Coal Handling Operation Manual
Coal Handling Operation Manual
Coal Handling Operation Manual
This COAL HANDLING OPERATION SYSTEM MANUAL was made according to the instruction
book of maintenance and relevant drawing offered by the coal handling equipment manufacturer of
the 2315M coal fired power plant project in PACITAN, Indonesia. It is only suitable for the
operation of the coal handling system of the 2315M coal fired power plant project in Pacitan,
Indonesia.
The manuals will be revised and improved with the project progress development.
Page 2 of 160
Content
1
1.1
1.1.1
Overview....................................................................................................................................................5
1.2
SUMMERY TABLE OF THE COAL HANDLING SYSTEM EQUIPMENTS DRAWING (SEE THE APPENDIX 1.2)
......................................................................................................................................................................
5
1.2.1
Drawing of the Overall Arrangement and Installation of the Equipments (See the Appendix
1.2.1)...........................................................................................................................................................5
1.2.2
2.1
2.1.1
2.1.2
2.1.3
Water Wiper.............................................................................................................................................73
2.1.4
Bulldozer..................................................................................................................................................75
2.2
2.2.1
Belt Conveyor..........................................................................................................................................79
2.2.2
Idler...........................................................................................................................................................83
2.2.3
Tension Device........................................................................................................................................84
2.2.4
Cleaning Device......................................................................................................................................86
2.2.5
Auxiliary Equipment................................................................................................................................86
2.2.6
2.2.7
2.2.8
Magnetic Separator................................................................................................................................99
2.2.9
2.2.10
2.2.11
2.2.12
2.2.13
2.2.14
2.2.15
2.3
2.3.1
2.3.2
2.3.3
2.3.4
The Main Coal Stack Mode for the Coal Handling System...........................................................127
2.3.5
2.3.6
2.4
2.4.1
Page 3 of 160
2.4.2
The Double-Pole Switch for Detecting Deviation State of Belt in Belt Conveyer.......................137
2.4.3
2.4.4
2.4.5
2.4.6
2.4.7
2.4.8
2.4.9
2.4.10
APPENDIX 142
1.2
1.2.1
1.2.2
Page 4 of 160
1.1.1
Overview
The coal handling system of this power plant is designed by the capacity of 2 units of
315MW. The function of the coal handling system is to unload coals from the coal
barge of coal unloading terminal and convey them to the coal yard. Then the coal will
be processed into those with the particle size needed by boiler combustion, and finally
delivered to the bin ahead of the boiler. The equipments of coal handling system
includes: unloader, belt conveyor, coal crusher and other equipments, which are
necessary to the procedure of coal unloading, conveying and crushing. The belt
conveying system between stackerreclaimer and main workshop is double. C-1C2c-3c-7are all with single belt, which are installed in the coal yard and emergency
coal bucket. The particle size of the incoming coal is below 300mm. That in the bin
ahead of boiler is below 30mm. All the equipments in the coal handling system can
meet the requirement of running continuously for 24 hours per day and 7 days per
week. They can also adapt the climate environment where the equipments are
located. The design service life is 30 years.
1.2
Summery Table of the Coal Handling System Equipments Drawing (See the
Appendix 1.2)
1.2.1
Drawing of the Overall Arrangement and Installation of the Equipments (See the
Appendix 1.2.1)
1.2.2
Page 5 of 160
2.1.1
2.1.1.1
Equipment overview
The equipment is of bridge type grad ship unloader with four leading wound rolls. The
representative unloading equipment is a bulk cargo crane with1.2-2 ton capacity. The
structure and location of this machine refers to the Fig. 1. During operation, the
grabber picks up material from the cabin of ship and then the grabber trolley moves
towards the shore and unload the material into the hopper that is located at front door
bridge interior. The crane moves along the jetty and takes material.
ZQX1250 ship unloader consists of systems like the metallic structure, the operation
mechanism with lifting parts, opening and closing parts, and trolley (three parts are on
a complete set, which is called four rolling spool mechanism), lifting mechanism,
crane operation mechanism, grabber and material collecting system, dust proof
system, mobile cab, maintenance facilities and safety tools like anticreeper,
anchoring, tie down device, safety hoop, and position limiting device, as well as
electrical system.
This equipment is of box girder structure. The front and rear crossbeams are
connected by pin shaft. During non-working state or when the ship approaches the
shore or leaves the shore, the front crossbeam lifts up for the ship to go. The front
crossbeam is of dual-crossbeam structure. There are horizontal girders located at two
sides to increase the side rigidity of the front crossbeam. The main building room and
electrical room are located back of the rear crossbeam lower platform. The gravity
center of the equipment is quite low and the stability is good. The lower outlet of the
hopper is a kind of vibration material feeder.
This mechanism uses the four-spool leading method. The gravity of buggy is quite
light with ease rope connection. The applied force of steel rope is small and it is easy
to replace. The guiding pulley is made of highly-reinforced nylon material, which can
extend service life of the steel wire rope. The AC frequency converting speed
adjustment system is used for the mechanisms like lifting, opening and closing, buggy
operation mechanism, amplitude variable mechanism and crane operation
mechanism. Material can be unloaded in semi-automatic mode or manual operation
by PLC programmable controller. The material collecting system and other machinery
equipment use the AC power supply and AC motor. The operation of each system and
mechanism can be done on the panel in the mobile cab or operated locally. The
mobile cab can move independently along the trail and can select the best view to
operate. The material hopper system can reliably supply for the sealing-tape machine
on the jetty. There are falling coal collecting board, coal hopper damper, dust collector
and water spraying system equipped the dust prevention pollution points like hopper.
Page 6 of 160
The wall board of main building and electrical house is made of high quality insulation
material. Appearance is good and suitable. Insulation and sealing performance is
good. This kind of setting improves the working environment of electrical equipment.
The vertical air conditioner in the electrical house helps to guarantee the reliable and
safe operation of electrical equipment. In addition, there are 5T crane for maintenance
use. The stairs, platforms and passage ways are all made of galvanized boards that
own the advantages like easy water discharge, hardly water accumulation and ice
forming, corrosion resistant, good rigidity and nice appearance.
There is a lifting suppose under the supporting leg in order to facilitate maintenance of
crane. Various kinds of limiting protection systems, interlock limiting device, and
communication systems are allocated for this machine to guarantee reliable and safe
work of ship unloader. Power supply of this equipment is 6300V, 50Hz. It is supplied
with cable rolling way. The length of rolling cable can support the ship unloader to
walk on the 180m trail. There is another controlling cable rolling disc located there to
communicate and contact with the personnel on ground and to serve a interlock
protection for the belt on jetty.
2.1.1.1.1
Unit
Value
mm
50
<8
t/m3
0.65~0.78
3550
t/h
1250
Coal
Material size (Max)
Moisture content
Bulk density
Angle of Repose
Unloading capacity
1250
t/h
Track distance
18
Base distance
16
32
13
Grabber capacity
19
25
14
Page 7 of 160
23
10.5
25
14
~170
KN
20/160
m/min
180
m/min
Single journey
-8min
20
m/min
20
m/min
Hopper capacity
110
m3
1250
t/h
-12~ 40
Max moisture
99
80
Power source
Control mode
PLC semi-auto
manual
~1250
kw
~830
400
2.1.1.1.2
2.1.1.1.2.1
Metal structure
or
The main metal structure of ship unloader is composed of the following parts: front
and rear crossbeam, front and rear pulling rod, small front gate, sloped supporting
rod, side girder, board, hopper and bracket. The most structures are constructed in
term of thin wall enclosed box form. They are made of Q345-B steel. The main
connecting joints are hinge joints or welded connection, which owns the advantages
like simple structure, good rigidity, easy assembly and light gravity weight.
The rotating hinge joints of front and rear crossbeam and front pulling rod uses the
graphite sliding bearing with self lubrication. The wear resistant performance of this
bearing is good and it is easy to maintain with easy rotation. There are upper and
lower supporting bases located directly under the track with adjusting gaskets to
ensure a precise position after the cross beam is lowered down. The track joints make
a good difference in twist resistance at hinge ear. Structure of the front and rear
Page 8 of 160
pulling rod is quite simple, which is made up with one or two transposition plates. The
platform board in computer room uses rear arm suspending method. The gravity
center of the whole equipment is then moved backwards. The balancing weight for
inclination prevention is decreased in this way and the stability of the equipment is
enhanced. Because it uses the leading system, the gravity weight of the buggy is light
with simple structure, low mobile load and easy maintenance. There are two couples
of horizontal guiding pulleys equipped at buggy bracket side (at two sides of the same
track). In this way, it can prevent the friction between the wheel rim and track side that
is caused by high speed operation of buggy, and also the vibration during buggy
operation can be overcome.
Fig. 1
2.1.1.1.2.2
Page 10 of 160
36NAT6x29Fi+Fc1770SZ. The high quality steel rope with hemo core filling is of
higher toughness, elasticity and certain lubricating grease. It has characteristics like
higher bearing capacity, extrusion resistant capacity, non rotation and fatigue resistant
ability. In order to effectively prevent rotation and properly use the steel rope. The
lifting/lowering and opening/closing should be rotated in pairs from both the left side
and right side. Use left rotating steel rope on the right spool and vice versa.
A special sliding block like clutch mechanism is equipped in the gearbox to facilitate
the assembly and disassembly of the steel wire rope. Single spool rotation is achieved
through lifting and lowering motor and buggy operation motor (or opening/closing
motor and buggy motor). In addition, steel wire rope going-through mechanism is set
to decrease the going through (rope changing) intensity.
2.1.1.1.2.3
Page 11 of 160
is used on the trolley. The driving mechanism is driven by one frequency variable
motor to motive the crane to move. The structure of this mechanism is easily
assembled, which is easy to disassembly and repair. There are interlocks between the
crane operation mechanism and anticreeper and the anchoring device.
Fig. 4
2.1.1.1.2.5
2.1.1.1.2.6
Page 12 of 160
by the water pump. Water becomes mist at the spraying nozzle. In this way, the dust
prevention aim is achieved.
The hopper upper part water spraying and unloading of grabber are in interlock. The
water spraying at coal re-conveying points is in interlock with the coal flow way. Water
spraying can be canceled manually.
2.1.1.1.2.7
2.1.1.1.2.8
Grabber
The European type advanced four-rope and four-pole grabber is equipped for this
equipment. The taking rate of the grabber is large with high production rate. The port
edge is made of highly reinforced corrosion resistant material with good welding
performance, intensity and rigidity. In addition, there are lifting ears for the bulldozer
located on the grabber. In order to equalize the force bearing of the four ropes, the
rope ends for opening and closing are fixed on the pulleys at two sides of the pulley
group. The length of two closing rope can be automatically equalized within certain
scope.
The easy broken problem of the steel rope at fixing connection can be avoided by
using this fixing method. The hinge joints of the pole inside the grabber use sliding
bearings to decrease daily work. There are rope protective shield located on the
grabber inner pulley group. A # type roller is located at head rope out-leading port to
prevent the steel wire rope falling off and to decrease the wear condition.
Working principle of the grabber:
The opening and closing of the grabber completely depends on the relative moving
Page 13 of 160
speed of the lifting up rope and the closing rope. When speed of these two is same,
certain opening/closing, lifting or lowering can be maintained. When the speed of
these two varies, hopper opening or closing are carried out at the same time during
grabber lifting up or lowering down process. The specific work circulation is shown in
the following:
(1) The empty hopper opens and decreases.
(2) At this point, the closing steel wire rope is loosened.
(3) The total weight of the grabber is borne by the lifting steel wire rope. The lifting
and opening/closing can be released with same speed. The grabber decreases
down with a nature open state and to the material pile on the cabin.
(4) Taking up of grabber.
(5) After the grabber is lowered down to the coal pipe and opened.
(6) Lift the steel wire rope and loosen it for a while to keep it in a slightly loose state.
With gravity weight, the jaw plate inserts in the pile. At this time, the lifting rope
does not work. Tighten the opening/closing rope, and the taking up of the grabber
can be completed.
(7) Full load lifting.
(8) Start lifting the rope when the grabber is about to be closed.
(9) As the rope lifts up, the grabber is lifted up in closing state. At initial stage when
the grabber leaves the pile, the total weight of the grabber is borne by the
opening/closing
rope. In this way, the grabber is lifted up and the load of
opening/closing rope is equalized.
(10) Hopper opening and material unloading, when the full load grabber moves to the
upper part of the hopper, release the opening/closing rope. At this point, the
weight of the grabber is borne by the lifting rope. With the gravity weight, it is
opened automatically. Unload the material from the hopper. Till now, one
circulation process of the grabber unloading is finished.
The working process is shown in the following:
Grabber state
Grabber
Grabber
opening
and opening
lowering down material
taking
Page 14 of 160
Take-up
Lower
down
Loosen
The grabber working condition and grabber unloading are in interlock in electrical
control. When the material storage amount of the grabber exceeds certain value, the
grabber cannot open to unload, cannot even when the grabber moves to the direct
top of the pile
2.1.1.1.2.9
Cable reel
The dynamic power, control signal and communication facility of the ship unloader are
lead in the equipment through the cable reel. The dynamic cable reel is mainly
responsible for the reclaiming and releasing of the 6300V AC HV cable. It is driven by
the hysteretic motor, which is similar to the constant tension driving function. This can
work reliably with safety guarantee. The controlling cable reel is mainly responsible for
the reclaiming and releasing of the LV communication cable. The driving device and
working condition are similar to the previous mentioned one. In order to guarantee the
normal work of the cable, there are cable leading bracket located under the reel.
Four anticreepers, four manual anchoring devices and four removable tie down
devices are equipped for this equipment. The anticreeper and anchoring device are
set to prevent strong wind attacking, to be specific, prevent the crane sliding off that
may cause severe damage. The ship unloader is stopped from moving along the track
by inserting the anchoring block into the base on the jetty.
The tie down equipment aims to prevent the unloader capsizing forwards and
backwards when strong wind occurs. There is one tie down located on four supporting
stems, which is firmly fixed on the anchoring base manually. Do not loosen the tie
down unless the equipment is activated. The anticreeeper, anchoring device and
crane are in interlock. If the rail clamping device is not loosened and anchoring block
is not lifted up to its position, the motor cannot be supplied with power. Therefore, the
crane cannot move. The anticreeper can withstand Level 10 gale. If the wind exceeds
Level 10, the anchoring and tie down work have to be done.
2.1.1.1.2.10.2
Safe hook
The safe hook is located at top of the ship unloader small frame in order to lock the
lifted boom. The model is of hook type. When the boom lifts up to set position, the
hook can be lifted up by hydraulic push pole. As the boom is lifted up to position, the
hydraulic push pole is powered off and stops working. The hook lowers down to lock
the boom. The hook sends out the signal when it reaches the position. The lifting
mechanism stops working.
Page 15 of 160
When the boom needs to be lowered down, first tighten the frequency variable steel
wire rope. The hydraulic push pole is powered on and lifts up the hook. As the hook is
pulled out, release the frequency variable steel wire rope. Lower down the boom to
the horizontal level. The activation signal of the hook is provided by the position
limiting switch.
2.1.1.1.2.10.3
Buffering device
There is a polyurethane buffer located at two ends of the crane travel mechanism
bogie frame. The buffering base is fixed at track on the jetty, at two ends of the trolley
frame, and one polyurethane buffer is equipped at two ends of the trolley track. In
addition, at two ends of the operator cab moving wheel, there is another buffer. The
main function of the buffer is to absorb running equipment, eliminating the impact and
decrease the impacting vibration.
2.1.1.1.2.10.4
There are activation switches controlling position limiting, speed reducing, locating,
and crash prevention that are in mechanical interlock with the electrical part of each
mechanism. In addition, safety protection devices like cam position limiting switch,
photoelectric encoder, overspeed protection are equipped for the four spool
mechanism and lifting mechanism. Purpose of using various protection systems is to
guarantee the reliable, safe and flexible operation of each mechanism on ship
unloader, and to reduce the labor force intensity of the driver at the same time.
2.1.1.1.2.10.5
Others
Apart from the above mentioned safety devices; there is wind velocity indicator
equipped on the ship unloader, which is installed at the top position of the unloader.
The signal that detects is transmitted to the display in operators cab. There is
acoustic-optic alarm located there also. If the velocity of the wind exceeds Level 7, it
is required to stop working. Do not work at all when the velocity exceeds Level 8 and
the anchoring has to be done. Tie down device has to be equipped in the typhoon
season.
Aviation light markers in read color are equipped at top of ship unloader and at boom
ends. Four speaker signal alarm slewing flash lights are equipped on bogies of the
crane travel mechanism. Acoustic-optic alarm is produced during crane operation to
alarm the operators on the jetty. Signals are sent to the display in the cab for better
understanding of material conveying condition. The ship unloader has to be located at
anchoring maintenance position when work is finished or when it is suspended.
Anchoring is then carried out and the tie down device has to be equipped if
necessary. The interconnection telephone and outside line for communication system
has to be complete.
2.1.1.1.2.11 Electrical system
2.1.1.1.2.11.1
Overview
Page 16 of 160
The electrical part of the ZQX1250 bridge type grab ship unloader includes the power
distribution, control, illumination, ventilation and communication for the following
systems: the lifting, opening/closing, trolley traveling, lifting, crane traveling, mobile
operator cab, and internal coal conveying system.
The power source for this equipment is HV 6.3KV, 3 phase, 50Hz, which is lead onto
the ship unloader from the jetty HV connection box through the dynamic cable winch
disc. The communication (including telephone and signal interlock) of this equipment
with the ground personnel is achieved by flat cable CFR(24 X1.5), which is also lead
onto the ship unloader from the jetty controlling connection box through the controlling
cable winch disc. The total capacity of this electric equipment of the unloader is
1250KW.
As one of the main equipment for power plant coal conveying system, the vital part of
electrical control part is the product from international famous ABB Corporation,
whose controlling performance is good and reliability is high.
There are interlock control panel, CMS display, power distribution box for dynamic
illumination, wind velocity indication, speaker, and air conditioners located in the
Operator Cab. Main and auxiliary transformers are located in the Transformer Room.
HV leading in panel, main transformer control panel, transmitting leading in panel,
transmitting panel, vibrating feeder and trolley/lifting switching panel, PLC panel, CMS
panel, power distribution box for auxiliary equipment, illumination box and air
conditioner for the Electrical Room are equipped in the Electrical Room.
One lifting operation box is located in the Lifting room. One computer room operation
box is located in the computers room. Other electrical equipment is located in vicinity
of the related mechanisms. Refer to the electrical related equipment locating sketch.
