Phasing in DCS Migration
Phasing in DCS Migration
Phasing in DCS Migration
qxp:00
2/28/08
1:21 PM
Page 24
266845.qxp:00
2/28/08
1:21 PM
Page 25
PROCESS AUTOMATION
THIS
FOR FAST FORWARD
FASTIS
FORWARD
G
G
G
G
G
G
G
This
boxgrowth
can become
or wider
as
Facility
leads taller
to imminent
upgrade
needed
for the
layout balance.
at Bolivian
petroleum
plant.
The
ruledisbox
should
align to column
Strategy
to link
all facilities
under one
guides
DCS system.
The
head divided
is the same
the arc.
Upgrade
into color
threeas
phases
for
costhead
efficiency.
The
and arc color should work off
of the color of the artwork.
Existing problems
The old system had old technology,
which required high maintenance costs.
It was difficult to obtain spare parts. The
hardware and software were saturated,
and we could add no more instruments
and I/O modules to the system. It was
impossible to work with modern instrumentation, such as, Hart, Foundation
Fieldbus, Profibus, and Ethernet.
The system was centralized. The whole
control system was under a control
processor, so when it broke down, the
whole plant shut down, with the consequent losses in production and time. The
systems software was old, and we could
not upgrade without totally changing to
a superior version and without losing
licenses. It was impossible to obtain
reports and historical data on Excel
spread sheets.
While we wanted to improve the system
and process efficiency, eliminate obsolescence, and reduce operation and
maintenance costs, it was not possible to
266845.qxp:00
2/28/08
1:21 PM
Page 26
PROCESS AUTOMATION
Proposed solution
Update the old DCS to a new technology.
Increase speed, field modules, software
capacity, and security.
Make it possible to manage modern
instrumentation.
Dont lose connection with old
instruments.
Update obsolete equipment.
Open systems.
The new DCS system is distributed in
different areas, in DCS cabinets connected
to the control room by means of Ethernet
optic fiber. We added two PCs to the control
room for graphic information because it
has corresponding software for configuring
the applications of the new DCS system.
The old system is in charge of three DCS
cabinets in which we have added what we
OPC
Systems proplus
host
Work station
oper-01
Room 1
LPG
Plant 01
Bulo Bulo
field
Kanata
field
Amine
plant
Controller CP40B
MCP 300
MCP 100 MCP 200
266845.qxp:00
2/28/08
1:21 PM
Page 27
PROCESS AUTOMATION
Implementing phases
To implement the first phase, we
planned the work jointly with operations
and supplier. We tested instruments and
the database in supplier office and
installed the cabinets one day before the
migration. Maintenance prepared a
report of signals and power supply
(100VAC and 24VDC) before the migration.
The day of the migration, operations
planned the work in such a way they
only passed to local control (in field) the
affected areas of the old DCS, allowing
the work without plant shutdown, and
completing in the shortest time period
(approximately six hours).
All connections followed the appropriate
standards for Zone 2, Division 1. The
control room was air-conditioned to
allow more comfort and facilitate the
operators job. While developing this
phase, we did not have any unforeseen
plant shutdowns, and the whole implementation process occurred without any
great inconvenience.
Project update
Today, the DCS implementation has
achieved 100% automation of the plants
gas treatment. We wrote new startup and
shutdown sequences, and we are now
adding new instrumentation to the new
DCS system (SCADA). We put new
automation areas into the system as well.
As a third phase of the project, we are
changing instruments with 4-20 mA or
proprietary protocol to HART-type instruments. Our objective is to have the whole
plant instrumentation (transmitters and
control valves) changed to the HART protocol. At the same time, we are managing
instrumentation, with inspection, calibration, qualification, and preventive maintenance plans, throughout the entire plant.
We hope to finish this phase during the
first trimester of 2008. As a fourth phase,
we plan to install a safety instrumented
system (SIS) throughout the plant.
ABOUT THE AUTHORS
RESOURCES
http://www.isa.org/intech/060009
The Perfect Storm Platform
http://www.isa.org/intech/20061002
Manufacturing Interoperability
Guideline Working Group
www.isa.org/link/MIGworking
ER-00071-Oct07