TI TI TI
Coolers CF 4052 4045 4044
127
CF CF CF49 TI TI
T E T 4055 4057 CF65 CF63
Turbine TI 129 128 TI
TI TI TI TI TI TI TI TI TI TI Generator 2003 2002 FS
4025 4024 4029 4028 4027 4026 4031 4030 4033 4032 5030
CF CF CF CF CF CF CF CF CF CF Machinery Room
94 91 93 90 92 89 08 10 57 56 Air Condition Unit
To / From
Technical Space
Service CF55 CF54
Cargo
System
TI P Air TI P Air
4035 TAH 4039 TAH
TI CF45 TI CF28
4034 TT PI E PI 4038 TT PI E PI
CF37 5014 4001 4002 CF17 5014 4005 4006
CF32 CF119
CF27 CF12 Key
Fresh Water TI CF40 CF43 Fresh Water TI CF21 CF26
Coolers 4037 PI PI Coolers 4041 PI PI
Fresh Water Cooling Pumps 5002 6002 Fresh Water Cooling Pumps 5001 6001
TI CF38 TI CF20 Fresh Water
4036 CF36 (100m3/h 3.5 bar) 4040 (650m3/h 3 bar)
CF18
Air
PI E PI PI E PI
CF33 4003 4004 CF11 4003 4004
Electrical Signal
LI TI LAL
CF78 CF76 CF60 CF58 CF85 CF81 CF87 CF83 CF53 CF51 LI TI LAL LI TI LAL
4075 4079 5005 4073 4076 5004 4074 4078 5003
CF
136
TI TI TI TI TI TI TI TI TI TI
4067 4066 4071 4070 4013 4012 4017 1 4021 4020
CF97 CF95 Filling CF75 CF74 Filling CF117 CF118
Filling
Line CF79 CF77 CF61 CF59 CF86 CF82 CF88 CF84 CF52 CF50 line line
FS FS
5026 5028
N2 Compressors Accommodation Service Air Compressors Control Air Compressors Refrigeration Machinery
Air Condensers Condensers
Pre-
heater
PS TI TI
Cooler for Hydraulic TI 0460 0422 0402
Deck Machinery Sample Coolers
CF122 0452 Air Cooler PI
0451
TI CF46
4051 TI PI TT TSH
CF 4050 Oil Cooler TI 0451 0402 0402
123 0472
TI TI
4023 4022 FS TI TI
CF CF CF47 Alternator Cooler 5029 4043 4042
TI TI Turbine TI 125 124 TI
CF99 CF98 4080 4081 Generator 1003 1002
CF64 CF62
HT
CF126 TI Cooler TI
4056 4054
Oil Coolers for Feed Water Pumps Stern Tube LO
TI CF48
Drain Coolers 4053 TI TI TI
Coolers CF 4052 4045 4044
127
CF CF CF49 TI TI
T E T 4055 4057 CF65 CF63
Turbine TI 129 128 TI
TI TI TI TI TI TI TI TI TI TI Generator 2003 2002 FS
4025 4024 4029 4028 4027 4026 4031 4030 4033 4032 5030
CF CF CF CF CF CF CF CF CF CF Machinery Room
94 91 93 90 92 89 08 10 57 56 Air Condition Unit
To / From
Technical Space
Service CF55 CF54
Cargo
System
TI P Air TI P Air
4035 TAH 4039 TAH
TI CF45 TI CF28
4034 TT PI E PI 4038 TT PI E PI
CF37 5014 4001 4002 CF17 5014 4005 4006
CF32 CF119
CF27 CF12 Key
Fresh Water TI CF40 CF43 Fresh Water TI CF21 CF26
Coolers 4037 PI PI Coolers 4041 PI PI
Fresh Water Cooling Pumps 5002 6002 Fresh Water Cooling Pumps 5001 6001
TI CF38 TI CF20 Fresh Water
4036 CF36 (100m3/h 3.5 bar) 4040 (650m3/h 3 bar)
CF18
Air
PI E PI PI E PI
CF33 4003 4004 CF11 4003 4004
Electrical Signal
Operational Aft hydraulic deck machinery cooler outlet control valve CF99 Open No.2 turbine generator LO cooler inlet valve CF128 g) Check that water is circulating to all users and check the system
Open No.1 accommodation air conditioning unit inlet valve CF58 Open No.2 turbine generator LO cooler outlet valve CF129 for leaks as the temperature rises when the users are on line.
Operational No.1 accommodation air conditioning unit outlet Open No.1 engine room conditioning unit inlet valve CF62 h) When the system is operating correctly using the duty pump
control valve CF60 select the other pump for automatic operation to act as the
Operational No.1 engine room air conditioning unit outlet
Open No.2 accommodation air conditioning unit inlet valve CF59 control valve CF64 standby pump.
Operational No.2 accommodation air conditioning unit outlet Open No.2 engine room air conditioning unit inlet valve CF63
i) Ensure that there is an electrical power supply available at
control valve CF61
Operational No.2 engine room air conditioning unit outlet the diesel generator preheater and start the diesel generator
Open Automatic vent valve CF136 control valve CF65 preheater. Ensure that the diesel generator engine jacket water
Open No.1 service air compressor inlet valve CF81 Open Diesel generator engine LT cooling water inlet valve CF54 system temperature rises to the appropriate value. When the
jacket water temperature is at the correct value the diesel
Operational No.1 service air compressor outlet control valve CF85 Operational Diesel generator engine LT cooling water outlet generator engine may be started if required.
control valve CF55
Open No.2 service air compressor inlet valve CF82
Open Diesel generator engine LT cooling water valves j) The central fresh water cooling system is now operational.
Operational No.2 service air compressor outlet control valve CF86
Open Diesel generator engine HT cooling valves k) Test the water in the central cooling system and the generator HT
Open No.1 control air compressor inlet valve CF83
Open Diesel generator HT system expansion tank cooling system at intervals advised by the chemical treatment
Operational No.1 control air compressor outlet control valve CF87
outlet valve CF117 supplier and supply treatment chemicals to the systems as
Open No.2 control air compressor inlet valve CF84 appropriate.
Open Diesel generator HT system expansion tank float
Operational No.2 control air compressor outlet control valve CF88 filling valve line valve
(Note: Water losses from the cooling systems will be made up from the water
Open No.1 nitrogen compressor inlet valve CF76 Closed Diesel generator HT system expansion tank manual supply to the expansion tanks by way of the float operated valve.
Operational No.1 nitrogen compressor outlet control valve CF78 filling valve The expansion tanks are fitted with low level alarms which will give
Closed Diesel generator HT system expansion tank chemical warning should the automatic make-up arrangements fail.
Open No.2 nitrogen compressor inlet valve CF77
filling valve CF121
Operational No.2 nitrogen compressor outlet control valve CF79 The flow meters on the make-up lines to the header tanks will give an
Closed Diesel generator HT system expansion tank early indication of excess make-up over and above the normal system
Open No.1 refrigerating machinery inlet valve CF51 drain valve CF118 losses.)
Operational No.1 refrigerating machinery outlet control valve CF53 Open Central cooling system expansion tank outlet valve CF75
Open No.2 refrigerating machinery inlet valve CF50 Open Central cooling system expansion tank float filling
Operational No.2 refrigerating machinery outlet control valve CF52 valve line valve
Open No.1 turbine generator inlet valve CF46 Closed Central cooling system expansion tank manual
filling valve
TI PI M Low Duty
T16A P16A Compressor No.2
TI PI
FW
S
T16B P16B
Cargo Low Temperature 01 S
Key Fresh Water Expansion Tank
FW03 Low Duty
FW TI PI M
Fresh Water T16A P16A Compressor No.1
Chemical 02
Additive
Compressed Air CF96 TI PI
FW FW04
T16B P16B
12 S
FW FW17 TI PI M
LI TI LAL
High Duty
14 T16A P16A
4075 4079 5005 Compressor No.2
FW05 TI PI
FW T16B P16B
15 S
FW FW20
CF97 CF95 TI PI M High Duty
Filling 16 T16A P16A
Compressor No.1
Line
Near Scupper
FW06
TI TI
5 6
FW07
FW13
PI PT TT
4200 5031 5032 Drain Cooler
FW FW PI
4201
18 19 Vacuum Pump No.1
TI FS TI PI
T10 FSL1 T9 P7
TI TI P Air S
4034 4035 TAH
Cargo Machinery Fresh Water Cooling Pump c) Open all instrumentation root valves and ensure that the Open No.2 low duty compressor inlet valve FW02
Maker: Hamworthy KSE instruments are all working correctly. Operational No.2 low duty compressor outlet control valve FW01
No. of sets: 2 Open No.1 vacuum pump cooler inlet valve FW08
d) Set the valves as in the following table.
Type: Centrifugal Open No.1 vacuum pump cooler outlet valve FW09
Model: CGB100 V48 FAN (Note: System valves are shown as open but they will only be open when a
Operational No.1 vacuum pump solenoid valve
Capacity: 100m3/h at 3.5 bar particular system is operating.)
Open No.2 vacuum pump cooler inlet valve FW10
Motor: 16.2kW
Position Description Valve Open No.2 vacuum pump cooler outlet valve FW11
Open No.1 cargo fresh water cooling pump suction valve CF40 Operational No.1 vacuum pump solenoid valve
Introduction
Open No.1 cargo fresh water cooling pump discharge valve CF43
The cargo machinery cooling system is separate from the engine room central
cooling system. Open No.2 cargo fresh water cooling pump suction valve CF39 e) Select one cargo fresh water cooling pump as the duty pump
and start that pump manuallyand select the other pump as the
Open No.2 cargo fresh water cooling pump discharge valve CF44
The cargo machinery fresh water circulation system consists of two circulation standby pump.
pumps, one normally acting as the duty pump and the other as the standby Operational Automatic pressure regulating valve CF45
pump, and two fresh water coolers circulated with sea water, see section Operational Three-way temperature controlled valve CF32 f) Check that water is circulating to all cargo cooling system users
2.3.2 Central Sea Water Cooling System. The duty pump draws fresh water and check the system for leaks as the temperature rises when
through the cargo machinery cooling water cooler(s), in order to maintain the Closed Drain valve CF38 users are on line.
desired temperature, and circulates the fresh cooling water to the to the cargo Open No.1 cargo fresh water cooler inlet valve CF27
machinery located in the cargo machinery room. This cargo machinery consists g) When the system is operating correctly using the duty pump,
of two high duty compressors, two low duty compressors, a drain cooler, and Open No.1 cargo fresh water cooler outlet valve CF37
select the other pump for automatic operation to act as the
two vacuum pump coolers. Open No.2 cargo fresh water cooler inlet valve CF33 standby pump.
Open No.2 cargo fresh water cooler outlet valve CF36
A three-way valve at the circulation pump suction allows water flowing to h) The cargo cooling system is now operational.
the pump suction to bypass the coolers or flow through the coolers in order to Open Supply valve to cargo equipment (in passageway) FW18
maintain the desired temperature of the water circulated to the cargo machinery. Open Return valve from cargo equipment (in passageway) FW19 i) Test the water in the cargo cooling system at intervals advised
The IAS controls the three-way valve and enables a set temperature of 36°C to by the chemical treatment supplier and supply treatment
be maintained in the central cooling water supply system. Open Drain cooler inlet valve FW07 chemicals to the systems as appropriate.
Open Drain cooler outlet valve FW13
The cargo machinery fresh water circulation system is provided with an (Note: Water losses from the cooling system will be made up from the water
expansion tank which allows for thermal expansion of water in the system, Open No.1 high duty compressor inlet valve FW06 supply to the expansion tank by way of the float operated valve. The
enables make-up water to be supplied via float operated and manual valves, Operational No.1 high duty compressor outlet control valve FW20 expansion tank is fitted with low level alarms which will give warning
and provides a facility for the addition of treatment chemicals. Chemical should the automatic make-up arrangements fail.)
Open Supply line isolating valve FW16
treatment is used to minimise the risk of corrosion on the system.
Open Return line isolating valve FW15 (Note: The flow meter on the make-up line to the header tank will give an
Open No.2 high duty compressor inlet valve FW05 early indication of excess make-up over and above the normal system
Procedure for Operation of the Cargo Machinery Fresh Water losses.)
Cooling System Operational No.2 high duty compressor outlet control valve FW17
Open Supply line isolating valve FW14 (Note: The vacuum pump solenoid outlet valve will open when the vacuum
a) Ensure that the cargo machinery fresh water cooling system is pumps are started.)
fully charged with chemically treated fresh water and that air Open Return line isolating valve FW12
is vented from all parts of the system. Ensure that the cargo Open No.1 low duty compressor inlet valve FW04
machinery cooling system expansion tank is at the normal
operating level and that the float make-up valve is operational.
Illustrations
Deaerator
(30m3)
LA
Water Drum Water Drum N 2 H4 From
L Desuperheater
From Condensed 67B 68B 67B 68B
Water Pump
BF27
From Fresh
Water Cooling M
System
BF34 TI
4113
TT
LA LA
BF50 5114
L L ZS SC SAH
BF25 2341
BF52
BF49
From Distilled Water Tanks
ZS ZS ZS
Fresh Water Cooling WATER ANALYSIS EQUIPMENT BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Water BF47
To Fresh Water
Cooling System To Clean Drain Tank
Auxiliary condenser outlet: Salinity The boiler chemical injection unit consists of two tanks of 150 litres capacity
Boiler/Feed Water Analysis Unit each into which the chemicals to be dosed are mixed with distillate water
Condensate drains pump discharge: Salinity supplied from the main condensate system. The two tanks serve the two boilers
Maker: DKK-TOA Corporation using high pressure dosing pumps to inject the chemicals into the boiler steam
No. of sets: 1 Deaerator outlet: Salinity drum, through its chemical injection valves. The dosing rate is 15 litres/hour
Model: BSC3-3M-3E-3P-3C and therefore the dosage can take place over several hours rather than a
No. of sample points: 3 - feed water, port boiler and starboard boiler Main condensate pump discharge: Salinity concentrated quick dose. The chemical dosing line is common and therefore
only one boiler can be dosed at a time although the independent mixes can be
Test equipment: pH, conductivity, temperature, flow prepared in the two separate tanks. The stirring paddles and the dosing pumps
The main water analyser unit for the boilers has permanent sample lines fitted.
Rating: 220V Each sample point is led to its own independent test equipment line which can be operated from the DCS screen.
comprises the sample being led through a cooler and then to permanent test
Introduction meters. The main water analyser unit for the boilers samples the following
points:
Chemical analysis and treatment of feed water is undertaken to prevent
Port boiler water drum sample: Test for pH and conductivity
corrosion and scale formation in the main boilers and feed system and
degradation of the steam quality. Inadequate or incorrect treatment can result
Starboard boiler water drum sample: Test for pH and conductivity
in severe damage to the boilers and constant monitoring is necessary to give an
early indication of possible contamination of the feed water.
Feed pump discharge sample: Test for pH and conductivity
Deaerator
(30m3)
LA
Water Drum Water Drum N 2 H4 From
L Desuperheater
From Condensed 67B 68B 67B 68B
Water Pump
BF27
From Fresh
Water Cooling M
System
BF34 TI
4113
TT
LA LA
BF50 5114
L L ZS SC SAH
BF25 2341
BF52
BF49
From Distilled Water Tanks
ZS ZS ZS
Fresh Water Cooling WATER ANALYSIS EQUIPMENT BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Water BF47
To Fresh Water
Cooling System To Clean Drain Tank
Deaerator
(30m3)
LA
Water Drum Water Drum N 2 H4 From
L Desuperheater
From Condensed 67B 68B 67B 68B
Water Pump
BF27
From Fresh
Water Cooling M
System
BF34 TI
4113
TT
LA LA
BF50 5114
L L ZS SC SAH
BF25 2341
BF52
BF49
From Distilled Water Tanks
ZS ZS ZS
Fresh Water Cooling WATER ANALYSIS EQUIPMENT BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Water BF47
To Fresh Water
Cooling System To Clean Drain Tank
Chemicals are injected into the boiler steam drum under its water level. This The hydrazine dosing unit should be operated continuously to maintain a Boiler blowdown through the valves on the water drum or steam drum imposes
is done so the natural water circulation system within the boiler will move the constant hydrazine reserve with little fluctuation. The capacity of the tank is a considerable load on the boiler. When in port, the duty deck officer should
chemicals around the boiler and ensure an even distribution. such that a full tank will continuously dose the system for approximately three be contacted, to ensure that the discharge from the ship’s side will not be
days. The concentration of hydrazine should be varied depending upon the dangerous. The correct amount of blowdown is determined from experience
results of the tests. and through consistent testing and blowing down procedures.
Dosing Procedure
a) Fill the two sections of the dosing tank with water from the a) Open the following valves fully.
Dosing Procedure
main condensate discharge, piped to the filling valves.
a) Fill the dosing tank with water from the main condensate Position Description Valve
b) Add the chemicals to be dosed to the separate tanks, based on discharge, piped to the filling valve.
the results of the boiler tests. Start the stirring paddles and allow Open Ship’s side blowdown valves BF32/BF31
any powdered chemical to dissolve. b) Add the hydrazine to be dosed to the tank based on the results Open No.1 boiler primary blowdown valve BF1065
of the condensate and boiler tests.
c) Open the tank outlet valves, the pump’s discharge valves and Open No.2 boiler primary blowdown valve BF2065
the boiler drum chemical injection primary and secondary c) Open the tank outlet valves, the pump’s discharge valves and the Open No.1 boiler primary scumming valve BF1062
valves. Ensure that the dosing pump crossover valve and the boiler drum chemical injection primary and secondary valves.
Open No.2 boiler primary scumming valve BF2062
boiler drum chemical injection primary and secondary valves Ensure that the dosing pump crossover valve is closed. Open
on the boiler not being dosed are closed. valve BF34 on the deaerator to the main feed pumps line.
b) For blowdown or scumming, slowly crack open the secondary
d) Start the pump motor which drives both pumps simultaneously. d) Start the pump motor which drives both pumps simultaneously. valve as required, as in the following table
Both the pumps and the paddles can be started locally or from Both the pumps and the paddles can be started locally or from
the IAS. the IAS. Position Description Valve
Open No.1 boiler secondary blowdown valve BF1064
The dosing pumps will be stopped by a level switch when the tank is nearly The dosing pumps will be stopped by a level switch when the tank is nearly
empty. empty. Open No.2 boiler secondary blowdown valve BF2064
Open No.1 boiler secondary scumming valve BF1061
WARNING WARNING
Handling chemicals is a hazardous procedure and full protective clothing Handling chemicals is a hazardous procedure and full protective clothing Open No.2 boiler secondary scumming valve BF2061
must be worn at all times whilst handling these substances. must be worn at all times whilst handling these substances.
c) The blowdown/scumming line is fitted with an orifice plate
which should limit the blowdown rate, allowing the secondary
valve to be fully opened. This should be done slowly and with
due regard to the boiler load.
2.6.2 Diesel Oil Purifier and Generator Engine Diesel Oil Service System
Illustrations
2.6.2a Diesel Oil Purifier and Generator Engine Diesel Oil Service System
Bu
nk
10,000 er 10,000 10,000
Fu
e lO
il
5,000 5,000 5,000
IF
- 30
4 4 4
Maker: Azcue • The transfer pump valves are opened and the pump is started The two HFO bunker tanks incorporate an overflow tank. A drop valve is fitted
to allow the overflow tank to drain into the bunker tanks.
No. of units: 2
Type: Gear When the level in the service tank operates a high level switch the following
The forward HFO system incorporates an HFO fore deep tank located forward
sequence is activated:
Model: BT-LV125T-F of the cargo tanks and above the forward water ballast tank. The HFO fore
Capacity: 90m3/hr at 6 bar • The transfer pump is stopped deep tank is located on the vessel’s centre line. The tank is filled from the same
• The outlet valve of the selected bunker tank is closed connections as the aft HFO tanks. The forward HFO transfer pumps are used
to transfer HFO from the HFO fore deep tank to the aft HFO bunker or service
Gas Oil Transfer Pump • The service tank inlet valve is closed tanks as required. Only one pump is used at any time.
Maker: Azcue When transferring from the forward bunker tanks, one of the two transfer All valves in the DO bunkering and transfer system are manually operated
No. of units: 1 pumps is selected for automatic use and the above automatic transfer sequence except for the following which are hydraulically operated:
Type: Gear is activated.
Model: BT-HM38D2-F Valve Location
All valves in the HFO bunkering and transfer system are manually operated
Capacity: 2.5m3/hr at 6 bar except for the following which are hydraulically operated: DO01 MGO storage tank filling valve
DO02 MDO storage tank filling valve
Valve Location
Introduction
FO02 IMO HFO tank filling valve All fuel tanks, HFO, MDO and MGO are fitted with high level alarms set at
Heavy fuel oil for the boilers is stored in two HFO bunker tanks located at the 95% volume. Incorporated in the MDO and MGO storage tanks is an overflow
FO03 Port HFO bunker tank filling valve
engine room, a HFO fore deep tank located forward of the cargo tanks and an system. The MGO daily tank overflows to the MGO storage tank whilst the
IMO HFO tank also located at the engine room. These bunker tanks are filled FO04 Starboard HFO bunker tank filling valve MGO storage tank overflows to the MDO storage tank. As does the MDO daily
from any of the four bunker manifolds. High level alarms are provided and will tank. The MDO storage tank is fitted with an overflow alarm situated 300mm
FO05 Starboard HFO service tank filling valve
automatically close the filling valve to the respective tank. from the top of the tank.
FO06 Port HFO service tank filling valve
FS FS
Emergency Incinerator 5145 5155
Generator Gas Oil DO70
Diesel Oil Tank Service Tank
LT LI LT LI FO FO FO
5101 4101 5140 4112 02 03 04
Overflow Tank From Overflow Tank
Sludge
86.7m3 Pump 86.7m3
TI LT TT LAH TI LT TT LAH FO FO
4104 5116 5118 5117 4110 5134 5136 5135 05 06
FO FO
LT TT LAH LT TT LAH 21 20 LT TT LAH LSH LT TT LAH LSH LT TT LAH
5110 5112 5111 5113 5115 5114 5119 5121 5120 5125 5122 5124 5123 5131 5128 5130 5129
LI LI
4107 4109
IMO Heavy Fuel oil
Heavy Fuel oil Heavy Fuel oil Heavy Fuel oil
Heavy Fuel oil Bunker Tank
Bunker Tank Service Tank Service Tank
Tank 649.3m3 1543.5m3
1757.8m3 TC 222.5m3 TC 184.9m3
FO TI FO FO FO FO FO FO
4102
12 13 14 TI TI FO 16 TI 17 18 TI 19
4103 WD 4105 WD 4106 WD 4108
5127 15 5127 5133
FO FO FO FO FO
FO 07 TC 08 FO FO TC 27 FO 10 FO 11
50 TC 53 56 57 LSL 58 LSL
5126 5132
To Boiler
Fuel Unit To Boiler
Fuel Unit
To Boiler To Sludge
Fuel Unit Pump
GO
778
DO
51 DO01
DO LT LAH DO02
5103 5102 LT LAH LT LAH LT LAH
49 5104 5105 DO 5106 5107 5108 5109
Main Diesel Oil 52
Daily Tank Main Diesel Oil Main Gas Oil Main Gas Oil From Fuel
58.8m3 Storage Tank Storage Tank Daily Tank Oil Room
DO DO FO DO 335.2m3 DO 58.6m3 DO 58.8m3 DO DO
41 54 From Key
03 04 08 05 06 07 From Boiler
Inert Gas
FO FO DO System Fuel Unit Heavy Fuel Oil
43 47 48 DO DO Diesel/Gas Oil
33 40
To Boiler DO34 DO FO42 FO
To Inert Gas Fuel Unit 39 44
From Diesel System DO
From To Boiler Generator 30 PT
PI PI 5142 PI
Diesel Fuel Unit
4114 4116 4118
Generator To Diesel
FO C B A
Generator
28 PI PI PI
4113 4115 4117
PT
5141
LT LAH TI DO FO FO
5137 5189 4111
31 35 45
Fuel OIl
Drain Tank
From Boiler 1950 Litres
Fuel Unit DO32 DO35 DO FO46
36
FS FS
Emergency Incinerator 5145 5155
Generator Gas Oil DO70
Diesel Oil Tank Service Tank
LT LI LT LI FO FO FO
5101 4101 5140 4112 02 03 04
Overflow Tank From Overflow Tank
Sludge
86.7m3 Pump 86.7m3
TI LT TT LAH TI LT TT LAH FO FO
4104 5116 5118 5117 4110 5134 5136 5135 05 06
FO FO
LT TT LAH LT TT LAH 21 20 LT TT LAH LSH LT TT LAH LSH LT TT LAH
5110 5112 5111 5113 5115 5114 5119 5121 5120 5125 5122 5124 5123 5131 5128 5130 5129
LI LI
4107 4109
IMO Heavy Fuel oil
Heavy Fuel oil Heavy Fuel oil Heavy Fuel oil
Heavy Fuel oil Bunker Tank
Bunker Tank Service Tank Service Tank
Tank 649.3m3 1543.5m3
1757.8m3 TC 222.5m3 TC 184.9m3
FO TI FO FO FO FO FO FO
4102
12 13 14 TI TI FO 16 TI 17 18 TI 19
4103 WD 4105 WD 4106 WD 4108
5127 15 5127 5133
FO FO FO FO FO
FO 07 TC 08 FO FO TC 27 FO 10 FO 11
50 TC 53 56 57 LSL 58 LSL
5126 5132
To Boiler
Fuel Unit To Boiler
Fuel Unit
To Boiler To Sludge
Fuel Unit Pump
GO
778
DO
51 DO01
DO LT LAH DO02
5103 5102 LT LAH LT LAH LT LAH
49 5104 5105 DO 5106 5107 5108 5109
Main Diesel Oil 52
Daily Tank Main Diesel Oil Main Gas Oil Main Gas Oil From Fuel
58.8m3 Storage Tank Storage Tank Daily Tank Oil Room
DO DO FO DO 335.2m3 DO 58.6m3 DO 58.8m3 DO DO
41 54 From Key
03 04 08 05 06 07 From Boiler
Inert Gas
FO FO DO System Fuel Unit Heavy Fuel Oil
43 47 48 DO DO Diesel/Gas Oil
33 40
To Boiler DO34 DO FO42 FO
To Inert Gas Fuel Unit 39 44
From Diesel System DO
From To Boiler Generator 30 PT
PI PI 5142 PI
Diesel Fuel Unit
4114 4116 4118
Generator To Diesel
FO C B A
Generator
28 PI PI PI
4113 4115 4117
PT
5141
LT LAH TI DO FO FO
5137 5189 4111
31 35 45
Fuel OIl
Drain Tank
From Boiler 1950 Litres
Fuel Unit DO32 DO35 DO FO46
36
q) When bunkering has finished and the lines have been blown
Depending on which HFO bunker tank is to be bunkered determines which
through close all bunker manifold and tank filling valves. Procedure for Transferring Heavy Fuel Oil from the Heavy
HFO line isolation valve will need to be closed. If the aft bunker tanks are to Fuel Oil Bunker Tanks to the Heavy Fuel Oil Service Tanks
be filled then valve CF07 will need to be closed isolating the forward HFO
r) Agree with the barge or shore connection on the quantity using the Machinery Heavy Fuel Oil Transfer Pump
deep tank. This valve would need to be opened and valve CF17 closed if the
supplied and then, if satisfied, sign the bunker receipt.
forward HFO deep tank is to be filled. When bunkering DO, valve DO10 must
The HFO service tanks are fitted with level switches and the machinery transfer
be opened.
s) Disconnect the bunker hose and replace the blank. pump is equipped for automatic stop/start under the control of these switches.
The service tank in operation must be checked periodically and an estimate
e) Establish effective communication between the control room,
made of when a changeover will be needed. If the service tank in operation is
the engine room, the bunker manifold and the bunker barge or Procedure for Transferring Heavy Fuel Oil from the Heavy likely to reach its low level during UMS operation the service tanks should be
shore station; this communication must remain at all times. Fuel Oil Fore Deep Tank to the Aft Heavy Fuel Oil Bunker changed over before that period of UMS operation commences. A low level
tanks using the Forward Heavy Fuel Oil Transfer Pumps service tank should be filled as soon as possible.
f) Agree filling rates, quantity and specification of the fuel to be
supplied and agree on a signalling system with the barge or
The HFO stored in the HFO fore deep tank can be transferred directly to the a) Check the quantity of HFO in the HFO service tank to be
shore connection.
HFO service tanks using the forward transfer pumps and the bunker filling filled and determine how much fuel is to be transferred. Check
line. The procedure is as follows: the quantity of HFO in the tank from which the fuel is to be
g) If possible, take meter readings on the barge or shore station
transferred and note the temperature. If the quantity of HFO
supply line prior to commencing bunker transfer and dip DO
a) Check the quantity of HFO in the service tank to be filled and in the bunker tank is less than the quantity to be pumped be
tanks using a little water finding paste to ensure no water is
check the quantity of HFO in the HFO fore deep tank. prepared to change over tanks.
present in the fuel.
b) Ensure the temperature of the HFO in the HFO fore deep tank b) Ensure the machinery HFO transfer pump filter is clean.
h) Signal to the shore station or barge to commence bunkering at a
is sufficient for pumping.
slow rate.
c) Open the quick closing suction valve and the hydraulic suction
c) Ensure the suction filter for the forward HFO transfer pump to valve on the bunker tank from which the fuel is to be transferred
i) Check the bunker hose connections and pipeline for any leaks.
be used is clean. from as follows:
j) Check the fuel is flowing into the correct tank and not to any
Open the valves as listed: Description Valve
other tank.
IMO HFO tank quick closing suction valve FO13
k) Increase the bunkering rate to the agreed maximum. Position Description Valve
IMO HFO tank hydraulic suction valve FO07
Open HFO fore deep tank outlet valve CF30
l) Ensure bunker sampling has commenced.
Open Forward HFO transfer pump suction valve CF02/CF03
Port HFO bunker tank quick closing suction valve FO14
m) As the level in the first bunker tank approaches the amount Open Forward HFO transfer pump discharge valve CF32/CF33
stated in the bunker plan open the filling valve to the second Port HFO bunker tank hydraulic suction valve FO08
Open Bunker line isolation valve CF07
tank and slowly close in the filling valve to the tank being
topped off. Open Bunker isolation valve CF17
Starboard HFO bunker tank quick closing suction valve FO15
Open HFO filling valve FO01
n) Fill the remaining tanks in the same way. For the final bunker Starboard HFO bunker tank hydraulic suction valve FO27
tank the filling rate must be reduced by slowing the pumping Open HFO service tank filling valve FO05/FO06
operation and this must be signalled to the barge or shore
station. It is important to ensure the valves are closed on all the other bunker tanks and d) Open the machinery HFO transfer pump suction and discharge
the service tank not being filled. valves FO45 and FO44 ensuring any crossover valves with the
MGO transfer pump are closed and the blanks fitted.
Port Starboard
CF34 CF DO DO CF CF35
12 07 04 11
PI TI PI PI TI PI
4301 4300 4302 4303 4305 4304
Key
PI TI PI PI TI PI Steam Tracing CF
4307 4306 4308 4313 4315 4314
31 CF CF
Condensate 32 33
CF DO DO CF
15 05 01 08
LAH
5018 PI PI
CF36 CF37 4318 4320
A A
Fuel Oil
PI PI
Fore Deep Tank 4319 4321
CF CF
02 03
PI PI
4316 4317
DO CF
10 17
CF30
Upper Deck Thruster Room
LT
5017
FS FS
5145 5155
Cofferdam
FO FO FO
DO 02 03 04
DO02
01 Overflow Tank From Overflow Tank
86.7m3 Sludge 86.7m3
LT LAH LT LAH
5104 5105 5106 5107 TI LT TT LAH Pump TI LT TT LAH FO FO
4104 5116 5118 5117 4110 5134 5136 5135
Main Diesel Oil Main Gas Oil 05 06
Storage Tank Storage Tank From
335.2m3 58.6m3 LT TT LAH LT TT LAH Fuel LT TT LAH LSH LT TT LAH LSH LT TT LAH
5110 5112 5111 5113 5115 5114 Oil Pump 5119 5121 5120 5125 5122 5124 5123 5131 5128 5130 5129
IMO Heavy Fuel oil Heavy Fuel oil Heavy Fuel oil LI Heavy Fuel oil LI
4107 4109
Heavy Fuel oil Bunker Tank Bunker Tank Service Tank Service Tank
Tank 649.3m3 1543.5m3 1757.8m3 222.5m3 184.9m3
Port Starboard
CF34 CF DO DO CF CF35
12 07 04 11
PI TI PI PI TI PI
4301 4300 4302 4303 4305 4304
Key
PI TI PI PI TI PI Steam Tracing CF
4307 4306 4308 4313 4315 4314
31 CF CF
Condensate 32 33
CF DO DO CF
15 05 01 08
LAH
5018 PI PI
CF36 CF37 4318 4320
A A
Fuel Oil
PI PI
Fore Deep Tank 4319 4321
CF CF
02 03
PI PI
4316 4317
DO CF
10 17
CF30
Upper Deck Thruster Room
LT
5017
FS FS
5145 5155
Cofferdam
FO FO FO
DO 02 03 04
DO02
01 Overflow Tank From Overflow Tank
86.7m3 Sludge 86.7m3
LT LAH LT LAH
5104 5105 5106 5107 TI LT TT LAH Pump TI LT TT LAH FO FO
4104 5116 5118 5117 4110 5134 5136 5135
Main Diesel Oil Main Gas Oil 05 06
Storage Tank Storage Tank From
335.2m3 58.6m3 LT TT LAH LT TT LAH Fuel LT TT LAH LSH LT TT LAH LSH LT TT LAH
5110 5112 5111 5113 5115 5114 Oil Pump 5119 5121 5120 5125 5122 5124 5123 5131 5128 5130 5129
IMO Heavy Fuel oil Heavy Fuel oil Heavy Fuel oil LI Heavy Fuel oil LI
4107 4109
Heavy Fuel oil Bunker Tank Bunker Tank Service Tank Service Tank
Tank 649.3m3 1543.5m3 1757.8m3 222.5m3 184.9m3
The procedure for transferring gas oil from the MGO storage tank to the MGO
daily tank is the same as the procedure for transferring diesel oil except for the
valves. Set up the valves as follows:
When filling the incinerator service tank the procedure is the same except open
the incinerator GO service tank filling valve DO70 instead of the MGO daily
tank filling valve.