2.1.1.1.2.11.2
The power distribution system consists of the HV power distribution and LV power
distribution systems
1)
HV power distribution
LV power distribution
The LV power distribution includes the LV power distribution for both the main system
and auxiliary systems. The main system LV power distribution supplies dynamic
power for lifting panel, opening/closing panel, trolley/lifting panel and crane panel
through the driving leading-in panel.
The auxiliary power distribution panel supplies the dynamic and control power for the
Page 17 of 160
auxiliary systems like coal feeding system. Double-pole and double-throw switch is
used to provide the dynamic power and control power for the illumination box,
operator cab illumination box, lifting control box, computer room illumination box and
electrical panel.
When the HV power has to be cut off for maintenance, the double-pole and doublethrow switch can be pulled downwards. At this time, the illumination and maintenance
power is supplied from the ground. The make-and-break of the illumination power
main contactor are controlled at four locations, which are respectively the operator
cab, stair climbing position, electrical room illumination box and computer room
illumination box.
2.1.1.1.2.12 Replacing method and adjustment of steel wire rope
a
2) Place the grabber onto the jetty surface and maintain the rope tension.
Disengage the nylon gears for lifting the main gearbox and opening/closing the limiter;
3)
4) Get rid of the fixing device on the grabber on which the steel wire rope needs to
be replaced;
5) Select the relevant drum whose rope needs to be replaced. Individual rotation of
this drum is controlled in computer room. Lower sufficient section of the rope to the
jetty;
6)
Pull out the damaged section of the rope and cut it off;
7)
Fix the rope that is in good condition onto the fixing device of the grabber again.
8)
Page 18 of 160
9)
10) Restore the grabber to the state as step 2 and restore the nylon gear for gearbox
lifting and closing/opening limiter.
11) Finish now.
Whole piece rope replacement method includes the following:
a)
b) Place the grabber almost on the jetty and maintain the rope tension. Disengage
the nylon gears for lifting and opening/closing of the main gearbox limiter;
c)
d) Get rid of the fixing device on the grabber on which the steel wire rope needs to
be replaced;
e) Select the relevant drum whose steel wire rope needs to be replaced. Get off the
rope fixing device on the drum. Fix the thin steel wire rope of the going-through
mechanism onto the rope that needs to be replace and place the ropes onto the jetty
completely;
f)
Connect the new rope onto the thin rope of the going-through mechanism;
g) Operate the going-through mechanism in the computer room and lead the new
rope into the related drum;
h)
i)
Fix the other end of the rope onto the fixing device in the grabber;
j)
k)
l) Restore the grabber to the state mentioned in Step 2 and restore the nylon gear
for the main gearbox lifting and closing/opening limiter;
m)
Finish now.
2.1.1.1.3
Operation
2.1.1.1.3.1
Page 19 of 160
bucket is also forbidden. Workers should not repair or regulate the rotating parts when
the equipment is still operating. The power supply should be cut off during checking
and repairing. The driver should immediately haul all the control handles back and cut
off the main switch during operation when power failure or dramatic pressure drop of
the circuit occur.
2.1.1.1.3.2
2.1.1.1.3.3
2.1.1.1.3.4
Energization
Press the light indication button on the right ganged platform in the drivers cab. If the
indication light is bright, the operation of the drivers cab is effective. If the operation is
effective at other place formerly and wants to be transferred to the drivers cab, then
de-energize at the former place or press the button tripping first and then energize
by pressing switch on.(Tripping and switch on here refer to the dynamic power
supply tripping and switch on.
2.1.1.1.3.5
Initialization
Page 20 of 160
At the starting up point, hoisting, closing and breaker mechanism should be limited at
low speed. After initialization, they can be operated at normal speed. Switch the
transfer switch SA800 to hoist + close position, and then lift the grab bucket to the
proper position (the operation of hoisting rotation limit switch. Hoisting and closing
photoelectric encoder set the reference value1000automatically and operate the
grab bucket at low speed to a proper aerial position. Switch the transfer switch SA800
to the closing position and close the grab bucket. Press the indication button SB806
and the grab bucket closing initialization is finished. The indication light will not shine,
but its bright at the closing position of the grab bucket. Then open the grab bucket
and press the indication button SB807 at the maximum opening position the operator
thinks proper. The grab bucket opening initialization is finished. The indication light will
not shine, but the light is bright here. Finally, drive the breaker to the side ground
parking place and the photoelectric encoder of the breaker sets the reference
value1000automatically. The whole process of Initialization is finished.
2.1.1.1.3.6
Manual unloading
Switch the transfer switch SA800 to the grab bucket position and manual unloading
can be operated after switching SA806 to manual. The operator controls the closing,
hoisting speed and anti-rolling of the grab bucket and operating speed of the breaker.
Due to using digital DC speed adjusting device and PLC control, the following
controlling functions are still available to reduce the operators work load in the
manual operation.
the speed adjustment devices has the function which suits the potential load, so when
the grabber is lifting or dropping, an electric torque should be built up to overcome the
load torque. Then loosen the band-type brake to make sure that the grabber will not
drop suddenly. Only when the working speed has reduced to about 10% of the rated
speed, can the brake perform automatic brake to decrease abrasion and start/brake
smoothly. However, in case of emergency shutdown or the action of terminal limit
switch or faults of power ect., the brake immediately closes for the seek of safety.
2.1.1.1.3.6.4 Control of Material Grabber close and loaded draught
When the grabber is closed in the air, set the master switch towards the close
direction. At this time, the close motor works while the lifting motor does not and the
band-type brake does not loosen. But when the grabber is grabbing materials the
master switch SA802 should be fully switched to the close position and to the lifting
position. These performances should be finished within two seconds
Then, the close motor automatically accelerates to a steady speed, and decelerates
speed when it is about to close realizing soft close. At the same time, the lifting motor
loosens brake and enters current control adding the wire rope a lifting force to make
sure the grabber will drop during closing process and the lifting wire rope will not
loosen. Grabber being in the close position makes the switching motor transfer into
personnel limit load control (the current of the motor is about 50% of the rated
current). The time is about 0.5 second. Thus, the loads of the lifting and switching
rope have been balanced before the grabber rises. Then, lifting and switching motor
rises the grabber in a load-balanced way.
2.1.1.1.3.7
Page 22 of 160
2.
3.
4.
5.
6.
After entering semi-auto, the master switch on the right should be at the zero position.
The grabber automatically rises to the unloading height and at the same time moves
towards the bunker on the land (safe curve track). If the transfer switch SA807 is at
the static unloading position, the grabber automatically begins to stabilize itself and
rest upon the center of the hopper, and then opens the grabber to unload
To achieve good anti-rolling effect, before the grabber enters the semi-auto
circulation, i.e. below the safe height, the breaker master switch on the left interlock
table can be operated to do the manual anti-rolling. When the transfer switch SA807
is in the dynamic unloading state, the anti-rolling process of the grabber can be
omitted before the hopper, instead, the grabber can use the shaking bucket to shake
off the materials. The breaker does not suspend upon the hopper. When the grabber
is at the greatest position angle on the landside, the breaker moves towards the
opposite position. When the grabber automatically moves towards seaside and drop
to the former grabbing position, the manual control is transferred into. And also, by
operating breaker master switch in advance to transfer into manual control, the
loading point is chosen to grab material. During semiautomatic circulation, as long as
the breaker master switch is out of zero position, e.i. the semi-auto operation is
stopped and the manual control is in charge.
2.1.1.1.3.7.4 Manual Operation in Semiautomatic Operation
2.1.1.1.3.8.1 Energization
Page 23 of 160
Press the button Switch in, with an indicating light on. The motor room operation is
valid.
2.1.1.1.3.8.1.1
Roller Selection
Threading or replacing steel wire rope should choose roller working mode. The two
rollers near lifting motor are coiling block number 1 and number 2.The two near motor
for start and stop and motor for driving unit are number 3 and number 4. The
cooperated operation between lifting motor and motor for start and stop or between
motor for driving unit and motor for start and stop can achieve roller isolated
operation.
Pressing lighted button roller selection makes roller working mode available. Each
inverter controls roller number 1 and number 4 respectively. The direction of inverter
rotation is identical to the direction of roller rotation. Attention: To make roller number
1 or number 2 in isolated operation separate the crane clutch on start and stop side
firstly. To make roller number 3 or number 4 in isolated operation separate the
carriage clutch on lifting side firstly.
2.1.1.1.3.8.1.2
Actuator Selection
Pressing lighted button actuator selection makes actuator operation mode available.
Each inverter controls low speed of lifting motor, motor for start and stop and motor for
driving unit respectively. Inverter SA204 and button SB214 control operation and
shutdown of lifting motor. Light HL201 indicates the startup of safety brake.
2.1.1.1.3.8.1.3
Overshoot Bypass
When lifting motor, motor for start and stop, motor for driving unit and amplitudechange motor over normal stop limit and make overshoot bypass emergency stop
because of mechanical breakdown or some else reasons, key type bypass inverter
SA212 should be operated in operation cabinet of motor room to reenergize
overshoot limit bypass. In addition, motors cant work normally until overshoot limit
bypass is reset by means of making the relevant motors operate with reverse low
speed in operation cabinet of motor room and the bypass inverter is reset too.
2.1.1.1.3.8.1.4
To assure the safety, lifting motor is equipped with safety brake beside normal working
brake. After shutdown of amplitude motor at horizontal, key type inverter SA201 is
operated to start safety brake separately for maintenance and repair easily.
2.1.1.1.3.9
2.1.1.1.3.9.1 Energizing
After Press the Stop button in operation cabinet of lifting room, lifting room is
Page 24 of 160
available.
2.1.1.1.3.9.2 Manual Operation
Turning switch SA205 to the rising direction, with lighting of lights HL206 and HL208,
lifting motor start rising. When it comes to the middle (about 70 ), the pin of lifting
motor rises manually and the light HL205 starts. Until lifting motor continues rising to
the normal upper stop point, it shuts down. Release the lifting pin and descend lifting
motor manual mode slightly. Till lifting slack-rope switch activates, lifting motor shuts
down automatically. The pinning operation is finished.
Turning switch SA205 to the rising direction, lifting motor slightly moves up to the
normal upper stop point and stops firstly. After that, turning primary control switch
SA205 to the descending direction, lifting pin descends manually. Release lifting pins
when lifting motor over the middle position. After lifting motor continues descending to
horizontal and lifting slack-rope switch activates, lifting motor shuts down
automatically. The releasing operation is finished.
2.1.1.1.3.10 Operation of Other Important Mechanisms.
2.1.1.1.3.10.1
The work of coal system means coal drops from hopper to vibrating feeder, and then
through filling pipe to terminal belt conveyor. The startup of vibrating feeder can be
operated with button Feeder Startup (Button SB810) and Feeder Shutdown (Button
SB811) at left interlock consoles in operator room. It also can be achieved with the
Feeder Shutdown (Button SB901) and Feeder Shutdown (Button SB902) with
hopper local operation cabinet. The frequency of vibrating feeder is coal flow rate and
it is controlled by the inverter SA812 at left interlock consoles in operator room. When
it works normally, startup of vibrating feeder is interlocked with terminal belt conveyor
signal and coal mount in hopper. In feeding operation, feeder starts up when coal
mount is more than 35%, and feeder shuts down when coal mount is less than 20%.
Lifting and shutdown of hopper pickup board is can be operated with the button up
hopper pickup board and button down pickup-board of hopper at left interlock
consoles in operator room. It also can be achieved with the up hopper pickup board
and down pickup-board hopper with hopper local operation cabinet.
When coal is accumulated at hopper walls, Vibrator Startup ( button SB816button
SB817button SB818) at left interlock consoles in operator room as well as Vibrator
Startup ( button SB905) on hopper local operation cabinet is used to make vibrator
work vibrating the coal.
2.1.1.1.3.10.2
Water system
Page 25 of 160
water injection control of spray valve on hopper is controlled by feeding on the upper
part of hopper. The water injection on inlet and the vibration feeder are in
synchronous operation. When the water spray valve and the water injection valve are
closed, the water return valve opens automatically.
The control of water system includes two parts, one is for water spray motor and the
other one is for spray magnet valves on both hopper and feeder. The water spray
motor can be started up or shutdown through pushing the button SB814 and SB815
which is on left linkage control console in operation cab or pushing the button SB903
and SB9044 on hopper operation cabinet at site. Spray magnet valve on hopper is
controlled by both the signal from button SA819 on left linkage control console in
operator cab and the signal of starting unloading on upper part of hopper from grab
bucket. For spray magnet valve on feeder, it is controlled by both the signal from
button SA818 on left linkage control console in operator cab and the signal of feeder
operating.
2.1.1.1.3.10.3
Operator cab
The operator cab is driven by two alternate squirrel-cage motors. The control panel in
operator cab supplies the power source and control power to these two motors.
Choosing soft start the director when start up to start up the motor smoothly. The
operation of operator cab is controlled by the button SA810 on left linkage control
console. Only when both the switch of operator cabs door and the amplitude
transversal switch are closed strictly, the operator cab can operate normally.
2.1.1.1.3.10.4
Crane mechanism
SA702 to crane bypass position on local panel, and at same time, let the crane run
inversely. After the cable drum empty limiter is reset, the crane can operate normally
again.
The crane power cable reel and control cable reel use TIC hysteretic cable reel.
Compared with torque motor type cable reel, this one is smaller, has more rich
functions, easier to install and maintain and near to constant tension. Besides, its
output moment can be adjust according to the working condition and this cable reel is
with fine auto brake character, no need braker, the cable reel operates smoothly and
no damage after long-term operation. Please pay seriously attention that the motor
using the cable reel can only be turned following the indicating direction signally. For
the detail, see the instruction from the manufacture.
When the vent speed is over setting value, never operate the crane.
Drive the crane to anchor hole to be anchored after the operation be finished.
2.1.1.1.3.11 Safety devices
The safety devices on ship unloader should be durable and its protection level should
not be less than IP65
The following safety devices should be provided on ship unloader (Not limited to this):
Limiter for lifting height and drop height;
Grabber position limiter for coal unloading;
Grabber lifting overload protection device;
Secondary limiter on the stroke end of
Secondary limiter on the stroke end of
Anti-collision protection device for ship unloader;
Stretch angle limitation and overspeed fall down protection
Cable break protection device;
Rotary type identify sound and light warning signal for ship unloader moving
Install light control red aviation obstruction lights on the top of ship unloader
Vent speed alarming signal
Wire cable anti-relaxation protection device
Allocate complete safety devices in every stage for electrical protection devices
according to the system settings needing.
2.1.1.1.3.12 Emergency shutdown
When each mechanism need to shutdown, turn the corresponding main order switch
Page 27 of 160
back to zero. Take electric braking to decrease the speed close to zero and then do
mechanism brake , while if electric apparatuses fault or in other emergency condition,
push the emergency button on right linkage operation console and do mechanism
brake immediately. Take same action if emergency shutdown is needed in other parts.
To restart operation, the emergency shutdown button should be reset.
2.1.1.1.3.13 Others
Push close button when shut down the machine. The monitor in operator cab not only
supplies the operation information to the operator, but also offers maintenance and
fault information. If fault happens, after it is treated, the operator should push SB803
fault reset button and then push the close button to supply the power again.
2.1.2
2.1.2.1
Equipment description
DQ1250/1250.40 Boom bucket wheel stacker reclaimer (BWSR) is a kind of large,
continuous and efficient bulk cargo stacking & Reclaiming equipment,
developed,designed and manufactured by Changchun Generating Equipment Co.,
Ltd, China for PLTU 1 Jatim - Pacitan (2315MW) Coal Fired Steam Power Plant
project,Indonesia.This machine has the function of unidirectional stacking and
shuttling reclaiming. There are interlocking protection among long travel drive, Slew,
luff, bucket wheel drive and boom conveyor etc transmission part (detailed information
refer to the instruction in each Chapter/Section). Operator must read Instruction
carefully and master daily operation and maintenance before starting to work; if
operation is not proper, not only can reduce the service life of equipment, but also can
cause the accident.
Technical specification
2.1.2.2.1
Type of equipment
D Q 1250 / 1250 .40 40slewing radius;
Page 28 of 160
2.1.2.2.3
Long travel
Traveling speed: Operating speed 5m/min
Commissioning speed 15m/min
Wheel base and wheel gauge: 8m x 8m
Motor power: 6x7.5kW
Reducer type: FH127GDV132M4BM/HF
Transmission ratio of reducer: i=170.83
Rail clamps type: TZT-J250 (hydraulic spring type)
Limit switch of anchor device: WLCA12
Limited switch for anti storm mooring arrangement
XS4-P30MA230
Slewing unit
Slewing radius: 40m
Slewing speed: 0.020.12r/min
Slewing angle: 110
Motor type: Y180L-8
Motor power: 2x11kW
Page 29 of 160
Bucket-wheel mechanism
Reclaiming capacity: 1250t/h
Outer diameter of bucket-wheel: 6300mm
Rotational speed of bucket-wheel 6.5r/min
Bucket volume : 0.51m3
Bucket quantity : 9 nos.
Driving device parameter
Motor power: 90kW
Reducer type: ZHP5.33K
Output torque of the reducer 94535Nm
Type of fluid coupling YOXA500
Luff unit
Lifting angle luff Up 9.54, luff down 10.61
Lifting speed : 4 6m/min ( at center of bucket wheel)
Type of hydraulic cylinder 320MP5MMBYLS14M1550M1144
Type of oil pump motor Y180M4A-B35
Rated working pressure: 16MPa
Boom conveyor
Length of boom conveyor 41.9m
Rated conveying capacity 1500t/h
Belt width x belt speed: 1400mm x3.15m/s
Idler diameter: 133mm
Trough angle of idler: 35
Take up type Heavy bob take up
Driving device parameter
Page 30 of 160
Page 31 of 160
Reeler device
Cable specification : 380VYEFBG-24x2.5mm2+2x4Gmm 2
Cable cross-section dimensions: 99mmx19mm
Transfer chute
Electrical thrustor DT30050-20II
Note: Other limit switches refer to boom rack lifting limited position, slewing angle,
slewing luff and terminal limited position of Long travel and tripper car luff end limited
switch etc.
L
Detection device
Detection device for traveling distance: TRD-GK30-BZ type rotary encoder
Detection device for slewing angle: E6C3-AG5C type rotary encoder
Detection device for lifting angle: E6C3-AG5C type rotary encoder
Detection device for material level 20-39 type inclining switch
2.1.2.4
Equipment Structure
2.1.2.4.1
pivot and the end part of the pylon will be hinged joint; and lower pivot support should
be welded with top surface of slew deck. The completed structure can waggle around
the support pivot point, Hydraulic cylinder which lie between slew deck and pylon acts
can achieve integral luff of super structure. Slew support bearing is mounted between
upper and lower pedestal ring, upper pedestal ring supports the slew deck, and lower
pedestal ring is fixed on the portal. Slew driving device is fixed on the slew deck, and
through output axis pinion of slewing reducer, the spur pinion is meshed with big gear
ring which is fixed under the bearing of lower pedestal ring, which shall transmit upper
structure to rotate around slew center. Pivot of traveling mechanism is welded with
support leg of portal. This part will be assembled on jobsite, and then welded together.
