Project Management Using GERT Analysis
Project Management Using GERT Analysis
Project Management Using GERT Analysis
LAURENCE J. MOORE
GERT Modeling
The conceptual framework for construction of PERT/CPM networks is straight
forward and generally well-known. However, since GERT networks are similar
in construction to PERT/CPM networks it will be useful to briefly review the
PERT/CPM components.
PERT/CPM networks consist of two major components, activities and events.
Network activities represent actual operations of the real-world project, while
events represent milestones in the project that occur at a point in time. Events
can represent the beginning or end of an activity or both; and, the beginning
or end of both of more than one activity. Activities generally consume time and
resources. In network configuration, events are represented by arrows. PERT
and CPM differ in that in CPM activities are assumed to have only a single
time for duration while in PERT the activity times are probabilistic, and
typically described by a three estimate beta distribution. (For a more detailed
explanation of PERT and CPM see [5]).
Model Results
The GERT R&D network was simulated 1000 times from which time and cost
statistics were generated. The results of the simulation are summarized in
Tables 2 and 3. Interpreting the results, there is a .745 probability that the
project will be successfully completed, with an expected completion time of
419 days. The average cost of successful completion is $473,000. The
maximum time the project will take, as indicated by the simulation, is 1,514
days, with a cost of $1,147,900. Alternatively, there is a .255 probability the
project will washout in an average time of 182 days, with an associated mean
cost of $195,000. The GERTS-IIIZ simulation package can also provide time
and cost statistics at individual network nodes in the form of frequency
distributions, which can then be converted to histograms. Figure 3 shows an
example of a histogram for time statistics collected on node 9, time to
successful completion of the project. Similar histograms can be developed for
time statistics on node 7, and cost statistics on both sink nodes.
Time (days)
This same type of probabilistic analysis can be performed for a project failure.
In this way management can ascertain information regarding its potential
losses since a project failure typically represents a loss. For the R&D example
there is a .96 probability that, if the project washes out, a cost (i.e. loss) of at
least $350,000 will be incurred. This potential loss may make the firm ponder
its undertaking more in-depth. Probabilistic data on project failure can further
be used to determine the most likely time a washout will occur so that
contingency plans can be developed (i.e., alternative projects arranged) in
order to keep R&D project teams and work forces fully scheduled.
GERT output can also be used to determine labor, equipment and resource
needs for the project under analysis. Typically, cost statistics are employed as
budget data with these factors included. For example, if statistics for project
time showed an excessive project duration then extra labor, equipment or
capital could be added to reduce total project time. Such additions could also
be made to reduce the possibility of project failure at late stages in the project
where associated costs would be highest. The effect of these resource
increases would subsequently be reflected in the project cost statistics (i.e.,
budget). (An alternative to resource determination is to use the fixed and
variable cost feature of the simulation model for resource units as opposed to
dollar values in order to determine resource consumption directly).
The network itself can be modified and adjusted to reflect alternative project
strategies. GERT networks in general are usually sensitive to outcome
probability changes. For example, in Figure 2 if the probability of realization
for activity 4-3, a problem redefinition, is altered the overall network time and
cost can be significantly effected. Management can take advantage of this
capability by adding and subtracting resources to see how outcome
probabilities are effected and hence how the overall network is affected. For
example, management might determine that their time frame is much more
flexible than the expected time indicated by the network simulation. By
reducing resources (i.e., pulling off men, capital and equipment), activity 3-4,
problem definition is not as effective, thus, the probability of activity 4-3,
problem redefinition, is increased which increases overall network time. In this
instance the firm saves resources (which might be critical) in lieu of time which
may be readily available. Of course, this logic can work in the opposite
direction, wherein the time frame is critical and resources are available in
abundance, in which case the outcome probabilities for looping are reduced
by adding resources. In general, the GERT model is ideal for testing trade-off
situations between project time and cost.
In general, the GERT network is not as sensitive to activity time changes as
node branching probability changes. Of course if the project activity times are
extremely cost sensitive then a slight alteration in an activity time can affect
network (project) cost even though the overall network time might not be
affected significantly. However, one of the unique capabilities available with
GERT is the ability to use any one of nine probability distributions for activity
times. Since projects which are networked tend to be unique, the selection of
activity probability distributions is subject to a great deal of uncertainty. In
such cases it can be useful to experiment with alternative distributions to
observe the overall affect on network statistics. Such experimentation can
lead management to perform much more in-depth research into the nature of
activity time distributions rather than simply accepting the subjective beta
distribution as is so often done in PERT This can lead to further insight into
the activities and project analysis in general.
An important network modification which can have a significant affect on the
management planning process is the probability of project washout (or
failure). This aspect of network analysis was briefly mentioned previously but
it needs to be discussed in greater detail. The probability of project failure
reflected by node 7 in the example network (Figure 2) represents the inherent
risk in undertaking the project. At the very least, the probability of a washout
offers a guideline to compare with some acceptable risk level for the projects
undertaking. This risk indicator can become more complex if there are several
opportunities for project washout. For example, in our R&D network, if there
were chances of washout from nodes, 4, 5, and 8 as well as node 6, then the
problem of determining how to reduce the probability of project failure
becomes more difficult. In such a case the opportunities to affect project
failure, either positively or negatively, increases via the additional activities
directly affecting a washout.
The type of information discussed in this section can have important
ramifications for project contract negotiations. If the project is for internal firm
use, it is beneficial in contracting for labor, materials, capital and equipment.
However, in the important case of project planning for external use, GERT
information can aid in setting contract prices so that the firm can be assured of
a profit. For example, since the probability of exceeding $700,000 for the
successful completion of the project is .07, a contract price of $900,000 would
seem to provide a reasonable chance to make a profit and management could
react accordingly. The same analysis could be used for establishing a project
due date. The washout data can enable the firm to build minimum losses into
a contract and perhaps distribute the potential losses between the firm and
the customer in an equitable fashion.
GERT vs PERT/CPM
Summary