Clauses of Contract Agreement
Clauses of Contract Agreement
Clauses of Contract Agreement
SL.
DESCRIPTION PAGE
NO.
MAJOR CLAUSES OF A SUPPLY AND SERVICE AGREEMENT
ORGANIZATION CHART AT A GROUP LEVEL
Handling Plant.
The scope of work covers design, manufacture, supply, construction, erection and
commissioning, testing and delivery at site of the complete coal handling plant
equipment and accessories only, including mechanical, civil & structural, Electricals,
1. Definition of terms:
Here the meaning of the following terms is clearly defined which reflects in the contract
agreement document, the meaning herein assigned holds good unless there is something
Contractor
Sub- contractor
Engineer
Inspector
Contract
Site
Test on completion
Pre-commissioning
Initial operation
Trial operation
Commissioning
Warranty period
Month
Writing
Services
In this clause the following main scope of supply & services of the contractor are
Civil works
Insurance,
Storage,
Erection,
Testing
Commissioning.
Providing of all labors
Here all the facilities / services to be provided by the owner to the contractor free of
all charges except whether specified are stated. Some of them pertaining to the
project are.
Unloading bay
Approach roads
4. Price:
Here the total price of the project is given on a break up basis as follows
entire scope.
5. Terms of payment:
Here the break up of the total price to be paid to the contractor defined based on the
6. Mode of payment:
Here the mode of all payment including advance payment is mentioned. If there is
any delay in the payment, which is due to contractor, beyond specified days from the
date of submission of invoice with complete document, then the owner pays
specified interest rate higher than the prevailing bank cash credit interest rate.
7. Completion schedule:
Time is the essence of the contract and this clause ensures that the contractor shall
erect, commission, put into commercial operation complete in all respect in the
agreed time.
8. Insurance:
This clause defines that the contractor shall cover on behalf of the owner, the MCE
insurance of all equipment during transit, storage, erection, testing commissioning till
successful completion of trial operation of each unit and shall remain responsible for
lodging claims and arrange settlement/ reimbursement of such claims with / from the
insurance company.
Subject to force majeure conditions, if the contractor fails to complete the project on
or before commercial operation date agreed then owner shall have the right to
recover as Liquidated damages (LD) and not by way of penalty a sum equivalent to
0.25% of contract value for delay of each week. The liability for delay shall not in any
Here the provision is made so that the contractor shall prepare a list of sub vendor
for the supply and services and furnish the same with necessary documents for
11. Indemnity:
Here the provision is made so that the contractor shall indemnify the owner for all
Here it is mentioned that no person other than the contractor or his duly appointed
Engineer/ inspector shall have at all reasonable time access to the contractors
premises of work and shall have the power at all reasonable time to inspect
shall carry out all necessary tests preparatory to starting up of the plant as per
And the final tests as the PG tests for total plant would be conducted as per L1
schedule.
Here it is specified that no order shall be cancelled after issue of the order or the
understanding to proceed with the work. In event of cancellation, the contractor shall
discontinue the work on the date and stop all further subcontracting or purchase
activity related to the work. In the event of such cancellation the contractor shall be
paid compensation as mutually agreed to depending upon circumstances prevalent
15. Arbitration:
This clause makes sure that if at any time question, dispute or difference whatsoever
shall arise between the owner and the contractor upon or in relation to or in
connection with the contract, either party may forthwith give to the other, notice in
writing to the existence of such question, dispute or difference and the same shall be
referred to the adjudication to two arbitrators- one to be nominated by the owner and
the other to be nominated by the contractor, and the two arbitrators shall appoint a
third arbitrator who shall be the presiding arbitrator as per provision contained in the
Here it is mentioned that the contract or an order will be considered as having been
accepted only when the contractor has confirmed it in writing. No legal proceedings
to enforce any claim and no suit arising out of any contract shall be instituted except
Here it is mentioned that the contractor shall submit to the owners engineer for
showing the programme and the sequence in which contractor proposes to carry out
the work with dates and erection completion time. There shall be regular co-
ordination meetings between the representative of the contractor and the owner.
And during the progress of the work, the contractor shall furnish monthly progress
contractor each item of equipment shall be thoroughly inspected by both parties for
Here it is mentioned that the unit shall be considered as provisionally taken over
finally taken over after successful completion of PG tests during post- commercial
operation.
Here it is mentioned that the contractor or the owner shall not be liable for failure in
performing his obligation resulting directly or indirectly from any force majeure cause
1. Any natural cause which, is beyond the control of the supplier or the
21. Warranty:
Here it is specified that the warranty of the plant in respect of erection, workmanship
and quality shall cover a period of twelve months from the date of successful
plant / equipment/ machinery due to faulty/ defective erection during the warranty
period.
Modification work of any nature arising out of faults not attributable to contractor
shall be treated as extra work and shall be executed by the contractor when asked
in writing by the owner subject to resources at site fr4o which payment shall be
This clause specifies that due to causes not attributable to the contractor or for
reasons over which contractor has no control, if the contactors work is either
conditions with time loss and financial compensation shall be intimated in writing by
Here it is mentioned that all materials brought by the contactor to meet erection
25. Safety:
precautions against fire and other accidents for the materials and personnel working
and within the contract period, the contractor shall provide from time to time
This clause compels the contractor that contractor shall fully cooperate with the
This clause ensures that if the complete plant or any portion is found to be defective
or fails to fulfill the requirements of the contract due to faulty erection &
commissioning, the Engineer shall forthwith give the contractor notice setting forth
particulars of defects and if the contractor accepts the defects in working, shall
forthwith make defects good or alter the same to make it comply with the
the owner may reject and replace at the cost of the contractor.
This clause ensures that all the activities like erection, testing and commissioning is
carried our as per relevant Indian / International (latest) codes and standards and
Here provision is made so that all demurrage, wharf age incurred by the owner due to
10 % of total contract price in the form of a Bank guarantee of equivalent value and the
Here the required drawing & instruction manuals are mentioned for erection and
34. Consignee:
Here the address of the consignee for all the erection materials / equipments including
Here provision is made for taking care the mutually agreed changes covered in the