Pylon
Pull rod
Cab
Pitch
cylinder
2.1.2.4.2
2.1.2.4.2.1
oil
Slewing
mechanism
Bucket-wheel mechanism mainly consists of bucket wheel body, bucket wheel axle,
bearing assembly, ring chute, sliding chute, guide chute device and bucket wheel
drive device etc.
Bucket wheel body is cell less type; it has the merits of rapidly discharge.
Bucket wheel mechanism has nine buckets total, they are evenly distributed at the
external of the wheel body circle, and fixed by pins and bolts, ferromagnetic wearing
resistance disassembled bucket teeth will be installed on the entrance of the bucket ,
Bucket blade position has the protective layer which is made of wearing resistance
electrode by building up welding. In order to be convenient for discharging the
material, bucket wheel shaft relevant horizontal should set up 7 tilt angle which will
be installed vertical bucket wheel body. Ring chute shall be installed inside bucket
wheel body circle, and 5 to 10mm gaps should be remained between ring chute and
bucket wheel body, so as to be sure the bucket can lift the coal reclaimed from the
coal yard to discharging chute which is on the upper part of the bucket wheel body,
through sliding chute to the boom conveyor, then through guide chute delivering along
Page 33 of 160
bucket wheel boom conveyor reclaiming direction. The working surface of ring chute
and sliding chute are all installed wearing resistance liner easy replaced.
Page 34 of 160
2.1.2.4.2.3
Driving device
Rotary plate
Small driving gear
Gear cover
Pedestal
Page 35 of 160
grease meanwhile slewing the bearing to make grease evenly distribute until grease
is squeezed out from seal lip. Fill lubricating grease for interval of 40hours, filling
interval may be shortened under severe environmental conditions and dusty
condition. New grease shall be refilled after long time stop operation fore and after.
2.1.2.4.2.4
11
8
10
7
9
2.1.2.4.2.5
2.1.2.4.2.6
Luff unit
2.1.2.4.2.6.1 Structure
Luff unit is hydraulic lifting type. it adopts dual action hydraulic cylinders, two ends of
Page 36 of 160
the cylinders will be connected to slew deck and the pylon separately with pivot ,
through the telescopic cylinder realize the super steel structure lifting. Lifting hydraulic
mechanism of main machine mainly consists of lifting hydraulic station, hydraulic
blocks, hydraulic cylinders, pipeline, pipe joint, hoses, and seal rings. Lifting hydraulic
station consists of motor, hydraulic pump, electromagnetic control valves, oil filters,
overflow valves, hydraulic-control check valves, gate valves, pipelines, pipe joints,
seal rings, pressure gauges, liquid level/temperature gauges and oil drain valves. Luff
action is carried out by expansion of hydraulic cylinder. Hydraulic system shall assure
dual hydraulic cylinders work at the same time to realize a safe, stable, reliable work
of lifting system. Start, stop, unloading (overpressure protection) of pump shall be
carried out in hydraulic station. Flow may be adjustable within allowable scope. When
ambient temperature is too low, oil shall be heated; if conditions like over-temperature,
overpressure, and choking of oil filter occur, warning signal shall send off to realize
overload protection. Lifting hydraulic cylinder may be stopped and maintained at any
positions.
Hydraulic system consists of hydraulic power station and pipeline etc. Considering
about the working environment is outdoor and much dust, hydraulic pump station
adopts cabinet-type structure. Manometer and thermometer shall be installed for
indicating the pressure and the temperature. At the same time, protection against
overpressure device should be installed to ensure lifting unit operating safely and
reliably. This system can carry out the pump starting, stopping, unloading
(overpressure protection), Flow may be adjustable within allowable scope. When
ambient temperature is too low, oil shall be heated; if conditions like over-temperature,
overpressure, and choking of oil filter occur, warning signal shall send off to realize
overload protection. So as to make lifting hydraulic cylinder to be stopped and
maintained at any positions.
2.1.2.4.2.6.2 Cautions during operation
a.
Filter shall be installed at oil inlet and outlet of pump, which shall prevent polluted
particles from damaging parts. Once filter of return oil is choked, warning signal
shall automatically send off; operation shall be stopped, operation may start only
after filter is cleaned or replaced.
b.
Frequently observe pressure, speed and temperature to see whether they are
normal (normal working temperature is 15~70), if abnormal conditions occur,
quickly find out and repair failure.
c.
Frequently observe whether oil is leak at joint surface of elements, pipeline and
oil cylinder, observe whether abnormal noise occurs; if any one of the above
conditions occur, quickly find out and repair failure.
d.
During the process of operation, frequently check whether pipeline and elements
are properly sealed, if leakage occurs, sealing parts shall be replaced in time.
c.
If the hydraulic station is not used for long time, periodic start of pump station
should be needed (once for 1~2months) and unloading lifting action should be
done several times to avoid any corrosion on parts of system.
d.
Failure symptoms
Possible causes
Possible causes
Pressure not
up in system
Page 38 of 160
(1)Re-adjust pressure;
(2)Remove such failure
according to above
mentioned method;
(3)Increase angle of sloping
cam plate;
(4) Same as (1)
2.1.2.4.2.7
Limited switches
Limited switches device consists of boom boom rack anti-collision device, slewing
angle limit, Slewing luff cross-system limit, long travel drive end limited switches and
boom luff limited switches.
2.1.2.4.2.8
a.
Boom rack anti-collision device: FKLT2-I switch shall be installed at two sides of
middle/front part of head boom. When bucket wheel boom travels, if steel wire
rope touches coal pile or other obstacle, switch shall be actuated to send off
signal, meantime power supply of slewing motor and travel motors will be cut off
in order to prevent head boom rack from colliding with obstacles.
b.
Slewing angle and slewing luff limit: WLCA12 travel switches shall be adopted;
slewing angle limited switch is installed between slew deck and pylon to control
slewing scope of bucket wheel boom under the equipment is in working status of
stacking/reclaiming or under condition of cross-system; slewing luff limited switch
is installed between pylon and slew deck to control lifting scope under condition
of cross-system slewing.
Long travel drive end limit: WLCA12 switch is adopted, and shall be installed on
non driven wheel bogie assembly of long travel mechanism to control travel
scope.
Luff limit of boom rack: WLCA12 traveling switch will be adopted and installed
between slew deck and portal to control luff limit scope of equipment bucket
wheel boom .
Limited switch for tripper car WLCA12 switch should be adopted for tripper car
Limited switch, It will be installed at tripper car luff unit to control the level of
stacking and reclaiming of the tripper car.
Detection device
Detection device consists of traveling distance detection device, slewing angle
detection device, luff angle detection device and material level detection device.
Traveling distance detection device is installed on rear part buffer of traveling
Page 39 of 160
mechanism to detect travel distance. Meanwhile, it will detect travel distance under
working condition of automatic stacking/reclaiming and will detect limit for travel end.
Slewing angle detection device is installed on drive gear of slewing unit to detect
slewing angle of bucket wheel boom rack; Meanwhile, it will realize to control the
working condition of automatic stacking/reclaiming and control the function of the end
limited switch; Lifting angle detection device is installed on support pivot to detect
lifting angle of bucket wheel boom rack. it will realize to control the working condition
of automatic stacking/reclaiming and control the function of the end limited switch;
Material level detection device is installed at front part of bucket wheel boom rack to
detect material position below bucket wheel. Meanwhile, it will control the working
conditions of automatic stacking
2.1.2.4.2.9
steel
Page 40 of 160
Tripper car
luffing mechanism
Tripper car
1. Metal structure of main tail cart 2. Belt conveyor of main tail cart 3. Single-wheel driven loop
wheel machine 4. Variable amplitude mechanism of auxiliary tail cart 5. Auxiliary tail truck
2.1.2.5
2.1.2.5.1
2.1.2.5.2
2.1.2.5.2.1
Page 41 of 160
(Refer to process drawing), height of boom rack is set as the same of preset height of
stacking, boom rack stacks in out and back rotary manner until set times are met, and
then travel mechanism makes a minor set movement, in sequent order 1-2-3,
operation will continue. Rotary stacking process in this occasion which transmission
quantity of raw material is not continuous or relatively les, length of stacked pile may
be preset according to transmission quantity to form a relatively regular pile, therefore
a high
Page 42 of 160
Intermittent rotary + intermittent traveling spot stacking shall refer to process drawing
of intermittent rotary + intermittent traveling spot stacking. Stacking operation starts
from the first pile layer by layer in order to reduce dust. Height detector will send off
command instruction to change over next layer until the last layer is finished. Height of
boom rack is kept unchanged; boom rack will rotate according to preset direction and
angle to the second pile, stacking operation continues; after boom rack arrives at
rotation scope, travel mechanism shall move in a preset minor distance until stacking
reaches a preset pile length, operation may stop.
Page 43 of 160
2.1.2.5.2.2
(Refer to rotary layer reclaiming process drawing), according to its pile height, it is
divided into layer subsection reclaiming and rotary layer non-subsection reclaiming.
The first operating mode Layer subsection automatic reclaiming: first of all, driver
operates the stacker reclaimer to travel, rotary and luff mechanism to move bucket
wheel to starting point of top layer of pile (single positioning rotation), reclaiming starts
its operation under control of rotation, when it reaches to a preset rotation scope,
travel mechanism will make a minor preset distance (feeding quantity), according to
preset length of material supply section Lm (or preset rotary times), after reclaiming of
the first layer is finished, operation changes over to next layer; rotary angle of each
layer is determined by angle of repose and number of layers; luff height is determined
by preset number of layers, traveling distance is determined by feeding quantity.
When reclaiming of the bottom layer is finished, reclaiming will change over the next
section. Bucket wheel will be placed at start point of top layer of the second section,
reclaiming operation continues; Length of material supply section is preset according
to principle that boom rack does not touch material pile.
The second operating mode Rotary layer non-subsection reclaiming: its working
efficiency is the highest to avoid overload danger of bucket wheel and boom rack
caused by collapse of material pile, which is suitable in stacking low and short
material pile. Boom rack cannot touch material pile. In order to realize purpose
Rotary layer quantitative reclaiming, under semi-automatic control, rotary speed of
boom rack should change according to 1/COS, and make further feedback
according to current of bucket wheel drive motor. Normally, rotary angle is 10~70,
rotary speed adopts frequency conversion speed within 10~60 according to
1/COS, if it is within 60~70, should be 60.
Page 44 of 160
b)
Refer to spot slope reclaiming (end face reclaiming) process drawing, it is a kind of
working process which is first stacking, first reclaiming, intermittent operation, and its
working efficiency is the lowest. During the process of operation, material pile easily
collapses and results in overload of bucket wheel. When driver adopts the above
several methods of reclaiming, driver should reclaim coal from top layer of material
pile, and should observe condition of material pile at all time to avoid that head or
bottom of boom rack touches or collides material pile during slewing operation of
bucket wheel. In order to avoid damaging the equipment, continuous traveling
reclaiming mode of Long travel is not allowed.
2.1.2.6.1
Single-action operation
Each mechanism of bucket wheel stacker/reclaimer shall make separate
start/stop operation in operator cabin.
b.
Interlock operation
When bucket wheel stacker/reclaimer makes interlock operation, the following
operation procedures shall be observed, otherwise it will not operate.
2.1.2.6.3
2.1.2.6.3.1
2.1.2.6.3.2
Check the HV switch panel is energized and observe the indicating gauge and
ON/OFF indicator;
Power supply
Page 46 of 160
When the 6kV 50Hz HV computer is activated, the voltage of power is transformed
into 380V 50Hz three-phase power. It can be used as power supply for complete unit
control, illumination, maintenance and central lubrication through the isolation switch
V1 QS1 in the 11 LV electrical panel.
(1) Control power source: serves as the complete unit control power source after it
goes through the isolation switch V1 QS1 and then the control and isolation
transformer V1 T1 (380V/220V).
(2) Illumination power: serves as the complete unit illumination and socket power
after it goes through the isolation switch V1 QS1 and then the circuit breaker V3
q1.
(3) Maintenance power: serves as the complete unit maintenance power after it goes
through the isolation switch V1 QS1 and then the circuit breaker V3 q1.
(4) Central lubrication power: serves as the complete unit central lubrication power
after it goes through the isolation switch V1 QS1 and then the circuit breaker V5
Q1.
2.1.2.6.3.3
HV room
(1) Control transformer HV1 T1.
(2) Dynamic transformer HV2 T1.
(3) HV in-coming circuit of the 10A HV electrical panel.
(4) HV feedback circuit of the 10B HV electrical panel.
b.
LV room
(1) 11 LV electrical panel: LV power circuit.
(2) 12 LV electrical panel: PLC main station and auxiliary control circuit.
(3) 13 LV electrical panel: control circuit for the crane travel mechanism, cable
drum, and rail clamping device.
(4) 14 LV electrical panel: control circuit for the slewing, lifting, water spraying,
intermediate section hopper damper, and bucket wheel guide through.
(5) 14 LV electrical panel: control circuit for the bucket wheel, boom belt,
auxiliary trailer alternation, and trailer belt.
c.
Operator cab
Page 47 of 160
1. 21 left side operation platform: there are gauges and operation switches located.
(1) Gauge: indicator on the 6kV HV computer power supply;
(2) Indicator: indications of HV power CB closing and opening;
(3) Buttons with lights: indications of control power source closing and opening;
(4) Buttons with lights: indications of control power source closing and opening;
(5) Buttons: loosening and tightening of the trail clamping device;
(6) Buttons: closing and opening of control power source CB;
(7) Main order switch: activation and deactivation of the wiper;
(8) Main order controller: moving, stopping and retracting of the crane.
2. 22 right operation platform: operation buttons and switches are located.
(1) Mushroom button: emergency shutdown button (in case of any accident);
(2) Transferring switch: control of stack reclaimer (reclaiming, shutdown and
taking);
(3) Transferring switch: selection of operation mode (single operation, interlock,
and semiautomatic);
(4) Transferring switch: transferring control of auxiliary trailer (changing of coal
stacking, stopping and taking transferring);
(5) Button: startup the crane and give out alarm. Signals are restored;
(6) Button: operation of lifting oil pump and control of deactivation;
(7) Main order switch: selection of high speed and low speed of the crane;
(8) Main order switch: system interlock (interlock and disconnection);
(9) Main controller: slewing (left, stop and right);
(10) Main controller: lifting (up, stop and down);
(11) Buzzer: failure alarm.
3. 23 LV control panel: main and auxiliary control circuit of the PLC program control.
4. Programmable end PT: used for equipment monitoring
(1) State display: running states of each mechanism of the stacker reclaimer are
displayed;
(2) Position limiting display: activation of the protection position limiter of each
mechanism of the stacker reclaimer is displayed;
(3) Failure list: present failure alarm lists are displayed;
Page 48 of 160
(4) Parameter setting: setting of lifting and slewing times during operation of
semiautomatic stack reclaimer. Manual interruption and button disconnection
are carried out during semi automatic operation process;
(5) Current indication: display of motor current of boom conveyor belt, trailer belt,
stack reclaimer, crane, and slewing device;
(6) Digital display: travel distance, slewing angle and lifting angle of the crane;
(7) Single activation control: single activation of boom conveyor belt, stack
reclaimer, intermediate section hopper damper, reclaimer guide through, trailer
belt and oil heater.
2.1.2.6.3.4
Press the POWER SUPPLY CB CLOSING button on the left operation platform, and
the relevant indicator will be on, indicating the CB closing is finished.
2.1.2.6.3.4.5 Releasing of trail clamping device
Press the TRAIL CLAMPER RELEASING button on the left operation platform and it
can be displayed on the state indicating display at the programmable end. The
relevant TRAIL CLAMPER RELEASED indicator is on, indicating it is released
already.
2.1.2.6.3.4.6 Selection of control mode
Controlling modes the stack reclaimer can be divided into single act control, interlock
control, and semi-automatic control. These three modes can be transferred freely.
One mode has to be decided before operation of the equipment
Note: these three modes cannot be transferred during operation
By operating the transferring switch of CONTROL MODE SELECTION on the right
operation platform, one mode can be selected. On the display of STATE INDICATION
at the programmable end, the relevant SINGLE ACT, INTERLOCK and
SEMIAUTOMATIC indicating lights will be on, indicating the control mode is already
selected
After preparation work of the above mentioned sequence, the normal operation of
stack reclaimer can be done
2.1.2.6.3.5
on
the
(3) The main order controller that controls the crane moving direction either
forwards or backwards can only be transferred (to the opposite direction)
when the crane maintains a outage state for a while.
(4) The crane ceases moving as it reaches the forward or backward limiting
positions. The indicators of CRANE MOVING FORWARD LIMITING
POSITION, CRANE MOVING FORWARD LIMIT, CRANE MOVING
BACKWARDS LIMITING POSITION and CRANE MOVING BACKWARD
LIMIT will be on on the programmable end LIMITING POSITION INDICATION
display.
(5) During crane moving process, the motor current can be observed at the
programmable end.
b.
c.
Page 51 of 160
(6) Current of the slewing motor can be observed at the programmable end
during the slewing process.
e.
f.
h.
Page 54 of 160
(2) Enter the programmable end SINGLE ACTIVATION CONTROL display, and
click the buttons controlling the intermediate hopper damper like STACK,
RECLAIM and STOP. By operating like this, the relevant work can be done.
After the damper moves to its position, on the display, the relevant
intermediate hopper damper STACKING POSITION and intermediate hopper
damper RECLAIMING POSITION indicators will be on.
i.
j.
Page 55 of 160
k.
b.
(1) Turn the STACKING CONTROL change-over switch on the right operation
panel to STACKING position, and the corresponding mechanisms will be
started in the following order:
the bucket-wheel guide chute lifts up (in stacking position)
the middle coal falling damper lifts up (in stacking position)
after delay for a certain period of time, the cantilever belt operates in stacking
direction;
after delay for a certain period of time, the trailer belt operates;
after delay for a certain period of time, the system belt operates in stacking
direction.
(2) After finishing the operation mentioned above, the operating lights of
corresponding mechanisms will turn on on the STATE INDICATION menu of
the programmable menu. At the same time, BUCKET-WHEEL STACKERRECLAIMER STACKING light turns on.