Sludge
TI TT
5158 DO FO
TAL
60 61
DO
51 From Forward Tank Heater
DO LT LAH DO02 and Manifold
5103 5102 LT LAH
49 5104 5105
Main Diesel Oil FM
4136
Daily Tank Main Diesel Oil
58.8m3 Storage Tank To Sludge
335.2m3 Pump
DO03 DO04 FO41
FO
DO 43 DO Boiler Fuel Unit
08 05
Diesel Oil
Purifier
PAL PI
5159 4111
Sludge Tank
1.0m3
LS LS LS
5162 5160
5161 FO
28
LO
22
To Sludge Pump
LT LAH TI
FT 5137 5189 4111
5149 PI Fuel OIl
4140
PT Drain Tank
PDI PDS PDI
4125 5163 4139
5164 2.0m3
b) Open any control air and operating water valves to the purifier. If the quality of the DO on board is poor then the DO daily tank can be Position Description Valve
recirculated. The procedure for starting the purifier is the same but the MDO Open MDO daily tank suction valve DO04
c) Ensure there is electrical power at the purifier control box. daily tank suction valve DO03 should be opened and the MDO storage tank
suction valve DO05 closed. Open Supply inlet valve ???
d) Set the valves as shown in the following list:
Open Supply outlet valve ???
To Stop the Purifier Open Generator fuel feed pump suction valve ???
Position Description Valve
Open MDO storage tank suction valve DO05 Open Generator fuel feed pump discharge valve ???
a) Press the PROGRAM 0 soft key button. Two total ejections will
Close DO transfer pump isolation valve DO36 be triggered and the purifier will stop automatically. Open Return inlet valve ???
Open DO purifier feed pump suction valve Open Return outlet valve ???
b) The feed pump will need to be stopped if it is running in manual
Open DO purifier heater inlet valve Open MDO daily tank return valve DO49
mode.
Open DO purifier heater outlet valve
c) Operate the generator engine as required and replenish the
MDO daily tank as required.
Issue: Draft 2 Heading - Page x of x
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 2.6.3a Boiler Fuel Oil Service System
P FO1371 DO29 Base Burner FO1223 FO1225 FO6225 FO6223 Base Burner
Atomising
Boiler Cold Start Diesel Oil Pump Steam Purge Atomising
DO60 FO61 Steam TI TI Steam Purge
(3.0m3/h x 10kg/cm2 1236 2236 Steam
P P P P
P
Degassing No.3 Burner FO5223 FO5225 FO6225 FO6223 No.3 Burner
Chamber Constant ZS Atomising
Pressure 0374 Steam Purge TT Steam Purge Atomising
Steam TT
Control Valve 1219 2219 Steam
TS TS
1234 2234
ZS ESA ZS ESA
FO1222 P FO2222 P
Fuel Oil Room
FO0372
FO1265 FO2265 E
E ZS
Automatic
Chemical PI FO 5238 P FO0371 FO2220 Combustion
Cleaning 1192 FO1264 FO1220 FO2232 FO2264
PI PI 1232 Control FO
4221 4222 PI PT Automatic Control Valve PT PI
Wind Box Wind Box
PT PS Fuel Oil 1178 Combustion Control 5264
FO65 0200 0250 FO Control Valve FO3265 DO1499 DO2499 FO4265
Heater
TI TI PI PT Furnace Furnace PT PI
1322 1179 5266
E 2322
TI
0206
Heavy Fuel Oil Pumps
(12.4m3/h x 28kg/cm2)
TT
0357
PI Chemical PI PI FS FS
2192 Cleaning 1328 2328 1360 2360
PI PI DPS TIC
4223 4224 0325
Fuel Oil TIC TT Key
Viscometer 0317 0198
Heater
TI TI Heavy Fuel Oil
E 4322 3322
Desuperheated Steam
To Fuel Oil Drain Tank
P FO1371 DO29 Base Burner FO1223 FO1225 FO6225 FO6223 Base Burner
Atomising
Boiler Cold Start Diesel Oil Pump Steam Purge Atomising
DO60 FO61 Steam TI TI Steam Purge
(3.0m3/h x 10kg/cm2 1236 2236 Steam
P P P P
P
Degassing No.3 Burner FO5223 FO5225 FO6225 FO6223 No.3 Burner
Chamber Constant ZS Atomising
Pressure 0374 Steam Purge TT Steam Purge Atomising
Steam TT
Control Valve 1219 2219 Steam
TS TS
1234 2234
ZS ESA ZS ESA
FO1222 P FO2222 P
Fuel Oil Room
FO0372
FO1265 FO2265 E
E ZS
Automatic
Chemical PI FO 5238 P FO0371 FO2220 Combustion
Cleaning 1192 FO1264 FO1220 FO2232 FO2264
PI PI 1232 Control FO
4221 4222 PI PT Automatic Control Valve PT PI
Wind Box Wind Box
PT PS Fuel Oil 1178 Combustion Control 5264
FO65 0200 0250 FO Control Valve FO3265 DO1499 DO2499 FO4265
Heater
TI TI PI PT Furnace Furnace PT PI
1322 1179 5266
E 2322
TI
0206
Heavy Fuel Oil Pumps
(12.4m3/h x 28kg/cm2)
TT
0357
PI Chemical PI PI FS FS
2192 Cleaning 1328 2328 1360 2360
PI PI DPS TIC
4223 4224 0325
Fuel Oil TIC TT Key
Viscometer 0317 0198
Heater
TI TI Heavy Fuel Oil
E 4322 3322
Desuperheated Steam
To Fuel Oil Drain Tank
Gas Hood
TT TT
ZS For Automatic Combustion Control 1238 2238 For Automatic Combustion Control ZS
FG1207 P FG2207 P
FG ZS ESA RO VOI Boil-Off Gas Pressure Low Boil-Off Gas Pressure Low ZS ESA RO VOI FG
P
P
1211 Boil-Off Gas Pressure High Boil-Off Gas Pressure High 6307 2211
PT PT
FG Master Gas Valve Trip 6219 7219 Master Gas Valve Trip FG
1208 From Automatic When Boiler Trips TT TAH TAL TI TT TAH TAL TI When Boiler Trips From Automatic 2208
Combustion Control 1202 4301 2202 4302 Combustion Control
ZS ZS
ZS ZS NI
FG712
P
P
6319 2212
P P
Gas Header Gas Header
FG FG
1218 2218
ZS FO ZS FO ZS Gas Room ZS FG ZS FG ZS FG
FO5214
P
P
ZS ZS ZS ZS ZS ZS
DPT DPT FT
3214 1214 6337
6214 6336
2214 6335
4214 DPT DPT FT
1203 1205 1249 ZS FO ZS FO ZS ZS FG ZS FG ZS FG 2203 2205 2249
FO5214
P
P
PAH ESA
P 3214 P 1214 P P 6214 P 2214 P 4214 PAH ESA
No.2 No.2
XI XI
Burner Burner From
XAH ESA Nitrogen
Buffer
30% Level Alarm 60% Level Gas Trip Tank
Gas Detection Monitor
Base Base
Burner Burner
Key
LNG Vapour
Nitrogen
No.3 No.3
Burner Burner
Incinerator
Exhaust Gas
TT
M Fan
LSH
Heater M 5166 Sludge Tank
Junction
Box TI
LT DO70 4142
5140
Incinerator
M LSL
Gas Oil Steam 5167
Service Tank M
(1.0m3)
LI
P 4112
DO10 Condensate
Electric
Cabinet
DO69 TI PI
4138 4132
(730,000kcal/h)
M
PI
Marine Gas 4133
Oil Storage
Tank
P
(58.6m3)
DO06
DO32
DO55 FO67 FO66
Marine Gas
DO31 DO33
Oil Daily Service Tank
Key
DO30
Marine Gas Oil
The sludge pump can be manually started from the local position, or remotely Position Description Valve
from the IAS and the incinerator sludge tank high level switch provides an Open Sludge tank outlet valve LO42
automatic stop facility.
Open Isolation valve LO28
After a period of settling in the incinerator sludge tank, with steam heating Open Sludge pump suction valve LO85
applied if necessary, the tank is sludged using the tank drain cocks before it
is burned in the incinerator. A waste oil circulation pump is operated taking Open Sludge pump discharge to incinerator sludge tank LO49
suction from the incinerator sludge tank and returning the oil to the tank. This Check for filling valve on incinerator sludge tank?
ensures an even temperature distribution and prevents stratification of the oil
Illustrations
LT LI LAL
5005 4047 PT PI
5042 0008
Lubricating Oil
Funnel Gravity Tank
(34m3) LO111 LO110
To
Lubricating Oil P
Drain Tank LO112
To
LO102 Lubricating Oil Ahead
Normally LO104 Drain Tank
LO Cooler Closed Servo
LO106 LO105 TI
Astern
PI
4014 4010
PI TI
PI PI 4009 4013
LOT305
4001 4000 LO98
LO97 To Main Turbine
LO96 TT
LO95 5108
PI TI TI PI From Main Turbine
4011 4015 4016 4012
TT TT
5012 5011
I
LO Cooler IAS P To Main Turbine
Control Air
To
Main To
Turbine Lubricating Oil
Drain Tank
LO119
P LOT304 LO100
PI PI To / From
4003 4005 Lubricating Oil
To LO118 LO116 Auxiliary From Main Turbine Purifiers
Lubricating Oil Lubricating Oil
Drain Tank Pumps Key
(180m3/h LO99
x4kg/cm2)
Lubricating Oil
LT
5002
Lubricating Oil
Electrical Signal
Sump Tank
LAL TI
5010 4017 (73.5m3)
Air
LO121
From Engine Room Air
TT
1520
PT
5132 TI
PT 4037 TI
0132 1561
To Funnel
TT
TI 1561 TI TI TI
1553 1552 1551
1562
TT TT TT TT
1553 1552 1551
1562
TI
PI 1582 TI TI
0132 1572 1571
TT
1581 TT TT Key
To Dirty Oil Tank TT 1572 1571
1602
TT TT Lubricating Oil
To 1591 1601
Lubricating Oil TI
TI TT TI 1601
Sump Tank 1592 1592 1591 Electrical Signal
PT
5148
PT TT TT Air
0131 TT 1532 1531
WD PI 1541
PI TI TT TI TI
5125 0012 1542 1542 TI 1532 1531
To Lubricating 0010
1541
Oil Coolers
TT TT TT
1522
To Lubricating TT TI 1513 1512
0147 0147 TI
Oil Sump Tank 1522 TT
TI TI
1513 1512
1521
From Lubricating
Oil Coolers TI
1521
TI
0148
Main LO Pump
PI
0013
(210m3/h x 4kg/cm2)
From Lubricating
Oil Sump Tank
PS TI
0069 1511
TT
1511
To Lubricating
Oil Sump Tank
Open Manoeuvring valves oil filter outlet valve LO110 MT034 Main Turbine bearing LO pressure 70kPa
g) Check the flow of lubricating oil throughout the system,
Closed Manoeuvring valves oil filter bypass valve LO112 ensuring that the flow is adequate to all parts, including the MT044 Main gearing LO pressure 70kPa
intermediate shaft bearings and that there are no leaks. Utilise MT046 Main Turbine manoeuvring control oil pressure 250kPa
Lock open Control oil to main turbine trip solenoid
LO flow sight glasses on all bearings and gravity tank. Engage
and turning gear interlock LO120 PP005 No.1 auxiliary LO pump outlet pressure control 350kPa
and start the turning gear.
Open Control gear oil filter inlet valve LO113 PP006 No.2 auxiliary LO pump outlet pressure control 350kPa
h) Keep the LO system circulating and allow the temperature of the
Open Control gear oil filter outlet valve LO114 BD035 Main LO sump level 0.3m
system to gradually increase to normal operating temperature.
Closed Control gear oil filter bypass valve LO115 BD041 Main LO gravity tank level 0.6m
Open LO inlet valves to LO coolers LO95, LO97 i) When the system LO temperatures and pressures are stable the
LO system is ready and the turbine may be started provided that Tag Description High High
Open LO outlet valves from LO coolers LO96, LO98 other systems are operating correctly.
Closed LO cooler drain valves (x2) 16491 Main thrust pad temperature 110°C
(Note: When the turbine is operating at full sea conditions the main LO
Open LO cooler vent valves (x2)
pump will be supplying LO to the system and the running auxiliary Tag Description Low Low
Operational LO cooler three-way valve LOT305 LO pump will be stopped. The standby LO pump remains in standby
mode.) MT074 Main Turbine LO pressure trip 50kPa
Open Main LO pump inlet valve from LO sump tank LO100
MT075 Main Tturbine control oil pressure trip 200kPa
Closed Gravity tank filling inlet valve LO102 During operation of the main LO system overflow from the gravity tank may
Open Gravity tank quick closing inlet/outlet valve be observed at the overflow sight glass situated near the gravity tank. System
pressures and temperatures may be observed at the main engine lubricating oil
Open Gravity tank overflow inlet valve LO104 system graphic screen. System pressure and temperature alarms and tank level
Open No.1 intermediate bearing inlet valve LO105 alarms operate through the IAS.
Open No.2 intermediate bearing inlet valve LO106
Open Dehumidifier inlet valve from gearbox and run unit
(should already be open whilst LO system is
shut down and maintain open until main turbine
is full away on passage) LO121
Closed Oil mist separator drain to dirty oil tank
(Note: It is assumed that all turbine and gearbox system lubricating valves
remain open.)
LI
TI 4024
4025
Stern Tube
LO51 Lubricating Oil
Gravity Tank
To be closed LAH
Filling 5010 (0.5m3)
in dry dock
Aft Seal Stern
Tube Lubricating LAL
5056
LO04 Oil Tank
(0.05m3)
LAL Normally
LO05 5055
Closed
LO64 To be closed in case
of damage to sealing ring
LO32
LO108
Fwd Seal Stern PI
4026
Tube Lubricating
Oil Tank
(0.2m3)
LAL
5006
To To From
Lubricating Oil Lubricating Oil Lubricating Oil
Drain Tank Transfer Pump Transfer Pump
TT Stern Tube TT
5011 5002
L013
LO21 LO30
Stern Tube Lubricating Oil
TI TI Pumps
4015 4016 (2.0m3/h 3 bar) LO34
PI PI
4018 4017
The bearing area is lubricated by means of a gravity tank system with oil being Closed Drain valve LO64
The centre pipe leading down from the header tank provides a static head for
supplied to the stern tube from one of two stern tube LO pumps. The stern tube Open LO gravity tank return to the stern tube LO tank valveLO107
the seal. The two pipes connected to the sides of the header tank form part of
LO pumps take suction from the stern tube LO tank and passes the oil through
the circulating system set up when the shaft is rotating.
a cooler before supplying the stern tube bearing. The stern tube LO cooler is d) Open the cooling water inlet and outlet valves to the stern tube
supplied from the central fresh water cooling system. LO cooler and ensure that cooling water is circulating through
A circulator is fitted between the two seals and forms a pumping action when
the propeller shaft rotates. The two pipes allow for ahead and astern rotation the cooler.
The position of the LO gravity tank determines and maintains the correct
of the shaft.
pressure in the system. The stern tube LO gravity tank is fitted with two e) Start the duty stern LO pump and check that oil is flowing
overflow returns to the stern tube LO tank. Each overflow incorporates a sight through the bearing system and returning to the LO tank by
glass to enable the operator to positively identify oil return. Oil returning from means of the sight glasses.
the bearing flows back to the stern tube LO tank from where the duty stern tube
LO pump takes suction. f) Set the other stern tube LO pump to the standby mode.
LI
TI 4024
4025
Stern Tube
LO51 Lubricating Oil
Gravity Tank
To be closed LAH
Filling 5010 (0.5m3)
in dry dock
Aft Seal Stern
Tube Lubricating LAL
5056
LO04 Oil Tank
(0.05m3)
LAL Normally
LO05 5055
Closed
LO64 To be closed in case
of damage to sealing ring
LO32
LO108
Fwd Seal Stern PI
4026
Tube Lubricating
Oil Tank
(0.2m3)
LAL
5006
To To From
Lubricating Oil Lubricating Oil Lubricating Oil
Drain Tank Transfer Pump Transfer Pump
TT Stern Tube TT
5011 5002
L013
LO21 LO30
Stern Tube Lubricating Oil
TI TI Pumps
4015 4016 (2.0m3/h 3 bar) LO34
PI PI
4018 4017
L020 L080
L088 L087 L090 L091 L092
Heater Heater
LT Diesel Gen. LI LT LT
P 5005 4027 P 5003 Lubricating Oil P 5004 Lubricating Oil Lubricating Oil Service Tanks Deck Machinery Oil Tank
Lubricating Oil
L014 L002 Storage Tank L001 Renovating Tank
Storage Tank LI (0.25m3) LI (0.25m3) LI (0.25m3) LI
(73.3m3) (45.1m3) 4048 4049 4050
(4.0m3) 4023 L0100 TAL TAL
L099 L098 L097
L036 TI TT TI TT
5030 5030
To / From TAH TAH
Fore Machinery L061 L041 L0103
Oil Tank
L045 P P
L070
No.1 No.2
Lubricating Oil Lubricating Oil
L003 L017 Purifier Purifier
(3.0m3/h) (3.0m3/h)
L0
96
Diesel Generator L0105 L059
Oil Tank
To Main
L0014 Lubricating Oil
Sump Tank
FI FI
To Incinerator 4030 4030
LO Sludge Tank
L050 Transfer Sludge
No.1 Pump Pump PI PI
Turbo Generator (5.0m3/h
L056 (15m3/h L049
4032 4032
Oil Tank 3.5 bar) L071 4 bar) PAL PAL
5032 5032
PI PI L044
L038 L0 L0 L0 L0 L0 4008 L0 4006 L0 L0 L0 L0 L0 L0 L0 L0 L0 L0
63 62 39 82 37 86 To HFO 66 65 08 18 10 11 69 19 67 33
Transfer
Line
PI PI L074
4007 4005
L054
No.2
Turbo Generator L043 L085 L075
Oil Tank L055
PI PI
Vapour Steam 4001 4002
L035 VP781
L057 No.1 L053
L028 Lubricating Oil Purifing Pumps
From Bilge Tank L046 (3.0m3/h 2.5 bar) L079
L025 PI PI
From Oily Water Tank 4003 4004
From Stern Tube
Lubricating Oil Pumps L026
L048 L024 L022 From Fuel Oil Drain Tank No.2 L052
L078
To Stern Tube L027 From
From Main Lubricating Oil Incinerator
Lubricating Oil Pumps L047 L060 Sump Tank Drains
Key
L089 L058 L040 From Fuel and Diesel Oil
Lubricating Oil TA29
From Turbines Sludge Tank
Electrical Signal LT LAH L015
5007 Lubricating Oil 5054 L042
Dirty Oil Tank LAH Sludge Tank LAH
Instrumentation Drain Tank 5025 5025
(59.4m3) (2.45m3)
(1.0m3) TI
4069
Steam
Maker: Westfalia A B C Software assignment for a each purifier is carried out in the factory using a
DOWN ALARMS UP 1 2 3
password function. Any alterations to the set parameters should only be carried
Type: Gear pump
. 0 +/- out by a person authorised to make such changes.
Model: R35/40
No. of sets: 2 INS The IAS controls the purifiers with a manual start/stop and provides indication
DIR DEL ESC
Capacity: 3,000 litres/hour for running and oil temperature and alarm for purifier failure and LO pressure.
SF DC5V RUN
The purpose of the lubricating oil purifier is to remove water and solid particles SEP FEED SLUDGE PARTIAL HEATER
REPEATER
HELP ENTER
from the lubricating oil to prevent damage being caused to the machinery the To purify lubricating oil to and from the main turbine LO sump tank using the
oil is supplying. No.1 purifier.
Liquid mixtures and solid/liquid mixtures can be separated by two means. The The C7-623 control unit is used for the automatic ejection control and condition a) Record the level of oil in all the tanks associated with the
gravity field of a settling tank or the centrifugal field of a purifier bowl. Both monitoring of the oil purifier. The control unit has three modes of operation. system.
systems rely on the product components having different densities. Since the 1) Partial ejections
centrifugal field of a purifier is considerably more effective than the gravity b) Open any control air and operating water valves to the purifier.
field of a settling tank it is usual practice to favour the centrifugal field method. 2) Total ejections
The heated dirty oil enters the purifier and the centrifugal force created by the 3) Preselected partial ejections followed by total ejection c) Ensure there is electrical power at the purifier control box.
rotating bowl causes the liquid mixture to separate into its different constituents
within the disc stack. With the time dependant program cycle, it is important for high clarifying d) Set the valves as shown in the following list.
efficiency and to avoid desludging losses that the separable solids content in
The disc stack consists of a large number of conical discs placed one above the the product do not fluctuate widely. The UNITROL system provides two basic
other. Each disc is provided with spacers to maintain the precisely determined monitoring systems. Position Description Valve
narrow disc interspaces. These interspaces are critical for the efficiency of the Open Outlet valve from sump tank LO19
separator. 1) Water content monitoring system (WMS)
2) Sludge space monitoring system (SMS) Closed Purifier pumps crossover valve LO75
The solid particles suspended in the oil settle on the underside of the discs Open Inlet valve to the No.1 purifier feed pump LO57
and slide down into the solid holding space. The smooth disc surfaces allow The illuminated Liquid Crystal Display (LCD) provides information about
the solids to slide down and provide self-cleaning of the discs. Each bowl Closed Purifier pumps suction crossover valve LO46
the operating and malfunction condition of the purifier and displays all the
assembly is fitted with a regulating ring, sometimes referred to as a gravity relevant process data. Open Outlet valve from the No.1 purifier feed pump LO53
disc. The diameter of the gravity disc is determined by the density of the oil
Closed Purifier pumps discharge crossover valve LO79
to be purified and will determine the position of the interface between the oil
and the sealing water. The position of this interface is critical for the effective Open Inlet to No.1 purifier steam heater LO19
separation of the liquid mixture. Open Outlet from the No.1 purifier steam heater LO69
L020 L080
L088 L087 L090 L091 L092
Heater Heater
LT Diesel Gen. LI LT LT
P 5005 4027 P 5003 Lubricating Oil P 5004 Lubricating Oil Lubricating Oil Service Tanks Deck Machinery Oil Tank
Lubricating Oil
L014 L002 Storage Tank L001 Renovating Tank
Storage Tank LI (0.25m3) LI (0.25m3) LI (0.25m3) LI
(73.3m3) (45.1m3) 4048 4049 4050
(4.0m3) 4023 L0100 TAL TAL
L099 L098 L097
L036 TI TT TI TT
5030 5030
To / From TAH TAH
Fore Machinery L061 L041 L0103
Oil Tank
L045 P P
L070
No.1 No.2
Lubricating Oil Lubricating Oil
L003 L017 Purifier Purifier
(3.0m3/h) (3.0m3/h)
L0
96
Diesel Generator L0105 L059
Oil Tank
To Main
L0014 Lubricating Oil
Sump Tank
FI FI
To Incinerator 4030 4030
LO Sludge Tank
L050 Transfer Sludge
No.1 Pump Pump PI PI
Turbo Generator (5.0m3/h
L056 (15m3/h L049
4032 4032
Oil Tank 3.5 bar) L071 4 bar) PAL PAL
5032 5032
PI PI L044
L038 L0 L0 L0 L0 L0 4008 L0 4006 L0 L0 L0 L0 L0 L0 L0 L0 L0 L0
63 62 39 82 37 86 To HFO 66 65 08 18 10 11 69 19 67 33
Transfer
Line
PI PI L074
4007 4005
L054
No.2
Turbo Generator L043 L085 L075
Oil Tank L055
PI PI
Vapour Steam 4001 4002
L035 VP781
L057 No.1 L053
L028 Lubricating Oil Purifing Pumps
From Bilge Tank L046 (3.0m3/h 2.5 bar) L079
L025 PI PI
From Oily Water Tank 4003 4004
From Stern Tube
Lubricating Oil Pumps L026
L048 L024 L022 From Fuel Oil Drain Tank No.2 L052
L078
To Stern Tube L027 From
From Main Lubricating Oil Incinerator
Lubricating Oil Pumps L047 L060 Sump Tank Drains
Key
L089 L058 L040 From Fuel and Diesel Oil
Lubricating Oil TA29
From Turbines Sludge Tank
Electrical Signal LT LAH L015
5007 Lubricating Oil 5054 L042
Dirty Oil Tank LAH Sludge Tank LAH
Instrumentation Drain Tank 5025 5025
(59.4m3) (2.45m3)
(1.0m3) TI
4069
Steam
L020 L080
L088 L087 L090 L091 L092
Heater Heater
LT Diesel Gen. LI LT LT
P 5005 4027 P 5003 Lubricating Oil P 5004 Lubricating Oil Lubricating Oil Service Tanks Deck Machinery Oil Tank
Lubricating Oil
L014 L002 Storage Tank L001 Renovating Tank
Storage Tank LI (0.25m3) LI (0.25m3) LI (0.25m3) LI
(73.3m3) (45.1m3) 4048 4049 4050
(4.0m3) 4023 L0100 TAL TAL
L099 L098 L097
L036 TI TT TI TT
5030 5030
To / From TAH TAH
Fore Machinery L061 L041 L0103
Oil Tank
L045 P P
L070
No.1 No.2
Lubricating Oil Lubricating Oil
L003 L017 Purifier Purifier
(3.0m3/h) (3.0m3/h)
L0
96
Diesel Generator L0105 L059
Oil Tank
To Main
L0014 Lubricating Oil
Sump Tank
FI FI
To Incinerator 4030 4030
LO Sludge Tank
L050 Transfer Sludge
No.1 Pump Pump PI PI
Turbo Generator (5.0m3/h
L056 (15m3/h L049
4032 4032
Oil Tank 3.5 bar) L071 4 bar) PAL PAL
5032 5032
PI PI L044
L038 L0 L0 L0 L0 L0 4008 L0 4006 L0 L0 L0 L0 L0 L0 L0 L0 L0 L0
63 62 39 82 37 86 To HFO 66 65 08 18 10 11 69 19 67 33
Transfer
Line
PI PI L074
4007 4005
L054
No.2
Turbo Generator L043 L085 L075
Oil Tank L055
PI PI
Vapour Steam 4001 4002
L035 VP781
L057 No.1 L053
L028 Lubricating Oil Purifing Pumps
From Bilge Tank L046 (3.0m3/h 2.5 bar) L079
L025 PI PI
From Oily Water Tank 4003 4004
From Stern Tube
Lubricating Oil Pumps L026
L048 L024 L022 From Fuel Oil Drain Tank No.2 L052
L078
To Stern Tube L027 From
From Main Lubricating Oil Incinerator
Lubricating Oil Pumps L047 L060 Sump Tank Drains
Key
L089 L058 L040 From Fuel and Diesel Oil
Lubricating Oil TA29
From Turbines Sludge Tank
Electrical Signal LT LAH L015
5007 Lubricating Oil 5054 L042
Dirty Oil Tank LAH Sludge Tank LAH
Instrumentation Drain Tank 5025 5025
(59.4m3) (2.45m3)
(1.0m3) TI
4069
Steam
The running of the purifier is as previously described with the following valve
settings:
L020 L080
L088 L087 L090 L091 L092
Heater Heater
LT Diesel Gen. LI LT LT
P 5005 4027 P 5003 Lubricating Oil P 5004 Lubricating Oil Lubricating Oil Service Tanks Deck Machinery Oil Tank
Lubricating Oil
L014 L002 Storage Tank L001 Renovating Tank
Storage Tank LI (0.25m3) LI (0.25m3) LI (0.25m3) LI
(73.3m3) (45.1m3) 4048 4049 4050
(4.0m3) 4023 L0100 TAL TAL
L099 L098 L097
L036 TI TT TI TT
5030 5030
To / From TAH TAH
Fore Machinery L061 L041 L0103
Oil Tank
L045 P P
L070
No.1 No.2
Lubricating Oil Lubricating Oil
L003 L017 Purifier Purifier
(3.0m3/h) (3.0m3/h)
L0
96
Diesel Generator L0105 L059
Oil Tank
To Main
L0014 Lubricating Oil
Sump Tank
FI FI
To Incinerator 4030 4030
LO Sludge Tank
L050 Transfer Sludge
No.1 Pump Pump PI PI
Turbo Generator (5.0m3/h
L056 (15m3/h L049
4032 4032
Oil Tank 3.5 bar) L071 4 bar) PAL PAL
5032 5032
PI PI L044
L038 L0 L0 L0 L0 L0 4008 L0 4006 L0 L0 L0 L0 L0 L0 L0 L0 L0 L0
63 62 39 82 37 86 To HFO 66 65 08 18 10 11 69 19 67 33
Transfer
Line
PI PI L074
4007 4005
L054
No.2
Turbo Generator L043 L085 L075
Oil Tank L055
PI PI
Vapour Steam 4001 4002
L035 VP781
L057 No.1 L053
L028 Lubricating Oil Purifing Pumps
From Bilge Tank L046 (3.0m3/h 2.5 bar) L079
L025 PI PI
From Oily Water Tank 4003 4004
From Stern Tube
Lubricating Oil Pumps L026
L048 L024 L022 From Fuel Oil Drain Tank No.2 L052
L078
To Stern Tube L027 From
From Main Lubricating Oil Incinerator
Lubricating Oil Pumps L047 L060 Sump Tank Drains
Key
L089 L058 L040 From Fuel and Diesel Oil
Lubricating Oil TA29
From Turbines Sludge Tank
Electrical Signal LT LAH L015
5007 Lubricating Oil 5054 L042
Dirty Oil Tank LAH Sludge Tank LAH
Instrumentation Drain Tank 5025 5025
(59.4m3) (2.45m3)
(1.0m3) TI
4069
Steam
The LO transfer pump can take suction from the following locations:
Introduction Description Valve
Lubricating oil is stored in the following main storage tanks located in the Location Valve From the Main Turbine Sump
engine room.
