SUBJECT: STG#2 Thermal Insulation works

ID No. ID No.
JEL's Activity Description MPS R3 Activity Description
(JEL) (MPS R3)

Gland Steam Piping for Unit 2 3270 Installation of Piping & Supports_Gland
Seal System
A Auxiliary Steam & Drain Piping (Large Bore)
2427 Insulation of piping
B Auxiliary Steam & Drain Piping (Small Bore)

Heater/Feedwater storage Tank equipment Installation of Piping & Supports_Feed


C 3269
& Level piping Water System (BFP to Boiler TP)
D Instrument Piping none none
G 3107 Insulation for cross-over pipe
Steam Turbine & Aux. Equipment
3131 Insulation work fro HP/IP/Turbine

3313 Condensate Pump (CP) operation


F Pump
3314 Boiler Feed Pump (BFP) operation

G Steam Jest Air Ejector 3271 Installation of Piping & Supports_Extraction


Piping
H Flash Tank none none
Duration MPS R3 Start MPS R3 Finish Remarks
(days) Date Date

199 18/Jul/16 6/Mar/17

143 18/Jul/16 19/Jul/16

131 1/Jul/16 30/Nov/16

none none none


33 21/Mar/17 27/Apr/17
64 16/Dec/16 28/Feb/17

9/May/17
Insulation works must
be completed before
27/May/17 CP & BFP operation
dates
196 27/Jul/16 11/Mar/17

none none none