(3) The stacking work of bucket-wheel stacker-reclaimer can be fulfilled by
controlling the corresponding operation of other mechanisms following the
operation of single control mode
2.1.2.6.3.5.3 Semi-automatic control
The semi-automatic control operation is divided into two parts: semi-automatic
stacking and semi-automatic reclaiming, which allows the manual interference in
semi-automatic operation conditions
a.
Notice: the auxiliary trailer must be switched to reclaiming position before put the
semi-automatic control into operation.
(1) Before putting the semi-automatic reclaiming into operation, the working
surface can be cleared in interlock mode and then switched over to semiautomatic mode if the shape of coal pile in coal yard is irregular.
(2) In interlock control mode, move the crane to the preset coal reclaiming
position and turn the CONTROL MODE SELECTION change-over switch to
SEMI-AUTOMATIC position.
(3) Then turn the STACKING-RECLAIMING CONTROL change-over switch on
the right operation panel to RECLAIMING position, and the bucket-wheel
stacker-reclaimer will start up the guide chute, middle hopper damper,
cantilever belt and bucket wheel in the program sequence.
(4) When the bucket-wheel stacker-reclaimer is started up, the cantilever is in the
position that is the first reversal point. The original slewing direction of the
Page 58 of 160
Page 59 of 160
Page 60 of 160
b.
Notice: the auxiliary trailer must be switched to stacking position before putting
the semi-automatic control of stacking into operation.
(1) In the interlock control mode move the crane to the preset stacking position.
(2) Turn the CONTROL MODE SELECTION change-over switch on the right
operation panel to SEMI-AUTOMATIC position.
(3) Enter the PARAMETER SETTING menu of the programmable terminal to set
the lifting times and slewing times of the cantilever.
(4) Turn STACKING-RECLAIMING CONTROL change-over switch on the right
operation panel to RECLAIMING position, the bucket-wheel stackerreclaimer will start up the guide chute, middle hopper damper, cantilever belt
and trailer belt in the program sequence.
(5) Confirm the original slewing direction of the cantilever by TURN LEFT and
TURN RIGHT of the master controller on the operation panel. Then turn
back to STOP position after stopping for a moment and the semi-automatic
reclaiming will be started.
(6) When the material level works, the cantilever will lift up for a certain angle.
Every time when the material level works once, the cantilever lifts up once.
The cantilever will not stop lifting up until it gets to the preset lifting times.
(7) When the material level works next time, the cantilever will slew a certain
angle in the original direction. Every time when the material level works
once, the cantilever slews once. The cantilever will not stop slewing until it
gets to the preset slewing times.
(8) When the material level works next time, the crane will move backward for a
distance.
(9) When the level meter works next time, the cantilever will slew for a certain
angle in the direction opposite to the original direction. Every time when the
material level works once, the cantilever slews once. The cantilever will not
stop slewing until it gets to the preset slewing times.
(10) When the material level works next time, the crane will move backward for
a distance.
(11) When the material level works next time, the cantilever will slew for a
certain angle in the original direction. Every time when the material level
works once, the cantilever slews once. The cantilever will not stop slewing
until it gets to the preset slewing times.
(12) When the material level works next time, the crane will move backward
and then turns in reverse direction. After that, the crane will move
Page 61 of 160
backward and turns in a natural direction, and then moves backward and
repeats the operation in this way till the equipment stops.
(13) Enter the PARAMETER SETTING menu of the programmable terminal
and the semi-automatic stacking-reclaiming flow can be paused by
clicking MANUAL INTERFERENCE button. At this time, the following
parameter setting can be done:
Enter the PARAMETER SETTING menu of the programmable terminal to
adjust the lift times and slewing times of the cantilever;
Adjust the slewing angle of the cantilever by left or right switchover of the
master controller on the right operation panel;
Adjust the stacking position by forward or backward switchover of the
master controller on the left operation panel;
Adjust the cantilever height by forward and backward switchover of the
master controller on the right operation panel.
After confirming, enter the PARAMETER SETTING menu of the
programmable terminal to realize the semi-automatic operation by clicking
MANUAL INTERFERENCE RELEASE button according to the new
parameter.
(14) Refer to the attached drawing two for the semi-automatic stacking process
flow
Page 62 of 160
Page 63 of 160
Reclaiming interlock
Enter the STATE INDICATION menu of the programmable terminal; when the
SYSTEM ALLOWING RECLAIMING light turns on, the bucket-wheel stackerreclaimer can come into normal reclaiming work state and send out BUCKETWHEEL STACKER-RECLAIMER RECLAIMING signal to the system program
control room. When the system belt stops operation due to fault, the reclaiming
work will automatically stop
At this time, all the change-over switches on the operation panel must be
switched to the stop position to prevent corresponding mechanisms automatically
restarting up when the system recovers to normal state
b.
Stacking interlock
Enter the STATE INDICATION menu of the programmable terminal; when the
SYSTEM ALLOWING STACKING light turns on, the bucket-wheel stackerreclaimer can come into normal stacking work state and send out BUCKETWHEEL STACKER-RECLAIMER STACKING signal to the system program
control room. When the bucket-wheel stacker-reclaimer stops operation due to
fault, the stacking work of the system belt will automatically stop
Emergency shutdown
In an emergency condition, press EMERGENCY SHUTDOWN button on the
right operation panel to immediately cut off the dynamical power and control
power of the whole equipment to stop the bucket-wheel stacker-reclaimer
In an emergency condition, the emergency shutdown pulling wire in the
middle of the cantilever and the trailer to stop the bucket-wheel stackerreclaimer
b.
Fault reset
Page 64 of 160
Fault reset is used to release the self-locking of the fault signal sent out
during the operation of bucket-wheel stacker-reclaimer. Press FAULT RESET
button on the right operation panel can release the fault signal
If the fault signal still alarms after pressing the fault reset button, the
maintenance staff needs to check it. Reset the signal again after the fault is
released
c.
Startup alarm
Startup alarm is used for the sound and light alarm before starting up each
mechanism of bucket-wheel stacker-reclaimer. Press STARTUP ALARM
button on the right operation panel can fulfill the alarm operation
The sound and light alarm starts automatically when the crane is moving
d.
e.
Lighting control
Pressing LIGHTING POWER ON button on the left operation panel can turn
on the projecting light of the whole equipment.
Pressing LIGHTING POWER OFF button on the left operation panel can turn
off the lighting projecting light of the whole equipment.
Pressing LIGHTING POWER ON button on the local lighting control button
box can turn on the lighting projecting light of the whole equipment.
Pressing LIGHTING POWER OFF button on the local lighting control button
box can turn off the lighting projecting light of the whole equipment;
2.1.2.6.3.6
Page 65 of 160
Page 66 of 160
(7) The door of the cab should be well closed during operation in the cab.
(8) Overload must be prevented during reclaiming. For the overload of a few times,
the overload capacity must not exceed 20% of the load
2.1.2.6.3.7.2 Precaution items required to be checked during the operation of bucket-wheel
stacker-reclaimer
When the bucket-wheel stacker-reclaimer is operating, the person in charge of work
should often inspect the following items to make sure the bucket-wheel stackerreclaimer is in good and safe working state
(1) whether the motor, bearings, speed reducer, coupling or brake has abnormal
sound, vibration and heating; whether the speed reducer body, drum, shaft or
wheel is cracked or broken, and especially, whether obvious abnormity can be
found through the abrasion condition of the wheel.
(2) Whether the bolts, nuts and shaft end retaining plate are loose or drop.
(3) Whether each brake works normally, and inspect the abrasion condition of the
brake shoe.
(4) Whether the lubrication oil inside the speed reducer is proper; whether theres oil
leakage; whether lubrication oil is fully distributed in other lubrication parts.
(5) Whether each limit switch is out of use.
(6) Inspect the conveying condition of the cantilever belt conveyor.
(7) Pay full attention to the stacking condition of spilled coal because the normal
work of the bucket-wheel stacker-reclaimer and the correct transmission of limit
switch signal will be influenced if too much spilled coal is stacked. In this way, the
stacked coal in the following positions must be cleared in time.
The two sides of traveling rail for crane
Slewing center
The traveling platform at the two sides for cantilever belt conveyor
If abnormity is found when inspecting each part mentioned above, the equipment
must be shut down immediately for treatment and then can continue to operate
after treatment.
2.1.2.6.3.7.3
Precautions to windstorm
When wind speed is 20m/s, the bucket-wheel stacker-reclaimer is not allowed to
be operated. Therefore, preparation must be done in advance when windstorm
alarm is sent out: the bucket-wheel stacker-reclaimer must be moved to the
anchor parking position and the rail clamp of the crane must clamp tightly. At the
same time, the anchor must be in locking position. The cantilever must be put on
the windbreak stake and locked. Inspect and lock the doors and windows of
Page 67 of 160
electric room and the cab, and cut off the power supply
2.1.2.6.3.8
Page 68 of 160
(1) Take apart the electric equipment to clean and maintain the equipment support.
(2) Clean the rolling bearing of the motor and change new lubricating grease for it;
(3) Measure the clearance between the stator and rotor; if it is uneven, the rolling
bearing needs to be changed.
(4) Measure the insulation resistance and take drying treatment measure if
necessary.
(5) Various faults found during annual maintenance have been treated.
(6) The parts that cant be repaired during annual maintenance should be replaced.
(7) The annual maintenance range should be decided by the actual abrasion and the
using degree
2.1.2.6.3.8.4 Fire treatment
Dry type fire extinguisher must and only can be provided for the bucket-wheel stackerreclaimer. The most common type is carbon tetrachloride fire extinguisher. It is not
allowed to use foam extinguisher. The dry sand only can be used to extinguish fire on
lead but cant be used to extinguish fire on motor
When theres fire, the power supply should be cut off first. At this time, emergency
switch or emergency button can be used to open the main contactor or main circuit
breaker in the power distribution cabinet. When the lead in front of the power supply
cabinet catches fire, the incoming line circuit breaker or fuse of the bucket-wheel
stacker-reclaimer should be opened, or the circuit breaker of the feeder line of the
ground system.
The bucket-wheel stacker-reclaimer that catches fire should be cleaned and dried,
and the electric equipment and electric line should be checked. It only can be reused
after it is repaired and meets the requirements
2.1.2.7
2.1.2.7.1
2.1.2.7.1.1 Operators shall be professional staff, be trained, and shall pass examination.
2.1.2.7.1.2
2.1.2.7.1.3
Bucket wheel stacker/reclaimer shall work only when wind speed is less than 25m/s,
Page 69 of 160
since brake of rail clamps and travel mechanism makes action only when wind speed
is less than 25m/s. Once bucket wheel stacker/reclaimer is blown away by wind, it is
difficult to make further braking action. Therefore, rail clamps shall be maintained well
at all time, and periodically check reliability of wind force warning system. Following
requirements shall be observed during operation of the equipment:
a.
When wind speed exceeds 25m/s(Grade 7 wind), warning system sends off
warning signal, operation shall be stopped immediately.
b When wind speed is predicted to exceed 25m/s, control room shall have sufficient
time to move bucket wheel stacker/reclaimer to be anchored and clamped,
meanwhile, bucket wheel should be quickly landed.
c
When wind speed reaches 25m/s, any work shall be halted, the equipment shall
be anchored at anchor position, rail clamps shall be clamped, bucket wheel
should be landed.
2.1.2.7.1.4
During the process of operation, when electricity suddenly is cut off or voltage in
power line fluctuates greatly, driver shall cut off master switch as soon as possible,
each control switch shall be reset.
2.1.2.7.1.5
During the process of operation, filling oil, cleaning and service are forbidden; Power
supply shall be cut off when the equipment stops for maintenance.
2.1.2.7.1.6
Tools and spares shall be stored in special-purpose box or cabinet, they shall not be
placed anywhere at random. Flammable, explosive materials shall not be allowed to
store on the equipment, in operators cabin and electrical room, dry fire extinguishers
shall be equipped.
2.1.2.7.1.7
Often clean oil dirt, rainwater, ice and scattered coal block and coal powder on ladder
and platform.
2.1.2.7.1.8
2.1.2.7.1.9
Page 70 of 160
to condition of strong wind in order to safeguard bucket wheel stacker reclaimer. Prior
to normal start-up, besides rules required in power generation plant, check the
following:
2.1.2.7.2
a.
b.
c.
d.
2.1.2.7.2.1
Lifting, traveling and slewing limit switches shall only be used in emergency stop of
failure; as to normal stop, switches (button) on control console shall be used. A short
period of pause shall be given in change of rotation direction in order to stabilize
operation.
2.1.2.7.2.2 Driver shall concentrate his attention on operation and observation, especially during
the process of slewing and lifting operation, to avoid any collision between the
equipment and coal pile or any construction facility. In the operation of automatic
stacking/reclaiming, driver shall strengthen monitoring of working conditions.
2.1.2.7.2.3 If sudden failure occurs in operation of equipment, use emergency stop switch to stop
the equipment.
2.1.2.7.2.4 Too much coal accumulated on head of boom rack may affect normal luff action, which
shall be removed in time.
2.1.2.7.2.5
b)
Bolt, nut, end cover, fixing plate of mechanical parts shall not be loosened or
damaged.
No oil leakage in reducer after the reducer is filled fully; other parts shall be totally
lubricated
e)
Emergency stop switch and pulling wire switch shall be used for stopping
Page 71 of 160
2.1.2.7.4
Oil filter shall be installed at oil suck inlet and oil return inlet of pump to prevent
polluted particles in oil from entering into and damaging parts. Warning signal will
send off if oil return filter is choked, motor of oil pump will stop power supply until
filter elements are cleaned or replaced.
b.
c.
d.
2.
Anchor device of travel mechanism and anchor seat on ground foundation shall
not be broken.
3.
4.
Operator cabin, electrical room, electrical parts and elements shall not be
moistened or damaged.
5.
Power supply cable and cable reel drum shall not be damaged.
No obstacle on rail, rail accuracy shall comply with the requirements specified in
Appendix 1.
2.
3.
4.
Page 72 of 160
After the equipment is confirmed to be normal, refill lubricants to any lubricating point,
first of all, commissioning the equipment in low speed unloading, only after limit
switches can work normally, to run the equipment in full speed.
2.1.2.8
2.1.2.8.1
Daily inspection
2.1.2.8.2
2.1.2.8.3
a.
b.
c.
d.
e.
b.
c.
Whether bolt is screwed, whether support bracket and base off or loosen.
d.
e.
f.
g.
h.
b.
c.
Whether wiring terminal of motor is loose, whether other electrical terminals are
damaged.
d.
e.
Working status of cable reels, check whether damage exists in slip ring.
f.
g.
Wear of reducer gear, roll bearing and slide bearing, clean reducer and replace
h.
oil.
Page 73 of 160
i.
Check whether long travel rail accuracy is within control limit according to
Appendix I.
2.1.3
Water Wiper
2.1.3.1
2.1.3.2
Technical specification
Parameter name
Parameter data
Parameter name
Parameter data
Type
SZC 1000
Motor power
1.5 KW
Belt width
1400
Rise
angle
plough head
DT100030
Acting time
5 S
Installation position
Installation number
1 set
of 250
2.1.3.3
2.1.3.3.1
Check the following items: the equipment installation has been finished; the frame is
well fixed and not loose; the idler frame moves up and down freely, and the idler
rotates flexibly
2.1.3.3.2
Before supplying power, do manual test first and shake the hand wheel to see running
condition of the whole equipment; at the same time, adjust the initial end and stroke of
the electric pushing rod
2.1.3.3.3
2.1.3.3.4
2.1.3.4
2.1.3.4.1
Supply power to the electric pushing rod; check the contact between the water wiping
plate and the belt is good; start up the belt of this section to operate
2.1.3.4.2
Check the contact between the water wiping plate and the belt is good
2.1.3.4.3
Page 74 of 160
2.1.3.4.4
2.1.3.4.5
Adjust the distance between the contacting block and the travel switch to move them
in the required positions
2.1.3.4.6
Screw down the adjusting screw to fix the contacting block and then supply power to
do test till the equipment gets to the best working state
2.1.3.6
2.1.3.6.1
Put the electric pushing rod in retracting position and cut off power of the motor
2.1.3.6.2
Confirm the water wiping plate has lifted up and the idler frame has been back to the
horizontal position, and then coal can be supplied to the belt
2.1.3.7
Fault cause
Fault treatment
Electric pushing rod No power in motor or fault Check the power supply or
out of work
in internal transmission dismantle the pushing rod
part
mechanism to check.
Incomplete
wiping
water Bad contact between water Adjust the wiping plate and fix
wiping plate and belt
the bolts; adjust the frame;
check whether the rotating
mechanism of the idler frame is
jammed and treat it.
2.1.4
Bulldozer
2.1.4.1
2.1.4.2
Technical specification
2.1.3.3
2.1.4.3.1
2.1.4.3.2
Check, maintain, adjust and fix the shovel following the daily routine maintenance
items
2.1.4.3.3
Check whether fuel, lubrication oil and cooling water are sufficient and add them if
they are insufficient. It is forbidden to smoke or get close to open flame when adding
fuel oil, so as to avoid fire
2.1.4.3.4
Check whether the electric line insulation and each switch contact are good
2.1.4.3.5
It is forbidden to stand inside the bucket, on the arm link, crawler and bulldozer crest
Page 75 of 160
slab
2.1.4.3.6
Before operating the bulldozer, big stones or other obstacles should be cleared if they
are in working area
2.1.4.4
2.1.4.4.1
Check whether all pipes, operating valves, working oil cylinder and oil pumps of the
hydraulic system leak and are abnormal
2.1.4.4.2
Put the joystick of the main clutch in NEUTRAL POSITION and start the engine.
Check whether all instruments, transmission mechanism, working device and brake
mechanism are normal. The work can be started after confirming all is correct
2.1.4.4.3
For night work, the working place should be provided with good lighting
2.1.4.5
2.1.4.5.1
2.1.4.5.2
The bulldozer should be operated stably; do not shovel too deeply; the shovel blade
should not be strongly moved up and down; it is proper that the distance between the
shovel blade and the ground is 0.4m; do not lift the shovel blade too high
2.1.4.5.3
When the bulldozer is traveling on the slope, the uphill gradient should not exceed
25, the down slope gradient should not exceed 35, and the transverse gradient
should not exceed 10. Transverse travel is forbidden on the steep slope (above 25)
2.1.4.5.4
Heavy turning movement is not allowed when the bulldozer is running in the steep
slope in longitudinal way. The bulldozer should be operated at low-speed when going
up and down the slope and it is not allowed to change the speed Throw-out of gear
sliding operation is forbidden when descending the slope
2.1.4.5.5
On the way to ascend slope, if the engine shuts down suddenly, put the shovel blade
on the ground immediately, step down and lock the brake pedal; when the bulldozer is
stopped steadily, disconnect the main clutch, put the gearshift lever in neutral position
and fix the crawler or tyre tightly with a triangle block, and then restart the engine
2.1.4.5.6
When the bulldozer is shoveling coal at the angle above 25, filling-digging operation
should be done first. The bulldozer only can start work when it can keep self-balance
2.1.4.5.7
When a number of bulldozers work in the coal yard at the same time, the distance
between the front one and the back one should not be less than 8m and the distance
between the left one and the right one should not be less than 1.5m
2.1.4.5.8
The bulldozer is forbidden to be turned heavily and quickly when it is under load or
operating at high speed.
