Date Taken: 17-Jun-17 Location: Unit 2 Boiler/Bunker Area #1 Date Taken: 17-Jun-17 Location: Unit 2 Ball Mills Area #2
Work Description: Installation of BLR drain piping Unit#2 Work Description: Installation of CCCW piping at Ball Mill#2 area
Date Taken: 17-Jun-17 Location: Unit 2 Coal Bunker Area #3 Date Taken: 17-Jun-17 Location: Unit 2 Boiler Area #4
Work Description: Installation of Instrument Air piping at Coal Bunker#2 Work Description: Installation of N2 piping at Boiler #2
Date Taken: 17-Jun-17 Location: Unit 2 Boiler Area #5 Date Taken: 17-Jun-17 Location: Near Unit 2 Boiler Area #6
Work Description: Installation of Service Air piping at BLR#2 Work Description: Insulation of SCAH drain Unit#2
THAI BINH THERMAL POWER PLANT PROJECT & TRASMISSION LINES CONSTRUCTION PROJECT
Date Taken: 17-Jun-17 Location: Unit 2 Boiler Area #7 Date Taken: 17-Jun-17 Location: Unit 2 Boiler to ESP/FGD Area #8
Work Description: Insulation of steam piping at BLR2 Work Description: Insulation of Auxiliary steam supply to FGD&ESP
Date Taken: 17-Jun-17 Location: Yard piping trench area #9 Date Taken: 17-Jun-17 Location: Pipe Rack @ Unit 2 #10
Work Description: Installation of discharge piping for Boiler blowdown water Work Description: FRP raw water Unit#2 installation
Date Taken: 14-Jun-17 Location: Unit 2 Economizer Area #11 Date Taken: 15-Jun-17 Location: East of Gypsum Dewatering Bldg. #12
Work Description: Installation of ash conveyor piping Work Description: Installation of Pipe for Fire Fighting Underground Line 13A