Main LO sump tank LO22 LO transfer pump suction valves LO22 and LO43
L020 L080
L088 L087 L090 L091 L092
Heater Heater
LT Diesel Gen. LI LT LT
P 5005 4027 P 5003 Lubricating Oil P 5004 Lubricating Oil Lubricating Oil Service Tanks Deck Machinery Oil Tank
Lubricating Oil
L014 L002 Storage Tank L001 Renovating Tank
Storage Tank LI (0.25m3) LI (0.25m3) LI (0.25m3) LI
(73.3m3) (45.1m3) 4048 4049 4050
(4.0m3) 4023 L0100 TAL TAL
L099 L098 L097
L036 TI TT TI TT
5030 5030
To / From TAH TAH
Fore Machinery L061 L041 L0103
Oil Tank
L045 P P
L070
No.1 No.2
Lubricating Oil Lubricating Oil
L003 L017 Purifier Purifier
(3.0m3/h) (3.0m3/h)
L0
96
Diesel Generator L0105 L059
Oil Tank
To Main
L0014 Lubricating Oil
Sump Tank
FI FI
To Incinerator 4030 4030
LO Sludge Tank
L050 Transfer Sludge
No.1 Pump Pump PI PI
Turbo Generator (5.0m3/h
L056 (15m3/h L049
4032 4032
Oil Tank 3.5 bar) L071 4 bar) PAL PAL
5032 5032
PI PI L044
L038 L0 L0 L0 L0 L0 4008 L0 4006 L0 L0 L0 L0 L0 L0 L0 L0 L0 L0
63 62 39 82 37 86 To HFO 66 65 08 18 10 11 69 19 67 33
Transfer
Line
PI PI L074
4007 4005
L054
No.2
Turbo Generator L043 L085 L075
Oil Tank L055
PI PI
Vapour Steam 4001 4002
L035 VP781
L057 No.1 L053
L028 Lubricating Oil Purifing Pumps
From Bilge Tank L046 (3.0m3/h 2.5 bar) L079
L025 PI PI
From Oily Water Tank 4003 4004
From Stern Tube
Lubricating Oil Pumps L026
L048 L024 L022 From Fuel Oil Drain Tank No.2 L052
L078
To Stern Tube L027 From
From Main Lubricating Oil Incinerator
Lubricating Oil Pumps L047 L060 Sump Tank Drains
Key
L089 L058 L040 From Fuel and Diesel Oil
Lubricating Oil TA29
From Turbines Sludge Tank
Electrical Signal LT LAH L015
5007 Lubricating Oil 5054 L042
Dirty Oil Tank LAH Sludge Tank LAH
Instrumentation Drain Tank 5025 5025
(59.4m3) (2.45m3)
(1.0m3) TI
4069
Steam
LO transfer pump discharge valves LO71, LO61 and LO88 a) Check that there is sufficient capacity in the tank to accommodate
the amount of LO ordered.
To the Lubricating Oil Renovating Tank b) Agree with the supplier the amount of LO to be supplied for
LO transfer pump discharge valves LO71, LO61 and LO87 each category of oil.
When transferring oil to the storage and renovating tanks care must be taken
to ensure that the deck LO filling connections are closed and the blanks are When loading oil into the diesel generator tank the only valve to be opened is
fitted with joints. the filling valve on deck.
Description Valve
From the LO storage tank to the turbine sump LO02 and LO45
From the LO renovating tank to the turbine sump LO01 and LO45
From the LO storage tank to the
diesel generator sump LO14, LO13 and LO105
Illustrations
2.8 1a Engine Room Bilge System
BB66
Key
Steering Gear Fresh Water
Room Tank Tank Top TA21 TA22
Bilges BB65 BB18
LAH LAH
5007 5008
Fresh Water
PI
4012 Reciprocating Holding Bilge Tank
Sea Water TI LO19 (102.3m3) LT
Bilge Pump 4014 5014
E
(20m3/h
Control Air
PI x3.5 kg/cm2)
4011
Electrical Signal
TI Oily Water Tank LT
4015 5015
Instrumentation LO20 (52.9m3)
Double Bottom
BB62 BB11 Cofferdam
Port
BB04
To Deck Via Sludge Pump
BB05
LSL
Stern BB03 BB02 LSH BB06 From Main TA07 BB08 BB10 BB09 BB17 BB60 BB81 BB24 TA23 BB82 BB25
Tube Condenser
Cooling LAH LAH LAL LAH
Tank Bilge Well Double Bottom Bilge Well Bilge Well Double Bottom 5013 5009 5010
(Aft) LS Cofferdam (Mid Ship) (Mid Ship) Cofferdam
5006 Forward
Aft (Port) (Starboard) Starboard Condensate Tank Top
LAH LAH Forward Bilge Well Forward Bilge Well
5043 5044 Pump Well
(Port) (Starboard)
BB66
Key
Steering Gear Fresh Water
Room Tank Tank Top TA21 TA22
Bilges BB65 BB18
LAH LAH
5007 5008
Fresh Water
PI
4012 Reciprocating Holding Bilge Tank
Sea Water TI LO19 (102.3m3) LT
Bilge Pump 4014 5014
E
(20m3/h
Control Air
PI x3.5 kg/cm2)
4011
Electrical Signal
TI Oily Water Tank LT
4015 5015
Instrumentation LO20 (52.9m3)
Double Bottom
BB62 BB11 Cofferdam
Port
BB04
To Deck Via Sludge Pump
BB05
LSL
Stern BB03 BB02 LSH BB06 From Main TA07 BB08 BB10 BB09 BB17 BB60 BB81 BB24 TA23 BB82 BB25
Tube Condenser
Cooling LAH LAH LAL LAH
Tank Bilge Well Double Bottom Bilge Well Bilge Well Double Bottom 5013 5009 5010
(Aft) LS Cofferdam (Mid Ship) (Mid Ship) Cofferdam
5006 Forward
Aft (Port) (Starboard) Starboard Condensate Tank Top
LAH LAH Forward Bilge Well Forward Bilge Well
5043 5044 Pump Well
(Port) (Starboard)
BB66
Key
Steering Gear Fresh Water
Room Tank Tank Top TA21 TA22
Bilges BB65 BB18
LAH LAH
5007 5008
Fresh Water
PI
4012 Reciprocating Holding Bilge Tank
Sea Water TI LO19 (102.3m3) LT
Bilge Pump 4014 5014
E
(20m3/h
Control Air
PI x3.5 kg/cm2)
4011
Electrical Signal
TI Oily Water Tank LT
4015 5015
Instrumentation LO20 (52.9m3)
Double Bottom
BB62 BB11 Cofferdam
Port
BB04
To Deck Via Sludge Pump
BB05
LSL
Stern BB03 BB02 LSH BB06 From Main TA07 BB08 BB10 BB09 BB17 BB60 BB81 BB24 TA23 BB82 BB25
Tube Condenser
Cooling LAH LAH LAL LAH
Tank Bilge Well Double Bottom Bilge Well Bilge Well Double Bottom 5013 5009 5010
(Aft) LS Cofferdam (Mid Ship) (Mid Ship) Cofferdam
5006 Forward
Aft (Port) (Starboard) Starboard Condensate Tank Top
LAH LAH Forward Bilge Well Forward Bilge Well
5043 5044 Pump Well
(Port) (Starboard)
c) Set the pump valves as in the following table: g) When the bilge well is empty, stop the bilge pump or select
The valve settings assume suction from the aft bilge well via the bilge main. If another bilge for emptying.
other bilge spaces are to be pumped the appropriate valves must be opened.
BB66
Key
Steering Gear Fresh Water
Room Tank Tank Top TA21 TA22
Bilges BB65 BB18
LAH LAH
5007 5008
Fresh Water
PI
4012 Reciprocating Holding Bilge Tank
Sea Water TI LO19 (102.3m3) LT
Bilge Pump 4014 5014
E
(20m3/h
Control Air
PI x3.5 kg/cm2)
4011
Electrical Signal
TI Oily Water Tank LT
4015 5015
Instrumentation LO20 (52.9m3)
Double Bottom
BB62 BB11 Cofferdam
Port
BB04
To Deck Via Sludge Pump
BB05
LSL
Stern BB03 BB02 LSH BB06 From Main TA07 BB08 BB10 BB09 BB17 BB60 BB81 BB24 TA23 BB82 BB25
Tube Condenser
Cooling LAH LAH LAL LAH
Tank Bilge Well Double Bottom Bilge Well Bilge Well Double Bottom 5013 5009 5010
(Aft) LS Cofferdam (Mid Ship) (Mid Ship) Cofferdam
5006 Forward
Aft (Port) (Starboard) Starboard Condensate Tank Top
LAH LAH Forward Bilge Well Forward Bilge Well
5043 5044 Pump Well
(Port) (Starboard)
Chain Lockers
Draining Detail
Deck at 25400
Plan View Sounding Mouth Sounding Mouth
Upper Deck
BG LAH B A
28 5001 Deck at 25400
Chain Locker Chain Locker
Hydraulic Room
Electric Room
From Fire Main System B
LAH
5003
BG40 BG32
BG
BG17 24
PI
Bosun Store 4303
BG23
BG08 BG20
BG LAH
15 5002 KEY PI PI
4304 4305
Bilge
PI
BG12 To Ejector
4301
BG
25
LAH LAH
5005 5004
Emergency Fire
Pump Room
Bow Thruster/Emergency Fire Pump Room Bilge Well f) Shut the water supply valve to each eductor when all bilges
connected to that eductor are empty and then close the system
Description Valve valves.
Sea water supply valve BG12
g) Close the eductors common overboard discharge valve BG20.
Eductor suction valve BG25
Thruster/emergency fire pump room bilge well suction valve BG01 AUTHORS NOTE - Passageway bilges system to be checked
Chain Lockers
Description Valve
Sea water supply valve BG23
Eductor suction valve BG24
Port chain locker suction valve BG40
Starboard chain locker suction valve BG32
Illustrations
P
s 254 CA176 FO2221
IG2 P CA160 DS331 P T-51
051 BS1 P NP-9 NP-3 P
FO2222
CA CA92 s 225 BF2 BF1
IG6 P P SST NP-10 026 026
021 220 CA80 CA177 NP-4 P
FO2223
CA161 BS1B 003
CS2 P
001 FO3 P NP-4 SS1 NP-5 P
FO2225
IG6 P 223 CA178 130
DS20 CA163 CA166 DS21 FO3 NP-6
041 P BST P NP-5
CS2 P I
303 225 NP-7 P
419 NP-6 BF P DS1 BS2224
P
Spare CA168 25 CA179 CA180 285 NP-8
BS35 CA165 CS91 P
I
BST BS3 P NP-7
P
BS2254
CA 302 224
221 BS3 P NP-8 SS2 P NP-9 P
P
254 079 BS2225
BS39 CA167 CA164 DS332 I CA182 CA181
LOT304 NP-10
BS3 P NP-9
P P 225
CA169 To Self Cleaning F02 P SS1
CA170 LO Filter NP-10 220 079 NP-4 P
CS2419 DS330 CA186 CA183 FO4223
CA
P
171 I NP-5 P
LOT305 FO5 P NP-4 DS2 P NP-4 P FO6 FO4225
223 285 223 NP-6
FO5 P NP-5 CA184 NP-5 P
To 225 FO6
CA CW24 225 NP-7 P
BS4224
Electrical NP-6 F01 SS2 NP-6
211 Workshop 220 130
CA137 CA89 CA215 CA187 NP-8 P
BS4254
BS5 P NP-7 NP-7 P BS6
P Spare 224 224
SC20 CA212 BS5 P NP-8 NP-8 P NP-9 P
BS6 BS4225
Main 254
P CA 254 NP-10
SC19 CA216 CA68 Condenser
Level Control
BS5 P NP-9 188 NP-9 P BS6
225 225
CA NP-10 NP-10
217
P
s 254 CA176 FO2221
IG2 P CA160 DS331 P T-51
051 BS1 P NP-9 NP-3 P
FO2222
CA CA92 s 225 BF2 BF1
IG6 P P SST NP-10 026 026
021 220 CA80 CA177 NP-4 P
FO2223
CA161 BS1B 003
CS2 P
001 FO3 P NP-4 SS1 NP-5 P
FO2225
IG6 P 223 CA178 130
DS20 CA163 CA166 DS21 FO3 NP-6
041 P BST P NP-5
CS2 P I
303 225 NP-7 P
419 NP-6 BF P DS1 BS2224
P
Spare CA168 25 CA179 CA180 285 NP-8
BS35 CA165 CS91 P
I
BST BS3 P NP-7
P
BS2254
CA 302 224
221 BS3 P NP-8 SS2 P NP-9 P
P
254 079 BS2225
BS39 CA167 CA164 DS332 I CA182 CA181
LOT304 NP-10
BS3 P NP-9
P P 225
CA169 To Self Cleaning F02 P SS1
CA170 LO Filter NP-10 220 079 NP-4 P
CS2419 DS330 CA186 CA183 FO4223
CA
P
171 I NP-5 P
LOT305 FO5 P NP-4 DS2 P NP-4 P FO6 FO4225
223 285 223 NP-6
FO5 P NP-5 CA184 NP-5 P
To 225 FO6
CA CW24 225 NP-7 P
BS4224
Electrical NP-6 F01 SS2 NP-6
211 Workshop 220 130
CA137 CA89 CA215 CA187 NP-8 P
BS4254
BS5 P NP-7 NP-7 P BS6
P Spare 224 224
SC20 CA212 BS5 P NP-8 NP-8 P NP-9 P
BS6 BS4225
Main 254
P CA 254 NP-10
SC19 CA216 CA68 Condenser
Level Control
BS5 P NP-9 188 NP-9 P BS6
225 225
CA NP-10 NP-10
217
Typhoon
CA01
Deaerator Area
PI PT
4001 5001
CA41
To Quick Closing Valves To Emergency Diesel
Control Panel Generator Room
CA38
Deck Store
CA09 CA37
Control To N2 Generator
Control Air
Compressor
Air PI N2 Generator Room
Gas Room
Receiver 4004 CA35 CA53
CA02 Paint Store
CA34
Control Control Chemical Products Station
CA06 CA08 CA18 CA20 CA23 CA24
Air Dryer Air Dryer CA40
In Foam/C02 Room
CA CA39
05 In Incinerator Room
To Control CA36
CA CA
11 10 Air System Flat 20968
CA33 To Accommodation
Control Air
PI PT Inert Gas Room
Compressor
4002 5002 CA32
CA03 In Steering Gear Room
Control Control CA31
To Passageway
CA19 Air Dryer CA21 CA22
Air Dryer CA25 CA56
CA30
CA In Electrical Workshop Store
17 CA52
General CA29
Service Air CA113
Receiver
CA14 CA16
General Service CA51
Air Compressor CA06
CA15 In Engine Workshop/Store
CA50
CA04 To ION
CA26 Exchange Unit
CA49
CA27
CA CA CA48
12 13 CA28
CA47
CA46
General Service
Air Compressor CA43 CA45 Key
In Fuel Oil Room
CA42 CA44 General Service Air
Control Air
SA99 SA97
CA109
5°
From Control Air Receiver
and General Service Air Receiver Near
CA54
Scupper
Diesel Generator Engine
Oil Mist Detector
PI PT
4006 5005
PI PT
4005 5004
(150
Litres) PT Starting Air
Compressor
5°
Starting
CA104 CA105
Air
Receiver
SA103
(500
Litres) SA100 SA98
5°
SA102 SA101
Near
Scupper
Starting Air
Compressor
Key
Air
Instrumentation
Illustrations
To / From Actuator
S0 S1 S2 S4
Interconnecting /
Isolating Valve Common
Tank
Automatic B T
Lock Valve
Safety Relief / A P
Bypass Valve
B T
P T
A P
Chamber Chamber
No.3 No.4 A B
System B
Chamber Chamber B T
No.1 No.2 P
A
To / From Actuator
B T
Safety Relief /
A P
Bypass Valve Automatic
Lock Valve
Interconnecting /
Isolating Valve
P T
A B
Leak Oil
Key
M No.2 Pump Unit
Hydraulic Oil
PUMP 1
AUTOSTART
OVERLOAD PHASE
FAILURE
POWER
FAILURE
POWER
FAILURE
LOW LOW
OIL LEVEL switch the local starter panels over to REMOTE control.
PUMP 2 PUMP 2 PUMP 2 POWER 2 CONTROL 2 PUMP 2
(Note: Only one hydraulic pump should be operated when on local emergency
HYDRAULIC HYDRAULIC COMMON CLOGGED CLOGGED
LOCK LOCK LOW FILTER FILTER control.)
MANUAL
BY-PASS
SYSTEM 1
BY-PASSED
MANUAL
BY-PASSED
SYSTEM 2
BY-PASSED
PUMP 1 PUMP 2 OIL LEVEL PUMP 1 PUMP 2
Procedure for Adding Oil to the Steering Gear System
SYSTEM 1 SYSTEM 2
Steering instructions will be sent to the steering gear compartment through
the sound powered telephone and the steering gear controlled locally using As described earlier, the hydraulic power pack is made up of three tanks. The
the manual controls on the manoeuvring solenoid valves. The emergency centre tank has an approximate capacity of 2,800 litres and is used to store
MANUAL SYSTEM controls are actuated by inserting a ‘T’ handle into the end of the valve and spare hydraulic oil. The tank is connected by valves, pipework and a small
SYSTEM
SEPARATE
SEPARATED
PANEL
AUDIBLE pushing until the internal spool moves, so directing oil from the pump to the semi-rotary hand pump to the two tanks with the submerged pumps. Should
TEST
rudder actuator. Putting the handle into the other side of the valve and pressing the oil level fall in either of these tanks, the valves from the storage tank can
inwards will reverse the direction of the rudder. A read out of the rudder angle be lined up and oil transferred accordingly by hand.
OVERRIDE
LOW RUDDER
LOW RUDDER
ANGLE
LOW RUDDER
ANGLE
can be obtained by viewing the mechanical rudder angle indicator bolted to the
ANGLE PUMP 1 PUMP 2
top of the actuator. When the storage tank is empty, it can be filled through a filling connection on
HIGH RUDDER
ANGLE
LOW RUDDER
ANGLE
the top of the tank. Any oil transfer to the storage tank should be done with a
small transfer pump that is fitted with a suitable filter. Oil should not be poured
PUMP 1 PUMP 2
Illustrations
d) Slowly open the gland steam make-up and spill control inlet
Procedure for Manual Generator Connection h) Close the gland steam make-up control valve inlet isolating
valve BS11 together with the outlet valve ES6. valve BS11.
The generator can also be connected manually at the main switchboard panel
by using the following procedure:
e) Set the gland steam controller to 1.4kg/cm2. i) Close the gland steam spill control valve inlet isolating valve
ES6.
a) Turn the remote/auto switch to the LM (Local Manual)
f) When full steam pressure is achieved, slowly open the main
position.
stop valve SS05 and close the bypass valve. Check that all the
instrumentation and gauges are open and reading zero when
b) Lower or raise the generator speed until the synchroniser light
appropriate.
slowly revolves in the + direction.
g) Open the bypass valve ES11 around the motorised exhaust
c) Turn the breaker trip/close switch to the CLOSE position
valve ES5 to the main condenser.
to connect the generator to the main switchboard when the
synchroniser light passes the top position.
This allows the vacuum to develop with in the system without adversely
affecting the main condenser vacuum. Check that the main condenser vacuum
d) Turn the remote/auto switch to RA (remote/auto) position to
does not fall significantly.
allow the IAS to control the generator and balance the load with
the No.2 turbine generator.
h) When the vacuum on the local gauge registers -0.7kg/cm2,
operate the motorised exhaust valve ES5 on the local panel
TRUE?. Close the exhaust valve bypass valve ES11.
i) Stop the turning gear motor and disengage the turning gear.
TI TI
Starting Booster
TI TE TI
for Speed Governor Starting Air
Distributor
Starting Air Valve
Alternator in Cylinder Head
T To Speed Governor
Fine Thermostatic Pneumatic Cylinder at each Injection Pump
Filter PDI Valve Centrifugal
Filter
PDS
PI PS PT
M Flame
Starting Fuel Limiter Arrester
PSZ
PI
Starting Air Master
Air Solenoid Valve
Filter
PT
Sump Tank
LS
Key
Lubricating Oil
Air
Electrical Signal
Instrumentation
c) Set up the central fresh water cooling system as in section b) At the local control panel turn the selector switch from
2.4.1. REMOTE to LOCAL and manually start the engine by pressing Emergency Stops
the pushbutton on the main starting valve. Allow it to run up to The engine is automatically shut down in the event of:
d) Check the level of oil in the sump and top up as necessary with normal speed.
the correct grade of oil. • Low lubricating oil pressure - ???kPa
(Note: A pneumatically operated start fuel limiter optimises fuel injection • Cooling water outlet high temperature - ???°C
e) Switch the generator engine prelubricating oil pump to during the acceleration period; the speed of the engine controls the
• Overspeed - 792 rpm
AUTOMATIC operation and check that the lubricating oil start fuel limiter.)
pressure builds up. The engine should be prelubricated at least
The engine is fitted with a number of alarms for various systems such
2 minutes prior to start. c) Make a thorough check of the engine to ensure that there are
as lubricating oil pressure and temperature, cooling water pressure and
no leaks and the engine is running smoothly and firing on all
temperature, charge air temperature, etc.
f) Check the pressure before and after the filters. cylinders.
g) Check the governor oil level. d) Check that the LO pressures and temperatures are normal. Engine Control
h) Check the air pressure in the starting air reservoir. e) Check that the pressure drop across the filters is normal. The diesel generator starting and stopping is normally controlled by the power
management system. See section 2.12.2 for details.
i) Turn the engine at least one complete revolution using the f) Check that the FO pressure and temperature is normal.
turning gear with the cylinder indicator cocks open. Remove
the turning gear. g) Connect the generator engine to the switchboard.
j) Vent the jacket cooling water space. h) Ensure that the engine temperatures and pressures remain
within normal limits as the load is applied to the engine and the
If any part of the engine has been drained for overhaul or maintenance, check engine heats up.
the level in the central fresh water cooling expansion tank and refill with fresh
water if necessary. i) Check the exhaust gas temperatures for deviation from normal.
k) Open the vent on the cooling water outlet line on the generator j) Check the exhaust gas for smoke.
air cooler, and close it again when all air has been expelled.
k) Keep the charge air temperature under control.
If maintenance work has been carried out on the engine, start the engine locally
as below, prior to switching the engine to automatic operation.
l) Check that all fuel pump indexes are at index ‘0’, when the
regulating shaft is in the STOP position.
f) When the engine has stopped, check that the heater switches
on. Turn the control switch to the AUTO position to restore the
engine to automatic standby.
Procedure to Manually Start the Emergency Diesel Engine
(Using the Air Starter)
c) Ensure that the air receiver is fully charged and that the air hose
to the air starter is secure.
j) To stop the engine turn the selector switch to the OFF position
or press the START/STOP pushbutton.
k) Restore the electric starter and set the engine to AUTO operation
with the electric starter.
2.12.2 Main Switchboard and Generator Operation 2.12.2a Switchboard Generator Control Panels
2.12.7 Preferential Tripping and Sequential Restart 2.12.3c Deck Switchboard 440V Distribution
2.12.8 24 Volt Battery System and Uninterruptible Power Supply 2.12.3d Main 220V Distribution
2.12.9 Cathodic Protection System 2.12.3e Emergency 440V and 220V Distribution
Auto/
Transformer
Soft Main Transformer Port Starter Soft
Main Transformer Stbd
Starter 3000kVA AC3300/440V Starter
CP1 CP2 CP3 CP4 HDC BT 3000kVA AC3300/440V HDC CP5 CP6 CP7 CP8
Earthing Cargo Cargo Cargo Cargo HD Auto/ Bow HD Auto/ Cargo Cargo Cargo Cargo Earthing
Transformer Pump Pump Pump Pump Compressor Transformer Thruster Compressor Transformer Pump Pump Pump Pump Transformer
(Port) No.1 No.1 No.1 No.1 (Port) (Starboard) No.2 No.2 No.2 No.2 (Starboard)
Tank No.1 Tank No.2 Tank No.3 Tank No.4 Tank No.1 Tank No.2 Tank No.3 Tank No.4
Auxiliary Feed Water Pump
LD LD
Galley / Laundry AF
LDC Compressor WP
Compressor LDC
Engine and (Port) (Starboard) Engine and
Transformer 440V Cargo Starters Cargo Starters Transformer
Normal Lighting Frequency Frequency Converter Frequency Normal Lighting
440V Converter Converter
Shore Shore
Connection Connection
No.1 No.2
Steering Gear Pump Steering Gear Pump
Accommodation Lights
Steering
Gear
220V
Emergency
Generator Transformer
G
Emergency Lighting
Key
Auto/
Transformer
Soft Main Transformer Port Starter Soft
Main Transformer Stbd
Starter 3000kVA AC3300/440V Starter
CP1 CP2 CP3 CP4 HDC BT 3000kVA AC3300/440V HDC CP5 CP6 CP7 CP8
Earthing Cargo Cargo Cargo Cargo HD Auto/ Bow HD Auto/ Cargo Cargo Cargo Cargo Earthing
Transformer Pump Pump Pump Pump Compressor Transformer Thruster Compressor Transformer Pump Pump Pump Pump Transformer
(Port) No.1 No.1 No.1 No.1 (Port) (Starboard) No.2 No.2 No.2 No.2 (Starboard)
Tank No.1 Tank No.2 Tank No.3 Tank No.4 Tank No.1 Tank No.2 Tank No.3 Tank No.4
Auxiliary Feed Water Pump
LD LD
Galley / Laundry AF
LDC Compressor WP
Compressor LDC
Engine and (Port) (Starboard) Engine and
Transformer 440V Cargo Starters Cargo Starters Transformer
Normal Lighting Frequency Frequency Converter Frequency Normal Lighting
440V Converter Converter
Shore Shore
Connection Connection
No.1 No.2
Steering Gear Pump Steering Gear Pump
Accommodation Lights
Steering
Gear
220V
Emergency
Generator Transformer
G
Emergency Lighting
Key
The 440V starters are generally of the Direct On Line (DOL) type, for example • Load dependent start
Sea Water Pump, Fresh Water Cooling Pump, or the Star Delta Starter type, for • Blackout restart
example Ballast Pump, Water Spray Pump.
• Load sharing/net frequency control
(Author’s Note: Presence of group starter boards or individual locally • Start blocking of heavy consumers
positioned starters to confirm.) • Preferential trip
Sequential Restarting
The generator PMS has the following facilities:
Essential service motors, which were in service before a blackout, are started
automatically on recovery of the main bus voltage. They will start according • Short circuit, overcurrent, overload and reverse power tripping
to the predetermined restarting sequence. Motors that were selected for duty protection for the generators and network via operation of the
before the blackout are automatically returned to duty after the blackout. circuit breaker, circuit breaker undervoltage trip or network
Similarly, motors selected for standby are automatically returned to standby. preferential trips
See section 2.12.7 for further information. • Power, voltage, frequency and current measurement (local and
Preference Tripping remote) of the generators and main bus/network
Non-essential loads are interrupted automatically in the case of an overcurrent • Earth monitoring
on any one of the main generators. This provides continuity of supply to the • Control of the number of running generators in accordance with
essential consumers. See section 2.12.7 for further information. the ship’s power demand
• Earth switch open The diesel generator PMS consists of four main control functions: The IAS blocks the engine from stopping if the engine is in local control or not
• Breaker motor spring charged reset from a previously corrected alarm
• Diesel engine start/stop on request or automatically from the
• Breaker in remote control PMS
A normal stop sequence of the engine can be caused by:
• REM545 in the logic position. • Diesel engine safety system
• Stop request from an operator station
• No synchronisation block signal • Control and auxiliary systems
• Load dependent stop from the PMS if the generator is in standby
• Enable restart from protective devices • Alarm and monitoring of the diesel engine mode
1. Engine start and stop, on request or automatically from the PMS. The engine
Disconnect by the IAS start sequence can be activated if it is in the standby mode and as a result of Diesel Generator Breaker Connect/Disconnect
The breaker disconnect can be initiated when the following apply: the following conditions:
• Disconnect request from an operator station • Start request from operator station (will start and connect to the Connect by the IAS
bus bar)
• Load dependent stop (if the generator is in standby mode) The generator breaker connect can be initiated if the generator is in the standby
• Bus bar blackout (will start and connect to the bus bar) mode and as a result of the following:
• Safety system of the connected generator activated (if the
generator is in standby mode) • Load dependent start (will start and connect to the bus bar and • When a connect request is sent from an operator station
share the load with the running turbine generator)
• Load dependent start
The breaker will be prevented from disconnecting when the following apply: • Start request from heavy consumers (will start and connect
• Start request from heavy consumer
• Breaker in local control to the bus bar and share the load with the running turbine
generator) • Bus bar blackout
• Internal blocking (e.g. not reset after downloading time-out)
• Boilers tripped or low/low steam pressure at turbine generator • Safety system of a turbine generator is activated
• Disconnect interlocked
(will start and connect to the bus bar and share the load with the
• Alarm start of any connected generator
running turbine generator)
The opening of the generator breaker is possible when:
• Generator load <10% of generator nominal load In order to start the diesel engine, the IAS gives a start signal of 10 seconds. If
• No interlock active the engine does not start in this time, a waiting time of 60 seconds is activated
before another start is attempted.
If the engine fails to start, a START FAILURE alarm is sounded and the
start failure must be reset on the diesel module before a new start can be
performed.
b) On the menu list click on the DISCONNECT button to Due to the limited short circuit rating of the 440V switchboards and to prevent
disconnect the generator from the main switchboard. load transfer between the port and starboard 3,300V switchboards via the
440V switchboards there is an interlocking system between the two 3,300V
(Note: The following procedure is for the diesel generator only.) transformer feeders and the 440V transfer breaker whereby only two of the
three can be closed at the same time. If the two transformer feeders are closed,
c) Before stopping, allow the engine to run for a few minutes for the transfer breaker will be open. The transfer breaker can be closed if only one
cooling down purposes, eg. the exhaust gas temperatures. transformer feeder is closed. To change the set up of the breakers, short time
parallelling is allowed. The breaker to close gets a close signal and closes. If
d) Finally, click on the DG icon to display the menu and click on this breaker does not receive a signal that one of the other two breakers has
STOP on the menu to stop the engine. opened within 40 seconds, it will trip.
e) Ensure that the LO pump starts when the engine stops. In addition to this, the 3,300V and the 440V transfer breakers are interlocked
whereby, if the 3,300V transfer breakers are not closed, the 440V transfer
breakers cannot close except when only one transformer feeder is closed and
Procedure to Manually Connect the Diesel or Turbine one open.