2.1.4.5.9
In working time, the operator is not allowed to leave the work post at will
2.1.4.5.10
It is forbidden to maintain and get on or get off the bulldozer when it is operating.
Page 76 of 160
2.1.4.6
2.1.4.6.1
Dust and dirt attaching to the external part of the bulldozer should be flushed and
cleaned after work
2.1.4.6.2
Check, maintain, adjust, lubricate and fasten the bulldozer in the routine maintenance
way
2.1.4.6.3
ground
Move the bulldozer to flat and safe place and put down the shovel blade on the
2.1.4.6.4
The operator must shut down the engine and lock the door and window before leaving
2.1.4.7
Reason
Solutions
The ammeter
good.
The
belt
adjustment
appropriate.
tension
is
not 2
is
not 1
Adjust
tension.
the
replace
belt
Replace it.
Check and
the line.
Check and
the line.
The
power
accumulator
insufficient.
in 3
is
4
Charge
accumulator.
replace
replace
the
Check and
the line.
Page 77 of 160
oil 1
is
is
2
oil
Oil
pressure
gauge 1
indication is too high.
2
Replace
the
pressure gauge.
oil
Add water.
Replace
thermostat.
Change
the
thermostat sealing.
Replace
thermometer.
3
4
5
the
blocking
Replace the
thermometer.
Clear
the
pipeline.
Discharge air.
Page 78 of 160
cooling
water
the
water
fuel
electric
speed is low.
5
The engine vibrates.
The
clearance 1
adjustment is not good.
2
The joy stick movement
is not good.
is 3
Inform
maintenance
adjustment.
the
for
Step down the brake The brake is not good or the Adjust it.
damper; the equipment travel range is too big.
cannot stop.
The crawler falls off; the The crawler is too loose or
chain wheel is worn too tight.
abnormally.
The shovel rises slowly or 1
does not rise at all.
Adjust it.
2.2
2.2.1
Belt Conveyor
2.2.1.1
Inform maintenance
for treatment.
Maintain or replace it.
The belts before no.3 transfer station are designed in single series. The belt width is
1400mm, with speed at 3.5m/s and conveying capacity of 2000t/h. The belts from the
stacker-reclaimer to the main building are designed in double way. C-1.C-2.c-3 and c7 are all single-way belts which are installed in coal yard and emergency coal hopper.
The double-way belt conveyor will be designed as: B=1200mm, v=3.15m/s,
Q=1250t/h while the belt A/B of C-6 installed in the coal bunker will be designed as:
B=1400mm, v=2.5m/s, Q=1250t/h, according to the electric sledges installed at the
two sides.
2.2.1.2
2.2.1.3
2.2.1.3.1
Check whether the foundation and the connecting bolts in all parts have been
Page 79 of 160
fastened.
2.2.1.3.2
Check whether the welded parts in the side lack of weld or not.
2.2.1.3.3
Check whether sufficient lubrication oil have been added to the motor, speed reducer
and bearing pedestal according to the requirements.
2.2.1.3.4
Check whether the electric signal, control protection and insulation meet the
requirements.
2.2.1.3.5
Check the groove inclination direction of the transmission drum with herringbone
rubber surface; press the button to start up the motor quickly and then release the
button to shut down the motor to confirm its running direction.
2.2.1.3.6
Fill oil in the hydraulic coupler and confirm the oil capacity after press the button to
start up the motor quickly and then release the button to shut down the motor to
check whether the running direction of the motor meets the requirements.
2.2.1.3.7
There should be no obstacles around the motors, speed reducer and belts; the
anchor bolt should be fixed steadily; the earthing wire is good; the guardrail, coupling
safety cover and dustproof device should be intact.
2.2.1.3.8
The oil of each part is sufficient; the oil quality is good; there is no severe oil leakage
(the oil level of the speed reducer should not be less than the specified oil level).The
head and rear drum, fraction increasing drum, turnabout drum, moveable drum, upper
and lower idler and adjusting drum should be intact without roll release. There is no
coal accumulation; all rotating parts are in good lubricating states, without a lack of oil.
2.2.1.3.9
All tension devices (moveable tension device, Trolley type tension device and lead
screw tension device), and the adjusting idler are flexible, without roll release; the
steel wire rope should be in guide wheel chute, without wire break or damage; the
counterweight device is proper and does not contact the ground.
2.2.1.3.10 The inversion brake and the stopper plug are in correct positions and play good
functions.
2.2.1.3.11
The coal wiping plate and cleaner are flexible and play good functions.
2.2.1.3.12
The coal falling pipe and lining plate inside the pipe and the set screw are intact; there
is no foreign matter and no accumulated coal; the rubber lining part of the guide chute
belt lining part is intact; there is no fly coal powder during coal loading and no foreign
matter blocking; the width of the newly replaced belt lining part is proper; the coal can
pass smoothly.
2.2.1.3.13 There should be no warning board for the (if there is, find out the cause and eliminate,
and then the equipment can be started up); the indications of power supply indication
light and ampere meter are normal; the positions of the interlock operation switch and
the emergency button are correct and in good use states. The coal interruption, coal
blocking, deviation, coal level, equipment position, limit, low speed and coal plough
ascending and descending signals are good.
2.2.1.3.14
2.2.1.3.15
The turnover plate is flexible and plays good function. Its position is correct.
Page 80 of 160
2.2.1.3.16
The coal plough is flexible, plays good function and can freely ascend and descend,
without coal blocking or running.
2.2.1.3.17
There should be no water, frost, foreign matter on the belt; the belt has no severe
damage, no bonding gap and coal leakage, and its tension is suitable.
2.2.1.3.18
2.2.1.3.19
2.2.1.4
2.2.1.4.1
2.2.1.4.1.1
Start the equipment one by one in the backward coal flow direction after the system
check is finished. The next equipment only can be started after confirming the last
equipment is operating normally.
2.2.1.4.1.2
The no-load test running of the system should be no less than 2 hours.
2.2.1.4.2
2.2.1.4.3
2.2.1.4.3.1
2.2.1.4.3.2
In manual or programmable no-load test running process, if the equipment has test
switch protection, deviation, coal blocking or belt tearing signal, the running
equipment before it should be stopped while the one after it should keep running.
2.2.1.4.4
2.2.1.4.4.1
On-load test running needs to be done after manual or programmable control startup,
the load should be increased gradually, in accord with 20%-50%-80%-100% of the
rated load. The test running time under each kind of load should be no less than 2
hours.
Decide whether the full-load startup and running test under the load of 110%-125% of
the rated load should be done according to the system process flow requirements.
2.2.1.5
2.2.1.5.1
Observe whether the running parts have friction or not; if there is, adjust those parts to
prevent belt damage.
2.2.1.5.2
Check whether the conveying belt deviates or not; if it deviates 5% of the belt width, it
should be adjusted.
Page 81 of 160
2.2.1.5.3
2.2.1.5.4
Check whether the speed reducer, hydraulic coupler and other lubrication parts leak
oil or not.
2.2.1.5.5
Check whether the temperature rises of lubrication oil or bearing are normal.
2.2.1.5.6
Check whether the contact between the wiping plate of the cleaner and the conveying
belt is normal.
2.2.1.5.7
2.2.1.5.8
Check whether the connecting bolts of the foundation and each part are loose or not.
2.2.1.6
2.2.1.6.1
The belts can be stopped after confirming there is no coal on the last belt. Stop the
equipment one by one according to the coal flow direction if manual shutdown mode
is used; if programmable control shutdown mode is used, press the shutdown button
directly.
2.2.1.6.2
It is not allowed to use the belt conveyor to do work beyond the design regulations.
2.2.1.6.3
2.2.1.6.4
2.2.1.6.5
2.2.1.6.6
2.2.1.6.7
2.2.1.6.8
The operator and patrol inspector should make a good record when finding the
equipment operation is abnormal and shut down the equipment in emergency
conditions.
2.2.1.7
Fault cause
Solution
Belt slip
Overheating
bearing
transmission
drum
Failed startup of There is coal on the belt Clear part of coal and restart.
belt conveyor
in shutdown process.
2.2.1.8
2.2.2
Idler
a.
Trough idler
Trough idler is generally consisted of three short idlers; the axis of the short idler in
the middle and the axis of the short idlers at the two sides forms an angle which is
called the trough angle of the idler. The trough angle of the belt conveyor is 35. As
figure a is showing, the idler body is generally made of seamless steel pipe, but
seamless steel pipe is replaced by seamed steel pipe in some places now. The idler
of the belt conveyor of the company is in a seamed steel pipe welding structure. No.2
lithium base grease is used for lubrication and labyrinth seal is used for the seal of
the idler.
b.
Parallel roller
Generally, parallel roller is a long idler which is mainly used as the idler for the under
layer belt (below idler for short), supporting the belt of no-load section, shown as
figure b.
c.
Impact idler
The function of impact idler is to decrease the impact of coal on the belt at the coal
loading part to protect the belt.
Page 83 of 160
The impact idler is divided into rubber type impact idler, spring plate type impact idler
and spring plate type apron impact idler, shown as figure c.
Common idlers
a) Trough idler group b) parallel idler c) impact idler d) inclined straight idler
d) Self-centering idler
Various belt conveyors inevitably have different deviation phenomena in operation
process due to many random factors, so a certain number of self-centering idlers
should be installed
The reversible self-centering idler is used for double-way operation belt conveyor,
whose structure is shown as figure 5-2. Its working process is like this: the two curve
plates at the left and right sides and the friction disc fixed on the idler shaft produce
certain friction force to make the support slew. When the belt deviates, it contacts the
left curve plate or the right one and produces a friction torque through the curve plate
to make the support rotates a certain degree so as to achieve the centering aim. The
double-way centering idler cancels the vertical idler, so the abrasion to the belt edge
is slight when the belt deviate and it is widely used.
Page 84 of 160
2.2.3
Tension Device
The function of tension device of belt conveyor: ensure the belt has enough tension;
make the drum and the belt produce required friction force; limit the sag of belt in support
idlers; leave a certain length for rebonding belts.
a. Trolley type tension device: the tail drum is installed on the trolley; the heavy hammer
pulls the trolley through the steel rope and guide pulley to move along the belt
conveyor in longitudinal direction, shown as the figure below.
4. winch
b. Heavy hammer tension device. It is consisted of two turnabout drums and a tension
drum, which is usually installed in the place where the empty belt of the conveyor is
near the driving drum, with the minimum belt tension. The tension drum and the
moveable frame can move together along the vertical guide rail, shown as the following
figure.
Page 85 of 160
5. Guide rail
6. Heavy hammer
2.2.4
Cleaning Device
In the operation process of the belt conveyor, slight coal particle will adhere to the
belt cause belt deviation and increase the movement resistance, so belt conveyor is
usually equipped with cleaning device.
The spring cleaner is one device to scrape off the coal on the belt via spring pressing on
coal scraper. The coal scraper is produced by improved alloy blade and fits with head
coal falling hopper. The coal cleaned off will fall into head hopper. There are empty
section cleaners in front of return tail drum, vertical tension device and middle driving
device.
Page 86 of 160
H-type
P-type
2.2.5
Auxiliary Equipment
2.2.5.1
Motor
2.2.5.1.1
Strictly carry out the relevant regulations on motor operation in Auxiliary Operation
Regulations.
2.2.5.1.2
2.2.5.1.2.1
In normal conditions, squirrel cage motor can be continuously started two times in
cold state, and the interval is not less than 5min; it can be started once in cold state.
Only during trouble shooting or when the startup time is not more than 2s 3s, the
motor can be started once more.
2.2.5.1.2.2
Refer to startup time interval table 1 when doing dynamic balance test.
Table 1 Startup time interval table
Motor capacity
Below 200kW
200500kW
No less than 1h
Above 500kW
No less than 2h
Remark: The condition that motor is restarted after less than 1 hours continuous
operation or after more than 1 hours continuous operation and shutdown for 4
hours is called as cold state; except the condition mentioned above, the other ones
are all called as hot states.
2.2.5.1.2.3
When the motor is started, the programmable control or the local operator should
closely monitor the starting current and starting time of the motor; when the starting
time exceeds the starting time limit, the operator should immediately press STOP
Page 87 of 160
The starting time limit of the coal handling equipment is specified as follows.
2.2.5.1.2.5 The starting time of the belt conveyor should not be more than 5 seconds (normally, 2
3s).
2.2.5.1.2.6
The starting time of the coal crusher should not be more than 10 seconds (normally,
7s).
Remark: starting time refers to the time interval that the current returns to normal
current from starting current when the motor is started.
2.2.5.1.2.7
The motor only can be started before the insulation is measured to make sure it
meets the standard when the motor is maintained, moistened or has been in standby
state for more than 15 days.
2.2.5.1.2.8
In motor operation, the vibration value measured at each bearing should not exceed
the following value, referring to table 2.
Table 2 Bearing vibration value of motor
2.2.5.1.2.9
Rated rotation
speedr/min
3000
1500
1000
Vibration
value(doubleamplitude) mm
0.05
0.085
0.10
0.12
The motor can be operated in accord with the rated parameters on the nameplate
provided by the manufacturer when then rated cooling air temperature is 35
40. When the cooling air temperature is more than the rated value, the operation
parameters should not be more than the allowable temperature of the motor.
2.2.5.1.2.10 The operating value of each part of the motor should follow the following table (table
3).
Table 3 Temperature value of each part of motor
Name
part
of
each Insulation
Stator winding
Rotor winding
Grade A
95
60
Grade B
115
80
Grade E
110
75
Grade F
120
85
Grade B
105
70
Page 88 of 160
Grade E
100
65
100
65
Slip ring
105
70
Sliding bearing
80
45
Rolling bearing
100
65
See Table 4 for the bearing temperature limits of each mechanism in operation
Table 4 Bearing temperature limits
ROTARY BERING
PULLEY BEARING
GEAR BOX
80
70
70
2.2.5.2
Gear box
2.2.5.2.1
2.2.5.2.2
(1)
Function: the function of gear box is to shift the high speed low torque
mechanical energy of motor into low speed big torque power to fit operation of
mechanical equipment.
(2)
Advantages: it has tight structure, wide application, permanent drive ratio, high
mechanical efficiency, long service life, small pressure on shafts and beings.
Page 89 of 160
CAUSES
CORRECTION
1. Inform maintenance
3.
Timely
contaminants
1. Inform maintenance
Bearing heated up
remove
surface
2. Inform maintenance
3. Inform maintenance
4. Adjust the coal feeding amount
4. Overload.
Oil leakage between 1. Bad sealing
end cap and gear
2. Vent cap blocked
box body
Noise
in
transmission
Vibration overlimited
2.2.5.3
Coupler
Page 90 of 160
2. Inform maintenance;
1. Inform maintenance
2. Inform maintenance
3. Inform the maintenance
operators
4. Fasten the bolts.
a.
b.
The advantages of hydraulic coupling: it has long life span, simple structure,
reliable performance and little maintenance.
c.
CAUSES
CORRECTION
rotation speed
or incorrect connection;
2. Brake fault of driven 2. Inform maintenance
mechanism
which
3. Reduce oil volume
caused overload;
3. Oil over filled.
1. Inform maintenance
2. Reduce load
3. Prevent frequent startup
3. Repeated startup
2.2.5.4.
Brake
2.2.5.4.1
2.2.5.4.2
Check whether the driving unit works normally on each shift, inspect if there
is oil leakage, maintain a certain oil level, define whether the travel is
inadequate or the brake shoes smoke;
b.
Check the oil quality every 6 months. Change the oil when foreign materials
entered into the oil or when the oil deteriorated, pull the rod up and down for
a few times to exhaust the air, fill adequate oil to the level below oil level
signing plug hole.
c.
2.2.5.4.3
CAUSES
CORRECTION
Page 92 of 160
driving
unit
2.2.6.1
Technical specifications
Technical specifications for ring hammer type coal crusher
Specification for the complete machine
Model
KRC12X29
Type
Rated output
1200t/h
22338w33c3
Number
2 sets
Rotor diameter
1200mm
Rotor length
2900mm
11000
47.1m/s
400mm
Page 93 of 160
2.2.6.2
25mm
Handling targets
4 rows
56Kg/12
63Kg/14
Rotor mass
9890 kg
3300X4440X1950
30000
Working principles
The coal briquettes, after entering into the crusher, will be crushed by the ring type
hammer in high rotation speed, and the primary crushed coals rush into the crusher
board and screen to be crushed in a second time. At the same time, coal briquettes
collide between themselves and output small pieces of coal to be pressed, cut and
grinded again on the screen by rotary ring hammer, and finally come out of the
crusher from screen holes.
Uncrushed debris such as iron ores are collected into de-ironing room by rotor.
2.2.6.3
2.2.6.4
2.2.6.5
b.
Startup the coal crusher after systematic belts are normally started up.
c.
Stop the coal crusher after the belt before it was stopped for 30 seconds.
d.
Put the control switch to REMOTE CONTROL after the machine was shutdown.
e.
When the coal crusher needs to be started or stopped for maintenance and
repairing, contact remote control operators and prepare relative safety measures.
Ensure that each indication light, button, selection switch, temperature and
vibration detecting devices are intact, and selection switch is on REMOTE
CONTROL position.
b.
2.2.6.6
c.
d.
Keep the adjusting bolt for screen plate stemmed out at a certain length, ensure
its lubrication and the tightness of bolt cover.
e.
Observe hole and man hole should be tightly sealed, the pins and fastening bolts
are firm, and there is no crack or big wearing on ring hammer and crusher plate.
f.
The hydraulic coupling should rotate flexibly without oil penetration or leakage,
and the surface temperature should no be more than 90.
g.
h.
Causes
Corrections
The
output
particle
obviously
increased (
30mm)
Contact maintenance
Contact maintenance
for condition 1, 2, 3
and 4;
Stop coal crusher to
clean
debris
or
jammed coal
Continuous
1. Unbreakable foreign materials entered
1. Stop for treatment
knocking sound
2. Screen plate flexible and knocked by
Page 95 of 160
in coal crusher
hammer
2.3.
