Pioneer Enterprises
Pioneer Enterprises
Pioneer Enterprises
A Complete Presentation On
Scope Of Work And Strategies To Complete The Said Project Under
Sterlite Technologies Limited
Presented By
Dimension of Work
By the medium of this tender BSNL intends to cover a length of 6386 kms
connecting 1369 Gram Panchayats in 18 Blocks of Chattarpur, Sagar,
Damoh Raigarh Vidisha District of MP4 Circle.
M/S Pioneer Enterprises intends to work in MP4 circle and would like to
take up the responsibilities of Survey, Planning, Installation, End to End
Integration, Testing, Commissioning of both (Underground and Aerial) and
GPON Network along with maintenance of the Project from Sterlite
Technologies Limited at a Fairly Competitive Rates.
As per the needs of the tender BSNL intends to lay 6386 km of OFC
connecting 1369 Gram Panchayat of 18 Blocks in 5 districts of Madhya
Pradesh in MP4 circle.
Also we are aware that completion of the said project is time bearing and
heavy Late Delivery Charges maybe slapped on the Project
Implementation Agency for any kind of delays.
To tackle the situation and to successfully execute the project on time M/S
Pioneer Enterprises has created a group of 6 Contactor firms under its
leadership which will collectively work for timely execution of MP4 circle for
Sterlite Technologies Limited.
These 6 Contractor Firms have a strong background in laying of OFC for
BSNL and Private Operators. These firms are well equipped with man
power and machinery necessary to carry out the job. These firms have
authorised M/S Pioneer Enterprises to procure the contract from Sterlite
Technologies on their behalf and are ready work under Leadership,
Supervision and Guidance of M/S Pioneer Enterprises.
Distribution Of Work
Estimate for Completion of the Project
Although all the contractor firms working on this project have a sound
availability of manpower and machinery on their own but M/S Pioneer
Enterprises has advised him to rope of with small contractors and upgrade
their output to complete the project in a record Time.
But there may be delays in achieving the target due to unforeseen reasons
like Bad Weather, Delay in permission from different departments, Delay in
supply of material from Sterlite Technologies Limited, Holidays and
Festivals, Disturbed local situation, Delay in payment from BSNL via
Sterlite Technologies Limited and etc.
There can be several reasons for which work get delayed unwantedly and
M/S Pioneer Enterprises understand these unavoidable circumstances
hence to keep its words on the safer side M/S Pioneer Enterprises pledges
to complete the project for Sterlite technologies in 250 days failing which
Late Delivery Charges may be slapped on M/S Pioneer Enterprises.
The central office of the project will create a pool of machinery and
manpower on standby and these machinery and manpower will be
provided to allied contractors on demand.
With the help of these Supervision Teams, the Central Office of the Project
set up by M/S Pioneer Enterprises will be kept informed on the progress of
the project on daily basis.
This team will also make availability of necessary ROW permissions from
various departments as and when it is required The necessary fees and
official charges will have to be borne by Sterlite Technologies Limited.
In the event if any team is reported to be performing below target then M/S
Pioneer Enterprises will appoint an additional contractor with them to
support the job to be completed in targeted time.
Establishment of Central Office for the Project
The MP4 circle is spread in Chattarpur, Sagar, Damoh, Raigarh and
Vidisha District of Madhya Pradesh. Amongst these five district Sagar is
centrally placed in the MP4 circle with most of the blocks available at a
stretch of 60kms to 100 km from Sagar.
A Central Office in Sagar will perfectly be suited to control the said Project.
M/S Pioneer Enterprises owns two big offices in Sagar District City Centre
out of which one could be made as a Central Office of the project.
If required M/S Pioneer Enterprises will provide a work place for Executive
from Sterlite Technologies Limited in the Central Office of the Project.
There is a need to have a Central Storage Depot for the project where all
the excess items can be safely stored.
1) M/S Pioneer Enterprises will complete the project in 250 days unless it is
delayed due to supply of material or delayed due to non-payment of
monthly bills.
9) M/S Pioneer Enterprises will have the full responsibility of hiring and
arranging required machinery and manpower for execution of the said
project in 250 days.
Sister Companies
M/S Madhuraj Purohit (Established in 2003)
This company is involved in construction of Roads and Bridges on
contracts from Government of Madhya Pradesh. The company has
completed several projects under Pradhan Mantri Gram Sadak Yojana,
Rural Engineering Services, Madhya Pradesh Roads Development
Corporation and etc.