Generator to the Main Switchboard
Key
Transformer
440V
3300V
2P Main Switchboard Starboard Interconnection - 2400kW 38P Vacuum Pump No.1 - 37kW 2S Main Switchboard Port Interconnection - 2400kW 38S Vacuum Pump No.2 - 37kW
3P Port AC220V Feeder Panel 39P Bilge Pump - 35kW 3S Starboard AC220V Feeder Panel 39S Reciprocating Bilge Pump - 4.6kW
4P Emergency Switchboard Interconnection - 550kVA 40P Engine Room Exhaust Funnel Port No.1 - 17.5kW 4S Emergency Switchboard - 550kW 40S Sanitary Hot Water Equipment (2 Pumps/2 Heaters) - 26kW
5P Shore Connection Port - 732kW 41P Engine Room Fan Aft Port - 43kW 5S Shore Connection Starboard - 732kW 41S Engine Room Fan Aft Starboard - 43kW
6P Engine Room Switchboard Supply No.1 - 175kW 42P Engine Room Exhaust No.1 - 17.5kW 6S Engine Room Switchboard Supply No.2 - 175kW 42S Engine Room Exhaust Funnel Starboard - 17.5kW
7P Low Duty Compressor No.1 - 175kW 43P Inert Gas Room Exhaust - 0.75kW 7S Low Duty Compressor No.2 - 280kW 43S Steering Gear Room Exhaust/Fan - 3.8kW
8P Steering Gear Main Supply No.1 - 105kW 44P Foam Room Exhaust - 0.5kW 8S Steering Gear Main Supply No.2 - 105kW 44S Incinerator Room Exhaust - 0.5kW
9P Main Sea Water Circulation Pump No.1 - 200kW 45P Gas Duct Hood Exhaust No.1 - 2.5kW 9S Main Sea Water Circulation Pump No.2 - 200kW 45S Gas Duct Hood Exhaust No.2 - 2.5kW
10P Main Sea Water Circ. Pump No.3 - 200kW 46P Paint Store Exhaust - 0.2kW 10S Main Sea Water Circulation Pump No.3 - 200kW 46S Purifier Room Exhaust - 3.5kW
11P Sea Water Cooling Pump No.1 - 75kW 47P Forced Draught Boiler Fan No.1 - 160kW 11S Sea Water Cooling Pump No.2 (Machinery) - 75kW 47S Welding Area Exhaust - 0.5kW
12P Main Condensate Pump No.1 - 45kW 48P Forced Draught Boiler Fan No.3 - 160/70kW 12S Main Condensate Pump No.2 - 45kW 48S Forced Draught Boiler Fan No.2 - 160kW
13P Drain Pump No.1 - 22kW 49P Seal Air Boiler Fan No.1 - 3.7kW 13S Drain Pump No.2 - 22kW 49S Seal Air Boiler Fan No.2 - 3.7kW
14P Drain Pump No.3 - 22kW 50P Air Conditioning Compressor No.1 - 162kW 14S Auxiliary Circulating Sea Water Pump - 75kW 50S Air Conditioning Compressor No.2 - 162kW
15P Sea Water Cooling Pump No.1 (Cargo) - 26.5kW 51P Provision Refrigeration Plant - 13kW 15S Sea Water Cooling Pump No.2 (Cargo) - 26.5kW 51S Technical Spaces Air Conditioning - 136kW
16P Fresh Water Cooling Pump No.1 (Machinery) - 65kW 52P Bridge Window Defrosting - 12.62kW 16S Fresh Water Cooling Pump No.2 (Machinery) - 75kW 52S Bridge Air Conditioning - 3kW
17P Fresh Water Cooling Pump No.1 (Cargo) - 17kW 53P Auxilliary Feed Water Pump Supply (Sulzer) - 560kW 17S Fresh Water Cooling Pump No.2 (Cargo) - 17kW 53S Electric Feed Water Pump Supply No.2 - 560kW
18P Cargo Spraying Water Pump - 230kW 54P Electric Room Switchboard Supply No.1 - 75kW 18S Service Crane (Cargo Compressor Room) - 22kW 54S Electric Room Switchboard Supply No.2 - 75kW
19P Nitrogen System Supply Unit 1 - 9.7kW 55P Inert Gas Dryer Unit (Panel 8) - 195kW 19S Nitrogen System Supply Unit 2 - 9.7kW 55S Inert Gas Sea Water Cooling Pump - 275kW
20P Main Feed Turbine Pump Starter No.1 - 4kW 56P Control Air Compressor No.1 - 54kW 20S Main Feed Turbine Pump Starter No.2 - 4kW 56S Control Air Compressor No.2 - 54kW
21P Fuel Oil Transfer Pump No.1 (Forward) - 34kW 57P Nitrogen Compressor No.1 - 52kW 21S Fuel Oil Transfer Pump No.2 (Forward) - 34kW 57S Nitrogen Compressor No.2 - 52kW
22P Lubrication Oil Purifier No.1 - 6.6 + 1.8kW 58P Service Air Compressor No.1 - 44kW 22S Lubricating Oil Purifier Pump No.2 - 6.6 + 1.8kW 58S Service Air Compressor No.2 - 44kW
23P Inert Gas Blower No.1 (Panel 10) - 230kW 59P Starting Air Compressor - 11kW 23S Inert Gas Blower No.2 (Panel 11) - 230kW 59S Inert Gas Freon Cooler Unit (Panel 7) - 230kW
24P HFO Boiler Pump No.1 - 22kW 60P Bow Thruster Hydraulic Pump No.1 - 11kW 24S HFO Boiler Pump No.2 - 22kW 60S Bow Thruster Hydraulic Pump No.2 - 11kW
25P Spare 61P Main Turbine Turning Gear - 11kW 25S Auxiliary Lubricating Oil Pump No.2 (Turbine) - 75kW 61S Diesel Generator Turning Gear Control Box - 2.6kW
26P Turbine Generator Auxiliary LO Pump No.1 - 3.7kW 62P Electrical Test Switchboard 26S Turbine Generator Auxiliary LO Pump No.2 - 3.7kW 62S Workshop Switchboard
27P Glycol Pump No.1 - 8kW 63P Fresh Water Generator (Sea Water Cooling) - 22kW 27S Glycol Pump No.2 - 8kW 63S Fresh Water Generator (Condensate Cooling) - 6.2kW
28P Stern Tube Lubricating Oil Pump No.1 - 1.7kW 64P Cargo Hose Crane Port - 95kW 28S Stern Tube Lubricating Oil Pump No.2 - 1.7kW 64S Cargo Hose Crane Starboard - 95kW
29P Turbine Generator Turning Gear No.1 - 0.75kW 65P Provision Crane Port - 52kW 29S No.2 Turbine Generator Turning Gear - 0.75kW 65S Provision Crane Starboard - 52kW
30P Deck Machinery Aft Hydraulic Pump No.1 - 145kW 66P Deck Machinery Forward Hydraulic Pump No.1 - 135kW 30S Deck Machinery Aft Hydraulic Pump No.2 - 145kW 66S Deck Machinery Forward Hydraulic Pump No.2 - 145kW
31P Deck Machinery Aft Hydraulic Pump No.3 - 145kW 67P ACC440V Feeder Panel Galley and Laundry 31S CO2 Room Exhaust - 0.5kW 67S Chemical Products Store Exhaust - 0.2kWy
32P Ballast Pump No.1 - 340kW 68P Impressed Current System Aft - 13kW 32S Ballast Pump No.2 - 340kW 68S Impressed Current System Forward - 6kW
33P Jockey Pump - 75kW 69P Air Conditioning Fans and Units Port - 130 kW 33S Ballast Pump No.3 - 340kW 69S Air Conditioning Fans and Units Starboard - 125 kW
34P Spray/Stripping Pump Tank No.1 - 14.9kW 70P Freefall Lifeboat Winch - 10 - 5 - 13kW 34S Spray/Stripping Pump Tank No.2 - 22.4kW 70S Rescue Boat Winch - 20kW
35P Spray/Stripping Pump Tank No.3 - 14.9kW 71P Spare 35S Spray/Stripping Pump Tank No.4 - 22.4kW 71S Spare
36P Spare Spray/Stripping Pump Port - 22.4kW 72P Glycol System Electric Heater - 90kW 36S Spare Spray/Stripping Pump Starboard - 22.4kW 72S Deck Machinery Forward Hydraulic Pump No.3 - 145kW
37P Emergency Cargo Pump (Interconnection) - 224kW 73P Feed Water Motor Valve No.1 (Boiler) - 1.5kW 37S Emergency Cargo Pump - 168kW 73S Feed Water Motor Valve No.2 (Boiler) - 1.5kW
74P Sewage Transfer Pump No.1 - 4.8kW 74S Sewage Transfer Pump No.2 - 4.8kW
75P Auxilliary Circulating Sea Water Pump (Interconnection)
Key
Transformer
3,300 Volts
6.3 Spare 6.19 Forward Deck Machinery Sea Water Cooling Pump - 13kW
6.4 Valves Actuators for Steam Turbine Generators - 1.7kW 6.20 MDO Purifier - 3.6 + 0.66kW
6.5 Lubricating Oil Transfer Pump - 2.5 kW 6.21 Sanitary Fresh Water Unit - 6.4 + 6.4kW
6.6 Sludge Pump - 6.4 kW 6.22 Aft Deck Machinery Control Panel - 1kW
6.7 Diesel Oil Transfer Pump - 6.4kW 6.23 Forward Deck Machinery Control Panel - 1kW
6.8 Fuel Oil Transfer Pump - 34kW 6.24 Sootblower Relay Panel
6.9 Cathodic Protection for Main Condenser (Turbine) - 5kW 6.25 N2H4 Injection Equipment - 0.4kW
6.10 Oily Water Separator - 3.35kW 6.26 Boiler Water Chemical Injection Equipment - 0.4kW
6.11 Inert Gas Fuel Oil Pump (Panel 12) - 2.5kW 6.27 Diesel Generator Preheater Unit Pump - 31kW
6.12 Low Duty Condensate Pump (Turbine) - 18.5kW 6.28 Diesel Generator Prelubricating Unit Pump - 6.9kW
6.13 High Pressure Cleaning Machine - 16kW 6.29 Lubricating Oil Electric Feed Water Pump - 0.75kW
6.14 UPS 24V Accommodation Services 3.6kW 6.30 Valve Starter 1st Bleed Steam - 0.75kW 3.3kV From 3.3kV From
Port Main Starboard Main
6.15 Gas Oil Transfer Pump - 1.3kW 6.31 Valve Starter 2nd Bleed Steam - 0.75kW Switchboard Switchboard
Main Transformer Port Auxiliary Feed Water Pump Main Transformer Starboard
3000kVA AC3300/440V AF 3000kVA AC3300/440V
WP
Transformer Transformer
Frequency Converter
440V From
Emergency Switchboard
440V Feeder Panel
Key
(Author's Note: Confirm no other services are supplied from this board.)
Transformer
3,300 Volts
440/220/24 Volts
Circuit Breaker
4 Bow Thruster and Hydraulic Room Fan 8.6kW 5.20 Further Information Required ?????
6 Electric Motors Room Fan No.1 4kW 5.22 Further Information Required ?????
7 Electric Motors Room Fan No.2 4kW 5.23 Further Information Required ?????
8 High Duty Compressor No.1 Oil Pump 2.5kW 5.24 Further Information Required ?????
9 High Duty Compressor No.2 Oil Pump 2.5kW 5.25 Further Information Required ?????
10 Low Duty Compressor No.1 Oil Pump 2.5kW 5.26 Further Information Required ?????
12 Forward Welding Machine 440V Socket 5.28 Further Information Required ?????
5.14 Further Information Required ????? 5.30 Further Information Required ?????
5.15 Further Information Required ????? 5.31 Further Information Required ?????
3.3kV From 3.3kV From
Port Main Starboard Main 5.16 Further Information Required ?????
Switchboard Switchboard
102P M01 Double Bottom Lighting Box Supply No.1 - 46kW Transformer 102S M01 Double Bottom Lighting Box Supply No.2 - 46kW
103P M02 First Platform Lighting Box Supply No.1 - 46kW 3,300 Volts 103S M02 First Platform Lighting Box Supply No.2 - 46kW
104P 220V Cargo Control Switchboard Supply No.1 - 27kW 440/220 Volts 104S 220V Cargo Control Switchboard Supply No.2 - 27kW
Circuit Breaker
105P 220V Navigation Equipment Swbd No.1 Supply No.1 - 38kW 105S 220V Navigation Equipment Swbd No.2 Supply No.1 - 26kW
106P Refrigeration Air Dryer No.1 - 1.9kW 106S Refrigeration Air Dryer No.2 - 1.9kW
107P H01 External Lighting Box Supply No.1 - 65kW 107S H01 External Lighting Box Supply No.2 - 65kW
108P H02 Navigation Bridge Deck Lighting Box Supply No.1 - 18.6kW 108S H02 Navigation Bridge Deck Lighting Box Supply No.2 - 18.5kW
109P H03 E Deck Lighting Box Supply No.1 - 23.3kW 109S H03 E Deck Lighting Box Supply No.2 - 23.4kW
110P H04 D Deck Lighting Box Supply No.1 - 19.5kW 110S H04 D Deck Lighting Box Supply No.2 - 18.8kW
3.3kV From 3.3kV From
111P H05 C Deck Lighting Box Supply No.1 - 21.2kW Port Main Starboard Main 111S H05 C Deck Lighting Box Supply No.2 - 21.2kW
Switchboard Switchboard
112P H06 B Deck Lighting Box Supply No.1 - 21.5kW 112S H06 B Deck Lighting Box Supply No.2 - 22.8kW
113P H07 A Deck Lighting Box Supply No.1 - 8.9kW 113S H07 A Deck Lighting Box Supply No.2 - 9kW
Main Transformer Main Transformer
114P H08 Main Deck Lighting Box Supply No.1 - 5.3kW 114S H08 Main Deck Lighting Box Supply No.2 - 5.3kW
Port 3000kVA Starboard 3000kVA
115P Navigation Lighting Switchboard Supply No.1 - 3kW AC3300/440V AC3300/440V 115S Technical Spaces Air Conditioning - 1kW
AF
116P Boiler Control Panel No.1 Boiler Part - 1.6kW LV Transformer Port WP LV Transformer Starboard 116S Boiler Control Panel No.2 Boiler Part - 1.6kW
440/220V 250kVA 440/220V 250kVA
117P Temperature Monitor for Port 3.3kV Transformer Frequency Converter 117S Electrical Test Switchboard
118P Signal and Provision Room Alarm Switchboard - 2kW 118S Temperature Monitor for Starboard 3.3kV Transformer
120P Engine Distribution Switchboard Supply No.1 - 24.5kW 119S Control Cabinet Provision Crane Starboard - 2kW
121P Provisions Refrigeration Plant - 9.8kW 120S Engine Distribution Switchboard Supply No.2 - 24.5kW
122P Inert Gas Control Panel (Panel 2) - 7.6kW 121S Engine Control Room Console - 7kW
123P Marine Growth Preventing System (Antifouling Aft) - 1kW 122S Spare
124P H11 Galley and Starboard Pantry Box Supply No.1 - 24.2kW 123S Marine Growth Preventing System (Antifouling Fwd) - 0.06kW
125P H12 Pantry and Duty Mess Box Supply No.1 20.8kW 124S H11 Galley and Starboard Pantry Box Supply No.2 - 19.8kW
126P H13 Laundry Box Supply No.1 - 38.3kW 125S H12 Pantry and Duty Mess Box Supply No.2 15.5kW
127P Forward Switchboard 220V Power Supply No.1 - 7kW 126S H13 Laundry Box Supply No.2 - 37.5kW
128P 110V DC System for the 3.3kV Switchboard Port 127S Forward Switchboard 220V Power Supply No.2 - 7kW
129P Heater Piping Sanitary Water - 10kW 128S 110V DC System for the 3.3kV Switchboard Starboard
130P Dehumidifier Panel From the Main Turbine - 1.3kW 129S Toilet Module - 1kW
131P Sootblower Control Panel 130S Spare
132P UPS No.1 Main Supply - 12kVA 131S Spare
133P Air Dryer No.1 (Autoregenerative) - 0.5kW 132S UPS IAS - 12kVA
134P Spare 133S Air Dryer No.2 (Autoregenerative) - 0.5kW
135P UPS No.3 IAS Convertor Room - 12kVA 134S UPS No.4 IAS Deck Electric Room - 12kVA
Transformer
3,300 Volts
3.3kV From 3.3kV From
Starboard Main 440/220/24 Volts
Port Main AF Circuit Breaker
Switchboard WP Switchboard
Transformer Main Transformer Main Transformer Transformer
Frequency Converter
Port 3000kVA Starboard 3000kVA
AC3300/440V AC3300/440V
Emergency
G Generator
Transformer
Emergency Switchboard
24V
Two shore power connection boxes are installed on the vessel, one on the port
side and one on the starboard. They are used during dry docks and refits to
provide the vessel with power from ashore when the vessel’s normal power
generator facilities are unavailable. The maximum current rating for each shore
connection is 1,200 amps.The port shore connection box is connected via a
breaker to the port main 440V switchboard and the starboard shore connection
box via a breaker to the starboard main 440V switchboard. With the port and
starboard main 440V switchboard bus tie breaker closed, power to either shore
connection box can supply both the port and starboard main switchboards.
Alternatively, with the bus tie breaker open, power can be supplied to both
shore connection boxes and the port and starboard shore connection boxes can
feed the port and starboard main 440V switchboards separately. If both shore
connection boxes are being supplied with power, the bus tie breaker must be
open.
WARNING
Do not attempt to close the circuit breaker for the shore power source
while the main transformers or the emergency generator are supplying
power to the main switchboards. o not attempt to close the circuit breaker
for the main transformers or the emergency generator while the shore
power is supplying power to the main switchboards.
Description (Author’s Note: The information required to complete this section is currently
Two main steam turbine generators and one main diesel generator are fitted. unavailable - where is the input power for the DECS from and what are the
They are all of the totally enclosed, cylindrical rotor, self-excited, brushless numbers of the AVR’s which will determine the specifications of each AVR ?)
type fitted with an integral air to fresh water cooler.
Emergency Cooling
Generator cooling is provided by passing air over the integral fresh water
If the cooling system fails, the alternator may still be run on reduced load with
cooler, using a closed circuit air supply. The cooler is constructed of double
the emergency ventilation in place, as follows;
tubes, the outer tube has internal grooves. The grooves drain any leakage
water from the primary tubes, which is drained out via a clearance between
a) Open all side cover plates on both sides of the alternator.
the primary and secondary tube plate to the leakage detector, which will raise
an alarm via the IAS alarm system.
b) Remove the plates but do not remove the nets behind them.
Space heaters are fitted which are energised when the generator circuit breakers
c) Close the emergency cooling plate on the top of the generator to
are open. These protect against internal condensation during shutdown periods.
block the top module airflow.
Six PT100 sensors are embedded in the stator to monitor the temperature in
each phase winding, three are active and three are spare. These temperatures
During emergency cooling the alternator protection is lowered to IP 21, therefore
can be monitored from the Integrated Automation System (IAS) screen mimics
the ingress of dirt must be kept to a minimum. The winding temperatures must
and will raise alarms when the temperature set points are exceeded.
be closely monitored when operating in this condition.
Bearings
The main bearings are of the self-lubricating sleeve type using oil ISO VG68.
EMERGENCY SWITCHBOARD
24V
Starting
1 2 3
Battery
Emergency Generator
4 5 6 Engine Control Panel
ACB Control
27 28 29
7 8 9 Emergency Generator
ACB
30
10 11 12 13 14
Monitoring/Control
Battery
Charger
15 16 31
Excitation Control
AVR
Key
32 33 34
1 - Power Measure 21 - xxx xxx
2 - Reserve Power Relay 22 - xxx xxx
17 18 19 20 21
3 - Over Current Relay 23 - xxx xxx
4 - Insulating Measure 24 - xxx xxx
22 23 24 Engine Control/
5 - Intensity Measure 25 - xxx xxx
Alarms/Monitoring
25 6 - Voltage Measure 26 - Emergency Generator
7 - Insulating Fault Relay Switch 27 - Load on Pressure
26
8 - Ammeter Switch 28 - RPM & xxx Counter
9 - Voltmeter Switch Frequency Measure 29 - Cool Water Temperature
10 - Earth Lamp Phase R 30 - SELCO Controller
11 - Earth Lamp Phase S 31 - Buzzer
12 - Earth Lamp Phase T 32 - Operation Switch
Automatic
13 - Heating On 33 - Governor Supply Starter Motor
Voltage
14 - Frequency Measure 34 - Start Switch Regulator
To test run the emergency diesel engine, the switch is turned to position1
(START TEST). The emergency diesel engine will run up but the emergency
generator will not feed the emergency switchboard. Upon completion of the
test, the switch is returned to the normal position 0 and the emergency diesel
engine stopped.
Putting the switch in position 2 (START + COUPLING TEST) will once again
run up the emergency diesel engine. Once voltage has been established from
the emergency generator, normal power will be removed from the emergency
switchboard and the emergency generator breaker will close. The emergency
switchboard will be fed from the emergency generator. Upon completion of the
test, the switch is returned to position 0 and, upon detection of normal power,
the emergency generator breaker will open and the main switchboard breaker
will close. The emergency switchboard will once again be fed from the main
switchboard.
The emergency diesel engine will run off load for a cooling down period of
approximately 5 minutes.
(Author’s note: Confirm that return to ship’s power is automatic operation not
manual??)
Back-Feeding from the Emergency Switchboard to the Main 440V
Switchboard
Preferential Tripping
First Stage
The power management system matches the generator capacity to the power IGG Freon Compressor 5" 59S
Preference Trips Third Stage No.1 Cargo Pump
requirements of the vessel. However, should a main generator or main 5 Seconds No.1 IGG Blower 5" 23P Preference Trips
transformer be overloaded to 105% of rated current for a set period of time, 15 Seconds No.2 Cargo Pump
certain service groups will be disconnected. Trip No.1 No.2 IGG Blower 5" 23S
Trip No.3 No.3 Cargo Pump
Air Conditioning (Fan and Units) Starboard 5" 69S
If the overload occurs in the 440V services (main transformers), the Trip No.1 Trip No.3
No.1 HD Compressor
disconnection is detected by an overload relay in the following sequence: Air Conditioning (Fan and Units) Port 5" 69P
No.2 HD Compressor
Technical Spaces Air Conditioning 5" 51S
• If the main transformers experience a 105% overload for a
period of 5 seconds, TRIP No.1. will be initiated. Transformer Galley and Laundry 5" 67P
• If the 105% overload is maintained on the main transformers for No.1 Service Air Compressor 5" 58P
a further 5 seconds, TRIP No.2. will be initiated. No.2 Service Air Compressor 5" 58S
If the overload occurs in the 3.3kV services, the disconnection is detected by No.1 Air Conditioning Compressor 5" 50P
the power management system with the following sequence
No.2 Air Conditioning Compressor 5" 50S
Second Stage
No.3 Ballast Pump 10" 33S
Preference Trips
10 Seconds No.2 Ballast Pump 10" 32S
Trip No.2
Navigation 24V DC Distribution Switchboards No.1 and No.2 Engine Room Services 24V DC Distribution Switchboards No.1 and No.2
V V
BT1 BT1
24V 110Ah 24V 110Ah
4 x 6VE110 FB2 4 x 6VE110 FB2
150A 150A
BT2 BT2
24V 110Ah 24V 110Ah
4 x 6VE110 4 x 6VE110
6A 6A 16A 16A
N1 -1 Conning Display Control Computer N2 -1 Sound Signal Reception Unit VSS-111 E1 -1 Boiler Control Panel No.1 - Boiler Part E2 -1 TG2 Turbine Supervisory Panel No.2
6A 6A 16A 16A
N1 - 2 ECDIS Route Planning and Chart Digitiser N2 - 2 Watch Safety System E1 - 2 Auxiliary Engine Safeties No.1 E2 - 2 Turbine Starter Feed Water Pump No.2
6A 6A 16A 16A
N1 - 3 Weather Facsimile Receiver N2 - 3 Steering Gear Alarm/Start-Stop Panel E1 - 3 TG1 Turbine Supervisory Panel No.1 E2 - 3 Oil Mist Detector
6A 6A 16A 16A
N1 - 4 No.1 Bridge Alarm Monitoring System N2 - 4 Rudder Indicator Amplifier E1 - 4 Turbine Starter Feed Water Pump No.1 E2 - 4 Spare
6A 6A 10A 10A
N1 - 5 Watch Safety System (Main) N2 - 5 Aldis Lamp E1 - 5 Steering Gear Alarm Cabinet E2 - 5 Auxiliary Engine Safeties No.2
6A 6A 10A 10A
N1 - 6 Gyrocompass N2 - 6 Master Clock System E1 - 6 Main Turbine Junction Box HTJ E2 - 6 Spare
6A 6A 10A 10A
N1 - 7 Batteryless Telephones N2 - 7 Navtex Receiver E1 - 7 Main Turbine Junction Box LTJ E2 - 7 Inert Gas Control Panel 2
6A 6A 10A 10A
N1 - 8 Compass Binnacle N2 - 8 No.2 Gyrocompass E1 - 8 ECR Console E2 - 8 Self Cleaning LO Turbine
6A 6A 10A 10A
N1 - 9 Rate of Turn Indicators N2 - 9 No.2 Bridge Alarm Monitoring System E1 - 9 MainTurbine Manoeuvring Control Box Energy Source E2 - 9 Central Cabinet External Water Spray System
6A 6A 10A 10A
N1 - 10 Workstation and Mode Control Box (Main) N2 - 10 Bow Thruster Control Panel E1 - 10 Main Turbine Sub Panel (ECR Console) E2 - 10 MainTurbine Manoeuvring Control Box Trip Circuit Source
6A 10A 6A 6A
N1 - 11 No.1 Autopilot Electronic Unit N2 - 11 Typhon Whistle E1 - 11 Cargo Hydraulic Power Pack E2 - 11 Boiler Control Panel No.2 - Boiler Part
6A 10A 6A 6A
N1 - 12 No.2 Autopilot Electronic Unit N2 - 12 Emergency Typhon Whistle Pushbutton E1 - 12 UHF Internal Communications E2 - 12 Ballast Hydraulic Power Pack
6A 10A 6A 6A
N1 - 13 No.3 VHF Transceiver N2 - 13 ECDIS Chart Table Terminal Board E1 - 13 Water Detector in Boiler Oil Pipe E2 - 13 Spare
6A 10A 6A 6A
N1 - 14 Gyrocompass Switch Over Unit N2 - 14 Turbine Bridge Control Panel E1 - 14 Spare E2 - 14 Spare
6A 10A 6A 6A
N1 - 15 No.1 DGPS Navigator N2 - 15 No.2 DGPS Navigator E1 - 15 Spare E2 - 15 Spare
10A 10A
N1 - 16 Public Address System N2 - 16 Anemometer System
10A 10A
N1 - 17 Multifunction Display N2 - 17 DS50 and DS80 Doppler Speed Logs
16A 10A
N1 - 18 CO2 Box Power Supply No.2 N2 - 18 No.1 Autopilot Electronic Unit Alarm
6A 10A
N1 - 19 Loran-C Navigator N2 - 19 No.2 Autopilot Electronic Unit Alarm
6A 10A
N1 - 20 Echosounder Distribution Box FE-702 N2 - 20 Workstation and Mode Control Box Alarm
6A 10A
N1 - 21 Electromagnetic Door Release System N2 - 21 Inmarsat Mini M System
• O/P Load = x% : Approximate percentage of UPS load capacity The boards and chargers are designed for continuous operation and are
being used by the protected equipment. practically maintenance free. However, the units should be kept clean and
• O/P Watt = xW : Output watts dry and a visual inspection of connection integrity, cable condition etc, made
once a year. At this time the charging voltages should be checked using a high
• O/P VA = xVA : Output VA quality digital voltmeter. All batteries should be kept clean and dry. The battery
• O/P Cur = x.xA : Output current poles and connections must be kept covered with acid free vaseline. The cell
voltages should be checked and logged once a month and the connection
• BAT VOLT = xx.xV : Battery voltage
terminals checked for tightness once a year.
• BAT CHARGE = xxx% : Approximate percentage of battery
capacity remaining. (Author’s Note: The location and operation of the charger to be confirmed.)
• Back Up Time = xxxM : Approximate battery time remaining
in minutes. Display changes to seconds when less than 1 minute
remains (xxxS)
• CPU Version x.xx
The UPS will exit this mode automatically after five seconds if the RETURN
button is not pressed.
Remote Monitoring
Panel
Rudder Stock Aft Power Supply Unit Forward Power Supply Unit
Bonding Input 440V 60Hz 1PH Input 440V 60Hz 1PH
Output 400A DC 24V Output 200A 24V DC
Bosun Store
Shaft mV
Meter
0 250
mV
IAS
Shaft Millivolt
Monitoring Panel Monitoring Brushes
100A Anode Reference Cell 100A Anode in Engine Room 100A Anode Reference Cell (Insulated From
Earth/Mounting)
Shaft Earthing
Brushes
JB JB JB JB JB
JB JB JB JB JB
100A Anode Reference Cell 100A Anode 100A Anode Reference Cell Propeller Shaft Earthing
and Monitoring Assembly
System Wiring
Illustrations
Fish -25°C Evaporator Meat -25°C Evaporator Vegetables +2°C Evaporator Dairy +3°C Evaporator Lobby +3°C Evaporator
S S S S S
Heating Heating
Coil Coil
Ozone
Generator
LP HP Manifold HP LP Manifold
AP AP
Motor Motor
Oil Manometer Oil Manometer
Key
Refrigerant Gas
Refrigerant Liquid
Filter
Lubricating Oil
Purge Purge
Valve Valve Cooling Water
Electrical Signal
Condenser When all the solenoid valves at the evaporators are closed by the room High Pressure Switch and Alarm
Model: Unable to determine thermostats, the low pressure switches will stop the compressor.
This switch has a double contact with a lever system which automatically
Type: Horizontal shell and tube closes one contact when the other opens. When the first contact is opened the
Evaporator pressure regulating valves are included in the lobby, vegetable and
dairy rooms to prevent these rooms dropping too far below the normal set compressor motor will stop and when the second contact closes an alarm will
Introduction point, which would damage the provisions should the inlet solenoid valves fail sound.
Cooling of the fish/meat rooms, vegetable room, dairy room and the lobby is to close properly.
provided by a direct expansion system. Low Pressure Switch and Alarm
Any leaks of refrigerant gas from the system will result in the system becoming
This cut-out switch protects the compressor in the event of undercharge. As
The plant consists of two compressors, two condensers, a refrigerant tank undercharged. The symptoms of an undercharged system will be low suction
previously mentioned low refrigerant pressure can lead to excess oil migration
and an evaporator coil in each of the four cold rooms plus one in the lobby. and discharge pressures with the system eventually becoming ineffective. A
in the gas.
Thermostatic expansion valves are fitted prior to each evaporator coil and an low charge level may result in excess lubricating oil being entrapped in the
oil separator is installed between each compressor and condenser. refrigerant and thus showing a low sump level. The refrigerant tank is fitted
with two sight glasses and the level should be checked at regular intervals. Oil Differential Pressure Switch
During normal operation one compressor will service all the cold rooms whilst Used as a safety switch for protection against too low a lubricating oil pressure
the other is on standby, but left on manual start-up, with all its valves shut. If the system does become undercharged and a leak is suspected the whole in the refrigeration compressor. If the oil pressure fails the compressor will be
system must be checked thoroughly using a gas leak detector. stopped after a time delay set at ???.
Cycle of Refrigeration When necessary, additional refrigerant can be added to the system using the
The compressor draws vapour from the cold room evaporators via the aspiration refrigerant load valve. Ensure the hose between the bottle and load valve System Running Checks at Regular Intervals
collector and pumps it under pressure to the water cooled condenser where the is properly vented of air before tightening the connection fully. The added • Cold room temperatures
vapour is condensed before returning to the refrigerant tank as a liquid. The refrigerant is dried at the dryer filter before entering the system. Any traces
of moisture in the refrigerant gas will lead to problems with the thermostatic • Evaporation coils for any signs of frosting
oil separator helps to remove any oil entrapped in the gas and returns it to the
compressor crank case via the oil return line. valves icing up and subsequent blockage. • Lubricating oil level in compressor crankcase
A thermostat in each cold room enables a temperature regulating device • Lubricating oil pressures
The liquid refrigerant is returned through the dryer and sight glass to the liquid
collector before passing through the manual isolation valves and to the cold to operate the solenoid valves independently thus reducing the number of • Suction and discharge pressures
room evaporators. starts and running time of the compressor. Each thermostat also provides
• Moisture indicators
alarm indication to the alarm panel situated in the ??? room if the cold room
temperatures vary from the set parameters. • Refrigerant tank level
• Fan belt tension
Fish -25°C Evaporator Meat -25°C Evaporator Vegetables +2°C Evaporator Dairy +3°C Evaporator Lobby +3°C Evaporator
S S S S S
Heating Heating
Coil Coil
Ozone
Generator
LP HP Manifold HP LP Manifold
AP AP
Motor Motor
Oil Manometer Oil Manometer
Key
Refrigerant Gas
Refrigerant Liquid
Filter
Lubricating Oil
Purge Purge
Valve Valve Cooling Water
Electrical Signal
h) Open the refrigerant returns from the cold rooms. Defrosting only takes place on the meat and fish room evaporators. Due to the
operating temperatures of the lobby, dairy and vegetable rooms, the associated
i) Check the compressor safety settings. evaporators do not require defrosting.
j) Open the compressor suction valve one full turn. The defrosting system has two modes of operation. Automatic and manual,
the latter being intended to permit manual defrosting in the event of a
k) Start the compressor. breakdown.
l) Continue to slowly open the suction valve taking care not to The fans are disconnected during defrosting to avoid hot air getting into the
allow liquid back to the compressor and keeping the suction cold store. Power is isolated from the solenoid valves, which prevents cooling
pressure above the cut-out point. liquid entering the evaporators.
CAUTION For greater safety, the compressor does not disconnect during defrosting
If the oil in the crankcase foams or knocking noises are heard from the times, in order to absorb the gases produced by the evaporation of liquid due
compressor, this indicates that droplets of liquid are being fed in with the to the rise in temperature. Running times for the compressor during defrosting
suction gas. The suction valve must be throttled in immediately. periods are very short, as it only has to absorb the evaporation of the liquid
already in the evaporator.
m) Once the suction valve is fully opened and the compressor is
running normally it is recommended that a full check of the When the temperature of the defrosting thermostat reaches the set point, the
system be carried out. heating elements are switched off. The meat and fish room evaporator fans
will not start until the evaporator coil surface temperature has dropped below
freezing.
Key
Refrigerant Liquid
Saturated Steam
Condensate
Cooling Water
Air
Key
Refrigerant Liquid
Saturated Steam
Condensate
Cooling Water
Air
4 3 2 1 8 9 9
Operation of the Air Conditioning System
I Suct.temp.
Suct.temp.
Disch.temp.
-25°C
-25°C
38°C
Set
Disch.temp. 38°C
The air conditioning system is designed to run with one compressor supplying Oil
Oilpress.
press. 4.3
4.3bar
bar
5 6 7 9 9
one air handling unit, however crossover valves allow two compressor/ Ready
Ready 0%
0%
condensers to be used by one air handling unit. To prevent damage if this is R O
to be undertaken, the plant must be stopped and all valves set to the correct
position for the crossconnection before selecting the mode on the controller.
The compressors can be run on either automatic or manual mode. Manual and
automatic modes are selected at the controller. A yellow lamp directly above
the manual/automatic key button will indicate when manual mode is selected.
(Note: This operation may need to be repeated several times to ensure all the
4 3 2 1 8 9 9 gas is collected in the receiver.)
I Suct.temp.
Suct.temp.
Disch.temp.
-25°C
-25°C
38°C
Set
c) The liquid receiver can now be isolated by closing the inlet
Disch.temp. 38°C
5 6 7
Oil
Oilpress.
press. 4.3
4.3bar
bar 9 9 valves.
Ready
Ready 0%
0%
R O
YORK
Refrigeration
UNISAB II
Daily Running Checks on Air Conditioning Compressor d) Isolate the compressor motor.