Contact
maintenance
1. Uneven feeding
2.3
Contact
maintenance
2.2.7.1
Specifications
Data
2.2.7.2
Number Width
Model
mm
BDS-1214 12
1400
Capacity
Granularity Efficiency
mm
1250
30
%
90
Drive
form
Chain
Mass
kg
10800
Application
Roller screen is the screening device used in coal handling system for thermal power
plant. After screening, coal pieces smaller than the screen holes fall into the
equipment below screen, and pieces bigger than the screen move forward on the
screen and were entered into coal crusher. Roller screen is used to prevent coal jam,
which is applicable when water content in raw coal is heavy.
BDS type inclination variable isochoric roller screen, which is developed on the basis
of common roller screen, has higher performance, wider application and better
adaptability to materials.
2.2.7.3
Page 96 of 160
Small material will directly pass the screen, and big blocks will be discharged to outlet.
BDS inclination variable isochoric roller screen is designed into two sections of screen
plates with different inclinations. Wherein, the screen closed to coal falling part has
bigger inclination, with 20-30of plate angle near coal feeding mouth, and the
inclination has material outlet is 5-15. Unit with bypass systems make it easier to
inspect the rolling of turbine, to make it more convenient for the maintenance of roller
screen. The distribution plates will actuate through the electric thrust rod.
2.2.7.4
2.2.7.5.
Main characteristics:
1.
The inclination of screen plate at the intake section is big, which force the
material to flow quickly into the next section and eliminated the jam or block
caused by accumulated coal.
2.
The speed of material slows down in the process when the screen plate
inclination decreases, and material will be gradually separated on each section
and form approximate isochoric screening.
3.
As the material flow gains speed due to increased screen plate inclination, unit
screening capacity increased, which improved the systematic efficiency.
The increased natural flowing speed of material reduced the possibility for
materials to stick together, and since the front section screen (intake section)
which has the biggest sticky possibility is designed with large screen shaft
distances, penetration was improved to reduce the jamming and sticky possibility
to a maximum extend.
5.
It adopts big hexagon type screen plate, and adjacent screen plates forms a
screening hole too. This type of screen plates can remove the stuck coal on the
shafts automatically, which considerably reduced the possibility of jam and
increased screening efficiency.
6.
Add shaft cleaner according to the water content of the coal to reduce the coal
which may stick on the shaft under overvalued water content.
7.
8.
It adopts chain type driving, which makes a simple, safe and reliable driving
system that is convenient for repair and maintenance.
9.
It adopts ZG40M n 2 screen plate with wearable and durable life span.
Commissioning
Commissioning of the roller screen are divided into no-load operation and loaded
operation.
a
No-load operation
1). Check and remove the tools, steel parts or other substances on the screen
plate.
Page 97 of 160
with enough
3). Operate the turning gear to manually rotate the screen shaft for a circle. Make
sure there is no blocking on any rotary part.
4). Connect the power supply and inching once after the preparation works are
finished, in order to make sure whether the rotary direction of screen shafts is
correct, i.e. make sure the materials on the screen surface will move to
direction of outlet. Incorrect direction requires an immediate modification to the
motor connection.
(5) Inching the power supply for several times and continue to operate if it rotated
normally. No-load test running should last for 2 hours, and stop the system if
there is any abnormal condition to check and resume before reactivate.
b. Loaded test running
(1) Loaded running can be carried out two hours later than no-load test running.
(2) Startup the roller screen and gradually increase the feeding
rated processing ability.
amount
until
(3) Observe the operation condition of the device during load increasing, stop and
handle the abnormal condition if any. Remove all the residual material in the
screen before restart up.
(4) Stop feeding during normal shutdown and wait until the coals are exhausted
before shutdown.
(5) Loaded operation should last for more than 1 hour.
2.2.7.6
Operation specifications
1. Put the change-over switch on the local control panel to MANUAL position.
2. Sequentially start up the roller screen after the belt conveyor and coal crusher
were normally started.
3. Stop the roller screen 30 seconds after the upstream belt conveyor had
stopped.
4. Put the control switch to REMOTE CONTROL position after
process was finished.
the
shutdown
5. Put the interlock switch onto LOCAL position when the roller screen needs to
be directly startup for maintenance or other purpose, inform the remote control
operators to take safety measures in advance.
6. Start up without load when using the roller screen and feed coal after it enters
into normal operation. Keep an even feeding and do not increase the feeding
amount suddenly.
Page 98 of 160
7. Do not stop the machine with load if there is no special condition. Stop feeding
before shutdown, and wait all the coals are removed.
8. Before restart up after emergent shutdown under loaded operation, remove the
coals manually and then inching several times to start.
9. Keep the lubricated parts in good lubrication condtion.
Lubricate the gear box according to the manufacturer instruction, and the
bearing supporters should be lubricated with dry oil. The gear box should be
checked once a month to ensure it is full of dry oil.
Lubricated the chains with dilute oil in each week and clean them every half a
year.
10. Check and remove the sticking and blockings if any on each shift.
11. Remove the stones stuck into the screen by reversing the motor if it is uneasy
to do manual cleaning.
2.2.7.7
2.2.7.8
Start up roller screen firstly, and then feeding, the opposite procedure is not
allowable.
b.
After putting roller screen into service, periodically check running state and
change lube oil regularly.
Causes
Solutions
1.Clear sundries
Bearing
temperature
over high
1Adjust load
2.
Ask maintenance
repair.
for
3.
Ask maintenance
repair.
for
3. Bearing damaged.
Obviously
output
decreasing
2.
Page 99 of 160
Ask maintenance
repair.
1. Adjust output.
2.Shutdown for clearing
for
equipment
2.2.8
Magnetic Separator
2.2.8.1
2.2.8.1.1
Overview
The self cooling belt magnetic separator does the natural cooling by the self heat
radiation structure; the belt can rectify the off-track automatically, do the center
control, continuously iron adsorption and discharge. The automatic iron discharge is
carried out by the circulation motion of motor-driven belt together with scraper. The
iron separator is totally 5 sets, one at front of ship unloader belt, one at front of C3
belt. The width of iron separator belt at ship unloader and C3 are 1400mm; others are
1200mm wide. Two separators at
2.2.8.1.2
Specifications
Specifications of self-cooling belt magnetic separator
2.2.8.1.3
Type
RCDD-14T2
Radiation type
Natural cooling
Belt width
1400mm
Hanging height
400mm
Excitation power
21.0KW
Drive power
5.5 KW
Magnetic induction
120mT
GLA-D
Equipment quantity
5 sets
Total weight
8.3t/set
Structural principle
The self cooling belt electromagnetic separator is composed by permanent magnet,
unit support, iron discharge belt, driving pulley, driven pulley, idler and electric
gearbox. The motor connects together with the gearbox; the automatic iron
discharging is achieved by the belt driven by the motor and the circulating iron
discharging movement of its scraper.
2.2.8.1.4
2.2.8.1.5
(2)
No screw loosing and falling off from rotating parts and traveling crane.
(3)
(4)
(5)
(6)
The belt should be checked without tearing, offset, stuck, scratch, and too
tight or too loose, joints and disposable iron belt scraper are well-fixed.
2.2.8.1.6
2.2.8.1.8
Problems
Causes
Solutions
Adjust equipment
hanging height and
obliquity.
Cased by vibration of
sucking and throwing iron,
etc.
Retighten the
connection points
2.2.8.2
2.2.8.2.1
Overview
Remarks
Disc type electromagnetic iron separator is a kind of suspended equipment which can
continuously operating with motor-driven single rail travel structure. It is installed two
sets. Two sets of disc type iron separators were installed in the middle of C-4AB belts.
The two iron separators for C-4AB were equipped with one set rectifier cabinet. The
two iron separators runs by turns, which can be operated by centralized control and or
local manual control.
2.2.8.2.2
Technical specifications
2.2.8.2.3
Equipment type
PDC-12T2
Natural cooling
Belt width
1200mm
Hanging height
350mm
Excitation power
17.6KW
0.8KW
120mT
GLA-X
Equipment amount
2 sets
5.3t/set
Working priciple
When the magnetic separator is activated, the iron articles in the material will be
aspirated quickly by the magnetic field force. When there is a certain amount of the
aspirated iron, move the Magnetic separator out of the belt, cut the power, discharge
the iron to the abandon iron hopper, then go back to the upward of the belt, reset the
power supply in order to remove the iron article.
2.2.8.2.4
Working characteristics
The self cooling disk electromagnetic separator does the natural cooling by its self
heat radiation structure; it has the small volume, good heat radiation and electric iron
discharging control, it also can use the program or the manual control to achieve the
iron adsorption and abandon of the Magnetic separator.
2.2.8.2.5
2.2.8.2.7
2.2.8.2.8
(3) During operation of this separator, the current of equipment hot state is lower
than that of cold state.
(4) Strong magnetic field exists when the iron separator is running so that easily
magnetized goods like wrist watch and instrument should not approach it.
2.2.8.2.9
Problems
Causes
Solutions
Weakened suck
and throw iron
capability
Hanging height or
obliquity is changed.
Poor
contact
between terminal
box and power
cable
Cased by vibration of
sucking and throwing
iron, etc.
Serious vibration
and
unacceptable
noise
Connection part
loose.
Manual travel
crane can not be
moved
Dolly band-type
brake over tight.
2.2.9
2.2.9.1
Overview
Remarks
Retighten
points
the
connection
This coal sampling device is scraper type, the scraper take coal samples from belt
accurately. The scraper is driven by motor via gearbox. The increase or decrease of
sample depends on sampling frequency of each cycle, i.e. time span decide quantity
of samples. Middle sampling device of as received coal is installed on C-1A belt
conveyor at T-0 transfer station, which are totally 2 sets. The sampling device is
mainly composed of sampling machine, coal feeder, crusher, divider, sample collector,
bucket elevator as well as electrical control system, assemble platform, and complete
enclosed unit control room. The excess coal will drop to C-1A belt conveyor.
2.2.9.2
Technical specifications
2.2.9.2.1
SF-40C
SF-65C
2.2.9.2.2
Line Speed
(mm)
(m/s)
400
0.0150.25
50150
adjustable
adjustable
0.0150.25
25100
adjustable
adjustable
650
Power
Drive
Collocation
(kw)
1.1
UDY1.1-XW4/43
1.5
UDY1.5-XW5/43
Rotor
spec
Input
granularity
Output
granularity
mm
mm
Motor
Type
Hammering
Power
Capability
t/h
HJC0302
300200
50
Y112M-4
4 KW
HJC0403
400300
150
Y132M-6
5.5 KW
HJC0404
400400
150
Y200L2-6
22 KW
Power
Power Device
Suitable belt
width
(mm)
RSDL-40
2.2.9.2.4
Door Height
Crushing
Type
2.2.9.2.3
Belt Width
400
Hatch
size
Line speed
(m/s)
(kw)
0.724
0.75
(mm)
3850
Belt
Width
Line Speed
Door Height
(m/s)
Power
(kw)
Drive
Collocation
(mm)
SF-40C
2.2.9.2.5
400
0.0150.25
50150
adjustable
adjustable
Sample collector
Page 106 of 160
1.1
UDY1.1XW4/43
Ty
Number
CubageLi
tre
Power
(KW)
25
0.75
pe
SC-R6
2.2.9.2.6
Drive Device
Brake Motor Reducer
2.1628.16 m
Transport Capability
1.33 m 3/h
Cubage of hopper
0.2 L
0.79 m/s
Type
Power
2.2.9.2.7
BWD 1.111/17
1.1 KW
Electrical part
Operation mode: Auto/manual/semi-auto
400VAC 50HZ
2.2.9.3.1
Check system equipment is finished and the single test running is eligible.
2.2.9.3.2
2.2.9.3.3
2.2.9.3.4
Check the tablet getting close to switch, and the power supply is connected the
moment the cutter gets off the belt on the rear part of cutter.
2.2.9.4
2.2.9.4.1
Manual Operation
2.2.9.4.1.1
Put auto, stop, manual on front panel of the sampling control cabinet to Manual.
2.2.9.4.1.2
Start up bucket elevator, collector, splitting device, coal crusher, primary material
feeder and sampler in sequence.
2.2.9.4.1.3
The system equipment should be running without load for 2 hours after being normal.
2.2.9.4.2
2.2.9.4.2.1
Put auto, stop, manual on front panel of the sampling control cabinet to Manual
after the unload-running is finished.
2.2.9.4.2.2
2.2.9.4.2.3 Interlock test: during system operating, disconnect the power supply for any
equipment in the system or send the emergency signal, the main power supply should
be disconnected and the equipment before the emergency equipment should be
stopped, but the equipment behind the emergency equipment should keep operating.
2.2.9.4.2.4
Equipment
Allowed conditions
Crusher
Dredging device
Material feeder
System operating
During material feeding, the system operation signal is sent out and the
signal light is on.
Initial sampler
System clearing
Splitting device
Interval running after initial sampler is acting and the splitting device
has no emergency.
Sample collector
2.2.9.4.2.5
Cleaning process
2.2.9.4.2.5.1 Press the CLEANING button when system is in operation to perform cleaning.
2.2.9.4.2.5.2 Stop the main belt when system is in operation.
2.2.9.4.2.5.3
During system operation, there are failures that can be corrected by cleaning,
such as primary sampling scoop failure, feeder failure, crusher failure, divider
failure, collector failure, and failure resulting from coal blockages. During cleaning
process, stop primary sampling device while keeping the other devices in
operation for ventilation.
Feeder failure
Unblocker failure
Divider failure
Operation
with load
2.2.9.4.2.7.1 Open the bucket elevator three-way damper and ensure that it is in the correct
position.
2.9.4.2.7.2
When coal is on a belt which has a sampler, start up the sampler by program control.
2.2.9.5
2.2.9.5.1
Check to ensure that the blade of sampler is not too close to the belt to prevent belt
wear. Adjust when necessary.
2.2.9.5.2
Check to ensure that the lube oil in the primary feeder gearbox is of appropriate
quality and that oil level is normal. The belt should not be off-track. Adjust the take-up
unit if necessary.
2.2.9.5.3
When particle size increases, check the crusher hammer. If it is seriously worn,
replace it.
2.2.9.5.4
There are oil holes and air plugs in the collector driving device. The gearbox should
be filled with standardized gear oil. Check oil level is normal.
2.2.9.5.5
Check that the bucket elevator does not vibrate and is not overheated; there is no
friction between bucket edge and casing; the gearbox oil quality and level are both
correct.
2.2.9.6
2.2.9.6.1
2.2.9.6.2
Press the stop button when carrying out program shutdown. Manual shutdown should
be done in the opposite order of manual startup.
2.2.9.6.3
Confirm there is no coal in the equipment when stopping manually to avoid an on-load
startup in the future.
2.2.9.7
Causes
Solutions
Adjust take-up unit
cannot
2.2.10
2.2.10.1
Overview
A scraper type sampler is used to sample the as-fired coal. The sampler scraper
precisely takes samples from the conveying belt. It is driven by a braking motor via a
gearbox. Sampling increase or reduction can be done by changing the number of
samples taken during each time frame, i.e. time intervals.
There are two as-fired coal intermediate section mechanical sampling systems
installed on the C-5AB belt inside the crusher room. The sampling device mainly
comprises sampler, coal feeder, crusher, divider, collector, bucket elevator, electrical
control system, installation platform, and wholly-sealed unit control chamber. The
remaining particles directly fall onto the C-5AB conveyor.
2.2.10.2
Technical specifications
2.2.10.2.1
Sampling section
Model
SWAX100-00
Sampling frequency
1-120 adjustable
150 mm
Sampling speed
5 m/s
Sampling intervals
adjustable
2.2.10.2.2
2.2.10.2.3
2.2.10.2.4
13 kg
61 RPM
Linear speed
3.03 m/s
Power
4 KW
Crusher
Model
PSM-00
Crusher type
reactive type
Output
0- 2t/h
Speed
1460RPM
Motor type
Y132M-4
Motor power
7.6 kW
Inlet granularity
60 mm
Outlet granularity
mm
Division part
Divider type
RD-38-00
Divider mode:
rotary type
40mm
Sampling interval
adjustable
Division ratio
1:10-1:00 adjustable
Rotational frequency
23RPM
Motor power
0.26kw
R37DR63L4/BMG-M2
Cut width
28mm
Particle size
10mm
2.2.10.2.5
2.2.10.2.6
Equipment type
JGP360J-00
Output
0-2t
60mm
SA67/DT80K6/T
Rotating speed:
4.1RPM
Power:
0.37KW
Speed:
0.032m/s
Drive pulley:
steel linear160400
Driven pulley
steel linear160400
Sample collector:
Equipment type:
RSC4/8-00
Whole power
0.37KW
Rotational frequency
2.1RPM
RCL60-30XLY-0.37-1-23
10L
TD-100-00
Output:
0-4m /h
Bucket width:
100mm
Bucket capacity :
0.16L
Buckets pitch:
200mm
Belt speed
1.4m/s
Drive pulley:
400
Driven pulley:
316
Motor power:
2.2KW
2.2.10.2.7
Electrical part
Operation mode :
automatic/manual/semi-automatic
26kw
400VAC 60HZ
Control mode
automatic/manual/semi-automatic
2.2.10.3
2.2.10.3.1
Ensure the complete installation of the equipment and single unit test runs are
passed.
2.2.10.3.2
2.2.10.3.3
2.2.10.3.4
Check the sensitive panel near the switch. Make sure it is power-on behind the cutter
as soon as it passes the edge of the belt.
2.2.10.4
2.2.10.4.1
Manual operation
2.2.10.4.1.1 Put the AUTO, STOP, MANUAL switch on the panel in front of the sample control
panel to MANUAL.
2.2.10.4.1.2 Start up successively the bucket elevator, collector, divider, crusher, primary feeder
and sampler.
2.2.10.4.1.3 The equipment in the system should be operated for 2 hours with no-load after it is
found to be in normal condition.
2.2.10.4.2
Program operation
2.2.10.4.2.1 After no load running, put the AUTOMATIC, STOP, MANUAL switch on the panel in
front of sampling control cabinet to AUTOMATIC.
2.2.10.4.2.2 Press the AUTO START button. The system will start running in program operation.
2.2.10.4.2.3 Performing the interlock test: during operation of the system, cut the power supply or
send a fault signal to any equipment. The equipment upstream of the equipment
being tested should immediately stop operating. The equipment downstream should
running continue.
