SUBJECT: STG#2 Thermal Insulation Works ID No. (JEL) ID No. (MPS R3)
SUBJECT: STG#2 Thermal Insulation Works ID No. (JEL) ID No. (MPS R3)
SUBJECT: STG#2 Thermal Insulation Works ID No. (JEL) ID No. (MPS R3)
ID No. ID No.
JEL's Activity Description MPS R3 Activity Description
(JEL) (MPS R3)
Gland Steam Piping for Unit 2 3270 Installation of Piping & Supports_Gland
Seal System
A Auxiliary Steam & Drain Piping (Large Bore)
2427 Insulation of piping
B Auxiliary Steam & Drain Piping (Small Bore)
9/May/17
Insulation works must
be completed before
27/May/17 CP & BFP operation
dates
196 27/Jul/16 11/Mar/17