• The lubricating oil pressure and level e) Close the compressor suction valve.
• Suction and discharge pressures
f) Close the compressor discharge valve.
• Liquid receiver level
• A regular system of refrigerant gas leak detection should be g) Close the cooling water valves on the condenser.
implemented to ensure leaks are detected at an early stage
h) Shut off the steam supply to the air handling unit.
To Stop the Compressor
To Shut Down the Compressor for a Prolonged Period or Maintenance
a) In automatic mode the compressor will start and stop as
determined by the control system. The compressor can be shut If the air conditioning system is to be shut down for a prolonged period, it is
down manually as follows. advisable to pump down the system and isolate the refrigerant gas charge in
the receiver.
b) Reduce the compressor capacity to a minimum by using the key
marked No.3, in the above illustration. Allow the compressor to This operation requires the compressor to be in the manual mode.
pump down the system so that the refrigerant is collected in the
condenser and receiver. a) Close the outlet valve from the liquid receiver and reduce the
capacity control on the compressor. It may be necessary to
c) Stop the compressor using the key marked No.7, in the above reduce the low pressure trip setting to prevent the compressor
illustration. Alternatively, close the liquid receiver outlet valve from cutting out.
and allow the compressor to run until the suction pressure drops
low enough to operate the low pressure trip. b) The compressor will eventually trip on low suction pressure.
After a period of time the suction pressure may rise, in which
Compressor
Maker: Bitzer
Model: 2 HC 2.2Y Semi-hermetic
Power supply: 3 phase 440v
Quantity: ???
Refrigerant: R-507
Description
(Author’s note: Further information is required on this system to complete this
section.)
The selfcontained air conditioning units are supplied with cooling circuits only
and do not have the ability to be used as local heaters. They are equipped with
circulating fans, a filter, an evaporator, a condenser and a compressor.
The desired cooling temperature can be selected at the control panel located
on the front of the unit.
oil with the use of gas oil to assist the combustion when required. The unit is
capable of burning 50 litres of waste oil per hour or 400 litres per charge of The electric control panel is installed on the incinerator and contains fuses, 4
compacted solid waste. A combination of both is allowed to a maximum of starters, PLC and operator panel. The operator panel, which is located at the
5
400,000kcal/hour. right hand side of the control panel has an LCD display and keys for selecting
burner modes. 6
fuel heater and electric control panel ambient air through the cooling jacket on the combustion chamber. The hot 4 5 6
7
• Flue gas fan gas from the furnace is diluted with the cooling air at the flue gas outlet on 1 2 3
9 PREV 11 MAIN 12
Stop Burner Stage No 1 a) Load the incinerator and close the incinerator door.
When pressed will stop all selected programs and activity. If the combustion Gas oil nozzle no. 1 in use.
chamber temperature is above 220°C the flue gas fan will continue to run until b) At the programme controller set the burning time (this depends
the temperature has decreased to 170°C and the door lock is released. on the amount of solid waste but is automatically repeated from
Burner Stage No 2
the previous burning). If 0 burning time is selected the burning
Gas oil nozzle no. 2 in use. will continue until the STOP button is pressed.
Slagging
This mode is used for slagging of the incinerator. It closes the flue gas damper c) If LOADING/SLAGGING is shown on the display press the
Burner Stage No 3
and starts the flue gas fan. The doors can be left open during this period. STOP button. The flue gas fan will stop and ‘READY’ will be
Gas oil nozzles no. 1 and 2 in use. displayed in line 4 of the LCD.
Solid Waste
Burner Stage No 4 d) Press the SOLID WASTE pushbutton and ‘SOLID WASTE’
Used for burning of solid waste loaded in the combustion chamber. The will be displayed in line 4 of the LCD for 5 seconds. The
incinerator is started in stage 3 and the gas oil burners and combustion air is Gas oil nozzle no. 1 in parallel with sludge burner. incinerator programme will commence with the flue gas fan and
controlled by the PLC. When the combustion chamber temperature exceeds gas oil burner operating when the conditions are correct. The
850°C the door lock on the sluice door is energised and the feeding of solid Burner Stage No 5 green LEDs for FG Fan, Burner and Running are illuminated.
waste can begin.
Gas oil nozzle no.2 in parallel with sludge burner.
e) When the set burning time has expired or the STOP button is
Solid Waste/Sludge pressed the burner will stop and the cooling down sequence will
Burner Stage No 6 commence. ‘COOLING’ is displayed in line 4 of the LCD.
This mode starts the incinerator in the solid waste mode but will change
over automatically to burn sludge controlling up to a maximum capacity Gas oil nozzle no. 1 and 2 in parallel with sludge burner.
f) When the temperature in the combustion chamber has fallen
whilst consuming a minimum of gas oil. The sludge capacity is controlled
below 170°C the flue gas fan will stop and the door interlocks
automatically and will be limited by the combustion chamber temperature. Burner Stage No 7 will be released.
Sludge burner only without diesel oil support.
Sludge
This mode is used to burn sludge at the maximum capacity whilst consuming
a minimum of gas oil. The chamber is heated by burning gas oil and will
automatically switch to sludge when the temperature reaches 650°C. The
incinerator will only burn sludge alone when the combustion chamber reaches
850°C.
h) When the combustion chamber has fallen below 170°C the flue MARPOL Annex V contains the following prohibitions for the discharge of
Non-burnable Dry Waste
gas fan will stop and the door interlocks will be released. solid waste outside special areas:
Non-burnable dry waste production for approximately 50 persons is given as
• No discharge of plastics
20kg per day or 80 to 100 litres per day without compacting.
Burning Solid Waste and Sludge • No discharge of buoyant dunning, lining or packing material
For simultaneous burning of solid and oil wastes, reduce the rate of waste within 25 nautical miles
Other Waste
oil burning to avoid an overheat trip. Oily rags etc., must be loaded in small • No discharge of garbage within 12 nautical miles. Food waste
quantities only (approximately 3kg per loading) and must not be present in the may be discharged if ground into pieces smaller than 1 inch • Oily rags may be burnt in the incinerator in small quantities
combustion chamber unless the induced draught fan is running.
• No discharge of any solid waste, including food waste, within 3 • Containers which were used for oils or chemicals must be
nautical miles stored on board and discharged ashore
Emergency Stop
• Incinerator ash must be on board in the location of a special
The incinerator may be stopped in an emergency by turning the main switch site if less than 12 nautical miles from land, otherwise the ash
on the control panel to the OFF position or by activation of the EMERGENCY can safely be dumped overboard but a log should be kept of the
STOP pushbutton located outside the incinerator room. amount dumped.
Illustrations
From
Ion Ejector T Feed Water Heater C
Silver Salt Steam a S Ejector
PI DF49 Salinity
Steriliser Condenser
Indicator TI C From
S Main/Auxiliary
Mineraliser Condensate Pump
a
SC
Discharge
TI TI e
TIC
Supply
DF48 From Heating
From Power Distillate Steam
Key Supply
Cooler
C
2ND 1ST M
SC
Stage Stage
Condensate/Distilled Water C
T
Distillate To Bilge
Steam Chemical
Pump To Vacuum
Cleaning
Fresh Water Chemical To Atmos. Chemical Condenser
Pump To Clean
C Injection Tank Drain Tank M SC
Cleaning
Instrumentation From Power Drain Tank
Tank
Supply
Electrical Signal Brine
Pump To Bilge
Sea Water
H
VA64
CS41 CS42 CS62 CS2 High Sea Chest
VA25 To
PI PI
To Cargo To Machinery 4018 Fresh Water 4020 Fresh Water To Fire Fighting
High Sea Chest Fresh Water Fresh Water Spray Generator Generator Jockey VA63
To Ballast Pumps To Inert E E
Coolers Coolers Pump Pump Pump Pump Steam
Steam Gas Generator (7.0m3/h 3
VA24 (45m /h
Cooling PI
4 bar)
PI
4 bar) Low Sea Chest
4017 4019
Hot Water Circulating Pumps Introduction Sea water feed to both evaporators is chemically treated in order to prevent
foaming in the evaporator and reduce the risk of scale formation.
Maker: There are two fresh water evaporators installed and these operate at low
No. of sets: 2 pressure using desuperheated steam as the heat source (see section 2.1). One Distillate from the FW evaporators is discharged to the domestic fresh water
fresh water evaporator is of the two stage flash type and employs sea water for tanks and the stern tube cooling water tank if required. The supply of water to
Type: Centrifugal
cooling but the other evaporator is of the low pressure submerged tube type the fresh water tanks first passes through a rehardening filter and then a silver
Model: which employs condensate for cooling. ion steriliser before flowing to the tanks. When the distillate is directed to the
Capacity: 2.0m3/h at 1.0kg/cm2 distilled water and stern tube tank the rehardening filter and silver ion steriliser
Each fresh water generator is self-contained with its own combined brine/air plant is bypassed.
ejector and distillate pump. The air ejector is driven steam which creates a
Steriliser (Silver Ion)
vacuum in the system in order to lower the evaporation temperature of the To continuously check the quality of the fresh water produced by each of the
Maker: Jowa AB feed water. distillation plants a salinometer is provided at the distillate outlet.
No. of sets: 1
Model: Jowa AG-S Flash Evaporator If the salinity of the produced fresh water exceeds the chosen maximum value,
Type: Silver ion the dump valve and alarm are activated to automatically dump the produced
The flash evaporator has two stages of evaporation, the second stage chamber fresh water to the bilge.
Capacity: 2.0m3/h fresh water being maintained at a lower pressure than the first stage. Sea water feed is
heated by means of a heater supplied with 0.1kg/cm2 desuperheated steam,
external to the evaporator unit. The heated sea water enters the first stage of the
evaporator where some of the water evaporates because the temperature of the
first stage is lower than the evaporation temperature of the brine corresponding
to the pressure in the first stage chamber.
TI PI PI SF20
4013 4007 4006 Located Near Chemical
HP18 Injection Equipment
PI
Ion Silver Salt Calorifier SF19
Sterilizer
HP17
S
Mineraliser 1st
Flat
Aft Peak
To Aft Bilge Well SF16
Tank Purifiers Room Located Near
Atmospheric Condenser
DF50 Key HP SF SF15
07 08
Condensate/Distilled Water HP SF To Oil Monitor on Bilge
Stern Tube 13 14 Separator Discharge
Cooling Tank BB01 Fresh Water HP10 SF12
To Bilge Pump Instrumentation
SF SF SF
68 02 04 HP09 SF11
Holding Bilge
Lubricating Oil Purifiers Diesel Oil Purifier Tank To Bilge
Well
TI PI PI SF20
4013 4007 4006 Located Near Chemical
HP18 Injection Equipment
PI
Ion Silver Salt Calorifier SF19
Sterilizer
HP17
S
Mineraliser 1st
Flat
Aft Peak
To Aft Bilge Well SF16
Tank Purifiers Room Located Near
Atmospheric Condenser
DF50 Key HP SF SF15
07 08
Condensate/Distilled Water HP SF To Oil Monitor on Bilge
Stern Tube 13 14 Separator Discharge
Cooling Tank BB01 Fresh Water HP10 SF12
To Bilge Pump Instrumentation
SF SF SF
68 02 04 HP09 SF11
Holding Bilge
Lubricating Oil Purifiers Diesel Oil Purifier Tank To Bilge
Well
a) Check that there is sufficient water in the domestic FW tank to Valves are shown as open but if the service was not being used the valve would
Engine Room Cold Fresh Water Services System
meet the immediate demand. be closed.
Position Description Valve
b) Vent the fresh water hydrophore tank and, using the No.1 FW Open Water services outlet (near deaerator) SF40 The fresh water system will operate as required with the duty pump operating
pump in local control, fill it until the water level gauge glass is in order to maintain pressure in the system.
Open Water services outlet (near economiser) SF39
¾ full; stop the pump. Suction valves SF63 and SF64 for the
fresh water hydrophore pumps must be open together with the Open Water services outlet (incinerator room) SF38 Domestic Hot Water System
pump discharge valves. The suction valve from 17A fresh water Open Water services outlet (deck store) SF37
tank SF44 should be open: tank 17F is assumed to be filling and This system supplies the hot water to the accommodation for domestic
so its outlet valve SF45 will be closed. Closed Spray system in lifeboat area SF69
purposes.
Open Water services outlet to deck system SF41
c) Connect the air supply line and open the air supply valve and Water is circulated continuously by one of the two the hot water circulating
the hydrophore tank air valve to pressurise the hydrophore Open Water supply to engine room washbasin SF32
pump, the water being passed through a calorifier, which can be either steam
tank from the ship’s air supply system. The hydrophore tank Open Water supply to laboratory washbasin PF35 or electrically heated to raise the water to the correct temperature. Top up to
gauge valves must be open. When the hydrophore tank is at the the system is from the hydrophore tank. The pumps can be changed over if
Open Water services outlet (near FD fans) SF29
correct operating pressure close the air valves and remove the necessary for maintenance. Pumps are started and stopped locally. Pumps
connection pipe. Open Water services outlet (near oil fired boilers) SF28 should be changed over periodically in order to avoid one pump having
Open Water services outlet (inert gas room) SF27 excessive running hours.
d) The fresh water hydrophore tank is now operational and FW can
be supplied to the various users. Open Water services outlet SF26 The system supplies hot water to the accommodation system, the wash basin
Open Water services outlet SF25 in the workshop, the laboratory wash basin, the wash basin in the engine room
e) At the local control panel set both fresh water hydrophore toilet.
pumps to remote and start No.1 pump. The pump will start Open Water services outlet (near ion exchange unit) SF22
and operate in automatic mode with control from the pressure Open Water services outlet (near N2H4 injection unit) SF21
switches stopping and starting the pump as necessary. Procedure for Operating the Hot Water System
Open Water services outlet (near chemical injection unit) SF20
f) Set the valves as in the following table: a) Operate the FW system as above and set the hot water system
Open Water services outlet SF19
valves as follows:
Open Water services outlet (near coolers/atm condenser) SF16
Position Description Valve Open Water services outlet (monitor bilge separator) SF15 Position Description Valve
Open Hydrophore tank outlet valve SF67 Open Water services outlet SF12 Open Calorifier water supply valve SF60
Open Non-return valve to expansion tank make-up DF66 Open Water services outlet SF11 Open Calorifier inlet valve
Open Flow meter inlet valve SF82 Open Water supply to washbasin SF14 Open Calorifier outlet valve
Open Flow meter outlet valve SF80 Open Water services outlet (DO purifier) SF04 Open No.1 hot water circulating pump inlet valve
Closed Flow meter bypass valve SF81 Open Water services outlet (LO purifier) SF02 Open No.1 hot water circulating pump outlet valve
TI PI PI SF20
4013 4007 4006 Located Near Chemical
HP18 Injection Equipment
PI
Ion Silver Salt Calorifier SF19
Sterilizer
HP17
S
Mineraliser 1st
Flat
Aft Peak
To Aft Bilge Well SF16
Tank Purifiers Room Located Near
Atmospheric Condenser
DF50 Key HP SF SF15
07 08
Condensate/Distilled Water HP SF To Oil Monitor on Bilge
Stern Tube 13 14 Separator Discharge
Cooling Tank BB01 Fresh Water HP10 SF12
To Bilge Pump Instrumentation
SF SF SF
68 02 04 HP09 SF11
Holding Bilge
Lubricating Oil Purifiers Diesel Oil Purifier Tank To Bilge
Well
b) After opening the hot water system supply valve from the cold If filling from the operating evaporator the three-way outlet line valve from the
water system, allow the system to fill from the hydrophore evaporator must be set for the distilled water line and the filling valve on the
tank. distilled water tanks must be closed. Distillate from the operating evaporator
will flow to the stern tube cooling water tank.
c) Ensure that the hot water circulating pumps are primed.
d) Start one of the hot water circulating pumps at the local starter
panel.
From Lobby
Bath Discharge
From Dairy
From Distilled
Water Tank
SD12
From Fresh
Water Tank
SD11
SD15
SD14
SD09
SD10
SD05 SD06
SD13
SD16
SD27
Chlorination NC SD
Overboard Discharges
SD04 Tank
28 To Bilge Holding Tank
SD08 SD07 SD28
SD17
SD03 SD21
S
Sewage Treatment PI
SD23 SD23 Plant PI
SD02
LI LT Key
SD18
PI LI LAH
PI LI SD30 Waste Water Lines
SD01 Sewage Holding
Tank (25m3
Sewage Soil Lines
PI PI
Removable SD31
Domestic Fresh Water
Spool SD19
PI Normally
PI NC
SD20 Closed
Fresh Water
Flushing
From Lobby
Bath Discharge
From Dairy
From Distilled
Water Tank
SD12
From Fresh
Water Tank
SD11
SD15
SD14
SD09
SD10
SD05 SD06
SD13
SD16
SD27
Chlorination NC SD
Overboard Discharges
SD04 Tank
28 To Bilge Holding Tank
SD08 SD07 SD28
SD17
SD03 SD21
S
Sewage Treatment PI
SD23 SD23 Plant PI
SD02
LI LT Key
SD18
PI LI LAH
PI LI SD30 Waste Water Lines
SD01 Sewage Holding
Tank (25m3
Sewage Soil Lines
PI PI
Removable SD31
Domestic Fresh Water
Spool SD19
PI Normally
PI NC
SD20 Closed
Fresh Water
Flushing
Open Sewage treatment plant overboard ship side valve SD01 is for use in port or when the vessel is operating in restricted waters. The tank Open No.1 discharge pump inlet valve SD30
is fitted with a level indicator and a level transmitter that will provide an alarm
Open No.1 discharge pump outlet valve SD18
to the engine control room on high level. To line the system up for use in this
b) Check the air intake filter elements on the aerator blowers for mode proceed as follows: Open No.2 discharge pump inlet valve SD31
cleanliness then switch the blowers ON. Open No.2 discharge pump outlet valve SD19
Position Description Valve
c) Set the discharge pumps to AUTO operation. This will allow Open Sewage treatment tank inlet valve SD28
the pumps to start and stop according to the liquid level in the Closed Soil line valve into treatment tank SD13
Closed Sewage treatment tank overboard valve SD27
chlorine contact chamber. Closed Port soil line discharge overboard SD11
Open Port soil line valve to holding tank SD12 The sewage treatment plant can be put back to normal operation and the valves
d) Set the sludge return control valve to AUTO.
Closed Starboard soil line valve from accommodation SD14 opened/closed accordingly as described previously.
e) Check the chlorine injection tank for level and refill if necessary. Open Starboard soil line valve from accommodation to holding
Adjust the flow control valve to the inlet of the plant to achieve tank Maintenance
the desired emissions. Note that for routine on-site testing a SD15
test kit has been supplied which can be used to analyse the To facilitate maintenance a connection from the fresh water system has been
effluent for pH value, dissolved oxygen and chlorine residue. Closed Soil overboard ship side valve SD02
provided to both the sewage treatment plant and the holding tank. Water is
The desired values of each of these elements for good operation Closed Waste water inlet valve into treatment tank SD08 supplied to a spray rail inside the holding tank through valve SD21. The
of the plant are as follows: connection to the treatment plant requires a spool pipe to be fitted between
Closed Port waste water valve to overboard discharge SD05
valve SD20 and the emptying lines from the aeration/clarification/chlorination
Test Location Range Open Port waste water valve to holding tank SD06 compartments. The spool has been incorporated to prevent contamination of
pH Clarifier chamber 6.8 - 8.0 Closed Starboard waste water valve to overboard discharge SD09 the fresh water system.
Oxygen Clarifier chamber 0 - 10.0ppm Open Starboard waste water valve to holding tank SD10
(Authors Note: Check on location of the spool pipe that it does not require
Chlorine Clarifier chamber 0 - 3.5ppm Closed Waste water overboard ship side valve SD03 fitting to allow flushing of the holding tank as well.)
Closed Hospital waste water to treatment tank SD07
h) Check that the blowers and the discharge pump are operating Daily Checks
Open Hospital waste water to holding tank SD22
correctly.
Closed Hospital waste water to overboard SD16 Visually check for any leakage. Check that the sludge is being returned to
the activation compartment from the clarification compartment, and that the
The above listing has assumed that the plant has been operating previously but Closed Hospital waste water overboard ship side valve SD17 discharge pump and the air blower are working. Check that the chlorine dosing
if it has been shut down and emptied for any reason then the following needs
unit is functioning correctly and has sufficient contents.
to be followed.
When operating in restricted waters or in harbour, the sewage treatment plant
Check the operation of the air lift and the air diffusers through the compartment
i) Remove all hatches and visually check for the presence of discharge pumps must be switched off and the overboard discharge valves
portholes.
foreign objects. If the unit is to be cleaned it is important to closed.
only use recommended cleaning agents that will not impair the
biological performance of the unit. When the vessel has left port and is sufficiently clear of coastal waters the
holding tank discharge pumps can be lined up to empty the contents into the
sewage treatment tank or directly overboard.
From Lobby
Bath Discharge
From Dairy
From Distilled
Water Tank
SD12
From Fresh
Water Tank
SD11
SD15
SD14
SD09
SD10
SD05 SD06
SD13
SD16
SD27
Chlorination NC SD
Overboard Discharges
SD04 Tank
28 To Bilge Holding Tank
SD08 SD07 SD28
SD17
SD03 SD21
S
Sewage Treatment PI
SD23 SD23 Plant PI
SD02
LI LT Key
SD18
PI LI LAH
PI LI SD30 Waste Water Lines
SD01 Sewage Holding
Tank (25m3
Sewage Soil Lines
PI PI
Removable SD31
Domestic Fresh Water
Spool SD19
PI Normally
PI NC
SD20 Closed
Fresh Water
Flushing
Waste water from the swimming pool can be drained directly overboard by
opening valve SD26 and the ship side valve SD04. Branched into this line are
also two drainage connections from the ship’s fresh water storage tanks.
The drains from the hospital can be discharged directly overboard or into the
sewage treatment system. Overboard discharge can be achieved by closing
valves SD22 and SD07 leading to the treatment plant and opening valves SD16
and SD17.
The provisions refrigeration chambers, the air conditioning room and the
garbage room all drain down to the bilge holding tank in the engine room. All
other internal drains and scuppers drain down to the engine room bilge wells.
(Authors Note: The manual provided for this system refers to remote start/stop
functions for the sewage treatment discharge pumps. Further information
required on location and function.)
Illustrations
1 1 1 1 2 2 4 5 6 7
8 9 10
11
19
3 18
17 16 15 14 13 12
Electrical
Workshop
Toilet
Lift
Key
1 - IAS Process Station Type PS-400-1 6 - No.1 Boiler Control Panel 11 - Boiler Group Starter Panel (BGSP) 16 - 220V AC Engine Room Services Distribution Switchboard
2 - IAS Process Station Type PS-400-R1 7 - No.2 Boiler Control Panel 12 - ME Lighting Box 17 - Indicators Pillars Relay Box Engine Room
3 - NDU For IAS 8 - No.1 Boiler Flame Scanner Amplifier Rack 13 - M2 Lighting Box 18 - No.1 24V DC Engine Distribution Switchboard
4 - Main Turbine Manoeuvring Control Box 9 - No.2 Boiler Flame Scanner Amplifier Rack 14 - M1 Lighting Box 19 - No.2 24V DC Engine Distribution Switchboard
5 - Soot Blower Control Panel (Boiler) 10 - NDU For IAS 15 - Steering Gear Alarm System
Introduction
The engine control room, situated on the 21800mm deck, is where the
necessary equipment and controls are located which allow the centralised
operation and supervision of the engine room machinery, via the Integrated
Automation System (IAS).
7
10 10
15
13
MOT
ORO
3 4
5 LA
2
1
8
0
6 18
16
PHO
NTE
CH
14
22
1 12 11 Views Alarms Keypad Trackball Views Alarms Keypad Trackball
2
10
3
9
17
CALL 4 HOME MACHINERY BOILER BOILER-1 BOILER-2 COMPUTER POWER ALARM F1 F2 F3 F4 F5 F6 F7 F8
HOME MACHINERY BOILER BOILER-1 BOILER-2 COMPUTER POWER ALARM F1 F2 F3 F4 F5 F6 F7 F8
8
5 PAGE COMMON PAGE COMMON
6
19
CALL
STOP STEAM MAIN ALARM STEAM MAIN ALARM
POWER BILGE DEAD MAN ACK. POWER BILGE DEAD MAN ACK.
SYSTEM TURBINE VIEW 1 2 3 ESC SYSTEM TURBINE VIEW 1 2 3 ESC
11 11
Command Command
20
4 5 6 BKSP HOME END PGUP 4 5 6 BKSP HOME END PGUP
CARGO GAS NGP IGS BALLAST CARGO GAS NGP IGS BALLAST
9
HANDLING
TAKE GIVE STATUS HANDLING
TAKE GIVE STATUS
4
ESD - - SYSTEM - 0 . ESD - - SYSTEM - 0 .
AND GAS GATOR AND GAS GATOR
5 21
12 12
3
23
6
2
9
5
1
8
4
?
7
0
F4
F3
F2
24
F1
25
28 26
FU
R
U
N
O
SP
EE
D 12 k
1
.3 t
27
31
29
50
30
PW
R
ON
10
0
33
VO
12
L
AS
2
0
TE
RN
50
32
minrpm
10
0
-1
12
0
AH
EA
D
Key
34
NA
BC
O
LAM
TEST
P
SOUSTO
NDP
R/U
S/B
35
F/E
1. KYMA Performance Monitor System 13. Boiler Monitor Panel 25. Main Turbine Control Panel
2. KYMA Printer 14. Boiler Operation Panel 26. Forced Draught Fan Vibration Monitor Panel
3. Fire Control Panel 15. Main Turbine Vibration Monitor 27. Electric Feed Water Pump Vibration Monitor Panel
4. CCTV System Monitors 16. UHF Base Station 28. Doppler Speed Log Indicator
5. CCTV System Control Panel 17. PABX Telephone 29. Main Turbine Revolution Counter
6. ICCP Millivoltmeter 18. Vibration Monitor 30. Main Turbine Revolution Indicator
7. Ship's Clock 19. Steering Gear Alarm Panel 31. Nozzle Valve Operation Panel
8. ICCP Remote Monitor Panel 20. Rudder Angle Indicator 32. Cordless Telephone
9. Sound Powered Phones 21. Low Duty Compressors Control Panel 33. Control Mode Changeover Panel
10. IAS Monitors 22. Turbo Feed Pumps Vibration Monitors 34. Turbine Lever Position Indicator
11. IAS Printer 23. KYMA Performance Monitor Panel 35. Telegraph Receiver
12. IAS Control Panel 24. Pressure Gauges
Illustrations
LD HD LD HD
1 1 2 2
PS
-11
220VAC
(UPS2) PS
-12
Mounting Plate
• Cargo and ballast control Monitoring and control is performed by software modules. The basic modules
Each station computer has a hard disk containing the software files for the are:
• Watch call system fitted equipment. Process values to be displayed at the operator stations are
generated in the process stations and transferred to each station as required. • Buttons
• Analogue measurement modules
Main Components
The Operator Interface • Digital measurement modules
The IAS system is made up of operator and history stations connected by a The graphic displays are shown on the monitor of the operator stations. These • Pulse measurement modules
dual bus to the Network Distribution Units (NDUs) and the process stations. displays show all or part of a system or process using standard symbols to
The process stations contain the input/output cards to and from the equipment represent the actual plant/equipment (valves, motors etc). Events (alarms and • Motor/pump control modules
controlled and/or monitored. messages) are also shown on the displays. • Valve control modules
• PID controller modules
Operator Stations The operator panel is used to interact with the display and control the process.
This is achieved by the use of the trackball and buttons to point and click on
The operator stations are the main interface between the operator and the All display views are made up from a set of standard modules. The symbols
symbols and menus.
processes under the operator’s control. The operator station has a colour on the screen are the symbols associated with these modules, valves, motors,
monitor, an operator panel with buttons and trackball and a controller measurements etc.
computer. These are installed in the cargo control room, the bridge and the Displays and Views
engine control room. The system is made up of the following types of views: Symbols
• Process The symbols indicate the operational mode and status of the represented
History Station equipment (motor/pump etc) by means of tag mark characters and changes in
• Flow
A history station is a specific computer on the network which runs the operator colour and appearance. Illustration 3.2.2b shows the common module symbols
• Event used within the system.
station software. It also contains the historical database, storing an historical
(time/date) series of process (samples). These series are used to produce trends • Trends
and reports at the operator and history stations. • Equipment
Kongsberg Panel
Command
4 5 6 BKSP HOME END PGUP
CARGO GAS NGP IGS BALLAST
HANDLING TAKE GIVE STATUS
The system’s operator/user interface is the monitor screen, control panel and Command Group • Flow: Showing the process equipment under system control
alphanumeric keyboard. The screen displays the system views and the operator for software configuration
This group contains the TAKE, GIVE and STATUS buttons. These buttons
panel is used to interact with those views. The alphanumeric keyboard is used allow the operator to transfer control of the process from one operator station to • Event: Showing process events and events generated by the
for set-up and configuration purposes. The operator panel is used to interact another. The TAKE and GIVE buttons allow the operator to transfer command system
with the views on the screen, display a new view or to act upon an element control between the operator stations. Above each of these buttons there is a • Trends: Showing historic trend curves for process variables
within a view. green status LED that indicates control transfer status. The STATUS button
allows the operator to view the current status of the command control. • Equipment: Showing the status of the process and operator
The layout of the pushbuttons, lamps and controls on the operator panel are control units
divided into six functional groups, as shown in illustration 3.2.2a.
View Selection Group Both process and flow types of view can display the same information.
This group contains three buttons that are used to display a map of the existing Normally, process views are used by the system. The system can also present
Views Group
views and select previous views or related views. The NAVIGATOR button detailed information regarding a single component, eg, a motor, valve or
The buttons of the views group select and display the views representing the displays the navigator dialog box. The LEFT ARROW button returns the pump.
various process areas. The most important and commonly used views are operator to the view displayed before the current one. The RIGHT ARROW
assigned to these buttons so that they are instantly accessible from the operator button displays the next view listed in the history navigator dialog box. This information is then displayed via the following dialog boxes:
panel. Each button is labelled with the name of the view. To display the views
• Single Point View: Shows the current operational status of
assigned to these buttons, the operator should press the appropriate button.
Keypad Group the module together with a trend (if configured) and selected
adjustable parameters
Above each button is a red status LED, which will flash when any This group contains FUNCTION, NUMERIC and CURSOR CONTROL
unacknowledged alarms are active in the view assigned to that button. When arrow buttons. The function buttons (F1 to F8) are user-definable. • Module Parameters: Shows all the adjustable parameters of the
all the active alarms in the view are acknowledged, the LED illuminates module
steadily. If there are no active alarms in the view, the LED will be off. The numerical and keypad buttons (ESC, SPACE etc) are used to enter values • Module Terminals: Shows the connection terminals of the
into dialog boxes, when setting parameters or required levels. module together with their signal values
There are are several different ways to navigate through the views of the IAS
system: The cursor control buttons (HOME, END, ARROWS etc) can be used to move • Show Connection: Shows the connections to and from the
between fields in dialog boxes and to scroll through lists. module terminals
• Using the views buttons on the operator panel
• Alarm Configuration: Shows the alarm limits set for the
• Using the previous view and next view buttons on the tool bar module
Trackball Group
• Using the history navigator which records the last 10 screens • I/O Card: Shows the input/output configuration and connections
viewed This group consists of three unannotated buttons and a trackball. The trackball
is used to position the cursor on the screen. of the module terminals
• Using the navigator • Module Status: Shows the operational configuration of the
• Using hot spots The left button is used to select symbols, open and operate menus and click module
buttons in the views and dialog boxes displayed on the screen. The right
• Using the context menu of a module • AIM Time Series Explorer: Allows the management of module
button is used to open pop-up context menus. The middle button is not
terminal series and parameter time series
used. These buttons are similar in action to those in a standard mouse button
Alarms Group configuration.
This group contains three indicator lamps and three buttons that are used to
indicate, acknowledge and handle alarms and events. (The COMPUTER and Alphanumeric Keyboard
POWER lamps are not used). The ALARM lamp flashes when unacknowledged The alphanumeric keyboard is a standard, QWERTY keyboard that is located
alarms are active in the system. When all the active alarms in the system in a compartment under the operator panel. A keyboard selection switch is
are acknowledged, the lamp becomes steadily illuminated. If there are no fitted to select the keyboard. When the keyboard is selected, the buttons of
active alarms in the system, the lamp will be off. The ACK button is used to the keypad group are disabled. For a desktop operator station, the keyboard
acknowledge alarms. selection switch is a toggle switch located on the back of the operator panel.