2.2.10.4.2.4 System sequential start program
Page 113 of 160
Equipment
Allowable conditions
Motorized 3-way
valve
Crusher
Unblocker
Feeder
System operation
Primary sampler
System cleaning
Divider
Sample collector
2.2.10.4.2.5.2
2.2.10.4.2.5.3
If there are some faults of system that need to be removed (sampling scoop fault,
feeder fault, crusher fault, divider fault, collector fault, coal jamming fault) when
system running. During cleaning, primary sampler stops sampling, but the rest of
the equipment continues running to clean out the system.
Clogged
coal
induced
Feeder
fault
Crusher
fault
Unblocker
fault
Divider
fault
Sample
collector fault
fault
Open the bucket elevator three-way damper and ensure that it is in the correct
position.
2.2.10.4.2.7.2
When coal is on a belt which has a sampler, start up the sampler by program
control.
2.2.10.5
2.2.10.5.1
Check to ensure that the blade of sampler is not too close to the belt to prevent belt
wear. Adjust when necessary.
2.2.10.5.2
Check to ensure that the lube oil in the primary feeder gearbox is of appropriate
quality and that oil level is normal. The belt should not be off-track. Adjust the take-up
unit if necessary.
2.2.10.5.3
When particle size increases, check the crusher hammer. If it is seriously worn,
replace.
2.2.10.5.4
The driving device of collector has oil filter hole and vent plug. The gearbox can be
filled with standard gear lube. Check lube level promptly in order to ensure lube level
is normal.
2.2.10.5.5
Inspect to ensure there is no vibration and overheating for elevator burner and no
friction between bucket and shell. Additionally, make sure lube quality and lube level
of gearbox are normal.
2.2.10.6
2.2.10.6.1
2.2.10.6.2
There are oil holes and air plugs in the collector driving device. The gearbox should
be filled with standardized gear oil. Check oil level is normal.
2.2.10.6.3
Check that the bucket elevator does not vibrate and is not overheated; there is no
friction between bucket edge and casing; the gearbox oil quality and level are both
correct.
2.2.10.7
Causes
Belt is too loose
Solutions
Adjust take-up unit
2.2.11
2.2.11.1
Overview
In order to calculate the quantity of as-received coal and as-fired coal, electronic belt
scales are installed respectively on belt conveyors C-1A and C-5A/B. Working
principle is as follows: belt scale consists of three main parts: weighbridge, speed
sensor and integrator.
The weighbridge of sensor with load can transfer the weight of materials on the belt
into a voltage output signal that is directly proportional to the belt load. Speed sensors
supply a series of pulses. Each pulse represents one unit length of a belt in operation.
Pulse frequency is directly proportional to belt speed.
The integrator receives signals from the load sensors and speed sensors and
converts them to a digital signal. It gets parameters via microprocessor calculations.
Weight signals are outputted by integrating load signals and speed signals.
2.2.11.2
Technical Specifications
Parameters
Rated output
of coal
handling
system
Parameter Data
Parameters
Parameter
Data
Trough
2000(t/h)
1000(t/h)
Precision of
0.25 (%)
Idler diameter
108(mm)
Belt conveyer
scale
Dimensions
of belt
conveyor
Widt
h
C-1A
1400 (mm)
C-5A/B
1200 (mm)
Speed
Control mode
2.2.11.3
3.5 (m/s)
Installation
location
Power supply
220V 50HZ
Quantity
2)
Check whether there is any coal or foreign matter stuck on the belt.
3)
4)
Check whether the reading on the indicator is zero. If not, adjust it to zero.
5)
2.2.11.4
2.2.11.4.1
Close the power supply switch. Carry out the following operations if the power supply
is in normal condition.
2.2.11.4.2
2.2.11.4.3
Selection ratio units: Default unit: t/h; optional units: t/h, Kg/h, %
2.2.11.4.4
Defined maximum weighing volume ratio: tacit: default 10.0; minimum 1.0; maximum:
200,000,0. Select maximum volume ratio, choose weighing indexing: standardized: 1
option: 0.1, 0.01, 0.001, 1
2.2.11.4.5
2.2.11.4.6
2.2.11.4.7
2.2.11.4.8
2.2.11.4.9
2.2.11.5
2.2.11.5.1
Check whether there is any dust or coal accumulated on the weighing bridge.
2.2.11.5.2
Check whether there is any coal or foreign matter stuck to the belt.
2.2.11.5.3
Check whether the coal on the belt is evenly spread. Maintaining uniform conveying is
a key condition for accurate measurement.
2.2.11.5.4
2.2.11.5.5
Check whether the indication displayed is normal, and check and calibrate.
2.2.11.6
2.2.11.6.1
Belt conveyor scale can be shutdown only after the conveyer has stopped running.
2.2.11.6.2
Check whether there is any dust or coal deposits on the weighing bridge after
shutdown.
2.2.11.6.3
Check whether there is any coal or foreign matter stuck to the conveyor belt.
2.2.11.6.4
2.2.11.6.5
2.2.11.7
2.2.11.7.1
When there is a large difference between the displayed indication and the actual
value, it is necessary to check whether zero shifting or span displacement has
happened to the belt scale system.
2.2.11.7.2
2.2.11.7.3
2.2.12
2.2.12.1
Overview
The magnetic separator only removes magnetic metal. It does not remove nonmagnetic metals such as manganese steel and copper clad aluminum. In order to
keep as-fired coal free from metals, two sets of non-magnetic metal detectors are in
located in the middle section of the C-4AB conveyor belt and behind the magnetic
separator. They are used to detect non-metals in the coal, preventing non-metals
entering the boiler and ensuring safe operation.
2.2.12.2
Technical specifications
No.
Parameter
Data
Model
LJT-12
Supply voltage
230V10%
20W
85% 40
-10 - 40
50HZ
Particle size
<400mm
Material character
60%
0.8 - 4.0m/s
Adaptive width
1200mm
10
11
12
Weight
15Kg
13
Location
14
Quantity
2.2.12.3
2.2.12.3.1
Check the sensor has been fixed on conveyer frame and the instrument box has been
fixed on wall space or frame. Check the position and stableness.
2.2.12.3.2
Ensure the following: secure power source, correct wiring connections in instrument
box, and indicators in good condition.
2.2.12.4
2.2.12.4.1
Put metal detector output control and interlock with belt conveyor into operation.
2.2.12.4.2
Open the box door. Close the power supply switch. The panel power indicators will
turn on. After 30s, the detector will start operating.
2.2.12.4.3
Adjustment of sensibility: the user can adjust the sensibility based on the site
condition. On the upper side of power panel, there is a needle potentiometer (2w1).
Turn it clockwise to increase sensibility and vice versa.
2.2.12.5
2.2.12.5.1
Make sure the indicating signals on the panel work normally. The left indicator is the
power indicator, which is always on when the equipment is operating. The right one is
the signal indicator, which is always on and activates the output relay.
2.2.12.5.2
Inspect the LED level indicator. There is a row of LED indicator lights in the middle of
the board which show the level signal when metal pass by the sensors. When the
green indicator on the left section turns on, it means the noise signal system or some
metals have been detected. When the red indicator on the right section turns on, it
shows there is a harmful metal signal.
2.2.12.5.3
Pick metals out immediately when instruments detect harmful metals and alarm.
2.2.12.6
Open the power switch. The indicator turns off. The detector stops working.
2.2.12.7
No.
Fault
Cause
Solution
prevention
Re-adjust.
3
4
5
and
and
replace
The
alarm Too high detector sensitivity.
Re-adjust
sounds even if
Sensors are installed close to metal Reinstall
there
is
no
like roller or electromagnetic magnetic
metal in the
separator.
coal.
2.2.13
2.2.13.1
Overview
The JZF type vibration anti-blocking mechanism is a kind of universal anti-blocking
mechanism, using the YZO type vibration motor as the vibration source. It can prevent
and eliminate the materials inside the storage hoppers, storage tanks or feeders. It is
also the special equipment for anti-blocking equipment like tubular passages and
toner hoppers to ensure the clear and smooth flow of material. On the top of the JZF
type vibration anti-blocking mechanism is a YZO type vibration motor, and below is a
stand, joined together by high strength bolts. The mechanism has high energy, low
noise, low energy consumption, long service life and adjustable exciting force.
2.2.13.2
Model
Technical specifications
Silo Wall Matched
mm
Vibration
Efficiency
kg
Vibration
Frequency
Excitin
g
Foundatio Power
n
Blot
Motor
Force
kg
Opening
Length X
Width
JZF-5
4.5-6
YZO-12-2
0.25
3000
250
124150
380V
50Hz
JZF-6
6-8
YZO-21-4
0.4
1450
500
130170
380V
50Hz
JZF-10
8-10
YZO-31-4
0.75
1450
800
130170
380V
50Hz
JZF-11
10-12
YZO-41-4
1.1
1450
1000
130170
380V
50Hz
JZF-15
15-25
YZO-51-2
2.2
3000
1200
156180
380V
50Hz
2.2.13.3
2.2.13.3.1
2.2.13.3.2
Ensure the fixed bolts of vibration motors are all in place, with appropriate wiring.
2.2.13.3.3
Ensure the two symmetrically installed vibration device are 50-100mm apart from
each other.
2.2.13.4
2.2.13.4.1
Start the vibration motor up after inspections, confirming there are no abnormal
vibrations and supplying power to the motor control box.
2.2.13.4.2
After two hours of operation without faults, vibration motors will go through an
interlock test. If there is a blockage signal, the motor should be started up. When the
alarm is activated, the signal will be transmitted to programme control, then the
control room will send rapping signal to the rapping control cabinet. This makes the
vibration motor rap automatically until the blockage has been removed. Then the
blockage device will send the signal to monitor room, where the stoppage of rap
signal will be delivered to the control cabinet to stop rapping. Finally, the rapper will be
restored to its normal operation.
2.2.13.5
2.2.13.5.1
Ensure the fixed parts of rapper are all in place, working properly, and the motor is not
overheated.
2.2.13.5.2
2.2.13.6
2.2.13.6.1
2.2.13.5.2
Cut off power supply to control casing during a long time shutdown.
2.2.13.7
Description
Causes
Solutions
No rapping
Poor rapping
remove
2.2.14
2.2.14.1
2.2.14.1.1
2.2.14.1.2
2.2.14.1.3
To inspect the coal storage of the coal groove, and to check if some
impurities intertwine the impeller
b.
To see whether the moving orbit is flat, straight, firm and not blocked;
whether the moving impeller contacts the orbit surface well and has no
out-of-orbit phenomenon.
c.
The coal driving actuator and moving actuator is both good; the
protection cover of the shaft joint is complete and firm. claw.
d.
e.
feed coal funnel is unblocked; the coal damper in the bottom of the feed
coal funnel should be good; the belt joint surface must be inseparable
2.2.14.1.4
2.2.14.1.5
f.
The earth line of all the electric motor, the gauges in the operating box,
the switch, buttons, and LCD indicator should be all completely good.
g.
h.
Every moving switch should be good and their position must be correct.
i.
Close the main power supply switch and LCD indicator will be lighted.
b.
c.
Startup the main electric motor, and at this moment, the adjusting
operating machine should in a low-speed positionand it is forbidden to
start it up in a high speed.
d.
After the main electric motor startup, gradually decrease the rotating
speed to the needed value.
After the main impeller startupthe moving TV can be start upand the
coal feeder moves forward or backward.
f.
when the coal feeder changes its moving direction, start up another
direction after the moving actuator stops.
g.
If press the stop moving button, the coal feeder will carry out the local
pushing coal work.
h.
when the impeller coal feeder shutdown, first stop the moving actuator, then
stop the rotation of coal pushing actuator after adjusting it to be in a low
speed.
cause
1.Power
Supply Is Not
Connected
2.Fuse
treatment
1. Energize The
Power Source
2. Change The
Fuse
Not Rotate
Damaged
Rotating
Speed Is Out
Of Control
1.Controlled
Silicon
Breakdown
2.Relay
Damaged
3.Printing
Board Electric
Circuit Socket
Contact
Unwell
Big Truck Stop
Moving
1.Impurities In
The Orbit Or
The
Orbit
Deformed
2.Not
Restored After
The
Moving
Open
And
Closed
3.Driving
Actuator
Failures
2.2.15
2.2.15.1.
(1)
(2)
(3)
2.2.15.2.
(4)
(5)
The roller carrier is lengthened and its number increases to six group,
with decreasing space. This design reduces the coulters abrasion and
material leakage.
(6)
The material of coulter uses 16Mn, which has the advantage of good
durability and long service life.
Auxiliary
plough cutter
2.2.15.4
2.2.15.5
(2)
Feed coal funnel has no coal blockage or jam,; coal plough is not stick
to coals and impurities; air lock valve. The switch of air lock valve is
flexible.
(3)
The coal plough blade should be flat, completely good, not abased
seriously, and the link rod does not draw off, and the limit switch is
completely good.
(4)
The couple between the electric push rod end and the plough blade is
not draw-off; the driving device is good; the limit switch of rise and
down places well and flexible.
(5)
(6)
(7)
The dust proof cover of the electric push rod is completely good.
The power source switch is closed and the convert switch is in local
position.
(2)
Press the rise or down button on the site operating box, the coal
plough will correspondingly rise or down. During the process, if need
to stop it, just press the stop button.
Faults
Cause
Solution
The
push
rod
moves
unwell
or the
plough
is
blocked
1.Motor
fails
2.Impuritie
s or coals
stick to the
coal
plough
Coal
leakage
1.
Coal
plougher
encounter
s serious
abrasion
3.
Push
rod
is
jammed by
the couple
bearing.
2.
Coal
plougher is
not in its
position
Coal
ploughe
r is not
in
its
postion
1.Rotating
shaft
is
jamed
dead
2.Electric
push rod
loses
functions.
3.Position
limit switch
loses
functions.
2.3
2.3.1
2.3.1.1
2.3.1.2
Equipments in coal handling system: coal feeder impeller, bucket wheel machine, belt
conveyer, disk iron remover, belt iron remover, one-sided plow discharger, bilateral
plow discharger, sampling instrument, electric damper to three-direction, coal crusher.
2.3.1.3
2.3.2
2.3.3
2)
Centralized program control: it refers to only send out startup and shutdown
order in centralized control chamber after operation mode is selected, and the
selected equipments can startup and shutdown in groups according to
programmed process flow.
3)
Local manual control: it refers to the operation mode of local single unit startstop equipment.
2.3.4
The Main Coal Stack Mode for the Coal Handling System
1) Coal unload machine---bucket wheel machine---coal yard;
2) Coal unload machine---coal bunker;
3) Coal yard---bucket wheel machine one---coal bunker.
2.3.5
Check the handling work record carefully to find out the start-stop and operation
condition of system equipments, and tell the watchmen on site to make a
comprehensive inspection to equipments which they are in charge when it is in
static state.
2)
Inspect that the alternate voltage of power supply cabinet in main control
chamber is 220 v, and direct output voltage is 24V15%, alternate branches
small switches and direct branches small switches are all connected (including
other remote stations)
3)
Confirm that the host computer are in work state, and every modules are normal
4)
5)
6)
Inspect that the indication of coal level and high coal level in coal bunker is
normal, and confirm the indication is identical to the real conditions. If there are
any questions, please tell the watchmen on site to confirm.
7)
8)
b)
c)
Confirm that the driver of coal unload machine and bucket wheel machine
have already come.
d)
Contact with watchmen on site, and confirm that all of the preparation work
have been done, and receive the startup response, and then implement
remote-control startup operation.
2.3.6
2.3.6.1
2.3.6.1.1
Move cursor to cancel the zero position button, when the main selected flow is coal
feeder, the coal feeder method should be procedural control, and the coal
distribution method should be remote distribution; when the main selected flow is
coal storage, the coal feeder method should be procedural control.
2.3.6.1.2
Move cursor to click the clear button, and then click the clear distribution button to
make the procedure in the initial state.
2.3.6.1.3
Move cursor to call out main selected flow display, choose one branch flow from
eight main selected flows according to the operation mode and then the display will
pop up this branch flow equipments.
2.3.6.1.4
Move cursor to choose the startup equipment according to the sequential coal flow,
and the selected equipment of upper machine will be changed from blue to green.
2.3.6.1.5
After choosing is finished, if the upper machine pop up valid flow, it indicates that
choice is right; if the upper display of upper machine pop up wrong flow, it indicates
that the choice is wrong, and it needs to rechoose until the upper display of upper
machine pop up valid flow.
2.3.6.1.6
When there is a valid flow tooltip, move cursor to click pre-start button, and the
language setting will remind the procedural control worker: the selected flow damper
have already started, when click remote distribution button, it will remind the
procedural control worker that: the end bunker and the end plow falled off, and the
other plow is started; after several minutes, the finished damper will be changed into
red, the indicative signals will come out, the indicative information startup is
permitted display will be clicked out in the upper display of upper machine.
2.3.6.1.7
If the damper is not in the proper place or the plow have no signal of falling down and
lift up, the verbal equipments will remind unmovable damper or unmovable plow, at
this time the watchmen on site should be told to inspect or dispose
2.3.6.1.8
If confirming that the damper have already in the proper place, but the signals is not
right, you can move cursor to click the damper position button to make the
procedure not check whether the damper are in the proper place or not, click clear
button, and then click the button until the upper display of upper machine pop up
indication and sent out
2.3.6.1.9
When the startup is permitted signals come out, move cursor to click remote
startup button, the selected flow equipment will be delayed to start up according to
reverse coal flow until the last equipment are finished to start up, the valid flow and
startup is permitted disappear; when the equipments is started, the upper
equipments of upper machine will be changed from green to red.
2.3.6.1.10
According to the demands of selected flow and startup mode, order properly dumper
or bucket wheel machine to pile and obtain coal
2.3.6.1.11
2.3.6.2
When click remote startup or advance startup button, the alarming ring along
the line will operate automatically
2.3.6.2.1
In the process of procedure coal distribution, when the sequential high coal level
have been distributed, the upper display of upper machine will open remote
When the procedural control watchmen stop feeding or storing coal, firstly, order the
coal piling and obtaining driver of dumper and bucker wheel machine to shut down,
after confirming shutdown, move cursor to click remote shutdown button, the display
of upper machine will open the window of coal supply shutdown, and then choose the
coal supply of flow which need to shut down.
2.3.6.2.3
Move cursor to click confirm button, the operation equipments will be delayed to shut
down automatically according to ordinal coal flow direction from coal supply, the
equipments of upper machine will be changed from red to green after shutdown.
2.3.6.2.4
Inspect all equipments of the selected remote shutdown flow have already been shut
down.
2.3.6.2.5
2.3.6.2.4
2.3.6.2.6
After all of equipments have been shut down, move cursor, click the display of main
selected flow, choose the branch flow of shutdown, use cursor to click to clear away
the selected equipments, the equipments on the upper machine will be changed from
green to blue.