Machines Quantity
HDD Machine Horizontal 4
JCB Machine 10
Porclain 200 With Breaker 2
Splicing Machine 10
Dumper 10
Trailer 2
Road Roller 5
Hot Mix Unit 1
Paver Finisher 2
Crusher 1
Excavator 110 4
Blasting Tractor (Compressor) 2
Blowing Machine 1
Bolero For Sight Inspection 4
Allied
Contractor
Details
M/S Om Construction Co.
32, Indrapuri Colony, Tikamgarh (M.P), India Pin 472001
Main Promoters - Mr. Durga Prasad Dixit
Constitution - Partnership
Year Of Incorporation - 2002
PAN - AAAFO9110F
GST Reg. No. - 23AAAFO9110F1ZR
ESIC Reg. - 18000241930000999
Machines Quantity
Jaw Cresar 2
Hot Mix Plant 1
Paver 1
Dumpher 4
Self Loader Mobile Concrete Mixer 1
Vibrator Roller Single Drum 1
Roller Stetics 2
110 TATA Truck 1
JCB 2
Hopar Mixer 2
Concrete Vibrator 2
Tractor 2
Water Tankler 4
Plate Shuttring 200
Letter Of Authorization
M/S Jai Mata Dee Construction
5-2, 501/98, Saket Nagar, Bhopal M.P - 462024
Main Promoters - Mr. A. K. Singh
Mr. S. S. Singh
Constitution - Partnership Firm
Year Of Incorporation - 2008
PAN - AAAGFJ5007L
GST Reg. No. - 23AAGFJ5007L2ZG
ESIC Reg. - 18000167970001000001
EPF Reg. - MP/BPL/0021146/000
Machines Quantity
JCB 2
Excavator 110 2
Splicing Machine 2
Rock Breaker 1
Blasting Tractor (Compressor) 2
Blowing Machine 1
HDD (20 Ton) 1
Letter Of Authorization
M/S Vab Agency, Itarsi
Arunodaya Apertment 1st Floor Near Dr. Heda's Clinic,
Deshbandhupura Itarsi (M.P)
Main Promoters - Mr. Tarun Popli
Constitution - Partnership Firm
Year Of Incorporation - 2005
PAN - ARXPP9652P
GST Reg. No. - 23ARXPP9652P1ZJ
ESIC Reg. - 1800021950000999
EPF Reg. - 21251/265
Machines Quantity
JCB 5
Splicing Machine 25
Rock Breaker 1
Blasting Tractor (Compressor) 3
Blowing Machine 4
HDD (20 Ton) 2
HDD (18 Ton) 5
HDD (30 Ton) 1
Letter Of Authorization
M/S Ashok Kumar Dubey Govt. Contractor
D-1/68, Danish Nagar, Hoshangabad Road, Bhopal (M.P)
Main Promoters - Mr. Ashok Kumar Dubey
Constitution - Proprietership Firm
Year Of Incorporation - 2008
PAN - AEAPD5230R
GST Reg. No. - 23AEAPD5230R12N
EPF Reg. - MP/BPL/18181/1473
Machines Quantity
JCB 2
Excavator 110 2
Splicing Machine 2
Rock Breaker 1
Blasting Tractor (Compressor) 2
Blowing Machine 1
HDD (20 Ton) 1
Letter Of Authorization
M/S Betwa Buildings & Engineering Works
74, Sadar Bazar, Jhansi (U.P.)
Main Promoters - Mr. Mohd. Nayeem
Constitution - Proprietor Ship
Year Of Incorporation - 1994
PAN - ACFPN3382F
GST Reg. No. - 09ACFPN3382F1Z1
ESIC Reg. - 21-26730-101
EPF Reg. - UP29607
Machines Quantity
JCB 4
Excavator 110 2
Splicing Machine 4
Rock Breaker 2
Blasting Tractor (Compressor) 3
Blowing Machine 2
HDD (20 Ton) 1
Letter Of Authorization
A Complete
Spectrum Of Work
&
Services Offered By
M/S Pioneer Enterprises
To
Sterlite Technologies Limited
In MP4 Circle
Scope of OFC work
Route Survey
Total Design
ROW Permissions
Trenching and associated Civil works
Horizontal Directional Drilling and Boring Works
Supply, Installation and Commissioning of -
HDPE, GI, RCC, DWC and PVC pipes
Cables (OF and Cu), Splice Closures, FMS, Optical Network
Equipment, Electronic Route Markers
RCC Markers, Chambers, Manholes, Hand holes, Splicing of Cables
Earthing and Link Testing, Operation and Maintenance of OFC
equipment’s and cables.