MANUAL
Acknowledge Acknowledge Acknowledge
Purifier Single Speed Pump
a a
Acknowledge (Stopped) Running
Module Operation Menu with Module Operation Menu Single Speed Electrical
Unavailable Commands Removed Motor/Pump Operation Menu
Dual Speed Electrical Non-Return Valve H L Dual Speed Pump
Motor/Pump Operation Menu
(Stopped) Running
97MC70942 X 21XV0180 X 21XV1540 X 21XV1570 X
Hand Operated Valve Single Speed Motor
(Not Under IAS Control)
M
0% CLOSE CLOSE CLOSE
100% STOP OPEN OPEN
Three Way Hand Operated Valve M M Dual Speed Motor
L H
SETPOINT OPEN SETPOINT RESET (Stopped) Running
DOWN 10% MANUAL Digital Valve Operation Menu Manually Operated Valve Circuit Breaker (Open)
(Not Under IAS Control)
Acknowledge
FREEZE
Acknowledge PID Controller (Manual) Generator
AUTO Control Valve Operation Menu G
Throttle Valve Operation Menu Numeric input
MANUAL OK
Inc PID Controller (Auto) Transformers
66.4 Cancel
Acknowledge Dec
Some of the menu commands are global, ie, available for all views, all users The commands on this menu are: The commands on this menu are:
and all modes (eg, the log off command on the file menu), whilst others are Acknowledge Command control PCU operation Navigator History Zoom centre
specific. If the menu commands are ‘blanked’ it means that they are unavailable
in the current context. HS operation Zoom point Zoom percent Zoom rectangle
Inc. display level Dec. display level Preferences
Tools Menu Redraw
Process View Menus
The commands on this menu are:
The commands on these menus are as follows: Browse modules Module status list Module editor
Message monitor Report system Alarm groups The following flow view menus have identical commands and contents as the
File Menu process menus:
System Menu
The commands on this menu are: Module Operation Tools
The commands on this menu are:
New image Save image Save image as System Panel Help
Palette Select time zone Set system time
Image properties Print image Event printer
Set time zone OS configuration OS config. mode
Print screen Exit Tool Bar
PCU configuration mode
The tool bar at the top of the display contains short cut buttons to many
Edit Menu commonly used functions. The type and function of the buttons displayed will
Panel Menu
The commands on this menu are: vary according to the display selected, blanked buttons are unavailable.
The commands on this menu are:
Undo Redo Cut
Lamp test Last Alarm Line
Copy Paste Add hot spot
This line is located just below the tool bar on the display and will always show
With the exception of Add hot spot, these are standard Windows NT editing Help Menu the most recent alarm.
commands that are not used with process views. The commands on this menu are:
About AIM/OS Image Area
V The area of the display showing the selected process, event, trend, flow and
This option displays details about the AIM operating system installed at that equipment view images.
operating station.
(Note: Flow views are for software configuration only and should not be used IAS System Modes
Input/Output View
as the user interface.)
The input/output view shows information on the input/output cards in a The system has four operational modes:
Event Views selected process station. It can be displayed by clicking the input/output view
These views are defined for displaying system and process events and form no button on the toolbar.
1. Monitoring
part of the view hierarchy.
This mode is for personnel who require access to the system but are not
View Hierarchy
qualified to operate it. To enter this mode the user’s name must be a member
Trend Views All the views in the system (except for the event and equipment views) are of the guest’s user group.
Trend views can be displayed as independent views, associated with process arranged in a configurable hierarchical system. The view hierarchy is shown
areas. They either form part of the view hierarchy or part of other views, eg, in the navigator dialog box, accessible from the navigator button.
2. Operational
single point views.
The view hierarchy comprises several levels, where the first (top) level This mode is for normal system operation. To enter this mode the user’s name
The trend system controls the displaying, creating and appearance of trends. represents a process system such as ballast or cargo. This top level view often must be a member of the user’s, power user’s or administrator’s user group.
It can create and present several trends in a view and allows splitting of these provides an overview of the process, whereas process details or components
trend windows on several levels. will be found in the second (lower) level views. Trend views are located on the 3. OS Configuration
second (lower) level.
A trend is the presentation of single or multiple trend curves in a scaled axis The user’s name must be a member of the administrator’s user group.
system. There are two different types of trend presentation: If all the available information for a process is included in a single process or
flow view, there is no lower level view for that system other than trend views. 4. PCU Configuration
1. Trend view: Has a fixed size, filling the screen
The first (top) level views are connected to the views buttons on the operator
2. Trend pop-up: Small, resizable, remains displayed irrespective panel. The user’s name must be a member of the administrator’s user group.
of the view selected and can be positioned anywhereon the
screen.
Both of these displays have a context menu for controlling their appearance.
The status of command control can be monitored using the status or command • A square status indicator preceding a text field • Equipment: Showing the status of the process and operator
status buttons. Command control can be transferred using the GIVE and TAKE • A bar graph indicator colour and the background colour of its control units
buttons or via the respective commands from the command control menu. numeric value field
Both process and flow types of view can display the same information.
Events Alarms can be suppressed individually or in groups (engines etc). The system Normally, process views are used by the system. The system can also present
also uses a system of alarm, event and horn filters to select which events are detailed information regarding a single component, eg, a motor, valve or
The event system handles reporting, presentation and storing of events within
displayed and annunciated at operator stations. Filters can be modified or pump.
the IAS system. The system provides the following:
created from the ‘select filter’ dialog box.
• Presentation of events This information is then displayed via the following dialog boxes:
• Event view The system uses colours to illustrate alarm priority levels as follows:
• Alarm indications in process views • Yellow: 1. Low priority Shows the current operational status of the module together with a trend (if
• Red: 2. High priority configured) and selected adjustable parameters.
• Alarm and message printing
• Audible alarm • Magenta: 3. Critical priority
Module Parameters
• Alarm acknowledgement • Cyan: Alarm disabled
Shows all the adjustable parameters of the module.
• Alarm suppression • Brown: Module not active or I/O
disabled
• Event filtering
ON DUTY WATCH BRIDGE UNIT ALARMS ON DUTY WATCH CABIN UNIT ALARMS
CHIEF CHIEF
ENG. MACHIN ENG. MACHIN
1ST 1ST
ENG. CARGO ENG. CARGO
Dead Man
System Bridge Bridge
3RD SELECT 3RD SELECT
Is Active Watch ESD Watch ESD
ENG. ENG.
Illustrations
Saturated Steam
Air Inlet Outlet
Economiser
Manhole (Front)
Removal Space
for Flame Eye
Maintenance Space
for Access Hole
Flame Eye
Steam Drum
Water Drum
Access Hole
Two seal air fans are supplied, one for each boiler. The seal air fan provides
cooling and sealing air to the burner flame eyes.
The seal air pressure is monitored by the IAS, and an audible alarm operates
when the pressure falls to below the set point of 3.5kPa. The IAS performs
the Duty/Standby logic for the fans. The operator must select which fan is to
be used as duty fan using the button DUTY 1 or DUTY 2, then press the ON
pushbutton to start the duty fan. The fan which is not selected as duty, will act
as standby for the running (duty) fan and start automatically upon detection
of a signal from the automatic boiler control system, or if the duty fan trips. A
STANDBY STARTED alarm will appear on the standby fan.
Control Control
PS-M6
IAS Alarm Cabinet
Control
Alarms Start/Stop
Alarms Alarms
Alarms Alarms
OS-6
OS-5 Key
Electrical Signal
The BMS remotely operates the three LNG/FO combination burners situated The desired fuel mode can be selected using the fuel mode switch on the ECR Condition Set Point Location
in the boiler roof. A dual programmable controller, used in the control section or CCR graphic operation panel, but only when the BMS automatic mode is Boiler tripped Local
of the BMS, enables a sequential operation of the LNG/FO combination burner selected. Fuel oil pressure low-low 1.0kg/cm2 Local
and piston valves. These are interlocked with the boiler protection system and Fuel oil temperature low-low 80°C Local
the ACC. The distributed control system DCS displays the flow of the sequence (Note: The fuel mode can not be changed directly from fuel oil to gas or from Atomising steam pressure low-low 3.0kg/cm2 Local
and the operation of the interlock on a graphic operating panel. gas to fuel oil.) Both fuel oil pumps stop No voltage Starter
There are three operating positions/modes: Prior to changing the fuel mode, the following interlocks must be established: The boiler fuel gas shut-off valve is operated by the following:
• Boiler gauge board BGB - This is a priority position/mode and
Fuel oil to dual firing mode
allows operation of the LNG/FO combination burner but not the Condition Set Point Location
operation of the master boil-off gas supply and the boiler gas • Master gas valve must be open Master gas valve tripped Local
supply. Boiler tripped Local
• GAS IGN. RATE OK signal from the automatic combustion
• Engine control room ECR - All remote operation of the LNG/ control Boil off gas header pressure high-high 75kPa Local
FO combination burners can be made in this position/mode. Boil off gas header pressure low-low 0.7kPa Local
• GAS CONT V/V IGN lamp must be on
• Centralised control room CCR on D deck - All remote operation
The boiler fuel gas master shut-off valve is operated by the following:
of the LNG/FO combination burners can be made in this
Dual firing to gas oil mode
position/mode.
• FO EXTINGUISH OK signal from the automatic combustion Condition Set Point Location
control Both boilers tripped Local
Selection of Operating Mode Both boiler gas valves tripped Local
• FO CONT V/V IGN LAMP must be on
Manual master gas trip operated BGB, ECR, CCR
The BGB position is selected for the initial burner start, but once the burner is Gas leak detection Local
in operation the control position is selected as follows: Gas firing to dual firing mode Boil off gas temperature low-low 5°C Local
• FO IGN. RATE OK signal from the automatic combustion Gas duct exhaust fan stop Local
Boiler Gauge Board (BGB) to Engine Control Room (ECR) control ESDS activated Local
Engine room fans - only 50% running Local
The ECR pushbutton is pressed on the BGB boiler graphic operating panel. • FO CONT V/V IGN LAMP must be on
Once the ECR position is established, the ECR is maintained, even in a
blackout, unless the BGB pushbutton is pressed to reclaim the operating
The system also includes a number of automatic safety operations as follows:
position.
The boiler is tripped by the following:
(Note: The BGB operation position has priority over the ECR and CCR and
can be selected at any time, however the BGB operation position
cannot control the boil-off gas operations.) Condition Set Point Location
All burner flames fail Local
FD fan trip Local
Engine Control Room (ECR) to Centralised Control Room (CCR)
Manual trip BGB, ECR, CCR
The CCR position is selected by pressing the CCR pushbutton on the ECR BMS controller failure Local
boiler operating panel. This has to be followed by the confirmation pushbutton Electrical power failure Local
being pressed at the CCR boiler operating panel. Drum level low-low -240mm Local
Drum level extremely high +240mm Local
Centralised Control Room (CCR) to Engine Control Room (ECR) Control power failure Local
Emergency manual trip ECR and Local
The ECR position is selected by pressing the ECR pushbutton on the CCR Forced draught fan trip Overcurrent Starter
boiler operating panel. This has to be followed by the confirmation pushbutton All burner flame failure Flame out Local
being pressed at the ECR boiler operating panel. Superheated steam temperature high 545°C Local
BF27
BF1013
Main Boiler Desuperheater
BF BF ZS
E BF1020 TI
1064 1065 BF58 BF57 BF56
4113
BF1026
TT
FT BF1001 BF50 5114
From Distilled Water Tanks
1030 ZS
BF61 BF60 BF59 SC SAH
BF1029 BF25
BF1011 2341
BF52
BF49 BF34
From Hydrazine Injection Unit
PAL PI PT
PT TI
0034
6034 4114 ZS ZS ZS
BF68
PI BF33 BF15 BF3 BF2 BF1
0028 PI PI
BF BF To Seal Control To Seal Control
1004 2004
32 31 BF64 BF63 BF62 PDI Valve Valve
Protection 4117
PI PI PI PI
Ring BF2029
4109 4107 1005 2005
FT
2030
E E T T
BF67 BF66 BF65 BF2001
BF2011 Cold Start Feed Electric Feed Turbine Feed Turbine Feed
BF2026 Water Pump Water Pump Water Pump Water Pump
PI
ZS
E BF2020 4110 PI PIC PS PIC PS
BF2013
4108 1009 1008 2009 2008
PIC
BF14 5108 PI PI
1006 2006
BF2008 BF17 BF18
BF BF BF2007 BF16
2064 2065 TT BF30
5136 BF37 BF36
TI BF29
4116 BF2003 BF41 BF42
BF2012 BF2004 BF Economiser BF43 BF44 BF45 BF46
2021
BF BF
2061 2062 BF13 BF12 BF11 BF10 BF9 BF8 BF7 BF6 BF5 BF4
Main Boiler Key
BF47 Feed Water
BF BF To Sample Cooler Instrumentation
2006 2005
Desuperheater Steam
g) Check that the boiler access doors, air duct and gas duct access Position Description Valve Preparation of the Fuel Oil System and Initial Firing
doors and header casing doors are properly closed. Author’s Note: This section will require checking and enhancing during the
Open Electric feed pump suction from storage tanks BF33
ship visit.
h) Open the superheat header drains 73B, 76B, 77B, 78B. Open Distilled storage tank suction CW43, CW44, CW35
Open Electric feed pump discharge BF14 The initial firing of the boiler can be carried out at the boiler gauge board using
i) Check that all water wall header drains and blow down valves the base burner. The process is manually operated
are shut. Open Electric feed pump discharge to auxiliary line BF11
Open Auxiliary feed line valve BF1011 a) With reference to section 2.4 Fuel Oil and Gas Service Systems,
j) Open the superheater vent (cold start) valve 73B, 74B and the set up the boiler fuel system with gas oil as the fuel supplied
superheater primary stop valves. Open Auxiliary to main feed line crossover BF1013
and recirculating at the burner header rail. With reference to the
Open Economiser inlet BF1003 Atomising Steam DCS faceplate, set up the valves to supply
k) Open the saturated steam pipe vent valves 49B, 50B. atomising air to the burner
Open Economiser outlet BF1004
l) Check that all the level gauge and instrumentation root valves Open Economiser header vent valves BF1008, BF1007 b) Start the forced draught fan with the vanes closed from the local
are open and that their drains are closed. control panel or from DCS faceplate Forced Draught Fans and
Open Feed line high point vents BF28, BF35
Air Heaters.
Open Main feed check valve BF1004
Procedure for Filling the Port Boiler and Establishing the
c) On the starboard or port boiler DCS faceplates, set the air
Correct Water Level flow to about 25%. The fuel pressure should rise accordingly,
b) Fill the boiler through this system and vent all air from the
economiser and feed water lines Close the vents when all air dependant upon the fuel/air ratio setting on the same faceplate.
Initial filling of the boiler with distilled water can be achieved by pumping
has been expelled and water issues from them. The fuel pressure at the fuel rail should be 3.0kg/cm2, if
distilled water either from the atmospheric drain tank or directly from the
necessary, adjust the air flow to achieve this figure.
storage tanks, as follows.
c) Fill the boiler to about 100mm below the normal level in the
gauge glass. Then bring up to the normal water level via the d) At the local boiler control panel select LOCAL operation. Purge
• From the atmospheric drain tank, using one of the drain
main feed line. the furnace by pressing REQUEST in the Furnace Purge section
pumps, where a crossover valve CW84 is provided between
of the panel. Allow the furnace purge to complete, as indicated
the auxiliary condensate line and the boiler auxiliary feed water
when the COMPLETE lamp illuminates.
5.88
4.90
3.92
0.98
0
Operating Time After Initial Firing
Approximately 3 Hours Approximately 2 Hours
Approximately 2 Hours
Changeover from
Port Boiler to Starboard Boiler
To Port
Warming L1
Steam Valve Drain Valve Sootblowers Steam Valve Drain Valve
Through Sootblower Finished
DS0284 DS1285 R1 - R6 DS0284 DS1285 Finished
Pipelines L1 Operates R1 - R6
Opens Closes Operate Closes Opens
Port Boiler 3 Minutes Ready
START
PB To Starboard
SEQ.
Waiting
LOCAL
ESCR
SETTING IAS
BOTH
BOILERS
From Starboard
Key
Manually Open the Manually Close Manually Operate Manually Close the Manually Open AND Gate
Local Operation Steam Inlet Valve the Drain Valve Each Sootblower Steam Inlet Valve the Drain Valve
OR Gate
R1 Rotary Sootblower
Each boiler is fitted with an automated drain valve for warming through and Either of the above conditions will cause all of the long stroke sootblowers to Operation of an Automatic Sequence using the Operating Panel
also a constantly open steam drain trap to ensure that the steam line remains retract and the system to shut down. The steam valve will not close until all the
clear of water. All operations are carried out from the Madic Monitoring graphic screen No.1
long stroke sootblowers are in the retracted position. Any rotary sootblowers
as follows:
will continue to turn until they reach their stop position.
Control of the boiler sootblowers is carried out by the IAS from graphic screen
XX-XXX-XX. The sequence can be observed from graphic screens XX-XXX- a) Ensure that the intermediate manually operated valves DS24
The following alarms are also fitted:
XX and XX-XXX-XX for the port and starboard boilers respectively. and DS25 are open.
• Long stroke sootblower time exceeded, due to:
All the sootblowers are fitted with a local start button for use in the local mode Forward motor not running a) Press the Setting pushbutton on the screen which will change
of operation. In addition, the long stroke blowers are fitted with an emergency the display to Madic Monitoring graphic screen No.11.
Reverse position switch time out
retract button for use in any operating mode. All the blowers have a stop
position switch and the long blowers have a reversing switch. Retract motor not running b) Select either ESCR or IAS on the operation position area of the
screen.
Stop position time out
These are fitted for control purposes within the IAS. Motor running, direction
and overload conditions are fed back to the IAS for indication, control and • Long stroke sootblower motor overload c) Select one of the three operation mode sequence pushbuttons
alarm purposes. marked as follows:
• Long stroke stop position abnormal
• BOTH BOILERS
• Emergency retract pushbutton operated on the IAS
Operating Modes • Emergency retract pushbutton operated locally
• No.1 BOILER
• No.2 BOILER
Each boiler can have its sootblowers operated automatically in two modes: • Rotary sootblower time exceeded/stop position time out
• Economiser sequence only • Rotary sootblower motor overload
d) If any of the sootblowers require bypassing, press the bypass
• Boiler full sequence pushbutton for that sootblower.
f) Press either the Boiler and ECO Sequence Start or the ECO e) Upon completion the system is shut down. The steam supply
Sequence Start pushbutton as required, which will change the valve is closed and both port and starboard drain valves open.
display to Madic Monitoring graphic screen No.21.
The start sequence will commence and lamps will indicate the progress as the Sealing Air
sootblowers operate.
The glands at the boiler casing are sealed by air pressure from the FD fans
The warming through sequence starts automatically indicated by the STEAM trunking.
INLET VALVE OPEN, WARMING and the BLOWING lamps being
illuminated. When the warming through sequence completes, after three
minutes, the DRAIN V CLOSE lamp illuminates. The selected automatic
sequence commences and sootblowing takes place. This is indicated by
individual sootblower lamps being highlighted.
When the sequence is completed the steam valve closes, the STEAM INLET
VALVE CLOSE lamp illuminates and the WARMING and the BLOWING
lamps are extinguished. Finally the drain valve opens, the DRAIN V CLOSE
lamp is extinguished and the STOP lamp illuminates.
At the end of the blowing sequence a five minute timer is activated. This is
to prevent the system going through another, unnecessary, warming through
sequence before starting the next program.
If a further automatic sequence is selected within the five minute period the
timer is cancelled and the new sequence takes place. When no further sequence
is selected within the five minute end of sequence period, the system shuts
down i.e. the main steam valve closes and the port and starboard drain valves
open.
Local Operation
The operation is carried out from the Madic Monitoring graphic screen No.1
as follows:
P From Main
Condensate Pump
CW88 CWT56 CW21 From Main
Set at 5kg/cm2 Condensate Pump
RO VOI VLV
ES0334 5473
TAH
ES14 DS0331 DS14
Silencer
TIC TI VLV
5471
TT TT TI
ES12 0486 0487 4401 AOC VOI RO VCI ZS
PS
1782 VOI ZS
ESD ESA 5420
P From Main Boiler
PT PT PS VI Desuperheated
0129 0129 0071 0129 From Gland Steam ES13 Steam Line
TAH TI TT DS0330
System VOI ZS PT PI
0129 5421 0488 4402 From Main
Condensate Pump
PAH PSH PI Set at 5kg/cm2
1001 1002 1003
RO VOI VLV
ES0335 5474
Main Condenser
Turbine Generator
LP Turbine To Atmosphere
PAH PSH PI
2001 2002 2003
ES24
To Gland Steam
From 5kg/cm2 E
Fan
System
BS31 BS29 BS25 ES5 ES9 ES29
ES11
BS44 PI PI
4405 5408
To Atmospheric ES32
Drain Tank
ES34
ES25
Key
Condensate
The main steam dump valves are controlled from the Automatic Boiler Control Flow Chart for Steam Dump Logic
Main Steam Dump Desuperheaters (ABC) system and the water spray valves are controlled by the ABC and IAS.
There is one spray valve for each main steam dump valve which prevents high
The main boilers burn excess boil-off gas, which is produced from the cargo.
temperature steam entering the main condenser. The spray valves receive the
If the boil-off gas produced exceeds the requirements for normal steam
same control signal from the ABC as the dump valves. A separate temperature
production, the excess steam produced is normally dumped to the main Steam No
controller will control the dump steam temperature and a high selector dump requested
condenser via the two main dump external desuperheaters. Steam can also
will select the highest output from the steam dump control signal and the by ABC?
be dumped to the atmospheric condenser, by opening valve ES13 and closing
temperature control signal. The temperature controller also provides a control
valve ES12, should the main condenser be unavailable although capacity is
signal for the pressure reducing valves.
greatly reduced. Yes
Condition for next step Action
The ABC will send a Dump Request command to the IAS, which will then
Desuperheaters are required to eliminate the effects of superheated steam Condenser spray valve open Open main condenser spray valve
open the condenser dump spray valve CW56 and both the desuperheater water Water spray valves 5% open
impinging on either the main condenser or the atmospheric condenser. Open water spray valves 5%
spray valves ES334 and ES335 to 5%. Condenser hotwell level below
Desuperheaters operate by injecting spray water directly into the steam flow, Check main condenser hotwell level
normal +300mm
reducing the temperature to 150°C. The spray water for the desuperheater sprays Check main condenser vacuum
The IAS will send a Dump Permitted signal to the ABC if the following Condenser vacuum below 600mmHg Check SW outlet temperature
is supplied from the main feed pump discharge. The temperature at the outlet Sea water outlet temperature below 70°C
conditions are fulfilled: Check dump steam valves to condenser
from the desuperheater is measured and a corresponding signal is transmitted One dump steam valve to condenser open
to the spray control valve, which alters the water supply accordingly. A further • Spray valves ES334 and ES335 5% open
cooling spray is provided at the dump steam inlet to the main condenser to • Condenser dump spray valve CW56 open
cool the inlet cowl and help prevent mechanical stresses being created in the
condenser shell. • Main condenser hotwell level below normal +300mm Give Dump Permitted signal to ABC
When the vapour header pressure is above 19kPa, the IAS will check the
High Boiler Pressure
condenser and prepare the water spray valves. When all the above conditions Dump
No
The main dump external desuperheaters are controlled from the integrated are met the IAS sends a Excess BOG Dump Order and a Dump Permitted requested
automation system (IAS). The piston valve DS0330 to the desuperheater will signal to the ABC. signal Off?
open when the boiler pressure exceeds its normal set point. It provides stability
during periods of fluctuation where the burners are reduced to minimum flow, The IAS will then receive the control signal sent to the dump pressure control Yes
such as during manoeuvring. The dump will control any excess steam pressure valves DS0331 and DS0332. This signal is then used to open the spray valves Condition for next step
generated during these periods. ES334 and ES335 in parallel with the dump pressure control valves DS0331 Close condenser spray valve
and DS0332. If the temperature after the desuperheater reaches the setpoint of Water spray valves closed after 5 minutes
Close water spray valves
High Tank Pressure 150°C, the signal from the temperature controller will override the ABC signal
and control the desuperheater water spray valves.
If the demand of steam is not sufficient to consume the entire boil-off gas from
the cargo tanks, the firing rate of the gas burners will be increased accordingly (Note: The dump valve BV324 will close if the main condenser SW outlet Release Dump Permitted
and any excess steam dumped to the main condenser. The amount of steam temperature reaches 70°C or the vacuum falls to 600mmHg.) signal to ABC
dumped will depend on the position of the main turbine manoeuvring valves
and the cargo tank pressure. The dump signal from the cargo tank pressure is
inhibited when burning fuel oil only. Steam to the desuperheaters is supplied
via a main piston valve DS0330, each desuperheater has its own control valve
DS0331 and DS0332.
a) Ensure that the instrument and gauge valves are open and
instrument air is supplied to the control units.
c) Open the main condenser dump steam inlet cowl spray cooling
valves CW21 and CW88. Ensure that the control valve CW156
is operating and that cooling water is being supplied to the
cowl.
CAUTION
Do not open both the dump to the main condenser and the dump to the
auxiliary condenser at the same time if the main condenser is under
normal vacuum. Doing so will cause a sudden loss of vacuum within the
main condenser and the subsequent trip of the main engine.
• Low LO pressure
Inlet Guide Vanes
• High high inner bearing temperature
To achieve the required gas flow, the compressors have inlet guide vanes fitted
• Low low gas seal pressure at the suction end.
• Low low bulkhead gas seal pressure
The vanes are operated by pneumatic actuators which receive control signals
• High high bulkhead gas seal temperature from the flow controller.
• Fuel gas valve closing
Rotation of the vanes is possible through an angle of 100°. The position is
• Low temperature fuel gas to boilers
indicated both locally and at the cargo control room.
Illustrations
T Q
A
O
E
Q R B
A
P
S
N
M
J I
G G
PLAN VIEW
J
I
F
Key
Both the HP and LP turbines are connected to the first pinions of the reduction • Control oil pressure low
gear by flexible couplings. The pinions drive the first reduction gear wheels. • HP turbine rotor excessive vibration
The first reduction gear wheels are connected through flexible shafts fitted
• LP turbine rotor excessive vibration
with flexible couplings to the second reduction pinions, which drive the
second-reduction gear wheel or main gear wheel. • Main reduction gearing vibration
• HP turbine rotor position excessive displacement
Gland steam make-up and spill is also controlled by the IAS. During this initial period of little drainage into the condenser, it is possible for k) Set valves for gravity tank supply and operation.
the level to drop due to leakage up to the deaerator. The level in the hotwell
The following graphic screens are used to monitor and control the main turbine will require monitoring and further topping up as necessary. Position Description Valve
functions carried out by the IAS:
Open Gravity tank quick-closing inlet/outlet valve
d) Open the gland leak off valve between the main turbine and the
Graphic Screen Description gland steam condenser. Throttled Gravity tank overflow control valve LO104
MT GEAR TEMP Main gearing bearing temperatures
e) Check and record the axial position of the rotors at the cold Check around the LO system for leaks. The level in the LO sump tank will
LO MAIN TURBINE Main turbine lubricating oil system condition. drop as the system charges and may require topping up. A flow of oil should
MT REMOTE CONTROL SYSTEM Main turbine mimic board be observed returning from the LO gravity tank and the control oil tank sight
f) Check the oil level in the main sump tank and top up as glasses. It is good practice to observe gear sprayers and any other oil returns
MT STATUS Main turbine protection
necessary, taking the amount of oil to be placed into circulation that can be accessed and viewed without loss of oil.
Procedure for Start-Up into consideration.
The system oil pressures should be as follows:
Successful operation of the turbine depends on the manner of the warming g) Set up the main turbine lubricating oil system and control oil
through, loading, stopping and cooling down of the turbines. Steam turbines system, placing the valves as follows: Main LO system: 0.1 - 0.15MPa
are built and operate with very close tolerances in their structure, and the very Control oil system: 0.29 - 0.39MPa
nature of the driving medium can lead to problems associated with thermal Position Description Valve
expansion unless due care is taken. Correct warming through and proper l) Engage and start the turning gear. Observe the amps being
Open Auxiliary LO pump discharge valves LO91, LO90
drainage is essential together with careful handling of load changes. drawn by the turning gear motor. If these are higher than normal
Closed LO system drain to the sump tank LO118 investigate the turbine, gearing and shafting to determine why
The preparation of the turbine for use is the responsibility of the operator. Open LO pressure control valves LO117, LO116 they are not turning freely.
Correct loading up times are programmed into the turbine control system, as
are the opening of the drain valves and bleeds. Open Gear driven LO pump suction valve LO100
ECP
To Manoeuvring Control Box
PI
From
Boilers PX PI
Servo Ahead
To Open To Open
Servo Astern To Astern Turbine
AXIS Feedback
Device
Key
To Overspeed Trip
From Lubricating Oil Pump
Superheated Steam
HP Lubricating Oil
LP Lubricating Oil
Electrical Signal
To Lubricating Oil Sump Tank
Instrumentation
The turbine will trip if the auto spinning rpm reaches xxrpm Prepare the main turbine for use as described in section 3.4.1 Main Turbine. a) Telephone contact between the bridge and engine control room
establishes the need to transfer control.
Automatic Slowdown a) Set the control location to ENGINE CONTROL ROOM. The
The main turbine is automatically slowed down when one of the following location is displayed by an indicator lamp on all the consoles. b) The telegraph levers in all locations must be in the same
conditions occur: positions. This can be checked by observing the pointers
b) The control lever in all locations should be at the STOP indicating the current telegraph position and the remote
Description/Tag No. Set Point position. telegraph position. When the levers are all correctly positioned
the MATCHING lamp is lit.
Main steam pressure low low ESLD-121 5.2MPa c) Select the control mode as LEVER then toggle switch. Engine
Main boiler steam drum level high high control positions may be selected as WHEELHOUSE or ECR. c) The engine control room control location switch is moved from
Main boiler steam drum level low low WHEELHOUSE to ECR.
The turbine can now be controlled from the telegraph lever which initiates the
Main condenser hotwell level high high ESLD-161 N+300mm control ramps and carries out all functions automatically. Use of the toggle The WHEELHOUSE CONTROL indicator lamp begins to flicker and the
switches on the engine control room console, to raise or lower turbine speed, buzzer sounds. The main turbine can now be controlled from the engine
Stern tube bearing temperature high high
bypasses the computer control system and actuates the governor servo motor control room.
One boiler strip directly when direct control is selected.
Description/Tag No. Set Point d) The bridge operator acknowledges the change of control location
Transfer of Control from the Engine to the Bridge by moving the wheelhouse console location switch from
Main condenser vacuum low low ESLD-129 55kPa
WHEELHOUSE to ECR and pressing the ACKNOWLEDGE
Main thrust pad temperature high high ESLD-160~2 110°C In bridge control the wheelhouse telegraph lever signals the MTRP directly.
pushbutton.
The telegraph levers in the engine control room does not need to be moved.
Main steam temperature high high ESLD-141 530°C The indicator built into the telegraph lever will show the position that which
The WHEELHOUSE CONTROL indicator lamp stops flickering and is
Gearing and turbine bearing temperature high high ESLD-151~159 G:57°C, the bridge telegraph lever has been placed.
extinguished. The ECR indicating lamp is lit.
T:77°C
a) Telephone contact between the bridge and engine room
Intermediate bearing temperature high high. establishes the need to transfer control.
The main turbine remote operating system has two modes of operation, Description Set Point
NORMAL and MANOEUVRING. The position of the telegraph lever and a 1. Manual emergency trip (ahead and astern)
changeover switch determines the mode to be used.
2. Overspeed trip 103.5rpm
3. LO pressure low low PS-69/PAL-131 49kPa
Alarms and Trips 4. Control oil pressure low low PS-70/PAL-134 196kPa
The main turbine is protected by alarms and trips which can be viewed through 5. Main condenser vacuum low low PS-71/VAL-129 380kPa
the IAS system. These are listed as follows. 6. Main condenser hotwell level very high FS-161A LAH-161 N +500mm
7. HP turbine rotor excessive axial displacement XAH-173A 1.0mm
Alarms
8. LP turbine rotor excessive axial displacement XAH-174A 1.0mm
Description/Tag No. Set Point
9. Main thrust bearing excessive axial displacement XAH-175A 1.6mm
Low LO pressure PS-69/PAL-131 69kPa
10. HP turbine rotor excessive vibration XAH-173V 130 microns
Control oil low pressure PS-70/PAL-134 245kPa
11. LP turbine rotor excessive vibration XAH-174V 180 microns
Main condenser low vacuum PS-71/VAL-129 -77kPa
12. Main reduction gearing excessive vibration XAH-175V 18mm/s
Gland steam high pressure PAH-128 49kPa
13. Turning gear engaged
Gland steam low pressure PAL-128 4.9kPa
14. Both boilers tripped
HP turbine thrust bearing axial displacement XAH-173A 0.5mm
15. Boiler drum level high high
LP turbine thrust bearing axial displacement XAH-174A 0.5mm
16. Power failure
Main thrust bearing axial displacement XAH-175A 1.1mm
17. Emergency manoeuvring handle not in neutral position
HP turbine vibration XAH-173V 100 microns
18. Safety system power failure
LP turbine vibration XAH-174V 150 microns
Main reduction gearing vibration XAH-175V 7mm/s (Note: A trip bypass switch is fitted to No. 5, 7, 8, 9, 10, 11, 12, and 15. In the
event of the turbine operating in the astern direction, trip No. 4, 6, 7,
Bearing LO high temperature TAH-147 50°C 8, 9, 10, 11 and 12 are not automatically activated.)