2.3.6.2.7
Move cursor to click clear, clear distribution button, make the procedure return to
the initial state.
2.3.6.2.8
Move cursor to click button to cancel the entire control mode of coal feeder and coal
storage.
2.3.6.2.9
Before handing over to the next shift, we should record the accumulative count and
overload time of every belt scale, and then calculate them.
2.3.6.3
2.3.6.3.1
Move cursor to cancel the neutral gear button, when the firm main selected flow is
coal feeder, the coal feeder method should be interlock, the coal distribution
method should be procedure distribution; when the firm main selected flow is coal
storage, the coal feeder method should be interlock.
2.3.6.3.2
Move cursor to click the clear button, and then click clear distribution button to
make the procedure in the initial state.
2.3.6.3.3
Move cursor to open main option flow display, according to personal mode, choose
one branch flow from eight main selected flow, and this display will pop up the
choosing window of this branch flow.
2.3.6.3.4
ordinal coal flow, the equipments in host computer will be changed from blue to green.
2.3.6.3.5
After choosing, if the upper display in host computer pop up a valid flow tooltip, it
indicates that the choice is right; if the display in host computer pop up a wrong flow
tooltip, it indicates that the choice is wrong, and it needs to rechoose again until the
display in host computer pop up valid flow.
2.3.6.3.6
When there is a valid flow tooltip, there are two ways to operate damper and coal
plowing
a. The first method: move cursor to click pre-start button, at this moment, sound
mechanism will indicate procedure-control watchman: the damper of selected flow
is ready, procedure distribution will indicate that: the plow of coal bunker tail
falls down, and the rest plow will lift up.
b. The second method: observe the main flow display of host computer, if the
selected damper is ready, the ready damper will be changed to red; if any
dampers are not ready, after local watchmen check and make sure it is ready, the
dampers can be operated, move cursor to open auxiliary equipment display,
press the manually controlled damper button to make the dampers in the right
place; move cursor to open coal distribution display, use cursor to make the raw
coal bunker fall down and the rest ones lift up.
c. If there are no signals of ready damper, the falling plow and the lift up plow, the
sound mechanism in host computer will indicate that unmovable damper or
unmovable plow, at this moment, inspectors should be informed to check and
handle.
d. If dampers is ready, but the signals are not right, move cursor to click damper
position button to make the procedure not check whether dampers are in right
place.(after the flow operation is finished, the damper position state should be
relieved without delay, and the forcibly fixed method should be used with great
delicacy.)
e. When the selected flow are right and in the very place, move cursor to start up the
head of belt and other equipments according to the reverse coal flow direction, at
this moment, the display will pop up the control and state inquiry window of these
equipments, after the alarming ring sound three times, operate the startup button
of equipments, start up the selected belt and equipments in correct order until the
startup of the selected equipments are finished. In the process of startup, the
following principles should be obeyed: (or it will not be started up)
2.3.6.3.7
a)
Preset the position of damper, and then start up the belt feeder.
b)
c)
Observe the controlling display of operational signals and ammeter in host computer
in the process of startup, and make sure last belts have already started up, and then
start next belt.
2.3.6.3.8
According to the firm operational flow to inform the materials piling and taking driver of
dumper and bucket wheel machine to operate according to the ruled power.
2.3.6.3.9
If another flow need to started up to carry out interlock manual control operation.
Repeat 2.3.6.3.32.3.6.3.9 operational procedure
2.3.6.4
2.3.6.4.1
In the process of procedural coal distribution, when the sequential high coal level
have been distributed, the upper display of host computer will pop up procedure
distribution are finished tooltip, at this moment, the procedure-control watchmen
should inform the materials piling and taking driver of dumper and bucket wheel
machine to shut down without delay.
2.3.6.4.2
When the procedure-control watchmen stop feeding coal or storing coal, inform the
materials piling and taking driver of dumper and bucket wheel machine to shut down
firstly.
2.3.6.4.3
After confirming it shut down, move cursor to stop the operational equipment in flow
according to the ordinal coal flow direction, after the equipments shut down, the color
of equipments in host computer will be changed from red to green: in the operational
process of shutdown, the following principles should be obeyed.
a. According to the length of belt feeder, calculate the stop time of belt, after
confirming through the industrial TV monitoring display, shut down equipments.
b.
Shut down belt feeder firstly, and then shut down magnetic separator.
c.
Shut down revolving roll picker firstly, and then shut down coal crusher with delay.
2.3.6.4.4
2.3.6.4.5
If it adopts parallel operation, after one-way equipments have been shut down,
choose another way equipments according to 2.3.6.4.1 2.3.6.4.4 operational
procedure.
2.3.6.4.6
After all of equipments shut down, move cursor to call out main selected flow
display, choose the branch flow of shutdown, use cursor to eliminate the selected
equipments, the color of host computer will be changed from green to blue.
2.3.6.4.7
Move cursor to press the clear, clear distribution button to make the procedure be
in the initial state.
2.3.6.4.8
Move cursor to press the neutral gear button, cancel all of the coal handling and
storing controlling method.
2.3.6.4.9
Before handing over to the next shift, we should record the accumulative count and
overload time of every belt scale , and then calculate them.
2.3.6.5
2.3.6.5.1
2.3.6.5.2
Move cursor to cancel the neutral gear button, and then choose the coal handling
mode is procedural control or interlock, and the coal distribution mode is manual
distribution.
2.3.6.5.3
2.3.6.5.4
Move cursor to call out coal distribution display, and then operate the manual falling
and lift up button of coal plowing to make sure the plow of tail bunker in raw coal
bunker fell.
2.3.6.5.5
According to the indicating condition of the coal level of host computer, use cursor to
click manual control button of coal plowing, manually operate the falling and lift up of
coal plowing to distribute coal.
2.3.6.5.6
Before finishing feeding coal, we should inform the materials piling and taking driver of
dumper and bucket wheel machine to shut down, and adopt the procedural control
or interlock manually controlling mode to shut down one by one.
2.3.6.5.7
Checking the selected equipments in procedure shutdown flow has already been
shut down.
2.3.6.5.8
If it adopts paralleled operation, after one-way equipments have been shut down,
choose another way equipments according to 2.3.6.2.1 2.3.6.2.4 or 2.3.6.4.1
2.3.6.4.4 operational procedure.
2.3.6.5.9
After all of equipments shut down, move cursor to call out main selected flow
display, choose the branch flow of shutdown, use cursor to eliminate the selected
equipments, and the color of host computer will be changed from green to blue.
2.3.6.5.10
Move cursor to click clear, clear distribution button, make the procedure return to
the initial state.
2.3.6.5.11
Move cursor to click button to cancel the entire control mode of coal feeder and coal
storage.
2.3.6.5.12
Before handing over to the next shift, we should record the accumulative count and
overload time of every belt scale, and then calculate them.
2.3.6.6
2.3.6.6.1
a.
Shut down the equipments in original flow which need to be switched according
to the ordinal coal flow direction.
b.
c.
8PA8PB switchover
a.
b.
c. Click the switch button in8PA/B switching control display, it will turn out a red
display 8PA is switching to 8PB, 8PBor 8PAstart up automatically.
2.3.6.7
The observation and cautions in the operation of coal handling procedural control.
2.3.6.7.1
Before the operation of procedural control, check and inquire the indication of
current, coal level in coal bunker, system alarm, and the indication of anunicator
window in equipments, pay attention to monitor the direction of damper. In order
to understand the operational condition, and carry out production management
and treatment disposal.
(2)
Observing that the coal quantity indicating value of belt scale are changing in
rated range, and overload operation in equipments are not allowed absolutely.
(3)
When adopt the procedural distribution mode to feed coal, we should pay more
attention to the signals of coal level in order to avoid the happening of overflow
and lack of coal and make sure the coal distribution operate in normal state.
(4)
(5)
When the procedural control operating, we should contact with workers on site
in order to adjust the power and manage the production properly.
When the procedural control start up, we should monitor strictly the startup
current and time of every equipment one by one, when the startup current
overpass the needs of startup time, we can press the emergency trip button.
(2)
When the procedural control starts up, we should observe whether the startup
procedures of equipments adapt to the set demands of flow.
(3)
When the procedural control start up, we should observe whether the color of
equipments in monitoring display is normal, and observe whether the coal
plowing in coal bunker adapt to the demands of procedural coal distribution,
and the industrial TV monitoring display is normal.
(4)
When the procedural control start up, if one of equipments can not be started up
or trip immediately after startup, we should find out the reasons of faults( inquire
through the sound alarm and system faults), and then inform the workers on site
to handle , report to monitor after confirming, and then we can rechoose the flow
startup.
(5)
When one of flows or all of flows shutdown, we should check and confirm all of
equipments in flow have already shut down, and the ammeter is in zero position.
(6)
After every shift work stop operating, and then check the variable reading of
electrical belt scale.
(7)
After finishing feeding coal, operate manually every electrical T-pipe action two
or three times, eliminate the coal in order to make sure the clear of electrical Tpipe.
2.3.6.8
2.3.6.8.1
When human injury happen, when the accidents which threatened the safety of
people and equipment happen.
2.3.6.8.2
2.3.6.8.3
When the belt is broken, the motor smoke, liquids spout oil and other fault happen
2.3.6.8.4
When sensor is ineffective, or coal blockage, heavy slippage and heavy off tracking
and other heavy faults happen
2.3.6.8.5
The signals of belt heavy off tracking, heavy slippage, coal blockage enter PLC and
they are not in shunt tripping.
2.3.6.8.6
2.3.6.8.7
2.3.6.9
Belt overload
Treatment
Belt emergency
shutdown
Belt deviation in second 1. inform personnel on site to find out the reasons of
deviation
pole
2. remove deviated protective equipment, and start up
belt to allign without influencing safty.
Relative-movement belt
Unmovable damper
Startup failure
Power fault
Coal blockage
2.4
2.4.1
2.4.2
The Double-Pole Switch for Detecting Deviation State of Belt in Belt Conveyer.
2.4.2.1
Function:
Through monitoring the deviation state of belt in belt conveyer to send out signals to
realize the automatic alarm and shutdown function of belt deviation, this switch have
double pole , one is used to alarm, the other is used to shut down
2.4.2.1
Work principle:
The working process of the double-pole switch for detecting deviation state of belt in
belt conveyer is that the belt touch the contact bar of switch to make it deviate, when it
deviates to a the switch will send out alarm signals to control chamber to warn the
supervisor on site to take some measures, when it deviates to , the switch will send
out shutdown signals.
Page 138 of 160
2.4.3
2.4.3.1
Function:
Two-throw pulling switch is one of protective equipments which is used in emergency
shutdown of belt conveyer on site. When the emergency happen, pulling switch
anywhere on site can shut down it.
2.4.3.1
2.4.4
2.4.4.1
Function:
D H-type relative-movement detector is used to detect the relative-movement
between belt and driving roller in the operation to avoid vicious events caused by
relative-movement, it also can be used in the interlock startup, shutdown, lower speed
braking and overspeed protect of belt conveyer which use more than one belt.
2.4.4.2
Work principle:
DH-type relative-movement detector is operating in this way: the belt drive contact
wheel to make it reflect the real speed of belt, contact wheel drive transmission shaft
of detector to make the inside speed relay work.. the work of relay mainly lies in the
inside magnetic material which produce magnetic turning torque through rotating, it will
drive moving fork to make the contact produce connecting or break signals
2.4.5
2.4.5.1
2.4.5.1
Work principle:
DHS-type speed detector is operating in this way: the sensor head change the
detected belt speed and rotating speed into pulse signals and send that into the
controlling cabinet, the calculating circuit inside of controlling cabinet will count in unit
time, and then make reasonable judgment comparing to the predicted belt speed and
rotating speed. If it equals to the predicted belt speed and rotating speed or a little
bigger than that, make the control relay absorb, at this time the operating speed of
belt is normal; If it is smaller than the predicted belt speed and rotating speed , make
the control relay release, at this time the operating speed of belt is lost.
2.4.6
2.4.6.1
Function:
Vertical slitting of belt is a vicious event, Vertical slitting protective equipments of ZL
series is fit for the tearing protection of every specification and type sealing-type
machine.
2.4.6.2
Work principle:
Vertical slitting protective equipments of ZL series can be divided into two kinds: one
is controlling cabinet and the other is sensor.
The sensor is the detecting device of vertical slitting protective equipment. When the
belt of belt conveyer presses B-type sensor during operation after pierced by
materials, or when the trap door presses A-type sensor caused by the material
blockage between the belt and chute discharging port, these two types of sensors will
send signals to control box and send signals of alarm and auto-stop through control
circuit. In this way, they function as protecting belt.
2.4.7
2.4.7.1
Overview
Supersonic wave material level instrument is a new-type measuring instrument for
material which is controlled by computer. This equipment employs the return wave
range finding theory, and makes use of supersonic wave to measure continuously
material in material bunker without touching to supply several signal-type analogue for
users
Supersonic wave material level instrument can indicate the real-time material level of
every bunker, high-level alarm, low-level alarm, overhigh level trip, and overlow level
trip, additionally, it also can have networking digital communication with other
computers.
2.4.7.2
This instrument can be controlled by computer, the logic judging function is very
good, meanwhile, it has the function of finding return wave automatically, window
tracking, slow and variable output and etc.
It has AGC and PLL wave filter circuit, the resolving ability of signals is strong.
Digital signal control is adopted between indicative cabinet and launching cabinet
and it is separated by opto-coupler correctly and reliably, the anti-jamming ability
is strong.
2.4.7.3
The detector is made by casting special silica gel, it has strong anticorrosive
property and permissibility
According to the practical experience of the using of material level gage, the
inside of instruments is detected in cms, and the indicating analogue output are
detected in dms, it is more reliable and practical.
Work principle
So far, the common-used ultrasonic material level gage has two structures. One of
two-state detector structure which can collect and send separately, the other is onestate detector structure which can collect and send simultaneously. They are all using
piezoelectric ceramic transductor to operate ultrasonic sending and collecting. When
sending, use a electrical signals to stimulate piezoelectric ceramic transductor, and
then piezoelectric ceramic transductor will send a series of ultrasonic signals, and this
ultrasonic signals will be reflected when it meet material. When the reflected
ultrasonic signals were received, it will be converted to electrical signals. Through
measuring the time interval t from the ultrasonic sending and material receiving and
calculate the distance between material surface and piezoelectric ceramic
transductor, and then calculate the height the real material level. The formula is :
H = L-
1
331.13+0.6Tt
2
2.4.8.1
Function
These controlling instruments are mainly used to detect the coal yard, coal bunker
and the height of coal level in coal handling coal spouting in order to control
automatically the coal handling quantity, simultaneously it also can be used to detect
the water level and the height of other material level.
2.4.8.1
Work principle:
High and low coal level detector are composed of controlling cabinet and electrode.
The working method and electrical theory can be seen in picture one, the working
process: when the coal in the coal bunker are in the low position, the electrode A send
a signal to low coal level controlling circuit through detecting coal resistance to output
binary of low coal level, when coal (or other materials) lift up to high coal level, the
electrode B send a signal to high coal level controlling circuit through detecting coal
Page 141 of 160
resistance. Output a high coal level binary. Thus, the detecting of high and low coal
level are finished.
2.4.9
2.4.9.1
Function:
This product can be used as belt to conveying materials which used to detect the
instantaneous state of material, the switch install in the inside of that, the binary
output according to material flow condition. User can connect it to the controlling
chamber in order to detect the material conveying state on site, it also can be used
with sprinkler to realize the sprinkling function automatically when it has materials.
2.4.9.2
Work principle:
LLtype material flow detector adopt cam and travel switch structure, there are one
normally closed contact, four normally open contact in static state, the user can install
according to demands, the user also can make use of four-group normally open
contact to connect the indicator light, when the conveying material in belt are different,
this detector deviate in different angle which means it has different indicator light, at
this way the material conveying condition can be observed in controlling chamber.
2.4.10
2.4.10.1
Function:
Downspouting Blockage protective equipments are used to inspect the downspouting
blockage of belt conveying machine, when the downspouting are blocked, this
detector can output the alarming and shutdown signals.
2.4.10.2
Work principle:
This instrument adopt door-type structure, install on the wall of one side of
downspouting. When the material in downspouting are in blocked state, the
accumulated material leave pressure to the sidewall of downspouting, and then push
outward the moving door of this equipments, when the moving door is deviated, and
the turning angle equals to or bigger than controlled angle, it control the switch action
in order to alarm the shutdown signals. If this signal will be connected to the
controlling line of shaker which can realize the automatic shaking function when the
equipments are in slight blocked state, when the blockage faults of downspouting are
relieved, the moving door can be resetted and recovered. The structure of these two
downspouting
The moving doors of this instrument will install the sliding bearings to add the rotating
reliability, the bearing adopt sealing measurement in order to adapt to the severe
atmosphere. This equipments and the side wall of downspouting adopt elastic rubber
to seal, thats why the flexible and reliable action can be guaranteed, additionally, it
also can be sealed entirely.
Appendix
1.2
1.2.1
1.2.1.1
1.2.1.2
1.2.1.3
1.2.2
1.2.2.1
1.2.2.2
Pylon
Pull rod
Cab
Counterweight
assembly
Pull rod
Support pivot
Bucket
mechanism
wheel
Slewing
mechanism
Counterweight
stack
Bucket
Body
Sliding
chute
Wheel
drive
3)
Head
device
buffer
Balance beam
Rail clamping device
Driven unit
Tail
device
Driven unit
Anchoring device
Rail sweeper
buffer
Slewing
mechanism
Driving device
Three-row roller bearings
Driving pinion
Gear cover
Belt
Idler group
Belt conveyor
protection device
Sweeper
Pylon
Driving
device
Transmission roller
Support pivot
Slewing mechanism
Tripper car
Main tripper car Single-wheel non-drivenTripper car
steel structure belt conveyor
wheel bogie assembly mechanism
luffing
Tripper car
1.2.2.3
1.2.2.3.1
1 Troughed idler
2)
Flat idler
1.2.2.3.2
1.2.2.3.3
H-type
P-type
1.2.2.3.4
1.2.2.3.5
1.2.2.4
Back door
Iron removal room
Front door
Surface
alignment
for
Lower side
door
Screw
cover
Lower back
door
Sieve
holes
Lower side
door
tray
Supports
Big hold
things
1.2.2.5
Speed
measuring
sensor
Belt conveyor
Belt conveyor
Force measuring
sensor
Secondary meter
1.2.2.6
Ripping
motor
Dust
suction
interface
Air fan
Electrical
valve
Air suction inlet
air
1.2.2.7
1.2.2.8
1.2.2.9
Plough tripper
1)
2)