Backbone Network
The entire route is surveyed for laying of Optical Fiber Cables for the
following inputs:
ROW demarcation
Soil Strata
Existing Underground Utilities
Road / Rail / Bridge / River / Canal Crossings
BOQ Estimation
Any other criticalities
BOQ Estimation
On the basis of survey details an estimated BOQ is prepared and
submitted to get
the approval from the customer.
State Highways
Railway Department
Roads and Buildings Department
Municipal Corporations
Panchayats
Irrigation Departments
National Highway Authorities
Cantonments
Line up of trench would be such that HDPE ducts will be laid in straight
line, both laterally as well as vertically except at locations where it has to
necessarily take a bend because of changes in alignment or gradient of
trench. Minimum radius of two meters will be maintained where bends are
the only option we are left with.
Duct Laying
Ducts are laid in a flat bottom trench, free from major obstructions and
sharp-edged debris. The duct will be placed in a trench as straight as
possible, however at bends horizontal and vertical, minimum
bending/ruling radius for duct will be maintained as per advised
specifications or standard codes.
Ducts will be laid preferably using dispenser designed for it. Our
Supervisor will ensure that duct laid is free from twist. Any such portion will
be rectified before backfilling by using couplers.
End of ducts will always be closed with END PLUGS to avoid ingress of
mud, water and dust. We ensure HDPE ducts are clean and clear or
abence of any unwarranted particles which can cause obstruction in laying
of cable. Prior to the aligning the ducts for jointing length of each HDPE
ducts will be thoroughly cleaned to remove any other debris that may
disturb or damage the optical fiber cable when it is pulled or blown at later
stage.
The ducts will be joined with couplers using duct cutter and other tools
so that it is secured. The duct joint will be practically air-tight to ensure
smooth cable blowing. Laying of GI and/or RCC pipes as additional
protection for the HDPE ducts at Rail / Road crossings, built-up area / city
limits, on culverts and also on stretches wherever depth of excavation is
less than specified will be done.
Crowning
When backfilling has been completed up to the ground level, an extra
layer of soil is made up to cater the primary settlement and future soil
consolidation. Entire excavated soil will be used for backfilling. Crowning
will be confined over the width of trench only.
Duct Integrity Test
The purpose of DIT (Duct Integrity Test) is to prove that the installed ducts
are ready to use for blowing from one manhole to the other. DIT should be
performed before blowing to avoid sudden surprises like missing section
of ducts, improper coupling, and kink and blockage in ducts. The DIT is
carried out with the help of compressed air and a suitable go- gauge
sponge and mandrel of appropriate size, which is pushed inside from one
end with pneumatic pressure and is thrown outside from the other end. It is
conducted in three steps.
2. Shuttle Test -To check that duct has not collapsed or kinked, a wooden
cylindrical piece (shuttle) is blown into the duct with far end fitted flexible
wire grip / stocking. The wooden shuttle should pass through duct at far
end without any obstruction andwithin approximately 10 minutes or less.
3. Sponge Test - Very often mud and water are found inside an
underground duct. In this test a sponge double the size of duct inner
diameter is passed through by compressed air to clean the duct.
Fiber Termination
1. With connectors that can mate two fibers to create a temporary joint or
connect the fiber to a piece of network gear
2. With splices which create a permanent joint between the two fibers.
Installation of FMS is done as per the Manufacturer's specification.
End to End testing can be carried out from the FMS to FMS using the
connectors which aremounted on the FMS.
Survey and Digitized Maps
Proposed OFC route and its relative position with respect to existing
cables.
Identification of Rocky, Submerged and Normal soil types and terrain.
Identifying important landmarks and Marking of Crossing locations and
the type of proposed crossing details viz. HDD, Open -cut and Boring
etc.
Geographical co-ordinates for all crossing HDPE duct coupling and
OFC joint locations.
Marking of Offset availability
Assessment of required materials.
Demarcation of Row.
Identifying critical points.
Cable Testing
All the laid cables are tested before pulling /blowing to ensure continuity as
well as to evaluate the loss, if any.
Aerial Cabling will be done at places where open trenching is not possible
due to very narrow roads or delay in obtaining Row as a temporary
solution. Also by using special cables (ADSS) this will be laid along the
Transmission Lines for longer distances.
Cable Drum will be loaded on payoff stand and unwound from topside of
the drum. Payoff stand will be placed properly so that it should not fall while
dispensing OFC.
Fusion Splicing
End to end link tests are basically carried out over the entire section at both
the ends after the completion of tasks to ensure that the work is done
efficiently and the loss is within permissible limits on all fibers.