Gearing LO low pressure PAL-132 69kPa
Main condenser high level alarm FS-161A LAH-161 +250mm MAIN TURBINE CONTROL – Further description to be written when information
available
Main condenser low level alarm LAL-161 -110mm
HP/LP turbine and thrust bearing temperature TAH-151~158 75°C
Main gear bearing TAH159 55°C
Main thrust bearing TAH160~1 55°C
Illustration
THRUSTER CONTROLLER Port Wing THRUSTER CONTROLLER Wheelhouse THRUSTER CONTROLLER Starboard Wing
Thruster Control AC SOURCE FAIL CONT SOURCE ON CONT. STATION Controller Thruster Control Port Solenoid Starboard Solenoid
ALARM CONT MODE DC SOURCE FAIL POWER AVAILABLE ALARM CONT MODE
INTERGRATED ALARM CONTROL
AVAIL
EMERGENCY
STOP
OIL LOW LEVEL
OIL LOW PRESS
MAIN SOURCE ON
FAN RUN
W/H WING
THRUSTER
REQUEST INTERGRATED ALARM CONTROL
AVAIL
EMERGENCY
STOP
Hydraulic
SYSTEM ABNORMAL OIL PUMP OVER LOAD
OIL TEMP HIGH
READY TO START
MOTOR FULL LOAD
SYSTEM ABNORMAL
Oil Gravity Tank
10
PITCH INDICATOR
5 0 5 10
MAIN MOTOR OVER LOAD
MAIN MOTOR TRIP
HYD PP SOURCE ON
CONT MODE 10
PITCH INDICATOR
5 0 5 10 (110 Litres)
MAIN MOTOR HIGH TEMP NON
FOLLOW EMERGENCY
FOLLOW
TURN TO PORT 0 TURN TO STBD M/M INSULATION LOW UP
UP STOP TURN TO PORT 0 TURN TO STBD
LAMP
5 5 SYSTEM ABNORMAL LAMP
5 5
DARK BRIGHT BUZZER DARK BRIGHT BUZZER
BUZZER BUZZER
STOP STOP
TEST PITCH INDICATOR TEST
LAMP
10 10 DARK BRIGHT BUZZER
BUZZER 10 5 0 5 10 10 10
STOP
TEST
KAWASAKI
HEAVY INDUSTRIES. LTD.
PI PI
PI
Overload
Port Wing Wheelhouse Starboard Wing Protection
Amplifier
Control Station Control Mode
Changeover Changeover
(Relay Circuit) (Relay Circuit) Port
Maximum
Amplifier Limit
Starboard
POWER SOURCE UNIT Maximum
Limit
Electrical Signal
Instrumentation
THRUSTER CONTROLLER
AC SOURCE FAIL CONT SOURCE ON CONT. STATION
DC SOURCE FAIL POWER AVAILABLE
OIL LOW LEVEL MAIN SOURCE ON W/H WING
THRUSTER
REQUEST
SYSTEM ABNORMAL
PITCH INDICATOR
LAMP
DARK BRIGHT BUZZER BUZZER 10 5 0 5 10
TEST STOP
10 10
! CAUTION
1. DON'T USE THE THRUSTER OVER 5 KNOTS PORT STBD
TO AVOID A VIOLENT VIBRATION.
2. SET THE CONTROL DIAL AT THE SAME
POSITION AS ORIGINAL TO KEEP A
CONSTANT PITCH WHEN CHANGE OVER
THE CONTROL STATION.
KAWASAKI
HEAVY INDUSTRIES. LTD.
• AC SOURCE FAIL d) Rotate the pitch control dial to alter the blade angle to the
• DC SOURCE FAIL desired position. The thruster will now assist the movement of
the bow in the required direction.
• OIL LOW LEVEL
• OIL LOW PRESSURE Stopping the Thruster
• OIL PUMP OVERLOAD a) Rotate the pitch control dial to alter the blade angle to zero
• MAIN MOTOR START FAIL pitch.
• MAIN MOTOR OVERLOAD
b) Press the STOP button. The thruster, oil pump and fan
• MAIN MOTOR TRIP will all stop automatically and the indicator lamps will be
extinguished.
• MAIN MOTOR LOW INSULATION
c) Turn the control power switch to the OFF position.
An emergency stop button is incorporated in the panel.
Sequential Start
a) Turn the control power source switch to the ON position. The
ON indicator lamp will now be illuminated.
d) Rotate the pitch control dial to alter the blade angle to the
desired position. The thruster will now assist the movement of
the bow in the required direction.
Individual Start
a) Turn the control power source switch to the ON position and the
ON indicator lamp will be illuminated.
b) Turn the oil pump switch to the ON position. The fan motor
starts and the indicator lamp illuminates. When the oil pump
indicator lamp goes from a flickering state to a solid state the
READY TO START lamp will be illuminated.
Illustration
4.3 Emergency Operation of the Main Turbine (Solo Running of HP Turbine/LP Turbine)
Illustrations
Flooding in the engine room may occur due to a defect in the hull structure,
possibly due to grounding, berthing or collision damage, or, more likely, due Bilge and Fire Pump (Double Speed)
to a defect in the sea water pipeline system. Can take suction from:
• Bilge main
Measures to Prevent or Alleviate Flooding
• Aft bilge well
Maintain pipelines externally, tighten slack supports and replace broken ‘U’ • Starboard forward bilge well
bolts on pipe brackets to minimise fretting in way of supports.
• Port forward bilge well
Operate all ship’s side valves regularly, so that they can be operated easily
when required. Valves such as fire pump suction valves, which are normally Centre Ballast Pump
open, should be closed and reopened regularly to prevent a build up of marine The centre ballast pump is provided with a direct bilge suction via valve BB66
growth. with the operating handwheel 460mm above the lower platform.
Before opening sea water filters for cleaning, make sure the shut off valves are
tight by opening the vent in the cover. In any case, break the cover joint before Bilge Suction Strainers
removing all cover bolts. The same applies when opening coolers and pipelines
anywhere in the system. Care must always be taken when removing covers or Bilge suction strainers should be checked and cleaned whenever the
opening any part of the sea water pipe system as valves which are indicated as opportunity arises. Frequent checking and cleaning will reduce the risk of a
being closed may not be fully closed. strainer becoming blocked and difficult to clear due to subsequent flooding.
Personnel should be familiar with the position of bilge suctions and the pumps
that can be utilised for bilge pumping duties. They should also be familiar with
the position of main sea suction and overboard valves and know which main
suction is currently in use.
In the event of a boiler shut down, planned or otherwise, the bridge must be f) Keep the forced draught fan running on the faulty boiler to cool
informed immediately. it down, or allow it to cool down naturally. Bear in mind the
possibility of economiser fires. Either fill the boiler to the top
The main turbine must be slowed down sufficiently to enable the remaining of the gauge glass or empty it out when cool.
boiler to be maintained within its operating parameters. Control of the boiler
coming out of service will be generally under manual operation and particular g) When conditions have stabilised, increase the engine speed
care must be taken to ensure the remaining boiler controls and associated as required up to the maximum firing rate on the remaining
systems function to compensate accordingly. The steaming rate of the boiler.
remaining boiler must be maintained below the design maximum.
Orifice F
Diameter 240mm Emergency
Pipe G
Blank Flange C
Emergency
Desuperheated Steam
Line
Spectacle Flange J
Spectacle Flange J Spectacle Flange I Spectacle Flange I Spectacle Flange I
Spectacle Flange J Open Side
Blank Side (Blank Side) Ring Flange A (Blank Side) (Orifice Side)
Ring Flange A Blank Side
H H Blank Flange E H
Stop
Valve
DS13
Main Steam
Pipe
Normal Operation Operation With HP Turbine Only Operation With LP Turbine Only
CAUTION
The LP astern turbine cannot be used so an astern movement is not
possible.
Crossover Trunking
Normally Open B
A Normally Closed C Normally Open
To Boiler To Boiler
Key
Normal Air Flow
Three fans are situated on the 21800mm deck platform and are controlled
by adjustable vanes, automatically positioned by the combustion control
equipment. The outboard fans are arranged to supply their respective boilers.
If either the port or starboard FD fans fail, the centre fan can be selected to
supply the boiler which has the defective FD fan. The flaps are arranged to
isolate the defective FD fan and open up the common trunking..
(Note: Due to the capacity of the individual fans a single fan must never be
used to supply two boilers.)
Control of the fans is from the Forced Draught Fans and Air Heaters IAS
graphic XXX-XXX-XX, from which the seal air fans are also controlled and
the Combustion Control IAS graphic XXX-XXX-XX.
The crossover flap B has a limit switch which indicates to the IAS that the
centre FD fan is operating on the port boiler.
Description
The steering gear, in accordance with IMO regulations the pumps, hydraulic
power circuits and rams can operate as two isolated systems.
The steering gear is fitted with an automatic isolation system. This system is
used to divide the hydraulic power circuits in the event of a hydraulic oil loss
from the oil tanks.
In accordance with IMO regulations the hydraulic pumps used in the steering
gear are supplied with power from two independent sources. In the event of
power failure from the main switchboard, one pump can be supplied from the
emergency switchboard.
Indication of the rudder angle and a compass repeater are provided for manual
control of the steering gear.
c) At the control panel for each steering gear turn the remote/local
switch to the LOCAL position.
e) If necessary start the emergency generator in order to ensure d) If personnel are missing, consider the possibility of searching in
continuity of electrical supply. the fire area.
5.1 Introduction
llustrations
5.1 INTRODUCTION
Illustrations
5.2b Fire Detection Equipment and Alarms on Bridge Deck and E Deck
5.2e Fire Detection Equipment and Alarms on Main Deck and Cargo Machinery Room
5.2f Fire Detection Equipment and Alarms on 21800mm Deck and Bow Thruster Room
5.2g Fire Detection Equipment and Alarms on Engine Room 2nd Flat
5.2h Fire Detection Equipment and Alarms on Engine Room 1st Flat
5.2i Fire Detection Equipment and Alarms on Engine Room Floor and Turbine Mezzanine Deck
5.2j Fire Detection Equipment and Alarms on 29600mm, 35200mm and 40100mm Decks
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.2a Fire Detection Panel
IRE AL
AL
1
2
UPPER DECK : CORRIDOR, STB
BRIDGE DECK : WHEEL HOUSE
SOUNDER SIL
DEVICE(S) STILL
IN ALARM COND.
PRE WARNING
FAULT
FUNCTION DISABLED
MAINS
AUTRONICA
The active prewarnings may be seen by calling up the menu function ‘Show More Alarms
Status’, ‘Prewarnings’. The menu is accessed by pressing the ENTER key Procedure in the Event of a Fire Alarm
and the arrow keys are used until the desired menu function is displayed and a) Carry out fire checks and corrective action as necessary for If more than one fire alarm is active the ‘MORE ALARMS’ indicator lamp will
pointed to by the cursor; the ENTER key is pressed in order to display the extinguishing the fire, observing all safety precautions. When be illuminated. The system will operate as for the fire alarm above but the text
prewarnings. the scene of the fire has been investigated and the necessary display will indicate the addresses of all devices in alarm. (If there is a printer
actions taken the audible horns may be switched off. the printer will operate to register all of the alarm information.)
Procedure in the Event of a Prewarning
b) Open the control panel door and press the SOUNDER SILENCE Action to be taken in the event of activation of the ‘MORE ALARMS’ indicator
pushbutton; all alarm devices including the internal buzzer will lamp is similar to the procedure for a single alarm. Upon opening the panel
CAUTION be muted. The red ‘FIRE’ indicator lamp will change to a steady door the MORE ALARMS pushbutton must be pressed and the second alarm
Always treat a prewarning condition as if it is a fire alarm. light. All alarm outputs from the control panel are turned off will be indicated on the second line of the display. Subsequent pressing of the
when the SOUNDER SILENCE pushbutton is pressed but the MORE ALARMS pushbutton will bring up each alarm in the queue.
a) Determine the location of the activated prewarning detector alarm message to the fire fighters remains.
and check this location for fire conditions, observing all safety
Operation of the SOUNDER SILENCE and RESET pushbuttons is the same
precautions. Deal with the situation as necessary in order to (Note: The system has a silent alarm function which may be activated if as for the single alarm; the silent alarm situation applies to each alarm in
remove the danger of fire. required. This has a time delay (T1) which must be counted down the queue. With multiple alarms some may remain in the alarm condition
before the general fire alarm is sounded after a fire detector is activated. for the reasons mentioned above and the ‘DEVICES STILL IN ALARM
b) Open the control panel door and press the SOUNDER SILENCE The alarm is sounded only at the duty station. If the alarm is not CONDITION’ lamp may remain illuminated.
pushbutton. The prewarning indicator lamp will now change to acknowledged within the delay period T1 by pressing the SOUNDER
a steady condition. SILENCE pushbutton an additional delay period (T2) is activated. If
the SOUNDER SILENCE pushbutton is not pressed within the delay
c) Press the RESET pushbutton. The following text will appear on period T1 and not reset within the delay period T2 the alarm outputs
the display ‘RESET PROCEDURE IN PROGRESS WAIT....’. are activated. Alarm delays are only active if the fire alarm is initiated
The text will remain for 60 seconds and the reset procedure will by one detector. The fire alarm is sounded immediately if activated
be executed in that period. from any manual call point or if two or more detectors are activated.)
d) If everything is in a normal condition the text display will c) Press the RESET pushbutton. The following text will appear on
indicate ‘RESET OK NORMAL CONDITION’. the display ‘RESET PROCEDURE IN PROGRESS WAIT....’.
The text will remain for 60 seconds and the reset procedure will
e) Close the panel door. After the door is closed only the mains be executed in that period.
power indicator lamp should be illuminated.
Restore Controls, Restore Sounders and Restore Fire Brigade operate in the
same way as the Restore Address and Restore Zone functions.
Spare Cabin
Key
Smoke Detector
Cable W.C.
Trunk
Senior Officer's Chief Engineer's Lift
W.C. Battery
Day Room Office Machinery Chart Table
Room
Lift Space Lift
Alarm Bell
Down
Down Up Down Navigation Consoles
Spare Cabin
Manual Call Point Wheelhouse
and Radio Room
Converter Room
Owner's Up Gas Detector Safety Console
Day Room
W.C.
Captain's Office
Clean Radio Console
Up
General Alarm Button
Up
Inmarsat B Table
Radio
Officer
Manoeuvring Console
C Deck D Deck
x2
Electrical Officer Workshop
Cargo Engineer's
Petty Officer/Bosun Cadet
Day Room
Petty Officer/Cook Key
2nd Officer
Alarm Bell
Cable Cable
Trunk Trunk
Manual Call Point
Officer's Laundry Linen
Locker 3rd Officer
Lift Lift
Gas Detector
GAS DETECTOR
CENTRAL
Key
A Deck
Smoke Detector
B Deck
Gas Detector
Oiler
Garbage
Chute Up W.C. Up Seaman
Sauna
Officer's Pantry W.C. Crew Lounge and TV Room
Service Freefall
Lift Lifeboat Up
Down
Dispensary Messman
Officer's
Mess
Administration Spare
Office W.C. Seaman Cabin
Seaman
Messman
Hospital
Up Up
Down Down Up Down
Chemical Products
Store
Bow Thruster
Distilled Cargo Auxiliaries Room Room
Water Tank
Trunk Deck Trunk Deck
Overflow Tank No.3 Tank No.2 Tank No.1 Tank Bosun's Store
No.4 Tank
Steering Heavy Fuel Oil
Bunker Tank
x4
Gear Fuel Oil Tank
No.4 Water Ballast Tank x4 x4 x4
After Peak (Port & Starboard) Fore Peak
Water Ballast
No.4 Double Bottom Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1 Water Ballast Tank Forward Deep
(Port & Starboard) (Port & Starboard) (Port & Starboard) (Port & Starboard) Tank
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310
Stern Tube Stern Tube Lubricating Dirty Oil Lower Sea
Cooling Water Oil Tank Oil Sump Tank Tank Chest
Bilge Holding Tank
GAS DETECTOR
CENTRAL
(REPEATER) Key
300
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 310
Overflow Tank
N2 Generator N2 Compressors 86.7m3
Inert Gas Inert Gas
Inert Gas and Nitrogen
Blower Blower
Generator Room
Spare Air Blower
and Spare Electric Motor
for Air Blower
Pipe Duct
N2 Receiver
Hydraulic Machinery
Electric
Accomodation Workshop
Emergency Exit Air Conditioning Electric Store
Units
Control Air
Lift
Receiver
Boiler Forced Draught Fan
Engine Control Electric Machinery
Steering Gear Hatch - Bolted Service Air Room
Gas Room Compressor
Escape Trunk Garbage
Compactor
Incinerator Room
Garbage Storage
Area
Main
Boiler
Steering Gear Hatch - Hinged
Key
Smoke Detector Manual Call Point Typhoon Alarm Indicator Gas Detector Fire Alarm Panel
Alarm Bell Heat Detector CO2 Siren Deadman's Alarm Reset General Alarm Button
Key
Smoke Detector
Inert Gas
Inert Gas Cooling Unit Drying Unit
Sanitary
Hot Water Unit
Steriliser
Heat Detector
Store Area
Sanitary
Water Fog Pump Fresh Water Main Boiler
Unit
3.3KV
Typhoon
Switchboard
440V Switchboards
Washbasin
Rope Store Area
Distilled Water LO Gravity Tank Diesel Generator LO Storage Tank 440V Switchboard
3
Tank 34m LO Tanks
Wires Store Area 151.7m
3 HFO Bunker
Tools Panel HFO Service Tank
Tank 3
Milling Machine 1757.8m
3
Tools Panel Grinding Machine 222.5m
Engine Store HFO Service
Pipe Bending
Tank
Machine 3
184.9m
Lathe
Key
Sewage Plant
Alarm Bell
Spare Tubes Chemical Dosing Chemical Dosing
Tank for Tank for
Fresh Water Fresh Water
Sewage Tank Generator Generator
Manual Call Point
Typhoon Main
Boiler
Turbine Generators
Alarm Indicator
Escape Trunk
Diesel Generator
Deadman's Alarm Reset ԏ Water Heating Unit
Auxiliary Feed Water Pump Diesel Generator
Oil Filter
Cooling Unit
Main Solenoid Valves Cabinet
Chemical Injection Equipment Boiler Pre Lubrication Pump
LO LO HFO Service
Renovating Storage Tank HFO Bunker
Tank Tank 222.5m3 Tank
45.1m 3 73.3m 3 1757.8m3
HFO Service
Chemical Products Room Tank
184.9m3
Boiler Burner
FO Unit
Jockey Pump
Ballast Pump
Oily Water Tank
Dirty Oil Tank
Ballast Eductor
Ballast Pump
Stern Tube Oil Tank
LO
Shaft Intermediate LO Transfer Drain LO
Bearing Shaft Pump Tank Filter
Key
Stringer at 8500 From Base Line
HFO Bunker Tank
Smoke Detector Alarm Indicator
1757.8m3
Level 29,600mm
Level 35,200mm
Diesel Generator
Silencer /
Spark Arrestor
Key
Cargo
Smoke Detector
Low Temperature
Fresh Water
Deaeator Tank Expansion Tank
Alarm Bell
Level 40,100mm
Gas Detector
Emergency
Switchboard
LO Storage
Tank
DO Storage
Emergency
Generator Room Tank
Illustrations
FS59
Deck 21800mm
FS58
FS53 FS55
2nd Flat 2nd Flat
FS52 FS54
From Boiler To Sewage Tank
Exhaust Drain
FS49 FS51
1st Flat 1st Flat
FS48 FS50
Neutralising FS
and 13
Washing Tank
Overboard
Discharge
BB12 PI
BB14
4013
PT
5016
To Water To Ballast
Spray System Eductor
36 Deck
CS45
Overboard
Discharge
BB61 FS29 PI
CS Fire 4004 FS FS
43From Bilge Fighting/ 40 41
Pump Bilge
PI
Pump 4003 From High
PI PI PI Sea Chest
4010 Fire 4006 Fire 4008
Spraying
Fighting Fighting
Water
CS Pump Jockey
Pump PI PI PI
4009 37 4005 Pump 4007 VA64
CS CS CS
44 BB BB 39 42 Low Sea
38 351 Chest
To Fresh Water
Generator Sea To Bilge
From Bilge System Water Supply Pump
P H
Port Side
Sea Water Crossover Main Key
CS5 CS61 CS1
Fire Water
Sea Water
The fire main and wash deck system supplies sea water to the following
Fire Pump locations:
Maker: Hamworthy KSE • The fire hydrants in the engine room
Model: CAC200-25 V48 AAN • The fire hydrants on deck
Type: Vertical centrifugal pump, self-priming • The fire hydrants in the accommodation block
No. of sets: 1
• The fire hydrants in forward stores
Capacity: 240m3/h at 10kg/cm2
Motor: 106kW • Neutralising and washing tank eductor
• The sewage tank
Jockey Pump • Bosun’s store and chain locker bilge eductor: Hawse pipes
Maker: Hamworthy KSE • The deck water spray system
Model: CAC125-25 V48 AAN • Ballast eductor
Type: Vertical centrifugal pump, self-priming
No. of sets: 1 All of the pumps listed in the equipment specifications at the beginning of
this section can have their suction and discharge valves configured to supply
Capacity: 80m3/h at 10kg/cm2 the engine room fire main although the primary pump for this purpose is the
Motor: 67kW dedicated fire pump.
The fire pump together with the dual speed fire/bilge pump are normally kept
Spraying Water Pump
ready for use on the fire main. In addition to these pumps the emergency fire
Maker: Hamworthy KSE pump, the water spray pump and the jockey pump can all be lined up and used
Model: C05BX6-10 V AAN on the fire main system. The pumps can be started locally, from the fire control
Type: Vertical centrifugal pump, self-priming centre and from the bridge. The pump suction valves from the sea suction main
and the discharge valves to the fire main outlet are normally left open. The
No. of sets: 1
fire and bilge pump can take its suction from the sea or the engine room bilge
Capacity: 510m3/h at 10kg/cm2 system but is normally left set up for sea suction.
The sea suction is from the main sea water crossover line in the engine room.
This crossover line has connections to the high sea chest and low sea chest.
FS59
Deck 21800mm
FS58
FS53 FS55
2nd Flat 2nd Flat
FS52 FS54
From Boiler To Sewage Tank
Exhaust Drain
FS49 FS51
1st Flat 1st Flat
FS48 FS50
Neutralising FS
and 13
Washing Tank
Overboard
Discharge
BB12 PI
BB14
4013
PT
5016
To Water To Ballast
Spray System Eductor
36 Deck
CS45
Overboard
Discharge
BB61 FS29 PI
CS Fire 4004 FS FS
43From Bilge Fighting/ 40 41
Pump Bilge
PI
Pump 4003 From High
PI PI PI Sea Chest
4010 Fire 4006 Fire 4008
Spraying
Fighting Fighting
Water
CS Pump Jockey
Pump PI PI PI
4009 37 4005 Pump 4007 VA64
CS CS CS
44 BB BB 39 42 Low Sea
38 351 Chest
To Fresh Water
Generator Sea To Bilge
From Bilge System Water Supply Pump
P H
Port Side
Sea Water Crossover Main Key
CS5 CS61 CS1
Fire Water
Sea Water
Closed Fire and bilge pump bilge main suction valve BB35 fire fighting pump room located between frames 288 and 294. The pump is Upper deck port side at approximately frame 130 FF32
self-priming and draws water from a sea chest positioned in the compartment.
Open Fire and bilge pump direct bilge suction valve BB38 Upper deck port side at approximately frame 180 FF33
The pump is independant of the engine room pumps and can be used to supply
Closed Fire and bilge pump overboard discharge valve FS29 water to the fire and wash deck main in situations when the engine room pumps Upper deck port side at approximately frame 227 FF34
are not available because of an engine room fire or collision damage etc. The Upper deck port side at approximately frame 250 FF11
Closed Cross connection valve fire main/water spray system CS45 pump is driven by an electric motor and is fed from the emergency switchboard
440V feeder panel located in the emergency generator room. Upper deck centre line crossover line at approximately frame 270 FF35
d) Select the jockey pump for AUTOMATIC mode. The pump will Upper deck starboard aft FF10
Starting and stopping of the pump can take place from three locations:
start and stop according to the pressure in the fire main. Upper deck starboard side at approximately frame 130 FF12
• Locally at the pump starter unit in the bow thruster and fire
e) If additional water is required at the fire main start either the fighting room Upper deck starboard side at approximately frame 180 FF17
fire pump, the fire and bilge pump or the emergency fire pump • Remotely from the fire control station on the 25,400mm deck Upper deck starboard side at approximately frame 227 FF18
depending upon circumstances. in the accomodation block Upper deck starboard side at approximately frame 250 FF01
f) Open the desired hydrant valve on the fire main after connecting • Remotely from the bridge at the central control console
the fire hose to the hydrant. The locations are as listed below: (Note: After use, the hose and nozzle unit must be properly stowed back in
the hose box. Any defects in the hose, nozzle, valve or system must
To operate the pump for use on the fire and wash deck main, the valves need
be reported immediately and rectified as soon as possible. Hose boxes
Description Valve to be configured as follows:
must never be left with components which are defective.)
Double bottom (port) FS46
Double bottom (starboard) FS47
Laboratory
Emergency
Generator
Room
Time Time Time Time Time Time Time Time Time Time Time
Delay Delay Delay Delay Delay Delay Delay Delay Delay Delay Delay Incinerator
Room
Paint
Store
Electrical
Store
Electrical
Workshop
To
Free
Air Purifier
Room
Engine
Control
Room
Switchboard
Room
Steering
C46 C24 C14 C9 C7 C2 C1 Gear Room
Issue: Draft 2 5.3.2 Engine Room CO2 Fire Extinguishing System - Page 1 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
5.3.2 ENGINE ROOM CO2 FIRE EXTINGUISHING SYSTEM • Emergency generator room 2 cylinders The pilot cylinders connect to the main pilot system pipe work via two isolation
valves installed within the release cabinet.
• Incinerator room 2 cylinders
Maker: Unitor One isolation valve is connected via small bore pilot gas pipework to the
Type: High pressure • Laboratory 1 cylinders cylinder bank to open the required number of cylinders, the other is connected
Capacity: 46 cylinders each containing 45kg via a separate pilot gas line to actuate the power cylinder to open the main
The number of cylinders required to afford complete protection of any valve which directs the released CO2 to the protected space. The isolation
protected compartment depends upon the volume of that compartment. The valves are positioned so that the control box door cannot be closed with the
INTRODUCTION cargo compressor room has the largest volume and requires 46 gas cylinders, valves in the open position. It is also arranged that the control box door will
thus 46 cylinders are carried. operate a switch, when it is in the open position, to initiate audible and visual
Dependent upon the application, CO2 is normally employed at levels of between alarms.
35% and 50% by volume to produce an oxygen deficiency and thus extinguish Central Bank CO2 System
a fire. This level of oxygen reduction is also capable of causing asphyxiation. The pilot CO2 line to the main cylinder actuation system passes through a time
Fixed systems are therefore designed to include safeguards which prevent the delay device which delays the passage of the CO2 for a preset period of time
The central bank CO2 system consists of 46 x 45kg CO2 cylinders located in
automatic release of the CO2 whilst the protected area is occupied. The use before the main CO2 charge is released into the compartment.
the CO2 room, which is situated on the 21800mm deck.
of portable extinguishers should ensure that there is sufficient air to breathe
normally. CO2 is not generally regarded as having a high intrinsic toxicity A pressure gauge is fitted to the pilot CO2 pipeline to indicate pilot CO2
Cylinders are grouped together according to the space they protect, apart from
and is not normally considered to produce decomposition products in a fire pressure.
the cargo compressor room which requires the release of all cylinders. These
situation. (Author`s Note. Check positions of release cabinets and inset details.)
cylinders are connected to discharge nozzles within the protected spaces via
cylinder manifolds and distribution pipe work. Operating Instructions
The CO2 cylinders are fitted with safety devices to relieve excess pressure
caused by high temperatures. To avoid these operating, it is recommended that A pressure gauge and relief are fitted to the main CO2 manifold. a) On discovering a fire, shutdown machinery, fuel supplies and
cylinders are located in areas where the ambient temperature will not exceed ventilation systems as appropriate. Close all door ventilators
46°C. Cylinders must not be stored in direct sunlight. The system is designed to discharge the required number of cylinders into each and other openings, having first ensured that all personnel have
space protected as follows: been evacuated.
Certain gaseous extinguishing agents may cause low temperature burns when
in contact with the skin. In such cases the affected area should be thoroughly b) Go to the release cabinet for the protected space in which the
CO2 Requirements
irrigated with clean water and afterwards dressed by a trained person. fire has occurred.
The amount of CO2 required to be carried on board the vessel depends upon
WARNING upon the volume of the largest protected compartment. This is the cargo c) Open the release cabinet door. This will cause the alarms to
DANGER OF ASPHYXIATION compressor room which requires 46 cylinders each containing 45kg. sound in the protected space and stop the ventilation fans if not
Re-entry to a CO2 flooded area should not be made until the area has been already done so (CHECK ON BOARD).
thoroughly ventilated. The vessel carries 46 cylinders of CO2 (each containing 45kg) to provide
protection for the spaces indicated above. If the release of CO2 is authorised, d) Check that all personnel have been evacuated from the protected
all 46 cylinders are released into the cargo compressor room; the other space and then open both isolation valves by pulling valve
System Description protected spaces have fewer cylinders released as indicated above. It should handles downwards.
Areas Protected be realised that if any cylinders are released into the smaller spaces then there
will be insufficient cylinders for the cargo compressor room. It is essential that, e) Release pilot CO2 by opening the screw down valve on one of
The CO2 system installed in the ship protects the following spaces; in the event of any CO2 release, used cylinders are replenished at the next port the pilot cylinders only.
of call.
• Cargo compressor room 46 cylinders
f) Extinguishing CO2 gas will be released from the main cylinder
• Steering gear room 24 cylinders bank for the protected space after the time delay period. The
Release Cabinets
• Switchboard room 14 cylinders main valve will be opened and CO2 will be discharged from the
The system is operated by a supply of CO2 separate from the main fire nozzles into the protected space.
• Engine control room 9 cylinders
extinguishing CO2. Pilot CO2 cylinders are used for activating the release of
• Purifier room 7 cylinders the main CO2 cylinders. Two pilot cylinders are located in the release cabinet g) After 10 minutes close the pilot cylinder hand wheel valve.
• Electrical workshop 2 cylinders for each protected space, one cylinder acts as a standby cylinder. Only one pilot
CO2 cylinder would be opened at any time to release the CO2. h) When the pilot pressure gauge within the control box is zero
• Electric store 2 cylinders close both pilot isolation valves.
• Paint store 2 cylinders
Issue: Draft 2 5.3.2 Engine Room CO2 Fire Extinguishing System - Page 2 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.2a CO2 System in Engine Room
Cargo Steering Switchboard Control Purifier Electrical Electrical Paint Incinerator Emergency Laboratory
Compressor Gear Room Room Room Workshop Store Store Room Generator
Room Room
Laboratory
Emergency
Generator
Room
Time Time Time Time Time Time Time Time Time Time Time
Delay Delay Delay Delay Delay Delay Delay Delay Delay Delay Delay Incinerator
Room
Paint
Store
Electrical
Store
Electrical
Workshop
To
Free
Air Purifier
Room
Engine
Control
Room
Switchboard
Room
Steering
C46 C24 C14 C9 C7 C2 C1 Gear Room
(Note: Allow time for structural cooling before opening the purifier room and
ventilating the CO2 gas.)
WARNING
Do not enter CO2 flooded space without using breathing apparatus.
In the unlikely event of pilot gas release failure the second pilot cylinder valve
must be opened in order to release CO2 from that cylinder.
Manual Operation
Should the pilot CO2 cylinders fail to open the main CO2 cylinders for the
protected compartment then these must be opened manually. The main line
valve to the protected compartment must also be operated manually. The CO2
cylinders for each protected compartment are grouped together and so it is
easy to recognise which cylinders must be manually opened for any protected
compartment. The procedure for opening the main cylinders is as below; these
should be opened by operation of the manual release lever on top of each CO2
cylinder as follows:
b) Insert the end of the handle into the hole in the release lever.
