You are on page 1of 5
At a glance
Powered by AI
The document describes several instruments used to monitor ground movements and fluctuations in groundwater levels, including settlement markers, groundwater standpipes, vibrating wire piezometers, inclinometers, and magnetic extensometers.

The different types of instruments described are settlement markers, groundwater standpipes, vibrating wire piezometers, inclinometers, and magnetic extensometers. Each instrument monitors a different parameter related to ground movement or water levels.

A vibrating wire piezometer has a tip installed at different borehole depths with coarse grain sand and bentonite pellets. It is connected to a data logger via electric cable to record changes in groundwater pressure. The borehole is protected to prevent disturbance.

SETTLEMENT MARKERS 

The settlement marker is used to measure a localised settlement or heave of roads, slopes, 
embankments, utility pipes and cables. 
 
Concrete to be 
  painted in yellow Painting

  Convex End 
Concrete Nail

 
Concrete Nail
 
800 minimum 

Concrete

50mm 
  Concrete Structure 
100Ф PVC or 
Steel Tube  Sand Fill 
 

  75 mm Ф hole filled with 
cement grout after  Schematic diagram of installed settlement 
  placing‐in the steel rod. 
marker on concrete 
  25Ф Steel rod 

 
Schematic diagram of installed settlement marker in soil 
 

 
Backfill  Backfill soil 
 
Varied Length 

soil 75 mm dia Heavy duty 
  PVC pipe with Cap 

  16 mm dia mild steel rod 

  50x50x4mm steel plate
 

  Cross‐section of 
10 cms  Utilities/Services 
 

  Schematic diagram of installed settlement marker on utility 
 

INSTALLATION AND MONITORING 

 
 
Settlement Marker on Concrete  Settlement Marker for Utility 
  Installed on a Pavement  services Settlement Marker in Ground 
 

 
The monitoring of settlement marker is carried out by leveling survey and readings are taken at regular intervals to 
check any settlement or heave. 
 
GROUNDWATER STANDPIPE 
Measures fluctuation of ground water level. It is used as part of a system for early detection 
of water loss that could cause ground settlement. 
 

INSTALLATION 
 

 
Protective 
  Cover 

  Ground Level 

  Bentonite Pellets 

  Perforated PVC Pipe 

 
Coarse Grain Sand 
 
Bottom Cap 
 

 
A cap and protective box is placed 
 
Schematic diagram of ground water stand pipe over  the  water  standpipe  tube 
  opening to prevent disturbance. 
 
 

MONITORING 
 

 
Water level indicator
 

 
Ground water level is measured by using water level indicator. The probe of water level indicator is lowered down into 
 
the water standpipe until light or buzzer indicates contact with the water. Depth to water level is measured from the 
  measuring tape attached to the indicator. 
 

 
VIBRATING WIRE PEIZOMETER 
Measures changes in the ground water pressure at different depths. It is used as part of a 
system for early detection of change in water pressure that could cause ground settlement. 

INSTALLATION 
 
To terminal
 
Ground Level
   

 
Grout
 

 
Electric Cable 
 

  Bentonite 
Pellets 
 
Vibrating wire 
Coarse Grain  Vibrating wire piezometer tip
Piezometer tip 
  Sand 

 
Schematic diagram
 

 
The borehole with vibrating wire piezometer installed is kept in a protective metal box to prevent 
damage & disturbance to the instrument. 
 
MONITORING 
 

 
Vibrating wire piezometer 
 
data logger
 
The vibrating wire piezometer is connected to the read out unit and the 
 
ground water pressure readings are recorded and stored in the data logger 
 
INCLINOMETER 
Measures lateral movements of the ground, retaining walls and piles for early detection of 
any disturbance or effect to structures and property due to construction activity. 
 

INSTALLATION 
 
Protective 
  cover

Ground Level 

Grout

 
 
 
 
After  the  installation  of  Metal  protective  boxes 
Inclinometer 
  casing inclinometer casing in the  are used to prevent the 
hole,  the  casing  top  is  instruments from being 
 
capped  to  prevent  the  disturbed.  Instrument 
Bottom 
  entry of foreign particles.  identification  is  affixed 
  on to the box. 
 
Schematic diagram of inclinometer casing
 

MONITORING 
 

 
Inclinometer probe 
 

  Cross section view of inclinometer probe inside the casing during monitoring works 

The inclinometer probe is lowered down in to the casing and at every 0.5 m intervals it records the lateral movement. The 
raw data obtained is transmitted from the inclinometer probe to a read out or a PDA by Bluetooth technology. 

 
MAGNETIC EXTENSOMETER 
Measures settlement of the ground at various depths for early detection of any disturbance 
or effect due to construction activity. 
 

INSTALLATION 
 

 
Installed casing is capped and kept in a protective 
 
metal box to prevent damage & disturbance  
 
 
 

  Schematic diagram of magnetic extensometer

MONITORING 
 

 
Magnetic extensometer probe & spider magnet
  
 

The magnetic extensometer probe is lowered down into the casing untill light or buzzer indicates the contact with the spider 
magnet. Depth of the magnet is measured from the measuring tape attached to the probe. 