Pull the handle as far as possible in order to operate the release
mechanism for the cylinder.
All cylinders can be individually manually discharged into any of the protected
cargo compartments as and when they are required.
Issue: Draft 2 5.3.2 Engine Room CO2 Fire Extinguishing System - Page 3 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.3a Engine Room Hot Foam Fire Extinguishing System Inert Gas Room
C
Test
Tank
Filling Line N.O
6 Generators
Local Control
Panel
Return Line Foam / Water Foam Foam / Water
Line Proportioner Line Engine Room Casing
L Valves
N.O C
Port
B Foam Tank PS PS
18 Generators
C
PS 18 Generators
Foam Pump
Local Control
D Panel
Starter
Engine Store
Flush Line C
2 Generators
Local Control
Panel
Main
Power Supply Control
Panel PS C Engine Workshop
A
4 Generators
Local Control
Panel
Key
Hot Foam
Electrical Signal
Sea Water
Fire Pump
(240m3/h 10kg/cm2) N.O Normally Open
Issue: Draft 2 5.3.3 Engine Room Hot Foam Fire Extinguishing System - Page 1 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
5.3.3 ENGINE ROOM HOT FOAM FIRE EXTINGUISHING of the system is designed to be able to supply foam to all of the protected but it should be noted that these remote panels only allow for operation of the
SYSTEM spaces simultaneously. foam system in that space.
The foam is generated by mixing the foam making chemical with sea water
Foam System
at a rate of 2% chemical solution to 98% sea water. The foam chemical mixes Procedure for Making the Foam System Operational
Maker: Unitor with sea water in the proportioner and the combined liquid is pumped to the
protected spaces through a 200mm supply line. a) Check the foam foam chemical tank visually for any damage or
No. of sets: 1 leakage.
Tank capacity: 6,000 litres
Each protected space is provided with hot foam generators designed to produce
Generator inlet pressure: 5.5 - 7.0kg/cm2 the required quantity and concentration of foam to meet SOLAS requirements. b) Ensure there is sufficient foam chemical in the foam tank.
Foam Pump The generators utilised are designated as HG-25s and these have a foam
production capability of 60m3/min. A total of 48 generators are used with the c) Check that the fire main sea water supply valves are all open.
No. of sets: 1 numbers in each location being as follows: These valves should be left open during normal service.
Type: Vertical centrifugal
• Engine room - 36 generators d) If the weather is cold, the pump and system heaters must be left
Model: DPVF 10-70
• Inert gas room - 6 generators on.
Capacity: 5.18m3/h
Discharge Pressure: 12kg/cm2 • Engine room workshop - 4 generators WARNING
• Engine room store - 2 generators Before activating the hot foam system in any protected compartment it is
essential to ensure that all personnel have been evacuated.
Fire Pump The generators are designed as an integral part of the hot foam system in
No. of sets: 1 which air from the protected space is used to aid foam production even when
Procedure for Operating the System from the Foam Room
Type: Vertical centrifugal smoke and combustion gases are present. The generators are constructed from
stainless steel and are built as one unit with no moving parts. They each have
Capacity: 240m3/h The following description and valve numbers refer to illustration 5.6a. When
three discharge nozzles. The water/foam mix enters the generator housing at a
Discharge pressure: 10kg/cm2 the system is not in use valves A, B, C and D must all be closed and valve E
pressure of between 5.5 and 7.0kg/cm2 and with the speed at which it passes
on the return line left open. If it is necessary to operate the system in the case
through the housing it creates a negative pressure. This pressure reduction
of a fire then the following procedure needs to be followed:
causes air and smoke to be drawn into the housing so mixing with the foam/
INTRODUCTION water solution to create a high expansion foam.
a) Ensure that power is available to the control panel and pumps.
The Unitor Hot Foam fire fighting system is a high expansion foam system that It is important to note that to ensure correct operation of this system only the
provides a local fire extinguishing capability to each of the following areas: b) Ensure that all personnel are evacuated from the space into
manufacturer’s approved foam making chemicals should be used.
which the foam is to be injected and close all doors and
• Engine room
openings to that space.
Electrical power for the pumps and control panels is supplied from the main
• Engine room casing
switchboard distribution system, however back-up power from the emergency
c) Start the fire pump.
• Inert gas room switchboard has been provided for.
• Engine room store d) Open the sea water supply valve A to the foam system in the
• Engine room workshop System Operation foam room.
The system supplies high expansion foam making chemical and salt water to The hot foam system may be operated in OP MODE or TEST MODE. Normal e) Open the solenoid operated valve C to the space into which
the spaces listed above through five dedicated lines that are each controlled by operation is in OP MODE and the system operation is controlled automatically foam is to be supplied. This will sound the local alarm to
solenoid operated butterfly valves. The system is manually operated and can by the programme logic circuit (PLC) in the control cabinet. In the event of this space and supply water only. The ventilation fans will be
be released from the main control cabinet in the foam room or locally from the failure of the control system the hot foam system may be controlled manually automatically stopped. This condition of only supplying water
remote control panels located outside each of the protected spaces. The foam in TEST MODE as described later. The test mode is normally used for testing is to be maintained for two minutes before foam is introduced.
chemical tank is fitted inside the foam room which is located on the starboard the system by utilising switches located at the front of the control cabinet.
side of the 21800mm deck. The tank is a standard 6,000 litre unit made from f) Open valve foam injection valve B to introduce foam into the
glass fibre reinforced polyester to safeguard against corrosion and has a full The hot foam system may be operated from the control panel in the foam room system.
charge when it has 5,824 litres of foam making chemical inside. The capacity or from individual remote panels situated outside each of the protected spaces
Issue: Draft 2 5.3.3 Engine Room Hot Foam Fire Extinguishing System - Page 2 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.3a Engine Room Hot Foam Fire Extinguishing System Inert Gas Room
C
Test
Tank
Filling Line N.O
6 Generators
Local Control
Panel
Return Line Foam / Water Foam Foam / Water
Line Proportioner Line Engine Room Casing
L Valves
N.O C
Port
B Foam Tank PS PS
18 Generators
C
PS 18 Generators
Foam Pump
Local Control
D Panel
Starter
Engine Store
Flush Line C
2 Generators
Local Control
Panel
Main
Power Supply Control
Panel PS C Engine Workshop
A
4 Generators
Local Control
Panel
Key
Hot Foam
Electrical Signal
Sea Water
Fire Pump
(240m3/h 10kg/cm2) N.O Normally Open
i) When the fire has been extinguished and the space has cooled In the event of failure of the system in OP MODE from the main control panel, System Testing
down the foam must be cleared from the room before personnel the system can be operated by utilising the TEST MODE according to the
may enter. Precautions must be observed regarding breathable following procedure. This is done from the control panel in the foam room. The system has been provided with a small 250 litre test tank that can be used
atmosphere and the risk of a further fire outbreak if the seat of to test the system without having to introduce foam into the engine room. The
the fire has not cooled down completely. a) Switch over to TEST mode on the panel and toggle the alarm method of operation is as follows:
switch to the ON position.
j) To stop injecting foam, stop both the foam and fire pumps and a) Attach a hose to the test connection hydrant valve with the other
close the foam injection valve B. b) Ensure that all personnel have been evacuated from the engine end of the hose directed overboard.
room.
b) Start the fire pump and open the supply valve A. Open the
Procedure for Operating the System from the Local Control c) Toggle the switch EM. POWER, FIRE PUMP and WATER hydrant valve so that it is passing water directly overboard.
Stations VALVE to the ON position. The fire pump will start.
c) Open the valve on the outlet of the foam test tank and start the
The foam system may be operated locally from four seperate locations which d) Move the INTERLOCK VENTILATION switch to the ON foam pump. After a short period, a mixture of foam and water
protect the five areas previously refered to. position and close all doors and openings to the engine room. should pass through the proportioner and go overboard.
In the event of a fire in any of these spaces the following procedure is to be e) Turn the water line valve switch to the ON position. d) When satisfied that the system is working correctly, close the
adopted to inject foam from the local control point. test tank outlet valve and stop the foam pump. It will now be
f) Turn the foam tank outlet valve switch to the ON position. necessary to fully flush through the lines to remove all of the
a) Open the remote panel door for the space in which there is a foam making chemical.
fire g) Turn the liquid foam pump start switch to the ON position.
e) Open flushing valve D and with the foam pump running again
b) Press the ALARM pushbutton for zone protection in the desired h) Turn the switches for the spaces into which foam is to be allow the lines to be flushed until all traces of the foam chemical
space. injected to the ON position. have been removed.
c) The alarm will sound in the selected space and the ventilation i) The system is now operating with immediate foam production. f) Stop the foam and fire pumps and revert all of the system valves
fans will be shut down. to their standby positions.
j) When the fire is extinguished the pumps must be stopped and all
d) After it has been determined that all personnel have left the valves closed. g) Refill the test tank as soon as possible.
protected area, close all doorways and openings.
Procedure After System Operation
e) Press the ON pushbutton for the protected zone into which foam
is to be injected. (Authors Note: No information on the control panels has been supplied and so
After finishing with the hot foam system the whole system must be thoroughly generic information has been obtained from similar installations. The method
flushed through with sea water. This is performed as follows: of initiating the system and controlling from the master and remote positions
f) The system is now operating for the required zone and after 2
minutes, during which time water only is injected, foam will be needs to be checked onboard.)
a) Start the fire pump and open the supply valve A.
injected into the space.
b) Close the foam return valve E back to the tank.
g) When the fire is extinguished the system must be manually
switched off by pressing the OFF pushbutton. c) Open the flushing valve B.
It is possible to operate the separate zone protection in TEST MODE from d) Start the foam pump and run water through the system until all
the control panel in the foam room. The operation is similar to emergency of the discharge pipes are free from foam concentrate.
Issue: Draft 2 5.3.3 Engine Room Hot Foam Fire Extinguishing System - Page 3 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.4a Water Fog System
Diesel Generator
Purifier Room
Tanks to be Verified
on Board
Incinerator
Key
Fresh Water
Boiler Port
Main Electrical Signal
Control
Power Supply Panel Manual Call Point
D D Detector
Dedicated
Fire Pump
Issue: Draft 2 5.3.4 Engine Room Water Fog Fire Extinguishing System - Page 1 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
5.3.4 WATER FOG FIRE EXTINGUISHING SYSTEM The protected spaces have detector heads and a local activation pushbutton There are a total of 38 deluge spray nozzles situated as follows:
situated just outside of the compartment. (Author`s Note. Insert details of
Water Fog Extinguishing System locations.) Protected Space No. of Nozzles
Maker: Unitor There are remote activation pushbuttons situated xxxxx (Author`s Note. Diesel generator 10
Pump model: CM-50/20 Insert details of the location of the remote pushbuttons and the control Port boiler 3
No. of sets: 1 panel.)
Starboard boiler 3
Type: Centrifugal
The fire detector heads, which control the operation of the water fog system via Purifier room 20
Capacity: 66.5m3/h at 6.0kg/cm2 the water fog control panel, are in addition to the detector heads which relay Incinerator room 2
a fire signal to the ship’s main fire alarm monitoring system. When a detector
head is activated an alarm is initiated and an alarm is raised on the water fog
Introduction Procedure for Setting the Water Mist System for Operation
fire alarm control panel. (Author`s Note. To check if the release of water
fog requires more than one detector to be activated. The system drawing (Author`s Note. This procedure is based upon the limited information
High pressure water forced through atomiser heads will break down into very supplied in the system manual and upon general knowledge of similar
only shows one detector in each compartment.) Under actual smoke/fire
fine droplets. These droplets have a very effective extinguishing effect on fires, systems. The actual details of the operation and valves must be checked
conditions, it can be expected that alarms will be indicated on both the ship’s
even oil fires. The fine droplets remain suspended in the air and so they do not on board.)
main fire alarm and water fog fire alarm panels at the same time.
disturb the oil surface nor do they settle to form a water layer on which burning
oil could float. Fine water droplets present a large surface area to the fire and so The description assumes that the port aft FW tank is being used.
The system uses fresh water in order to reduce the risk of corrosion but the
they exert a cooling effect as the droplets rapidly evaporate. The large droplet
lines are dry between the solenoid valves and the spray heads unless the system
concentration and the evaporation have the effect of reducing the local oxygen a) Check that the fresh water tank to be used has sufficient water.
is actually operating. The fresh water is taken from the port fresh water tanks
level. The cooling effect and the reduced local oxygen concentration result in
via dedicated valves, one of which must always be open. The water fog pump
the fire being extinguished. b) Open the supply valve from the port aft FW tank and close the
is located near the port fresh water tanks.
valve from the port forward fresh water tank.
The fresh water mist fire extinguishing system relies upon the delivery of
high pressure water to nozzle heads located at sites of fire risk. Five areas The fire alarm detector control panel for the water fog system is located in the (Note: There should always be sufficient fresh water available to cover the
are protected by the water mist system, these are the diesel generator engine, xxxx (Insert details of location of main control panel, any other panels ). largest section for a minimum of 20 minutes.)
the purifier room, the port boiler, the starboard boiler and the incinerator. The
area to be protected is provided with a number of nozzle heads fitted in the During daywork periods when the engine room is manned, the water fog c) Set the valves as in the following table:
supply pipe for that compartment. The main supply line to the compartment system may be set for manual operation as this will allow the engine room
has a solenoid operated isolating valve. The solenoid valve is activated by staff to assess a fire situation before activation of the water fog system. When
Position Description Valve
the fire control system when a fire detector senses a fire in the protected the engine room is in UMS unattended condition, the water fog system must
be set to automatic operation. (Author`s Note. This is normal but check on Open Port aft FW tank suction valve FS68
compartment.
board if it is applicable in this case; the manual gives no details of the Closed Port forward FW tank suction valve FS67
The dedicated fire pump is operated whenever the release of water fog into a control panel or control system.)
Operational Water fog pressure line solenoid valve
protected compartment is initiated by the control panel and this pump supplies
pressure water to the water fog distribution manifold. A main supply line The fresh water fog system releases water fog into a compartment automatically Open Water fog manifold inlet valve from pump
isolating valve is opened by the control panel when the pump is running and when a fire is detected by the compartment fire detection head(s). It can also
Closed Hydrant valve (01.3)
the isolating valve(s) to the protected compartment(s) allows release of water be activated by pressing the appropriate local compartment pushbutton, these
to the spray heads in the compartments where the fire is located. Operation of pushbutton units are coloured blue and can therefore be readily distinguished. Open Pressure gauge valve (01.2)
the pump and the solenoid operated valves is activated by the control panel The water fog control system also shuts off the ventilation system for the
Operational Supply solenoid valve to diesel generator engine
when compartment detector heads indicate a fire in a particular compartment compartment into which the water fog is being injected. (Author`s Note.
Check if this is the case for all compartments.) Operational Supply solenoid valve to port boiler
or a manual call point is activated for a particular compartment. Water fog is
only released into the protected compartment in which there is a fire. Operational Supply solenoid valve to starboard boiler
(Author`s Note. To be checked on board as the manual does not indicate A fire hydrant conection and valve (01.3) at the end of the pump high pressure
supply manifold enables the water fog system to be supplied from the fire main Operational Supply solenoid valve to purifier room
if the pump maintains pressure in the system or only starts when a fire
alarm is initiated.) if necessary. (Author`s Note. Check this on board.) Operational Supply solenoid valve to incinerator
Issue: Draft 2 5.3.4 Engine Room Water Fog Fire Extinguishing System - Page 2 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.4a Water Fog System
Diesel Generator
Purifier Room
Tanks to be Verified
on Board
Incinerator
Key
Fresh Water
Boiler Port
Main Electrical Signal
Control
Power Supply Panel Manual Call Point
D D Detector
Dedicated
Fire Pump
e) At the water fog main control panel ensure that the isolation
supply breaker at the side of the panel is set to ON and the
control voltage OK lamp and ‘heater on’ lamps are illuminated.
Set the dedicated fire pump space heater to ON. The system is
supplied from the emergency switchboard.
The nozzle heads and valves should be checked at intervals in order to detect
any leakage. The spray heads have plastic protective covers which should be
kept in place; they blow off when the system operates.
Issue: Draft 2 5.3.4 Engine Room Water Fog Fire Extinguishing System - Page 3 of 3
F T N AV I E R A
F. TAPIAS GAS-III Inigo Tapias Machinery Systems Operating Manual
Illustration 5.3.5a Fire Fighting Equipment on Engine Room 21800mm Deck and Bow Thruster Room
FOAM
Overflow Tank
N2 Generator N2 Compressors 86.7m3
Inert Gas Inert Gas
Inert Gas and Nitrogen
Blower Blower
Generator Room
Spare Air Blower
and Spare Electric Motor
for Air Blower
Pipe Duct
N2 Receiver
P
10
P
F12 10
Electric Hydraulic Machinery
Workshop CO2 CO2
Accomodation
Emergency Exit Air Conditioning
CO2 Electric Store
CO2 5
Units
W
Control Air Lift
Receiver
Boiler Forced Draught Fan CO2
P W
Engine Control Electric Machinery
Steering Gear Hatch - Bolted 10
Service Air Room
Gas Room Compressor
Escape Trunk Garbage
Compactor
W
Incinerator Room W
Garbage Storage
Area
P
CO2 CO2 10
P
Main 10
Boiler
Steering Gear Hatch - Hinged
CO2 5
FOAM Engine Control Room Console
CO2 5 5 kgs. CO2 Extinguisher
E.F.P
P
9 kgs. Dry-Powder Extinguisher 9 Lts. Foam Extinguisher A-0 Class Door Fire Control Plan Remote Start / Stop Fire F. Emergency Pump
10 F12 E.F.P
CO2
Release of CO2 Warping for Water Hose (30m) Water Mist Extinguishing Control Station
W
Space with CO2 Extinguisher System Hose Connection Foam Concentrate Pump Inert Gas Local
CO2 FOAM
FOAM
Space with Foam Extinguisher System Self Closing A-0 Class Door CO2 Battery Fire Fighting Emergency Pump
CO2
Inert Gas
Inert Gas Cooling Unit Drying Unit
Key
HFO Tank HFO Bunker Tank
Fresh Water 3 3
649.3m 1543.5m
Tank
3
258.6m
CO2 5 kgs. CO2 Extinguisher Fresh Water
5 Tank
3
279.4m
Inert Gas Generator Unit
P
10 9 kgs. Dry-Powder Extinguisher P
10
440V Switchboard
Sanitary
Hot Water Unit W P
10
Steriliser W
CO2
Release of CO2 Store Area
Sanitary
P Main Boiler
Water Fog Pump 10 Fresh Water
CO2 Unit
3.3KV
Space with CO2 Extinguisher System WMS Switchboard
CO2 440V Switchboards
W W
A-0 Class Door P
Washbasin 10
Rope Store Area
Distilled Water LO Gravity Tank P Diesel Generator LO Storage Tank 440V Switchboard
3 10
Tank 34m LO Tanks
Wires Store Area 151.7m
3 HFO Bunker
Water Mist Extinguishing Tools Panel HFO Service Tank
Tank 3
Milling Machine 1757.8m
3
Tools Panel Grinding Machine 222.5m
Engine Store HFO Service
Pipe Bending
Portable Foam Applicator Tank
F Machine 3
184.9m
Lathe
Sewage Plant
P
Space with CO2 Extinguisher System Main 50
CO2 Boiler
Diesel Generator
Warping for Water Hose (30m) ԏ Water Heating Unit
W Auxiliary Feed Water Pump Diesel Generator
Oil Filter
Cooling Unit
Main Solenoid Valves Cabinet
Chemical Injection Equipment Pre Lubrication Pump
Boiler
Hose Connection
Starting Air Receiver
Hydrazine (N2H4) Injection Equipment F12
Boiler Burner
FO Unit
FOAM
HFO Bunker Tank
Engine Room Floor
1543.5m3
Sea Water Pump
HFO Tank for Fresh Water Generator
649.3m3 Drain Centrifugal
Tank Bilge Pump
Auxiliary Upper Sea Chest
Drain Circulating Fire
Pumps Pump Pump
Lower Sea Chest
Jockey Pump
FO - DO Transfer LP CSW
Cargo Spraying Water Pump
Pump Turbine
Sea Water Cooling Pumps for Cargo
Stern Tube LO Sump Reduction
LO Pump Tank Gearing
Sea Water Cooling Pumps for Machinery
Bilge Well
Fire / Bilge Pump
Stern Tube FO Drain GO Transfer
Sea Water Cooling Pump for Inert Gas
LO Cooler Tank Pump
Condensate P Bilge Holding Tank
10
Filter Ballast Pump
Tail Shaft Idle
P
10 Condensate
Pump
W
Condensate Ballast Pump
Pumps
F12 Ballast Eductor
Ballast Pump
Oily Water Tank
Dirty Oil Tank
Key
Hose Connection
9 Lts. Foam Extinguisher
F12
Level 29,600mm
P
10
Key
Low Temperature
Fresh Water
Deaerator Tank Expansion Tank
P
10 9 kgs. Dry-Powder Extinguisher
CO2
Deaerator Tank
Release of CO2
Lifeboat W
Space Protected for Water Spray System
W W W CO2
Emergency
Switchboard
Emergency
2
Generator Room LO Storage
5
Tank
CO2
DO Storage
W W W Tank
Illustrations
FF22
FF34
FF27
FF31 FF32 FF33
FF11
FF19 FF14 FF24 FF29
PI
FF48 4004
FF30
From
Accommodation No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
FF35 FF15
FF46
PI FF16
To 4003
Accommodation
FF03
PI
4002
FF40 FF04 FF41 FF13 FF42 FF07 FF43 FF36
From
(Port) (Stbd) (Port) (Stbd) (Port) (Stbd) (Port) (Stbd)
Engine Room
See Illustration
5.3.1a
FF05
To Bilge To Power
No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank Ejectors Pack Cooler
PI
4001 FF39
Emergency Fire Fighting
Forward Pump
(285m3/h x 10 bar) PI
4000
FF37
To Power Pack Cooler Pump
H FF20
Sea Chest
B Deck C Deck
Main A Deck
Deck
PI
Hose boxes are located close to each fire hydrant. The hose box contains a fire
hose with nozzle and standard fixture to the fire hydrant. Hoses and nozzles
must be stored correctly after use.
Key
Nozzles for
SP551F SP552F
Cargo Domes
Cargo Manifold
(Port and Starboard)
SP608F
Passage
Passage Way
Way For Cargo
For Cargo Manifold Machinery Room
SP04
SP10 Manifolds
SP05 SP09 PI
4001
S SP01 S SP03 Liquid Gas Liquid Gas Liquid Gas Liquid Gas
Lifeboat Area Engine Casing
Dome Dome Dome Dome Dome Dome Dome Dome
S SP02
PI
4000
SP11 Manifolds
SP12
The emergency fire pump is located in the bow thruster and emergency fire
pump room. The pump is fed from the emergency switchboard 440V feeder
panel via breaker number 8E.
The pump is of the centrifugal type with a Eureka priming system type PMB
which ensures that the pump primes immediately it is brought into service. The
priming system operates automatically when the pump is started and makes
use of solenoid valves and an air ejector unit. The suction valve FF20 opens
automatically when the IAS receives a running signal from the pump. The
suction valve is closed manually and will give an alarm on the IAS screen.
Starting and stopping of the pump can take place from four locations;
• Locally at the pump
• From the 21800mm deck at the top of the compartment in which
the pump is located; the starter panel contains an isolation
switch and ammeter load indicator
• In the ship’s control centre
• The bridge
(Author’s Note: The emergency fire pump manual gives no details of starting and
stopping locations but the above are typical for such an installation: these must be
checked on board and amended as required.)
The emergency fire pump draws water from an independent sea water chest
located within the bow thruster room. The emergency fire pump sea chest
suction valve FF20 is actuated remotely; a suction valve FF37 is located before
the suction strainer. These valves are normally locked open. A non-return
valve FF39 is fitted in the discharge line, this discharge valve is normally
locked open. The pump and suction valves should be operated and lubricated
weekly.
Illustrations
E1
DO10 FO21 FO15 FO18 FO19
E2 Air Air
Gas Oil To HFO To HFO To HFO To Bottle Bottle
to Bunker Transfer Transfer Boilers E3
Incinerator Tank Pumps Pumps
Starboard
E4
Lubricating Oil Lubricating Oil Lubricating Oil Lubricating Oil Lubricating Oil
for Storage Tank Renovating Tank Storage Tank Gravity Tank
Deck Machniery for Diesel
Generator
CS5
LO?? LO02 LO01 LO14 LO??
Interconnection Valve for
Fire Fighting/Sea Water Service
To LO To LO To Diesel To Main on Sea Water Crossover Main
Transfer Transfer Generator Turbine
Pump/Purifier Pump/Purifier Sump
The emergency generator diesel oil tank quick-closing valve is operated by a Group E4
directly connected wire from outside the emergency generator room.
LO storage tank to LO transfer pumps and purifiers LO02
Oil Tank Quick-Closing Valves LO renovating tank to LO transfer pumps and purifiers LO01
LO storage tank for diesel generator sump LO14
CAUTION
Some tanks such as lubricating oil daily use tanks do not have quick- LO gravity tank for main turbine LO???
closing apparatus fitted. This is because they are normally closed and only Interconnecting fire fighting and SW cooling services CS5
opened for short periods when required. It is important to ensure that
Deck machinery oil tank LO???
these are always closed when not in use.
The sea water crossover line in the engine room which connects the low sea
Tank Valve
chests is fitted with a pneumatically operated fire fighting/sea water service
Group E interconnecting valve, CS5. The purpose of this valve is to ensure that in the
event of the fire fighting, fire fighting/bilge, or spray pumps being required
MDO daily service tank to diesel generator DO04 for fire fighting duty, the interconnecting valve can be shut to ensure that the
flow to these pumps will not be affected by the demand from the main sea
water circulation pumps. In normal sea mode, valve CS5 is kept closed. If the
Group E1
starboard low sea suction chest is being used to supply the main circulating and
MDO daily service tank to boiler burner for cold start DO08 sea water service pumps, and it then becomes necessary to quickly isolate the
starboard auxiliary sea water line to supply the fire and spray pumps, then it is
MDO daily service tank to diesel oil transfer pump DO03
very important that valve CS5 is not closed until either the port low sea suction
MDO storage tank to diesel oil transfer pump DO05 or high sea suctions are put in line.
MGO storage tank to gas oil transfer pump DO06
It is normal good working practice to ensure that a sea chest which is isolated
MGO daily service tank to IG burner DO07 is fully primed but left in an isolated condition.
Ventilation dampers are installed at various locations in order to shut off the
flow of air which would feed a fire in a particular compartment. The dampers
are to be closed in the event of a fire and ventilation fans shut off. In the event
of a fire in a space where CO2 is used ventilation is automatically shut off when
the system is initiated.
Ventilation systems in the engine room and accommodation spaces are also
provided with fan stops and fire dampers. Fans and ventilation systems may
be stopped locally or remotely as required depending upon the nature of the
incident. The shutting off of engine room ventilation fans automatically shuts
the ventilation dampers.
In the fire control station there is an emergency shutdown panel which contains
stops for fans and ventilation systems throughout the ship, together with stops
for machinery which might aggravate a fire situation. Ventilation systems
are grouped in order to allow any particular part of the ship to be isolated
quickly.
Within the accommodation fire doors provide protection and these must be
closed in the event of a fire. The doors are of the self-closing type and are kept
open by means of magnetic catches which are released in the event of a fire.
Insert details of the ventilation damper and emergency stops when available
Illustrations
5.6a Lifesaving Equipment and Escape Routes - Main Deck, Bosun’s Store and Bow Thruster Room
5.6b Lifesaving Equipment and Escape Routes - Engine Room 21800mm Deck
5.6c Lifesaving Equipment and Escape Routes - Engine Room 2nd Flat
5.6d Lifesaving Equipment and Escape Routes - Engine Room 1st Flat
5.6e Lifesaving Equipment and Escape Routes - Engine Room Floor and Turbine Mezzanine Deck
Chemical Products
Store
Bow Thruster
Distilled Cargo Auxiliaries Room Room
Water Tank
Trunk Deck Trunk Deck
Overflow Tank No.3 Tank No.2 Tank No.1 Tank Bosun's Store
No.4 Tank
Steering Heavy Fuel Oil
Gear Bunker Tank
Fuel Oil Tank
No.4 Water Ballast Tank
After Peak (Port & Starboard) Fore Peak
Water Ballast
No.4 Double Bottom Ballast Tank No.3 Water Ballast Tank No.2 Water Ballast Tank No.1 Water Ballast Tank Forward Deep
(Port & Starboard) (Port & Starboard) (Port & Starboard) (Port & Starboard) Tank
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310
Stern Tube Stern Tube Lubricating Dirty Oil Lower Sea
Cooling Water Oil Tank Oil Sump Tank Tank Chest
Bilge Holding Tank
Key
Primary Escape Route Life Jacket Immersion Suit Rescue Boat 6 Persons Manual Pilot Ladder
Lifebuoy Locker for Life Jackets Protective Clothing Lifeboat 40 Persons Bell
Lifebuoy With Line (30m) Inflatable Liferaft Safety Equipment Rocket Trigger Support Gong
Lifebuoy with Self-Igniting Light Embarkation Ladder Emergency Escape Breathing Device Ship's Whistle
x4 x2 x7 x6
No.5 Dry No.2 Dry No.1 Dry
Cofferdam No.4 Dry Cofferdam No.3 Dry Cofferdam Cofferdam Cofferdam
300
0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 310
Emergency Generator
Room x4 x4
Overflow Tank
N2 Generator N2 Compressors 86.7m3
Inert Gas Inert Gas
Inert Gas and Nitrogen
Blower Blower
Generator Room
Spare Air Blower
and Spare Electric Motor
for Air Blower
Pipe Duct
N2 Receiver Water Analysis Unit
Steering Gear
Air Exhaust
Electric Electric
Accomodation Workshop Store Key
Emergency Exit Air Conditioning
Units
Primary Escape Route
Boiler Forced Draught Fan General Service
Air Receiver
Steering Gear Air Fan Main
Boiler Lifebuoy with
Control Air Self-Igniting Light
Compressor
Control Air
Lift
Receiver
Boiler Forced Draught Fan
Lifebuoy With Line (30m)
Engine Control
Steering Gear Hatch - Bolted Service Air Room
Gas Room Compressor
Escape Trunk Garbage
Compactor
Life Jacket
Garbage Storage
Incinerator Room Area
Emergency Escape
Breathing Device
Main
Boiler
Steering Gear Hatch - Hinged
Rope Hatch
Acetylene Bottle Room
CO2 Room
Pipe Duct
Oxygen Bottle Room
Illustration 5.6c Lifesaving Equipment and Escape Routes - Engine Room 2nd Flat
Inert Gas
Inert Gas Cooling Unit Drying Unit
440V Switchboard
Sanitary
Hot Water Unit
Steriliser
Store Area
Sanitary
Water Fog Pump Fresh Water Main Boiler
Unit
3.3KV Switchboard
440V Switchboards
Washbasin
Rope Store Area
Distilled Water LO Gravity Tank Diesel Generator LO Storage Tank 440V Switchboard
3
Tank 34m LO Tanks
Wires Store Area 151.7m
3 HFO Bunker
Tools Panel HFO Service Tank
Tank 3
Milling Machine 1757.8m
Key 222.5m
3
Tools Panel Grinding Machine
Engine Store HFO Service
Primary Escape Route Pipe Bending
Tank
Machine 3
184.9m
Lathe
Secondary Escape Route
Pipe Threading Machine
Key
Sewage Plant
Main
Boiler
Turbine Generators
Escape Trunk
Diesel Generator
ԏ Water Heating Unit
Auxiliary Feed Water Pump Diesel Generator
Oil Filter
Cooling Unit
Main Solenoid Valves Cabinet
Chemical Injection Equipment Boiler Pre Lubrication Pump
LO LO HFO Service
Renovating Storage Tank HFO Bunker
Tank Tank 222.5m3 Tank
45.1m 3 73.3m 3 1757.8m3
HFO Service
Chemical Products Room Tank
184.9m3
Boiler Burner
FO Unit
Jockey Pump
Ballast Pump
Oily Water Tank
Dirty Oil Tank
Ballast Eductor
Ballast Pump
Stern Tube Oil Tank
LO
Shaft Intermediate LO Transfer Drain LO
Bearing Shaft Pump Tank Filter
Emergency Exit
Level 29,600mm
Cargo
Low Temperature
Fresh Water
Deaerator Tank Expansion Tank
Deaeator Tank
Key
Lifeboat x40
SART
Emergency
Switchboard
Emergency
Generator Room LO Storage
Tank
DO Storage Lifeboat 40 Persons
Tank
Life Jacket